G. T. Leach Builders, L. L. C. v. Sapphire Vp, Lp , 2013 Tex. App. LEXIS 6456 ( 2013 )


Menu:
  •                             NUMBER 13-11-00793-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    G.T. LEACH BUILDERS,
    L. L.C., ET AL.,                                                         Appellants,
    v.
    SAPPHIRE VP, LP,                                                           Appellee.
    On appeal from the 404th District Court
    of Cameron County, Texas.
    MEMORANDUM OPINION
    Before Chief Justice Valdez and Justices Benavides and Perkes
    Memorandum Opinion by Chief Justice Valdez
    This is an interlocutory appeal challenging the trial court’s denial of appellants’
    motions to compel arbitration. Appellee, Sapphire, V.P., L.P. sued appellants for breach
    of contract and negligence for damage to its condominium complex caused by
    Hurricane Dolly. The appellants include: (1) the architectural firm that designed the
    condominium complex, ZCA Residential, LLC (“ZCA”)1; (2) the general contractor, G.T.
    Leach Builders, LLC (“GTL”); (3) the subcontractors, CHP & Associates, Consulting
    Engineers, Inc. (“CHP”), Comfort Systems USA–South Central f/k/a Atlas Comfort
    Systems USA, LLC (“Atlas”), and Power Design, Inc. (“PDI”); and (4) the insurance
    providers for the condominium complex, Arthur J. Gallagher Risk Management
    Services, Inc., Tracy Williams, and Adams Insurance Services, Inc., (collectively the
    “Insurance Appellants”). We affirm.
    I. BACKGROUND
    In July 2008, during construction of a condominium complex Sapphire owned,
    Hurricane Dolly hit South Padre Island, Texas causing damage to the complex. In
    November 2009, Sapphire filed its original petition in Cameron County against the
    “Insurance Appellants” for negligence and breach of contract seeking $3.5 million for
    water damage and $6 million for “soft costs.”2 Sapphire claimed that the Insurance
    Appellants had failed to procure insurance to adequately compensate Sapphire for any
    damage caused during the construction of the complex. According to Sapphire, the
    builder’s risk policy that would have covered all of the damages, including soft costs,
    was allowed to expire before the hurricane hit, even though the construction of the
    complex had not been completed.3
    1
    ZCA has not filed a brief in this appeal and has indicated that it has settled with Sapphire.
    However, ZCA has also informed this Court that it cannot produce settlement papers due to Sapphire’s
    pending bankruptcy action.
    2
    According to the Insurance Appellants, Sapphire recovered approximately $23 million in
    insurance proceeds due to the damages.
    3
    Williams and Gallagher argue in their brief that it was Gary Leach, the owner and employee of
    GTL, who decided to allow the Builder’s Risk policy to expire and transition to a permanent insurance
    policy eight days before Hurricane Dolly hit the Island on July 23, 2008. According to Williams and
    Gallagher, the Builder’s Risk policy provided coverage for certain soft costs that Sapphire is attempting to
    recover from them. Williams and Gallagher also point out that there is evidence that the Builder’s Risk
    2
    In July 2010, Sapphire filed its original petition against ZCA in Harris County,
    Texas, seeking damages for negligence and breach of contract in designing the
    condominium complex. Sapphire alleged that ZCA’s negligence related to the design of
    the project that led to the water damage, and Sapphire sought $26.3 million in damages
    and $6 million for other expenses, delay costs, and lost sales revenue. ZCA designated
    GTL, CHP, PDI, and Atlas (collectively the “Construction Appellants”) as responsible
    third parties.
    On March 28, 2011, the trial court granted the Insurance Appellants’ motion to
    designate the Construction Appellants as responsible third parties in the Cameron
    County lawsuit. Accordingly, Sapphire amended its Cameron County pleadings on April
    11, 2011 to include the Construction Appellants as defendants. Sapphire alleged that
    the Construction Appellants were negligent in their respective duties because the
    louvers, mechanical/electrical rooms, and other areas in the upper floors of the
    condominium complex were not designed and constructed properly which resulted in
    water entering and damaging the building during the hurricane. Sapphire also sued the
    Construction Appellants for breach of contract claiming that the Construction Appellants
    had “agreed that all of their services would be of the standard and quality that prevails
    among reputable [professionals] engaged in similar practices in the State of Texas on
    projects similar to the Sapphire project” and had failed to do so.
    policy needed to be extended to September 2008 because construction was behind schedule. They also
    point to evidence that Leach allegedly incorrectly informed Sapphire that the Builder’s Risk policy could
    not be extended. According to Williams and Gallagher, the evidence shows that Leach did not extend the
    policy because he believed that it was too expensive. However, these arguments are not relevant to our
    discussion of whether the trial court erred in denying appellants’ motions to compel arbitration.
    3
    In May 2011, all appellants filed motions to transfer venue and then filed motions
    to abate. The trial court denied the appellants’ motions to transfer venue and abate.
    The parties do not challenge the trial court’s rulings on these motions.
    On August 11, 2011, the Construction Appellants filed a joint motion for
    continuance requesting a new trial date of May 7, 2012 and entry of a new docket
    control order subject to their motions to transfer venue in Cameron County.4 On August
    31, 2011, the Cameron County trial court granted the Construction Appellants’ motion
    for continuance and set a trial date of April 2, 2012.
    On October 13, 2011, all of the parties signed an agreed discovery control
    plan/scheduling order, agreeing to deadlines for designation of responsible third parties,
    joinder of new parties, designation of expert witnesses, discovery, dispositive motions
    and pleas, summary judgment motions, alternative dispute resolution, and amendments
    to pleadings.        The parties also agreed to a pretrial conference or docket call on
    February 15, 2012 and to the previously set trial date of April 2, 2012.
    On November 3, 2011, Adams filed a motion for summary judgment on the basis
    that Sapphire could not show that there was privity of contract with Adams because its
    contract for insurance was with GTL; therefore, Adams argued it owed no duty to an
    additional insured, such as Sapphire.                  Adams further argued that the evidence
    conclusively established that it did not enter into an oral or written contract with
    Sapphire to procure insurance for the project. The trial court granted the summary
    4
    The trial court had previously set a trial date of November 7, 2011.
    4
    judgment in favor of Adams with regards to Sapphire’s claim for breach of contract but
    denied it with regards to Sapphire’s negligence claim.5
    GTL then served Sapphire with a written demand to arbitrate the issues raised in
    the lawsuit and filed its motion to compel arbitration and to stay the litigation pursuant to
    the Texas Arbitration Act (the “TAA”) in Cameron County. GTL relied on a provision in
    its contract with Sapphire (the “General Contract”) it claimed required arbitration of
    Sapphire’s claims. All other appellants filed similar motions to compel arbitration and/or
    join GTL’s motion to compel arbitration.
    Sapphire challenged the motions to compel arbitration on two grounds: (1) only
    GTL had a contractual arbitration provision, so the other defendants had no right to
    compel arbitration; and (2) GTL’s conduct of agreeing by Rule 11 to go to trial, together
    with the totality of the conduct of all of the parties in the case, constituted waiver of
    GTL’s right to compel arbitration. Sapphire argued that it did not have a written contract
    with any of the appellants, except for GTL, and that its contract with GTL “specifically
    provide[d] that there are no third party beneficiaries and that non-signatories to the
    contract [could not] claim any rights under its terms, including the right to arbitrate.”
    Sapphire also argued that GTL could not demand arbitration because a clause in the
    General Contract prohibited the parties from demanding arbitration after the statute of
    limitations had expired.6 After a hearing on December 7, 2011, the trial court denied the
    appellants’ motions to compel arbitration. The trial court did not state its basis for
    denying arbitration. This interlocutory appeal followed.
    5
    Gallagher filed motions for summary judgment on no evidence and traditional grounds, which
    the trial court denied. These motions were filed prior to joinder of the Construction Appellants.
    6
    The parties do not dispute that the applicable statute of limitations had expired when GTL
    sought arbitration.
    5
    II. STANDARD OF REVIEW
    We apply an abuse of discretion standard to the trial court’s denial of appellants’
    motions to compel arbitration. Okorafor v. Uncle Sam & Assocs., Inc., 
    295 S.W.3d 27
    ,
    38 (Tex. App.—Houston [1st Dist.] 2009, pet. denied). A trial court abuses its discretion
    when it acts arbitrarily or unreasonably and without reference to any guiding rules or
    principles. 
    Id. When the
    trial court’s ruling under review depends on the resolution of underlying
    facts, we must defer to the trial court on its resolution of those facts and any credibility
    determinations that may have affected those resolutions. 
    Id. Furthermore, we
    may not
    substitute our judgment for the trial court on those matters. 
    Id. However, we
    must
    apply a de novo standard of review to the trial court’s legal conclusions because a trial
    court has no discretion in determining what the law is, which law governs, or how to
    apply the law. 
    Id. III. APPLICABLE
    LAW
    Whether a valid arbitration agreement exists is a question of law and is therefore
    reviewed de novo. In re C & H News Co., 
    133 S.W.3d 642
    , 645 (Tex. App.—Corpus
    Christi 2003, orig. proceeding); Tenet Healthcare Ltd. v. Cooper, 
    960 S.W.2d 386
    , 388
    (Tex. App.—Houston [14th Dist.] 1998, pet. dism’d w.o.j.). The party seeking arbitration
    has the initial burden to prove, and the trial court must initially decide whether there is a
    valid arbitration agreement and if so, whether the claims fall within the scope of the
    arbitration agreement. In re Kellogg Brown & Root, 
    80 S.W.3d 611
    , 615 (Tex. App.—
    Houston [1st Dist.] 2002, orig. proceeding); Mohamed v. Auto Nation USA Corp., 
    89 S.W.3d 830
    , 836 (Tex. App.—Houston [1st Dist.] 2002, no pet.) (combined appeal &
    6
    orig. proceeding) (“The burden of showing one’s status as a party or one’s right to
    enforce, as with the overall burden of establishing the arbitration agreement’s existence,
    is generally evidentiary.”); In re Koch Indus., Inc., 
    49 S.W.3d 439
    , 444 (Tex. App.—San
    Antonio 2001, orig. proceeding) (“The party seeking arbitration has the initial burden to
    present evidence of an arbitration agreement.”). The initial burden of establishing the
    existence of a valid arbitration agreement includes proving that the entity seeking to
    enforce the arbitration agreement was a party to it or had the right to enforce the
    agreement notwithstanding. 
    Mohamed, 89 S.W.3d at 836
    (citing Pepe Int’l Dev. Co. v.
    Pub Brewing Co., 
    915 S.W.2d 925
    , 931 (Tex. App.—Houston [1st Dist.] 1996, no writ)
    (combined appeal & orig. proceeding); Tex. Private Employment Ass’n v. Lyn-Jay Int’l,
    Inc., 
    888 S.W.2d 529
    , 531, 532 (Tex. App.—Houston [1st Dist.] 1994, no writ) (op. & op.
    on reh’g) (holding association itself was not party to arbitration agreement, set out in
    association’s by-laws, that required association’s members to arbitrate disputes among
    themselves)). If a valid arbitration agreement exists, the burden then shifts to the party
    resisting arbitration to show that the party seeking arbitration has waived its right to
    compel arbitration. Williams Indus., Inc. v. Earth Dev. Sys. Corp., 
    110 S.W.3d 131
    , 137
    (Tex. App.—Houston [1st Dist.] 2003, no pet.) (citing 
    Mohamed, 89 S.W.3d at 835
    ).
    There is a strong presumption favoring arbitration; however that presumption
    does not apply to the initial determination of whether a valid arbitration agreement
    exists. J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 227 (Tex. 2003). Arbitration
    agreements are interpreted under traditional contract principles. 
    Id. An obligation
    to arbitrate not only attaches to one who has personally signed the
    written arbitration agreement but may also bind a non-signatory under principles of
    7
    contract law and agency. 
    Id. at 738.
    Generally, however, parties must sign arbitration
    agreements before being bound by them. In re Rubiola, 
    334 S.W.3d 220
    , 223 (Tex.
    2011) (orig. proceeding); see Grigson v. Creative Artists Agency, L.L.C., 
    210 F.3d 524
    ,
    528 (5th Cir. 2000) (noting that “arbitration is a matter of contract and cannot, in
    general, be required for a matter involving an arbitration agreement non-signatory”).
    III. GTL
    By their first issue, appellants argue that the trial court erred in denying their
    motions to compel arbitration because there was a valid arbitration agreement in the
    General Contract. Sapphire acknowledges that it had a valid arbitration agreement with
    GTL in the General Contract; however, it argues that GTL has waived its right to compel
    arbitration for several reasons.
    A. Arbitration Agreement
    Pursuant to section 4.6.1 of the General Contract, Sapphire and GTL agreed that
    “[a]ny Claim arising [o]ut of or related to the [General Contract] . . . shall . . . be subject
    to agreed private arbitration.”     It is undisputed and we agree that this is a valid
    arbitration agreement and that Sapphire’s claims against GTL fall within the scope of
    this agreement.    Therefore, the trial court could have only denied GTL’s motion to
    compel arbitration on another basis.
    Although we have concluded that GTL had a valid arbitration agreement with
    Sapphire, and the claims at issue were within the scope of the arbitration agreement,
    we may not yet sustain its sole issue because we have not yet considered Sapphire’s
    defenses to the arbitration agreement. See J.M. Davidson, 
    Inc., 128 S.W.3d at 227
    (stating that if the trial court finds a valid agreement, the burden shifts to the party
    8
    opposing arbitration to raise an affirmative defense to enforcing arbitration); In re H.E.
    Butt Grocery Co., 
    17 S.W.3d 360
    , 367 (Tex. App.—Houston [14th Dist.] 2000, orig.
    proceeding); City of Alamo v. Garcia, 
    878 S.W.2d 664
    , 665 (Tex. App.—Corpus Christi
    1994, no writ).       Accordingly, we will discuss whether any of Sapphire’s defenses
    applied. See In re C & H News 
    Co., 133 S.W.3d at 645
    (providing that once the trial
    court determines that a valid arbitration agreement exists and the claims fall within the
    agreement’s scope, the party opposing arbitration has the burden of presenting
    evidence that prevents enforcement of the arbitration agreement).
    B. Running of the Statute of Limitations
    Sapphire asserts that the trial court may have denied GTL’s motion to compel
    arbitration because section 4.6.4 of the General Contract prohibited the parties from
    seeking arbitration if the statute of limitations for the claims made had expired.
    Sapphire states that in this case, the statute of limitations had expired when GTL filed
    its motion to compel arbitration. GTL does not contest that the statute of limitations for
    Sapphire’s claims had expired when it filed its motion to compel arbitration.                         GTL
    instead contends that the parties did not intend for the statute of limitations to bar its
    demand for arbitration.7
    Section 4.6.4 of the General Contract states:
    A demand for arbitration shall be made within the time limits specified in
    Section 4.4.6 and 4.6.1 as applicable, and in other cases within a
    reasonable time after the Claim has arisen, and in no event shall it be
    made after the date when institution of legal or equitable proceedings
    7
    GTL also claims that Sapphire has waived this argument by not making it in the trial court. In its
    response to all of the motions to compel arbitration, Sapphire did make its statute of limitations argument.
    Therefore, Sapphire has not waived this argument, and the trial court may have determined that GTL
    waived arbitration based on section 4.6.4.
    9
    based on such Claim would be barred by the applicable statute of
    limitations as determined pursuant to Section 13.7.
    Section 4.4.6 had been crossed out by the parties. Section 4.6.1 states that any claims
    made pursuant to the General Contract shall be subject to arbitration after
    recommendation by the architect or 30 days after submission of the Claim to the
    architect (emphasis added).
    Section 13.7 is entitled, “Commencement of Statutory Limitation Period.” Section
    13.7.1 set out three possible scenarios—before substantial completion, between
    substantial completion and final certificate for payment, and after final certificate for
    payment—and the date the statute of limitations begins to run in those scenarios. Thus,
    we agree with Sapphire that section 13.7 provided a method of determining the
    commencement of the limitations periods, depending on when the Contractor’s act or
    omission occurred during the building of the condominiums.
    However, as Sapphire points out, section 13.7 was crossed out and thus deleted
    from the General Contract. Section 13.7 was not replaced. GTL argues that because
    of this deletion, the contract no longer prohibits arbitration of claims when the statute of
    limitations has expired.    Sapphire responds that the parties’ intent to prohibit the
    compulsion of arbitration after the statute of limitations had run is evident because they
    did not delete section 4.6.4 of the contract. Moreover, Sapphire notes that none of the
    parties dispute that Sapphire’s negligence claim accrued when Hurricane Dolly hit the
    Island in July 2008 or that the statute of limitations had run when appellants filed their
    motions to compel arbitration.
    It appears from our reading of section 4.6.4 that the parties did not want to allow
    a demand for arbitration to occur outside the applicable statute of limitations period.
    10
    Although the parties deleted section 13.7, the parties did not delete section 4.6.4, and it
    must be given some meaning.         See J.M. Davidson, 
    Inc., 128 S.W.3d at 229
    (“In
    construing a written contract, the primary concern of the court is to ascertain the true
    intentions of the parties as expressed in the instrument. To achieve this objective, we
    must examine and consider the entire writing in an effort to harmonize and give effect to
    all the provisions of the contract so that none will be rendered meaningless.”).
    Therefore, because the parties deleted section 13.7, it is clear the reference in section
    4.6.4 to that section no longer applies. See Frost Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 311–12 (Tex. 2005) (“In construing a contract, we must ascertain and give
    effect to the parties’ intentions as expressed in the document[,]” and “[w]e consider the
    entire writing and attempt to harmonize and give effect to all the provisions of the
    contract by analyzing the provisions with reference to the whole agreement.”); In re
    Bayer Materialscience, L.L.C., 
    265 S.W.3d 452
    , 454–56 (Tex. App.—Houston [1st Dist.]
    2007) (orig. proceeding) (“Arbitration is a creature of contract, and parties seeking to
    compel arbitration must rely upon an agreement to arbitrate. If such an agreement
    exists, then the law favors enforcing it. But the law favoring arbitration does not go so
    far as to create an obligation to arbitrate where none exists.           Thus, arbitration
    agreements are ‘as enforceable as other contracts, but not more so.’”) (internal citations
    omitted).
    Thus, harmonizing and giving effect to all of the provisions of the General
    Contract, we interpret section 4.6.4 to say, “in no event shall [a demand for arbitration]
    be made after the date when institution of legal or equitable proceedings based on such
    Claim would be barred by the applicable statute of limitations.” Therefore, we conclude
    11
    that pursuant to section 4.6.4 of the General Contract, any party wishing to compel
    arbitration must have done so before the statute of limitations expired. Here, the parties
    do not dispute that when GTL filed its motion to compel arbitration, the statute of
    limitations had expired.
    In the alternative, GTL states that pursuant to former section 33.004 of the Texas
    Practice and Remedies Code, Sapphire filed suit against it after the statutory limitations
    period had expired; therefore, it was impossible for GTL to have filed its motion to
    compel arbitration before the statute of limitations had run. Former section 33.004 of
    the civil practice and remedies code allowed a plaintiff to join a designated responsible
    third party, “even though joinder would otherwise be barred by limitations.”8 In this
    case, the Insurance Appellants designated GTL as a responsible third-party, and in
    response, Sapphire, pursuant to section 33.004, amended its pleadings and joined GTL
    as a defendant after the statute of limitation had expired.
    There is nothing in the General Contract showing that when the parties signed it
    they contemplated allowing an exception to section 4.6.4 on the basis that a party has
    been joined in a suit after the statute of limitations had expired. If the parties had so
    intended, they would have included a provision in the General Contract making such an
    exception. J.M. Davidson, 
    Inc., 128 S.W.3d at 227
    . GTL responds that the intent of the
    parties was to allow for a reasonable time to demand arbitration, which is shown by the
    parties’ deletion of section 13.7 of the General Contract. Therefore, GTL argues the
    demand for arbitration was not dependent on any statute of limitations periods.
    8
    This section was repealed by the legislature and the legislature has restricted a defendants’
    future ability to designate responsible third parties after the applicable statute of limitations period has
    run.
    12
    However, GTL cites nothing in the General Contract, and we find nothing supporting
    such an interpretation of the General Contract.9 Accordingly, GTL was not excused
    from demanding arbitration before the applicable statute of limitations expired. We
    conclude that the trial court did not abuse its discretion by denying GTL’s motion to
    compel arbitration. We overrule GTL’s sole issue on appeal.
    IV. THE NON-SIGNATORY APPELLANTS
    By their first, second, and third issues, CHP, Atlas, PDI, and the Insurance
    Appellants (collectively the “Non-Signatory Appellants”) argue that they can compel
    arbitration based on a variety of theories as set out below.10 Sapphire responds that no
    appellant other than GTL can claim a right to compel arbitration pursuant to the General
    Contract and there is no other basis for the Non-Signatory Appellants to compel
    arbitration.
    A. Right to Compel Arbitration under the General Contract
    By their first issue, CHP, PDI, and the Insurance Appellants first argue that
    although they are non-signatories to the General Contract, they are entitled to compel
    arbitration because section 4.6.1 states:
    Any Claim arising [out] of or related to the Contract, except those waived
    as provided for in Section 4.3.10, 9.10.5, shall, after recommendation by
    the Architect or 30 days after submission of the Claim to the Architect, be
    9
    We recognize that the parties entered into a valid arbitration agreement pursuant to section
    4.6.6; however, parties to a contract are free to determine the terms that they are bound by and our only
    duty is to ascertain and give effect to the parties’ intent as expressed by the document. J.M. Davidson,
    Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003). As stated above, we construe section 4.6.4 as limiting
    the parties’ ability to demand arbitration once the applicable statute of limitations has expired. Moreover,
    there is nothing in the contract itself indicating that the parties’ intended for there to be any exceptions
    including that the parties be allowed a reasonable time after the claim has arisen to seek arbitration. See
    Altman v. Blake, 
    712 S.W.2d 117
    , 118 (Tex. 1986) (providing that we must determine the parties'
    intentions as expressed within the four corners of the instrument).
    10
    We have renumbered the Non-Signatory Appellants’ issues for purposes of this appeal.
    13
    subject to agreed private arbitration. Prior to arbitration, the parties shall
    endeavor to resolve disputes by the process provided for in Section 4.5.
    CHP argues that the work it performed as a subcontractor arises out of and relates to
    Sapphire’s contract with GTL. PDI also asserts that once Sapphire conceded that there
    was a valid arbitration agreement with GTL, the burden shifted to Sapphire to show that
    it waived arbitration. However, section 1.1.2 of the General Contract contradicts such a
    conclusion. It states:
    The [General] Contract Documents form the Contract for Construction.
    The [General] Contract represents the entire and integrated agreement
    between [Sapphire and GTL] and supersedes prior negotiations,
    representations or agreements, either written or oral. The [General]
    Contract may be amended or modified only by a Modification. The
    [General] Contract shall not be construed to create a contractual
    relationship of any kind (1) between the Architect and [GTL], (2) between
    [Sapphire] and a Subcontractor or Sub-subcontractor, (3) between
    [Sapphire] and Architect or (4) between any persons or entities other than
    [Sapphire and GTL]. The Architect shall be entitled to performance and
    enforcement of obligations under the [General] Contract intended to
    facilitate performance of the Architect’s duties.
    (Emphasis added). This language clearly indicates that GTL and Sapphire agreed that
    the General Contract could not be construed as providing any contractual relationship
    between Sapphire and the subcontractors, such as Atlas, PDI, and CHP. Furthermore,
    this language also clearly indicates that the General Contract was not to be construed
    as creating a contractual relationship between any other parties other than GTL and
    Sapphire. Therefore, we disagree with appellants that Sapphire agreed to entitle non-
    signatories to the General Contract the right to compel arbitration.
    Moreover, as non-signatories to the General Contract, the Non-Signatory
    Appellants had the initial burden of showing that each of them had a valid arbitration
    agreement with Sapphire, and they could not prevail merely by showing that a valid
    14
    arbitration agreement existed between GTL and Sapphire. See 
    Mohamed, 89 S.W.3d at 836
    ; see also TEX. CIV. PRAC. & REM. CODE ANN. § 171.001 (setting out that a written
    agreement to arbitrate is valid and enforceable if the agreement is to arbitrate a
    controversy that arises between the parties to the agreement).        As such, the Non-
    Signatory Appellants had to show that an accepted theory applies to this case allowing
    them to enforce the arbitration agreement in the General Contract. See Cappadonna
    Elec. Mgmt. v. Cameron County, 
    180 S.W.3d 364
    , 371 (Tex. App.—Corpus Christi
    2005, no pet.). Therefore, to the extent that the Non-Signatory Appellants’ argument
    relies on a theory that they could compel Sapphire to go to arbitration merely because
    Sapphire had a valid arbitration agreement with GTL, we conclude that argument is
    without merit.
    The Insurance Appellants and CHP also argue that section 4.6.6 of the General
    Contract requires joinder of the Non-Signatory Appellants in the arbitration proceeding.
    Section 4.6.6 of the General Contract states:
    Limitation on Consolidation or Joinder. NoAn arbitration arising or out of
    or relating to the Contract shall may include, by consolidation or joinder or
    in any other manner, the Architect, the Architect’s employees or
    consultants, except by written consent containing specific reference to the
    Agreement and signed by the Architect, Owner, Contractor and any other
    person or entity sought to be joined. No consultants. Any arbitration shall
    may include, by consolidation or joinder or in any other manner, parties
    other than the Owner, Contractor Contractor, a Subcontractor, a separate
    contractor as described in Article 6 and other persons substantially
    involved in a common question of fact or law whose presence is required
    of complete relief is to be accorded in arbitration. No person or entity
    other than the Owner, Contractor, or Subcontractor, or a separate
    contractor as described in Article 6 shall be included as an original third
    party or additional third party to an arbitration whose interest or
    responsibility is insubstantial.    Consent to arbitration involving an
    additional person or entity shall not constitute consent to arbitration of a
    Claim not described therein or with a person or entity not named or
    described therein. The foregoing agreement to arbitrate and other
    15
    agreements to arbitrate with an additional person or entity duly consented
    by parties to the Agreement shall be specifically enforceable under
    applicable law in any court having jurisdiction thereof.
    (Emphasis and deletions in orginal).
    We disagree that section 4.6.6 requires joinder of non-signatory third-parties.
    This section of the General Contract merely allows for the consolidation or the joinder of
    third-parties in the arbitration proceeding. It does not give non-signatories a right to
    compel arbitration.   Accordingly, the trial court properly concluded that the Non-
    Signatory Appellants could not compel arbitration based on section 4.6.6 of the General
    Contract. We overrule appellants’ first issue to the extent they argue that the General
    Contract gave non-signatories a right to compel Sapphire to go to arbitration.
    B. Incorporation by Reference
    Next, by their second issue, PDI and Atlas claim that their subcontracts were
    incorporated into the General Contract. PDI and Atlas further argue that the General
    Contract incorporated their subcontracts.
    “Under the doctrine of incorporation by reference, where one contract refers to
    another contract or instrument, the second document may properly constitute part of the
    original contract.” Cappadonna Elec. 
    Mgmt., 180 S.W.3d at 371
    (citing City of Port
    Isabel v. Shiba, 
    976 S.W.2d 856
    , 858 (Tex. App.—Corpus Christi 1998, pet. denied)).
    Questions of contract interpretation are often raised in relation to disputes concerning
    the doctrine of incorporation by reference. 
    Id. The primary
    concern of the appellate
    court in construing the subcontractors’ rights and duties under their subcontracts is to
    ascertain and give effect to the intentions of the parties as expressed in the subcontract.
    See Kelley-Coppedge, Inc. v. Highlands Ins. Co., 
    980 S.W.2d 462
    , 464 (Tex. 1998).
    16
    “To ascertain the true intentions of the parties to the subcontract, we examine the entire
    agreement in an effort to harmonize and give effect to all of the provisions of the
    contract so that none will be rendered meaningless.” Cappadonna Elec. 
    Mgmt., 180 S.W.3d at 371
    .
    First, Atlas claims that the general terms of the General Contract, specifically
    section 5.3.1, provides that each subcontractor is bound by the contract. 5.3.1 states:
    By appropriate agreement, written where legally required for validity, the
    Contractor shall require each Subcontractor, to the extent of the Work to
    be performed by the Subcontractor, to be bound to the Contractor by
    terms of the Contract Documents, and to assume toward the Contractor all
    the obligations and responsibilities, including the responsibility for the
    safety of the Subcontractor’s Work, which the Contractor, by these
    Documents, assumes toward the Owner and Architect. Each subcontract
    agreement shall preserve and protect the rights of the Owner and
    Architect under the Contract Documents with respect to the Work to be
    performed by the Subcontractor so that subcontracting thereof will not
    prejudice such rights, and shall allow to the Subcontractor, unless
    specifically provided otherwise in the subcontract agreement, the benefit
    of all rights, remedies, and redress against the Contractor that the
    Contractor, by the Contract Documents, has against the
    Owner . . . The Contractor shall make available to each proposed
    Subcontractor, prior to the execution of the Subcontract agreement,
    copies of the Contract Documents to which the Subcontractor will be
    bound. . . .
    (Emphasis added).
    We disagree with Atlas’s interpretation of this clause. This clause relates to
    GTL’s relationship with the subcontractors and requires that the subcontractors assume
    the “obligations and responsibilities, including the responsibility for the safety of the
    Subcontractor’s Work” that GTL is bound to provide under the General Contract to
    Sapphire. This clause imposes a requirement that each subcontract will preserve and
    protect the rights of Sapphire and the architect under the General Contract. This clause
    shows that the intent of Sapphire and GTL was to ensure that Sapphire’s rights will not
    17
    be prejudiced under the subcontracts. The clause also gives the subcontractors the
    benefit of all rights, remedies, and redress against GTL that GTL had against Sapphire
    under the General Contract. (Emphasis added). It does not, however, provide that the
    subcontractors have the benefits of all rights, remedies, and redress against Sapphire
    that GTL has under the General Contract. (Emphasis added). Moreover, this clause
    does not mention arbitration and there is nothing in it showing Sapphire’s intent was to
    agree to arbitrate its claims against the subcontractors. We conclude that section 5.3.1
    of the General Contract does not bind Sapphire to arbitration with the subcontractors.
    Next, Atlas argues that the General Contract incorporated by reference its
    subcontract and the subcontract has a valid arbitration clause; therefore, it has a right to
    compel arbitration with Sapphire. According to Atlas, incorporation of a subcontract into
    the prime contract is the industry norm. Atlas points to section 11.2 of its subcontract
    with GTL, which states:
    Should GTL enter into arbitration with [Sapphire] or others regarding
    matters relating to this Subcontract, Subcontractor will agree, if requested
    by GTL to consolidation of this arbitration with GTL’s arbitration with
    [Sapphire], but in any event, Subcontractor shall be bound by the result of
    the arbitration with [Sapphire] to the same degree as GTL.
    This provision provides that Atlas must agree to consolidation of arbitration if requested
    by GTL in the event that GTL enters arbitration with Sapphire and that Atlas is bound by
    the results of any arbitration between GTL and Sapphire. However, there is nothing in
    this clause that binds Sapphire to arbitration with the subcontractors.          So, even
    assuming without deciding that the General Contract incorporated the subcontract,
    section 11.2 does not show that Sapphire’s intent was to arbitrate its claims against the
    subcontractors.
    18
    Finally, Atlas argues that the intent of Sapphire and GTL was to incorporate the
    General Contract into its subcontract with GTL.        Therefore, Atlas claims that the
    subcontractors were bound by section 4.6.1 of the General Contract requiring arbitration
    of any claim arising out of or related to the contract. However, section 12.13 of Atlas’s
    subcontract with GTL states: “Notwithstanding any provision to the contrary contained
    in the Contract Documents, Subcontractor expressly agrees that this Subcontract does
    not contain a provision for the mandatory arbitration of disputes, nor does it incorporate
    by reference such provision if such is contained in the [General Contract].” This clause
    in the subcontract expressly rejects incorporation of the arbitration clause of the General
    Contract. It further provides that the parties have not agreed to mandatory arbitration in
    the subcontract; thus foreclosing any of Atlas’s arguments that a valid arbitration
    agreement existed between it and GTL. Thus, even assuming that the subcontract was
    incorporated into the General Contract or vice versa, this clause negates the
    incorporation of any arbitration provisions in the Contract Documents and states that the
    subcontractor has expressly agreed that there are no provisions in the subcontract
    requiring mandatory arbitration of disputes.
    PDI also argues its subcontract with GTL required the parties to arbitrate any
    disputes. However, PDI does not explain how the General Contract incorporated the
    subcontract. See TEX. R. APP. P. 38.1(i). Accordingly, we are unable to conclude that
    under the doctrine of incorporation by reference, PDI can compel Sapphire to
    arbitration.
    We conclude that Sapphire was not bound to arbitration with Atlas and PDI
    based on the theory of incorporation by reference. Thus, the trial court properly rejected
    19
    that theory as a ground for allowing the Non-Signatory Appellants to compel arbitration.
    We overrule appellants’ second issue.
    C. Equitable Estoppel
    By their third issue, Williams and Gallagher also argue that their motion to
    compel arbitration should be granted because the doctrine of equitable estoppel allows
    “a non-signatory-to-an-arbitration-agreement-defendant [to] compel arbitration against a
    signatory-plaintiff.” Williams and Gallagher rely on the arbitration clause contained in
    the General Contract. Williams and Gallagher cite a case from United States Court of
    Appeals for the Fifth Circuit, Grigson v. Creative Artists Agency, quoted by the Texas
    Supreme Court in Meyer v. WMCO-GP LLC, explaining, that “the claimant cannot ‘have
    it both ways’: it cannot, on the one hand, seek to hold the non-signatory liable pursuant
    to duties imposed by the agreement, which contains an arbitration provision, but, on the
    other hand, deny arbitration’s applicability because the defendant is a non-signatory.”
    
    211 S.W.3d 302
    , 306 (citing 
    Grigson, 210 F.3d at 528
    ).
    Equitable estoppel allows a non-signatory to compel arbitration if the nature of
    the underlying claims requires the signatory to rely on the terms of the written
    agreement containing the arbitration provision in asserting its claims against the non-
    signatory. In re Hartigan, 
    107 S.W.3d 684
    , 691 (Tex. App.—San Antonio 2003, orig.
    proceeding [mand. denied]). In Neatherlin Homes, Inc. v. Love, we stated that “[u]nder
    certain circumstances, a party to an arbitration agreement may be compelled to
    arbitrate claims with a nonparty if the controversy arises from a contract containing an
    arbitration clause.” Neatherlin Homes, Inc. v. Love, Nos. 13-06-328-CV & 13-06-411-
    CV, 2007 Tex. App. LEXIS 1788, at *27 (Tex. App.—Corpus Christi Mar. 8, 2007, orig.
    20
    proceeding) (mem. op) (citing Meyer v. WMCO-GP LLC, 
    211 S.W.3d 302
    , 306–07 (Tex.
    2006); In re Palm Harbor Homes, 
    Inc., 195 S.W.3d at 678
    ; see In re Vesta Ins. Group,
    Inc., 
    192 S.W.3d 759
    , 760 (Tex. 2006) (per curiam); In re Weekley Homes, L.P., 
    180 S.W.3d 127
    , 130 (Tex. 2005); In re Kellogg Brown & Root, 
    Inc., 166 S.W.3d at 738
    –39;
    see also Merrill Lynch Trust Co. 
    FSB, 159 S.W.3d at 168
    (“A party that is not a
    signatory to an arbitration agreement may enforce it if the party falls into a recognized
    exception     under    general     equitable     or   contract    law that      would     allow such
    enforcement.”)).      We cited Meyer v. WMCO-GP LLC, which states, “sometimes a
    person who is not a party to the agreement can compel arbitration with one who is, and
    vice versa. We have held that a person who seeks by his claim ‘to derive a direct
    benefit from the contract containing the arbitration provision’ may be equitably estopped
    from refusing 
    arbitration.” 211 S.W.3d at 305
    .
    Sapphire’s claims against the Insurance Appellants are clearly not based on the
    General Contract.       In the General Contract, GTL agreed to build the condominium
    complex.     Sapphire does not contend that the Insurance Appellants breached the
    General Contract by not properly constructing the complex. Instead, Sapphire claims
    that the Insurance Appellants failed to procure the appropriate type of insurance. 11 This
    claim is not related to the construction of the complex. Accordingly, we overrule the
    Insurance Appellants’ third issue to the extent that they argue that the theory of
    equitable estoppel applies in this case.
    11
    Sapphire claimed in its petition that the Insurance Appellants had contracted with Sapphire to
    procure adequate insurance to protect Sapphire while the Sapphire condominiums were being built and
    that the Insurance Appellants breached that agreement. Sapphire does not claim that the Insurance
    Appellants breached the General Contract in any way.
    21
    By its third issue, Atlas also relies on the theory of equitable estoppel. Atlas
    argues that Sapphire is seeking the benefits of the subcontract and relying on it
    expressly; therefore, Sapphire cannot deny the applicability of the arbitration agreement
    contained in the subcontract. The subcontract on which Atlas relies is between GTL
    and Atlas.
    The flaw in this argument is that the subcontract does not contain a valid
    arbitration agreement. We acknowledge that section 11.1 of the subcontract states, “All
    claims, disputes and other matters in question arising out of, or relating to, this
    Subcontract or the breach thereof shall be decided in arbitration in accordance with the
    Construction Industry Arbitration Rules of the American Arbitration Association unless
    the parties mutually agree otherwise.” However, as stated above, section 12.13 of
    Atlas’s subcontract with GTL also states: “Notwithstanding any provision to the contrary
    contained in the Contract Documents, Subcontractor expressly agrees that this
    Subcontract does not contain a provision for the mandatory arbitration of disputes, nor
    does it incorporate by reference such provision if such is contained in the [General
    Contract].” (Emphasis added). Atlas does not explain how the language contained in
    section 12.13 does not apply; thus, nullifying section 11.1’s arbitration clause. See TEX.
    R. APP. P. 38.1(i). Therefore, we are unable to conclude that the trial court should have
    determined that the subcontract between Atlas and GTL contained a valid arbitration
    agreement.12 We overrule appellants’ third issue.
    12
    We note that the subcontract between GTL and PDI contained the exact same provisions.
    Thus, to the extent PDI intended to make a similar argument, we conclude it is without merit.
    22
    V. CONCLUSION
    We conclude that the trial court did not abuse its discretion when it denied the
    appellants’ motions to compel arbitration. Therefore, we affirm the trial court’s denial of
    appellants’ motions to compel arbitration.
    ____________________
    ROGELIO VALDEZ
    Chief Justice
    Delivered and filed the
    23rd day of May, 2013.
    23
    

Document Info

Docket Number: 13-11-00793-CV

Citation Numbers: 456 S.W.3d 570, 2013 Tex. App. LEXIS 6456, 2013 WL 2298447

Judges: Benavides, Perkes, Valdez

Filed Date: 5/23/2013

Precedential Status: Precedential

Modified Date: 11/14/2024

Authorities (20)

City of Port Isabel v. Shiba , 976 S.W.2d 856 ( 1998 )

City of Alamo v. Garcia , 1994 Tex. App. LEXIS 1384 ( 1994 )

In Re Hartigan , 107 S.W.3d 684 ( 2003 )

In Re Koch Industries, Inc. , 2001 Tex. App. LEXIS 2477 ( 2001 )

Pepe International Development Co. v. Pub Brewing Co. , 1996 Tex. App. LEXIS 351 ( 1996 )

Grigson v. Creative Artists Agency, L.L.C. , 210 F.3d 524 ( 2000 )

Tenet Healthcare Ltd. v. Cooper , 1998 Tex. App. LEXIS 236 ( 1998 )

Mohamed v. Auto Nation USA Corp. , 2002 Tex. App. LEXIS 7829 ( 2002 )

In Re H.E. Butt Grocery Co. , 2000 Tex. App. LEXIS 2754 ( 2000 )

Williams Industries, Inc. v. Earth Development Systems Corp. , 110 S.W.3d 131 ( 2003 )

Okorafor v. UNCLE SAM & ASSOCIATES, INC. , 295 S.W.3d 27 ( 2009 )

In Re Weekley Homes, L.P. , 49 Tex. Sup. Ct. J. 55 ( 2005 )

In Re C H News Company , 2003 Tex. App. LEXIS 393 ( 2003 )

In Re Kellogg Brown & Root , 80 S.W.3d 611 ( 2002 )

Frost National Bank v. L & F Distributors, Ltd. , 48 Tex. Sup. Ct. J. 803 ( 2005 )

In Re Rubiola , 54 Tex. Sup. Ct. J. 654 ( 2011 )

In Re Vesta Insurance Group, Inc. , 192 S.W.3d 759 ( 2006 )

Cappadonna Electrical Management v. Cameron County , 2005 Tex. App. LEXIS 10049 ( 2005 )

In Re Bayer Materialscience, LLC , 2007 Tex. App. LEXIS 8760 ( 2007 )

Altman v. Blake , 29 Tex. Sup. Ct. J. 457 ( 1986 )

View All Authorities »