  •                                    In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-17-00457-CV
    HEMINK FARMS, LTD., LAURENS SCHILDERINK, ILONA VAN VLIET A/K/A ILONA
    SCHILDERINK, AND HEMINK MANAGEMENT, LLC, APPELLANTS
    V.
    BCL CONSTRUCTION, LLC, APPELLEE
    On Appeal from the 64th District Court
    Castro County, Texas
    Trial Court No. A10098-1608, Honorable Robert W. Kinkaid, Jr., Presiding
    March 20, 2019
    MEMORANDUM OPINION
    Before QUINN, C.J., and PIRTLE and PARKER, JJ.
    Appellants Hemink Farms, Ltd., Laurens Schilderink, Ilona Van Vliet, and Hemink
    Management, LLC, appeal from the jury verdict and judgment in favor of BCL
    Construction, LLC, on its claims arising from the construction of a house near Hart, Texas.
    We affirm in part and reverse and render in part.
    Background
    In 2012, BCL finished construction on a house for Schilderink and Van Vliet that
    another contractor had begun. The house was later sold and, in 2015, BCL was hired to
    build a new house for Schilderink and Van Vliet. The new home was to be a near-replica
    of the first one. It was constructed on property owned by Hemink Farms, a company
    which is owned by Schilderink and Hemink Management. Both Schilderink and Van Vliet,
    husband and wife, exercised control over the project and had power to make payments.
    There was no written contract.
    The first house had been completed at a cost of approximately $1.3 million.
    Schilderink testified that his budget for the second house was $1.5 million. When Thomas
    Robertson, who was a subcontractor BCL hired to be the project manager, outlined a
    projected budget of $1.57 million, Schilderink said it was close enough, and to get started.
    Schilderink and his family were living in a rental property and wanted to move into the
    new house at the end of their one-year lease term. Robertson testified that the budget
    was “a starting point,” because he did not have all the facts or any design. Both Robertson
    and Schilderink said that the parties agreed that BCL would build the house for cost plus
    a flat builder’s fee of $200,000.
    Construction on the house was soon underway. Over the course of the project,
    Schilderink and Van Vliet made changes to the design of the house and to the materials
    used. For example, they raised the pitch of the roof after construction had started, put in
    stamped concrete, added a theater room to the basement, built an indoor pool instead of
    an outdoor pool, upgraded finishes in the pool house, used solid cedar beams rather than
    2
    the faux beams used in the first house, increased the size of the garage, installed a “man
    cave” constructed with materials from an old barn which BCL gathered, and more. Also,
    some features of the house, such as cabinetry and millwork, were redone multiple times
    as a result of Schilderink and Van Vliet changing their minds or communicating
    contradictory instructions. This led to additional expenses. By the end of 2015, Hemink
    Farms had paid $1.678 million in construction costs. Steve Long, the owner of BCL,
    testified that as the project neared completion, Schilderink was slow in making payments.
    This caused Long to get behind in paying subcontractors. Long testified that when he
    sought assurances from Schilderink, Schilderink told him to “just finish, and I’ll pay you.”
    He believed Schilderink was withholding payment with the intent to get the project finished
    faster. Robertson also testified about the changes and additions made to the house and
    stated that “the overarching statement that Mr. Schilderink continued to make to me, was
    ‘get these finished and I’ll pay you.’”
    The family moved into the house in March of 2016, by which time the project had
    reached substantial completion.       Robertson had made a “punch list” of items that
    Schilderink and Van Vliet had identified as requiring completion or correction to finish the
    house, and BCL was working on those items in April 2016.
    On April 27, 2016, Robertson met with Schilderink at Schilderink’s Spandet Dairy
    office to discuss payment of two invoices which remained unpaid. The first, dated March
    11, 2016, was for $197,683.43, and the second, dated April 22, 2016, was for
    $328,688.34.     Schilderink told Robertson he was not expecting another bill, as he
    believed he had already paid too much. He testified, “I knew I was over the 1.5 million
    but I thought it was still fairly close and I – and I added it up. So we came to 2.1 million I
    3
    already paid and then I got $500,000-something thousand on top of that, I really got a
    shock of that [sic].” Robertson testified that Schilderink wanted to hold BCL to a $1.5
    million budget even though he continued to order expensive items for the house.
    Robertson had brought the box of invoices for the project, but Schilderink did not want to
    review them. Schilderink indicated that he wanted to speak to Long, so Long came from
    Amarillo to join the meeting.
    All three men testified at trial that, at the time of their April meeting, a dispute
    existed regarding payment. Schilderink offered to pay the smaller of the two still-due bills,
    but Long said that was not enough and that Schilderink needed to pay the larger bill.
    Eventually, Schilderink wrote BCL a check for $263,185, roughly half of the amount due
    under the two final bills. BCL deposited the check. Schilderink testified that Long agreed
    to “call it good” and took the position that the $263,185 payment was a final settlement.
    Long, however, testified that he did not agree to accept the check as a settlement of the
    two invoices.
    No further payment was forthcoming, so Long eventually filed a mechanic’s and
    materialman’s lien against the property. BCL then filed suit against appellants, seeking
    foreclosure of the lien and alleging breach of contract, suit on a sworn account, quantum
    meruit, and promissory estoppel. Appellants asserted that BCL’s claims were barred by
    the doctrines of accord and satisfaction and waiver. Hemink Farms filed counterclaims
    against BCL, alleging breach of contract and fraudulent lien filing.
    Following a four-day trial, the jury found that all parties, BCL, Schilderink, Van Vliet,
    Hemink Farms, Ltd., and Hemink Management, LLC, had agreed that BCL would
    4
    construct the project and be paid construction costs plus a $200,000 builder’s fee. The
    jury found for BCL against all four defendants on its theories of breach of contract,
    quantum meruit, and promissory estoppel. Additionally, the jury found that BCL and
    Hemink Farms, Ltd., had not reached a settlement agreement that Hemink Farms would
    pay $263,185 and receive a credit of $263,186.77. The jury awarded BCL $193,592.99
    in damages, representing the amount owed after a partial payment and the punch list
    items credited by BCL, on BCL’s contract claim and equitable claims. The jury also
    awarded BCL $72,546.50 in legal fees.           Appellants filed a motion for judgment
    notwithstanding the verdict. The trial court entered judgment on the jury’s verdict. After
    their motion for new trial was overruled by operation of law, appellants brought this
    appeal.
    Analysis
    Accord and Satisfaction
    In their first two issues, appellants contend they established their affirmative
    defense of accord and satisfaction as a matter of law and the jury’s failure to find an
    accord and satisfaction was against the overwhelming weight of the evidence.
    The consequence of a finding of accord and satisfaction is a bar to any action on
    the original obligation. Harris v. Rowe, 
    593 S.W.2d 303
    , 306 (Tex. 1979). The defense
    rests upon a new contract, express or implied, by which parties agree to discharge an
    existing obligation by means of a lesser payment tendered and accepted. Lopez v.
    Munoz, Hockema & Reed, L.L.P., 
    22 S.W.3d 857
    , 863 (Tex. 2000). Appellants, as the
    movants on the defense of accord and satisfaction, were required to establish both (1)
    5
    the existence of a dispute, and (2) an unmistakable communication to BCL that tender of
    a reduced sum was upon the condition that acceptance would satisfy the underlying
    obligation. 
    Id. BCL and
    appellants had to specifically and intentionally agree to the
    discharge of appellants’ existing obligations. 
    Id. At trial,
    Long, Robertson, and Schilderink all testified that there was a dispute
    regarding the two outstanding invoices. Schilderink testified that he told Robertson he
    had already paid too much. Robertson testified that Schilderink told him he would never
    pay them a dime, that he would hire lawyers and string the matter out for years, and that
    someone would be going to jail if Long did not bring him a check. Long testified that he
    went to the April 27 meeting with Schilderink to collect the money he was owed, but he
    was aware that Schilderink felt he had been overcharged. He expected there would be
    some “bartering” over the invoices and that the meeting would be a “battle.” When Long
    arrived at the meeting, Schilderink told him that Long should write a check for $250,000
    to Schilderink. This evidence established the existence of a dispute.
    Appellants contend they also met their burden to establish a specific and
    intentional agreement to discharge Schilderink’s obligation. To show the necessary
    meeting of the minds, “[t]here should be a statement that accompanies the tender of the
    lesser sum, which statement also must be so clear and so explicit and so complete that
    the statement is simply not susceptible of any other interpretation but one of complete
    accord and complete satisfaction.” Pate v. McClain, 
    769 S.W.2d 356
    , 362 (Tex. App.—
    Beaumont 1989, writ denied) (citing Jenkins v. Henry C. Beck Co., 
    449 S.W.2d 454
    , 455
    (Tex. 1969)).
    6
    Appellants rely heavily on the $263,185 check to BCL, which BCL deposited, and
    the attached check stub, which stated a “credit,” dated February 29, 2016, for
    $263,186.77, the remaining balance of the two invoices. Appellants argue that the check
    stub “clearly noted the parties’ agreement.” Schilderink testified that when he gave Long
    the check, he showed him the check stub and said, “See this is what we did, those two
    invoices added up, credit that number so this is the final amount.”             According to
    Schilderink, Long responded with, “That’s okay.”
    However, Schilderink acknowledged that neither he nor Long used the words “full
    payment.” He also acknowledged that he did not write “final payment” or “full payment”
    on the check and that Long did not write “paid” or “paid in full” on the bill. He testified:
    Q: We’ve already talked about that Mr. Long didn’t tell you he would take
    this 263,185.00 as payment in full, right?
    A: He did take it as payment in full.
    Q: He never told you that, did he?
    A: He did not use the words but it says on the invoice with the credit on the
    invoice stub.
    Q: Mr. –
    A: We agreed on – on accepting that number and that is translation for paid
    in full. It – it says the two invoices minus the credit and he okayed that.
    Q: You’re saying the translation is “paid in full” that’s your translation,
    correct?
    A: No, that’s not correct, that is – that is the same as paid in full if it says
    credit and he okayed that and we handshake and that is the same as paid
    in full.
    Schilderink’s testimony that there was an agreement to settle was controverted at
    trial. Long testified that, when Schilderink offered to pay the $197,000 invoice, he told
    7
    Schilderink that the amount was “not even close” to what he needed to pay the
    subcontractors. He asked Schilderink to pay the larger invoice, saying that would “get
    [him] by for now.” When Schilderink refused to pay the invoice, Long then suggested that
    they add up the two invoices and that Schilderink pay half, with Long adding, “I said that
    will get [me] by.” Long testified that when Schilderink brought him the check, he stuck it
    in his pocket. His secretary later deposited the check. He never told Schilderink that the
    partial payment would be considered as payment in full and that he never did anything to
    lead Schilderink to believe that he considered himself paid in full. Long further testified
    that he did not stamp the two outstanding invoices as “paid,” as he had with all the other
    invoices generated during the project. The day after the meeting, Long stopped sending
    people to finish the punch list work because he did not want more work to be done until
    the matter was settled. He testified that he gave Schilderink some time to come to his
    senses, and when he did not hear from him, BCL filed liens on the property.
    Robertson testified similarly.   He said that both he and Long explained to
    Schilderink that subcontractors needed to be paid and that the amount owed to them was
    more than $328,000. When asked directly whether Long offered to take $328,000 as
    payment in full, Robertson answered, “Oh, no.” BCL’s evidence demonstrated that if Long
    accepted the lesser amount of $263,185 as payment in full, BCL would not only give up
    its $200,000 builder’s fee, but would still owe money to the subcontractors who worked
    on the house. The jury also heard testimony from Dean Mason, a mutual acquaintance
    of Schilderink and Long, whom Schilderink had asked to help resolve the situation with
    Long. Although Schilderink testified that he told Mason the parties had settled, Mason
    testified that neither Schilderink nor Long mentioned any settlement to him.
    8
    The evidence offered in support of an accord and satisfaction must demonstrate
    that “both parties agreed the amount paid by the debtor to the creditor fully satisfied the
    entire claim.” Avary v. Bank of Am., N.A., 
    72 S.W.3d 779
    , 788 (Tex. App.—Dallas 2002,
    pet. denied) (emphasis added).      Based on the foregoing, we cannot conclude that
    appellants established the existence of the specific and intentional agreement necessary
    for appellants to prove their affirmative defense of accord and satisfaction as a matter of
    law.
    Appellants maintain that the check and check stub speak for themselves and
    constitute an unmistakable communication that acceptance of the check would result in
    satisfaction of appellants’ obligation.   We disagree.    Appellants cite Case Funding
    Network, L.P. v. Anglo-Dutch Petroleum Int’l, Inc., 
    264 S.W.3d 38
    , 51 (Tex. App.—
    Houston [1st Dist.] 2007, pet. denied), for their argument that where a creditor “obviously
    should understand that the check is tendered in full satisfaction” of the claim, acceptance
    of the check binds the creditor, regardless of an actual understanding. We observe that,
    unlike the present case, Case Funding involved checks that contained unmistakable
    accord and satisfaction language on both the front and back, and were accompanied by
    letters that stated the payment was tendered “in an effort to compromise any dispute,”
    and emphasized, in bold and underlined text, that depositing the checks would constitute
    a release of liability and an accord and satisfaction. 
    Id. The other
    cases cited by
    appellants also involve statements that were clearer and more conspicuous than the
    check stub at issue here. For example, in Pileco, Inc. v. HCI, Inc., 
    735 S.W.2d 561
    , 561
    (Tex. App.—Houston [1st Dist.] 1987, writ ref’d n.r.e.), the check negotiated by the
    creditor included the notation “By signature hereto, endorser acknowledges full, complete
    9
    and final settlement of all claims against payer.” In Hixson v. Cox, 
    633 S.W.2d 330
    , 330-
    32 (Tex. App.—Dallas 1982, writ re’d n.r.e.), the check featured a restrictive endorsement,
    typed on both the front and the back, stating that the check constituted full and final
    payment of the account, and it was mailed with a letter stating that acceptance of the
    check constituted full settlement of the account. In First State Bank v. Knapp, 
    3 S.W.2d 468
    , 469 (Tex. Civ. App.—Amarillo 1928, no writ), the check-writer had written “Payment
    in full of note” and specifically told the bank cashier that the check was given in full
    payment of all sums due. And in Indiana Lumbermen’s Mut. Ins. Co. v. State, 
    1 S.W.3d 264
    , 266 (Tex. App.—Fort Worth 1999, pet. denied), the tendered checks were
    accompanied by a letter explaining that they were tendered “in settlement” of the disputed
    amounts due.
    We do not believe that the “credit” notation on the check stub was so clear, full,
    and explicit that BCL had to understand that it was conditioned on the premise that
    acceptance would constitute the full satisfaction of BCL’s claims. Any inferences to be
    drawn from the check and check stub concerning the parties’ intent to reach an accord
    and satisfaction were factual issues to be resolved by the jury. Richardson v. Allstate
    Tex. Lloyd’s, 
    235 S.W.3d 863
    , 865 (Tex. App.—Dallas 2007, no pet.) (op. on reh’g). The
    jury, which heard evidence of the circumstances surrounding the meeting and the
    purposes the parties intended to accomplish, rejected appellants’ contention that by
    accepting the check, BCL was releasing appellants from their obligations. The evidence
    before the jury supports its refusal to find an accord and satisfaction.
    Accordingly, we conclude that the evidence does not establish accord and
    satisfaction as a matter of law and that the jury’s finding that appellants failed to meet
    10
    their burden to establish the defense is not against the overwhelming weight of the
    evidence. We therefore overrule appellants’ first and second issues on appeal.
    In their third issue, appellants challenge the jury’s answer awarding attorney’s fees
    to BCL, as it was predicated on the breach of a contract that appellants contend was
    resolved by accord and satisfaction. As set forth above, we will not disturb the jury’s
    finding that there was no accord and satisfaction. Therefore, we overrule appellants’ third
    issue.
    Parties to the Contract
    By their fourth issue, appellants assert that the evidence was insufficient to support
    the jury’s finding that an agreement existed between BCL and appellants Schilderink, Van
    Vliet, and Hemink Management for the construction project.1 Appellants do not challenge
    the jury’s finding that an agreement existed between BCL and Hemink Farms.
    Evidence is legally insufficient to support a jury finding when (1) the record
    discloses a complete absence of evidence of a vital fact; (2) the court is barred by rules
    of law or of evidence from giving weight to the only evidence offered to prove a vital fact;
    (3) the evidence offered to prove a vital fact is no more than a mere scintilla; or (4) the
    evidence establishes conclusively the opposite of a vital fact. Uniroyal Goodrich Tire Co.
    v. Martinez, 
    977 S.W.2d 328
    , 334 (Tex. 1998), cert. denied, 
    526 U.S. 1040
    , 
    119 S. Ct. 1336
    , 
    143 L. Ed. 2d 500
    (1999). When we determine whether legally sufficient evidence
    1 Appellants also state that there is legally insufficient evidence to support the jury’s finding of a
    breach of the contract, but their briefing only addresses the existence of a contractual relationship.
    Therefore, we will limit our review to the issue raised by appellants in their briefing. See TEX. R. APP. P.
    47.1, 47.4.
    11
    supports a finding, we must consider evidence favorable to the finding if a reasonable
    factfinder could and disregard evidence contrary to the finding unless a reasonable
    factfinder could not. Cent. Ready Mix Concrete Co. v. Islas, 
    228 S.W.3d 649
    , 651 (Tex.
    2007). The evidence is legally sufficient if it constitutes more than a “scintilla” of evidence
    on which a reasonable juror could find the fact to be true. Rocor Int’l, Inc. v. Nat’l Union
    Fire Ins. Co., 
    77 S.W.3d 253
    , 262 (Tex. 2002).
    For a contract to exist, there must be an offer, acceptance, and consideration.
    Domingo v. Mitchell, 
    257 S.W.3d 34
    , 39 (Tex. App.—Amarillo 2008, pet. denied). The
    existence of an oral contract may be proved by circumstantial or direct evidence. 
    Id. Courts consider
    the communications between the parties and the acts and circumstances
    surrounding those communications when determining the existence of an oral contract.
    
    Id. BCL directs
    us to the following evidence presented at trial regarding whether
    Schilderink and Van Vliet were parties to the contract: when Schilderink was asked
    whether he or Hemink Farms hired BCL for the construction project, he answered that he
    and his wife hired BCL. Schilderink also testified that all payments on the house were
    authorized, and all checks were signed, by him or his wife. He testified that only he or his
    wife could make a decision not to pay. Additionally, BCL points to evidence that both
    Schilderink and Van Vliet exercised decision-making authority about the home’s design
    and materials.
    Considering the evidence in the light most favorable to the jury’s finding and
    indulging every reasonable inference that would support the finding, as we must, we
    12
    conclude that the record reflects more than a scintilla of evidence that an agreement
    existed between BCL and appellants Schilderink and Van Vliet. We overrule appellants’
    fourth issue as to Schilderink and Van Vliet.
    BCL acknowledges that there is little evidence of Hemink Management as a party
    to the contract. The only evidence regarding Hemink Management’s role was evidence
    that Hemink Management is a part owner of Hemink Farms. We conclude that BCL did
    not produce more than a scintilla of evidence establishing the existence of a contract
    between BCL and Hemink Management. Therefore, we sustain appellants’ fourth issue
    as to Hemink Management.
    Equitable Claims
    Appellants’ fifth issue challenges the jury’s findings in favor of BCL on its equitable
    theories of quantum meruit and promissory estoppel. After finding in BCL’s favor on its
    equitable claims, the jury awarded BCL $193,592.99 in damages on both claims, the
    same amount it had awarded on BCL’s contract claim.2
    Quantum meruit is based on an implied agreement to pay for benefits received.
    Heldenfels Bros., Inc. v. City of Corpus Christi, 
    832 S.W.2d 39
    , 41 (Tex. 1992).
    Promissory estoppel prevents a party from insisting upon its strict legal rights under the
    statute of frauds, when enforcing a non-compliant agreement would be necessary to
    2 The final judgment made clear that BCL is entitled to only one recovery of its damages and
    attorney’s fees. As BCL acknowledged in its motion for entry of judgment, the jury awarded BCL the same
    amount under each liability theory. Therefore, BCL was not required to elect from among the three theories
    by the trial court.
    13
    avoid an injustice. “Moore” Burger, Inc. v. Phillips Petro. Co., 
    492 S.W.2d 934
    , 936 (Tex.
    1973).
    First, appellants assert that BCL is not entitled to recover on its equitable theories
    because BCL’s right to any further recovery is precluded by accord and satisfaction.
    Because we have previously concluded that the jury’s refusal to find an accord and
    satisfaction is supported by the evidence, we overrule this point.
    Next, appellants contend that BCL’s equitable theories are inconsistent with and
    unavailable in light of the finding that there was a contract between BCL and Hemink
    Farms for the construction of the residence. BCL concedes that its equitable theories are
    not applicable given the finding of an existing contract. We agree. The right to recover
    under a theory of quantum meruit is independent of any contract. Vortt Expl. Co. v.
    Chevron U.S.A., Inc., 
    787 S.W.2d 942
    , 944 (Tex. 1990). Promissory estoppel is likewise
    unavailable when a contract covers the subject matter of the dispute. Blackstone Med.,
    Inc. v. Phoenix Surgicals, L.L.C., 
    470 S.W.3d 636
    , 655 (Tex. App.—Dallas 2015, no pet.).
    The jury’s finding that an agreement existed between BCL and Hemink Farms is
    not contested on appeal, and we have overruled appellants’ issue challenging the jury’s
    finding as to an agreement between BCL and Schilderink and Van Vliet. BCL is precluded
    from recovering damages, under equitable theories, for work which was the subject of a
    contract. See Iron Mountain Bison Ranch, Inc. v. Easley Trailer Mfg., Inc., 
    42 S.W.3d 149
    , 161 (Tex. App.—Amarillo 2000, no pet.). Accordingly, we sustain appellants’ fifth
    issue.
    14
    Legal Fees
    The jury awarded BCL $69,046.50 in attorney’s fees for preparation and trial, the
    exact amount sought by BCL. In their sixth issue, appellants contend the evidence was
    legally and factually insufficient to support the jury’s award of legal fees.
    BCL’s claim for legal fees included $4,438 in legal assistant fees.3 Appellants’ first
    point under their sixth issue asserts that BCL failed to present legally sufficient evidence
    of each element required for the recovery of legal assistant fees. To recover payment for
    a legal assistant’s time, a party must provide evidence of: (1) the legal assistant’s
    qualifications through education, training, or work experience to perform substantive legal
    work; (2) substantive legal work that was performed under the direction and supervision
    of an attorney; (3) the nature of the legal work that was performed; (4) the hourly rate
    charged for the legal assistant; and (5) the number of hours expended by the legal
    assistant. El Apple I, Ltd. v. Olivas, 
    370 S.W.3d 757
    , 763 (Tex. 2012). Here, appellants
    specifically claim that there was no testimony on the second element for paralegal fees,
    i.e., whether the substantive legal work was performed under the direction and
    supervision of an attorney.
    BCL’s attorney Tim Newsom testified regarding the attorney’s fees BCL had
    incurred. He stated that he had a paralegal, Terri Harrison, work on this case. Newsom
    testified that when Harrison generates her monthly bills, which are based upon her daily
    time entries, he segregates her secretarial time and her paralegal time. He said he
    reviews billing statements internally and makes any necessary corrections before sending
    3Although the evidence showed the amount of legal assistant fees BCL incurred to total $8,876,
    BCL sought only $4,438 in legal assistant fees at trial.
    15
    bills out to clients. Newsom then explained the final bills which were sent to Long,
    showing the date of the work, the timekeeper, the description, the time spent, the rate,
    and the total charge. The billing records submitted in evidence detail the nature of the
    work done by Harrison and reflect instances where Newsom gave instruction to her on
    tasks to be performed and reviewed the work she did. Newsom’s testimony and the billing
    records indicate that Harrison’s work was done under his direction and supervision.
    Considering all the record evidence in the light most favorable to the jury’s verdict and
    indulging every reasonable inference from that evidence in support of the verdict, legally
    sufficient evidence exists to show the legal assistant performed substantive legal work
    under the direction and supervision of an attorney. We therefore overrule this point.
    In their second point under their legal fees issue, appellants claim that the evidence
    only established attorney and legal assistant fees totaling $65,684.50, yet the trial court
    awarded $69,046.50 in fees, which appellants allege incorrectly includes court costs and
    other expenses.
    The testimony given at trial contradicts this argument. Although appellants argue
    that Plaintiff’s Exhibit 73 summarizes the fees sought by BCL, Newsom explained that the
    $65,684.50 in fees shown on Plaintiff’s Exhibit 73 represented attorney’s fees of
    $56,808.50 and paralegal fees of $8,876 charged to BCL as of July 17, 2017. He testified
    that BCL was not seeking to recover the court costs and other expenses shown on Exhibit
    73. He further explained that Plaintiff’s Exhibit 84 was a summary of the billing records
    in evidence showing the legal fees incurred by BCL through the date of his testimony,
    July 20, 2017. That amount included $56,808.50 in attorney’s fees through July 18;
    $10,800 in attorney’s fees incurred during the trial; paralegal fees of $4,438; and a credit
    16
    of $3,000 for a segregated claim. The jury’s award of $69,046.50 corresponds exactly
    with the total amount on Plaintiff’s Exhibit 84.
    We find this evidence sufficient to support the award of attorney’s fees. Appellants’
    sixth issue is overruled.
    Conclusion
    We reverse the trial court’s determination that there was a contract between BCL
    and Hemink Management. We also reverse the judgment in favor of BCL on its claims of
    quantum meruit and promissory estoppel because the existence of a valid contract bars
    those claims. Judgment is rendered that BCL take nothing on its breach of contract claim
    against Hemink Management and take nothing on its equitable claims.             In all other
    respects, the trial court’s judgment is affirmed.
    Judy C. Parker
    Justice