Gerardo Lascano v. Huser Construction Company ( 2015 )


Menu:
  •                              Fourth Court of Appeals
    San Antonio, Texas
    MEMORANDUM OPINION
    No. 04-14-00311-CV
    Gerardo LASCANO,
    Appellant
    v.
    HUSER
    HUSER CONSTRUCTION COMPANY,
    Appellee
    From the 198th Judicial District Court, Kerr County, Texas
    Trial Court No. 12406B
    Honorable M. Rex Emerson, Judge Presiding
    Opinion by:      Rebeca C. Martinez, Justice
    Sitting:         Karen Angelini, Justice
    Marialyn Barnard, Justice
    Rebeca C. Martinez, Justice
    Delivered and Filed: May 27, 2015
    REVERSED AND REMANDED
    Gerardo Lascano sued Huser Construction Company asserting claims for breach of
    contract, promissory estoppel, and quantum meruit based on work he performed on a project for
    which Huser was the general contractor and construction manager. Huser filed motions for
    traditional and no-evidence summary judgment asserting numerous grounds in each motion. The
    trial court granted both motions without stating the basis on which the motions were granted.
    Lascano appeals asserting he presented evidence raising genuine issues of material fact in response
    04-14-00311-CV
    to both motions. We reverse the trial court’s judgment and remand the cause to the trial court for
    further proceedings.
    BACKGROUND
    The Salvation Army contracted with Huser for the construction of a community center. As
    previously noted, Huser was both the general contractor and the construction manager for the
    project. The Salvation Army separately contracted with ACFS Security, LLC to install the fire
    and security systems for the project. Lascano was an employee of ACFS.
    At the beginning of the project, Lascano’s work was being supervised by two ACFS
    supervisors, Alfred Trevino and Pete Padilla, and ACFS was paying Lascano for the work he
    performed. During this time, Lascano would attend regular on-site meetings to discuss the project
    schedule.    Marty Dressen, Huser’s project manager, and Barry Fisher, Huser’s project
    superintendent, were in charge of the schedule. Scott Rain, Huser’s director of operations, was
    also present at the construction site at various times.
    At some point during the project, Trevino and Padilla disappeared from the project.
    Lascano stated the disappearance occurred when he was in the middle of his part of the project.
    On September 27, 2010, Frank Dunlap, Salvation Army’s director of operations and planning for
    the community center, sent an email to Dressen, Fisher, and Rain informing them that Trevino and
    Padilla were no longer with ACFS.
    Around the same time Trevino and Padilla disappeared, Lascano told Fisher he was not
    going to continue working on the project because ACFS was not paying him. Lascano stated both
    Fisher and Rain told him to continue working and they “would make sure [he] got paid.” Based
    on their promises, Lascano continued working and completed the project. A certificate of
    occupancy was issued for the community center on November 22, 2010.
    -2-
    04-14-00311-CV
    When Huser subsequently failed to pay Lascano, he filed the underlying lawsuit, alleging
    breach of contract, promissory estoppel, and quantum meruit claims. 1 As previously noted, the
    trial court granted summary judgment in favor of Huser. Lascano timely appealed.
    STANDARD OF REVIEW
    We review a trial court’s decision to grant no evidence and traditional motions for summary
    judgment de novo. Valance Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005);
    Strandberg v. Spectrum Office Bldg., 
    293 S.W.3d 736
    , 738 (Tex. App.—San Antonio 2009, no
    pet.). “When reviewing a traditional or a no-evidence summary judgment, we accept the non-
    movant’s evidence as true and ‘indulge every reasonable inference and resolve any doubts in the
    non-movant’s favor.’” Strandberg, 203 S.W.3d at 738 (quoting Joe v. Two Thirty Nine Joint
    Venture, 
    145 S.W.3d 150
    , 157 (Tex. 2004)). A traditional summary judgment may be granted
    when the summary judgment evidence shows “there is no genuine issue as to any material fact and
    the moving party is entitled to judgment as a matter of law.” TEX. R. CIV. P. 166a(c).
    A movant is entitled to a no-evidence summary judgment if, “[a]fter adequate time for
    discovery, ... there is no evidence of one or more essential elements of a claim or defense on which
    an adverse party would have the burden of proof at trial.” TEX. R. CIV. P. 166a(i). The trial court
    “must grant” the no-evidence motion unless the non-movant “produces summary judgment
    evidence raising a genuine issue of material fact” on the elements challenged by the movant. 
    Id.
    “A genuine issue of material fact exists if more than a scintilla of evidence establishing the
    existence of the challenged element is produced.” Ford Motor Co. v. Ridgway, 
    135 S.W.3d 598
    ,
    600 (Tex. 2004). “More than a scintilla of evidence exists when the evidence rises to a level that
    would enable reasonable and fair-minded people to differ in their conclusions.” King Ranch, Inc.
    1
    Lascano sued both ACFS and Huser. Lascano obtained a default judgment against ACFS. ACFS is not a party to
    this appeal.
    -3-
    04-14-00311-CV
    v. Chapman, 
    118 S.W.3d 742
    , 751 (Tex. 2003) (internal citations omitted). “Less than a scintilla
    of evidence exists when the evidence is so weak as to do no more than create a mere surmise or
    suspicion of a fact.” 
    Id.
    EXISTENCE OF A VALID CONTRACT
    One of the elements of a breach of contract claim is the existence of a valid contract. CCC
    Group, Inc. v. South Cent. Cement, Ltd., 
    450 S.W.3d 191
    , 196 (Tex. App.—Houston [1st Dist.]
    2014, no pet.); MacIntire v. Armed Forces Benefit Ass’n, 
    27 S.W.3d 85
    , 88-89 (Tex. App.—San
    Antonio 2000, no pet.). Huser’s no-evidence motion for summary judgment asserted no evidence
    existed of a contract between Huser and Lascano. In response, Lascano asserted evidence existed
    of a unilateral contract.
    “[A] unilateral contract is created when a promisor promises a benefit if the promisee
    performs.” City of Houston v. Williams, 
    353 S.W.3d 128
    , 135-36 (Tex. 2011). “A unilateral
    contract becomes enforceable when the promisee performs.” 
    Id.
     For example, “when an employer
    offered to share five percent of the proceeds of a sale or merger of the company with certain
    employees if they remained employed until the sale or merger, a unilateral contract was formed
    when the employees remained employed for the requisite time.” 
    Id.
    In this case, Lascano produced his affidavit and his deposition testimony as summary
    judgment evidence. Lascano stated in his affidavit and testified in his deposition that Fisher and
    Rain promised they would make sure Lascano “got paid” if he continued working on the project,
    Because Lascano continued working until the project was completed, a unilateral contract was
    formed based on Fisher’s and Rain’s promises. Therefore, summary judgment was not proper on
    this ground.
    -4-
    04-14-00311-CV
    DAMAGES
    In its no-evidence motion, Huser challenged the damages element of each of Lascano’s
    claims. In response to Huser’s motion, Lascano was not required to marshal evidence to prove his
    damages, but was only required to point out evidence that raised a fact issue regarding his damages.
    See Johnson v. Brewer & Pritchard, P.C., 
    73 S.W.3d 193
    , 207 (Tex. 2002); TEX. R. CIV. P.
    166(a)(i) cmt.; see also Community Initiatives, Inc. v. Chase Bank of Tex., 
    153 S.W.3d 270
    , 280
    (Tex. App.—El Paso 2004, no pet.) (noting non-movant was not required to present all of its
    evidence in the order it would be presented at trial but only had to point out some evidence that
    raises a fact issue).
    To recover damages on a breach of contract claim, Lascano was required to establish that
    he suffered some pecuniary loss as a result of the breach. S. Elec. Servs., Inc. v. City of Houston,
    
    355 S.W.3d 319
    , 324 (Tex. App.—Houston [1st Dist.] 2011, pet. denied). Generally, the measure
    of damages for breach of contract is that which restores the injured party to the economic position
    he would have enjoyed if the contract had been performed. Mood v. Kronos Products, Inc., 
    245 S.W.3d 8
    , 12 (Tex. App.—Dallas 2007, pet. denied); Bowen v. Robinson, 
    227 S.W.3d 86
    , 96 (Tex.
    App.—Houston [1st Dist.] 2006, pet. denied). Damages recoverable for promissory estoppel are
    the amount necessary to restore the party to the position the party would have been in had it not
    acted in reliance on the promise. Fretz Const. Co. v. S. Nat’l Bank of Houston, 
    626 S.W.2d 478
    ,
    483 (Tex. 1981); G.D. Holdings, Inc. v. H.D.H. Land & Timber, L.P., 
    407 S.W.3d 856
    , 862 (Tex.
    App.—Tyler 2013, no pet.). The correct measure of damages to recover on quantum meruit is the
    reasonable value of the work performed and the materials furnished. LTS Group, Inc. v. Woodcrest
    Capital, L.L.C., 
    222 S.W.3d 918
    , 920-21 (Tex. App.—Dallas 2007, no pet.).
    In this case, Lascano produced records showing the number of hours he spent completing
    the project. Lascano also produced receipts for materials he purchased in order to complete the
    -5-
    04-14-00311-CV
    project. In his affidavit, Lascano stated that ACFS was paying him $18.50 per hour. Lascano
    further stated that he was paid around $18 to $20 per hour for work installing alarm systems, and
    after completing the project, he worked another job installing alarms and was paid about $18.00
    per hour.
    We recognize the nature of the evidence that must be produced to defeat a no-evidence
    motion will vary based on the nature of the alleged damages. We also acknowledge that whether
    a party adequately points out evidence relating to the challenged elements of a claim can be “a
    close question.” Johnson, 73 S.W.3d at 207. However, we hold Lascano’s “response met the
    minimum requirements of Rule 166a(i)” because the records, receipts, and affidavit testimony he
    produced pointed out some evidence that raised a fact issue as to his damages. Johnson, 73 S.W.3d
    at 207-08; TEX. R. CIV. P. 166a(i) cmt. Accordingly, summary judgment was not proper on this
    ground. 2
    VALUABLE SERVICES FOR HUSER
    To recover on a claim for quantum meruit, a plaintiff must show (1) he rendered valuable
    services, (2) to the party sought to be charged, (3) which were accepted by the party sought to be
    charged, and (4) under circumstances as would reasonably notify the recipient that the plaintiff
    expected to be paid by the recipient. Heldenfels Bros. Inc. v. City of Corpus Christi, 
    832 S.W.2d 39
    , 41 (Tex. 1992); Walker & Assocs. Surveying, Inc. v. Roberts, 
    306 S.W.3d 839
    , 858 (Tex.
    App.—Texarkana 2010, no pet.). In its no-evidence motion, Huser contended no evidence existed
    2
    In its brief, Huser cites San Saba Energy, L.P. v. Crawford, 
    171 S.W.3d 323
    , 331 (Tex. App.—Houston [14th Dist.]
    2005, no pet.), to assert this court’s job is not to sift through Lascano’s evidence to calculate what Lascano is owed.
    First, as previously noted, Lascano was only required to point out evidence that raises a fact issue regarding his
    damages. He was not required to prove the exact amount he was owed. Second, in San Saba Energy, L.P., the non-
    movants’ response generally stated the summary judgment raised fact issues as to all elements of their claims and
    incorporated six hundred fifty pages of evidence by reference. 
    Id.
     In this case, Lascano stated the amount he typically
    was paid for each hour worked, and attached 40 pages of time records as one exhibit to his affidavit and 17 pages of
    receipts as another exhibit. Accordingly, San Saba Energy, L.P. is clearly distinguishable from the instant case.
    -6-
    04-14-00311-CV
    to show Lascano “provided valuable services for Huser.” Similarly, in its traditional motion for
    summary judgment, Huser contended, “as a matter of law, [Lascano] cannot establish that the
    services or material he provided were provided for Huser.” In this motion, Huser argues it was
    not the owner of the project and received absolutely no benefit or only an incidental benefit from
    Lascano’s work. 3
    In his brief, Lascano asserts the facts in this case are similar to the facts in Concept Gen.
    Contracting, Inc. v. Asbestos Maint. Servs., Inc., 
    346 S.W.3d 172
     (Tex. App.—Amarillo 2011, pet.
    denied). In that case, BW Affordable Housing, L.P. contracted with Concept General Contracting,
    Inc. to renovate some apartment units. 
    Id. at 178
    . As part of this project, Concept and Asbestos
    Maintenance Services, Inc. (AMS) entered into a subcontract for AMS to provide asbestos
    abatement for certain, specific areas. 
    Id.
     During the course of the project, Concept requested
    additional work. 
    Id.
     AMS gave Concept a quote for the additional work, and after the work was
    performed, Concept paid AMS for the additional work. 
    Id.
     While AMS was still performing the
    work pursuant to the contracts, Concept’s construction superintendent kept adding additional areas
    to the specified area. 
    Id.
     Although Concept paid for some of the additional work, Concept stopped
    paying at a certain point in time, and AMS eventually stopped working. 
    Id.
     AMS sued Concept
    to recover damages for the work performed and judgment was entered in favor of AMS. 
    Id.
    On appeal, Concept asserted it could not be liable for quantum meruit damages because it
    did not own the apartment units. 
    Id. at 181-82
    . The Amarillo court first noted in order to recover
    quantum meruit damages, the plaintiff must show that its efforts were undertaken for the person
    sought to be charged. 
    Id. at 182
    . The court also noted the evidence was clear that AMS contracted
    3
    Huser’s traditional motion also asserted that Lascano was required to show that Huser was “unjustly enriched” as an
    element of Lascano’s quantum meruit claim; however, “unjust enrichment” is a separate theory from quantum meruit.
    See Heldenfels Bros., Inc., 832 S.W.2d at 41; Pepi Corp. v. Galliford, 
    254 S.W.3d 457
    , 459-60 (Tex. App.—Houston
    [1st Dist.] 2007, pet. denied).
    -7-
    04-14-00311-CV
    with Concept and never dealt with BW directly. 
    Id.
     Finally, the court noted that all of the extra
    work was requested at the direction of Concept’s construction superintendent. 
    Id.
     Therefore, the
    court held that AMS performed the extra work for Concept, not BW. 
    Id.
     The court also held that
    the work was performed for Concept’s benefit because the evidence established that Concept
    needed AMS’s abatement work to complete its general contract with BW. Id.; see also RC Mgmt.,
    Inc. v. Tex. Waste Sys., Inc., No. 04-02-00488-CV, 
    2003 WL 1712535
    , at *3-4 (Tex. App.—San
    Antonio Apr. 2, 2003, no pet.) (holding evidence supported quantum meruit claim where appellant
    contractor promised payment and needed services provided by appellee to fulfill its contractual
    obligations to owner) (mem. op.).
    Huser argues the Concept case is distinguishable from the present case because Huser did
    not contract with ACFS. We disagree that this distinction makes the Amarillo court’s holding
    inapplicable to the instant case.
    Although ACFS initially contracted with Salvation Army to perform the installation
    services, ACFS’s performance under that contract ended when it stopped paying Lascano to
    perform its work. At that time, Lascano informed Fisher that he would no longer perform the
    installation work. Both Rain and Dressen admit in their depositions that they then asked Lascano
    to remain on the job to complete the work. Dressen stated she told Lascano she needed him to
    stay, and Rain and Fisher promised they would make sure Lascano “got paid.” Therefore, as
    previously noted, a unilateral contract existed based on Rain’s and Fisher’s promise. Accordingly,
    like the facts in Concept, a contract did exist between Lascano and Huser.
    With regard to whether Huser benefitted from Lascano’s services, Rain, Dressen, and
    Fisher all testified about the scheduling sequence necessary for Huser to complete its contract, and
    delays in the alarm and security installation would have adversely impacted the schedule. In
    addition, the fire alarm was required to be completely installed and tested before Huser could
    -8-
    04-14-00311-CV
    obtain the certificate of occupancy for the community center that Huser was required to deliver
    under its contract. Finally, both Rain and Dressen testified that Huser benefitted from Lascano’s
    work which enabled Huser to achieve substantial completion and obtain the certificate of
    occupancy. Accordingly, we hold the evidence established a genuine issue of material fact as to
    whether Lascano provided valuable services to Huser for its benefit, and summary judgment was
    improper as to Lascano’s quantum meruit claim.
    STATUTE OF FRAUDS
    In its traditional motion, Huser asserted Lascano’s breach of contract and promissory
    estoppel claims were barred by the statute of frauds because the claims were based on Huser’s
    promise to answer for ACFS’s debt. See TEX. BUS. & COM. CODE ANN. § 26.01(b)(2) (West 2015)
    (promise to answer for debt of another person is not enforceable unless promise is in writing).
    Lascano responded that the statute of frauds was not applicable to its promissory estoppel claim,
    and with regard to its breach of contract claim, Lascano responded Huser’s promise is enforceable
    under the “main purpose” exception to the statute of frauds.
    “Although promissory estoppel is normally a defensive theory, it may nonetheless be
    asserted by a plaintiff as an affirmative ground for relief.” Medistar Corp. v. Schmidt, 
    267 S.W.3d 150
    , 163 (Tex. App.—San Antonio 2008, pet. denied). The statute of frauds “is not a defense to
    an action for affirmative relief under the doctrine of promissory estoppel.” 
    Id.
     Accordingly,
    summary judgment would not be proper on this ground.
    “Whether a contract comes within the statute of frauds is a question of law,” which is
    reviewed de novo. Dynegy, Inc. v. Yates, 
    422 S.W.3d 638
    , 642 (Tex. 2013). Under the “main
    purpose” exception to the statute of frauds, a promise to pay the debt of another is not barred by
    the statute of frauds if the promisor assumed primary responsibility for the debt and his leading
    objective is to serve some interest or purpose of his own. Cruz v. Andrews Restoration, Inc., 364
    -9-
    04-14-00311-CV
    S.W.3d 817, 827 (Tex. 2012) (quoting Lemmon v. Box, 
    20 Tex. 329
    , 333 (1857)); Haas Drilling
    Co. v. First Nat’l Bank in Dallas, 
    456 S.W.2d 886
    , 891 (Tex. 1970). “The main purpose doctrine
    requires that: (1) the promisor intended to create primary responsibility in itself to pay the debt;
    (2) there was consideration for the promise; and (3) the consideration given for the promise was
    primarily for the promisor’s own use and benefit—that is, the benefit it received was the promisor’s
    main purpose for making the promise.” Cruz, 364 S.W.3d at 828.
    “Unless reasonable minds could not differ as to the intent to be a surety or not, the precise
    words or form used are not controlling.” Gulf Liquid Fertilizer Co. v. Titus, 
    354 S.W.2d 378
    , 384
    (Tex. 1962). “If the words used are not clear and are susceptible of more than one meaning, the
    question of intent to be primarily responsible for another’s debt is one for the finder of fact, taking
    into account all the facts and circumstances of the case including the words used by the promisor.”
    
    Id.
    In Gulf Liquid Fertilizer Co., the Texas Supreme Court stated that a promise “to see that
    the debt was paid” were words “subject to several interpretations as to intent.” 
    Id.
     Accordingly,
    the court deferred to the trial court’s interpretation as the trier of fact that those words coupled with
    some evidence that the promisor also agreed to pay the debt was a promise to accept primary
    responsibility. Id. at 384-85. Similarly, in this case, we hold the promise “to make sure [Lascano]
    got paid” is “subject to several interpretations as to intent.” Id. at 384. Accordingly, a genuine
    issue of material fact exists as to the applicability of the main purpose doctrine, and summary
    judgment would not be proper on statute of frauds grounds. 4
    4
    Huser relies heavily in its brief on a 1910 opinion styled E.J. Chauvin & Co v. McKnight, 
    63 Tex. Civ. App. 35
    , 
    132 S.W. 383
     (Tex. Civ. App. 1910). In that case, the plaintiffs sought to hold Aaronson Bros. responsible for paying for
    the work the plaintiffs performed under a construction contract they entered into with J.F. McKnight. 
    132 S.W. at 384
    . One of the plaintiffs testified when the work was “half done I saw Mr. Aaronson again. And he again told me
    that he would see me paid. I was to look to Mr. Aaronson if Mr. McKnight didn’t pay. Unless Mr. McKnight didn’t
    pay, Mr. Aaronson didn’t owe me anything. In case Mr. McKnight didn’t pay, then I looked to Mr. Aaronson. If Mr.
    McKnight didn’t pay us, he would pay us.” 
    Id. at 386
    . The other plaintiff testified, “I had no particular right to go to
    - 10 -
    04-14-00311-CV
    ENFORCEABILITY OF PROMISE AND ORAL AGREEMENT
    Huser’s traditional motion for summary judgment asserted Lascano’s alleged oral
    agreement failed because no agreement was reached regarding the amount Lascano would be paid.
    Huser’s motion similarly asserted the promise to “make sure [Lascano] got paid” was not
    sufficiently certain to be enforceable. Based on these assertions, Huser contended Lascano was
    not entitled to recover on his breach of contract and promissory estoppel claims as a matter of law.
    In its brief, Huser asserts any oral agreement between Huser and Lascano would be an
    employment agreement, and compensation typically is an essential term of an employment
    agreement.     See City of Houston, 353 S.W.3d at 138-39 (“In the context of employment
    agreements, typical essential terms include, among other, compensation, duties or
    responsibilities.”). Huser further asserts Lascano cannot inform the court what Huser allegedly
    agreed to pay Lascano or any other terms of the alleged promise. Lascano responds that the
    agreement was one for services, not an employment agreement, and contends the law favors
    holding agreements to be sufficiently definite when the services have been fully performed.
    A.       Enforceability of Contract
    “[W]hether an agreement fails for indefiniteness is a question of law to be determined by
    the court.” America’s Favorite Chicken Co. v. Samaras, 
    929 S.W.2d 617
    , 622 (Tex. App.—San
    Antonio 1996, writ denied). As previously noted, we review questions of law de novo. Dynegy,
    Inc., 422 S.W.3d at 642.
    “[T]o be enforceable, a contract must be sufficiently certain to enable the court to determine
    the legal obligations of the parties.” Bendalin v. Delgado, 
    406 S.W.2d 897
    , 899 (Tex. 1966). “It
    has often been said, moreover, that a contract which does not fix the price or consideration or
    Aaronson unless McKnight didn’t carry out his contract.” The foregoing testimony makes the facts in the cited case
    clearly distinguishable from the instant case.
    - 11 -
    04-14-00311-CV
    provide an adequate way in which it can be fixed is too incomplete to be specifically enforceable.”
    
    Id.
     The Texas Supreme Court noted, however, that this rule appeared to arise in actions for specific
    performance of contracts for the sale of land, and the requirement that a price be fixed arose, in
    part, from concerns for the statute of frauds. 
    Id.
     The court then concluded, “Where the parties
    have done everything necessary to make a binding agreement for the sale of goods or services,
    their failure to specify the price does not leave the contract so incomplete that it cannot be enforced.
    In such a case it will be presumed that a reasonable price was intended.” Id. at 900.
    In discussing when courts should be willing to presume a reasonable price was intended,
    this court stated, “The law favors finding agreements sufficiently definite for enforcement”
    particularly where one party “has already provided the services for which the compensation was
    to be paid.” America’s Favorite Chicken Co., 929 S.W.2d at 623-24. In this case, Rain and
    Dressen admit that they requested Lascano to remain on the job, and he fully performed all of the
    services necessary for Huser to obtain a certificate of occupancy as required by its contract.
    Moreover, “there is a certain basis for determining the remedy” since the action is one for damages
    and Lascano’s damages can be calculated based on the number of hours he worked in completing
    the project. Id. at 623 (“Where the evidence shows that the parties intended to enter into an
    agreement, the courts should find the contract to be definite enough to grant a remedy provided
    that there is a certain basis for determining the remedy.”). Therefore, we hold the unilateral
    contract between Huser and Lascano was sufficiently definite to be enforceable, and summary
    judgment was improper as to Lascano’s breach of contract claim.
    B.      Promise Sufficiently Specific
    To support a finding of promissory estoppel, the asserted ‘promise’ must be sufficiently
    specific and definite that it would be reasonable for the promisee to rely upon it as a commitment
    to future action. Corpus Christi Day Cruise, LLC v. Christus Spohn Health Sys. Corp., 398 S.W.3d
    - 12 -
    04-14-00311-CV
    303, 311 (Tex. App.—Corpus Christi 2012, pet. denied); Comiskey v. FH Partners, LLC, 
    373 S.W.3d 620
    , 635 (Tex. App.—Houston [14th Dist.] 2012, pet. denied). In this case, Lascano
    testified that Huser promised it would make sure Lascano “got paid” if he kept working. Because
    Huser raised this issue in its traditional motion for summary judgment, Huser was required to
    conclusively establish that it would not be reasonable for Lascano to rely on Huser’s promise as a
    commitment to making sure Lascano “got paid” for the work he continued to perform. Having
    reviewed the summary judgment evidence presented, we hold Huser failed to establish as a matter
    of law that its promise was not sufficiently specific and definite. Accordingly, summary judgment
    was improper as to Lascano’s promissory estoppel claim.
    CONCLUSION
    Because the granting of the summary judgment was not proper on any of the asserted
    grounds as to any of Lascano’s causes of action, the trial court’s judgment is reversed, and the
    cause is remanded to the trial court for further proceedings.
    Rebeca C. Martinez, Justice
    - 13 -