Lani K. White and Charles White v. DR & PA Deliverance, Ltd., F/K/A Deliverance-PAR Services, Ltd. ( 2014 )


Menu:
  • Opinion issued February 25, 2014
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-12-00227-CV
    ———————————
    LANI K. WHITE & CHARLES WHITE, Appellants
    V.
    DR & PA DELIVERANCE, LTD., F/K/A DELIVERANCE-PAR SERVICES,
    LTD., Appellee
    On Appeal from the 344th District Court
    Chambers County, Texas
    Trial Court Case No. CV25059-A
    MEMORANDUM OPINION
    Lani K. White and Charles White appeal a summary judgment in favor of
    DR & PA Deliverance, Ltd., f/k/a Deliverance-Par Services, Ltd. (Deliverance).
    We affirm.
    Background
    In 2005, the Whites bought a home in Baytown, Texas. Movers Specialty
    Services Inc. (MSS) was hired to move the Whites’ appliances. MSS contracted
    with Deliverance to disconnect and reconnect the Whites’ appliances, including
    their electric dryer. Deliverance assigned the job to Patrick Rusk, with whom
    Deliverance had entered into an independent contractor agreement.               Rusk
    connected the electric dryer in the utility room of the Whites’ new home. Almost
    four years later, a gas leak from an uncapped gas line in the Whites’ utility room
    caused an explosion that injured Lani White.
    The Whites sued MSS, Deliverance, Rusk, and others.              They alleged
    Deliverance was negligent for failing to inspect, detect and correct the uncapped
    gas line, for failing to install proper caps for the shutoff valve, and for failing to
    warn the Whites about the dangers of an uncapped gas line.
    Deliverance moved for summary judgment contending it was not vicariously
    liable for Rusk’s alleged negligence because Rusk was an independent contractor,
    not an employee of Deliverance. In their summary-judgment response, the Whites
    argued that, notwithstanding the independent contractor agreement, there was a
    fact issue about whether Rusk was an independent contractor because (1) the
    independent contractor agreement had been modified by a second agreement
    between Deliverance and MSS and (2) other evidence extrinsic to the independent
    2
    contractor agreement raised a fact issue regarding whether Deliverance controlled
    the details of Rusk’s work.
    After a hearing, the trial court granted Deliverance’s motion for summary
    judgment and severed the Whites’ claims against Deliverance.           The Whites
    appealed.
    Discussion
    The Whites challenge the summary judgment on two grounds. They argue
    that an agreement between MSS and Deliverance specifying the procedures by
    which Deliverance was to perform MSS jobs modified Rusk’s independent
    contractor agreement with Deliverance. They also contend that, notwithstanding
    the terms of the independent contractor agreement between Deliverance and Rusk,
    the summary-judgment evidence raised a fact issue about whether, at the time Rusk
    installed the Whites’ dryer, Deliverance exercised actual control over the operative
    details of Rusk’s work.
    A.    Standard of Review and Summary Judgment Standard
    We review a trial court’s grant of summary judgment de novo. Valence
    Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005) (citing Provident Life
    & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215 (Tex. 2003)). When reviewing
    a summary judgment, we must (1) take as true all evidence favorable to the
    nonmovant, and (2) indulge every reasonable inference and resolve any doubts in
    3
    the nonmovant’s favor. 
    Id. In a
    traditional summary judgment motion, the movant
    has the burden to show that no genuine issue of material fact exists and that the
    trial court should grant judgment as a matter of law. TEX. R. CIV. P. 166(a), (c);
    KPMG Peat Marwick v. Harrison Cnty. Hous. Fin. Corp., 
    988 S.W.2d 746
    , 748
    (Tex. 1999).
    B.    Applicable Law
    Under the doctrine of respondeat superior, an employer may be vicariously
    liable for the negligence of its agent or employee who acts within the scope of his
    employment even though the employer did not personally commit a wrong. St.
    Joseph Hosp. v. Wolff, 
    94 S.W.3d 513
    , 542 (Tex. 2002); Baptist Mem’l Hosp. Sys.
    v. Sampson, 
    969 S.W.2d 945
    , 947 (Tex. 1998). But an independent contractor has
    sole control over the means and methods of his work and, therefore, the individual
    or entity that hires the independent contractor is generally not vicariously liable for
    the negligence of that person. 
    Wolff, 94 S.W.3d at 542
    .
    The right to control the details of the work is the supreme test for whether a
    master-servant relationship exists and whether the rule of vicarious liability
    applies. 
    Id. (citing Golden
    Spread Council, Inc. No. 562 of Boy Scouts of Am. v.
    Akins, 
    926 S.W.2d 287
    , 290 (Tex. 1996)).      A right of control requires more than
    a general right to order the work stopped or resumed, to inspect its
    progress or to receive reports, to make suggestions or
    recommendations which need not necessarily be followed, or to
    prescribe alterations and deviations. Such a general right is usually
    4
    reserved to employers, but it does not mean that the contractor is
    controlled as to his methods of work, or as to operative detail. There
    must be such a retention of a right to supervision that the contractor is
    not entirely free to do the work in his own way.
    Koch Refining Co. v. Chapa, 
    11 S.W.3d 153
    , 155 (Tex. 1999) (quoting
    Restatement (Second) of Torts § 414 cmt. c (1965)). Employers may direct when
    and where an independent contractor does the work and may request information
    about the work, but an employer is liable for the independent contractor’s torts
    only if the employer controls the details and methods of the independent
    contractor’s work to such an extent that the contractor cannot perform the work as
    he so chooses. 
    Koch, 11 S.W.3d at 155
    –56; Weidner v. Sanchez, 
    14 S.W.3d 353
    ,
    373 (Tex. App.—Houston [14th Dist.] 2000, no pet.).
    A contract expressly providing that a person is an independent contractor “is
    determinative of the [parties’] relationship absent evidence that the contract is a
    mere sham or subterfuge designed to conceal the true legal status of the parties or
    that the contract has been modified by a subsequent agreement between the
    parties.” Farlow v. Harris Methodist Fort Worth Hosp., 
    284 S.W.3d 903
    , 911
    (Tex. App.—Fort Worth 2009, pet. denied) (citing Newspapers, Inc. v. Love, 
    380 S.W.2d 582
    , 588–90, 592 (Tex. 1964)); 
    Weidner, 14 S.W.3d at 373
    .
    When a contract establishes an independent contractor relationship, evidence
    outside the contract must be produced to show that despite the contract terms, the
    true operating agreement vested the right of control in the principal. 
    Id. at 374
                                             5
    (citing Farrell v. Greater Houston Transp. Co., 
    908 S.W.2d 1
    , 3 (Tex. App.—
    Houston [1st Dist.] 1995, writ denied)). Neither sporadic action directing the
    details of the work nor an occasional assertion of control will destroy the original
    contract forming the basis of the independent contractor relationship. 
    Id. The assumption
    of exercise of control must be so persistent and the acquiescence
    therein so pronounced as to raise an inference that when the accident occurred, the
    parties by implied consent had agreed that the principal might have the right to
    control the details of the work. 
    Id. C. Analysis
    The Independent Contractor Agreement created an independent contractor
    relationship
    Deliverance and Rusk entered into an “Independent Contractor Agreement,”
    in which they agreed that “[Rusk] is an independent contractor, and not the
    employee or agent of [Deliverance] for any purpose whatsoever.”          Other key
    terms of the agreement provide:
    • Deliverance “shall have no right to, and shall not control the manner,
    or prescribe the method, of accomplishing the portion of
    [Deliverance’s] business which shall be performed by [Rusk]
    pursuant to this Agreement.”
    • Rusk has “the right to refuse acceptance of any or any part of
    particular assignments submitted to the Contractor for service” for
    any reason, provided he submits the reason in writing.
    6
    • For jobs tendered, Rusk “shall provide the necessary vehicles, labor
    and materials (except lumber, paper pads) to complete the
    assignment.”
    • Any labor hired by Rusk to complete jobs shall be hired at Rusk’s
    expense, and persons employed by Rusk to perform such labor “shall
    be under the sole direction and control of [Rusk].”
    • Rusk shall complete all documents in accordance with guidelines
    required by Deliverance.
    • Rusk shall furnish, at his expense, worker’s compensation insurance
    for himself and his employees.
    • Rusk agrees to obtain at his expense automobile liability insurance
    and general liability insurance.
    • Rusk was to be paid 40% of the amount Deliverance invoiced the
    customer for each job Rusk performed.
    We agree with Deliverance that the independent contractor agreement
    created an independent contractor relationship between Deliverance and Rusk. We
    thus turn to the question of whether the Whites met their burden to adduce
    summary-judgment evidence raising a fact issue about whether the agreement
    should not be determinative of the parties’ relationship either because it was
    modified by a subsequent agreement or because other extrinsic evidence raises a
    fact issue about whether Deliverance exercised control over the details and
    methods of Rusk’s work, despite the terms of the independent contractor
    agreement.
    7
    The Whites’ summary judgment evidence failed to raise a fact issue
    regarding whether the independent contractor agreement is determinative
    a. The MSS agreement and MSS’s Suggested Operating Procedures
    The Whites argue that Rusk’s independent contractor agreement was
    modified when Deliverance and MSS entered into their own contract, in which
    Deliverance agreed to perform all work for MSS in accordance with MSS’s
    Suggested Operating Procedures and manual. They contend that the step-by-step
    procedures set forth in MSS’s service guidelines dictated the details and methods
    of the work of those working for Deliverance, including Rusk, to the extent that
    they wrested control over the methods and details of the work from Rusk. The
    Whites’ summary-judgment evidence showed that Deliverance trained Rusk on
    MSS’s guidelines and policed compliance with them by periodically circulating
    memoranda reminding Rusk that he would be docked pay for failing to comply.
    We note, first, that the record contains only an unsigned version of an
    agreement between MSS and Deliverance Movers Service (“DMS”), which is not a
    party to this appeal.   The record contains no evidence of the nature of the
    relationship between DMS and Deliverance, nor does it indicate that MSS and
    DMS intended to be bound by the agreement despite the lack of signatures. The
    Whites contend the agreement is binding on Deliverance because Deliverance
    produced it in response to a request for production. We indulge doubts and
    reasonable inferences in the Whites’ favor, but, here, the Whites urge us to stack
    8
    one inference upon another: (1) the contract was binding on DMS despite the lack
    of signatures or evidence demonstrating an intent to be bound in their absence and
    (2) the contract also bound Deliverance, despite the fact that it is nowhere
    mentioned in the agreement, because Deliverance is a successor to DMS. See
    Marathon Corp. v. Pitzner, 
    106 S.W.3d 724
    , 728 (Tex. 2003) (an inference stacked
    only on other inferences is not legally sufficient evidence); Zavala v. Burlington N.
    Santa Fe Corp., 
    355 S.W.3d 359
    , 373 (Tex. App.—El Paso 2011, no pet.)
    (“Stacking inferences is insufficient to create a fact issue precluding summary
    judgment.”).
    b. Other extrinsic evidence
    The Whites contend that summary-judgment evidence other than the MSS
    agreement and guidelines raised a fact issue regarding whether Rusk’s independent
    contractor agreement was determinative of the parties’ relationship. Deliverance,
    the movant, relied primarily on Rusk’s independent contractor agreement and the
    affidavit of Paul Arena to prove that Rusk independently controlled the details and
    methods of his work and that it was entitled to judgment as a matter of law. In
    response, the Whites argued that Rusk’s affidavit raised a fact issue as to Rusk’s
    independent contractor status.
    We examine the summary-judgment evidence against the five Limestone
    factors: (1) the independent nature of the worker’s business; (2) the worker’s
    9
    obligation to furnish necessary tools, supplies, and materials to perform the job;
    (3) the worker’s right to control the progress of the work except about final results;
    (4) the time for which the worker is employed; and (5) the method of payment,
    whether the worker is paid by time or by the job. Limestone Prods. Distrib., Inc. v.
    McNamara, 
    71 S.W.3d 308
    , 312 (Tex. 2002).
    In addition to the independent contractor agreement, the terms of which are
    outlined above, Deliverance offered the Arena affidavit, which established the
    following undisputed facts:
    • Rusk had the right to refuse all or any part of a work assignment.
    • No employees or agents of Deliverance oversaw or were present while
    Rusk worked at the Whites’ home, and none inspected Rusk’s work.
    • Rusk was paid on a form 1099 and did not receive W-2 forms.
    • Rusk received no pay if there was no work, and Deliverance did not pay
    Rusk for vacation time, sick leave or holidays.
    • Rusk was responsible for hiring, supervising and paying any labor
    required to complete his work.
    • Rusk was responsible for all costs and expenses incurred by him or any
    of his employees while completing his work.
    • Rusk paid state and federal income tax, unemployment insurance, and
    Social Security benefits for himself and his employees.
    • Rusk maintained general liability insurance naming Deliverance as an
    insured.
    • Rusk was liable for any property damage he or his employees caused.1
    1
    Arena also averred that “Rusk was an independent contractor hired by
    Deliverance,” but we accord that legal conclusion no evidentiary value. The same
    is true for Rusk’s statement in his affidavit that “Deliverance controlled all the
    specifics of my work.” See Anderson v. Snider, 
    808 S.W.2d 54
    , 55 (Tex. 1991)
    (legal conclusions and conclusory statements are not proper summary-judgment
    evidence).
    10
    The Whites adduced no summary-judgment evidence controverting these
    facts. Rather, they offered Rusk’s affidavit, which makes the following key points:
    • Rusk was required to report to Deliverance’s office by 8:00 a.m. six days
    a week and worked up to 80 hours each week.
    • Each morning, Deliverance gave him a list of jobs that he was required to
    complete by the end of the day.
    • Rusk was required to call Deliverance dispatch at the completion of each
    individual job he completed throughout the day.
    • Deliverance provided Rusk with 6 weeks of training on packing, crating
    and installation policies and procedures. Rusk was required to follow
    these procedures and was docked in pay if he did not.
    • Deliverance required Rusk to wear uniforms bearing Deliverance’s logo,
    fill out a Deliverance checklist indicating that he had completed various
    aspects of the job and, when introducing himself to customers, was
    required to “announce that [he] worked for Deliverance.”
    • Rusk worked exclusively for Deliverance for nearly four years, during
    which time he considered himself a Deliverance employee.
    The Whites also adduced evidence that Rusk entered into a non-competition
    agreement with Deliverance.
    The first Limestone factor relates to the independent nature of the business
    and, in particular, who has the right to control the details and methods of the work.
    
    Limestone, 71 S.W.3d at 312
    ; 
    Wolff, 94 S.W.3d at 542
    . The summary-judgment
    record demonstrates that Rusk could refuse any job, was solely responsible for
    deciding whether to hire additional labor for any job, and performed the work
    without physical oversight or inspection by Deliverance. Deliverance’s evidence
    thus demonstrated that Rusk was “free to do the work in his own way.” See 
    Koch, 11 S.W.3d at 155
    ; 
    Limestone, 71 S.W.3d at 312
    .
    11
    The Whites nevertheless argue that Rusk’s business was not independent
    because Rusk (1) was required to follow detailed procedures, report to
    Deliverance’s office by 8:00 a.m. each morning, work long hours, and call dispatch
    at the completion of each job, and (2) believed himself to be an employee of
    Deliverance and gave customers the impression that he was a Deliverance
    employee. The evidence that Deliverance exercised the right to determine when
    Rusk would begin work, to require reports, and to suggest methods for
    accomplishing the work safely and cost-effectively, even taken together, falls short
    of raising a fact issue because none of it suggests that Deliverance persistently
    controlled the methods and operative details of the work. See 
    Limestone, 71 S.W.3d at 312
    (affirming summary judgment as to independent contractor status
    where worker called Limestone daily to see if there was any work, was told where
    to pick up and deliver loads, was given deadlines for completing each job, and was
    required to use load tickets bearing Limestone logo for each job); Hoechst-
    Celanese Corp. v. Compton, 
    899 S.W.2d 215
    , 221 (Tex. App.—Houston [14th
    Dist.] 1994, writ denied) (noting that key inquiry is control, not a worker’s belief
    as to his status or general supervision of time or place of work, or manner of
    worker’s dress); 
    Farlow, 284 S.W.3d at 916
    (hospital bylaws contractually
    requiring doctor to provide treatment in specified ways were results-oriented only
    and did not raise a fact issue regarding independent contractor relationship); Koch,
    
    12 11 S.W.3d at 155
    (right to order work stopped or resumed, receive progress
    reports, make suggestions or recommendations, prescribe alterations does not mean
    that contractor is controlled as to his methods of work or as to operative detail).
    The evidence relating to the second factor—the obligation to furnish
    necessary tools and materials—favors Deliverance. The undisputed evidence is
    that Rusk was responsible for the expense of necessary labor, tools, and materials.
    The record shows that Deliverance provided some materials to Rusk, apparently to
    take advantage of volume discounts, but the Whites do not dispute that Rusk
    nevertheless was obligated to pay for them.
    The third factor—the right to control the progress of the work—also
    suggests Rusk was an independent contractor. Deliverance exercised the right to
    tell Rusk when to start work and which jobs to do—Rusk was expected to be in the
    office at 8:00 a.m. to pick up daily job assignments—but this is not inconsistent
    with an independent contractor relationship. 
    Koch, 11 S.W.3d at 155
    (right of
    control requires more than a general right to order work stopped or resumed). Nor
    is the fact that Rusk was required to inform Deliverance that he had completed
    work. 
    Id. (right of
    control requires more than right to receive reports). And it is
    undisputed that Rusk, after learning which jobs were assigned to him, was
    responsible for contacting customers and scheduling a time in which to do the job.
    13
    Under the fourth factor, we examine the time for which the person is
    employed. Rusk worked exclusively for Deliverance for nearly four years, and the
    Whites rely heavily on this fact, and the existence of a non-competition agreement,
    to argue for employee status. But courts have concluded persons were independent
    contractors in cases involving far longer tenures. See Mid-Continent Cas. Co. v.
    Davis, 
    683 F.3d 651
    , 658 (5th Cir. 2012) (finding workers were independent
    contractors despite 17 and 18 year tenures where they got paid only if they
    worked). Likewise, the existence of a non-compete is unrelated to the central issue
    of control over methods and operative detail of the work.
    The evidence relevant to the fifth factor is undisputed. Rusk was paid by the
    job and only upon completion of a job, receiving no pay if there was no work. In
    sum, application of the Limestone factors requires affirmance.
    The Whites rely heavily on Weidner v. Sanchez, 
    14 S.W.3d 353
    (Tex.
    App.—Houston [14th Dist.] 2000, no pet.) to argue for a different result. There,
    Weidner, a cab driver, and Liberty Cab had a Daily Pay Agreement that recited
    that Weidner was an independent contractor. 
    Weidner, 14 S.W.3d at 374
    . The
    court of appeals held there was ample evidence that a subsequent agreement
    between Liberty Cab and Metro modified the Daily Pay Agreement and that
    Liberty exercised such control over Weidner that he was not an independent
    contractor in the transaction at issue. Weidner is different for two reasons. First,
    14
    here, we have concluded that the summary-judgment evidence did not raise a fact
    issue as to whether the MSS agreement modified Rusk’s independent contractor
    relationship. Second, and more important, in Weidner, the cab driver was paid by
    the hour and the details of his work—driving—were dictated by Liberty Cab to the
    degree that “precious little was left to Weidner’s discretion on the day of the
    accident.” 
    Id. at 375
    (noting that “a salaried school bus driver probably has more
    discretion than Weidner”).     Here, while Rusk was required to follow results-
    oriented procedures, go to Deliverance’s office each morning, meet deadlines, and
    periodically report on the progress of his work, there is no indication that he lacked
    discretion as to the operative details of his work—installing the Whites’ dryer. See
    
    Farlow, 284 S.W.3d at 916
    (hospital bylaws contractually requiring doctor to
    provide treatment in specified ways did not raise a fact issue as to independent
    contractor status); 
    Koch, 11 S.W.3d at 155
    (right to order work stopped or
    resumed, receive progress reports, make suggestions or recommendations,
    prescribe alterations does not mean that contractor is controlled as to his methods
    of work or as to operative detail).
    15
    Conclusion
    We affirm the trial court’s judgment.
    Rebeca Huddle
    Justice
    Panel consists of Chief Justice Radack and Justices Bland and Huddle.
    16