G. C. Buildings, Inc. v. RGS Contractors, Inc. ( 2014 )


Menu:
  • AFFIRMED; Opinion Filed October 13, 2014.
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-13-00151-CV
    G.C. BUILDINGS, INC., Appellant
    V.
    RGS CONTRACTORS, INC., Appellee
    On Appeal from the 191st Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-03-04559-J
    MEMORANDUM OPINION
    Before Justices Francis, Lang-Miers, and Myers
    Opinion by Justice Myers
    G.C. Buildings, Inc. appeals the trial court’s judgment that it take nothing on its claims
    against RGS Contractors, Inc. for breach of contract following a trial before the court. Appellant
    brings four issues on appeal contending (1) appellant provided evidence on each element of its
    contract cause of action and there was no contrary evidence; (2) appellant is not estopped from
    pursuing damages; (3) appellant did not assign its claims to the United States Department of
    Housing and Urban Development (HUD); and (4) certain of the trial court’s “findings” were not
    proper findings of fact. We affirm the trial court’s judgment.
    BACKGROUND
    In 1997, appellant hired appellee to build an apartment complex on property owned by
    appellant in Oklahoma. The project was financed by a $7 million loan from GMAC Commercial
    Mortgage, and that loan was insured by HUD. The contract called for completion of work by
    February 1, 1999. Due to a fire, the parties extended the completion date to May 4, 2000.
    Although the buildings were substantially completed and possession was turned over to appellant
    by June 8, 2000, there was an extensive punch list of problems with the individual units that
    prevented most of them from being leased.          The contract provided that the date of final
    completion was “the date the HUD representative signs the final HUD Representative’s Trip
    Report.” The final trip report was signed on October 12, 2000, 161 days after May 4.
    From May to December 2000, appellant made monthly (and occasionally bimonthly)
    interest payments on the loan, averaging about $46,520 per month and totaling $372,156.14.
    Appellant’s income from rentals was $1,500 in June 2000 and by August 2000 had risen to
    $9,000. Appellant’s chief financial officer testified that if all the apartments had been rentable in
    May 2000, the rental income would have been $77,400 per month. In January 2000, appellant
    defaulted on the loan and abandoned the property to GMAC and HUD.
    The contract between appellant and appellee contained a liquidated-damages provision
    stating that if the construction was not completed timely, the amount appellee would be paid
    under the contract
    shall be reduced by $2,101.68, as liquidated damages, for each day of delay until
    the date of final completion. When the Owner cost certifies to HUD, the actual
    cost of interest, taxes, insurance, mortgage insurance premiums, and construction
    and permanent loan extension fees, as approved by the Commissioner, for the
    period from the scheduled date of completion through the date construction was
    actually completed, shall be determined. The lesser of the liquidated or actual
    damages shall be applied.
    Appellant did not certify to HUD “the cost of interest, taxes, insurance, mortgage insurance
    premiums, and construction and permanent loan extension fees . . . from the scheduled date of
    completion through the date construction was actually completed.” Instead, appellant approved
    appellee being paid with no deduction for actual or liquidated damages for the delay.
    –2–
    In May 2003, appellant brought suit against appellee, alleging appellee breached the
    contract by not finally completing construction by May 4, 2000. Appellant sought “liquidated
    damages of $2,101.68 per day for each day of delay until final completion or the actual cost of
    interest, taxes, insurance, mortgage insurance premiums and extension fees, whichever is less.”
    Alternatively, appellant sought “its actual damages based on the General Conditions and
    applicable common law.”
    During trial, appellant presented evidence that it made interest payments after May 4,
    2000 on the loan of $372,156.14. Appellant calculated the amount of liquidated damages as
    $338,370.48. Appellant’s chief financial officer testified appellant would have had to make the
    interest payments regardless of whether the project was timely completed. The trial court
    concluded that appellant “has failed . . . to establish a proper measure of damages against”
    appellee.”
    DAMAGES
    In its first issue, appellant contends it “provided evidence on each element of its contract
    cause of action and there was no contrary evidence.”            We interpret appellant’s issue as
    contending that appellant proved its breach-of-contract cause of action as a matter of law, and
    that the trial court’s determination that appellant did not prove its cause of action was against the
    great weight and preponderance of the evidence.
    When reviewing a trial court’s findings of fact and conclusions of law for legal and
    factual sufficiency, we apply the same standards used in reviewing the evidence supporting jury
    findings. Catalina v. Blasdel, 
    881 S.W.2d 295
    , 297 (Tex. 1994). When an appellant attacks the
    legal sufficiency of the evidence to support an issue on which the appellant had the burden of
    proof, the appellant must show the evidence establishes, as a matter of law, all vital facts in
    support of the issue. Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001). In reviewing
    –3–
    a “matter of law” challenge, we first examine the record for evidence supporting the finding, and
    then examine the entire record to determine if the contrary proposition is established as a matter
    of law. 
    Id. We sustain
    the point of error only if the contrary proposition is conclusively
    established. 
    Id. When a
    party attacks the factual sufficiency of an adverse finding, it must demonstrate
    the adverse finding is against the great weight and preponderance of the evidence. 
    Id. at 242.
    We must consider and weigh all of the evidence and can set aside the finding only if the evidence
    is so weak or if the finding is so against the great weight and preponderance of the evidence that
    it is clearly wrong and unjust. 
    Id. One of
    the elements of a claim for breach of contract that appellant had the burden of
    proving is that the breach of the contract caused appellant’s damages. See Marquis Acquisitions,
    Inc. v. Steadfast Ins. Co., 
    409 S.W.3d 808
    , 813 (Tex. App.—Dallas 2013, no pet.) (elements of
    breach of contract are “(1) a valid contract; (2) performance or tendered performance by the
    plaintiff; (3) breach of the contract by the defendant; and (4) damages sustained by the plaintiff
    as a result of the breach.”). To recover damages for breach of contract, appellant had to prove it
    suffered some pecuniary loss as a result of the breach. S. Elec. Servs., Inc. v. City of Hous., 
    355 S.W.3d 319
    , 324 (Tex. App.—Houston [1st Dist.] 2011, pet. denied). The “losses must be the
    natural, probable, and foreseeable consequence of the defendant’s conduct.” 
    Id. (citing Mead
    v.
    Johnson Group, Inc., 
    615 S.W.2d 685
    , 687 (Tex. 1981)). The absence of a causal connection
    between the alleged breach and the damages sought will preclude recovery. 
    Id. In its
    brief on appeal, appellant argues it
    submitted evidence based on an out of pocket measure of damages premised on
    its interest payments prior to final completion and ending when it abandoned the
    project. Those amounts are set forth in GCB exhibits 8 and 9 and aggregate
    $372,156.14. Alternatively, GCB submitted evidence of liquidated damages of
    $338,370.48 per Article 2E [sic] of the Construction Contract.
    –4–
    Appellant’s chief financial officer testified that appellant had to make those interest payments
    regardless of whether the apartments were timely completed:
    Q. After May [4, 2000], you were already obligated to make interest payments
    under the mortgage, were you not?
    A. Yes.
    ....
    Q. GCB would have been making interest payments to GMAC regardless of how
    many apartments were available for occupancy, correct?
    A. Yes, we have a commitment to pay GMAC for the money we borrowed from
    them.
    ....
    Q. Okay. That represent[s] interest payments on the loan that you would have
    been making anyway, sir; isn’t that right?
    A. Yes.
    Because appellant had to make the interest payments regardless of whether the construction was
    timely, the interest payments were not the consequence of appellee’s alleged failure to timely
    complete construction. The interest payments were not the result of the breach of the contract
    and were not “the natural, probable, and foreseeable consequence” of any breach by appellee for
    untimely completing the construction. 
    Mead, 615 S.W.2d at 687
    . We conclude the evidence is
    legally and factually sufficient to support the trial court’s determination that appellant failed to
    prove the interest payments were damages from appellee’s untimely completion of the
    construction.
    –5–
    Appellant also argues it is entitled to liquidated damages under “Article 2E of the
    Construction Contract.” Article 2E does not concern liquidated damages. 1 However, article 2C
    addresses liquidated damages. That provision states,
    C. If the work is not brought to final completion in accordance with the Drawings
    and Specifications, including any authorized changes, by the date specified above,
    or by such date as to which the contract time may be extended, the maximum sum
    stated in Article 3A(1) below shall be reduced by $2,101.68, as liquidated
    damages, for each day of delay until the date of final completion. When the
    Owner cost certifies to HUD, the actual cost of interest, taxes, insurance,
    mortgage insurance premiums, and construction and permanent loan extension
    fees, as approved by the Commissioner, for the period from the scheduled date of
    completion through the date construction was actually completed, shall be
    determined. The lesser of the liquidated or actual damages shall be applied. The
    applicable amount shall be reduced by the project’s net operating income.
    Thus, the contract provided that if appellee did not complete construction timely, then the
    amount appellee would be paid under the contract would be reduced by either the liquidated
    damages amount or the amount that appellant certified to HUD was the cost of the interest, etc.,
    during the delay, whichever was less. Appellant did not certify to HUD that it had any costs for
    interest, etc. during the delay, so appellant was not entitled to have the amount appellee was paid
    reduced by the amount of the liquidated damages. The contract did not provide for recovery of
    liquidated damages for delay outside of the procedure set forth in article 2C of the contract.
    We conclude the trial court’s determination that appellant failed to prove its damages
    from breach of contract was supported by legally and factually sufficient evidence. We overrule
    appellant’s first issue.
    In the second and third issues, appellant contends it was not estopped from pursuing
    damages and that it did not assign its breach-of-contract claim to HUD. Because we have
    1
    Article 2E provides, “E. The date of final completion shall be the date the HUD representative signs the final HUD Representative’s Trip
    Report provided that the trip report is subsequently endorsed by the Chief Architect.”
    –6–
    determined appellant failed to prove the element of damages, determination of these issues is not
    necessary for final disposition of the appeal. Accordingly, we do not address these issues. See
    TEX. R. APP. P. 47.1 (opinion must address “every issue raised and necessary to final disposition
    of the appeal”).
    FINDINGS OF FACT
    In its fourth issue, appellant contends that the trial court’s findings of fact 12 through 15,
    21, 22, and 24 were not findings of fact. Appellant asserts these “findings” are legal conclusions
    or the trial court’s legal interpretation of the contracts. Appellant did not object to any of the
    findings, he cites no authority for the proposition that the mislabeling of conclusions of law as
    findings of fact is reversible error, and he provides no argument explaining why the mislabeling
    constitutes reversible error. When a conclusion of law is mislabeled as a finding of fact, the
    mislabeled conclusion is reviewed de novo instead of for evidentiary sufficiency. See In re
    Office of Attorney Gen. of Tex., 
    264 S.W.3d 800
    , 804 n.3 (Tex. App.—Houston [1st Dist.] 2008,
    orig. proceeding); Nikolai v. Strate, 
    922 S.W.2d 229
    , 237 n.1 (Tex. App.—Fort Worth 1996, writ
    denied).
    Appellant also asserts there was no evidence to support these findings. For purposes of
    this appeal, only finding 24 is relevant because it concerns appellant’s proof of damages. The
    relevant portion of that finding states, “GCB’s only offer of alleged damages is certain interest
    payments made by GCB on the loan. In that regard, GCB agrees that it would have had to pay
    those same interest payments on the loan any way, regardless of whether there was delay under
    the Contract or not.” That finding of fact was supported by the testimony of appellant’s chief
    financial officer, who testified appellant had to make the interest payments regardless of whether
    the apartments were timely constructed. This finding was supported by legally and factually
    sufficient evidence.
    –7–
    We conclude appellant has not shown reversible error in this issue.   We overrule
    appellant’s fourth issue.
    CONCLUSION
    We affirm the trial court’s judgment.
    /Lana Myers/
    LANA MYERS
    JUSTICE
    130151F.P05
    –8–
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    G.C. BUILDINGS, INC., Appellant                    On Appeal from the 191st Judicial District
    Court, Dallas County, Texas
    No. 05-13-00151-CV        V.                       Trial Court Cause No. DC-03-04559-J.
    Opinion delivered by Justice Myers. Justices
    RGS CONTRACTORS, INC., Appellee                    Francis and Lang-Miers participating.
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    AFFIRMED.
    It is ORDERED that appellee RGS CONTRACTORS, INC. recover its costs of this
    appeal from appellant G.C. BUILDINGS, INC.
    Judgment entered this 13th day of October, 2014.
    –9–