Juan Villarreal and Laura Villarreal v. Albert J. Hanks D/B/A a & M Construction Co. ( 2012 )


Menu:
  •                             NUMBER 13-11-00700-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    JUAN VILLARREAL AND LAURA VILLARREAL,                                    Appellants,
    v.
    ALBERT J. HANKS D/B/A A & M CONSTRUCTION CO.,                               Appellee.
    On appeal from the 92nd District Court
    of Hidalgo County, Texas.
    MEMORANDUM OPINION
    Before Justices Rodriguez, Benavides, and Perkes
    Memorandum Opinion by Justice Benavides
    By three issues, which we renumber as one, appellants Juan and Laura Villarreal
    (“the Villarreals”) contend that the trial court erred when it granted appellee Albert J.
    Hanks’s d/b/a A & M Construction Co.’s, (“A & M Construction”) motion to confirm an
    arbitration award and denied their motion to vacate. We affirm.
    I.        BACKGROUND1
    The underlying dispute in this case stems from work performed under a
    residential construction contract entered into between the Villarreals and A & M
    Construction. The Villarreals, as homeowners, contracted with A & M Construction, as
    contractor, to build a 3,590 square-foot home.                   During construction, the Villarreals
    alleged, generally, that A & M Construction breached the contract because it had not
    performed in a good and workmanlike manner, citing specific flaws in construction. 2
    The following provision was included in the contract regarding disputes:
    13. [A & M Construction] and [the Villarreals] both agree to resolve any
    conflicts or dispute in arbitration before pursuing any legal matter.
    The Villarreals eventually enlisted the help of the Better Business Bureau (“BBB”).
    The BBB drafted—and both parties signed—an agreement for the Villarreals and A & M
    Construction to submit to binding arbitration to settle their contractual dispute.                  After the
    arbitration hearing, the arbitrator outlined his decision, which denied the Villarreals’
    request to, among other things:              (1) remove and replace the home’s hardwood floor; (2)
    remove and replace the marble tile in the master bathroom; and (3) change the cabinets
    and deep sink in the laundry/utility room. However, the arbitrator ruled in the Villarreals’
    favor on other complaints and ordered                A & M Construction to:         (1) polish the master
    bathroom tile; (2) produce a written copy of the items discussed during a recent
    1
    Because this is a memorandum opinion and the parties are familiar with the facts, we will not
    recite them here except as necessary to advise the parties of the Court’s decision and the basic reasons for
    it. See TEX. R. APP. P. 47.4.
    2
    More specifically, the Villarreals complained, in part, that: (1) the wood flooring was not properly
    installed and requested that it be replaced; (2) the marble tile in the master bathroom was not what the
    Villarreals ordered and should be removed and replaced at A & M Construction’s expense; (3) the cabinets
    and deep sink in the laundry room were not as specified by the plans.
    2
    walk-through; and (3) provide all necessary documents to allow the closing of the home
    to proceed.
    Following the arbitrator’s decision, the Villarreals petitioned the trial court to
    vacate the arbitration award on various grounds.                    A & M Construction moved that the
    trial court confirm the award and enter judgment. The trial court denied the Villarreals’
    motion to vacate and granted A & M Construction’s motion to confirm. This appeal
    followed.     See TEX. CIV. PRAC. & REM. CODE ANN. § 171.098 (West 2011).
    II.      VACATUR OF ARBITRATION
    By one issue, the Villarreals contend that the trial court erred in declining to
    vacate the arbitration award.3
    A.      Applicable Law and Standard of Review
    Arbitration is strongly favored by Texas law, and judicial review of an arbitration
    award is extraordinarily narrow.            See E. Tex. Salt Water Disposal Co., Inc. v. Werline,
    
    307 S.W.3d 267
    , 271 (Tex. 2010) (citing Prudential Sec. Inc. v. Marshall, 
    909 S.W.2d 896
    , 898 (Tex. 1995); CVN Group, Inc. v. Delgado, 
    95 S.W.3d 234
    , 238 (Tex. 2002));
    see also In re Guardianship of Cantu de Villarreal, 
    330 S.W.3d 11
    , 17 (Tex.
    App.—Corpus Christi 2010, no pet.).                Accordingly, we review a trial court’s decision to
    vacate or confirm an arbitration award de novo, and we review the entire record.                           See In
    re Cantu de 
    Villarreal, 330 S.W.3d at 17
    .
    3
    For reference, the Villarreals asserted by three issues that the trial court erred for failing to vacate
    the arbitration award because (1) there was no agreement to submit the dispute to binding arbitration in the
    parties’ initial construction contract; (2) the Residential Construction Liability Act pre-empts any agreement
    made by the parties; and (3) the arbitrator exceeded his authority by committing gross mistake and
    manifestly disregarding the law of construction contracts. We consolidated these three specific issues into
    one general issue and addressed the original issues as arguments. See TEX. R. APP. P. 47.1.
    3
    “Subjecting arbitration awards to judicial review adds expense and delay, thereby
    diminishing the benefits of arbitration as an efficient, economical system for resolving
    disputes.”   CVN 
    Group, 95 S.W.3d at 238
    .            An arbitrator’s award upon matters
    submitted to them is given the same effect as the judgment of a court of last resort, and
    all reasonable presumptions are indulged in favor of the award, and none against it.       In
    re Cantu de 
    Villarreal, 330 S.W.3d at 18
    (citing CVN 
    Group, 95 S.W.3d at 238
    ). Where
    there is no allegation of a statutory or common law ground to vacate or modify the
    arbitration award, we lack jurisdiction to review the arbitrator's decision.   
    Id. Pursuant to
    civil practice and remedies code section 171.087, unless grounds are offered for
    vacating an award under the sections 171.088 or 171.091 of the civil practices and
    remedies code, the trial court, on application of a party, shall confirm the award.      See
    TEX. CIV. PRAC. & REM. CODE ANN. § 171.087 (West 2011).
    Section 171.088 provides the following statutory grounds for which a trial court
    shall vacate an arbitration award:
    (1) the award was obtained by corruption, fraud, or other undue means;
    (2) the rights of the party were prejudiced by:
    (A) evident partiality by an arbitrator appointed as a neutral
    arbitrator;
    (B) corruption in an arbitrator; or
    (C) misconduct or wilful misbehavior of an arbitrator;
    (3) the arbitrator:
    (A) exceeded his powers;
    (B) refused to postpone the hearing after a showing of sufficient
    cause for the postponement;
    4
    (C) refused to hear evidence material to the controversy;
    (D) conducted the hearing, contrary to sections 171.044–.047 of the
    civil practice and remedies code, in a manner that substantially
    prejudiced the rights of a party; or
    (4) there was no agreement to arbitrate, the issue was not adversely
    determined in a proceeding under [statutes to compel arbitrations], and the
    party did not participate in the arbitration hearing without raising the
    objection.
    See 
    id. B. Discussion
    1.      Agreement to Arbitrate
    First, the Villarreals argue that the arbitration award should have been vacated
    because no agreement existed between the parties to submit the dispute to binding
    arbitration.
    Arbitration agreements are interpreted under traditional contract principles.   J.M.
    Davidson v. Webster, 
    128 S.W.3d 223
    , 227 (Tex. 2003).         The arbitration agreement’s
    validity is a legal question subject to de novo review.    Id.; see In re Kellogg Brown &
    Root, 
    80 S.W.3d 611
    , 615 (Tex. App.—Houston [1st Dist.] 2002, orig. proceeding).         In
    construing an agreement, we determine whether it is possible to enforce the contract as
    written, without resorting to parol evidence, and with the primary concern of ascertaining
    the true intentions of the parties expressed in the instrument.      J.M. 
    Davidson, 128 S.W.3d at 229
    . We must examine and consider the entire writing in an effort to
    harmonize and give effect to all the provisions of the contract so that none will be
    rendered meaningless.      
    Id. No single
    provision taken alone will be given controlling
    effect; rather, all the provisions must be considered with reference to the whole
    instrument. 
    Id. (citing Myers
    v. Gulf Coast Minerals Mgmt. Corp., 
    361 S.W.2d 193
    , 196
    5
    (Tex. 1962)).   Furthermore, a contract is unambiguous if it can be given a definite or
    certain legal meaning.     J.M. 
    Davidson, 128 S.W.3d at 229
    .     However, if the contract is
    subject to two or more reasonable interpretations after applying the pertinent rules of
    construction, the contract is ambiguous, creating a fact issue on the parties’ intent.    
    Id. In this
    case, the Villarreals assert that the initial residential construction contract
    they entered into with A & M Construction did not contain a clause which expressed
    intent to enter into binding arbitration. We agree.    The pertinent clause included in the
    residential construction contract stated that the parties agreed to arbitrate any dispute
    prior to pursuing any legal matter.           This provision is subject to reasonable
    interpretations regarding whether the parties intended to submit to binding or
    non-binding arbitration.    Accordingly, we conclude that the residential construction
    contract is ambiguous and creates a fact issue regarding the parties’ intent.     See 
    id. However, the
    Villarreals do not address the subsequent BBB binding arbitration
    that was signed by both parties.           The BBB instrument displays a large title,
    “AGREEMENT TO ARBITRATE” with the word “BINDING” below it in parenthesis. The
    remainder of the document also shows clear intent by both parties to resolve the
    Villarreals’ breach of contract claim through binding arbitration.
    The opening paragraph of the BBB agreement states the following, in part:
    You should remember that your signature on this contract means that
    you have decided to use this private way of settling your dispute
    instead of going to court, and that you will be bound by the
    arbitrator’s decisions. After a decision by an arbitrator, a court
    normally will refuse to hear the facts in a case in all but the most
    unusual situations.
    (Emphasis in original.)    Furthermore, another clause shows the Villarreals’ consent to
    arbitrate under the Better Business Bureau’s Rules of Arbitration and to follow the
    6
    arbitrator’s decision after the hearing on the dispute. Accordingly, our review of the
    BBB instrument shows an unambiguous intent by the Villarreals and A & M Construction
    to mutually enter into binding arbitration regarding the Villarreals’ allegations against
    A & M Construction for breach of contract.
    2.    Residential Construction Liability Act Preemption
    Next, the Villarreals argue that the Texas Residential Construction Liability Act
    (RCLA), see TEX. PROP. CODE ANN. Chapter 27, preempts the Texas Arbitration Act, see
    TEX. CIV. PRAC. & REM. CODE ANN. Chapter 171, and that the parties could not, by virtue
    of including a clause in their contract submitting to arbitration, alter the notice and
    settlement provisions provided for under the RCLA.          See TEX. PROP. CODE ANN. §
    27.004 (West Supp. 2011).
    We decline to address this argument because it exceeds the scope of our
    “extraordinarily narrow” judicial review of arbitration awards.    See E. Tex. Salt Water
    Disposal 
    Co., 307 S.W.3d at 271
    .       The statutory grounds for which a trial court shall
    vacate an arbitration award are clearly outlined in this opinion and in section 171.088 of
    the civil practices and remedies code.       See TEX. CIV. PRAC. & REM. CODE ANN. §
    171.088.    Here, the Villarreals’ argument of statutory conflict is not a ground for vacatur
    of an arbitration award.   See 
    id. Therefore, we
    are without jurisdiction to review this
    argument.    See In re Cantu de 
    Villarreal, 330 S.W.3d at 18
    .
    3.    Exceeding Authority
    In their final argument, the Villarreals argue that the BBB arbitrator exceeded his
    authority by committing a gross mistake or manifestly disregarding the controlling law in
    the area of construction contracts.
    7
    “Manifest disregard” is a very narrow standard of review.          Xtria L.L.C. v. Intern.
    Ins. Alliance Inc., 
    286 S.W.3d 583
    , 594 (Tex. App.—Texarkana 2009, pet denied).              It is
    more than error or misunderstanding of the law.            
    Id. Instead the
    error must be
    “obvious and capable of being readily and instantly perceived by the average person
    qualified to serve as an arbitrator.” 
    Id. Under this
    standard, the arbitrator recognizes a
    clearly governing principle and ignores it.    
    Id. The issue
    is not whether the arbitrator
    correctly interpreted the law, but whether the arbitrator, knowing the law and recognizing
    that the law required a particular result, simply disregarded the law.        
    Id. (citing Pheng
    Invs., Inc. v. Rodriquez, 
    196 S.W.3d 322
    , 332 (Tex. App.—Fort Worth 2006, no pet.)).
    The burden of proof in this argument rests with the Villarreals.    
    Id. The Villarreals
    assert that the arbitrator’s conclusions essentially place blame on
    them regarding the issues with the hardwood floor and the master bathroom tile. They
    further assert that these conclusions “fly in the face” of construction law, which requires
    quality of workmanship and control of the construction project to rest in the hands of
    A & M Construction and not with the Villarreals.
    However, the arbitrator’s findings do not reflect this contention.     Our review of the
    record indicates that the arbitrator found that the hardwood flooring was the choice
    product of the Villarreals and that the Villarreals chose the particular method of
    installation. With regard to the master bathroom tiles, the arbitrator found that despite
    not being the tile selected by the Villarreals, the Villarreals nonetheless agreed with
    A & M Construction to install the wrong marble tile.         After indulging all reasonable
    presumptions in favor of the arbitration award, we conclude that the Villarreals did not
    meet their burden to demonstrate that the arbitrator manifestly disregarded the law.
    8
    “Gross mistake” is a Texas common-law standard used to attack arbitration
    awards that implies bad faith or failure to exercise honest judgment.       See Callahan &
    Assoc. v. Orangefield Ind. Sch. Dist., 
    92 S.W.3d 841
    , 844 (Tex. 2002). The Villarreals
    contend that the arbitrator failed to exercise honest judgment by manifestly disregarding
    the applicable law of construction contracts. A reading of the arbitrator’s award in this
    case indicates that the Villarreals initially acquiesced to the purported flaws regarding the
    hardwood floors and marble tile in the master bathroom.             More specifically, the
    arbitrator found that the hardwood floor’s defects were not the result of poor
    workmanship, but rather the natural occurrences of wood under humid conditions. After
    indulging all reasonable presumptions in favor of the arbitration award, our review of the
    record and the Villarreals’ arguments do not meet their burden to show that the arbitrator
    exercised bad faith or failed to exercise honest judgment. See 
    id, 92 S.W.3d at 844
    .
    Accordingly, we overrule the Villarreals’ sole issue on appeal.
    III.   CONCLUSION
    We affirm the trial court’s judgment.
    __________________________
    GINA M. BENAVIDES,
    Justice
    Delivered and filed the
    30th day of August, 2012.
    9