Tony Miller, Individually and D/B/A Tony Miller Renovations & Construction v. Gail McCarty ( 2010 )


Menu:
  •                        In The
    Court of Appeals
    Sixth Appellate District of Texas at Texarkana
    ______________________________
    No. 06-10-00007-CV
    ______________________________
    TONY MILLER, INDIVIDUALLY AND D/B/A
    TONY MILLER RENOVATIONS & CONSTRUCTION, Appellant
    V.
    GAIL MCCARTY, Appellee
    On Appeal from the 202nd Judicial District Court
    Bowie County, Texas
    Trial Court No. 08C0269-202
    Before Morriss, C.J., Carter and Moseley, JJ.
    Opinion by Justice Moseley
    OPINION
    Spencer and Gail McCarty experienced problems with their Bowie County home which
    appeared to be caused by flaws in its foundation. In November or December 2007, Spencer made
    contact with a family friend, Tony Miller, doing business as Tony Miller Renovations and
    Construction, to repair the foundation. Spencer died during December 2007 and Gail contracted
    with Miller to perform the work, this being the construction of pilings under the foundation to give
    added support to the foundation’s southwest corner. Upon commencement of the anticipated
    repairs, Miller discovered concrete pilings beneath the foundation which indicated that there had
    apparently been two previous attempts to ameliorate the foundation problem. Although the
    existence of these unexpected pilings created more difficulty than Miller had anticipated when
    bidding the work, he attempted to work around them, but was unable to do so. Various disputes
    arose regarding the deposit McCarty was to pay, the existence of an agreement that more work was
    needed to lend additional support to the entire south end of the house, and the existence and impact
    of an alleged plumbing leak which Miller maintained was the precipitating cause of the foundation
    problems. As a result of the cumulative disputes, work on the job ceased with Miller and
    McCarty blaming each other, McCarty claiming that Miller voluntarily quit and Miller
    maintaining that he had been ordered by McCarty to leave the job site.
    McCarty filed suit against Miller individually and as Tony Miller Renovations &
    Construction, alleging negligence, breach of contract, and violations of the Texas Deceptive Trade
    2
    Practices—Consumer Protection Act (DTPA). TEX. BUS. & COM. CODE ANN. §§ 17.41–.63
    (Vernon 2002 & Supp. 2010). Miller alleged contributory negligence, counterclaimed for breach
    of contract, and pled excuse for his failure to perform. After a jury trial, the jury found: (1) that
    both parties were negligent; (2) that McCarty had been damaged in the sum of $4,700.00 due to
    Miller’s nonperformance of the contract; (3) that Miller performed compensable work of the value
    of $2,937.50; and (4) that both parties had failed to comply with the contract; (5) but that Miller’s
    failure to comply with the contract was excused. The issue of attorney’s fees was submitted to the
    trial court. McCarty submitted attorney’s fees of $18,135.00 and Miller submitted attorney’s fees
    of $1,800.00.
    After the filing of warring motions for judgment non obstante veredicto and motions to
    enter judgment, the trial court entered a judgment which (1) disregarded the jury’s finding that
    Miller was excused from complying with the contract, and (2) after weighing offsets, payments,
    attorneys’ fees, and costs of court, awarded McCarty judgment for $18,204.90.
    On appeal, Miller argues that the trial court erred in disregarding the jury’s finding that
    Miller’s breach of contract was excused on the stated basis that the finding was inconsistent with
    the greater weight of the evidence. Miller further contends that because the jury found that he was
    excused from performance of the contract, the trial court erred in awarding McCarty attorney’s
    fees and recovery for damages.
    3
    In her cross-appeal, McCarty contends that: (1) there is factually insufficient evidence
    that Miller and McCarty were twenty percent and eighty percent negligent, respectively; (2) there
    is factually insufficient evidence that McCarty failed to comply with the contract; (3) there is
    factually insufficient evidence that Miller’s failure to comply with the contract was excused; and
    (4) the trial court erred because it did not award attorney’s fees consistent with the uncontroverted
    evidence.
    As to Miller’s appeal, we reverse the trial court’s order disregarding the jury’s finding
    because there is legally and factually sufficient evidence that Miller’s failure to comply with the
    contract was excused. We also reverse the award against Miller for damages incurred by
    McCarty and the attorney’s fee award given to her.
    As to McCarty’s cross-appeal, we reject McCarty’s argument that: (1) there is legally and
    factually insufficient evidence that McCarty was negligent; (2) there is legally and factually
    insufficient evidence that McCarty failed to comply with the contract; and (3) there is legally and
    factually insufficient evidence that Miller’s failure to comply was excused.
    Standard of Review
    The issues on appeal are the legal and factual sufficiency of the jury findings and the trial
    court’s decision to disregard one of those findings. A trial court may disregard a jury’s finding
    only if there is no evidence to support the finding. Spencer v. Eagle Star Ins. Co. of Am., 
    876 S.W.2d 154
    , 157 (Tex. 1994); C. & R. Transp., Inc. v. Campbell, 
    406 S.W.2d 191
    , 194 (Tex.
    4
    1966). In determining a no-evidence issue, we are to consider only the evidence and inferences
    that tend to support the finding and disregard all evidence and inferences to the contrary.
    Bradford v. Vento, 
    48 S.W.3d 749
    , 754 (Tex. 2001); Cont’l Coffee Prods. Co. v. Cazarez, 
    937 S.W.2d 444
    , 450 (Tex. 1996); Hooper v. Smallwood, 
    270 S.W.3d 234
    (Tex. App.––Texarkana
    2008, pet. denied).
    In a legal sufficiency review, we view the evidence in a light favorable to the finding,
    crediting favorable evidence if a reasonable fact-finder could, and disregarding contrary evidence
    unless a reasonable fact-finder could not. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex.
    2005). Anything more than a scintilla of evidence is legally sufficient to support the jury finding.
    
    Cazarez, 937 S.W.2d at 450
    . When reviewing the factual sufficiency of evidence, we examine all
    the evidence and set aside a finding only if it is so contrary to the evidence as to be clearly wrong
    and unjust. Bledsoe Dodge, L.L.C. v. Kuberski, 
    279 S.W.3d 839
    , 841–42 (Tex. App.––Dallas
    2009, no pet.); Cameron v. Cameron, 
    158 S.W.3d 680
    , 683 (Tex. App.––Dallas 2005, pet. denied).
    Legally and Factually Sufficient Evidence Regarding Miller’s Excuse to Comply with Contract
    In its answer to Question 7, the jury found that Miller’s failure to comply with the contract
    was excused. Finding that the answer was ―inconsistent with the greater weight of evidence,‖ the
    trial court granted McCarty’s motion to disregard the jury’s answer to Question 7.1 Miller argues
    1
    By citing the ―greater weight of evidence‖ as its basis for disregarding the jury’s answer, the trial court failed to use
    the proper ―no-evidence‖ standard. However, we will affirm the trial court’s decision if there is less than a scintilla of
    evidence to support any of Miller’s theories of excuse. See Point Lookout W., Inc. v. Whorton, 
    742 S.W.2d 277
    , 278
    (Tex. 1987) (per curiam); see also In re Acevedo, 
    956 S.W.2d 770
    , 775 (Tex. App.––San Antonio 1997, orig.
    5
    that the trial court erred because there is sufficient evidence that Miller’s failure to comply was
    excused. 2 Contraveningly, McCarty contends that there is legally and factually insufficient
    evidence to support the jury’s finding in the first place.
    At trial, Miller argued that his failure to comply with the contract was excused because:
    (1) he and McCarty agreed that a new contract would take the place of the original, (2) McCarty
    failed to comply with a material obligation of the contract, and/or (3) McCarty repudiated the
    contract. The charge of the court listed each of these potential excuses for performance in its
    instructions; therefore, the jury was permitted under those instructions to find Miller’s excuse from
    performance on any one or more possibly inconsistent grounds without specifying the specific
    reason.
    A contract that is modified or amended by the mutual consent of the parties constitutes a
    new agreement that takes the place of the original. S & D Group, Inc. v. Talamas, 
    710 S.W.2d 680
    (Tex. App.––Corpus Christi 1986, writ ref’d n.r.e.); Martin v. Davis Constructors, Inc., 
    552 S.W.2d 873
    , 877 n.4 (Tex. App.––San Antonio 1977, writ ref’d n.r.e.).
    Here, the contract called for Miller to repair McCarty’s foundation in three phases. It is
    undisputed that phase one included the installation of six concrete piers beneath the southwest
    corner of McCarty’s residence for a total cost of $4,000.00. The contract required McCarty to
    proceeding); Hawthorne v. Guenther, 
    917 S.W.2d 924
    , 931 (Tex. App.––Beaumont 1996, writ denied); Luxenberg v.
    Marshall, 
    835 S.W.2d 136
    , 141–42 (Tex. App.––Dallas 1992, no writ).
    2
    Miller also argued that the trial court erred because it failed to apply the proper standard of ―no evidence‖ when ruling
    on the motion and it failed to address all three of Miller’s proffered reasons for excuse.
    6
    pay Miller $2,000.00 at the beginning of phase one and another $2,000.00 upon the completion of
    phase one. Shortly after McCarty paid the initial $2,000.00 and Miller began work, Miller
    discovered concrete blocks near the foundation that were apparently part of a previous attempt to
    repair the foundation.
    Miller testified that after he attempted to work around the previous foundation repair work,
    McCarty inquired of him what would be needed to raise the entire south end of the residence (as
    opposed to raising only the southwest corner as had been previously contemplated by the parties).
    Miller advised that this change would require six additional piers added to phase one of the
    contract, an action that would elevate the total cost of phase one by $1,875.00. Miller also
    testified that in order to do the expanded work, he would require one-half of the additional cost (or
    an additional $937.50) before he commenced work. Miller testified that McCarty paid $500.00 of
    the $937.50, but failed to pay the remaining $437.50.
    McCarty admitted having paid Miller the additional $500.00 which Miller mentioned, but
    attributes that additional payment to a very different fact circumstance.         Instead, McCarty
    testified that Miller approached her and said he was broke and needed more money and that plea is
    the sole reason she paid him the additional $500.00. McCarty specifically denied requesting that
    Miller add more piers and, by implication, denies modifying or amending the original contract in
    any way.
    7
    The conflicting evidence raises a fact issue as to whether a new agreement was made. It is
    the jury’s province to resolve conflicts in the evidence. 
    Wilson, 168 S.W.3d at 819
    –20. The jury
    remains the sole judge of witnesses’ credibility and the weight to be given their testimony; it is free
    to accept or reject all or part of a witness’s testimony. Golden Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 761 (Tex. 2003). Having considered all the evidence, we find legally and factually
    sufficient evidence from which the jury could have determined that the parties agreed that a new
    contract would take the place of the original.3 See 
    Bradford, 48 S.W.3d at 754
    . The jury’s
    finding is supported by more than a scintilla of evidence and is not so against the great weight and
    preponderance of the evidence that it is clearly unjust.               Therefore, the trial court erred in
    disregarding the jury’s answer to Question 7, and we reverse that portion of the judgment.
    Legally and Factually Sufficient Evidence to Support the Jury’s Findings
    McCarty’s 80% Negligence
    In her pleadings, McCarty made allegations of violations of the DTPA. At trial, McCarty
    argued that Miller’s negligence was responsible for the damages to her home. While Miller
    admitted to damaging a few patio tiles and some of the brick on the home, he contended that the
    rest of the damages were the result of McCarty’s failure to timely repair the foundation problem or
    the plumbing leak that allegedly caused it.
    3
    The jury did not specify the grounds upon which they found Miller’s breach to be excused. Having found sufficient
    evidence supporting one of Miller’s proffered grounds for excuse, we need not address the others.
    8
    The issues were presented to the jury and, in its answers to Questions 1 and 2, the jury
    found that the negligence of both McCarty and Miller proximately caused the damages. The jury
    found McCarty to be eighty percent negligent and Miller to be twenty percent negligent. In her
    cross-appeal, McCarty argues that there is legally and factually insufficient evidence to support the
    finding that she was eighty percent negligent. We disagree.
    McCarty knew of the home’s foundation problems as early as November 2005, but she did
    not attempt to have them repaired until Miller began work in December 2007.4 Several witnesses
    testified to the condition of the home prior to Miller beginning work. Mike Moon, a plumber,
    testified that he noticed a ―steep‖ downward slope in the floor of the home. Joe Russ, Jr., a
    construction manager for an engineering company that does failure analysis, foundation repair,
    and other construction, testified that he noticed a slope in the floor years prior to McCarty buying
    the house. Just prior to Miller’s work, he was in the home and saw damages consistent with
    foundation problems: the floor had a downward slope to it, the fireplace listed to one side, doors
    would not open or latch, and there were deep cracks in the walls and ―cracks, rips, [and] tears in the
    sheetrock‖ and wall paper.
    McCarty argued that the pre-existing problems with the walls, doors, and molding got
    worse after Miller’s work. McCarty’s expert architect, Mark Glenn, testified to the home’s
    condition several weeks after Miller stopped working on the McCarty residence. Outside, he saw
    4
    In late 2005 and early 2006, McCarty contacted a repair company, received an estimate, and agreed to a contract to
    have her foundation repaired, but McCarty later canceled that contract.
    9
    several large, water-filled holes 5 that were dug under the home, broken pipes, ―jerry-rigged
    electrical and gas connections,‖ damage to a small portion of the home’s brick exterior, and some
    damage to ―small patio slabs.‖ Inside, he observed ―[m]edium to large sized cracks‖ in the
    drywall, doors that were stuck, and separated crown molding. Glenn testified that based on the
    information he was given at the time of his inspection, Miller’s work ―definitely contributed to the
    more extensive damage.‖
    Determining the degree, if any, that the parties’ respective negligence proximately caused
    McCarty’s damages is the province of the jury. See Pearson v. DeBoer, Inc., 
    99 S.W.3d 273
    , 276
    (Tex. App.––Corpus Christi 2003, no pet.); see Smith v. Cent. Freight Lines, Inc., 
    774 S.W.2d 411
    ,
    412 (Tex. App.––Houston [14th Dist.] 1989, writ denied).                       The jury determined that the
    negligence of both Miller and McCarty ―proximately cause[d] the occurrence in question.‖ It is
    the jury’s role to weigh witnesses’ credibility and determine whether McCarty’s conduct
    contributed to her damages, and if so, to what degree. Golden Eagle 
    Archery, 116 S.W.3d at 761
    .
    Here, the jury could have reasonably concluded that McCarty’s two-year delay in repairing the
    foundation was the predominant proximate cause of the wall cracks, jammed doors, sloped floor,
    and other damages, as well as any aggravation thereof. We find the evidence supporting the
    jury’s finding to be more than a scintilla and not so weak or the finding so against the great weight
    5
    There was conflicting testimony regarding whether Miller initially covered the holes and whether McCarty or anyone
    else subsequently removed the tarpaulin covers, causing the holes to fill with water. Glenn testified that failing to
    cover the holes and allowing them to stay filled with water would aggravate the existing foundation problems.
    10
    and preponderance of the evidence that it was clearly wrong and unjust. Therefore, we overrule
    this point of error.
    Failure of McCarty to Comply with Contract
    In its answer to Question 5, the jury found that McCarty failed to comply with the contract.
    McCarty contends that the evidence supporting the finding is legally and factually insufficient.
    We disagree.
    Hereinabove, we found sufficient evidence that the parties agreed that a new contract
    would take the place of the original contract. Under the terms of the modified contract, six
    additional piers were required at an additional cost of $1,875.00. Miller required McCarty to pay
    one-half of the additional cost ($937.50) at the outset. Miller testified that McCarty failed to
    make the required up-front payment. Even though she denied modifying the contract, McCarty
    paid Miller an additional $500.00, but did not pay him the remaining $437.50.
    This issue was contested and a fact issue was presented to the jury, which it resolved
    against McCarty and determined that she failed to comply with the contract. We conclude the
    evidence supporting the finding amounts to more than a scintilla and was not so weak or the
    finding so against the great weight and preponderance of the evidence that it was clearly wrong
    and unjust.
    Issue of Attorney’s Fees
    11
    The parties stipulated that attorney’s fees would be determined by the trial court through
    submitted affidavits. McCarty’s affidavit reflected attorney’s fees of $18,135.00, but the trial
    court awarded McCarty only $14,000.00 in attorney’s fees. McCarty contends that the trial court
    erred by failing to award the $18,135.00 in attorney’s fees because the evidence was undisputed
    and must be taken as true as a matter of law.
    The jury having determined that Miller was excused from performing the contract, Miller
    had no obligation to perform. Had McCarty recovered in her claim of breach of contract, she
    would have been entitled to attorney’s fees. TEX. CIV. PRAC. & REM. CODE ANN. § 38.001(8)
    (Vernon 2008). Because Miller was found by the jury to have been excused from performance,
    he cannot now be held liable for attorney’s fees in a suit to enforce a contract, the performance of
    which he has been excused.
    Accordingly, a discussion of the parameters which guide a trial court in the award of
    attorney’s fees is unnecessary and would be superfluous.
    We overrule this point of error.
    No point of error was raised as to the correctness of Miller’s quantum meruit claim and
    attorney’s fee award. Because there is sufficient evidence that Miller’s breach was excused,
    McCarty did not prevail on her contract claim, and therefore, is not entitled to either damages or
    attorney’s fees. See TEX. CIV. PRAC. & REM. CODE ANN. §§ 38.001–.006 (Vernon 2008 & Supp.
    2010).
    12
    We reverse the awards as to McCarty, as to both damages and attorney’s fees, and render
    judgment that McCarty take nothing.        We further render judgment in favor of Miller in
    accordance with the jury’s verdict.
    Bailey C. Moseley
    Justice
    Date Submitted:       September 8, 2010
    Date Decided:         September 21, 2010
    13