J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton ( 2015 )


Menu:
  •                                        In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-14-00019-CV
    J.R.'S LANDSCAPING & SPRINKLER SYSTEMS, INC., APPELLANT
    V.
    CITY OF CROSBYTON, APPELLEE
    On Appeal from the 72nd District Court
    Crosby County, Texas
    Trial Court No. 2010-7347, Honorable Ruben Gonzales Reyes, Presiding
    September 21, 2015
    MEMORANDUM OPINION
    Before CAMPBELL and HANCOCK and PIRTLE, JJ.
    Appellant J.R.’s Landscaping & Sprinkler Systems, Inc. brought suit against the
    City of Crosbyton, Texas, alleging breach of its construction contract with the City. The
    City brought a counterclaim, asserting J.R.’s had failed to perform the contract as
    required.1    Each sought damages. After a bench trial, the court awarded the City its
    damages for the cost of completion of the project.
    1
    The elements of a breach of contract claim are: (1) the existence of a valid contract; (2)
    performance or tendered performance by the plaintiff; (3) breach of the contract by the defendant; and (4)
    On appeal, J.R.’s brings two issues, one contending the court erred by rejecting
    its claim for damages, the second contending it erred by entering judgment for the City.
    After we abated the appeal, the court signed findings of fact and conclusions of law. 2
    We will affirm.
    Background
    The contract called for J.R.’s to furnish materials and labor for the construction of
    new concrete sidewalks, curbs and gutters, access ramps, handrails and related work at
    locations in downtown Crosbyton. The final contract amount was $142,632.80. During
    construction J.R.’s requested, and was paid, $64,307.
    Chester Carthel of Carthel’s Engineering served as engineer and owner’s
    representative. At a point, a difference of opinion arose between Carthel and the City
    regarding J.R.’s completion of the work. Carthel received J.R.’s notice that work was
    substantially complete, inspected the work, concluded the project was substantially
    complete and complied with the contract, and approved J.R.’s application for payment
    of the remaining contract amount. At trial, Carthel agreed it was his opinion that the
    work was substantially complete and that the application should have been paid.
    The City was dissatisfied with the work. The mayor testified he told J.R.’s on
    several occasions that he was not satisfied with the appearance of the sidewalks and
    complained about defects such as pitting. J.R.’s attempted repairs to several areas by
    ____________________
    damages sustained by the plaintiff as a result of the breach. Wright v. Christian & Smith, 
    950 S.W.2d 411
    ,
    412 (Tex. App.—Houston [1st Dist.] 1997, no writ).
    2
    See J.R.’s Landscaping & Sprinkler Sys. v. City of Crosbyton, No. 07-14-00019-CV, 2014 Tex.
    App. LEXIS 12666 (Tex. App.—Amarillo, November 21, 2014, no pet.) (mem. op.).
    2
    patching the concrete, but the mayor testified the patching was not successful. He said
    J.R.’s was “going to get us a proposed way of taking care of the problem. And then we,
    the council, would approve.” He testified he never received a proposed plan of action
    from J.R.’s, who merely attempted more patches. The City never formally accepted the
    work.
    The City hired another engineer, Michael Adams, who testified he found several
    issues with the concrete, including exposed aggregate rock, spalling, sloping and
    rusting of exposed rebar. He expressed the opinion the workmanship was “at a low
    level,” and recommended that the areas of concrete containing the defects be torn out
    and replaced, at an estimated cost of $160,000.
    When the City did not pay its final payment application, J.R.’s filed suit. On the
    City’s counterclaim, the court awarded it damages of $160,000, interest and attorney’s
    fees.
    Analysis
    All the trial court’s findings of fact and conclusions of law favor the City. In
    support of its first issue, J.R.’s contends the evidence established as a matter of law
    that the City breached the contract by failing to pay J.R.’s final invoice. See Dow Chem.
    Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001) (per curiam); Barnett v. Coppell N. Tex.
    Court, Ltd., 
    123 S.W.3d 804
    (Tex. App.—Dallas 2003, pet. denied) (standard of review).
    To reach that conclusion, J.R.’s argues that the contract unambiguously provided that
    acceptance of the project by the owner’s representative was conclusive and binding on
    the City. To sustain its contention, we would be required to agree that J.R.’s reading of
    3
    the contract is the only reasonable reading. See, e.g., Columbia Gas Trans. Corp. v.
    New Ulm Gas, 
    940 S.W.2d 587
    , 589 (Tex. 1996); Universal C.I.T. Credit Corp. v.
    Daniel, 
    150 Tex. 513
    , 517, 
    243 S.W.2d 154
    , 157 (Tex. 1951) (ambiguity of contracts).
    J.R.’s relies on a section of the contract with the title, “Contract Closeout.”3 Its
    subsections include those entitled “substantial completion,” “final inspection,” and “final
    payment.” It contains a statement reading, “The Owner's Representative will determine
    if the project is Substantially Complete.” It also contains the provision that, within 14
    days of notice from the contractor that he believes the work is substantially complete,
    the Owner’s Representative will inspect the job and determine if he agrees. The “final
    inspection” subsection contains a similar requirement for a response from the Owner’s
    Representative to the notice from the contractor.
    But the provisions on which J.R.’s relies are not the only contract terms
    addressing the subject of payments on completion of the work. The contract’s General
    Contract Conditions contain a section entitled “Payments to Contractor,” with
    subsections entitled “partial payments,” and “final payment.” As the City points out,
    language there appears stating that the contractor’s “requisition for final payment,” will
    be prepared “[a]fter final inspection and acceptance by the Owner of all work under the
    Contract.” Another provision, contained in the “payment procedures” subsection of a
    section entitled “Administrative Requirements,” states that the “Owner’s Representative
    3
    In addition to several pages of General Contract Conditions, the contract document includes
    several pages of specifications and other provisions, some of which address topics also addressed in the
    General Contract Conditions. The General Contract Conditions and these latter provisions appear taken
    from different contract forms. The language of the General Contract Conditions and these latter
    provisions of the contract is not consistent, and each contained phrases not used in the other. For
    example, the General Contract Conditions refer to Carthel as “Engineer,” while the latter contract pages
    refer to the individual filling his role as the “Owner’s Representative,” a phrase not appearing in the
    General Contract Conditions. The capitalized, but undefined, phrase “Substantially Complete” appears in
    the latter provisions but not in the General Contract Conditions.
    4
    will review pay request [sic] and recommend action to the Owner within 14 calendar
    days of submission.”4
    J.R.’s cites Texas cases describing contract provisions it contends are like those
    in its contract with the City. See State v. Martin Bros., 
    160 S.W.2d 58
    , 60-61 (Tex.
    1942) (contract stated engineer’s decisions would be “final”); City of San Antonio v.
    McKenzie Constr. Co., 
    150 S.W.2d 989
    , 998 (Tex. 1941) (certificate of final acceptance
    to be issued by engineer); Tribble & Stephens Co. v. RGM Constructor, L.P., 
    154 S.W.3d 639
    , 652 (Tex. App.—Houston [14th Dist.] 2004, pet. denied) (plurality op.)
    (contractor’s work subject to “final approval” of project architect). The clear and
    consistent contract provisions described in those cases are unlike the uncertain and
    conflicting language that confronted the court here. We do not agree the contract here
    unambiguously provides that Carthel’s decision regarding completion of the work would
    be final and binding on the City. 5 J.R.’s contention effectively ignores the contract
    language indicating it was up to the City to grant final acceptance.
    We overrule J.R.’s first issue.
    In its second issue, J.R.’s argues the trial court erred by entering judgment in
    favor of the City. The court found that the concrete’s exposed aggregate and spalling
    4
    Other provisions of the General Contract Conditions emphasize the role of the Owner, here the
    City, with respect to acceptance of the work. An inspection provision states, “The Owner shall have the
    right to reject defective material and workmanship or require its correction. Unacceptable workmanship
    shall be satisfactorily corrected.” Another general contract condition states that “all instructions and
    approval with respect to the work will be given to the Contractor only by the Owner through its authorized
    representatives or agents.” Note that provision refers to the Owner, not the Engineer.
    5
    As stated in the trial court’s findings of fact, Joe Ramirez, the owner of J.R.’s, “agreed at trial
    that the city could ‘decide whether or not to accept or reject’ the work.” And, although Carthel was hired to
    be the engineer on the project, “under the terms of the Agreement, the City had the ultimate right to
    decide to accept or reject the work and was free to disagree with Carthel’s opinions.”
    5
    issues were a result of poor workmanship by J.R.’s, and found the workmanship was
    not in compliance with the contract. It concluded J.R.’s breached the contract by failing
    to construct or complete the project in accordance with its terms. J.R.’s cites Mustang
    Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    (Tex. 2004), and acknowledges its
    holding that one contracting party’s performance may be excused if the other materially
    breaches the contract. 
    Id. at 196.
    J.R.’s asserts, however, there is no evidence it had
    committed a material breach when the City failed to make payment. The assertion is
    founded on Carthel’s agreement the work was substantially complete. J.R.’s argument
    ultimately relies, then, on the same contention that underlies its first issue, the assertion
    the contract made Carthel’s decision final and binding on the City. Having rejected
    J.R.’s contention that, as a matter of law, the contract made Carthel’s determination
    final, we cannot agree the trial court was required to disregard the evidence of poor
    workmanship and defective concrete work cited in the court’s findings. 6 We overrule
    J.R.’s no-evidence issue. See Catalina v. Blasdel, 
    881 S.W.2d 295
    , 296-97 (Tex. 1994)
    (standard of review for no-evidence issue on appeal).
    6
    J.R.’s does not directly challenge any of the trial court’s findings of fact. Its findings include the
    facts that an inspection after J.R.’s substantial completion notice showed large areas of concrete
    containing “exposed aggregate and spalling” as well as “substantial cracking of the concrete in those
    areas.” The finding continues, “[e]xposed aggregate and spalling are defects in concrete that are a
    delamination of the top layer of concrete. This exposes the inner layers of the concrete to weather
    elements. A concern is with a freeze-thaw issue, where water can penetrate into the concrete through
    the exposed aggregate or spalling areas, and when that water freezes, it will expand and damage the
    concrete. Exposed aggregate and spalling shorten the life of the concrete.” Further, “[t]he concrete was
    not smooth, and it was not aesthetically pleasing,” an “important aspect of the project” to “improve the
    look of the downtown area.”
    6
    Conclusion
    Having resolved each of J.R.’s issues against it, we affirm the judgment of the
    trial court.
    James T. Campbell
    Justice
    7