Kenneth G. Martin and Karken Corporation v. Barry Beitler BAB 8, L.L.C. Living Architecture and Construction Management, Inc. And Marley Porter ( 2015 )


Menu:
  •       TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    NO. 03-13-00605-CV
    Kenneth G. Martin and Karken Corporation, Appellants
    v.
    Barry Beitler; BAB 8, L.L.C.; Living Architecture and Construction Management, Inc.;
    and Marley Porter, Appellees
    FROM THE DISTRICT COURT OF BURNET COUNTY, 33RD JUDICIAL DISTRICT
    NO. 34,655, HONORABLE PAUL R. DAVIS, JUDGE PRESIDING
    MEMORANDUM OPINION
    Kenneth G. Martin and Karken Corporation appeal from the trial court’s judgment
    rendered on a jury verdict in a case involving a commercial dispute. The jury found against Martin
    and Karken, except as to Martin’s quantum meruit claim, and in favor of Barry Beitler; Beitler’s
    company, BAB 8, L.L.C.; Marley Porter; and Porter’s company, Living Architecture and
    Construction Management, Inc. (LACM), on their counterclaims. On appeal, Martin and Karken
    challenge the sufficiency of the evidence supporting the jury’s negative findings on their claims and
    its affirmative findings on Beitler’s and Porter’s counterclaims and corresponding damage awards.
    They also allege errors in the court’s charge and its decision to exclude certain evidence. In the
    alternative, they seek judgment to reflect the jury’s award of quantum meruit damages, which the
    trial court omitted from the judgment. For the reasons that follow, we affirm in part and reverse and
    render in part.
    FACTUAL AND PROCEDURAL BACKGROUND
    In late 2006 or early 2007, Daniel J. Robbins approached Martin, a long time resident
    of Horseshoe Bay, seeking to engage Martin as a preconstruction consultant and his company,
    Karken, as general contractor on a retail development project in Horseshoe Bay. Martin eventually
    agreed on the condition that Porter be the architect on the project. Robbins agreed, and Martin began
    work on the project. He subsequently became concerned that he had no written agreement with
    Robbins and Beitler, whom Martin contends Robbins held out as his partner in the project. Martin
    sent Robbins a proposed “Letter of Professional Engagement” (the Letter Agreement) between
    Robbins’s company—The D.J. Robbins Company (Robbins Company)—Martin, and Karken. The
    Letter Agreement provided that the parties agreed to enter into a more formal contract that
    incorporated an American Institute of Architects (AIA) standard form contract structured to pay
    Karken on a “cost plus 15% basis with a Guaranteed Not-to-Exceed Maximum Price” and Martin
    “5% of the Maximum Price out of the first bank draw.” The Letter Agreement listed the duties
    Martin was to perform and included a provision for Robbins Company to pay Martin $10,000 upon
    execution of the agreement. After some delay, in late August 2007, Robbins faxed Martin the Letter
    Agreement, signed by Robbins on behalf of Robbins Company and by Beitler, with one
    change—payment to Martin was to be “on hard costs only.” The Letter Agreement did not define
    the “Maximum Price” or “hard costs.” Within a week, Robbins gave Martin a check for $10,000.
    Martin continued working on the project, performing such duties as seeking approval
    of the property owners’ association, obtaining subcontractors, seeking tenants, and working with
    Horseshoe Bay city officials and community leaders. At Porter’s suggestion, he also met with MST
    2
    Constructors about serving as prime subcontractor. In mid-October 2007, Porter began discussions
    with MST about acting as general contractor “through a specific scope of work.” MST offered to
    perform the work for cost plus 7.5%. Martin called Porter, concerned that Porter was interfering
    with his contract. After Porter assured him there was no need for concern and both Porter and MST
    told Martin that MST would participate only if Martin was still involved in the project, Martin
    continued his work.
    In November 2007, the project was introduced to the Horseshoe Bay community
    through a newspaper article, town hall meeting, and city council meeting. Only a conceptual plan
    was presented, and the evidence is conflicting on whether and to what extent further redesign would
    have been necessary to obtain subsequent city approval. No AIA contract had been negotiated or
    executed, and Martin continued to be concerned that Robbins and Beitler did not intend to honor the
    Letter Agreement. The day after the council meeting, Martin sent Robbins a proposed “Receipt and
    Release,” whereby he would withdraw from the project provided he was paid for work performed.
    Robbins never responded but informed Martin that his and Karken’s fees needed to be reduced.
    Martin refused and stopped work, and Porter offered to step into Martin’s role for a lower fee. A
    series of contentious emails followed that form the basis of Porter’s and Beitler’s counterclaims.
    Martin accused them of undermining him, engaged in name calling, and accused Porter of certain
    dishonest practices concerning his fees. Martin copied the emails to various community and city
    leaders. Porter, Robbins, and Beitler began to redesign the project, but there is nothing in the record
    to indicate they ever presented another plan to the city for approval.
    3
    Martin and Karken sued Beitler, Robbins, and Robbins’s Company for breach and
    repudiation of contract;1 Porter for tortious interference with contract; and Robbins, Porter, and
    LACM for impossibility of performance of contract.2 In the alternative, they sought quantum meruit
    damages. Porter filed a counterclaim for defamation, and Porter and Beitler filed counterclaims for
    tortious interference with prospective business relationships. Following a week-long trial, the jury
    found against Martin and Karken on all but Martin’s quantum meruit claim, for which it awarded
    him $74,600, and in favor of Beitler and Porter on their counterclaims, for which it awarded damages
    totaling $575,000. The trial court rendered judgment on the verdict but omitted the quantum meruit
    damage award to Martin. Martin and Karken filed a motion for judgment notwithstanding the
    verdict, motion to modify judgment, and alternatively, motion for new trial. The motion was
    overruled by operation of law. This appeal followed.
    DISCUSSION
    Porter’s Defamation Counterclaim
    In issue one, Martin and Karken challenge the legal sufficiency of the evidence
    supporting the jury’s findings on Porter’s counterclaim for defamation and damage awards. When
    1
    Martin’s and Karken’s claims against Robbins Company were severed prior to trial.
    Robbins did not participate in the trial, and Martin’s and Karken’s claims against him were severed
    post-judgment. Although the actions of Robbins and Robbins Company are relevant to the factual
    background and issues in this case, they are not parties to this appeal.
    2
    Although Martin and Karken named BAB 8 as a defendant, they asserted no allegations
    against it. The trial court submitted no issues as to BAB 8 and rendered a take-nothing judgment
    against Martin and Karken on their claims against it, which Martin and Karken do not appeal.
    Although LACM did not assert a counterclaim, the trial court submitted the liability and damages
    issues on tortious interference as to Porter “and/or” LACM. Martin and Karken refer only to Porter
    in their briefing of that issue.
    4
    the appellant challenges the legal sufficiency of the evidence supporting an adverse finding on which
    he did not have the burden of proof at trial, he must demonstrate that there is no evidence to support
    the adverse finding. Croucher v. Croucher, 
    660 S.W.2d 55
    , 58 (Tex. 1983); Texas Dep’t of Pub.
    Safety v. Alexander, 
    300 S.W.3d 62
    , 72 (Tex. App.—Austin 2009, pet. denied). We review the
    evidence in the light most favorable to the verdict, crediting favorable evidence if a reasonable fact
    finder could, and disregarding contrary evidence unless a reasonable fact finder could not. City of
    Keller v. Wilson, 
    168 S.W.3d 802
    , 807 (Tex. 2005). “Our traditional legal sufficiency—or ‘no
    evidence’—standard of review upholds a finding supported by ‘[a]nything more than a scintilla of
    evidence.’” In re K.M.L., 
    443 S.W.3d 101
    , 112 (Tex. 2014) (quoting Formosa Plastics Corp. U.S.A.
    v. Presidio Eng’rs & Contractors, Inc., 
    960 S.W.2d 41
    , 48 (Tex. 1998)). More than a scintilla exists
    when the evidence would enable reasonable and fair-minded people to reach different conclusions.
    Burbage v. Burbage, 
    447 S.W.3d 249
    , 259 (Tex. 2014). “However, if the evidence is so weak that
    it only creates a mere surmise or suspicion of its existence, it is regarded as no evidence.” Waste
    Mgmt. of Tex., Inc. v. Texas Disposal Sys. Landfill, Inc., 
    434 S.W.3d 142
    , 156 (Tex. 2014).
    The jury found that certain email statements concerning Porter made by Martin to
    Horseshoe Bay city and community leaders were defamatory and awarded Porter $50,000 for past
    injury to reputation and $200,000 for past mental anguish. Martin and Karken contend that the
    statements were neither defamatory per se nor defamatory per quod as a matter of law and that there
    was no evidence to support the jury’s damage award. Assuming without deciding that the statements
    were defamatory, we conclude that there is no evidence to support the award of damages.
    5
    Question 31 instructed the jury that if they found that Martin had published certain
    statements concerning Porter, that the statements were defamatory and false, and that Martin knew
    or should had known in the exercise of ordinary care that they were false, then they were to
    determine “[w]hat sum of money, if any, if paid now in cash, would fairly and reasonably
    compensate Marley Porter for his injuries, if any, proximately caused by Kenneth G. Martin’s
    defamatory statements.” Question 3 further instructed the jury that if the statements were “deemed
    to be defamatory per se,” [they] must award at least nominal damages for injury to reputation in the
    past.” Question 3 then asked the jury to determine damages for past and future injury to reputation
    and past and future mental anguish. Martin and Karken did not object to the submission of question
    31. When a party fails to object, “it is the court’s charge, not some other unidentified law, that
    measures the sufficiency of the evidence.” Osterberg v. Peca, 
    12 S.W.3d 31
    , 55 (Tex. 2000).
    Accordingly, we will evaluate the award of damages based on question 31.
    “Texas law presumes that defamatory per se statements cause reputational harm and
    entitle a plaintiff to general damages such as loss of reputation and mental anguish.” 
    Burbage, 447 S.W.3d at 259
    . However, this presumption yields only nominal damages, which the Supreme
    Court has defined as a “trifling sum,” such as $1–100, and which are awarded when there is no proof
    of serious harm. Id.; Hancock v. Variyam, 
    400 S.W.3d 59
    , 65 (Tex. 2013); MBM Fin. Corp.
    v. Woodlands Operating Co., 
    292 S.W.3d 660
    , 665 (Tex. 2009). “Beyond nominal damages, we
    review presumed damages for evidentiary support[, including] whether any evidence supports the
    amount of jury damages.” 
    Burbage, 447 S.W.3d at 259
    (citing 
    Hancock, 400 S.W.3d at 66
    ; Bentley
    v. Bunton, 
    94 S.W.3d 561
    , 606 (Tex. 2002)). Because the jury awarded substantial damages,
    6
    whether we assume for the sake of argument that the statements were defamatory per se or
    defamatory per quod, there must be legally sufficient evidence to support both the jury’s findings of
    damage for reputational injury and mental anguish and the amount of the jury’s compensatory
    damage awards. Id.; Waste 
    Mgmt., 434 S.W.3d at 160
    (evidence must be legally sufficient as to both
    existence and amount of non-economic damages such as damages for loss of reputation); see
    
    Hancock, 400 S.W.3d at 68
    (“Having concluded that Hancock’s statements were not defamatory per
    se, we need not decide whether the statements were defamatory because—even if they were as a
    matter of law—there is no evidence of actual damages.”).
    The jury awarded Porter $50,000 in damages for past injury to reputation. However,
    we agree with Martin and Karken that the record contains no evidence that Porter’s reputation was
    actually damaged. When asked if the emails made him feel that his reputation was being attacked,
    Porter responded that he felt like his “soul was being attacked.” When asked if he felt the emails
    were an attack on his personal and professional credibility, he responded that he thought “it was
    screaming from a very sad friend.” Although Porter testified that he “believe[d]” the comments
    damaged his reputation in Horseshoe Bay, he did not show any actual loss of reputation or provide
    any evidence that any of the recipients of the email statements actually believed them. Concerning
    the one recipient Porter mentioned in his testimony, Porter stated only that he did not know if the
    statements led the recipient to refuse to refer business to him and added that Porter’s business did
    not “parallel” that of the recipient. Porter also testified that he could not estimate the number of jobs
    he did not receive and there was no way to calculate the potential loss of business from the emails.
    7
    Although it is impossible to calculate the exact amount of injury to reputation, which
    requires that the jury be given a measure of discretion in finding damages, there must be some
    evidence to justify the amount awarded. 
    Bentley, 94 S.W.3d at 606
    . A “‘private defamation plaintiff
    . . . may recover only such damages as are sufficient to compensate him for actual injury.’” 
    Burbage, 447 S.W.3d at 259
    (quoting Gertz v. Robert Welch, Inc., 
    418 U.S. 323
    , 350 (1974)). The jury was
    charged with finding an amount that would “fairly and reasonably compensate” Porter, not to “pick
    a number and put it in the blank.” 
    Bentley, 94 S.W.3d at 606
    .
    Here, there was no evidence of injury to reputation, see 
    Burbage, 447 S.W.3d at 262
    –63 (evidence of community awareness of defamatory statements and testimony that effect on
    reputation was unknown was no evidence that anyone believed statements and no evidence of actual
    loss of reputation); 
    Hancock, 400 S.W.3d at 71
    (noting that “loss of reputation for defamation is
    concerned with recipient believing statement,” and holding that where plaintiff offered no evidence
    that recipient of allegedly defamatory letter believed defendant’s statements, plaintiff offered no
    evidence of injury to reputation), and no evidence to justify the amount of damages the jury awarded
    for loss of reputation, see 
    Burbage, 447 S.W.3d at 261
    (citing “ballpark estimate” of business’s value
    and speculative evidence of actual loss of value in concluding there was no evidence to support
    damage award); Waste 
    Mgmt., 434 S.W.3d at 160
    –61 (corporate executive’s estimate of value of
    company’s reputation and exhibits showing lost profits—which are not sort of general damages that
    necessarily flow from defamatory publication—and showing decline in business in area affected by
    publication relative to overall business constituted no evidence of actual damages for injury to
    reputation). In the absence of any evidence that anyone believed the email statements or that they
    8
    caused actual injury to Porter’s reputation in any amount, we conclude that the evidence is legally
    insufficient to support the jury’s award of $50,000 damages for injury to Porter’s reputation.
    The jury also awarded Porter $200,000 damages for past mental anguish. As with
    injury to reputation, beyond nominal damages, there must be evidence of both the existence of
    compensable mental anguish and evidence to justify the amount awarded. 
    Burbage, 447 S.W.3d at 259
    ; 
    Hancock, 400 S.W.3d at 68
    (citing 
    Bentley, 94 S.W.3d at 606
    ). Mental anguish is “‘only
    compensable if it causes a ‘substantial disruption in . . . daily routine’ or ‘a high degree of mental
    pain and distress.’” 
    Hancock, 400 S.W.3d at 68
    (quoting Parkway Co. v. Woodruff, 
    901 S.W.2d 434
    ,
    444 (Tex. 1995)). “Even when an occurrence is of the type for which mental anguish damages are
    recoverable, evidence of the nature, duration, and severity of the mental anguish is required.” 
    Id. (citing Service
    Corp. Int’l v. Guerra, 
    348 S.W.3d 221
    , 231 (Tex. 2011)). Mental anguish damages
    must constitute compensation for actual injuries and not a “disguised disapproval of the defendant.”
    
    Bentley, 94 S.W.3d at 605
    .
    The Supreme Court has held that evidence a person experienced insomnia, frustration,
    and agony is not legally sufficient to support an award for mental anguish, see 
    Guerra, 348 S.W.3d at 232
    , and that evidence the plaintiff was embarrassed, distracted at home and at work, and stressed
    did not reflect substantial disruption in daily routine or a high degree of mental pain and distress so
    as to support an award for mental anguish, see 
    Hancock, 400 S.W.3d at 69
    –70. On the other hand,
    evidence that a plaintiff sought medical treatment for anxiety and depression and experienced
    headaches, stomach problems, and sleeplessness has been held to be some evidence of mental
    anguish. See 
    Guerra, 348 S.W.3d at 233
    . And evidence that a judge accused of corruption
    9
    experienced embarrassment in the community where he spent almost all of his life, was distressed,
    lost sleep, and according to his friends’ testimony, was depressed, suffered a major change in
    demeanor, and would never be the same, along with evidence that his children were distressed and
    that everywhere he went people would say they had heard he had been called corrupt has been held
    evidence of mental anguish. See 
    Bentley, 94 S.W.3d at 576
    , 606–07.
    Porter did not offer any evidence that he suffered mental anguish. He did not testify
    that he had suffered any physical pain or stress or any disruption. He stated only that in response to
    the email statements, he felt, “attacked,” “hurt,” “shocked,” “sadness,” and “despair” and that when
    he read Martin’s accusation of tortious interference, his “heart started racing,” he thought “[Martin’s]
    going to sue us,” and felt “threatened” but “optimistic it would never come to that.” This testimony
    does not reflect a substantial disruption in daily routine or a high degree of mental pain and distress.
    See 
    Hancock, 400 S.W.3d at 70
    (citing 
    Guerra, 348 S.W.3d at 232
    ). Porter did not require medical
    attention, claim to suffer any disruption in his home or professional life, “elaborate on the impact
    of anxiety or depression on his life,” or offer any witness to “corroborate an outward manifestation
    of the mental anguish [he] allegedly experienced.” See id. (citing 
    Guerra, 348 S.W.3d at 232
    –33,
    
    Bentley, 94 S.W.3d at 606
    –07). We conclude that there is no evidence of the existence of
    compensable mental anguish and that the evidence is therefore legally insufficient to support the
    jury’s compensatory damage award to Porter for mental anguish. See 
    id. at 68,
    70. We sustain
    Martin’s and Karken’s first issue.3
    3
    Because Martin’s and Karken’s legal sufficiency argument is dispositive of this issue, we
    do not reach their alternative factual sufficiency argument.
    10
    Tortious Interference with Prospective Business Relations
    In their second issue, Martin and Karken challenge the legal sufficiency of the
    evidence supporting the jury’s findings on Porter’s and Beitler’s counterclaims for tortious
    interference with business relations and corresponding damage awards. These counterclaims were
    based on Martin’s allegedly defamatory statements. The jury found that Martin intentionally
    interfered with Porter’s and/or LACM’s potential business relationships and awarded $150,000 in
    damages.    The jury further found that Martin intentionally interfered with other business
    relationships that would be necessary for Beitler to develop the project and awarded $174,699.50 for
    costs to redesign the project. Assuming without deciding that Martin’s emails were defamatory and
    that there was evidence to support a finding of tortious interference, we conclude that the evidence
    was legally insufficient to support the jury’s damage awards to Porter and Beitler.
    The jury awarded Porter $150,000 in past lost profits. The rule concerning adequate
    evidence of lost profit damages is well established:
    Recovery for lost profits does not require that the loss be susceptible of exact
    calculation. However, the injured party must do more than show that they suffered
    some lost profits. The amount of the loss must be shown by competent evidence with
    reasonable certainty. What constitutes reasonably certain evidence of lost profits is
    a fact intensive determination. As a minimum, opinions or estimates of lost profits
    must be based on objective facts, figures, or data from which the amount of lost
    profits can be ascertained. Although supporting documentation may affect the weight
    of the evidence, it is not necessary to produce in court the documents supporting the
    opinions or estimates.
    ERI Consulting Engr’s, Inc. v. Swinnea, 
    318 S.W.3d 867
    , 876 (Tex. 2010) (quoting Holt Atherton
    Indus., Inc. v. Heine, 
    835 S.W.2d 80
    , 84 (Tex. 1992)). In ERI Consulting, the Supreme Court held
    11
    that testimony by a co-owner of the company concerning its profit margin and detailed invoices
    showing a substantial drop in revenue over the relevant period constituted legally adequate evidence.
    
    Id. at 876–77.
    In Holt Atherton, the plaintiff testified that he had suffered $200,200 in lost 
    income. 835 S.W.2d at 84
    . The Supreme Court concluded that testimony was legally insufficient because
    it did not provide any indication of how the plaintiff had determined what his lost profits were. 
    Id. The Supreme
    Court also held that the bare assertion that contracts were lost—absent specification
    of which contracts were lost, how many were lost, how much profit would have come from the lost
    contracts, and who would have awarded the contracts—did not demonstrate a reasonably certain
    objective determination of lost profits. 
    Id. at 85
    (“Recovery of lost profits must be predicated on one
    complete calculation.”).
    Here, Porter offered no evidence that he lost any profits. He did not identify any lost
    contracts and stated only that Martin’s email comments “did affect business for awhile, but it’s come
    back.” He did not testify concerning his profit margin or loss of revenue at all, much less testify to
    any specific amount or offer any documentary proof. Nor did he offer any facts, figures, or data on
    which the jury could calculate any award of lost profits. When asked about providing some
    calculable number of jobs or money lost as a result of Martin’s emails, he stated only that “it’s
    impossible” to estimate the number of jobs that he simply did not receive. We conclude that the
    evidence does not provide a reasonable basis for determining Porter’s lost profits and is therefore
    legally insufficient to support the jury’s damage award. See ERI 
    Consulting, 318 S.W.3d at 876
    ;
    Holt 
    Atherton, 835 S.W.2d at 84
    –86.
    12
    The jury awarded Beitler $174,699.50 as reasonable and necessary expenses to
    redesign the project. Beitler offered evidence that Martin’s plans for the project, in particular its
    overall size and the dimensions of the parking spaces, did not meet city requirements and
    necessitated redesign. We conclude that there is no evidence to support the jury’s damage award to
    Beitler. In support of his damage claim, Beitler relied on an exhibit listing fees paid to Porter for
    project design. The exhibit covered a period of time both before and after Martin ceased work on
    the project and reflects fees of $349,339. However, the exhibit does not indicate what portion of the
    fees was attributable to redesign, and the only testimony on this issue was Beitler’s affirmative
    answer to his attorney’s question that “part of that $349,339 . . . would be attributable to [redesign].”
    Although Beitler’s attorney in closing argument offered the figure of $174,699.50—which the jury
    apparently adopted—counsel’s argument is not evidence. Elkins v. Stotts-Brown, 
    103 S.W.3d 664
    ,
    669 (Tex. App.—Dallas 2003, no pet.). Accordingly, we conclude that the evidence was legally
    insufficient to support the jury’s award of damages in that amount. We sustain Martin’s and
    Karken’s second issue.4
    Jury Charge
    In their third issue, Martin and Karken complain that the trial court committed
    harmful error in its jury charge as to their claims. Specifically, they contend that the trial court erred
    in improperly conditioning the breach of contract questions on questions concerning the parties’
    intent to be bound by the Letter Agreement and in refusing to submit their fraud claims. However,
    4
    As with their first issue, because Martin’s and Karken’s legal sufficiency argument is
    dispositive of this issue, we do not reach their alternative factual sufficiency argument.
    13
    the record reflects that Martin and Karken failed to object to the charge on these grounds prior to
    submission to the jury and have therefore waived these complaints on appeal. See 
    Burbage, 447 S.W.3d at 256
    (discussing preservation of jury charge error). Rule 272 requires that objections
    be presented to the court before the charge is read to the jury. See Tex. R. Civ. P. 272. In addition,
    Rule 279 provides that on appeal, “all independent grounds of recovery or of defense not
    conclusively established under the evidence and no element of which is submitted or requested are
    waived.” See Tex. R. Civ. P. 279.
    Martin and Karken contend that the trial court was on notice from the pleadings and
    arguments that one of their theories of recovery was fraud and “refused to submit a fraud question.”
    Similarly, they argue that the trial court was aware that they had asserted in summary judgment
    briefing that the issue of whether there was a binding contract should be decided by the court, thus
    preserving their complaint that the trial court improperly submitted their contract claims. However,
    although Martin and Karken pleaded a cause of action for fraud, the reporter’s record contains no
    reference to fraud during trial other than in the opening statement of Martin and Karken’s counsel,
    which, as we have already observed, does not constitute evidence to support a jury question. See
    
    Elkins, 103 S.W.3d at 669
    . Further, the record reflects that while Martin and Karken objected to
    certain jury questions at the charge conference, they did not challenge the breach or repudiation of
    contract questions or request that their fraud claims be submitted to the jury or object to their
    omission from the charge before the charge was read to the jury. On this record, we cannot say that
    the trial court had the opportunity to remedy the alleged charge errors. Consequently, Martin and
    Karken have waived these complaints on appeal. See Tex. R. Civ. P. 272, 274, 279; Tex. R. App.
    
    14 P. 33
    .1; 
    Burbage, 447 S.W.3d at 256
    ; Cruz v. Andrews Restoration, Inc., 
    364 S.W.3d 817
    , 831 (Tex.
    2012) (holding party could complain on appeal only if it made trial court aware, timely and plainly,
    of purported problem and obtained a ruling). We overrule Martin and Karken’s third issue.
    Exclusion of Evidence
    In their fourth issue, Martin and Karken argue that the trial court committed harmful
    error in excluding from evidence a letter they contend Beitler sent to Fred Barrington, the owner of
    the land Beitler ultimately purchased to build the project. We review a trial court’s decision to admit
    or exclude evidence for an abuse of discretion. In re J.P.B., 
    180 S.W.3d 570
    , 575 (Tex. 2005) (per
    curiam). A trial court abuses its discretion when it acts without regard to any guiding rules or
    principles. Downer v. Aquamarine Operators, Inc., 
    701 S.W.2d 238
    , 241– 42 (Tex. 1985). We must
    uphold a trial court’s evidentiary ruling if there is any legitimate basis in the record to support it.
    Owens-Corning Fiberglas Corp. v. Malone, 
    972 S.W.2d 35
    , 43 (Tex. 1998).
    The letter, written on the letterhead of one of Beitler’s companies, stated that Beitler
    and Robbins were partners. Although the letter was purportedly written and signed by Beitler, the
    “signature” was typed, not handwritten. Martin offered the letter, and the trial court conducted an
    evidentiary hearing. Martin testified that he received it from Barrington and that it was produced
    from Karken’s business records. Beitler testified that he saw the letter for the first time at his
    deposition, did not write it, and did not authorize anyone to write it and that Robbins was never his
    partner on this project. He also testified that everyone in his building had access to his copy room
    where his letterhead was kept and that he presumed Robbins had written the letter and “signed”
    his name.
    15
    Texas Rule of Evidence 901(a) establishes the authentication requirements for the
    admissibility of evidence.       “[A]uthentication or identification as a condition precedent to
    admissibility is satisfied by evidence sufficient to support a finding that the matter in question is
    what its proponent claims.” Tex. R. Evid. 901(a). This requirement can be satisfied by testimony
    of a witness with knowledge that the matter is what it is claimed to be. Tex. R. Evid. 901(b)(1);
    Good v. Baker, 
    339 S.W.3d 260
    , 273 (Tex. App.—Texarkana 2011, pet. denied). Beitler offered
    uncontroverted testimony that he did not write or authorize the letter. He also testified that he did
    not sign it, and the letter on its face contained only a typed “signature.” Martin testified that he
    received the letter from Barrington. He did not claim to have received the letter directly from Beitler
    or have seen Beitler write it, and he testified that he did not ever discuss it with Beitler. Thus, Martin
    had no firsthand knowledge that the letter was what he claimed it to be.
    Finally, although Martin testified the letter was a Karken business record, he also
    testified that he “never realized it was a forgery until later,” essentially admitting that Beitler did not
    author the letter. “Simply put, [Martin] failed to sufficiently link the exhibit[] to [its] purported
    author.” See Tex. R. Evid. 901(a); Martinez v. AA Foundries, Inc., No. 04-11-00879-CV, 2013 Tex.
    App. LEXIS 789, at *14. (Tex. App.—San Antonio Jan. 30, 2013, no pet.) (mem. op.) (citing Tienda
    v. State, 
    358 S.W.3d 633
    , 638 (Tex. Crim. App. 2012) (fact that email on its face purports to come
    from certain person’s email address, without more, is typically insufficient to support finding of
    authenticity)). Faced with this evidence, we cannot conclude that the trial court abused its discretion
    in excluding the letter. See In re 
    J.P.B., 180 S.W.3d at 575
    ; Martinez, 2013 Tex. App. LEXIS 789,
    at *14. We overrule Martin and Karken’s fourth issue.
    16
    Martin’s and Karken’s Claims
    In their fifth issue, Martin and Karken first argue that the findings on their contract
    claims are against the great weight and preponderance of the evidence. Although Martin and Karken
    challenge the factual sufficiency of the evidence supporting the jury’s negative findings on their
    claims, their arguments are premised on their contention that the Letter Agreement contained all
    essential terms and was a binding contract. Beitler contends the Letter Agreement was merely an
    “agreement to agree” that was missing essential terms, including definitions of “hard costs” and
    “Maximum Price,” terms which would have been agreed to in the AIA contract that was never
    negotiated or executed. Whether an agreement has all the essential terms to be legally enforceable
    is a question of law for the court, and whether a term is essential is determined on a case-by-case
    basis. T. O. Stanley Boot Co. v. Bank of El Paso, 
    847 S.W.2d 218
    , 221 (Tex. 1992); America’s
    Favorite Chicken Co. v. Samaras, 
    929 S.W.2d 617
    , 625 (Tex. App.—San Antonio 1996,
    writ denied). We agree with Beitler’s construction of the Letter Agreement as merely an agreement
    to agree.
    Generally, a contract is legally binding only if its terms are sufficiently definite to
    enable a court to understand the parties’ obligations. Fort Worth Indep. Sch. Dist. v. City of Fort
    Worth, 
    22 S.W.3d 831
    , 846 (Tex. 2000). If an alleged agreement is so indefinite as to make it
    impossible for a court to fix the legal obligations and liabilities of the parties, it cannot constitute an
    enforceable contract. University Nat’l Bank v. Ernst & Whinney, 
    773 S.W.2d 707
    , 710 (Tex.
    App.—San Antonio 1989, no writ). A lack of definiteness in an agreement may concern various
    elements, including time of performance, price to be paid, work to be done, or service to be rendered.
    17
    Gannon v. Baker, 
    830 S.W.2d 706
    , 709 (Tex. App.—Houston [1st Dist.] 1992, writ denied); Terrell
    v. Nelson Puett Mortg. Co., 
    511 S.W.2d 366
    , 369 (Tex. Civ. App.—Austin 1974, writ ref’d n.r.e.).
    Although the parties may leave some terms for future negotiation, the essential terms of the contract
    must be agreed on before a court can enforce it. T. O. Stanley Boot 
    Co., 847 S.W.2d at 221
    ;
    Cleveland Reg’l Med. Ctr., L.P. v. Celtic Props., L.C., 
    323 S.W.3d 322
    , 334 (Tex. App.—Beaumont
    2010, pet. denied). “[A]n agreement to make a future contract is enforceable only if it is ‘specific
    as to all essential terms, and no terms of the proposed agreement may be left to future negotiations.’”
    Fort Worth Indep. Sch. 
    Dist., 22 S.W.3d at 846
    (quoting Foster v. Wagner, 
    343 S.W.2d 914
    , 920–21
    (Tex. Civ. App.—El Paso 1961, writ ref’d n.r.e.)). It is well settled that when an agreement leaves
    material matters open for future adjustment and agreement that never occur, it is not binding upon
    the parties and constitutes merely an agreement to agree. Id.; see Oakrock Exploration Co. v. Killam,
    
    87 S.W.3d 685
    , 690 (Tex. App.—San Antonio 2002, pet. denied).
    We conclude that the Letter Agreement lacks essential terms. Although it specifies
    percentages for Martin’s and Karken’s fees, it does not specify what constitutes “hard costs,” on
    which Martin’s percentage was to be based, or state the “Maximum Price,” by which both
    percentages were limited. Instead, these terms were left open for future negotiation, and the Letter
    Agreement expressly provides that the parties would enter into a formal AIA form contract —which
    the evidence shows would have contained these essential and numerous other to-be-negotiated terms,
    but which was never executed. It is inescapable, then, that the fee payments would be determined
    by a formula based on numbers yet to be arrived at and agreement that never occurred.
    Consequently, we conclude that because the Letter Agreement does not sufficiently fix the terms to
    18
    enable a court to determine what the parties agreed Martin and Karken were to be paid for their
    consulting and construction services and because it left essential terms for future negotiation, it fails
    for indefiniteness and is an unenforceable agreement to agree as a matter of law.5 See Fort Worth
    Indep. Sch. 
    Dist., 22 S.W.3d at 847
    (where letter agreement for future contract did not include
    amount or percentage of telephone company’s payment to city to be apportioned to school district,
    it lacked essential term and was unenforceable); Fiduciary Fin. Servs. of the Sw., Inc. v. Corilant
    Fin., LLC, 
    376 S.W.3d 253
    , 258 (Tex. App.—Dallas 2012, pet. denied) (letter of intent that
    expressly stated definitive agreement would be drafted to memorialize terms and conditions
    of agreement between parties and left material terms for future adjustment and negotiation
    failed for indefiniteness and was not enforceable as matter of law); Playoff Corp. v. Blackwell,
    
    300 S.W.3d 451
    , 457–58 (Tex. App.—Fort Worth 2009, pet. denied) (where parties agreed to term
    “fair market value” but left agreement as to how market value was to be determined for future
    5
    Martin and Karken rely on David J. Sacks, P.C. v. Haden in arguing that the absence of a
    fixed total price for services does not indicate a failure of the parties to reach a meeting of the minds
    with regard to essential terms. See 
    266 S.W.3d 447
    , 450 (Tex. 2008) (per curiam). In Sacks, which
    involved an attorney-client fee agreement, the parties agreed to an hourly rate but did not specify an
    exact total price to be paid or set a cap on fees. 
    Id. at 448.
    After performing legal work for Haden,
    Sacks sought to recover the fees incurred. Citing the rule that when parties who have done
    everything else necessary to make a binding agreement fail to specify price, courts presume a
    reasonable price was intended, the Supreme Court concluded that the specified hourly rates made
    the agreement explicit as to the manner to be used in determining the price and confirmed that the
    charges would be reasonable. Here, the parties had not “done everything else necessary” besides
    state a total payment amount to make a binding agreement; they agreed to a minimal number of
    terms and expressly agreed to enter into a detailed AIA contract that would have defined essential
    terms necessary to determine the price. Further, the evidence showed that unlike Sacks, neither
    Martin nor Karken fully performed the contemplated services. We do not find Sacks, where the total
    price of an open-ended hourly fee agreement was dependent only on the number of hours ultimately
    required and where the plaintiff fully performed, controlling on these facts.
    19
    negotiations that never occurred, agreement lacked essential term and failed for indefiniteness as
    matter of law); Ski River Dev., Inc. v. McCalla, 
    167 S.W.3d 121
    , 134 (Tex. App.—Waco 2005, pet.
    denied) (provisions requiring future negotiation on certain terms, including when and by what
    method “market value” was to be determined, suggested parties agreed only to make future contract);
    COC Servs., Ltd. v. CompUSA, Inc., 
    150 S.W.3d 654
    , 664–65 (Tex. App.—Dallas 2004, pet. denied)
    (franchise agreement that failed to state minimum required sales volume—which set price
    and payment terms and which was to be determined by parties—lacked essential term
    and was unenforceable as matter of law); DKH Homes, LP v. Kilgo, No. 03-10-00656-CV,
    2011 Tex. App. LEXIS 3655, at *8–10 (Tex. App.—Austin May 11, 2011, no pet.) (mem. op.)
    (agreement for construction of home that did not include size or price of house or time for
    completion lacked essential terms and was merely unenforceable agreement to agree). We overrule
    Martin’s and Karken’s fifth issue as to their contract claims.6
    Also in their fifth issue, Martin and Karken challenge the factual sufficiency of the
    evidence supporting the jury’s negative finding on their claim against Porter and LACM for tortious
    interference with his contract to perform services on the project. To prove tortious interference with
    an existing contract, a plaintiff must first establish the existence of a valid and enforceable contract
    subject to interference. Powell Indus., Inc. v. Allen, 
    985 S.W.2d 455
    , 456 (Tex. 1998) (per curiam);
    Khan v. GBAK Props., Inc., 
    371 S.W.3d 347
    , 358 (Tex. App.—Houston [1st Dist.] 2012, no pet.).
    6
    Because our determination that the Letter Agreement lacked essential terms is dispositive
    as to Martin’s and Karken’s contract claims, we do not reach their factual sufficiency arguments
    concerning those claims, including their contention that Robbins and Beitler were partners on the
    project, which we address in our discussion of issue six.
    20
    Having concluded that the Letter Agreement was an unenforceable agreement to agree as a matter
    of law, we further conclude that Martin’s and Karken’s claim for tortious interference with that
    agreement also fails as a matter of law. See WTG Gas Processing, L.P. v. ConocoPhillips Co.,
    
    309 S.W.3d 635
    , 653 (Tex. App.—Houston [14th Dist.] 2010, pet. denied) (“Because we have
    concluded there was no contract, we agree that, as a matter of law, [appellee] is not liable for tortious
    interference.”); Texas Oil Co. v. Tenneco Inc., 
    917 S.W.2d 826
    , 830–31 (Tex. App.—Houston
    [14th Dist.] 1994), rev’d on other grounds sub nom. Morgan Stanley & Co. v. Texas Oil Co.,
    
    958 S.W.2d 178
    (Tex. 1997) (holding that letter agreement lacking essential terms was agreement
    to agree and summary judgment on claim for tortious interference was proper); Odem v. Deloitte
    & Touche, LLP, No. 04-09-00747-CV, 2011 Tex. App. LEXIS 731, at *21–22 (Tex. App.—San
    Antonio Feb. 2, 2011, pet. denied) (mem. op.) (where defendant presented summary judgment
    21
    establishing absence of contract as matter of law, trial court did not err in granting summary
    judgment on claim for tortious interference with contract).7 We overrule Martin’s and Karken’s
    fifth issue.
    Quantum Meruit
    In their sixth and final issue, Martin and Karken request, in the alternative to their
    request for a new trial on their other issues, that this Court render judgment reflecting the quantum
    meruit damages the jury awarded to Martin. The jury found that Martin had performed compensable
    work for “The D.J. Robbins Company and/or Barry Beitler” and awarded $74,600 in damages.
    Beitler argues, among other things, that whatever compensable work was done was performed by
    7
    Martin and Karken rely on Clements v. Withers, 
    437 S.W.2d 818
    (Tex. 1969) for their
    contention that unenforceability of a contract is no defense to an action for tortious interference with
    its performance. Clements involved a written commission agreement between a landowner and a
    real estate broker that lacked an adequate property description under the predecessor to the Texas
    Real Estate License Act (RELA) and violated the general statute of frauds. 
    Id. at 820.
    Thus, unlike
    this case, there was an existing contract, but it was unenforceable for lack of statutory compliance.
    
    Id. As the
    Supreme Court explained in Trammel Crow Co. No. 60 v. Harkinson, 
    944 S.W.2d 631
    ,
    635 (Tex. 1997), there is a “subtle but critical . . . distinction” between a “technical deficiency in a
    writing” and the absence of a written contract.
    In Harkinson, the Supreme Court held that because there was no written commission
    agreement, as required by RELA, the tortious interference claims were barred, instructing that
    Clements should be limited to its facts. 
    Id. Here, where
    there was merely an agreement to agree,
    there was no contract on which to base a claim for tortious interference. See WTG Gas Processing,
    L.P. v. ConocoPhillips Co., 
    309 S.W.3d 635
    , 652–53 (Tex. App.—Houston [14th Dist.] 2010, pet.
    denied) (distinguishing between contract that was unenforceable under statute of frauds and no
    contract in context of tortious interference claim); Superior Phones, Ltd. v. Cherokee Commc’ns.,
    Inc., 
    964 S.W.2d 325
    , 331 (Tex. App.—Corpus Christi 1998, pet. denied) (holding that Clements
    reasoning does not apply where there is no contract). Clements does not inform our decision here.
    22
    Martin at the behest of Robbins for Robbins Company, not at the request of or for Beitler and that
    any assessment of quantum meruit damages should therefore not be against Beitler.8
    The elements of a quantum meruit claim include proof that:
    1) valuable services were rendered or materials furnished; 2) for the person sought
    to be charged; 3) which services and materials were accepted by the person sought
    to be charged, used and enjoyed by him; 4) under such circumstances as reasonably
    notified the person sought to be charged that the plaintiff in performing such services
    was expecting to be paid by the person sought to be charged.
    Bashara v. Baptist Mem’l Hosp. Sys., 
    685 S.W.2d 307
    , 310 (Tex. 1985) (internal quotations
    omitted). To satisfy the second element, it is not enough that a plaintiff’s efforts benefit the person
    from whom he seeks damages; they must have been undertaken “for the person sought to be
    charged.” Truly v. Austin, 
    744 S.W.2d 934
    , 937 (Tex. 1988) (citing 
    Bashara, 685 S.W.2d at 310
    ).
    Thus, incidental benefits and advantages that may have flowed to Beitler do not justify an award of
    quantum meruit damages against him unless Martin’s services were performed for him. See 
    id. The record
    reflects that Martin undertook the services he performed based on
    communications with Robbins and pursuant to the Letter Agreement between him, Karken, and
    Robbins Company. The testimony and evidence showed that Martin’s contact concerning the project
    was Robbins, with Beitler only being copied on emails, and that Martin never spoke with Beitler on
    the phone and met him on only one occasion, on the day of the town hall meeting, when Robbins
    introduced Martin as the person “who [Robbins] wanted to be the general contractor on the project.”
    8
    As previously noted, Martin and Karken’s claims against Robbins Company were severed
    prior to trial.
    23
    In short, Martin had virtually no direct communication with Beitler concerning the services he
    provided for the project. Thus, whether Martin undertook the services for Beitler hinges on whether
    Beitler and Robbins were partners on the project, as Martin and Karken allege. See Tex. Bus. Orgs.
    Code § 152.304 (partners generally jointly and severally liable for all obligations of partnership).
    The jury found that they were not partners, and Martin and Karken challenge the
    factual sufficiency of the evidence supporting that finding. When an appellant attacks the factual
    sufficiency of an adverse finding on an issue for which he had the burden of proof, he must
    demonstrate that the adverse finding is against the great weight and preponderance of the evidence.
    Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 242 (Tex. 2001) (per curiam). We consider and weigh
    all of the evidence and set aside the finding only if it is so contrary to the overwhelming weight of
    the evidence as to be clearly wrong and unjust. Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    ,
    406–07 (Tex. 1998); Pool v. Ford Motor Co., 
    715 S.W.2d 629
    , 635 (Tex. 1986). We must not pass
    on the credibility of the witnesses or merely substitute our judgment for that of the trier of fact.
    Golden Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 761 (Tex. 2003); 
    Pool, 715 S.W.2d at 634
    .
    We begin with the jury charge and instructions. See Jackson, 
    116 S.W.3d 757
    , 762
    (“Before a court can properly conduct a factual sufficiency review, it must first have a clear
    understanding of the evidence that is pertinent to its inquiry. The starting point generally is the
    charge and instructions to the jury.”). Question 3 asked:
    Were The D.J. Robbins Company, Inc. and Barry Beitler partners in the August 31,
    2007 Letter of Professional Engagement and/or the project known as Village Square?
    Definition/instructions: A partnership is defined as “an association of two or more
    people or entities to carry on an undertaking or a business, as owners, for profit.”
    24
    Factors indicating that people have created a partnership include· (1) receipt or right
    to receive a share of profits of the business; (2) expression of an intent to be partners
    in the business; (3) participation or right to participate in control of the business; (4)
    agreement to share or sharing: (a) losses of the business; or (b) liability for claims
    by third parties against the business; and ( 5) agreement to contribute or contributing
    money or property to the business. In determining whether a partnership exists, no
    single factor is decisive by itself and you should consider the evidence and what the
    parties said and did in light of the surrounding circumstances. You may not consider
    the parties’ unexpressed thoughts or intentions.
    Under Texas law, a partnership is defined as “an association of two or more persons to carry
    on a business for profit as owners . . . regardless of whether (1) the persons intend to create a
    partnership; or (2) the association is called a ‘partnership,’ ‘joint venture,’ or other name.” See Tex.
    Bus. Orgs. Code § 152.051(b). The Texas Revised Partnership Act (TRPA) sets out the factors
    indicating a partnership:
    (1) receipt or right to receive a share of profits of the business;
    (2) expression of an intent to be partners in the business;
    (3) participation or right to participate in the control of the business;
    (4) agreement to share or sharing:
    (A) losses of the business or
    (B) liabilities for claims by third parties against the business; and
    (5) agreement to contribute or contributing money or property to the business.
    
    Id. § 152.052(a).
    In evaluating the existence of a partnership, direct proof of the parties’ intent to
    form a partnership is not required, nor is proof of all of the statutory factors. Ingram v. Deere,
    
    288 S.W.3d 886
    , 895 (Tex. 2009). Instead, the question of whether a partnership exists should be
    25
    decided after consideration of all the evidence bearing on the TRPA partnership factors. 
    Id. at 895–96
    (adopting totality-of-circumstances test). One person holding another out as a partner is
    evidence of an expression of intent that they are partners, as are statements that they are partners.
    
    Id. at 900.
    Martin testified that Robbins held Beitler out as his partner in writing and at the town
    hall meeting at which Beitler was present. The evidence showed that Beitler and Robbins were
    members in a limited liability company that expended money for the project and that Robbins used
    an email address using Beitler’s domain. In addition, the mayor of Horseshoe Bay testified that it
    was his impression that Beitler and Robbins were partners, and the city’s proposed planned
    development ordinance referred to Beitler and Robbins as the project developers.
    However, the mayor also testified that he never had any discussion with Beitler
    concerning whether he was Robbins’s partner on this particular project, and Beitler testified
    unequivocally that he was not. He stated that at the time of the town hall meeting he and Robbins
    were partners on another project, pursuant to a written partnership agreement, but never had a
    partnership on this project. He also stated that it was “absolutely” his practice to have a written
    agreement for partnerships or limited liability companies and that he had never done a business deal
    with a partner without a written agreement. Beitler testified that he initially paid little attention to
    the project because Robbins was the developer and he planned to partner with Robbins later only if
    Robbins put together a deal he could invest in with less risk and if Robbins contributed money,
    neither of which occurred.
    26
    On the record before us, we cannot conclude that the jury’s finding that Beitler and
    Robbins were not partners is against the great weight and preponderance of the evidence. Although
    there was evidence that Robbins held out Beitler as his partner and stated that Beitler had a “big
    vote” in decisions, Beitler’s clear and direct testimony on that issue contradicted evidence of
    Robbins’s claims. The jury is the sole judge of the credibility of witnesses and the weight to be
    given to their testimony, and its first-hand assessments of Beitler’s and Martin’s credibility rationally
    could have informed its view of their testimony and the evidence. See City of 
    Keller, 168 S.W.3d at 819
    ; 
    Jackson, 116 S.W.3d at 761
    ; Turner v. KTRK Television Inc., 
    38 S.W.3d 103
    , 120 (Tex.
    2000) (“Because the trier of fact has the ability to examine the witness’s demeanor, we must defer
    to its credibility determinations.”). The jury could have reasonably believed Beitler’s testimony and
    disbelieved the evidence of Robbins’s partnership claims. As such, we will not disturb the jury’s
    finding. See City of 
    Keller, 168 S.W.3d at 819
    ; Durban v. Guajardo, 
    79 S.W.3d 198
    , 208 (Tex.
    App.—Dallas 2002, no pet.).
    Moreover, there was no evidence of any agreement that Beitler would share in any
    profits or losses. While there was evidence that Beitler contributed money, he testified that he did
    so only to advance the project in the hopes of getting it to a point where it was viable for him to
    partner with Robbins and fully participate. In light of the totality of circumstances, we conclude that
    the evidence was not so contrary to the jury’s finding that Beitler and Robbins were not partners as
    to be clearly wrong and unjust. See 
    Ellis, 971 S.W.2d at 407
    ; 
    Ingram, 288 S.W.3d at 895
    –96; Lentz
    Eng’g, L.C. v. Brown, No. 14-10-00610-CV, 2011 Tex. App. LEXIS 7723, at *16–17 (Tex.
    App.—Houston [14th Dist.] Sept. 27, 2011, no pet.) (mem. op.) (holding, under totality of
    27
    circumstances, evidence of two factors, splitting profits and participating in control, did not make
    finding of no partnership so against great and preponderance of evidence as to be clearly wrong and
    unjust). We conclude that the evidence was factually sufficient to support the jury’s finding that
    Beitler and Robbins were not partners. Accordingly, we further conclude that Martin is not entitled
    to quantum meruit damages against Beitler. See 
    Truly, 744 S.W.2d at 937
    ; Lentz Eng’g, 2011 Tex.
    App. LEXIS 7723, at *16–17 (where evidence supporting finding of no partnership was factually
    sufficient, alleged partner was not personally liable to plaintiff for quantum meruit damages). We
    overrule Martin’s and Karken’s sixth issue.
    CONCLUSION
    Having concluded that there is no evidence of damage to Porter’s reputation, Porter’s
    mental anguish, or Porter’s lost profits and no evidence of Beitler’s expenses for redesign, we
    reverse the trial court’s judgment on Porter’s counterclaim for defamation and Porter’s and Beitler’s
    counterclaims for tortious interference with business relationships and render judgment that they take
    nothing on their counterclaims. We affirm the trial court’s judgment in all other respects.
    __________________________________________
    Melissa Goodwin, Justice
    Before Chief Justice Rose, Justices Goodwin and Field
    Affirmed in Part; Reversed and Rendered in Part
    Filed: July 7, 2015
    28