concierge-nursing-centers-inc-and-houston-concierge-care-lp-v-antex ( 2013 )


Menu:
  • Opinion issued May 9, 2013
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-11-00882-CV
    ———————————
    CONCIERGE NURSING CENTERS, INC. AND
    HOUSTON CONCIERGE CARE, L.P., Appellants
    V.
    ANTEX ROOFING, INC., NEVCO WATERPROOFING,
    INC., CONEX CONSTRUCTORS, INC., AND
    MITCHELL CHUOKE PLUMBING, INC., Appellees
    On Appeal from the 80th District Court
    Harris County, Texas
    Trial Court Case No. 2008-64390
    OPINION
    In this contract action, property owners Concierge Nursing Centers, Inc. and
    Houston Concierge Care, L.P. (collectively, “Concierge”) appeal from the trial
    court’s summary judgment in favor of four construction subcontractors. In a single
    issue, Concierge contends that the subcontractors were not entitled to summary
    judgment on its contractual indemnity claims against them. We reverse the
    judgment and remand for further proceedings.
    Background
    After discovering water damage and resulting mold in its newly constructed
    facility, Concierge sued the construction project’s general contractor, Brae Burn
    Construction Company, Ltd., and its subcontractors Antex Roofing, Inc.; Nevco
    Waterproofing, Inc.; Conex Constructors, Inc.; and Mitchell Chuoke Plumbing,
    Inc. In that lawsuit, Concierge ultimately settled its claims against Brae Burn and
    nonsuited its claims against the subcontractors. In Concierge’s settlement
    agreement with Brae Burn, Brae Burn assigned to Concierge all of Brae Burn’s
    contractual rights against the subcontractors.
    Brae Burn’s subcontracts with the subcontractors contain two indemnity
    provisions. The parties disagree about the meaning of the word “property” in the
    first paragraph:
    6.1 Subcontractor hereby agrees with Contractor to defend,
    indemnify and hold harmless Contractor, Owner, Architect, and all
    parties claiming by, through or under Contractor, Owner, or Architect
    (hereafter referred to as the “Indemnified Parties”) from all claims,
    suits, actions and proceedings (WHETHER ARISING UNDER
    NEGLIGENCE, WARRANTY, CONTRACT, STRICT LIABILITY,
    PRODUCTS LIABILITY, COMPARATIVE NEGLIGENCE OR
    FAULT, OR OTHER THEORY OF ACTION, the foregoing being
    2
    collectively referred to as “Claims”) whatsoever which may be
    instituted on account of injuries to or death of persons or damage to
    property caused or alleged to have been caused in connection with the
    performance by Subcontractor of the work or any extra work or in any
    way related to the acts, conduct, or condition created by or on behalf
    of the Subcontractor with respect to the premises or project upon
    which the Work is being performed, and all losses, costs, damages and
    expenses resulting therefrom, including but not limited to attorney’s
    fees and other costs of defending against the Claims, regardless of
    whether the claim was caused in part by any of the Indemnified
    Parties. . . . SUBCONTRACTOR’S DUTY TO INDEMNIFY
    EXTENDS TO CLAIMS CAUSED BY NEGLIGENCE OR FAULT
    OR LIABILITY UNDER ANY THEORY OF ACTION OF AN
    INDEMNIFIED PARTY, BUT NOT FROM THE SOLE
    NEGLIGENCE OR SOLE FAULT OR SOLE LIABILITY OF AN
    INDEMNIFIED PARTY. SUBCONTRACTOR’S DUTY TO
    INDEMNIFY EXTENDS TO ACTIONS FOR DAMAGES ON
    ACCOUNT OF INJURY TO OR DEATH OF AN EMPLOYEE OF
    SUBCONTRACT.
    (Italics added for emphasis).1 A definition for the word “property” appears
    in the following paragraph:
    1
    The text we have redacted—the second and third sentences in the
    paragraph—addresses the subcontractors’ other indemnity-related duties.
    While those sentences are not directly relevant here, we quote them below
    because they do provide some guidance on the structure of the contract and
    the proper interpretation of the word “property” as used in paragraph 6.1:
    Subcontractor shall assume on behalf of the Indemnified Parties
    and conduct with due diligence and in good faith the defense of
    all claims, regardless of whether the claim is meritorious or
    whether any Indemnified Party is joined therein, and shall bear
    the cost of all judgments and settlements in connection
    therewith; provided however, without relieving the
    Subcontractor of its obligation hereunder, any of the
    Indemnified Parties, at its election, may defend or participate in
    the defense of any or all of the Claims. Neither the maintenance
    3
    6.2 “Property” means any tangible personal property including
    equipment, tools, material, and scaffolding and ladders, in which a
    subcontractor has an ownership or possessory interest. Use by a
    subcontractor includes use by an employee of Subcontractor or by [a]
    person or organization under contract with Subcontractor. In the event
    that a subcontractor (“using subcontractor”) uses the property of
    another subcontractor (“owning subcontractor”), then the using
    subcontractor SHALL INDEMNIFY AND HOLD HARMLESS the
    owning subcontractor from any claim or cause of action arising out of
    the use of the property by the using subcontractor. THIS
    INDEMNITY SHALL INCLUDE ANY CLAIM WHICH ALLEGES
    NEGLIGENCE OR STRICT LIABILITY ON THE PART OF THE
    OWNING SUBCONTRACTOR AS TO THE DESIGN, USE, OR
    CONDITION OF THE PROPERTY. THIS INDEMNITY SHALL
    COVER CLAIMS AND CAUSES OF ACTION OF THE
    EMPLOYEES OF THE USING SUBCONTRACTOR.
    (Italics added for emphasis). One of the subcontracts, Antex’s subcontract, also
    includes a handwritten delineation adding the word “tangible” to paragraph 6.1, so
    that it reads: “damage to [tangible] property.”
    After settling with Brae Burn, Concierge initiated against the subcontractors
    a second suit, which is the basis of this appeal. Concierge sued the subcontractors
    as Brae Burn’s assignee, asserting contract claims based on the subcontractors’
    failure to indemnify and defend Brae Burn against Concierge’s claims in the earlier
    of the insurance referred to in Section V hereinabove nor the
    limits referred to therein shall diminish Subcontractor’s
    obligations hereunder or Subcontractor’s duties of
    indemnification to contractor elsewhere in this Subcontract.
    4
    suit.2 Each of the subcontractors moved for summary judgment, and the trial court
    granted the motions and ordered that Concierge take nothing. This appeal
    followed.
    Standard of Review
    We review summary judgments de novo. Mann Frankfort Stein & Lipp
    Advisors, Inc. v. Fielding, 
    289 S.W.3d 844
    , 848 (Tex. 2009); Valence Operating
    Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005). We consider the summary
    judgment evidence in the light most favorable to the nonmovant. Mann Frankfort
    
    Stein, 289 S.W.3d at 848
    . The subcontractors were entitled to traditional summary
    judgment on Concierge’s claims against them if they conclusively negated at least
    one essential element of the claims or conclusively established each element of an
    affirmative defense to the claims. See TEX. R. CIV. P. 166a(c); Frost Nat’l Bank v.
    Fernandez, 
    315 S.W.3d 494
    , 508–09 (Tex. 2010). They were entitled to no-
    evidence summary judgment on Concierge’s claims against them if, after adequate
    time for discovery, the subcontractors challenged Concierge’s evidence to support
    one or more elements of Concierge’s claims and Concierge failed to produce
    summary judgment evidence raising a genuine issue of material fact on the
    2
    The subcontracts also contained provisions requiring the subcontractors to
    name Brae Burn as an additional insured. Concierge asserted breach of
    contract claims based on this provision, but it does not appeal from the trial
    court’s judgment with respect to those claims.
    5
    challenged elements. See TEX. R. CIV. P. 166a(i); LMB, Ltd. v. Moreno, 
    201 S.W.3d 686
    , 688 (Tex. 2006) (per curiam).
    Because the trial court’s judgment and orders do not specify the grounds on
    which it granted summary judgment on Concierge’s indemnity claims, Concierge
    must demonstrate that none of the proposed grounds are sufficient to support the
    judgment. See Rogers v. Ricane Enters., 
    772 S.W.2d 76
    , 79 (Tex. 1989); West v.
    SMG, 
    318 S.W.3d 430
    , 437 (Tex. App.—Houston [1st Dist.] 2010, no pet.).
    Conversely, we will affirm the judgment if any of the theories advanced in the
    summary judgment motions is meritorious. Joe v. Two Thirty Nine Joint Venture,
    
    145 S.W.3d 150
    , 157 (Tex. 2004); 
    West, 318 S.W.3d at 437
    .
    Assignment of Brae Burn’s Indemnity Claims
    A.    The parties contentions and pertinent background
    Three of the four subcontractors contended in their summary judgment
    motions that Concierge—who purportedly acquired Brae Burn’s indemnity claims
    against the subcontractors by an assignment in the settlement agreement among
    Concierge, Brae Burn, and an insurer, Hartford Fire Insurance Company—actually
    acquired no cause of action because Brae Burn no longer had a cause of action to
    6
    assign at the time. 3 Before the events giving rise to this litigation, Brae Burn had
    two commercial general liability insurance policies; AIG issued one and St. Paul
    issued the other. The AIG policy contains a provision explaining the company’s
    subrogation rights: “If any Insured has rights to recover all or part of any payment
    we have made under this policy, those rights are transferred to us.” The St. Paul
    policy also contains a subrogation provision: “Any person protected under this
    policy may be able to recover all or part of a loss from someone other than us. . . .
    If we make a payment under this policy that right of recovery will belong to us.”
    Under the settlement agreement between Concierge and Brae Burn, National
    Union Fire Insurance Company of Pittsburgh, PA was to pay to Concierge
    $3 million on behalf of Hartford. Although the record does not reflect the precise
    relationships among AIG, St. Paul, Hartford, and National Union, Concierge
    admitted in a response to interrogatories that “[a] total of $3,000,000 was paid in
    settlement by both insurers, AIG and St. Paul.” Thus, the parties do not dispute that
    3
    Nevco, Conex, and Mitchell Chuoke argued about unassignability in their
    respective summary judgment motions; Antex did not.
    Nevco, Conex, and Mitchell Chuoke argued in the traditional part of their
    summary judgment motions that the insurance policies demonstrated the
    ineffectiveness of the purported assignment. Thus, it was their burden as
    summary judgment movants to prove that the subrogation clauses operated
    to nullify the assignment. See TEX. R. CIV. P. 166a(c). They also argued in
    the no-evidence part that Concierge had no proof of a valid assignment.
    Thus, it was Concierge’s burden as the nonmovant to produce evidence that
    it received a valid assignment. See TEX. R. CIV. P. 166a(i).
    7
    the $3 million payment specified in the settlement agreement was made under the
    AIG and St. Paul insurance policies.
    The subcontractors argue that “pursuant to Brae Burn’s insurance contracts,
    once AIG and/or St. Paul paid settlement funds on behalf of Brae Burn in the
    underlying lawsuit, any rights Brae Burn may have had to recover those payments
    from third-parties (i.e. its subcontractors) automatically transferred to AIG and St.
    Paul.” Therefore, they argue, “AIG and St. Paul, not Brae Burn, owned the
    contractual claims against Brae Burn’s subcontractors at the time Brae Burn
    attempted to assign them to” Concierge. Consequently, “Brae Burn’s alleged
    assignment to [Concierge] of Brae Burn’s contractual claims against its
    subcontractors was ineffective.”
    Concierge advances three grounds to support the validity of Brae Burn’s
    assignment.4 First, it contends that either a subrogee or a subrogor may maintain
    4
    Besides the three grounds we identify, Concierge also relies on evidence that
    the insurers assigned to it all causes of action that the insurers had acquired
    from Brae Burn via subrogation. The evidence, a one-page document
    entitled “INSURER’S ACKNOWLEDGMENT AND WAIVER OF
    SUBROGATION RIGHTS” and signed only by National Union, was
    attached to Concierge’s motion to reconsider the order granting partial
    summary judgment. The subcontractors argue that this evidence “was never
    made part of the summary judgment record and cannot be considered on
    appeal.” We do not reach the issue of whether we may consider this
    document, as the issue is unnecessary to the disposition of this appeal. See
    TEX. R. APP. P. 47.1. For the purposes of this appeal only, we will assume,
    without deciding, that this evidence was not part of the summary judgment
    record.
    8
    the cause of action that is subject to the subrogation. By this argument, Concierge
    apparently contends that Brae Burn as the subrogee legally has the right to assign
    its causes of action to Concierge despite the language in the subrogation clauses.
    Second, Concierge contends that the contractual rights and remedies between the
    insurers (as subrogees) and their insured (as subrogor) are private in nature, and the
    subcontractors as third parties “are not entitled to the benefit of any arrangements
    made between Brae Burn and its subrogated insurer(s).” Third, Concierge contends
    that when “the insurers” executed the settlement agreement, they assented to Brae
    Burn’s assignment of its claims to Concierge.
    We agree that the subrogation respecting Brae Burn’s contract claims does
    not prevent assignment of those claims to Concierge. When AIG and St. Paul (as
    subrogees) acquired their respective rights to recover payments made under the
    insurance policies, Brae Burn (as subrogor) retained the original claim. In other
    words, the subrogation provisions in this case do not contemplate a complete
    transfer of Brae Burn’s claims to the insurers. Rather, each policy contemplates the
    transfer of rights to recover from a liable third-party up to the amount the insurer
    paid under the policy. Thus, Brae Burn retains the original contract claims
    burdened by the insurers’ subrogation rights; the subcontractors have not brought
    to our attention a valid prohibition against the assignment of these claims.
    9
    B.    Language and structure of the insurance policies
    The insurance policies at issue contain written subrogation provisions.
    Therefore, as between Brae Burn and its insurers, the subrogation rights arising
    from the policies are governed by these provisions. See Fortis Benefits v. Cantu,
    
    234 S.W.3d 642
    , 650–51 (Tex. 2007). We interpret insurance policies according to
    the rules of contract construction. Am. Mfrs. Mut. Ins. Co. v. Schaefer, 
    124 S.W.3d 154
    , 157 (Tex. 2003). Thus, they are construed from a utilitarian standpoint,
    bearing in mind the particular business activity sought to be served. See Frost Nat’l
    Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005) (per curiam)
    (citing Reilly v. Rangers Mgmt., Inc., 
    727 S.W.2d 527
    , 530 (Tex. 1987)).
    The language and structure of the policies indicate that AIG and St. Paul
    acquired rights to recover payments made under the insurance policies as opposed
    to Brae Burn’s entire claims. In section O of the AIG policy, subsection 1 states
    that “[i]f any Insured has rights to recover all or part of any payment we have made
    under this policy, those rights are transferred to us.” The term “those rights”
    apparently references the preceding term “rights to recover all or part of any
    payment we have made.” Thus, this provision contemplates the transfer of the right
    to recover up to the amount AIG paid under the policy, not the transfer of an entire
    claim. Subsection 2, concerning the order in which recoveries are to be applied,
    confirms this interpretation:
    10
    Any recoveries shall be applied as follows:
    a. any person or organization, including the Insured, that has paid an
    amount in excess of the applicable Limits of Insurance of this
    policy will be reimbursed first;
    b. we then will be reimbursed up to the amount we have paid; and
    c. lastly, any person or organization, including the Insured that has
    paid an amount over which this policy is excess is entitled to claim
    the remainder.
    This provision contemplates that if AIG obtains a recovery, other parties—
    including the insured—may have rights to part or all of the recovery proceeds. If
    subclause a applies, AIG’s right to recover proceeds under subclause b is
    subordinate to the rights of the parties identified in subclause a. The AIG
    subrogation provision thus provides that AIG has certain rights to recover
    payments made under the policy, but it does not transfer all of Brae Burn’s rights
    in its claims.
    The St. Paul subrogation provision likewise does not contemplate a complete
    transfer of Brae Burn’s claims. It states in pertinent part:
    Any person protected under this policy may be able to recover all or
    part of a loss from someone other than us. Because of this, each
    protected person must do all that’s possible after a loss to preserve any
    right of recovery available. If we make a payment under this policy
    that right of recovery will belong to us. If we recover more than we’ve
    paid, the excess will belong to the person who had the loss.
    The term “that right of recovery” apparently references the right “to recover all or
    part of a loss from someone other than us.” Read in isolation, the sentence—“If we
    11
    make a payment under this policy that right of recovery will belong to us”—could
    be understood to mean that the entire claim is transferred. The following sentence
    belies this interpretation, however, because it provides that if St. Paul recovers
    more than it paid under the policy, it must pay the excess to the person who had the
    loss. Thus, like the AIG policy, the St. Paul policy contemplates a transfer of a
    right of recovery up to the amount the insurer paid under the policy rather than a
    complete transfer of a claim.
    C.    Business activity served by the insurance policies
    The “particular business activity sought to be served” by the policies, Frost
    Nat’l 
    Bank, 165 S.W.3d at 312
    , bolsters our interpretation of the subrogation
    provisions. “The principal purpose of an insurance contract is to protect the insured
    from loss, thereby placing the risk of loss on the insurer.” Esparza v. Scott and
    White Health Plan, 
    909 S.W.2d 548
    , 551 (Tex. App.—Austin 1995, writ denied)
    (citing Ortiz v. Great S. Fire and Cas. Ins. Co., 
    597 S.W.2d 342
    , 344 (Tex. 1980)).
    In an insurance arrangement, the insurer assumes the risk that a loss may occur in
    exchange for a premium payment. In re Tex. Ass’n of Sch. Bds., Inc., 
    169 S.W.3d 653
    , 658–59 (Tex. 2005) (orig. proceeding) (citing MURRAY           ON   CONTRACTS
    § 105(C), at 663 (4th ed. 2001)). In this way, insurance companies are in the
    business of spreading losses across the premiums they receive. See 
    id. 12 Insurers
    may have either “contractual” subrogation rights, which arise from
    contract language, or “equitable” subrogation rights, which exist in equity to
    prevent the insured from receiving a double recovery to the insurer’s detriment.
    See Fortis 
    Benefits, 234 S.W.3d at 645
    , 647. Either way, “the principle of
    subrogation provides that once an insured is made whole from his damages, the
    insurer that has paid for the insured’s covered losses is entitled to the insured’s
    rights and remedies against a third party for the covered losses.” Osborne v.
    Jauregui, Inc., 
    252 S.W.3d 70
    , 78 (Tex. App.—Austin 2008, no pet.). Thus,
    subrogation operates to reduce the insurer’s risk and boost its solvency. See Fortis
    
    Benefits, 234 S.W.3d at 650
    n.53. Subrogation is not intended to place the insurer
    in a position to profit from the loss. See In re Tex. Ass’n of Sch. 
    Bds., 169 S.W.3d at 659
    (observing that “both parties hope that the condition [triggering coverage]
    will never occur”) (quoting MURRAY ON CONTRACTS § 105(C), at 663).
    “Generally, rights conferred by subrogation are entirely derivative of the
    subrogor’s interests, to which the subrogee merely succeeds.” Guillot v. Hix, 
    838 S.W.2d 230
    , 232 (Tex. 1992). When an insurer pays out on its insured’s loss, it
    becomes a “pro tanto owner” of the cause of action. Thoreson v. Thompson, 
    431 S.W.2d 341
    , 347 (Tex. 1968); Warwick Towers Council of Co-Owners v. Park
    Warwick, L.P., 
    298 S.W.3d 436
    , 439 (Tex. App.—Houston [14th Dist.] 2009, no
    pet.). This means that the insurer receives “the rights of its insured to the extent of
    13
    payments made under the insurance contract.” Rushing v. Int’l Aviation
    Underwriters, Inc., 
    604 S.W.2d 239
    , 243 (Tex. Civ. App.—Dallas 1980, writ ref’d
    n.r.e.); see also 16 COUCH ON INSURANCE § 223:85 (3d ed. 1995) (“[B]ecause an
    insurer’s right of subrogation is merely derivative from that of the insured, the
    recovery by an insurer cannot exceed the amount to which the insured would be
    entitled.”). Although the insurer, as subrogee, has a right to recover, there is still
    but one cause of action, that of the insured, whose ownership rights are burdened
    by the insurer’s right to recoup payment made. 
    Guillot, 838 S.W.2d at 232
    (discussing principle in context of Workers’ Compensation Act). Thus, the insurer
    as subrogee does not own the entire claim as if the claim were wholly transferred
    by an assignment; it has only the right to recover an amount equal to its payment
    under the insurance policy. See 
    Rushing, 604 S.W.2d at 244
    (“Any money
    recovered by the insurer in excess of that which the insurer has expended must be
    remitted to the insured.”); 16 COUCH          ON   INSURANCE § 222:53 (contrasting
    subrogation, which “is a designation of proceeds recovered from a wrongdoer,”
    with assignment, which “transfers the entire cause of action to the insurer”).
    When the AIG and St. Paul subrogation provisions are considered in light of
    these general insurance and subrogation principles, it is even more apparent that
    the provisions are not intended to transfer entire claims, but rather they transfer
    certain rights to recover payments made under the policies. Thus, the insured, Brae
    14
    Burn, retains the original claim which is burdened by the insurers’ rights to recover
    payment.
    D.    After subrogation, Brae Burn’s claims are assignable
    The settlement agreement among Concierge, Brae Burn, and Hartford
    contains this provision, entitled “Additional Consideration”:
    For further consideration, Brae Burn hereby agrees to assign to
    [Concierge] all contractual claims it possesses against any third
    parties. Brae Burn hereby represents and warrants that such claims
    have not previously been assigned to any third parties.
    The word “assign” or “assignment” in its most general sense means the transfer of
    property or some right or interest from one person to another. Twelve Oaks Tower
    I, Ltd. v. Premier Allergy, Inc., 
    938 S.W.2d 102
    , 113 (Tex. App.—Houston [14th
    Dist.] 1996, no writ). “It is the act by which one person transfers to another or
    causes to vest in another, his right or property or an interest therein, and unless it is
    qualified in some way, it is a transfer of one’s whole interest.” 
    Id. (emphasis in
    original). Thus, the “Additional Consideration” clause, which is unqualified,
    operates to transfer from Brae Burn to Concierge “all contractual claims it
    possesses against any third parties,” such as the subcontractors.
    The subcontractors argue that by operation of the contractual subrogation
    provisions, Brae Burn did not own the contract claims it purportedly assigned to
    Concierge. However, as we discussed above, after subrogation Brae Burn retains a
    claim that is burdened by the insurers’ rights to recover payment. As a general rule,
    15
    causes of action are freely assignable. State Farm Fire and Cas. Co. v. Gandy, 
    925 S.W.2d 696
    , 707 (Tex. 1996); Delaney v. Davis, 
    81 S.W.3d 445
    , 448 n.4 (Tex.
    App.—Houston [14th Dist.] 2002, no pet.). While Brae Burn could not assign
    greater rights than it had, the subcontractors have not brought to our attention a
    valid prohibition against this assignment. See John H. Carney & Assocs. v. Tex.
    Prop. & Cas. Ins. Guar. Ass’n, 
    354 S.W.3d 843
    , 849–50 (Tex. App.—Austin 2011,
    pet. denied) (observing that “general rule” of assignability applies “unless
    assignment is prohibited by statute or is contrary to public policy”).
    To be clear, we do not adjudicate here what subrogation rights, if any, the
    insurers have against Concierge, Brae Burn, or the subcontractors. The only
    question examined is whether Brae Burn’s claims were unassignable solely
    because they were subject to the insurers’ purported subrogation rights. To that
    extent only, we hold that the subcontractors did not meet their traditional summary
    judgment burden to prove that the assignment of Brae Burn’s claims to Concierge
    was ineffective. Moreover, we hold that by presenting the settlement agreement in
    response to the summary judgment motions, Concierge met its burden to defeat the
    no-evidence part of the motions concerning the assignment of claims.
    The Parties’ Indemnity Agreement
    Each of the subcontractors sought traditional summary judgment on
    Concierge’s indemnity claims against them on the ground that, under the
    16
    subcontracts, they did not owe a duty to indemnify Brae Burn from Concierge’s
    earlier lawsuit.
    A.    The parties’ contentions
    Concierge contends that the subcontractors breached the subcontracts by not
    providing a defense and indemnity in the original lawsuit. The subcontractors
    assert that they did not breach the subcontracts. According to the subcontractors,
    their indemnity obligations under the subcontracts extended only to claims for
    “injuries or death of persons or damage to property,” with property being defined
    as “tangible personal property . . . in which a subcontractor has an ownership or
    possessory interest.” Because the property damage at issue relates to damage to
    real property—not “tangible personal property”—in which the subcontractors have
    no ownership interest, the subcontractors contend that the claims fall outside the
    scope of the subcontracts’ indemnity provisions and therefore there was no breach
    of contract.
    Concierge responds that the subcontractors rely on a definition of “property”
    found in paragraph 6.2 of the subcontract, but that definition is limited to that
    paragraph and does not apply to the term “property” as used in paragraph 6.1, the
    paragraph on which Concierge relies for the subcontractors’ alleged indemnity
    obligations. According to Concierge, paragraphs 6.1 and 6.2 “create two separate
    indemnity obligations with two separate purposes” and “the definition of
    17
    ‘property’ found in paragraph 6.2 has no reasonable application to the indemnity
    obligation in paragraph 6.1.” Concierge asserts that applying the definition of
    “property” provided in paragraph 6.2 to the use of the term “property” in paragraph
    6.1 “would lead to absurd results.”
    B.    The contractual definition of “property” in paragraph 6.1
    Both parties contend that paragraph 6.1’s indemnity provision is
    unambiguous, but they interpret the provision differently. We determine, as a
    matter of law, whether a contract is ambiguous. See Dynegy Midstream Servs., Ltd.
    P’ship v. Apache Corp., 
    294 S.W.3d 164
    , 168 (Tex. 2009). If we can give the
    contract’s language a certain and definite meaning, the contract is not ambiguous,
    and we construe the contract as a matter of law. Milner v. Milner, 
    361 S.W.3d 615
    ,
    619 (Tex. 2012); Dynegy Midstream 
    Servs., 294 S.W.3d at 168
    . Our primary
    concern in construing a contract is to ascertain the intent of the parties as expressed
    in the instrument. Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 662 (Tex.
    2005). We give the contract’s terms their “plain and ordinary meaning” unless the
    contract indicates that the parties intended a different meaning. Dynegy Midstream
    
    Servs., 294 S.W.3d at 168
    ; Valence 
    Operating, 164 S.W.3d at 662
    . We construe a
    contract “according to what it says, not what [the contracting parties] thought it
    said.” See Fiess v. State Farm Lloyds, 
    202 S.W.3d 744
    , 745 (Tex. 2006)
    (construing insurance agreement); see also Anglo-Dutch Petroleum Int’l, Inc. v.
    18
    Greenberg Peden, P.C., 
    352 S.W.3d 445
    , 451 (Tex. 2011) (“Extrinsic evidence
    cannot be used to show that the parties probably meant, or could have meant,
    something other than what their agreement stated.”); Union Pac. R.R. Co. v. Novus
    Int’l, Inc., 
    113 S.W.3d 418
    , 421 (Tex. App.—Houston [1st Dist.] 2003, pet.
    denied) (“We glean intent from what the parties said in their contract, not what
    they allegedly meant.”). We look at the entire contract, rather than any single
    provision, in determining whether a particular term is ambiguous. Henry v. Mason,
    
    333 S.W.3d 825
    , 844 (Tex. App.—Houston [1st Dist.] 2010, no pet.). A contract
    term is not ambiguous merely because the parties disagree as to its meaning. Sun
    Oil Co. v. Madeley, 
    626 S.W.2d 726
    , 727 (Tex. 1981); Houston Lighting & Power
    Co. v. City of Wharton, 
    101 S.W.3d 633
    , 641 (Tex. App.—Houston [1st Dist.]
    2003, pet. denied); see also GTE Mobilnet of S. Tex. Ltd. P’ship v. Telecell
    Cellular, Inc., 
    955 S.W.2d 286
    , 289 (Tex. App.—Houston [1st Dist.] 1997, writ
    denied) (“[T]he parties’ interpretations of the contract are irrelevant if the meaning
    of the contract is plain from its face.”). An agreement is ambiguous only if the two
    conflicting interpretations are both reasonable. Columbia Gas Transmission Corp.
    v. New Ulm Gas, Ltd., 
    940 S.W.2d 587
    , 589 (Tex. 1996).
    Applying these principles, we hold that the word “property” as used in
    paragraph 6.1 has its ordinary meaning rather than the particular meaning used in
    paragraph 6.2. We reach this conclusion because the language, structure, and
    19
    apparent intent of the subcontracts unambiguously impose an indemnity obligation
    on the subcontractors for all property damage that occurs on the project or to the
    finished structure as a result of the subcontractors’ performance. Paragraphs 6.1
    and 6.2 of the subcontracts constitute all of section 6, and no other provision in the
    subcontract concerns indemnity obligations. While the definition of “property” in
    paragraph 6.2 does not expressly limit the definition to that paragraph, the structure
    of the contract does.
    Unless otherwise limited, the indemnity obligation in section 6.1 plainly
    covers the alleged water damage to the Concierge. The word “property” ordinarily
    means “[t]hat which one owns; a thing or things belonging to or owned by some
    person or persons; a possession (usually material), or possessions collectively[.]”
    12 OXFORD ENGLISH DICTIONARY 639 (2d ed. 1991). Structurally speaking, the
    narrow definition of “property” advocated by the subcontractors—that “property”
    only encompasses tangible property owned by other subcontractors—must be
    exported from paragraph 6.2 as it is not found in paragraph 6.1. The subcontract in
    its other uses of capitalizations to define terms always includes the definition
    immediately after the first use of the word or phrase in question and the defined
    term is thereafter used throughout the contract.5 Other than the term “property,”
    5
    For example, the subcontracts use capitalizations to define the words
    Contractor, Contract Documents, Subcontractor, and Work.
    20
    there is no term in the contract that is used in one provision but is expressly
    defined in a latter provision. 6
    Other parts of the subcontract use the word “property” in accordance with its
    ordinary meaning. The word “property” is first used in paragraph 3.2, which
    discusses liens filed “against the real property.” In this paragraph, the ordinary
    definition of “property” is expressly modified through the insertion of the adjective
    “real.” In contrast, the absence of the adjective “tangible” in paragarph 6.1
    suggests that the ordinary definition is not modified. The word “property” next
    appears in section 5 of the subcontract, which addresses the parties’ obligations
    regarding “property insurance” and sets forth the amounts of “Property Damage”
    to be covered by a comprehensive general liability policy and “Property Damage”
    to be covered by a comprehensive automobile liability policy. There is no
    contention that the word “property” in this section is limited to tangible personal
    property owned by other subcontractors.
    We also note that the word “property” is not used in any paragraph after
    paragraph 6.2. Thus, there is no indication that the narrow definition of 6.2 was
    intended to apply outside this paragraph. And if the narrow definition cannot apply
    6
    There are a few instances where the defined word is not capitalized in
    subsequent uses but the context makes it clear that the uncapitalized word
    retains the expressly defined meaning.
    21
    to subsequent contractual provisions, it is less reasonable to apply the narrow
    definition to the word’s earlier uses.
    We think it is unreasonable that in a fine-print boilerplate contract the
    subcontractor would read a narrow definition of the word “property” in paragraph
    6.2 and impute that narrow definition back to the word in the preceding paragraph,
    particularly when the word “property” in 6.1 appears only once in a four-sentence,
    519-word paragraph and it is separated from the defined word “property” in the
    next paragraph by three sentences and 372 words. A reasonable party reading 6.1
    in this context is in a different position than it would be if the narrow definition
    had immediately followed in the next sentence or if a subsequent definition had
    explicitly stated that it applies to all prior uses of the term or to all uses in the
    contract. This is particularly true when the two paragraphs concern completely
    different indemnity obligations—the first of which is owed to the contractor (Brae
    Burn), the owner (Concierge), and the architect, while the second one is owed to
    other subcontractors and not to the contractor, owner or architect.
    Moreover, the apparent general purpose of paragraph 6.1—which is to
    indemnify the general contractor for defects in the subcontractors’ performance—
    supports imputing the ordinary definition of “property” to that term. Section 6.2
    addresses only a narrow set of circumstances—in contrast to 6.1, which is broader
    22
    and more sweeping—so logically it also contains its own narrower definition of
    “property” that is unique to those circumstances.
    If the definition of tangible personal property were exported into 6.1, the
    indemnity provision would essentially read: Subcontractor agrees to indemnify
    Contractor (and others) from all claims whatsoever which may be instituted on
    account of injuries to or death of persons or damage to tangible personal property
    in which a subcontractor has an ownership or possessory interest. The
    subcontractors offer no explanation for why the parties would agree that the
    subcontractors’ indemnity obligation would be broad for death claims but narrow
    for property damage (i.e., be limited to damage to tools and equipment). The most
    significant property damage exposure in a construction contract is for claims to the
    constructed building, like the claims here. We construe contracts “from a utilitarian
    standpoint bearing in mind the particular business activity sought to be served” and
    “will avoid when possible and proper a construction which is unreasonable,
    inequitable, and oppressive.” Frost Nat’l 
    Bank, 165 S.W.3d at 312
    (quoting 
    Reilly, 727 S.W.2d at 530
    ). The commercial purpose of an indemnity provision in a
    construction contract supports the conclusion that the ordinary definition of
    property must apply in section 6.1
    The other provisions in the contract that describe the subcontractors’
    responsibilities are broad, not narrow, and reflect an intention to make the
    23
    subcontractors responsible for all aspects of their performance. Paragraph 1.3
    provides, in pertinent part:
    Subcontractor agrees to be bound to Contractor by the Contract
    documents insofar as they relate in any way to the Work undertaken
    by the Subcontractor and to assume towards contractor, in connection
    with the Work covered by this Subcontract, all of the obligations and
    responsibilities which Contractor assumed under the Contract
    documents by any party.
    Paragraph 2.2 provides:
    Subcontractor shall be liable for damages sustained by Contractor,
    which are caused by delay caused by Subcontractor and Subcontractor
    shall indemnify and save harmless Contractor from any liability for
    damages, liquidated or otherwise, caused by delay caused by
    Subcontractor and for which Contractor is liable to any other party
    under the Contract Documents.
    These provisions lend further support that a narrow reading is not the proper
    interpretation of the subcontracts.
    The subcontractors argue that the parties’ intent to export paragraph 6.2’s
    definition of “property” to paragraph 6.1 is evidenced in a delineation made by
    Antex Roofing in its subcontract; Antex, presumably, added the word “tangible”
    before the term “property” in paragraph 6.1. We disagree that this revision by
    Antex constitutes proof of the other subcontractors’ intention for their respective
    subcontracts. On the contrary, this delineation indicates that Antex concluded the
    word “property” in paragraph 6.1 did not clearly utilize the narrow definition found
    in paragraph 6.2 without that modification. Furthermore, we may not affirm the
    24
    summary judgment for Antex on the basis of the delineation because Antex did not
    present this argument to the trial court in its summary judgment motion.
    We hold that the trial court could not have granted the subcontractors
    summary judgment on Concierge’s indemnity claims on the ground that, under the
    subcontracts, they did not owe a duty to indemnify Brae Burn from Concierge’s
    earlier lawsuit.
    Evidence on Breach of the Indemnity Agreement
    Finally, the subcontractors contend that Concierge produced no evidence of
    a breach of the indemnity agreement, that is, evidence that their conduct caused
    water damage or mold. More specifically, they assert that the original petition in
    the underlying lawsuit brought by Concierge against Brae Burn is insufficient to
    create a duty to indemnify and that the evidence offered in response to their
    summary judgment motions—the affidavit of Concierge’s expert, Mark Stanford—
    constituted no evidence because it was conclusory. According to the
    subcontractors, Stanford failed “to explain or make any causal link between [the
    subcontractors’] work on the project and the alleged mold and water damage.”
    They also contend that the trial court “determin[ed] that Mr. Stanford’s affidavit
    was conclusory.”
    Contrary to the subcontractors’ contentions, the trial court did not rule that
    Stanford’s affidavit was conclusory. None of the subcontractors filed any objection
    25
    to Stanford’s affidavit, and the record does not reflect an order striking the
    affidavit in whole or in part. Furthermore, we disagree with their assessment of the
    affidavit as conclusory.
    In the summary judgment context, “affidavits shall be made on personal
    knowledge, shall set forth such facts as would be admissible in evidence, and shall
    show affirmatively that the affiant is competent to testify to the matters stated
    therein.” TEX. R. CIV. P. 166a(f). Conclusory statements in affidavits are
    “incompetent to support the rendition of summary judgment as a matter of law[.]”
    Anderson v. Snider, 
    808 S.W.2d 54
    , 55 (Tex. 1991) (per curiam, op. on rehearing).
    “Conclusory” means “[e]xpressing a factual inference without stating the
    underlying facts on which the inference is based.” Arkoma Basin Exploration Co.,
    Inc. v. FMF Assocs. 1990-A, Ltd., 
    249 S.W.3d 380
    , 389 n.32 (Tex. 2008) (quoting
    BLACK’S LAW DICTIONARY 308 (8th ed. 2004)). Thus, to be competent summary
    judgment evidence, affidavit statements regarding causation must be supported by
    underlying facts. See LMB, Ltd. v. Moreno, 
    201 S.W.3d 686
    , 688–89 (Tex. 2006)
    (per curiam); IHS Cedars Treatment Ctr. of DeSoto, Tex., Inc. v. Mason, 
    143 S.W.3d 794
    , 803 (Tex. 2004).
    According to the affidavit produced by Concierge to defeat the no-evidence
    summary judgment motions, Stanford is the owner of Stanford Consulting &
    Construction, which constructs and remodels buildings and provides consulting
    26
    services. Stanford averred that he inspected the Concierge and reviewed the
    construction documents, “numerous depositions” taken in this case, inspection
    reports, reports by the parties’ experts, photographs, and depositions taken in the
    underlying lawsuit between Concierge and Brae Burn. Stanford stated that the
    construction documents required the building to be constructed in accordance with
    the Uniform Building Code, which “requires that a building be constructed so that
    water is not able to penetrate into the building envelope.” This obligation was
    breached because water “did penetrate into the building envelope.” Moreover,
    mold “occurred because of water intrusion at the facility.” The water penetration
    occurred in areas where the roof was constructed (Antex Roofing) and where
    landscaping was installed (Conex Constructors); the rubber membranes around the
    window openings were not properly installed (Nevco Waterproofing); and
    plumbing intrusions were left unsealed (Mitchell Chuoke Plumbing). “But for
    these subcontractors’ failure to perform their work in accordance with [the]
    Uniform Building Code and ensure that water would not penetrate into the building
    envelope, there would have been no water intrusion as a result of these
    subcontractors’ work.”
    We reject the subcontractors’ contention that Stanford’s affidavit was
    conclusory and therefore no evidence. The affidavit explains the facts underlying
    the cause of the water damage and the mold. None of the subcontractors have
    27
    identified any details omitted from the affidavit that are essential to demonstrate
    causation. Accordingly, the trial court could not have granted summary judgment
    on the ground that the affidavit’s statements were conclusory and thus constituted
    no evidence of the subcontractors’ breaches.
    Conclusion
    We hold that the trial court erred in granting summary judgment in favor of
    Antex, Nevco, Conex, and Mitchell Chuoke. Accordingly, we reverse the trial
    court’s judgment and remand for further proceedings.
    Harvey Brown
    Justice
    Panel consists of Chief Justice Radack and Justices Higley and Brown.
    28
    

Document Info

Docket Number: 01-11-00882-CV

Filed Date: 5/9/2013

Precedential Status: Precedential

Modified Date: 2/1/2016

Authorities (34)

West v. SMG , 2010 Tex. App. LEXIS 4040 ( 2010 )

Joe v. Two Thirty Nine Joint Venture , 47 Tex. Sup. Ct. J. 1058 ( 2004 )

Arkoma Basin Exploration Co. v. FMF Associates 1990-A, Ltd. , 51 Tex. Sup. Ct. J. 342 ( 2008 )

Milner v. Milner , 55 Tex. Sup. Ct. J. 419 ( 2012 )

Guillot v. Hix , 838 S.W.2d 230 ( 1992 )

IHS CEDARS TREATMENT CTR OF DESOTO, TEXAS, INC. v. Mason , 143 S.W.3d 794 ( 2004 )

Dynegy Midstream Services, Ltd. Partnership v. Apache Corp. , 52 Tex. Sup. Ct. J. 1176 ( 2009 )

Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd. , 40 Tex. Sup. Ct. J. 42 ( 1996 )

Frost National Bank v. Fernandez , 53 Tex. Sup. Ct. J. 609 ( 2010 )

Valence Operating Co. v. Dorsett , 48 Tex. Sup. Ct. J. 671 ( 2005 )

Delaney v. Davis , 2002 Tex. App. LEXIS 4515 ( 2002 )

Union Pacific Railroad v. Novus International, Inc. , 113 S.W.3d 418 ( 2003 )

Rogers v. Ricane Enterprises, Inc. , 32 Tex. Sup. Ct. J. 458 ( 1989 )

Henry v. Masson , 2010 Tex. App. LEXIS 10271 ( 2010 )

Thoreson v. Thompson , 11 Tex. Sup. Ct. J. 565 ( 1968 )

Ortiz v. Great Southern Fire & Casualty Insurance Co. , 597 S.W.2d 342 ( 1980 )

Rushing v. International Aviation Underwriters, Inc. , 1980 Tex. App. LEXIS 3650 ( 1980 )

Reilly v. Rangers Management, Inc. , 30 Tex. Sup. Ct. J. 333 ( 1987 )

Esparza v. Scott and White Health Plan , 909 S.W.2d 548 ( 1995 )

LMB, LTD. v. Moreno , 49 Tex. Sup. Ct. J. 1019 ( 2006 )

View All Authorities »