Larry T. Long v. RIM Operating, Inc. ( 2011 )


Menu:
  • Opinion filed April 14, 2011
    In The
    Eleventh Court of Appeals
    __________
    No. 11-09-00328-CV
    __________
    LARRY T. LONG, Appellant
    V.
    RIM OPERATING, INC., Appellee
    On Appeal from the 106th District Court
    Dawson County, Texas
    Trial Court Cause No. 08-06-17940
    OPINION
    This is a dispute over the ownership of a working interest in a 160-acre tract of land in
    Dawson County. RIM Operating, Inc. filed suit against Larry T. Long seeking a declaratory
    judgment that Long relinquished his interest to other working interest owners when he did not
    consent to a workover operation. The trial court granted summary judgment for RIM and
    awarded it attorney‘s fees. We reverse the attorney‘s fee award and remand for a factual
    determination but otherwise affirm the trial court‘s judgment.
    I. Background Facts
    The 160-acre tract for which this dispute concerns was leased with ten leases (Lindsey
    Leases). The properties covered by the Lindsey Leases are not uniform, but all include the
    eastern portion of Section 109.1 In January 1995, the working interest owners executed an
    1
    Specifically, Section 109, Block M, E.L. & R.R. Ry. Co. Survey, Dawson County, Texas.
    A.A.P.L. Form 610-1982 Model Form Operating Agreement (JOA) that covered all of Section
    109.    In 1997, the Lindsey Trust 109-A No. 1 Well (Lindsey Well) was drilled in the
    southeastern corner of Section 109. The Lindsey Leases provide that a well maintains the lease
    only as to the proration unit designated by the Railroad Commission. In 1998, the operator filed
    an affidavit in the real property records of Dawson County designating a 160-acre proration unit
    surrounding the Lindsey Well.2 A survey showing the unit and well location was attached to the
    affidavit.
    Forcenergy was a working interest owner in the Lindsey Well. It assigned its interest in
    the Lindsey Well and one other well, along with the underlying leases, to Long on December 1,
    2000. Long concedes that his interest is subject to the 1995 JOA.3 RIM became operator of the
    Lindsey Well in October 2004.
    The Lindsey Well was the only producing well on the 160-acre tract. On December 19,
    2006, the Lindsey Well ceased to produce because of parted rods. On January 10, 2007, RIM
    submitted an AFE (Authorization for Expenditure) to all working interest owners proposing a
    workover, or repair, operation. The total estimated cost was $320,686. Long‘s share was
    $124,540. Long did not respond. RIM attempted to repair the Lindsey Well, and it determined
    that there was a partial casing collapse. In July 2007, RIM drilled a replacement well and
    reestablished production.
    The JOA provides that, if a working interest owner goes nonconsent on a proposed
    operation, it relinquishes its right to any production from that well until its share of the costs,
    plus an additional 200% or 500% depending upon the type of cost incurred, has been recouped
    by the consenting parties.                 However, for operations denominated as ―Required Well or
    Operations,‖ JOA Article XV.K. provides:
    Notwithstanding anything to the contrary herein contained, it is
    understood and agreed that the non-consent provisions of Article VI.B.2. shall not
    be applicable to any well or operation which is necessary to perpetuate an
    expiring lease or leases* or to earn an interest in a lease or leases pursuant to any
    2
    This tract was described as:
    The south 188.182 acres of the East 3/8ths of said Section 109, SAVE AND EXCEPT the 26.667 acre tract
    included in the pooled unit surrounding the Patrick – Lindsey Trust 109 No. 1 Well as described in Pooling
    Agreement and Declaration of Pooled Unit dated January 1, 1995, filed at Volume 371, Page 385 of the Oil
    and Gas Lease Records of Dawson County, Texas; and, LESS the South 100 feet of said 188.182 acre tract.
    3
    During a hearing on RIM‘s motion for summary judgment, Long acknowledged that he was subject to the JOA‘s
    nonconsent penalty.
    2
    farmout or other agreement. To ―earn an interest‖ as abovementioned is herein
    understood to include completion operations if production is required to earn,
    whether or not drilling has extended the lease or continued the right to drill. Any
    well drilling or other operation which is necessary to perpetuate or earn a lease or
    interest therein shall be deemed to be a ―required well‖ or ―required operation.‖
    As to any required well or required operation proposed by any party hereto in
    which any other party hereto elects not to participate, the non-participating party
    shall release and relinquish forever proportionately to the participating parties all
    of non-participating party‘s interest in and to the lease or leases or interest
    (―relinquished leases‖) herein which would be perpetuated by such required well
    or required operation. The interest in such relinquished leases shall be assigned
    by the non-participating party to the participating parties without warranty of title
    except as to claims by, through or under assignor and shall be free of any
    additional burdens as is provided for in Article III.D hereof. All other leases or
    interests in which the non-participating party owns an interest which are pooled
    with the relinquished leases to form a proration unit under the regulations of the
    governmental authority having jurisdiction shall be subject to Article XV.L.
    herein. Nothing herein shall be construed to require the reduction of such non-
    participating party‘s interest in any producing wells or units.
    *As used in this section, an expiring lease(s) is defined to be any oil and
    gas lease which would expire within 60 days of the commencement of the
    proposed operation but will not then expire if such operation is commenced.
    In January 2008, RIM forwarded Long an assignment of his interest in the 160-acre tract
    to the consenting parties. Long did not respond. RIM then filed this declaratory judgment
    action.
    II. Issues
    Long challenges the trial court‘s judgment with eleven issues. Long argues first that the
    trial court erred because the JOA violates the statute of frauds. Long argues in Issues Two and
    Five that there are unresolved fact questions. In Issue Three, he contends that conditions pre-
    cedent were unsatisfied. He argues in Issue Four that there was no evidence of the actual
    commencement date of the rework operation. In Issue Six, Long argues that the JOA contains an
    unenforceable penalty.       In Issue Seven, he contends that the JOA‘s forfeiture provision is
    unenforceable. In Issue Eight, he argues that the JOA violates the Rule Against Perpetuities. He
    contends in Issue Nine that the trial court lacked subject-matter jurisdiction because RIM did not
    have standing. In Issue Ten, he argues that the trial court erred by denying his plea in abatement.
    Finally, in Issue Eleven, he contends that the trial court erred by granting attorney‘s fees because
    there were unresolved questions of fact.
    3
    III. Special Exception
    Long‘s brief begins with a discussion of his special exception to RIM‘s motion for
    summary judgment. We assume that this was intended as an introduction to his other issues
    because he raises no specific issue complaining of the trial court‘s ruling. Even if we are
    incorrect, Long has identified no error with respect to his special exception.
    IV. Jurisdiction
    Long complains that the trial court lacked jurisdiction because RIM lacked standing.
    Specifically, Long complains that RIM is improperly using a suit for declaratory judgment to
    affirmatively alter the rights, status, and legal relationships of the parties to the JOA by forcing
    him to assign his interests and that RIM suffered no legal injury because it owns no interest in
    the well and, therefore, is not entitled to an assignment of his interest.
    Standing is a prerequisite to subject-matter jurisdiction. Bland Indep. Sch. Dist. v. Blue,
    
    34 S.W.3d 547
    , 553, 558 (Tex. 2000). A party has standing if: (1) it has sustained, or is
    immediately in danger of sustaining, some direct injury as a result of the defendant‘s wrongful
    act; (2) it has a direct relationship between the alleged injury and the claim being adjudicated;
    (3) it has a personal stake in the controversy; (4) the challenged action has caused it some injury
    in fact, either economic, recreational, environmental, or otherwise; or (5) it is an appropriate
    party to assert the public‘s interest in the matter, as well as its own. Walton v. City of Midland,
    
    287 S.W.3d 97
    , 100 (Tex. App.—Eastland 2009, pet. denied).
    Whether a court has subject-matter jurisdiction is a question of law and, therefore, is
    reviewed de novo. Tex. Natural Res. Conservation Comm’n v. IT-Davy, 
    74 S.W.3d 849
    , 855
    (Tex. 2002). Initially, we determine jurisdiction by considering whether a plaintiff has alleged
    facts that affirmatively demonstrate a trial court‘s subject-matter jurisdiction. Tex. Dep’t of
    Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 226 (Tex. 2004). The pleadings are construed
    liberally in favor of the plaintiff, and we look to the pleader‘s intent. Tex. Ass’n of Bus. v. Tex.
    Air Control Bd., 
    852 S.W.2d 440
    , 446 (Tex. 1993). In some instances, however, consideration of
    evidence and resolution of disputed facts are necessary to determine jurisdiction. 
    Miranda, 133 S.W.3d at 226
    . In that instance, we consider any relevant evidence submitted by the parties
    when necessary to resolve the jurisdictional issue raised. 
    Id. at 227.
           The trial court had subject-matter jurisdiction. District courts have a broad grant of
    jurisdiction to resolve disputes. Consequently, a constitutional presumption exists that they are
    authorized to resolve a dispute. In re Entergy Corp., 
    142 S.W.3d 316
    , 322 (Tex. 2004). TEX.
    4
    CIV. PRAC. & REM. CODE ANN. § 37.004(a) (Vernon 2008) specifically vests trial courts with the
    jurisdiction to hear requests for declaratory relief from persons interested under a written
    contract, to determine any question of construction or validity arising under that contract, and to
    issue a declaration of rights, status, or other legal relations under that contract.
    RIM was an interested party. RIM‘s live pleading, its third amended petition, alleged
    that it was the operator of the land in dispute, that Long‘s interest was subject to the terms of a
    JOA, that this JOA covered the Lindsey 109-A No. 1 well, that Long failed to respond to an AFE
    seeking approval of a repair to the well, and that, therefore, he was deemed to have relinquished
    his interest to the participating parties. RIM also provided the court with a copy of the P-4
    naming it operator of the Lindsey Trust ―109‖ A Lease and an affidavit from its senior landman
    offering testimony that Goodrich Petroleum Company of Louisiana transferred operation of the
    Lindsey Well to RIM effective October 1, 2004.
    RIM did not seek inappropriate relief. RIM sought a declaratory judgment that (1) Long
    was bound by the terms of the JOA, (2) Long refused to consent to operations necessary to
    perpetuate the leasehold, (3) Long has forfeited his interest in the leasehold, (4) Long‘s interest is
    now owned by the consenting working interest owners, and (5) Long‘s forfeiture was effective
    no later than thirty days after February 5, 2007. Contrary to Long‘s argument, these were not
    requests to affirmatively alter the rights, status, and legal relationships of the parties to the JOA
    by forcing him to assign his interests. First, RIM merely sought clarification of the parties‘
    current ownership interests. Second, RIM did not request specific performance.
    Finally, it was unnecessary for RIM to own an interest in the well to have standing. As
    the operator, it is responsible to the working interest owners and, therefore, has an interest in
    determining who they are. Because the working interest owners‘ rights and liabilities depend, in
    part, on their percentage of ownership, RIM also has an interest in determining those
    percentages. RIM established that a justiciable controversy existed because of Long‘s alleged
    failure to respond to the AFE and the possibility that this failure resulted in a forfeiture of his
    interest in favor of the consenting working interest owners. The trial court, therefore, did not err
    by denying his plea to the jurisdiction. Issue Nine is overruled.
    Long also argues that the trial court lacked jurisdiction because it could not issue a
    declaratory judgment as to parties who were not before it. There is no dispute that the parties to
    whom RIM alleges Long is contractually obligated to assign his interest in the Lindsey Well are
    not parties. TEX. CIV. PRAC. & REM. CODE ANN. § 37.006(a) (Vernon 2008) provides that,
    5
    ―[w]hen declaratory relief is sought, all persons who have or claim any interest that would be
    affected by the declaration must be made parties. A declaration does not prejudice the rights of a
    person not a party to the proceeding.‖ Because this suit could result in a declaration that the
    consenting working interest owners are entitled to a portion of Long‘s interest, they are
    undoubtedly permissive parties. But their absence did not deprive the trial court of jurisdiction.
    This court has held that all royalty owners are not required to be joined in a declaratory judgment
    action seeking a declaration that a lease had terminated and that a unit was void. Sabre Oil &
    Gas Corp. v. Gibson, 
    72 S.W.3d 812
    , 816 (Tex. App.—Eastland 2002, pet. denied). We noted in
    that case that, even though the missing royalty owners had an interest in the litigation because
    their share of the production from the pooled unit would be affected, their presence was
    unnecessary to determine whether Sabre pooled in bad faith and breached the terms of the lease.
    
    Id. The same
    situation is present here. The other working interest owners have an interest in
    this litigation, but their presence was unnecessary for the trial court to determine whether JOA
    Article XV.K. required Long to assign his interest to them. Issue Ten is overruled.
    V. Statute of Frauds
    Long contends that JOA Article XV.K. violates the statute of frauds, TEX. BUS. & COM.
    CODE ANN. § 26.01 (Vernon 2009). Specifically, Long complains that there is no designation or
    description of the assignor or assignees, that there is an insufficient description of the interests in
    the leases to be released and assigned, and that there is no reference to an extrinsic writing
    sufficient to supply the missing information. As we understand Long‘s position, Article XV.K.
    violates the statute of frauds because the day it was executed the parties conditionally agreed to
    convey real property interests in the future but did so without knowing what interests they could
    be required to assign or to whom those assignments would be made. RIM responds that we must
    look beyond Article XV.K. and consider the four corners of the JOA; that we must also consider
    any documents referenced in the JOA or otherwise in Long‘s chain of title; and that, when we do
    so, all the information necessary to satisfy the statute of frauds will be found.
    The statute of frauds requires that the property to be conveyed be adequately described by
    providing the means or data by which it may be identified with reasonable certainty. Kmiec v.
    Reagan, 
    556 S.W.2d 567
    (Tex. 1977). The description cannot be arrived at from tenuous
    inferences and presumptions of doubtful validity. Rowson v. Rowson, 
    275 S.W.2d 468
    (Tex.
    1955). The description must be either in the writing itself or in another existing document
    6
    specifically referenced in the writing. Wilson v. Fisher, 
    188 S.W.2d 150
    (Tex. 1945). The
    certainty of the contract may be aided by parol evidence in limited situations. Essential elements
    may never be supplied. The details that merely explain or clarify the essential terms appearing in
    the instrument may ordinarily be shown by parol evidence. But the parol evidence must not
    constitute the framework or skeleton of the agreement. That framework must be contained in the
    writing. Thus, the resort to extrinsic evidence is not for the purpose of supplying the location or
    description of the land, but only for the purpose of identifying it with reasonable certainty from
    the data in the memorandum. Swinehart v. Stubbeman, McRae, Sealy, Laughlin & Browder,
    Inc., 
    48 S.W.3d 865
    , 877 (Tex. App.—Houston [14th Dist.] 2001, pet. denied).
    Long initially argues that there is no proper description of the assignor or assignee within
    JOA Article XV.K. We disagree with both Long‘s inference and his conclusion. First, we
    disagree with his inference that our analysis is limited to the language of JOA Article XV.K. We
    can, instead, consider the entire agreement and any other documents referenced in that
    agreement. Second, we disagree that the JOA fails to adequately identify the assignors and
    assignees. The JOA itself is limited to the parties to that agreement. From this group, assignors
    will be those who do not participate in a required well or operation. The assignees will be those
    who do.
    Long next argues that Article XV.K. contains an insufficient description of the leases to
    be released and assigned. Again, we disagree. The first page of the JOA defines the contract
    area as:
    See Exhibit ―A‖ Attached Hereto[.] All of Section 109, the N/2 of Section 108
    and the W/4 of Section 94, Block M, EL&RR Ry. Company Survey COUNTY
    OR PARISH OF Dawson STATE OF Texas.
    Exhibit ―A‖ to the JOA further defines the lands subject to the agreement as:
    Tract No. 1:   The East 3/8th acres of Section 109
    Tract No. 2:   The West 5/8th acres of Section 109
    ....
    [A]ll in Block M, EL&RR Ry. Co. Survey, Dawson County, Texas from the
    surface of the earth to all depths.
    Exhibit ―A‖ continues with descriptions of each of the leases covering each tract. The JOA,
    therefore, adequately described the lands to which it was subject.
    7
    Long is correct that, at the time the JOA was signed, the parties did not know which
    leases would be expiring if Article XV.K. was invoked or even if the expiring leases were
    described in Exhibit ―A‖ or would be subsequently acquired leases. This, however, is not fatal.
    In Westland Oil Development Corp. v. Gulf Oil Corp., 
    637 S.W.2d 903
    (Tex. 1982), the court
    considered whether an AMI (Area of Mutual Interest) provision in a letter agreement was
    enforceable. One of the challenges to the provision was the contention that it violated the statute
    of frauds. The AMI provision read:
    5. If any of the parties hereto, their representatives or assigns, acquire any
    additional leasehold interests affecting any of the lands covered by said farmout
    agreement, . . . such shall be subject to the terms and provisions of this 
    agreement. 637 S.W.2d at 905
    . This AMI provision suffers from the same problem raised by Long. There
    was a reference to a contractual area, and there was a conditional agreement to assign interests in
    the future within this contractual area. But, the AMI did not specifically identify what interest
    would be assigned because no one knew whether any additional interest would be acquired, let
    alone what those interests might be. Despite this, the court held that the provision did not violate
    the statute of frauds because the farmout agreement contained a sufficient description of the three
    sections it covered. 
    Id. at 909.4
              A comparable situation exists here. The original parties did not know if Article XV.K.
    would be invoked and, if so, exactly what interest would be assigned or who would be required
    to assign. They did, however, know that Article XV.K. was limited to the JOA‘s contract area.
    Because that area is sufficiently described, the agreement does not violate the statute of frauds.
    Issue One is overruled.
    VI. Conditions Precedent
    Long argues that two conditions precedent to the application of Article XV.K. were not
    met. First, Long argues that the consent of all consenting parties was not obtained. Long relies
    upon JOA Article VII.D.2. to contend that a well may not be reworked without first obtaining
    4
    Long argues that a similar situation existed in Long Trusts v. Griffin, 
    222 S.W.3d 412
    (Tex. 2006), and that the
    supreme court held that an agreement to assign undefined interest within a larger defined area was unenforceable. The court,
    however, held that the agreement was unenforceable because the larger area was insufficiently defined. In that case, the contract
    area was defined as being located ―in the Northeast portion of Rusk County, Texas, and consist[ed] of 50+ leases covering
    approximately 2100+ net mineral acres in the Dirgin and Oak Hill Fields area‖ as ―described in the attached Exhibit ‗A.‘‖
    Exhibit A identified the lessor‘s name, the survey name, the term, and net acreage for each lease. The court held that this was
    insufficient to identify the exact location of the lease with reasonable certainty. 
    Id. at 416.
    But as we have previously noted, the
    contract area description in the JOA was legally sufficient.
    8
    this consent.5 Long is correct that the JOA requires prior consent before engaging in any
    reworking operations. Article XV.K., however, makes this provision inapplicable for required
    operations.        The article begins ―[n]otwithstanding anything to the contrary,‖ and then it
    specifically excludes the consent provisions of Article VI.B.2. Because Article VI.B.2. creates
    the consenting parties, by excluding it, Article XV.K. necessarily excludes Article VII.D.2. as
    well.
    Long next argues that there was no evidence that the operation was proposed by a party
    to the JOA because there is no evidence that RIM is a party to the JOA. Long contends that
    there was disputed evidence whether RIM was the operator, but he points to no conflicting
    evidence. RIM offered the affidavit of a senior landman, Debby Harrington. She testified that
    Goodrich Petroleum transferred operation of the Lindsey Well to RIM on October 1, 2004. She
    identified the JOA and a letter and AFE sent by RIM to Long proposing the repair operation on
    the Lindsey Well. RIM also produced a copy of the P-4 that named RIM operator of the Lindsey
    Well as of October 1, 2004. Finally, RIM offered the affidavit of its controller, Thomas M.
    Murphy. He authenticated over 150 pages of joint interest billings for the Lindsey Well sent by
    RIM to Long and payment records evidencing payments to Long for his share of the Lindsey
    Well‘s production. In the absence of any conflicting evidence, RIM offered sufficient evidence
    to establish that it was the operator of the Lindsey Well and was a party to the JOA. Issue Two
    is overruled.
    Long correctly notes that the record does not establish that RIM was properly selected as
    successor operator pursuant to Article V. of the JOA and that no evidence was produced that
    RIM owned any interest in any of the leases covered by the JOA. Neither, however, is of any
    moment. Long may have had grounds to challenge RIM‘s selection as successor operator, but
    there is no evidence that he ever complained of RIM‘s selection.                            Instead, the evidence
    establishes that, prior to the disputed operation, he paid RIM‘s bills and accepted his share of
    production. Long has, therefore, waived the right to complain of RIM‘s status as operator.
    Abraxas Petroleum Corp. v. Hornburg, 
    20 S.W.3d 741
    , 750-52 (Tex. App.—El Paso 2000, no
    pet.). Issue Three is overruled.
    5
    This provision provides:
    2. Rework or Plug Back: Without the consent of all consenting parties, no well shall be reworked or plugged
    back except a well reworked or plugged back pursuant to the provisions of Article VI.B.2. of this agreement.
    Consent to the reworking or plugging back of a well shall include all necessary expenditures in conducting such
    operations and completing and equipping of said well, including necessary tankage and/or surface facilities.
    9
    VII. Penalty
    Long contends that Article XV.K. creates an unenforceable penalty or forfeiture. The
    supreme court considered the enforceability of nonconsent penalties in Valence Operating Co. v.
    Dorsett, 
    164 S.W.3d 656
    (Tex. 2005). In that case, the operator proposed drilling eight wells.
    Dorsett did not consent to any of 
    them. 164 S.W.3d at 660
    . The parties‘ JOA imposed a 300%
    nonconsent penalty. 
    Id. Dorsett contended
    that this penalty was an unenforceable liquidated
    damages provision. 
    Id. at 664.
    The supreme court disagreed, finding that the clause rewarded
    consenting parties for undertaking a defined risk. The court also noted that liquidated damages
    are recoverable only where there has been a failure to perform a contractual obligation; a
    nonconsent election, however, is a contractual right. Consequently, nonconsent penalties are not
    liquidated damages. 
    Id. at 664-65.
    Instead, they are an incentive for the risk takers by allowing
    reasonable compensation for agreeing to participate in new wells.
    A similar situation is present here. The JOA contains standard nonconsent language for
    most operations. The parties, however, elected to include a customized provision for a specific
    class of operations. Required wells or required operations were defined as those necessary to
    perpetuate or earn a lease or interest therein. RIM produced evidence that the Lindsey Well was
    the only producing well on its proration unit and that, therefore, if the proposed rework operation
    was not performed, the leases would expire as to that proration unit. Long had a choice: agree to
    participate in operations to keep the leases in force or not. He chose not to participate. If the
    other working interest owners had made the same decision, the leases would have terminated,
    and Long would be in the same position he is in now. But, they did not. They agreed to accept
    the financial risk of keeping the leases intact by undertaking a workover. The extent of this risk
    is highlighted by the fact that RIM knew the rods had parted and suspected a casing leak. Under
    the best case scenario, the cost to repair the well was $320,686, but RIM warned the working
    interest owners that it might be necessary to sidetrack and redrill the well. We know today that
    not only was this additional expense incurred but, in fact, the consenting working interest owners
    ultimately paid to drill a replacement well. Because the consenting owners agreed to this risk
    and because Long is in no different position than he would be if the Lindsey Leases had not been
    maintained, Article XV.K. is not an unenforceable penalty or forfeiture. Issues Six and Seven
    are overruled.
    10
    VIII. Rule Against Perpetuities
    Long also argues that Article XV.K. creates a future executory interest in real property in
    violation of the rule against perpetuities. Texas courts have held that the rule against perpetuities
    is only a means of preventing unreasonable restraints on alienation and, therefore, does not bar
    enforcement of contractual rights to sell property that does not constitute an unreasonable
    restraint on alienation. See, e.g., Cherokee Water Co. v. Forderhause, 
    641 S.W.2d 522
    , 526
    (Tex. 1982) (preferential purchase right did not violate the rule against perpetuities).6 Article
    XV.K. is not an unreasonable restraint on alienation because it does not prevent a working
    interest owner from selling its interest, restrict their ability to do so at a time of their choice,
    constrain to whom they may sell, or limit the price to which they may agree. Issue Eight is
    overruled.
    IX. Other Issues
    Long‘s list of issues includes Issues Four and Five complaining of unresolved fact
    questions and Issue Eleven complaining of the award of attorney‘s fees. Long did not brief any
    of these issues in the argument section of his brief, and RIM argues that they have been waived.
    See Trenholm v. Ratcliff, 
    646 S.W.2d 927
    , 934 (Tex. 1983) (listing of points without argument
    and authorities constituted waiver). Long responds in his reply brief that these issues are briefed,
    contends that there is no authority limiting where an issue may be argued, and points us to his
    factual summary for his arguments.                 However, TEX. R. APP. P. 38.1(g) provides that the
    statement of facts ―must state concisely and without argument the facts pertinent to the issues or
    points presented.‖ Rule 38.1(i) defines the argument section of the brief as containing ―a clear
    and concise argument for the contentions made, with appropriate citations to authorities and to
    the record.‖ Consequently, RIM is correct.                    Issues Four, Five, and Eleven have not been
    preserved. In the interest of justice, however, we will consider them.
    In Issue Four, Long complains that there was no evidence that any relinquishment duty
    owed by Long under Article XV.K. arose because there was no evidence of the actual
    commencement date of the rework operation. Because the operation was proposed under Article
    XV.K. rather than Article VI.B.1. or Article VI.B.2., it was unnecessary to prove the actual date
    the rework operation commenced.
    6
    The supreme court adopted the reasoning of the lower court on this point. That opinion is at Forderhause v. Cherokee
    Water Co., 
    623 S.W.2d 435
    , 438-39 (Tex. Civ. App.—Texarkana 1981).
    11
    Long argues that there was no evidence that the proposed operations were legitimate
    operations that invoked Article XV.K. Jason B. Rouse, an engineer for RIM, testified that the
    Lindsey Well was the only producing well on the 160-acre proration unit and that it ceased to
    produce because of parted rods. This is sufficient to establish that the repair was a required
    operation as defined by Article XV.K. Long also complains that there was insufficient evidence
    that RIM was the operator. We have previously held otherwise. Issue Four is overruled.
    Long‘s fifth issue complains of several unresolved fact questions. Issue 5(a) contends
    that there was insufficient evidence describing his interest in the oil and gas leases within the
    proration unit. We have previously held that the JOA satisfied the statute of frauds, and Long
    has conceded that the JOA applied to his interest. Moreover, Long acquired his interest from
    Forcenergy Onshore Inc. The assignments into Forcenergy all referenced the JOA. He was,
    therefore, bound not only by that agreement but also by all the property descriptions contained
    within it.7 We note also that the assignment from Forcenergy to Long specifically referred to the
    ―W6613 – Lindsey Trst 109 A1‖ Well. Prior to his assignment, the operator filed an affidavit in
    the real property records designating a proration unit for a 160-acre tract surrounding the Lindsey
    Trust ―A‖ No. 1 Well. The affidavit provided a legally sufficient description of the proration
    unit. Collectively, this is sufficient to describe the interests Long must assign because of his
    decision to go nonconsent on the workover. Issue 5(a) is overruled.
    In Issue 5(b) Long contends that there was a fact question on whether the Lindsey Well is
    subject to the JOA. Long conceded in open court that his interest was subject to the JOA, and
    the assignments into Forcenergy, his predecessor in title, refer to the JOA.                                  Issue 5(b) is
    overruled.
    Long argues in Issue 5(c) that there was insufficient evidence that RIM was a party to the
    JOA. We have previously found that RIM was the operator. Issue 5(c) is overruled.
    Long argues in Issue 5(d) that there was insufficient evidence that he breached
    Article XV.K. RIM offered uncontroverted evidence that by correspondence dated January 10,
    2007, it sent the working interest owners an AFE to find and repair a suspected casing leak. It
    produced a certified mail receipt evidencing that Long received this correspondence on
    January 30, 2007. It also offered affidavit testimony that Long did not respond to the AFE or the
    request for an assignment of his interest.                    We have previously found that RIM produced
    7
    See 
    Westland, 637 S.W.2d at 908
    (―a purchaser is bound by every recital, reference and reservation contained in or fairly
    disclosed by any instrument which forms an essential link in the chain of title under which he claims‖).
    12
    sufficient evidence to establish that the proposed repair was a required operation because the
    leases underlying the 160-acre proration unit would otherwise expire. This additional evidence
    sufficiently established that Long was required to participate in that operation or to assign his
    interest to the working interest owners who did participate and that he refused to do so.
    Issue 5(d) is overruled.
    Long next complains in Issue 5(e) that there was insufficient evidence that RIM gave
    notice of the work to be performed. RIM‘s January 10, 2007 correspondence informed the
    working interest owners that it intended to do the following:
    Perforate tubing @ 5460'. Establish circulation & clean annulus to surface.
    Chem-cut tubing above anchor catcher and @ 5465'.
    PU wash pipe, jars & overshot & jar tubing out of hole.
    RIH w/ wash pipe, jars & overshot & jar TAC out of hole (may need to swedge
    casing).
    Run casing inspection log & set CIBP @ 9000'.
    Freepoint casing, cut & pull from hole as close to Top of cement (8700') as possible.
    Replace bad casing & rerun w/ Bowen cementing casing patch.
    Cement casing into surface pipe.
    Drill out and test casing.
    Re-perforate producing interval & stimulate w/ acid.
    Rerun production equipment and return to production.
    RIM also advised the working interest owners that this would cost an estimated $320,686, and it
    provided a breakdown of these costs. Finally, RIM told the working interest owners that, if it
    encountered additional problems, operations would be suspended and a revised plan submitted.
    Long correctly notes that the plan of operation described in the correspondence did not
    include a sidetrack operation or drilling a replacement well, but that both were done. We note
    that the letter did advise the working interest owners that both were possible if the initial repair
    was unsuccessful. RIM was not required to provide Long with additional notice. The summary
    judgment evidence establishes that Long did not respond to RIM‘s January correspondence.
    There is no contention that RIM did anything other than what was originally contemplated. That
    effort was unsuccessful, and RIM proceeded with additional activities. Because Long did not
    respond to the AFE, he no longer had an interest in the Lindsey Well and was not entitled to
    additional notice. Issue 5(e) is overruled.
    In Issues 5(f) and 11, Long complains of the award of attorney‘s fees, contending that
    there were disputed questions of fact on the reasonableness of that award. RIM‘s counsel filed
    13
    an affidavit dated December 17, 2008, and testified that RIM had incurred fees to date of
    $16,931.50. He filed a second affidavit dated August 20, 2009. In that affidavit, he testified that
    RIM had incurred attorney‘s fees of $41,380. He also offered testimony as to reasonable and
    necessary fees in the event of an appeal. Long contends first that the difference between the two
    affidavits creates a fact question. However, because they represent fees incurred as of two
    separate dates, they are not inconsistent and no fact question was created.
    Long contends second that he raised a fact question. Long responded with the affidavit
    of his counsel. Counsel testified that the requested fees were, in his opinion, excessive and that
    even $15,000 would be excessive. RIM contends that Long‘s affidavit was insufficient to create
    a fact question because it was conclusory. Long‘s affidavit is short on detail but no less so than
    RIM‘s affidavit. RIM‘s affidavit established counsel‘s expertise and experience in this area of
    the law, his familiarity with reasonable and necessary fees, and RIM‘s incurrence of
    approximately $41,000 in fees so far. Counsel did not, however, offer any evidence describing
    the work performed. In light of this, Long‘s counsel‘s affidavit that $41,000 was excessive
    based upon his experience is sufficient to create a fact question.
    Issues 5(f) and 11 are sustained. This case is remanded solely for a factual determination
    of the reasonable and necessary fees to be awarded.
    IX. Conclusion
    The judgment of the trial court is affirmed in part and reversed and remanded in part.
    That portion of the judgment awarding attorney‘s fees is reversed, and this cause is remanded to
    the trial court for a factual determination of that issue only. The remainder of the judgment is
    affirmed.
    RICK STRANGE
    JUSTICE
    April 14, 2011
    Panel consists of: Wright, C.J.,
    McCall, J., and Strange, J.
    14