City of San Antonio v. Casey Industrial, Inc. ( 2015 )


Menu:
  •                               Fourth Court of Appeals
    San Antonio, Texas
    DISSENTING OPINION
    No. 04-14-00429-CV
    CITY OF SAN ANTONIO,
    Appellant
    v.
    CASEY INDUSTRIAL, INC.,
    Appellee
    From the 408th Judicial District Court, Bexar County, Texas
    Trial Court No. 2008-CI-06252
    Honorable Michael E. Mery, Judge Presiding
    Opinion by: Sandee Bryan Marion, Chief Justice
    Dissenting Opinion by: Patricia O. Alvarez, Justice
    Sitting:          Sandee Bryan Marion, Chief Justice
    Patricia O. Alvarez, Justice
    Jason Pulliam, Justice
    Delivered and Filed: July 1, 2015
    The majority assumes only arguendo that Casey raised a genuine issue of material fact on
    whether Casey complied with the contract’s provisions to seek additional compensation, but it
    concludes Casey failed to raise a fact issue on any damages due for additional work CPS Energy
    directed it to perform. Based on these conclusions, the majority decides CPS Energy’s immunity
    was not waived, and the trial court erred by denying CPS Energy’s plea to the jurisdiction. Because
    Casey met its evidentiary burden and CPS Energy failed to conclusively disprove its immunity
    was waived, I would affirm the trial court’s order. Therefore, I respectfully dissent.
    Dissenting Opinion                                                                  04-14-00429-CV
    PLEA TO THE JURISDICTION
    In its plea to the jurisdiction, CPS Energy asserted its immunity from suit was not waived
    and it moved to dismiss Casey’s claims. CPS Energy argued Casey failed to meet the statutory
    requirements to waive CPS Energy’s immunity under Texas Local Government Code sections
    271.152 and 271.153. See TEX. LOC. GOV’T CODE ANN. § 271.152 (West 2005); 
    id. § 271.153
    (West Supp. 2014). After Casey met its burden to raise a fact issue on waiver of immunity, then,
    as the movant, CPS Energy had to conclusively disprove any essential element of waiver. In
    reviewing the evidence, we take all of Casey’s evidence as true, and resolve any doubts and make
    all reasonable inferences in its favor. See Tex. Dep’t of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 228 (Tex. 2004). I address the evidence pertaining to the two sections’ requirements.
    SECTION 271.152 REQUIREMENTS
    A.      Casey’s Burden
    Casey’s burden was to plead facts supported by some evidence sufficient to raise a genuine
    issue of material fact that it met the requirements of section 271.152. See Zachry Const. Corp. v.
    Port of Hous. Auth. of Harris County, 
    449 S.W.3d 98
    , 110 (Tex. 2014). It pled that its suit was
    against CPS Energy, a local governmental entity; that CPS Energy entered into a contract with
    Casey; and its suit comprised claims for breach of that contract. I recite the supporting evidence.
    •   The City of San Antonio is a local governmental entity. See TEX. LOC. GOV’T CODE
    ANN. § 271.152 (“local governmental entity” (emphasis added)).
    •   Acting through CPS Energy, the City was authorized by statute to enter into a contract
    with Casey for the J.T. Deely power station modifications. See 
    id. (“authorized by
                statute . . . to enter into a contract” (emphasis added)); City of San Antonio ex rel.
    City Pub. Serv. Bd. of San Antonio v. Casey Indus., Inc., 
    381 S.W.3d 589
    , 596 (Tex.
    App.—San Antonio 2012, pet. denied) (citing TEX. LOC. GOV’T CODE ANN. § 271.119
    (“Design-Build Contracts for Facilities”)).
    •   It did so in August 2004. See TEX. LOC. GOV’T CODE ANN. § 271.152 (“enters into a
    contract” (emphasis added)); Casey 
    Indus., 381 S.W.3d at 596
    –97.
    -2-
    Dissenting Opinion                                                                 04-14-00429-CV
    •   In its pleadings, Casey (1) alleged that CPS Energy breached the August 2004 contract
    and (2) provided evidence of the executed contract and affidavits supporting its
    allegations of breach. Casey also provided evidence that contract provisions under
    paragraph 14.1.2 include procedures for CPS Energy or Casey to modify the scope of
    work, change the performance schedule, and seek an increase or decrease in the D/B
    contractor’s (Casey’s) compensation. It argued and pled evidence showing that it
    complied with the procedures to raise, discuss, and resolve a claim. See TEX. LOC.
    GOV’T CODE ANN. § 271.152 (“claim for breach of contract” (emphasis added)).
    Taking Casey’s evidence as true and making all reasonable inferences in its favor, I
    conclude Casey met its burden to raise a genuine issue of material fact that CPS Energy’s immunity
    was waived under section 271.152. See 
    Miranda, 133 S.W.3d at 228
    ; see also Zachry 
    Const., 449 S.W.3d at 109
    (“The waiver does not depend on the outcome, though it does require a showing of
    a substantial claim that meets the Act’s conditions.”).
    B.      CPS Energy’s Burden
    Although Casey met its burden, CPS Energy’s plea to the jurisdiction could be granted if
    CPS Energy conclusively disproved any essential element of waiver of immunity. See 
    Miranda, 133 S.W.3d at 226
    –28; Elliott-Williams Co. v. Diaz, 
    9 S.W.3d 801
    , 803 (Tex. 1999) (“The
    defendant as movant must disprove at least one of the essential elements of the plaintiff’s causes
    of action to prevail on summary judgment.”). To conclusively disprove any waiver of immunity,
    CPS Energy argued that Casey did not comply with what CPS Energy asserts are the applicable
    contract procedures, e.g., contract Article 9.1 Change Orders. CPS Energy contended that the only
    contractual procedure to modify Casey’s scope of work was the change order provision, Casey
    never requested a change order for the work in question, CPS Energy did not issue one, and
    therefore any additional work Casey did was not covered by a written contract. Thus, CPS Energy
    argues, without a written contract for the additional work, Casey did not meet section 271.152’s
    requirements and CPS Energy’s immunity was not waived.
    -3-
    Dissenting Opinion                                                                     04-14-00429-CV
    C.      Contract Provisions to Request Additional Compensation
    But CPS Energy’s view ignores other contract provisions that expressly create procedures
    for Casey to request additional compensation. I trace the path along the applicable contract articles
    and recite some of the evidence relating to each article.
    1.      Article 14.1.2
    In its January 3, 2006 letter, CPS Energy notified Wheelabrator that Wheelabrator was in
    default under the contract. Under Article 14.1.2, a default by Wheelabrator constitutes a Force
    Majeure.
    Provided D/B Contractor is not in Default itself, a Default by Wheelabrator under
    Section 14.1.1, which results in an impairment or frustration of D/B Contractor’s
    Work through no fault of D/B Contractor, shall be considered a “Force Majeure”
    event and will entitle D/B Contractor to request an extension of time and/or
    additional compensation by Notice to Owner as required in Section 9.1.3.
    (Emphasis added).
    2.      Article 9.1.3
    Wheelabrator’s default—a force majeure—invokes Article 9.1.3’s provisions.
    D/B Contractor shall provide Owner with Notice of any circumstance described in
    Section 9.1.4 which D/B Contractor believes will entitle D/B Contractor to a
    Change Order modifying the Scope of Work, Project Schedule, Contract Price, or
    other obligations of D/B Contractor under this Agreement. D/B Contractor shall
    bear the burden of establishing that it is entitled to such relief under Section 9.1.4,
    that the relief sought is the minimum relief required, and that any monetary relief
    requested by D/B Contractor is in excess of any insurance proceeds recoverable by
    D/B Contractor. Such Notice shall be issued within ten (10) Days after D/B
    Contractor’s knowledge of a circumstance described in Section 9.1.4, and such
    Notice shall describe such occurrence in detail. Within ten (10) Days following
    delivery of such Notice, or such other period as may be agreed upon by the Parties,
    D/B Contractor shall submit to Owner a written estimate (including detailed
    calculations supporting such estimates) of any adjustments to the Scope of Work
    (including adjustments to the Facility Guarantees or warranties), Project Schedule,
    Contract Price (including adjustments to the Schedule of Values and other
    obligations of D/B Contractor under this Agreement requested by it. Following
    Owner’s receipt of such Notice, Owner shall determine whether it agrees with such
    adjustments to the Scope of Work, Project Schedule, Contract Price or any other
    obligations of D/B Contractor. If Owner agrees with such adjustments, the Parties
    -4-
    Dissenting Opinion                                                                   04-14-00429-CV
    shall execute an appropriate Change Order. In the event that the Parties reach
    agreement on all terms of a Change Order except for a lump sum price, Owner may
    direct D/B Contractor to proceed with such additional Work with the price to be
    established in accordance with Section 9.1.5. If Owner disagrees with such
    adjustments, the Parties shall attempt to negotiate an equitable resolution, failing
    which the Parties shall resolve such disagreement in accordance with Article 15.
    Pending such resolution, the Owner shall issue a Construction Change Directive in
    accordance with Section 9.2.
    (Emphasis added). Casey’s December 30, 2005 letter advised CPS Energy that Wheelabrator’s
    problems were costing Casey money, and if Wheelabrator failed to compensate Casey, “Casey will
    formally notify CPS that your action is requested. At that time, Casey will request that CPS
    exercise your rights, through the Contract, to compensate Casey for the recovery costs.”
    (emphasis added).
    Even if the December 30, 2005 letter alone was not sufficient notice under Article 9.1.3,
    the record shows Casey had recurring project status meetings with CPS Energy and one may
    reasonably infer that Casey informed CPS Energy of Wheelabrator’s performance issues. E.g.,
    Casey’s December 30, 2005 letter to CPS Energy states Casey will give CPS Energy copies of the
    documents Casey issues to Wheelabrator regarding project progress; CPS Energy’s January 3,
    2006 letter referring to the “December 14, 2005 Weekly Construction Meeting.” Further, CPS
    Energy declared Wheelabrator in default, and CPS Energy unquestionably knew that Wheelabrator
    was failing to perform and Wheelabrator’s default would impair or frustrate Casey’s work.
    Taking Casey’s evidence as true and making reasonable inferences in its favor, Casey gave
    CPS Energy written notice in accordance with Article 9.1.3 and Casey was entitled to request relief
    under Article 9.1.3. In such a circumstance, if the parties agree on relief, CPS Energy issues a
    change order. If the parties do not agree, then Article 15, Claims and Dispute Resolution, is
    invoked.
    -5-
    Dissenting Opinion                                                                   04-14-00429-CV
    3.      Article 15, Claims and Dispute Resolution
    Article 15.2.1 addresses claims procedures:
    A Claim is a demand or assertion by the Parties, as a matter of right, adjustment or
    interpretation of Contract terms, payment of money, Extension of Time or other
    relief with respect to the terms of the Contract. The term “Claim” also includes
    other disputes and matters in question between the Owner, Wheelabrator and/or
    D/B Contractor arising out of or relating to the Contract.
    (Emphasis added).
    Article 15.2.2 addresses initiating a claim:
    Claims must be initiated within 10 days after occurrence of the event giving rise to
    such Claim or within 10 days after the claimant first recognizes the condition giving
    rise to the Claim, whichever is later. Claims must be initiated by written notice to
    the other Parties. Claims submitted to the Owner after the ten-day period will be
    rejected.
    (Emphasis added).
    Taking Casey’s evidence as true and making all reasonable inferences in its favor, I
    conclude Casey’s December 30, 2005 letter to CPS Energy, combined with Casey’s project reports
    and CPS Energy’s written declaration that Wheelabrator was in default, satisfied the written notice
    requirement. See Zachry 
    Const., 449 S.W.3d at 110
    (requiring the claimant to “plead facts with
    some evidentiary support that constitute a claim for which immunity is waived”).                After
    intervening months and meetings, Casey’s letter of August 3, 2007 states it has already tried the
    lower levels for dispute resolution, and it is seeking senior level review.         Casey attached
    documentation “in accordance with . . . Article 9 of the Contract” which “includes backup
    documentation to identify and support individual cost issues.” CPS Energy’s letter of July 27,
    2007 shows the items in dispute under Article 15.1.1.
    Even assuming Casey did not meet the Article 15.2.2 notice requirement, CPS Energy may
    have waived notice. See Jernigan v. Langley, 
    111 S.W.3d 153
    , 156 (Tex. 2003) (“‘Waiver is
    defined as ‘an intentional relinquishment of a known right or intentional conduct inconsistent with
    -6-
    Dissenting Opinion                                                                    04-14-00429-CV
    claiming that right.’” (quoting Sun Exploration & Prod. Co. v. Benton, 
    728 S.W.2d 35
    , 37 (Tex.
    1987))). In its August 15, 2007 letter, CPS Energy acknowledged outstanding disputed items,
    requested more information on the claims, and participated in dispute resolution procedures under
    Article 15. I agree with the majority’s conclusion that “[t]he 2007 correspondence indicates the
    parties’ attempt to resolve their dispute pursuant to the contract’s ‘Clams and Dispute Resolution’
    provisions as set forth in Article 15 of the contract.”
    Article 15.2.4 addresses procedures for making a claim for “other reasonable grounds”:
    If the D/B Contractor wishes to make a Claim for an increase in either the
    Wheelabrator Contract Price or D/B Contractor’s Contract Price, or if the D/B
    Contractor believes additional cost is involved for reasons including, but not
    limited to, (1) an order by the Owner to stop or repair Work where the D/B
    Contractor nor Wheelabrator was at fault, (2) in a situation in which the Work is
    considered additional to the Specifications, (3) a written order for a change in the
    Work issued by the Owner, or (4) other reasonable grounds, written Notice as
    provided herein shall be given by the D/B Contractor before proceeding to execute
    the Work.
    (Emphasis added). This provision is not expressly tied to, or limited by, the change order
    procedure. It requires notice, but making reasonable inferences in Casey’s favor based on the
    evidence in the record such as the correspondence and weekly project meetings, Casey either gave
    notice or CPS Energy waived the notice requirement.
    Article 15.4.4 provides for redress from a rejected claim:
    The Owner will approve or reject Claims by written decision, which shall state the
    reasons therefore and which shall notify the D/B Contractor of any change in the
    Contract Price or Contract Time, or both. The approval or rejection of a Claim by
    the Owner shall be subject to dispute resolution as outlined in Section 15.1 prior to
    litigation.
    (Emphasis added).
    Article 15.1, Procedure for Dispute Resolution, requires the parties to “use their Best
    Efforts in good faith to reach a reasonable and equitable resolution of the matter.” If project level
    managers are unable to resolve the matter, it is referred to senior officers. If they cannot resolve
    -7-
    Dissenting Opinion                                                                     04-14-00429-CV
    the matter, the parties must use their “Best Efforts in good faith” to agree on non-judicial
    resolution. If the dispute resolution fails, neither party may sue until at least thirty days after the
    senior officers received written notice of the dispute. Although Article 15.1 seeks to promote
    alternate dispute resolution and avoid litigation, it expressly anticipates the parties may seek relief
    in court.
    Viewing the parties’ evidence in the light most favorable to Casey, 
    Miranda, 133 S.W.3d at 228
    , I conclude CPS Energy failed to meet its burden to disprove as a matter of law any essential
    element of section 271.152, see Elliott-Williams 
    Co., 9 S.W.3d at 803
    ; cf. Mission Consol. Indep.
    Sch. Dist. v. Garcia, 
    372 S.W.3d 629
    , 642 (Tex. 2012) (granting a plea to the jurisdiction on a
    claim because the governmental entity negated an essential element of plaintiff’s claim and
    plaintiff failed to raise a fact question on the negated element). Because “Section 271.152 uses
    Section 271.153 to further define to what extent immunity has been waived,” I next consider
    whether Casey’s claimed damages are of the type recoverable under section 271.153. See Zachry
    
    Const., 449 S.W.3d at 110
    .
    SECTION 271.153 REQUIREMENTS
    A.      Casey’s Burden
    To show CPS Energy’s immunity was waived, Casey must also raise a genuine issue of
    material fact on whether its damages are recoverable under section 271.153. See id.; 
    Miranda, 133 S.W.3d at 228
    . Casey may recover damages from CPS Energy’s alleged breach of contract
    for “(2) the amount owed for change orders or additional work the contractor is directed to perform
    by a local governmental entity in connection with the contract.” TEX. LOC. GOV’T CODE ANN.
    § 271.153(a) (emphasis added).
    -8-
    Dissenting Opinion                                                                    04-14-00429-CV
    Disregarding the $150,000 per day liquidated damages provision, the majority states that
    “Casey points to no evidence of any directive from CPS Energy” to perform any additional work.
    But Casey’s vice-president’s affidavit averred that Casey performed work Wheelabrator—not
    Casey—was otherwise obligated to perform and includes letters between CPS Energy and Casey.
    For example, in an attachment to Casey’s August 3, 2007 letter to CPS Energy, Casey quoted
    Article 20.20 of the contract: “[Casey] and its surety shall bear no responsibility or liability for
    the Wheelabrator obligations, Wheelabrator’s design or the Performance Guarantees associated
    with the Wheelabrator portion of the Work.” (emphasis added).              Casey insisted that “as
    construction manager Casey bore no responsibility for ensuring Wheelabrator’s performance,” and
    Article 9.4 states that “[Casey] and Wheelabrator accepts [sic] the risk of mistake or error relating
    to the portion of their respective Work as outlined in [the Split Contract Matrix].” There is also
    evidence of weekly construction meetings and numerous letters between the parties addressing the
    scope and progress of the construction. Further, in its response to CPS Energy’s motion to dismiss,
    Casey pled that “Casey followed a process that was directed by CPS, all the while reserving
    Casey’s rights to bring a claim for the Wheelabrator-caused impacts associated with the default as
    acknowledged by CPS” and added that “Casey was continuously following CPS’[s] direction.”
    B.      CPS Energy’s Burden
    To be entitled to a grant of its plea to the jurisdiction, CPS Energy’s burden is to
    conclusively disprove CPS Energy directed Casey to perform additional work in connection with
    the contract. See TEX. LOC. GOV’T CODE ANN. § 271.153(a)(2); 
    Miranda, 133 S.W.3d at 228
    .
    CPS Energy’s evidence includes an affidavit that insists CPS Energy had little or no visibility into
    the Casey-Wheelabrator interactions. It also argued that as of August 2006 Casey had not raised
    any issues related to “the steel painting it performed which was within Wheelabrator’s scope of
    -9-
    Dissenting Opinion                                                                   04-14-00429-CV
    work or its costs related to an increase in steel quantities for the Project.” But CPS Energy
    acknowledged that on May 2, 2007, Casey informed CPS Energy that Casey would seek
    compensation from CPS Energy for the steel painting costs. This evidence supports the reasonable
    inference that CPS Energy directed Casey to perform work that—at least in Casey’s view—Casey
    was not otherwise obligated to perform by the contract.
    Article 20.20 requires Casey to “act as the overall construction manager of the Project” and
    to “oversee Wheelabrator’s . . . performance,” but Casey insists the article’s disclaimer that Casey
    “shall bear no responsibility or liability for the Wheelabrator obligations” shows Casey was not
    responsible for performing Wheelabrator’s work. Given Casey’s reliance on Article 20.20’s
    disclaimer, it is not reasonable to infer that Casey volunteered to perform Wheelabrator’s work at
    considerable expense to itself but at no cost to CPS Energy. To the contrary, considering the direct
    and circumstantial evidence, it is quite reasonable to infer that Casey performed Wheelabrator’s
    work because CPS Energy directed Casey to do so. It was CPS Energy’s burden to prove as a
    matter of law that in its many communications to Casey, including letters and project meetings, it
    did not direct Casey to perform the additional work. The evidence does not show CPS Energy met
    that burden.
    CONCLUSION
    It is undisputed that Wheelabrator defaulted and Casey performed some of the work
    originally assigned to Wheelabrator. CPS Energy seems to view Casey as a prime contractor with
    an obligation to perform Wheelabrator’s work at no additional cost to CPS Energy. Casey sees
    itself as Wheelabrator’s co-contractor, not its prime contractor, and Casey raises Article 20.20 as
    evidence it was not obligated to perform Wheelabrator’s work without additional compensation.
    - 10 -
    Dissenting Opinion                                                                   04-14-00429-CV
    Although many statements in CPS Energy’s affidavits contradict assertions in, and
    reasonable inferences I draw from, Casey’s evidence, this court must leave disputed questions of
    material fact to the fact-finder. See 
    Miranda, 133 S.W.3d at 228
    . Casey argued and pled facts
    with supporting evidence that it complied with the contract’s procedures to request additional
    compensation. Whether Casey can prove by a preponderance of the evidence that it actually
    complied with the contract’s provisions is not the question before us. See Zachry 
    Const., 449 S.W.3d at 110
    (restating the claimant’s burden: “the claimant must plead facts with some
    evidentiary support that constitute a claim for which immunity is waived, not [prove] that the
    claimant will prevail”).
    Our question is whether, viewing all the evidence in the light most favorable to Casey and
    making all reasonable inferences in its favor, Casey raised a genuine issue of material fact on
    whether its claims meet the statutory requirements to waive CPS Energy’s immunity. The
    evidence shows Casey raised a genuine issue of material fact on whether it asserted a claim for
    breach of a written contract, and thus Casey met its burden under section 271.152. The evidence
    also shows Casey raised a genuine issue of material fact on whether CPS Energy directed Casey
    to perform “additional work . . . in connection with the contract,” and thus Casey met its burden
    under section 271.153.
    Because Casey met its burdens, and CPS Energy failed to conclusively disprove any
    essential element of waiver, I would affirm the trial court’s order. Because the majority reverses
    the trial court’s order, I respectfully dissent.
    Patricia O. Alvarez, Justice
    - 11 -