Trebuchet Siege Corporation & DFW Metroplex Architecture, Inc. v. Pavecon Commercial Concrete, LTD ( 2014 )


Menu:
  • Reverse and Remand; Opinion Filed August 19, 2014.
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-12-00945-CV
    TREBUCHET SIEGE CORPORATION AND DALLAS FT. WORTH
    METROPLEX ARCHITECTURE, INC., Appellants
    V.
    PAVECON COMMERCIAL CONCRETE, LTD., Appellee
    On Appeal from the 134th Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. 09-17344
    DISSENTING OPINION
    Before Justices Moseley, Lang, and Brown
    Dissenting Opinion by Justice Moseley
    I agree with the majority opinion’s conclusion that the trial court properly granted
    summary judgment on appellants’ negligence counterclaim on account of the economic loss rule.
    See LAN/STV v. Martin K. Eby Contr. Co., No. 11-0810, 
    2014 WL 2789097
    , at *1 (Tex. June 20,
    2014). However, I disagree with the majority opinion’s conclusions that the trial court properly
    (1) sustained an objection to a portion of Sarah Harrison’s affidavit as a “conclusory factual
    statement” and (2) granted a no-evidence summary judgment against Dallas Ft. Worth Metroplex
    Architecture, Inc. (DFM) and in favor of Pavecon Commercial Concrete, Ltd. on DFM’s claim
    for breach of contract. Based on these disagreements, I would reverse the summary judgment as
    to that cause of action and remand the case for further proceedings. Because the majority does
    not, I respectfully dissent.
    I generally agree with the majority opinion’s recitation of the facts in this case, and thus I
    do not repeat those facts here in detail. Pavecon filed a no-evidence motion for summary
    judgment asserting DFM had no evidence of any element of its breach of contract claim. As part
    of DFM’s response, it filed the affidavit of Sarah Harrison, who was vice-president of DFM and
    president of Trebuchet, and an affidavit by Jerald Kunkel, an engineer hired by DFM in
    connection with its claim. Kunkel’s affidavit referred to his report, which was attached. The
    trial court struck Harrison’s affidavit as conclusory and granted Pavecon’s no-evidence motion.
    A.     Affidavit
    In paragraph 13 of the Harrison’s affidavit, she states: “Both DFM and Trebuchet have
    incurred damages to polish and treat the floors against further damage.” The trial court sustained
    Pavecon’s objection that this sentence was a conclusory factual statement.
    We review rulings sustaining objections to summary judgment evidence for an abuse of
    discretion. See Cantu v. Horany, 
    195 S.W.3d 867
    , 871 (Tex. App.—Dallas 2006, no pet.). An
    objection that an affidavit is conclusory goes to the substance of the affidavit, rather than the
    form.   See Thompson v. Curtis, 
    127 S.W.3d 446
    , 450 (Tex. App.—Dallas 2004, no pet.).
    Although a conclusory affidavit will not support a summary judgment, the prohibition against
    conclusory evidence does not mean that logical conclusions based on stated underlying facts are
    improper. See Eberstein v. Hunter, 
    260 S.W.3d 626
    , 630 (Tex. App—Dallas 2008, no pet.).
    In her affidavit, Harrison states Pavecon’s work was to be “performed in a good and
    workman like manner.” However, “[o]n the initial day that Pavecon poured the concrete slabs,
    cracking was immediately visible.” Harrison’s affidavit continues to describe the problems
    arising from Pavecon’s work. She avers: (1) “[o]nce Pavecon completed its work in April 2009,
    excessive cracking appeared on the polished concrete flooring inside the buildings;” (2) cracking
    “caus[ed] damage to already-completed work on the Project;” and (3) “[a]lmost four months
    –2–
    after Pavecon poured the foundation, water continued to surface and pool in the low areas of the
    floors.”
    In the context of Harrison’s affidavit, I would conclude the objected-to portion of
    paragraph 13 is a statement that appellants have incurred costs in their effort to polish and treat
    the floor and attempt to mitigate against further damage to the floor. Considering appellants’
    account in Harrison’s affidavit of the extensive problems with the floor—cracking and water
    pooling—it is logical such problems would cause appellants to incur costs if they attempted to
    prevent further damage, particularly to other parts of the project that had already been completed.
    When read in the context of her affidavit, the statement that “[b]oth DFM and Trebuchet
    have incurred damages to polish and treat the floors against further damage” is not an improper
    conclusion, but rather a summary of “factual account[s] of events which are proper summary
    judgment proof.” Triland Inv. Grp. v. Tiseo Paving Co., 
    748 S.W.2d 282
    , 284 (Tex. App.—
    Dallas 1988, no writ); see also Cooper v. Circle Ten Council Boy Scouts of Am., 
    254 S.W.3d 689
    , 699–700 (Tex. App.—Dallas 2008, no pet.). Harrison provided factual background to
    support her statement; therefore, her statement is proper summary judgment evidence that we can
    consider. Strother v. City of Rockwall, 
    358 S.W.3d 462
    , 469 (Tex. App.—Dallas 2012, no pet.)
    (affidavit was not conclusory when it set out facts supporting conclusions). I would conclude
    that the trial court abused its discretion by sustaining Pavecon’s objection.
    B.      Summary Judgment on Breach of Contract Counterclaim
    The majority opinion sustains the no-evidence summary judgment on DFM’s breach of
    contract counterclaim on the basis that DFM failed to present summary judgment evidence
    raising a genuine issue of material fact as to the damage element of the breach of contract claim.
    (Trebuchet did not assert a breach of contract claim). Again, I disagree.
    We review a no-evidence summary judgment to determine whether the nonmovant
    –3–
    produced more than a scintilla of probative evidence to raise a fact issue on the material
    questions presented. Flood v. Katz, 
    294 S.W.3d 756
    , 762 (Tex. App.—Dallas 2009, pet denied).
    When analyzing a no-evidence summary judgment, “we examine the entire record in the light
    most favorable to the nonmovant, indulging every reasonable inference and resolving any doubts
    against the motion.” Sudan v. Sudan, 
    199 S.W.3d 291
    , 292 (Tex. 2006) (quoting City of Keller
    v. Wilson, 
    168 S.W.3d 802
    , 823 (Tex. 2005)). A no-evidence summary judgment is improperly
    granted if the nonmovant presented more than a scintilla of probative evidence to raise a genuine
    issue of material fact. King Ranch, Inc. v. Chapman, 
    118 S.W.3d 742
    , 751 (Tex. 2003). “More
    than a scintilla of evidence exists when the evidence rises to a level that would enable
    reasonable, fair-minded persons to differ in their conclusions.”         
    Id. (quoting Merrell
    Dow
    Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 711 (Tex. 1997)). “Less than a scintilla of evidence
    exists when the evidence is ‘so weak as to do no more than create a mere surmise or suspicion’
    of a fact.” 
    Id. (quoting Kindred
    v. Con/Chem, Inc., 
    650 S.W.2d 61
    , 63 (Tex. 1983)).
    In its motion, Pavecon asserted DFM had no evidence that: (1) DFM had a valid,
    enforceable contract with Pavecon; (2) DFM performed all of its contractual obligations pursuant
    to the terms of the contract; (3) Pavecon breached the contract; or (4) DFM suffered any
    damages as a result of the breach. See Paragon Gen. Contractors, Inc. v. Larco Constr., Inc.,
    
    227 S.W.3d 876
    , 882 (Tex. App.—Dallas 2007, no pet.) (elements of breach of contract). After
    reviewing the record, I would conclude that DFM’s summary judgment evidence, when read in
    the light most favorable to the nonmovant and indulging every reasonable inference in DFM’s
    favor, was sufficient to raise an issue of material fact as to each element of its breach of contract
    counterclaim.
    First, the unobjected-to portions of Harrison’s affidavit raise at least a fact issue as to the
    –4–
    first three elements of DFM’s breach of contract cause of action. 1 And as noted above, I contend
    Harrison’s affidavit also raised an issue as to whether DFM suffered injury as a result of
    Pavecon’s breach of contract. When taken in the context of the other statements in her affidavit,
    and again indulging every reasonable inference in DFM’s favor, I would conclude Harrison’s
    statement that “[b]oth DFM and Trebuchet have incurred damages to polish and treat the floors
    against further damage” means they both incurred costs in their efforts to polish and treat the
    floor and attempt to mitigate against further damage to the floor.
    Also, Kunkel’s affidavit and attached report raise an issue of fact as to the element of
    damages caused by Pavecon’s alleged breach. His affidavit states he concluded the excessive
    cracking of the slabs was caused by Pavecon’s work on the project. His expert report states the
    problems DFM encountered with the floor were “a direct result of the concrete mix that was
    used, then [sic] procedure that was used at the time of placement and the low concrete
    compressive strengths.” He “observed excessive surface cracking” on each of the four slabs at
    the project, which “was caused by Pavecon’s work on the Project.” He also states that core
    samples of the floor slabs do not compare with a core sample of a test concrete slab that Pavecon
    poured previously at DFM’s request, and that DFM had approved as to quality and appearance.
    As the majority opinion notes, Kunkel’s report also “talked about the various fixes that
    had been done to address the cracking in the concrete floors. He observed that a crack-filling
    treatment had been applied to ‘several of the cracks’ and a ‘polishing contractor’ reported
    numerous failed attempts to properly polish the floors.” (Majority, slip op. at 7). In conjunction
    1
    By way of summary, Harrison stated DFM contracted with Pavecon—and only Pavecon—to pour the concrete slabs; they agreed on
    the form of a contract, and the form attached to her affidavit is the contract they followed. Harrison’s affidavit clearly states the parties agreed to
    the terms of the document that she attached to her affidavit. Whether that document actually created a contract between the parties, her affidavit
    is more than a scintilla of probative evidence raising a genuine issue of material fact on that element of DFM’s claim.
    In return for Pavecon’s work, DFM agreed to pay Pavecon for “the labor and materials”; Harrison stated that DFM “agreed to pay
    Pavecon for all work that complied with the Contract terms and that was performed in a good and workman like manner.” Harrison stated that
    DFM agreed to pay Pavecon $577,252, although that amount was increased with change orders. DFM has paid that amount except for a retainage
    amount of $58,418.54 and that amount has not been paid “because of this pending litigation over poor workmanship and damage to the Project.”
    –5–
    with Harrison’s affidavit, this evidence indicates both DFM and Trebuchet spent funds trying to
    fix the concrete floor problem, including hiring a contractor in an unsuccessful attempt to polish
    the floors to an acceptable level. Certainly this evidence does “more than create a mere surmise
    or suspicion” that DFM suffered damages as a result of Pavecon’s breach of contract. See King
    Ranch, 
    Inc., 118 S.W.3d at 751
    (quoting 
    Kindred, 650 S.W.2d at 63
    ).
    Kunkel’s report also states that leaving the floor slabs in their current condition is not a
    viable option, as their cracking and appearance make them undesirable for public use. The
    report goes on to evaluate several options for addressing the problem, including replacing the
    slabs or repairing them with epoxy and then refinishing them. Again, this evidence makes clear
    that DFM did not get what it contracted for, that the polished concrete floor slabs are not suitable
    for their intended purpose, and that fixing the problem will require replacing or repairing and
    recoating the slabs. Viewing this evidence in the light most favorable to DFM, it did more than
    create a mere surmise or suspicion that it was damaged as a result of Pavecon’s breach of
    contract.
    In conclusion, DFM was not required to prove it would prevail at trial in order to avoid
    an adverse ruling on summary judgment. Applying the appropriate standard, I would conclude
    the evidence raises a genuine issue of material fact as to each challenged element of DFM’s
    cause of action.
    –6–
    Accordingly, I would reverse the summary judgment in part and remand for further
    proceedings. Because the majority reaches a different conclusion, I respectfully dissent.
    /Jim Moseley/
    JIM MOSELEY
    JUSTICE
    120945DF.P05
    –7–