Safeco Surety and C. A. Walker Construction v. J.P. Southwest Concrete, Inc. ( 2013 )


Menu:
  • Opinion issued October 29, 2013
    In The
    Court of Appeals
    For The
    First District of Texas
    NO. 01-12-00672-CV
    SAFECO SURETY AND C.A. WALKER CONSTRUCTION, Appellants
    V.
    J.P. SOUTHWEST CONCRETE, INC., Appellee
    On Appeal from the 189th District Court
    Harris County, Texas
    Trial Court Cause No. 2005-70198
    MEMORANDUM OPINION
    This is the second appeal in this dispute between C.A. Walker Construction
    and Safeco Surety (collectively “Walker”) and J.P. Southwest Concrete, Inc.
    (“J.P.”). See C.A. Walker Constr. Co. v. J.P. Sw. Concrete, Inc., No. 01-07-00904-
    CV, 
    2009 WL 884754
    (Tex. App.—Houston [1st Dist.] Apr. 2, 2009, no pet.)
    (mem. op.). In the first appeal, we remanded for a new trial on damages. Walker
    now appeals from the trial court’s judgment on remand, which awarded J.P.
    $74,193.90 in actual damages, as well as attorney’s fees and pre- and post-
    judgment interest. Walker contends that the trial court erred in allowing J.P. to
    present new damages theories and evidence that were precluded by our 2009
    opinion in this case. It also challenges the trial court’s findings of fact and
    conclusions of law and contends that the evidence is legally and factually
    insufficient to support the judgment. We modify the trial court’s judgment to
    exclude the award of retainage in the amount of $7,105.28, and we affirm the
    judgment as modified.
    Background
    2007 Trial and First Appeal
    Our first opinion sets forth in detail the factual background that gave rise to
    this dispute. Walker was the general contractor on a Spring Branch Independent
    School District construction project. J.P. was a subcontractor. In their written
    contract, Walker agreed to pay J.P. $243,000 to do all the concrete work for the
    project. The contract price for J.P.’s work was later revised via change orders to
    $274,149.
    2
    When J.P. began work in September 2004, it encountered severe subsoil
    obstructions that prevented it from drilling pier holes. Walker instructed J.P. to
    prepare and submit written change orders to cover the removal of the obstructions.
    J.P. submitted a number of written change orders, but Walker only approved some
    of them.
    The contract provided that J.P. would be paid in monthly installments as the
    work progressed. Accordingly, as work on the project progressed, J.P. submitted
    applications for payment along with supporting documentation. As of December
    2004, J.P. had been paid $57,349.25. In January 2005, J.P. requested further
    payment of $79,796. Later, J.P. sought payment of $17,099 for work done in
    February 2005. On March 16, 2005, Walker paid J.P. $84,756.35. In exchange for
    that payment, J.P.’s president, Jeff Pantle, executed a “Subcontractor Affidavit of
    Payment and Partial Release of Lien” on behalf of J.P. The release states that the
    payment received on March 16, 2005 “constitutes full payment for the work
    performed to date and any and all change orders or claims for additional work
    performed.” The release further provides:
    Subcontractor waives, releases, relinquishes and discharges all known
    and unknown causes of action, including, but not limited to those
    arising out of contract, by statute, in tort or otherwise, and waives,
    releases, relinquishes and agrees to discharge any suits, debts,
    accounts, bonds, contracts, promises, damages, liens, encumbrances,
    judgments, claims and demands whatsoever, in law or equity, which
    3
    are against the Contractor . . . that the Subcontractor now has or might
    hereinafter obtain that relates directly or indirectly to the aforesaid
    relationship, Contract, and/or Project.
    J.P.’s work on the project continued after it entered into the release. Walker
    told J.P. that subsoil debris and obstructions had been removed and requested it
    continue drilling pier holes. J.P. went to the site, bringing with it another drilling
    subcontractor, but was unable to perform the work due to subsoil debris and
    obstructions. J.P.’s last day at the site was March 22, 2005. Walker acknowledged
    that it owed J.P. for work that was done after March 16, but contended the amount
    owed was only $2,848.
    For several months, J.P. attempted to collect payment from Walker. J.P.
    eventually sued for breach of contract, and Walker counterclaimed. In its pre-trial
    disclosures and at the 2007 bench trial, J.P. asserted that it was entitled to recover
    the following damages: $19,501 for unpaid work and $58,000 for lost profits, for a
    total of $77,501.
    However, in its motion for entry of judgment filed several weeks after trial,
    J.P. sought new and different damages. The motion asserted J.P. was entitled to
    recover damages in the amount of $74,059.52, consisting of the following:
    • $17,099 for unpaid contract work in February 2005;
    • $21,748.52 for unpaid contract work in March 2005;
    4
    • $8,389 for retainage;
    • $26,823 for extra work completed for unsigned change orders; and
    • $3,600 for attorney’s fees J.P. paid Transit Mix, another
    subcontractor on the project, after Transit Mix sued J.P. to recover
    payment for supplies Transit Mix provided for the project.
    In addition, instead of the $58,000 originally sought for lost profits, J.P. requested
    a lost profits award of $26,499.05. The trial court rendered judgment, awarding
    J.P. $47,000 in damages, but did not indicate how it reached that figure. It entered
    no findings of fact or conclusions of law.
    In Walker’s first appeal, we reversed the trial court’s damages award, but
    otherwise affirmed the judgment. We held that J.P. released all claims for any
    amounts due for work performed before March 16, 2005 by signing the March 16,
    2005 release and that “any lost profits incurred before March 16, 2005 are not
    properly included in the award.” C.A. Walker Constr. Co., 
    2009 WL 884754
    , at
    *5–6.    With respect to lost profits, we concluded that J.P. failed to present
    “objective facts, figures, or data from which the amount of lost profits can be
    ascertained” and that therefore “the evidence [was] factually insufficient to support
    an award of lost profits.” 
    Id. at *6.
    In addition, we held that J.P. was not entitled
    to “any damages for a suit filed against J.P. by Transit Mix for services or
    materials, or the attorney’s fees incurred by Transit Mix and paid by J.P,” because
    5
    the plain language of the parties’ contract excused Walker from paying any
    damages for a suit filed against J.P. 
    Id. at *7.
    Finally, we held that Texas Rule of
    Civil Procedure 193.6 precluded J.P.’s recovery of damages that had not been
    disclosed before trial. TEX. R. CIV. P. 193.6, 194.2(d); C.A. Walker Constr. Co.,
    
    2009 WL 884754
    , at *7. We concluded that the trial court erred in awarding
    $47,000 in damages, “because the figure could not have been reached without
    taking into consideration amounts that were disclaimed by the release, were for lost
    profits, were for Transit Mix’s lawsuit, or were not properly disclosed before post
    trial.”    C.A. Walker Constr. Co., 
    2009 WL 884754
    , at *8. Accordingly, we
    remanded the case to the trial court “for the limited purpose of conducting a new
    trial on the issue of damages.” 
    Id. at *8.
    New Trial on Damages and Second Appeal
    On remand, Walker moved for summary judgment, asking the trial court to
    enter judgment awarding J.P. $2,848 in damages. Walker contended this was the
    only amount supported by evidence that had not been rejected by this Court’s
    opinion. The trial court denied the motion.
    Before the retrial, J.P. timely supplemented its responses to Walker’s
    requests for disclosure and disclosed an expert witness.         The supplemental
    responses reflected J.P.’s intent to seek damages in the amount of $38,000 for
    6
    unpaid labor, services, goods, and materials for work that J.P. performed between
    March 16, 2005 and March 22, 2005, $10,355 for retainage, and $48,355 for lost
    profits. J.P. also timely designated Lane Parish as a testifying expert on lost
    profits, produced Parish’s report, served new discovery requests on Walker, and
    sought an additional deposition. Walker objected to the supplementation and new
    discovery on the grounds that they were precluded by our opinion, but the trial
    court permitted them. Walker propounded no discovery and did not seek to depose
    Parish.
    The trial court held a bench trial on damages. At the trial, Walker objected
    to the admission of new evidence of damages disclosed on remand, but the trial
    court overruled Walker’s objections.
    At trial, Pantle testified about the work J.P. performed for Walker between
    March 16, 2005 and March 22, 2005. He testified about the number of employees
    that were on site on each day, the work they performed, the tools, materials, and
    equipment that were used each day, and the cost for each. He testified that the
    total amount due for work performed on those dates was $30,422.23.
    Pantle also testified that J.P. was seeking $7,105.28 in damages for
    retainage. Under the parties’ contract, Walker would pay J.P. progress payments
    equal to 95% of the value of J.P.’s work but retain the other five percent as
    7
    retainage until the end of the term of the contract. Pantle testified that J.P. was
    owed the retainage for work performed through March 16, $7,105.28.
    J.P.’s expert, Lane Parish, testified that J.P. was entitled to lost profits in the
    amount of $36,642.39. Parish testified that he used information from the start date
    to the end date of the job to calculate J.P.’s “job profit percentage.” To determine
    that percentage, he subtracted the cost of the work performed through March 16
    from the total amount J.P. was paid for that work plus five percent retainage, and
    then divided that gross profit by the total amount paid plus five percent retainage.
    This yielded a job profit percentage of 27.75%. Parish then applied this percentage
    to the outstanding total contract amount that was reflected on the March 16, 2005
    release, $132,043.40, and this yielded a lost profit figure of $36,642.39.
    The trial court signed a final judgment awarding damages to J.P. in the
    amount of $74,193.90, carrying forward the award of attorney’s fees awarded in
    the first judgment and awarding fees for the new trial and conditional appellate
    fees, and awarding pre- and post-judgment interest. The trial court also entered
    findings of fact and conclusions of law. According to the trial court’s findings of
    fact, the $74,193.90 damages award is comprised of $30,442.23 for unpaid labor,
    goods, services, and materials, $7,105.28 for retainage, and $36,646.39 in lost
    profits.
    8
    Law of the Case and Scope of Remand
    In its first issue, Walker argues that our first opinion and the law of the case
    doctrine precluded the trial court’s consideration of new damages theories and
    evidence that had not been disclosed before the first trial on the merits.
    A. Applicable Law
    When we remand a cause to the trial court for a new trial, the remand is
    generally unlimited in scope and the cause is reopened in its entirety. See Cedillo
    v. Gaitan, 
    981 S.W.2d 388
    , 390 (Tex. App.—San Antonio 1998, no pet.). We may
    limit our remand to include only certain issues, as stated in the mandate. Cessna
    Aircraft Co. v. Aircraft Network, LLC, 
    345 S.W.3d 139
    , 144 (Tex. App.— Dallas
    2011, no pet.) (“When an appellate court remands a case with specific instructions,
    the trial court is limited to complying with the instructions and cannot re-litigate
    issues controverted at the former trial.”). The scope of the remand is determined
    by referring to both the appellate opinion and to the mandate itself. See Hudson v.
    Wakefield, 
    711 S.W.2d 628
    , 630 (Tex. 1986) (in interpreting mandate of appellate
    court, “courts should look not only to the mandate itself, but also to the opinion of
    the court”).
    Under the law of the case doctrine, “questions of law decided on appeal . . .
    will govern the case throughout its subsequent stages” and therefore “a court of
    9
    appeals is ordinarily bound by its initial decision if there is a subsequent appeal in
    the same case.” Briscoe v. Goodmark Corp., 
    102 S.W.3d 714
    , 716 (Tex. 2003);
    
    Hudson, 711 S.W.2d at 630
    . “By narrowing the issues in successive stages of the
    litigation, the law of the case doctrine is intended to achieve uniformity of decision
    as well as judicial economy and efficiency.” 
    Briscoe, 102 S.W.3d at 716
    (quoting
    
    Hudson, 711 S.W.2d at 630
    ). The law of the case applies only to questions of law
    and does not apply to questions of fact. 
    Hudson, 711 S.W.2d at 630
    .
    B. Analysis
    Our first opinion stated that we were remanding the case “for the limited
    purpose of conducting a new trial on the issue of damages.” C.A. Walker Constr.
    Co., 
    2009 WL 884754
    , at *8. Our mandate stated that the cause was remanded
    “for the limited purpose of conducting a new trial on the issue of the amount of the
    amount [sic] of damages.” We otherwise affirmed the judgment of the trial court.
    Walker argues that the trial court exceeded the scope of the remand in three ways.
    First, Walker argues that our original opinion precluded J.P. from introducing
    evidence of damages that had not been disclosed before the first trial. Second,
    Walker argues that our holding that the release bars J.P. from recovering damages
    for work performed before March 16, 2005 also bars J.P. from recovering an award
    of retainage attributable to work performed during that period of time. Third,
    10
    Walker argues that the trial court impermissibly entered findings of fact and
    conclusions of law regarding matters beyond the limited scope of the remand. We
    address these issues in turn.
    1. Does Rule 193.6 preclude J.P. from seeking damages in amounts that
    had not been disclosed before the first trial?
    Walker urges that this Court’s holding that Rule 193.6 precluded J.P. from
    recovering damages not disclosed before the first trial became the “law of the
    case,” and, therefore, J.P. was limited on remand to recovering only the amount of
    damages disclosed before the first trial. We disagree. When a new trial is ordered,
    the case is reopened in its entirety except to the extent that any limiting instructions
    are provided. See 
    Hudson, 711 S.W.2d at 630
    ; Manon v. Solis, 
    142 S.W.3d 380
    ,
    386 (Tex. App.—Houston [14th Dist.] 2004, pet. denied); 
    Cedillo, 981 S.W.2d at 390
    . Here, the new trial was limited to the issue of damages, but it was not
    otherwise limited, and J.P. was therefore not precluded, in the trial court’s
    discretion, from amending its disclosures or seeking additional discovery on
    remand. See Dillard Dep’t Stores, Inc. v. Hall, 
    909 S.W.2d 491
    , 492 (Tex. 1995)
    (scope of discovery is within the trial court’s discretion); 
    Hudson, 711 S.W.2d at 630
    ; 
    Manon, 142 S.W.3d at 386
    ; 
    Cedillo, 981 S.W.2d at 390
    .
    Walker argues that “[t]he punitive impact of the exclusionary mandate set
    forth in rule 193.6 would be eviscerated” if parties are permitted to introduce new
    11
    evidence after remand for a new trial. However, on remand for a new trial, the
    case is again in a pre-trial posture. And as we explained in our previous opinion,
    the purpose of Rule 193.6 “is to prevent trial by ambush” by requiring a party to
    “make, amend, or supplement a discovery response in a timely manner.” C.A.
    Walker Constr. Co., 
    2009 WL 884754
    , at *7 (quoting Harris Cnty. v. Inter Nos,
    Ltd., 
    199 S.W.3d 363
    , 367 (Tex. App.—Houston [1st Dist.] 2006, no pet.). Walker
    does not argue that J.P. failed to disclose its damage model before the retrial.
    Accordingly, J.P. was not precluded by Rule 193.6 from adducing on remand
    damages evidence that had not been disclosed before the first trial.
    We overrule this subpart of Walker’s first issue.
    2. Does the release preclude J.P.’s recovery of the retainage award?
    Walker next contends that our holding that the release bars J.P.’s recovery
    for amounts it is owed on account of pre-March 16, 2005 work is the law of the
    case, and it bars J.P. from recovering the retainage due on J.P.’s pre-March 16
    work. See 
    Hudson, 711 S.W.2d at 630
    . We agree. In the first appeal, we
    concluded that “by signing the release, J.P. acknowledged it was fully paid for all
    work it had performed as of March 16, 2005.” C.A. Walker Constr. Co., 
    2009 WL 884754
    , at *5. Accordingly, J.P. cannot recover for any amounts attributable to
    work performed as of March 16, 2005.
    12
    Walker argues that the $7,105.28 retainage award is attributable to work
    performed before March 16, 2005, and it is therefore unrecoverable. The record
    demonstrates that the amount the trial court awarded for retainage, $7,105.28, is
    five percent of $142,105.60, which is the amount J.P. had been paid as of March
    16, 2005.
    J.P. nevertheless contends it is not barred from recovering this retainage,
    because J.P. was not entitled to collect it until Walker made the final payment due
    under the contract. Accordingly, J.P. argues that its right to receive the retainage
    had not arisen as of March 16, 2005, and therefore the March 16, 2005 release
    could not operate as a release of the retainage.
    The March 16, 2005 release is broad. It states that the payment received on
    that date “constitutes full payment for the work performed to date and any and all
    change orders or claims for additional work performed.” It also states that J.P.
    waived, released, relinquished, and discharged all debts, claims and demands
    “whatsoever, in law or equity, which are against [Walker] . . . that [J.P.] now has
    or might hereinafter obtain that relates directly or indirectly to the abovesaid
    relationship, Contract, and/or Project.” (Emphasis added). It does not expressly
    carve out unpaid retainage, and it does expressly release even those claims that
    would arise in the future, provided they related to pre-March 16 work. The plain
    13
    language of the release thus bars recovery of the retainage award. And we have
    already held that “by signing the release, J.P. acknowledged it was fully paid for all
    work it had performed as of March 16, 2005.” 
    Id. at *5.
    Accordingly, we hold
    that the trial court erred in awarding J.P. the five percent retainage for work
    performed on or before March 16. See 
    Briscoe, 102 S.W.3d at 716
    (court of
    appeals is bound by its initial decision if there is a subsequent appeal in the same
    case); see also Keck, Mahin & Cate v. Nat’l Union Fire Ins. Co., 
    20 S.W.3d 692
    ,
    698 (Tex. 2000) (broad release releases all claims pertaining to subject matter).
    We sustain Walker’s first issue with respect to the $7,105.28 award of
    retainage.
    3. Findings of Fact and Conclusions of Law
    Walker complains that the trial court entered findings of fact and
    conclusions of law regarding matters outside the scope of our remand.
    Specifically, Walker complains that the trial court entered findings and conclusions
    related to liability, and it did not limit its findings and conclusions to the issue of
    damages. But we cannot ascertain, and Walker does not explain, how, if at all,
    14
    these findings and conclusions caused the rendition of an improper judgment. * See
    TEX. R. APP. P. 44.1(a); McWhorter v. Sheller, 
    993 S.W.2d 781
    , 786 (Tex. App.—
    Houston [14th Dist.] 1999, pet. denied) (overruling issue regarding alleged errors
    in findings of fact and conclusions of law where party did not explain how alleged
    errors caused the rendition of an improper judgment).
    We overrule this subpart of Walker’s first issue.
    Factual and Legal Sufficiency
    In its second issue, Walker contends that the evidence is legally and
    factually insufficient to support the trial court’s judgment, findings of fact, and
    conclusions of law.
    A. Standard of Review
    In an appeal from a bench trial, we review a trial court’s conclusions of law
    de novo. Zenner v. Lone Star Striping & Paving, L.L.C., 
    371 S.W.3d 311
    , 314
    (Tex. App.—Houston [1st Dist.] 2012, pet. denied) (citing BMC Software Belgium,
    *
    To the extent that Walker is complaining here about the trial court’s award to J.P.
    of attorney’s fees for the first appeal in the second judgment, we note that in the
    first appeal, in addition to remanding the cause for a new trial on damages, this
    Court affirmed the trial court’s take-nothing judgment against Walker as well as
    the remainder of the judgment, which held Walker liable for breach of contract.
    C.A. Walker Constr. Co. v. J.P. Sw. Concrete, Inc., No. 01-07-00904-CV, 
    2009 WL 884754
    , at *8 (Tex. App.—Houston [1st Dist.] Apr. 2, 2009, no pet.) (mem.
    op.). Under these circumstances, the trial court did not abuse its discretion in
    awarding attorney’s fees for the first appeal to J.P. See Weaver v. Jamar, 
    383 S.W.3d 805
    , 813 (Tex. App.—Houston [14th Dist.] 2012, no pet.) (award of
    attorney’s fees for breach of contract is reviewed for abuse of discretion).
    15
    N.V. v. Marchand, 
    83 S.W.3d 789
    , 794 (Tex. 2002)). We will uphold the
    conclusions on appeal if the judgment can be sustained on any legal theory
    supported by the evidence. 
    Id. at 314–15.
    A trial court’s conclusions of law may
    not be challenged for factual sufficiency of the evidence, but we may review the
    legal conclusions drawn from the facts to determine their correctness. 
    Id. at 314.
    In an appeal from a bench trial, the trial court’s findings of fact have the
    same weight as a jury verdict. Catalina v. Blasdel, 
    881 S.W.2d 295
    , 297 (Tex.
    1994); Nguyen v. Yovan, 
    317 S.W.3d 261
    , 269–70 (Tex. App.—Houston [1st Dist.]
    2009, pet. denied). We review a trial court’s findings of fact under the same legal
    and factual sufficiency of the evidence standards used when determining whether
    sufficient evidence exists to support an answer to a jury question. 
    Catalina, 881 S.W.2d at 297
    ; 
    Nguyen, 317 S.W.3d at 270
    .
    The test for legal sufficiency is “whether the evidence at trial would enable
    reasonable and fair-minded people to reach the verdict under review.” City of
    Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex. 2005). In making this determination,
    we credit evidence favoring the findings if a reasonable factfinder could and
    disregard contrary evidence unless a reasonable factfinder could not. See 
    id. at 822.
      Although we consider the evidence in the light most favorable to the
    challenged findings, indulging every reasonable inference that supports them, we
    16
    may not disregard evidence that allows only one inference. 
    Id. at 822.
    In reviewing a factual sufficiency issue, we consider all the evidence
    supporting and contradicting the finding. Plas—Tex, Inc. v. U.S. Steel Corp., 
    772 S.W.2d 442
    , 445 (Tex. 1989). We set aside the verdict only if the finding is so
    contrary to the overwhelming weight of the evidence as to be clearly wrong and
    unjust. Pitts & Collard, L.L.P. v. Schechter, 
    369 S.W.3d 301
    , 312 (Tex. App.—
    Houston [1st Dist.] 2011, pet. dism’d by agr.) (citing Cain v. Bain, 
    709 S.W.2d 175
    , 176 (Tex. 1986)).
    The trial court, as finder of fact, is the sole judge of the credibility of the
    witnesses and the weight to be given their testimony. City of 
    Keller, 168 S.W.3d at 819
    ; Salomon v. Lesay, 
    369 S.W.3d 540
    , 549 (Tex. App.—Houston [1st Dist.]
    2012, no pet.).    The factfinder may believe or disbelieve the testimony of a
    witness, in whole or in part, and it may resolve any inconsistencies in a witness’s
    testimony. 
    Salomon, 369 S.W.3d at 549
    . We may not pass upon the witnesses’
    credibility or substitute our judgment for that of the factfinder, even if the evidence
    would clearly support a different result. Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 407 (Tex. 1998).
    B. Analysis
    In its second issue, Walker argues that the evidence presented at the new
    17
    trial on damages was legally and factually insufficient to support the judgment.
    First, Walker argues that the trial court erroneously admitted Exhibit 33, a
    compilation of J.P.’s business records supporting its claim for damages for unpaid
    work and for lost profits, and that, without Exhibit 33, insufficient evidence
    supports the award of $30,442.23 for unpaid labor, goods, services, and materials
    and the award of $36,646.39 for lost profits. Walker next argues that Parish’s lost
    profits calculation was impermissibly based on work performed and amounts paid
    for work performed before March 16, 2005 and was based on unreliable evidence.
    Walker also argues that the trial court abused its discretion in considering
    testimony by Pantle that contradicted his testimony in the 2007 trial. Finally,
    Walker contends that the trial court abused its discretion in admitting testimony on
    attorney’s fees that had not been disclosed before the new trial on damages. We
    address each contention in turn.
    1. Exhibit 33
    Walker asserts that the trial court erred in admitting Exhibit 33, a
    compilation of J.P.’s records reflecting the costs J.P. incurred on the project.
    Exhibit 33 was admitted as a business record and sponsored by J.P.’s president,
    Pantle, who testified that the documents within Exhibit 33 supported J.P.’s claim
    for unpaid work. Relying on Texas Rule of Civil Procedure 193.6, Walker argues
    18
    that Exhibit 33 should have been excluded, because it was not timely disclosed.
    J.P. agreed that the documents that made up Exhibit 33 were not produced to
    Walker before trial, but argued that Walker knew that the documents existed, were
    being relied upon by J.P.’s lost profits expert, and were available for review at
    J.P.’s counsel’s office if Walker had asked to review them.
    A party’s failure to provide complete responses to discovery results in
    automatic exclusion of the evidence, unless the trial court finds good cause or lack
    of unfair surprise or prejudice. TEX. R. CIV. P. 193.6; see Dyer v. Cotton, 
    333 S.W.3d 703
    , 717 (Tex. App.—Houston [1st Dist.] 2010, no pet.); Norfolk S. Ry.
    Co. v. Bailey, 
    92 S.W.3d 577
    , 580–81 (Tex. App.—Austin 2002, no pet.). The
    burden of establishing good cause, lack of unfair surprise, or lack of unfair
    prejudice is on the party seeking to introduce the evidence or call the witness.
    TEX. R. CIV. P. 193.6(b); 
    Dyer, 333 S.W.3d at 717
    . The trial court has discretion in
    determining whether good cause or lack of unfair surprise exists. TEX. R. CIV. P.
    193.6(b); 
    Dyer, 333 S.W.3d at 717
    .
    Here, Walker contends that pre-trial disclosure of the documents in Exhibit
    33 was required by Rule 194.2(f)(4)(A). That rule required J.P. to disclose “all
    documents, tangible things, reports, models, or data compilations that have been
    provided to, reviewed by, or prepared by or for the expert in anticipation of the
    19
    expert’s testimony.” TEX. R. CIV. P. 194.2(f)(4)(A). Parish, J.P.’s expert, relied
    upon the documents in Exhibit 33. Indeed, Parish included these documents as
    exhibits to his report. His report, which was timely disclosed to Walker, makes
    clear that Parish relied on the documents and that the documents were supposed to
    be attached to Parish’s report as exhibits. Walker argues for exclusion on the basis
    that it did not receive the exhibits to Parish’s report. But the information disclosed
    by J.P. alerted Walker of the existence of the documents, the fact that they were
    relied upon by Parish, and the fact that they should have been attached to Parish’s
    report, and Walker nevertheless failed to notify J.P. that, in fact, the documents
    were not attached as exhibits to Parish’s report. On this record, we hold that the
    trial court did not abuse its discretion in concluding that Walker was not unfairly
    surprised or unfairly prejudiced by the untimely disclosure and therefore, the trial
    court did not abuse its discretion in admitting Exhibit 33. See Williams v. Cnty. of
    Dallas, 
    194 S.W.3d 29
    , 33 (Tex. App.—Dallas 2006, pet. denied) (no abuse of
    discretion in admitting undisclosed documents supporting damages where face of
    pleading indicated that such damages would be sought at trial); see also Marin v.
    IESI TX Corp., 
    317 S.W.3d 314
    , 323–24 (Tex. App.—Houston [1st Dist.] 2010,
    pet. denied) (exhibits admitted through fact witness were not required to be
    produced in response to Rule 194.2(f) disclosure request and were not subject to
    20
    exclusion under Rule 193.6).
    We overrule Walker’s complaint about the admission of Exhibit 33.
    2. Lost Profits
    The rule concerning recovery of lost profit damages is “well established:”
    Recovery for lost profits does not require that the loss be susceptible
    of exact calculation. However, the injured party must do more than
    show that they suffered some lost profits. The amount of the loss must
    be shown by competent evidence with reasonable certainty. What
    constitutes reasonably certain evidence of lost profits is a fact
    intensive determination. As a minimum, opinions or estimates of lost
    profits must be based on objective facts, figures, or data from which
    the amount of lost profits can be ascertained. Although supporting
    documentation may affect the weight of the evidence, it is not
    necessary to produce in court the documents supporting the opinions
    or estimates.
    ERI Consulting Eng’rs, Inc. v. Swinnea, 
    318 S.W.3d 867
    , 876 (Tex. 2010) (quoting
    Holt Atherton Indus., Inc. v. Heine, 
    835 S.W.2d 80
    , 84 (Tex. 1992)). Here, the
    trial court awarded $36,646.39 in lost profits, based on the testimony of J.P.’s lost
    profits expert, Lane Parish.
    Walker argues that the lost profit award is improper in light of the release
    and our earlier opinion, because Parish “admitted that his analysis and calculations
    included amounts related to work performed prior to March 16, 2005.” The record
    reflects that Parish calculated J.P.’s lost profits by determining J.P.’s profit margin
    on the project during the first several months and then applying that percentage to
    the outstanding total contract amount, $132,043.40. This yielded a lost profits
    21
    calculation of $36,642.39.
    We agree with Walker that, based on our prior opinion, any pre-March 16
    lost profits may not be awarded to J.P. However, Parish testified that he only used
    pre-March 16 billing and cost data to determine J.P.’s “job profit percentage” on
    the project.   He multiplied the percentage by the contract amount that was
    outstanding as of March 16, 2005 to ascertain the amount of profit J.P. would have
    earned had it performed all of the work contemplated by the contract.
    Accordingly, the record does not support Walker’s contention that Parish’s lost
    profits calculation awards J.P. damages for pre-March 16 lost profits.
    Walker also argues that Parish’s lost profits testimony was unreliable.
    Walker was required to raise this objection before trial or when the testimony was
    offered. See City of San Antonio v. Pollock, 
    284 S.W.3d 809
    , 816–17 (Tex. 2009).
    Walker did object to the admission of Parish’s testimony at trial, but only on the
    grounds that Parish should not be permitted to testify given the limited scope of the
    remand. Accordingly, we hold this complaint is not preserved for our review. See
    
    Pollock, 284 S.W.3d at 816
    –17.
    Walker does not complain that the evidence of lost profits is otherwise
    insufficient to support the lost profits award, and we conclude that it is. Parish
    testified in detail about the manner in which he determined J.P.’s profit margin,
    22
    and the post-March 16 lost profits figure. His conclusions were supported by
    Exhibit 33. Accordingly, we hold the lost profits evidence is “reasonably certain”
    and therefore legally and factually sufficient to support the lost profits award of
    $36,646.39. 
    Swinnea, 318 S.W.3d at 876
    (recovery for lost profits does not require
    that the loss be susceptible of exact calculation, but must be shown by reasonably
    certain evidence); Anthony Equip. Corp. v. Irwin Steel Erectors, Inc., 
    115 S.W.3d 191
    , 204–05 (Tex. App.—Dallas 2003, pet. dism’d) (application of profit margin
    percentage to anticipated total project amount indicated with reasonable certainty
    the amount of lost profits).
    3. Pantle’s testimony supporting unpaid work award
    The trial court awarded J.P. $30,442.23 for work performed between March
    16, 2005 and March 22, 2005. This was based on the testimony of J.P.’s president,
    Pantle. Walker argues that the trial court abused its discretion when it awarded this
    amount based on Pantle’s testimony, because Pantle’s testimony was not credible
    as a matter of law and it is therefore legally and factually insufficient to support the
    award. Walker argues that Pantle testified unequivocally in the 2007 trial that J.P.
    was owed only $19,501 for unpaid work, but on remand, Pantle testified that J.P.
    was entitled to a higher amount. Walker argues that this conflict makes Pantle’s
    testimony on remand insufficient to support the award for unpaid work.
    23
    Pantle testified on remand that the $19,501 figure he offered at the first trial
    included amounts for February but not March. He clarified that he mistakenly
    confused damages for unpaid work with lost profits damages during the first trial.
    In addition, Pantle’s testimony regarding the value of unpaid work was supported
    by J.P.’s invoices, ledgers, checks, and other business records reflecting the value
    of J.P.’s work performed between March 16, 2005 and March 22, 2005.
    The trial court is the sole judge of Pantle’s credibility and the weight to be
    given his testimony. City of 
    Keller, 168 S.W.3d at 819
    ; 
    Salomon, 369 S.W.3d at 549
    . The trial court could believe or disbelieve Pantle’s testimony, in whole or in
    part, and it was entitled to resolve any inconsistencies in Pantle’s testimony.
    
    Salomon, 369 S.W.3d at 549
    . We will not disturb the trial court’s determination
    that Pantle’s testimony was credible. City of 
    Keller, 168 S.W.3d at 819
    ; 
    Ellis, 971 S.W.2d at 407
    ; 
    Salomon, 369 S.W.3d at 549
    . We hold that legally and factually
    sufficient evidence supports the trial court’s finding that J.P. was entitled to
    recover $30,442.23 for unpaid work.
    4. Attorney’s Fees
    Walker argues that the trial court abused its discretion in admitting
    testimony on attorney’s fees that had not been disclosed before the new trial.
    Walker contends that “Texas Rules of Civil Procedure 193.6 and 194.2 required
    24
    disclosure of the amount and any method of calculating damages.”             Walker
    apparently contends that evidence supporting a claim for attorney’s fees, like “the
    amount and any method of calculating economic damages,” must be disclosed
    under the timeframe prescribed in rule 194.2(d). See TEX. R. CIV. P. 194.2(d).
    However, where, as here, attorney’s fees are not sought as an element of damages,
    they are not economic damages and are therefore not required to be disclosed in
    accordance with rule 194.2(d). See Carter v. Flowers, No. 02-10-00226-CV, 
    2011 WL 4502203
    , at *4 (Tex. App.—Fort Worth Sept. 29, 2011, no pet.) (mem. op.)
    (“Attorney’s fees are not economic damages and are therefore not required to be
    disclosed under rule 194.2(d).”); Shafer v. Gulliver, No. 14-09-00646-CV, 
    2010 WL 4545164
    , at *11 (Tex. App.—Houston [14th Dist.] Nov. 12, 2010, no pet.)
    (mem. op.) (holding that Rule 194.2(d) did not require plaintiffs to disclose method
    of calculating attorney’s fees). And, Walker agrees that J.P. properly designated
    its attorney as a testifying expert on fees pursuant to Texas Rule of Civil Procedure
    194.2(f) and made the disclosures required by that provision. Walker does not
    otherwise challenge the sufficiency of the evidence to support the award of
    attorney’s fees.    Accordingly, we hold the evidence is legally and factually
    sufficient to support the trial court’s fee awards.
    We overrule Walker’s second issue.
    25
    Conclusion
    We modify the trial court’s judgment to exclude the award of $7,105.28 for
    retainage and affirm the judgment as modified.
    Rebeca Huddle
    Justice
    Panel consists of Chief Justice Radack and Justices Bland and Huddle.
    26