Walton & Marie Brown v. Potter Concrete Residential, Ltd. ( 2014 )


Menu:
  • Affirmed and Opinion Filed June 30, 2014
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-13-00585-CV
    WALTON AND MARIE BROWN, Appellants
    V.
    POTTER CONCRETE RESIDENTIAL, LTD., LAWRENCE MONDY D/B/A
    LAWRENCE MONDY CONTRACTING, AND KB HOME LONE STAR, INC., F/K/A
    KB HOME LONE STAR, L.P., Appellees
    On Appeal from the County Court at Law No. 1
    Dallas County, Texas
    Trial Court Cause No. CC-10-09065-A
    MEMORANDUM OPINION
    Before Justices Bridges, Francis, and Lang-Miers
    Opinion by Justice Francis
    Walton and Marie Brown appeal the trial court’s judgment confirming an arbitration
    award. In two issues, the Browns argue the trial court erred in confirming the award because
    they did not agree to binding arbitration with appellees Potter Concrete Residential, Ltd. and
    Lawrence Mondy Contracting. We affirm.
    The Browns filed an original petition and motion to compel arbitration against KB Home
    Lone Star, Inc., formerly known as KB Home Lone Star, LP. The petition alleged causes of
    action for statutory fraud, negligence, and breach of contract and warranty in connection with the
    purchase of their home from KB Home. In the motion to compel arbitration, the Browns
    asserted that under the binding agreement, KB Home was obligated to arbitrate the claims with
    the results binding only on KB Home.
    KB Home filed an answer asserting a general denial, a “special” denial, and several
    affirmative defenses. As to the motion to compel, KB Home argued that any arbitration award
    should be binding on both KB Home and the Browns, except for any award for warranty claims
    or construction defects for which the Browns should have the right to accept the arbitration
    results or continue with the litigation. KB Home also filed a third-party petition against Potter
    and Mondy, subcontractors who performed work relating to the preparation of the property’s
    grading prior to construction of the foundation.
    After finding the parties had agreed the matter was subject to arbitration, the trial court
    signed an order sending the parties to arbitration and appointing an arbitrator. The Browns’
    counsel approved the substance and form of the order. Ten months later, the trial court signed an
    agreed amended arbitration order abating the matter in its entirety, resetting the upcoming trial,
    and continuing the dispute in arbitration until completion. Counsel for the Browns, KB Home,
    Potter, and Mondy approved the order as to form and substance.
    Once in arbitration, the Browns asserted direct claims against Potter Concrete and
    Mondy.1 The arbitration was conducted over two days in November 2011. Ten months later, the
    arbitrator issued his Arbitrator’s Award. In the award, the arbitrator stated that “[a]n agreement
    to binding arbitration was entered into by the parties.” Further, the arbitrator noted that the
    parties and arbitrator “participated in several pre-arbitration hearings.” Additionally, the parties
    engaged in discovery, exchanged documents, and provided expert reports and designations. The
    1
    The Browns’ Statement of Claims, filed in the arbitration, is not a part of this Court’s record; however, the Arbitration Award addresses
    the Browns’ claims against Potter Concrete and Mondy.
    award also provided, “Pursuant to the Court’s order and agreements of counsel, the parties have
    submitted all matters to binding arbitration.”
    As to the merits of the causes of action, the arbitrator found in favor of Potter and Mondy
    with respect to the claims against them by the Browns and KB Home. The arbitrator found KB
    Home was liable to the Browns for (1) cosmetic repairs to the foundation, (2) cosmetic repairs to
    the interior and exterior of the home, (3) regrading the front and side yards so the property would
    properly drain, (4) engineering fees, attorney fees, and litigation expenses; and (5) temporary
    housing during the time of repairs. The total amount of the award, excluding interest, was
    $44,928.56.
    After the arbitrator issued his award, both Potter and Mondy filed applications to confirm
    the award under section 171.087 of the Texas Civil Practice and Remedies Code. The Browns
    did not file a motion to vacate the award, but did file a response arguing the applications should
    be denied because they never agreed to binding arbitration with Potter and Mondy. Following a
    hearing, the trial court confirmed the arbitrator’s award and rendered judgment against KB Home
    according to the award.
    In two issues on appeal, the Browns argue the trial court abused its discretion in binding
    them to an arbitration award involving Potter and Mondy when there was “no evidence of an
    agreement to be so bound.” According to the Browns, the only arbitration agreement was
    between them and KB Home and was subject to a Modified Consent Decree entered in federal
    court mandating that the results of any mandatory arbitration between KB Home and a
    homeowner was binding only on KB Home.
    Potter and Mondy make two arguments in response. First, they argue the Browns failed
    to move to vacate the arbitration award within ninety days as required by statute, leaving the trial
    court with no option but to confirm the award. Second, they argue the Browns not only signed
    agreed orders to arbitrate the case, they never objected to the binding effect of the arbitration
    among and across all parties until more than one year after the arbitration occurred and an award
    issued. Consequently, they assert the Browns have waived their right to complain about the
    award.
    We begin with the first argument. Under the Texas Arbitration Act, “[u]nless grounds
    are offered for vacating, modifying, or correcting an award under Section 171.088 or 171.091,
    the court, on application of a party, shall confirm the award.” TEX. CIV. PRAC. & REM. CODE
    ANN. § 171.087 (West 2011). A party has ninety days from the date of delivery of an award to
    apply to the trial court to vacate the award. See TEX. CIV. PRAC. & REM. CODE ANN. §
    171.088(b). Although the Browns did not specifically move to vacate the award, they did file a
    response arguing the applications to confirm should be denied.
    There are no specific requirements for an application to vacate an arbitrator’s award. See
    TEX. CIV. PRAC. & REM. CODE ANN. § 171.088 (West 2011); Morris v. Morris, No. 09-10-00385-
    CV, 
    2012 WL 34454
    , at *2 (Tex. App.—Beaumont Jan. 5, 2012, no pet.) (mem. op.). There is
    no policy or efficiency reason to require a separate, formal application so long as the party
    apprises the court and opposing party of its desire to have the award vacated. Morris, 
    2012 WL 34454
    , at *2; Sydow v. Verner, Liipfert, Bernhard, McPherson & Hand, Chartered, 
    218 S.W.3d 162
    , 172 (Tex. App.—Houston [14th Dist.] 2007, no pet.) (including request to vacate award in
    amended answer to petition requesting confirmation adequately apprised court and opposing
    party of desire to vacate award).
    We conclude the Browns’ response to the applications to confirm the arbitration award
    was sufficient to apprise the court and opposing parties of their desire to vacate the award.
    Having so concluded, we turn now to appellees’ argument that the Browns waived any right to
    complain about the arbitration award by agreeing to arbitration, participating in the hearing, and
    failing to object.
    Under section 171.088 of the civil practice and remedies code, a court may vacate an
    arbitration award under limited circumstances. TEX. CIV. PRAC. & REM. CODE ANN. § 171.088.
    Subsection (a)(4) provides one such ground: if “there was no agreement to arbitrate, the issue
    was not adversely determined in a proceeding under Subchapter B, and the party did not
    participate in the arbitration hearing without raising the objection.” 
    Id. 171.088(a)(4). The
    record here shows that after KB Home filed its third-party petition bringing Potter
    and Mondy into the lawsuit, KB Home filed an agreed motion to amend the previous arbitration
    order. According to the motion, the parties agreed to amend the previous arbitration order so that
    the “matter would be abated in its entirety and the claims remain in arbitration until completion.”
    The motion identified both Potter and Mondy as third-party defendants.            The agreed order
    resulting from the motion abated the case in its entirety, continued the upcoming trial setting, and
    ordered the dispute to continue in arbitration until completion. Counsel for all of the parties,
    including the Browns, approved the order as to form and substance.               The Browns then
    participated at the arbitration, asserting claims against Potter and Mondy.             Finally, the
    arbitrator’s award stated the parties agreed to binding arbitration and had “submitted all matters
    to binding arbitration.” Having reviewed the record, there is nothing in it to suggest the Browns
    ever objected or voiced any opinion that the arbitration would not be binding with respect to
    Potter and Mondy for lack of an arbitration agreement. We therefore conclude the Browns’
    issues are without merit.
    We affirm the trial court’s judgment.
    130585F.P05
    /Molly Francis/
    MOLLY FRANCIS
    JUSTICE
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    WALTON AND MARIE BROWN,                            On Appeal from the County Court at Law
    Appellants                                         No. 1, Dallas County, Texas
    Trial Court Cause No. CC-10-09065-A.
    No. 05-13-00585-CV         V.                      Opinion delivered by Justice Francis;
    Justices Bridges and Lang-Miers
    POTTER CONCRETE RESIDENTIAL,                       participating.
    LTD., LAWRENCE MONDY D/B/A
    LAWRENCE MONDY CONTRACTING,
    AND KB HOME LONE STAR, INC. F/K/A
    KB HOME LONE STAR, L.P., Appellees
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    AFFIRMED.
    It is ORDERED that appellees Potter Concrete Residential, Ltd., Lawrence Mondy d/b/a
    Lawrence Mondy Contracting, and KB Home Lone Star, Inc. f/k/a KB Home Lone Star, L.P.
    recover their costs of this appeal from appellants Walton and Marie Brown.
    Judgment entered June 30, 2014
    