Bhp Engineering and Construction, L.P. v. Heil Construction Management, Inc. ( 2013 )


Menu:
  •                             NUMBER 13-13-00206-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    BHP ENGINEERING AND
    CONSTRUCTION, L.P.,                                                       Appellant,
    v.
    HEIL CONSTRUCTION
    MANAGEMENT, INC.,                                                          Appellee.
    On appeal from the 28th District Court
    of Nueces County, Texas.
    MEMORANDUM OPINION
    Before Chief Justice Valdez and Justices Benavides and Longoria
    Memorandum Opinion by Justice Benavides
    This case involves chapter 150 of the Texas Civil Practice and Remedies Code.
    By two issues, appellant, BHP Engineering & Construction, L.P. (BHP), contends the trial
    court abused its discretion when it:          (1) granted appellee, Heil Construction
    Management and Construction, L.P.’s (Heil’s) request for extension of time to file a
    certificate of merit and (2) denied BHP’s motion to dismiss. We affirm.
    I. BACKGROUND
    U.S. Ecology owns and operates a hazardous waste facility in Robstown, Texas.
    U.S. Ecology contracted with Heil to serve as the general contractor for an expansion of
    their facility.   The expansion sought to include a new stabilization building (the “Stab
    Building”) which would house equipment that would convert hazardous waste into
    environmentally acceptable waste for disposal.
    Heil issued a request for proposals for the mechanical and design engineering
    services required to construct the Stab Building.       BHP submitted a proposal and
    ultimately received the contract. The project included designs for, among other things,
    a mechanical transfer system, a toxic dust collection system, a baghouse, a shredder
    drum-lift system, and a four-sided dust containment curtain system. The latter, the
    four-sided dust containment curtain system, became the subject of the underlying
    lawsuit.
    Heil alleged that it discovered BHP incorrectly designed the dust containment
    curtain system on January 18, 2011.         Heil claimed it was forced to re-design and
    replace the faulty containment system at its own cost in order to meet U.S. Ecology’s
    strict construction deadline.   As a result of this, Heil sued BHP on December 27, 2012
    for negligence, breach of contract, and breach of express warranty for services.    Even
    though Heil was suing BHP, an engineering firm, it did not file a certificate of merit as
    2
    required by chapter 150 of the Texas Civil Practices and Remedies Code.             Chapter 150
    requires a plaintiff to file an affidavit of a third-party licensed engineer practicing in the
    same area as defendant, setting forth specifically at least one negligent act, error, or
    omission which caused the alleged injury.           See TEX. CIV. PRAC. & REM. CODE ANN.
    § 150.002(a) (West 2011). The certificate should be served on the same day as the
    lawsuit.   
    Id. However, some
    exceptions exist to this rule:       (1) if the lawsuit is filed ten
    days before the statute of limitation, a party has an automatic extra 30 days to provide a
    certificate of merit and (2) when a trial court can grants an extension for good cause.         
    Id. § 150.002(c).
        Heil filed its lawsuit 22 days before the statute of limitations on its claims
    expired.
    On February 28, 2013, BHP filed a Motion to Dismiss against Heil for failing to file
    a certificate of merit.   In response, Heil filed its Certificate of Merit with the trial court on
    March 15, 2013.      Heil filed a Motion for Extension of Time to file its certificate of merit on
    the same day.      In its motion, Heil asserted various reasons why it could not file the
    certificate of merit on the same day as its petition:      (1) it did not engage an attorney
    until late 2012, and the statute of limitations on its claim was about to run in January
    2013; (2) the initial engineer it wanted to engage was not qualified to render the
    certificate of merit, so it had to search for another one in short order; and (3) after filing
    suit in this case, its attorney of record had eye surgery and then immediately proceeded
    to trial in a different Texas county.    Heil argued that BHP had asserted no prejudice in
    its motion to dismiss, and that “the case ha[d] been on file less than 90 days and that
    3
    [BHP had] been in the suit less than 45 days.” It also stressed that the trial court had
    discretion in determining whether good cause existed.
    In response, BHP reasserted that the certificate of merit was untimely—Heil’s
    claim was not filed within 10 days of the statute of limitation, and its certificate was not
    filed within thirty days of the deadline.   Instead, Heil’s petition was filed 22 days before
    the statute’s expiration and its certificate was served 78 days after the lawsuit was filed.
    BHP further argued that Heil failed to set forth valid reasons for a good cause extension.
    BHP also asserted that Heil’s engineer, Jean-Paul Budinger, was unqualified to write the
    certificate of merit because he was a structural engineer and not a chemical engineer.
    Finally, BHP proclaimed that Budinger’s certificate was insufficient because it was
    conclusory and lacked a factual basis.
    The trial court granted Heil’s motion for extension of time to file a certificate of
    merit and denied BHP’s motion to dismiss. BHP appealed.           See 
    id. § 150.002(f)
    (West
    2011) (providing that an order “denying a motion for dismissal is immediately appealable
    as an interlocutory order”).
    II. STANDARD OF REVIEW AND APPLICABLE LAW
    A.     Standard of Review
    We review a trial court's decision to grant or deny a defendant's motion to dismiss
    under section 150.002 of the Texas Civil Practice and Remedies Code for abuse of
    discretion.   See WCM Group, Inc. v. Brown, 
    305 S.W.3d 222
    , 229 (Tex. App.—Corpus
    Christi 2009, pet. dism’d); Landreth v. Las Brisas Council of Co–Owners, Inc., 
    285 S.W. 3d
    492, 496 (Tex. App.—Corpus Christi 2009, no pet.).              A trial court abuses its
    4
    discretion by acting arbitrarily, unreasonably, or without considering guiding principles.
    Downer v. Aquamarine Operators Inc., 
    701 S.W.2d 238
    , 241–42 (Tex. 1985).            “A trial
    court has no discretion in determining what the law is or applying the law to the facts.”
    
    Landreth, 285 S.W.3d at 496
    .    A trial court does not abuse its discretion when it bases a
    decision on conflicting evidence—rather, a factual decision is an abuse of discretion only
    if there is no evidence to support the decision.         
    Whirlpool, 251 S.W.3d at 102
    .
    “Merely because a trial court may decide a matter within its discretion in a different
    manner than an appellate court does not demonstrate an abuse of discretion.”
    Landreth, 
    285 S.W. 3d
    at 496.
    B.    Applicable Law
    The applicable version of section 150.002 provides as follows:
    (a) In any action or arbitration proceeding for damages arising out of the
    provision of professional services by a licensed or registered
    professional, the plaintiff shall be required to file with the complaint an
    affidavit of a third-party licensed architect, licensed professional
    engineer, registered landscape architect, or registered professional
    land surveyor who:
    (1) is competent to testify;
    (2) holds the same professional license or registration as the
    defendant; and
    (3) is knowledgeable in the area of practice of the defendant and
    offers testimony based on the person's:
    (A)   knowledge;
    (B)   skill;
    (C)   experience;
    (D)   education;
    (E)   training; and
    (F)   practice.
    5
    (b) The affidavit shall set forth specifically for each theory of recovery for
    which damages are sought, the negligence, if any, or other action,
    error, or omission of the licensed or registered professional in
    providing the professional service, including any error or omission in
    providing advice, judgment, opinion, or a similar professional skill
    claimed to exist and the factual basis for each such claim. The
    third-party licensed architect, licensed professional engineer,
    registered landscape architect, or registered professional land
    surveyor shall be licensed or registered in this state and actively
    engaged in the practice of architecture, engineering, or surveying.
    (c) The contemporaneous filing requirement of Subsection (a) shall not
    apply to any case in which the period of limitation will expire within 10
    days of the date of filing and, because of such time constraints, the
    plaintiff has alleged that an affidavit of a third-party licensed architect,
    licensed professional engineer, registered landscape architect, or
    registered professional land surveyor could not be prepared. In such
    cases, the plaintiff shall have 30 days after the filing of the complaint to
    supplement the pleadings with the affidavit. The trial court may, on
    motion, after hearing and for good cause, extend such time as it shall
    determine justice requires.
    (d) The defendant shall not be required to file an answer to the complaint
    and affidavit until 30 days after the filing of such affidavit.
    TEX. CIV. PRAC. & REM. CODE ANN. § 150.002(a)-(d).
    III. DISCUSSION
    A.     The Extension of Time
    Heil set forth three reasons why it did not file the certificate of merit on the same
    day as its petition.   First, Heil claimed that it did not engage an attorney until late 2012,
    and the statute of limitations on its claim against BHP would expire in January 2013.
    Second, the initial engineer Heil wanted to engage was not qualified to render the
    certificate of merit, so it had to search for another one quickly.     Third, Heil’s attorney
    had eye surgery in December 2012 and then immediately had another trial in a different
    Texas county shortly after filing suit in this case.
    6
    1.     The Statute of Limitations Exception
    It is undisputed that Heil did not file a certificate of merit when it filed its original
    petition on December 27, 2012. It is further undisputed that Heil filed its original petition
    more than ten days before the expiration of the limitations period; its lawsuit, in fact, was
    filed 22 days before the limitations period expired.    Section 150.002(b)’s plain language
    provides for an automatic extension of 30 days to file the certificate of merit if the suit is
    filed within ten days of the expiration of the limitations period.     
    Id. § 150.002(b).
    We
    agree with BHP that Heil was not entitled to this automatic exception.       
    Id. 2. The
    Good Cause Exception
    In the alternative, section 150.002 provides that “the trial court may, on motion,
    after hearing and for good cause, extend such time as it shall determine justice requires.”
    
    Id. In WCM
    Group, Inc. v. Brown, we held that we would not
    limit the good cause extension to situations where the party files suit within
    ten days of the expiration of limitations, particularly given that the purpose
    of the statute is to provide a basis for the trial court to conclude that the
    plaintiff’s claims have merit, not to dismiss meritorious claims on a
    procedural technicality. . . . Thus, the trial court was within its power, as
    provided by the statute, to consider and grant the [plaintiffs’] request for an
    extension of time upon a showing that good cause existed and justice
    requested an 
    extension. 305 S.W.3d at 230
    (internal citation omitted).          BHP invites us to reconsider this
    analysis, and hold instead that the “good cause” extension only applies when a movant
    has filed their lawsuit within ten days of the statute of limitations.              See Apex
    Geoscience, Inc. v. Arden Texarkana, 
    370 S.W.3d 14
    , 18–20 (Tex. App.—Texarkana
    2012, pet. filed) (concluding that a movant is only entitled to a “good cause” extension
    when it meets the limitations requirement); Pakal Enters., Inc. v. Leska Enters., LLC, 369
    
    7 S.W.3d 224
    (Tex. App.—Houston [1st Dist.] 2011, pet. denied) (same). We decline this
    invitation and choose instead to follow our precedent that allows trial courts to determine,
    in their own discretion, if an extension is warranted.              
    Brown, 305 S.W.3d at 230
    ; see
    also 
    Apex, 370 S.W.3d at 24
    (Carter, J., dissenting) (holding that “the Legislature
    entrusted the trial courts with making prudent decisions on the issue of ‘good
    cause’. . . .”).
    In its order granting the motion for extension of time, the trial court did not specify
    the ground upon which it based its motion to extend time.                    Instead, it just generally
    proclaimed that “Plaintiff Heil Construction Management, Inc.’s time to file its Certificate
    of Merit is extended to March 15, 2013.” Heil offered two grounds to support that it had
    good cause to file a late certificate of merit: that its initial choice of an engineer was not
    qualified to render the certificate of merit;1 and that its attorney had surgery and then
    immediately proceeded to trial, not giving him adequate time to engage an expert to
    provide the certificate.
    BHP argued in the alternative that this case could be easily distinguished from our
    Brown case. They assert that, in Brown, the plaintiffs were unaware of the defendant’s
    status as an engineering firm, whereas here, Heil specifically engaged BHP for its
    engineering services.       They also argue that the plaintiffs in Brown were more prompt in
    1
    In its Motion for Extension of Time, Heil indicated that it wanted to engage a former engineer
    from U.S. Ecology to provide its certificate of merit. However, once this engineer was located, Heil
    determined that he was not qualified to render the certificate. BHP, in its Reply, argued that attempting to
    engage a former U.S. Ecology engineer was inappropriate because the engineer was involved with the
    project and, thus, would not be a “third-party licensed engineer” as required by section 150.002(a). See
    TEX. CIV. PRAC. & REM. CODE ANN. § 150.002(a) (West 2011). We need not address this argument,
    however, as it was never presented to the trial court. See TEX. R. APP. P. 33.1.
    8
    providing a certificate of merit.   However, because our standard of review is an abuse of
    discretion, we defer to the trial court’s decision that either or both of Heil’s proposed
    grounds constituted “good cause” for the certificate of merit to be filed late.      Landreth,
    
    285 S.W. 3d
    at 496; see also WCM Group v. Camponovo, 
    305 S.W.3d 214
    , 220–21
    (Tex. App.—Corpus Christi 2009, pet. dism’d) (discussing “good cause” in the context of
    chapter 150 certificate of merit extensions). We will not conclude that a trial court has
    abused its discretion merely because it decided a matter in a different manner than we
    would have.     
    Landreth, 285 S.W.3d at 496
    . As we held in Brown, “[t]he purpose of the
    [chapter 150] statute is to provide a basis for the trial court to conclude that the plaintiff’s
    claims have merit, not to dismiss meritorious claims on a procedural 
    technicality.” 305 S.W.3d at 230
    .     Here, we defer to the trial court’s decision that Heil’s claims have merit.
    We overrule BHP’s first issue.
    B.     Denial of the Motion to Dismiss
    By its second issue, BHP argues that the trial court abused its discretion in
    denying its motion to dismiss because:       (1) the engineer that wrote Heil’s certificate of
    merit, Jean-Paul Budinger, was not qualified to provide the certificate, and (2) the
    affidavit was conclusory.
    1.     The Licensed Engineer’s Qualifications
    Section 150.002(a)(3) directs us to look at the affiant’s knowledge, skill,
    experience, education, training, and practice to determine if they are qualified to provide
    the certificate of merit.   TEX. CIV. PRAC. & REM. CODE ANN. § 150.002(a)(3)(A)–(F). The
    affiant must hold the same professional license or registration as the defendant and be
    9
    knowledgeable in the same area of practice of the defendant.                    See 
    id. § 150.002(a)(2)–(3).
    Budinger’s curriculum vitae establishes that he has a Bachelor of Architecture
    (Engineering Option) from the University of Illinois-Champaign in Urbana, Illinois. He is
    a “licensed professional engineer” in three states, including Texas, and a “registered
    architect” in nine states, including Texas.   In his thirty years of work experience, he has
    designed multiple structures, including “complex hazardous material storage facilities.”
    Budinger claims he has expertise in “engineering design, failure analysis, construction
    and facilities management and cause and origin of building component failures.”
    BHP contends that Budinger is not qualified to provide a certificate of merit in this
    case because he is a structural engineer and not a chemical engineer. We disagree.
    Chapter 150 “does not state that the affiant's knowledge must relate to the same, much
    less the same specialty, area of practice,” as BHP contends.          Dunham Eng’g, Inc. v.
    Sherwin-Williams Co., 
    404 S.W.3d 785
    , 794 (Tex. App.—Houston [14th Dist.] no pet.).
    “Indeed, section 150.002 ‘imposes no particular requirements or limitations as to how the
    trial court ascertains whether the affiant possesses the requisite knowledge.’”          
    Id. (citing M–E
    Engineers, Inc. v. City of Temple, 
    365 S.W.3d 497
    , 503 (Tex. App.—Austin
    2012, pet. denied)).   Heil’s claims against BHP involve the alleged defective design of
    the Stab Building, which was intended to store and convert hazardous waste products.
    Budinger, a licensed engineer and registered architect in Texas, has experience
    designing hazardous material storage structures.       His expertise also includes failure
    analysis and determining the cause and origin of structure failure.
    10
    Budinger’s “knowledge, skill, experience, education, training, and practice”
    demonstrate that he has knowledge “in the same area of practice of the defendant” in
    this case.   
    Id. We hold
    that the trial court did not abuse its discretion in holding that
    Budinger was qualified to render a certificate of merit.
    2.     The Sufficiency of the Certificate of Merit
    We also disagree with BHP’s assertion that Budinger’s affidavit was conclusory or
    lacked a sufficient basis. BHP complains that Budinger’s assertions generally recited
    the allegations in Heil’s original petition and failed to “state the manner or method in
    which [BHP’s] designs were deficient.”
    Chapter 150 “does not define ‘factual basis,’ but the purpose of the certificate of
    merit ‘is to provide a basis for the trial court to conclude that the plaintiff's claims are not
    frivolous.’” Dunham 
    Eng’g, 404 S.W.3d at 795
    –96.           “The statute does not require the
    plaintiff to marshal all his evidence and does not foreclose the defendant from later
    challenging the sufficiency or admissibility of the plaintiff's evidence.”         
    Id. at 796.
    “Because the core focus of section 150.002(b) is ascertaining and verifying the existence
    of errors or omissions in the professional services provided, it does not ‘require that a
    certificate address operative facts other than the professional errors and omissions that
    are the focus of the statute.’”   
    Id. In his
    affidavit, Budinger stated that BHP was negligent when it failed to provide
    proper engineering and designing of the mix pan dust collection system, overhead
    hoods, and curtains for the Stab Building.     In particular, Budinger claimed that BHP had
    a duty to meet U.S. Ecology and Heil’s design specifications, and that the failure to do so
    11
    proximately damaged Heil. Because we conclude that these statements constitute a
    sufficient “factual basis” for Heil to assert negligence, breach of contract, and breach of
    express warranty claims against BHP, we hold that the trial court did not abuse its
    discretion when it determined that Budinger’s affidavit was sufficient.      The affidavit
    generally set forth the errors or omissions BHP committed “in providing advice,
    judgment, opinion, or a similar professional skill” for each of BHP’s claims.    TEX. CIV.
    PRAC. & REM. CODE ANN. § 150.002(b). We overrule BHP’s second issue.
    IV. CONCLUSION
    Because we overruled both of BHP’s issues, we affirm the trial court’s judgment.
    __________________________
    GINA M. BENAVIDES,
    Justice
    Delivered and filed the
    5th day of December, 2013.
    12
    

Document Info

Docket Number: 13-13-00206-CV

Filed Date: 12/5/2013

Precedential Status: Precedential

Modified Date: 10/16/2015