Issac Savvas Molho v. Weichert, Realtors Reichardt & Associates ( 2012 )


Menu:
  • Affirmed and Memorandum Opinion filed December 20, 2012.
    In The
    Fourteenth Court of Appeals
    NO. 14-11-00861-CV
    ISSAC SAVVAS MOLHO, Appellant
    V.
    WEICHERT, REALTORS REICHARDT & ASSOCIATES, Appellee
    On Appeal from the 400th District Court
    Fort Bend County, Texas
    Trial Court Cause No. 06-DCV-148762
    MEMORANDUM OPINION
    In this breach-of-contract case, appellant Issac Savvas Molho challenges the
    trial court’s judgment notwithstanding the verdict (―JNOV‖) in favor of appellee
    Weichert, Realtors and Reichardt & Associates (―Weichert‖). In a single issue,
    Molho asserts that the trial court entered an erroneous judgment on the jury’s
    verdict. We affirm.
    BACKGROUND
    As is relevant to this appeal, Weichert, a real estate agency, sued Molho, an
    independent sales associate, for breach of an Independent Contractor Sales
    Associate Agreement (the ―agreement‖) between the parties. Weichert alleged that
    Molho had altered the term length of a property listing agreement from one year to
    three months in violation of the agreement. Molho counterclaimed for breach of
    the agreement, alleging unlawful termination of the agreement and conversion,
    among other claims. In its first amended answer, Weichert asserted the defense of
    prior material breach in response to Molho’s breach-of-contract claim.
    The parties tried their case to a jury in May 2011.1 At the charge conference,
    the following jury questions were agreed upon by Weichert and Molho:
    Question No. 1: Did [Molho] fail to comply with the [agreement]
    with [Weichert]?
    ...
    Question No. 2: What sum of money, if any, if paid now in cash
    would fairly and reasonably compensate [Weichert] for its damages, if
    any, that resulted from such failure to comply?
    ...
    Question No. 8: Did [Weichert] fail to comply with the [agreement]?
    ...
    Question No. 9: What sum of money, if any, paid now in cash would
    fairly and reasonabl[y] compensate [Molho] for his damages, if any,
    that resulted from [Weichert’s] failure to comply with the terms of the
    [agreement]?
    ...
    Question No. 11: Who failed to comply with the agreement first?
    Answer ―[Weichert]‖ or ―[Molho].‖
    1
    The only portion of the reporter’s record from the jury trial provided to us is the charge
    conference.
    2
    Molho neither challenged Question 11,2 nor requested an instruction on material
    breach during the charge conference.
    On May 20, 2011, the jury returned its verdict. In pertinent part, it answered
    ―Yes‖ to Question 1, but entered ―-0-‖ in response to Question 2, finding that
    Molho had failed to comply with the agreement, but that this failure did not result
    in monetary damages. The jury answered ―Yes‖ to Question 8 and ―$1,443.06‖ to
    Question 9, finding that Weichert also had failed to comply with the agreement and
    that this failure resulted in monetary damages to Molho.3 Finally, in response to
    Question 11, the jury found that Molho was the first to fail to comply with the
    agreement.
    On June 16, 2011, Weichert moved for JNOV, asserting that the jury’s
    award of damages to Molho for breach of contract and attorney’s fees was
    improper as a matter of law. It asserted that its duty to perform under the contract
    was excused by Molho’s prior material breach, which the jury found by its
    response to questions 1 and 11. Thus, Weichert argued, as a matter of law, Molho
    could not recover on his breach-of-contract claim. And because Moho could not
    recover on his breach-of-contract claim, he could not recover attorney’s fees.
    On July 15, 2011, Molho moved for entry of judgment based on the jury’s
    answers to questions regarding Weichert’s breach of the agreement, damages, and
    attorney’s fees. Molho responded to Weichert’s JNOV motion on August 22, 2011.
    He did not reply to Weichert’s arguments that his prior breach of the agreement
    2
    The clerk’s record contains a proposed jury question, with a notation indicating it was
    rejected by the trial court, asking whether Molho’s obligations under the contract were excused
    because Weichert breached the agreement first. But at the charge conference, this question was
    not specifically referenced. Additionally, Molho’s trial counsel affirmatively stated, ―I’m okay
    with [Question] 11.‖
    3
    The jury also found that $9,180 was a reasonable amount for Molho’s attorney fees for
    preparation and trial, as well as finding reasonable appellate fees.
    3
    was material in his response to Weichert’s JNOV motion. Instead, Molho asserted
    that Question 11 was irrelevant because no damages had been awarded to Weichert
    on its breach-of-contract claim.
    On September 1, 2011, the trial court rendered a take-nothing judgment in
    favor of Weichert on Molho’s breach-of-contract claim.4 The trial court also denied
    Molho attorney’s fees. Molho filed a motion for reconsideration, which was
    overruled by operation of law. Molho timely filed this appeal.
    ANALYSIS
    In Molho’s sole issue, he contends that the trial court misapplied the law in
    overruling the jury’s award of damages and attorney’s fees on his breach-of-
    contract claim. Specifically, he argues that because no damages were awarded to
    Weichert on its breach-of-contract claim, the jury’s finding that Molho breached
    first is immaterial and the trial court should not have granted JNOV. Weichert
    counters that the court properly applied the law to the jury’s findings, the jury
    found Molho’s breach material, and damages were not required to find a material
    breach.
    We affirm a trial court’s decision to grant a JNOV if there is no evidence to
    support one or more jury findings necessary for liability, 5 or when a legal principle
    precludes recovery. Autry v. Dearman, 
    933 S.W.2d 182
    , 190–91 (Tex. App.—
    Houston [14th Dist.] 1996, writ denied); John Masek Corp. v. Davis, 
    848 S.W.2d 170
    , 173 (Tex. App.—Houston [1st Dist.] 1992, writ denied). In considering a
    JNOV, we apply the standards for ―no evidence‖ embodied in a legal sufficiency
    review. Hartland v. Progressive Cnty. Mut. Ins. Co., 
    290 S.W.3d 318
    , 321 (Tex.
    4
    The court further awarded Molho $300 as damages for his conversion claim plus court
    costs. This portion of the judgment is not at issue in this appeal.
    5
    Wal-Mart Stores, Inc. v. Miller, 
    102 S.W.3d 706
    , 709 (Tex. 2003).
    4
    App.—Houston [14th Dist.] 2009, no pet.); see City of Keller v. Wilson, 
    168 S.W.3d 802
    , 823 (Tex. 2005). Thus, we will affirm a JNOV if (1) there is a
    complete absence of evidence of a vital fact; (2) rules of law or evidence preclude
    according weight to the only evidence offered to prove a vital fact; (3) the evidence
    offered to prove a vital fact is no more than a mere scintilla; or (4) the evidence
    conclusively establishes the opposite of the vital fact. 
    Hartland, 290 S.W.3d at 321
    (citing City of 
    Keller, 168 S.W.3d at 810
    ). We must review the evidence in the
    light most favorable to the verdict and assume that the jury resolved all conflicts in
    accordance with the verdict. City of 
    Keller, 168 S.W.3d at 820
    . To the extent that
    the trial court’s ruling is based on a question of law, we review that part of the
    ruling de novo. COC Servs., Ltd. v. CompUSA, Inc., 
    150 S.W.3d 654
    , 662 (Tex.
    App.—Dallas 2004, pet. denied); see also In re Humphreys, 
    880 S.W.2d 402
    , 404
    (Tex. 1994) (―[Q]uestions of law are always subject to de novo review.‖)
    ―It is a fundamental principle of contract law that when one party to a
    contract commits a material breach of that contract, the other party is discharged or
    excused from further performance.‖ Mustang Pipeline Co. v. Driver Pipeline Co.,
    
    134 S.W.3d 195
    , 196 (Tex. 2004) (per curiam). As noted above, Molho contends
    that because no damages were awarded for his prior breach, the jury’s finding that
    he breached the agreement first should be disregarded. However, there is no
    requirement that damages be associated with a defense of prior material breach.
    See 
    id. at 199–201
    (holding a contract to construct a pipeline was terminated by the
    construction company’s prior material breach of the contract, although awarding
    no damages to the other party for this prior material breach). Thus, we reject
    Molho’s argument.6
    6
    Molho did not challenge the materiality of his prior breach until he filed his reply brief
    on appeal, notwithstanding the fact that Weichert raised prior material breach in its answer and
    its JNOV. In his reply brief, he asserts that the jury did not find that the breach was material and
    5
    Accordingly, we overrule Molho’s sole issue and affirm the trial court’s
    judgment.
    /s/           Adele Hedges
    Chief Justice
    Panel consists of Chief Justice Hedges and Justices Brown and Busby.
    thus Weichert had not established a necessary element of this defense. Arguments may not be
    raised for the first time in a reply brief. Brown v. Green, 
    302 S.W.3d 1
    , 13–14 (Tex. App.—
    Houston [14th Dist.] 2009, no pet.).
    6