the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do ( 2013 )


Menu:
  • Opinion issued March 5, 2013
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-11-00966-CV
    ———————————
    THE WATERHILL COMPANY, LLC, JONATHAN WASSERBERG, AND
    JASON FELT, Appellants
    V.
    Y HOANG DO AND QUY LINH NGO DO Appellees
    On Appeal from the 334th District Court
    Harris County, Texas
    Trial Court Case No. 2008-21558
    MEMORANDUM OPINION
    Appellants, The Waterhill Company, LLC (“Waterhill”), Jonathan
    Wasserberg, and Jason Felt, challenge the trial court’s rendition of summary
    judgment in favor of appellees, Y Hoang Do and Quy Linh Ngo Do (the “Dos”), in
    the Dos’ suit for violations of the Texas Trust Fund Act, 1 breach of contract, fraud,
    fraudulent transfer, 2 and conversion. In seven issues, Waterhill, Wasserberg, and
    Felt contend that the trial court erred in striking their amended pleadings and
    granting the Dos’ summary-judgment motion.
    We reverse and remand.
    Background
    In their sixth amended petition, the Dos alleged that on March 30, 2005,
    they entered into a “Construction Agreement” with Waterhill to build the Dos a
    residence at 12 Farnham Park Drive for $1.313 million. On October 9, 2007, the
    Dos and Waterhill executed an “Addendum to the Waterhill Companies Limited
    Construction Agreement,” which adjusted the total construction cost of the
    residence to $1,819,320.00. The Addendum provided that “construction of the
    residence should be completed at the end of a twelve month period from the time
    the foundation is completed. Change orders may extend construction time.”
    In 2007, Waterhill submitted to the Dos a draw request for $372,933.04, and
    on January 4, 2008, it submitted to the Dos a draw request of $72,223.54, with
    $57,543.00 of the request designated to be paid to Boswell Construction, L.P.
    1
    See TEX. PROP. CODE ANN. § 162.031 (Vernon Supp. 2012).
    2
    See TEX. BUS. & COM. CODE ANN. § 24.005(a) (Vernon 2009).
    2
    (“Boswell”). In its January 4, 2008 request, Waterhill certified that “all suppliers
    and subcontractors had been paid for work and materials on previous draws.”
    However, the Dos subsequently received a letter from Boswell, informing them
    that Waterhill owed it $56,100 for work done on the Dos’ residence. The Dos
    further alleged that Waterhill had failed to pay a steel contractor, KV Weld, Inc.
    (“KV Weld”) $48,455.00 for work done on the residence. And Waterhill then
    “abandoned all activities on the property without excuse and materially breached
    the[ir] Agreement by the repeated and extensive construction delays.” Finally, the
    Dos alleged that Waterhill breached their contract by failing to deliver “travertine
    tiles” pursuant to another request and converting the tiles for Waterhill’s own use.
    In their original answer to the Dos’ original petition, appellants generally
    denied the Dos’ claims. After the Dos filed several amended petitions, appellants
    filed an amended answer, raising various affirmative defenses and counterclaims.3
    Appellants then filed a second amended answer, generally denying the Dos’
    allegations and raising twenty-four affirmative defenses. The Dos filed a motion to
    strike appellants’ amended answers, asserting that appellants had “stalled, delayed
    and used the arbitration process to avoid discovery and trial.” The Dos asserted
    that appellants had “avoided the first trial at the last minute by demanding
    3
    Waterhill’s first amended answer does not appear in the record. However,
    Waterhill’s brief and the Dos’ “Motion to Strike [Waterhill’s] Amended Answer
    and Original Counterclaim” indicate that the first amended answer was filed on
    August 20, 2010.
    3
    arbitration” and then “avoided the arbitration trial by refusing the pay the
    arbitrator.” They also argued that appellants’ “late filed answer and counterclaim
    should be stricken” because it was filed “after 28 months of litigation and only 23
    days before trial” and Waterhill had not disclosed the affirmative defenses during
    discovery. The trial court granted the Dos’ motion and struck Waterhill’s first and
    second amended answers.
    In their summary-judgment motion, the Dos asserted that it was
    “undisputed” that appellants had breached their construction contract by failing to
    “complete the construction of the home within the contract period,” “properly
    construct the home,” and “pay subcontractor[s] as per the parties’ agreement.” The
    Dos attached to their motion a copy of a contract that they entered with Mike Stahl
    to complete their residence at a cost of $1,765,506.00. Asserting that they had paid
    appellants $569,589.96, the Dos sought breach-of-contract damages of
    $524,326.49.
    The Dos further argued that Felt and Wasserberg were individually liable for
    Waterhill’s debts and obligations because they “acted as general partners and held
    themselves out as general partners,” “participated in the daily control of the
    business,” and “admitted that they were in fact general partners of Waterhill.”
    They argued that appellants violated the Texas Trust Fund Act, committed fraud,
    and converted the Dos’ funds because appellants received draw request payments
    4
    from the Dos for construction of their residence, but “commingled those specific
    trust funds . . . by depositing [them] into a general bank account.” The Dos
    asserted that appellants “misappropriated, converted or misapplied over
    $108,000.00 in trust funds,” “used the funds to pay their debts on other projects,”
    and “converted [the Dos’] tiles . . .[,] causing damages in the amount of $10,665.45
    to replace the converted tiles.” And the Dos sought attorney’s fees in the amount
    of $43,575 and punitive damages in the amount of $200,000.00.
    The Dos attached to their summary-judgment motion the affidavit of Y
    Hoang, who testified that he and his wife, Ling Ngo, had met with Wasserberg and
    Felt prior to their signing of the construction contract with Waterhill. At the
    meeting, Wasserberg and Felt told Y Hoang and Ngo that they were Waterhill’s
    general partners and “all funds deposited or transferred to them from [the Dos]
    would be used only on” the construction of the Dos’ residence. Hoang further
    testified that Waterhill “never completed the construction of [the] home within the
    time period set forth in the contract,” “walked off the jobsite in February 2008
    without cause,” and “refused to complete the work set forth in the contract and pay
    the subcontractors.”
    The Dos also attached to their motion the depositions of Wasserberg and
    Felt. Wasserberg testified that he was “an owner of Waterhill Companies Limited
    in a general partner capacity” and Felt was a “co-managing partner” who
    5
    “oversee[s] bank relationships.” Felt testified that he was a “managing partner” of
    Canary Financial, LLC (“Canary Financial”), which was “one of the general
    partners of Waterhill.” He explained that he was “in charge of securing financing
    for [Waterhill] and “other various banking relations.”
    Finally, the Dos attached to their motion the affidavit of Jack Arnold, the
    president of KV Weld, who testified that his company was hired by Waterhill to
    “provide the structural steel” for construction of the Dos’ residence. Wasserberg
    told Arnold that “he was the person who controlled the day to [day] activities of
    [Waterhill].” Arnold noted that “KV Weld submitted an invoice and received the
    sum of $48,455.00 . . . to be used at the Dos’ residence,” but Wasserberg directed
    Arnold to “apply” the money to “prior debts” that Waterhill owed to KV Weld.
    In their response 4 to the Dos’ summary-judgment motion, appellants
    asserted that genuine issues of material fact precluded granting the Dos summary
    judgment and “the facts of this case will show that [the Dos] actually breached the
    contract first” by “making numerous revisions to the construction plans” and
    unreasonable demands, which “caused significant delays.”             Appellants also
    asserted that the Dos first terminated the contract without just cause, “preemptively
    4
    In their response, appellants asserted that the Dos had previously “moved several
    times for summary judgment.” Appellants asked to “incorporate the responses
    they ha[d] made in previous motions” and “incorporate by reference” the exhibits
    it had “previously offered.” However, only appellants’ December 3, 2010
    response is included in the record.
    6
    sued [them] in an attempt to get out of the contract,” and genuine issues of material
    fact existed as to appellants’ “intent.” Finally, appellants asserted that the Dos’
    summary-judgment      motion     was   “inadequately   supported”    and   did   not
    “conclusively establish breach” or “intent.”
    Appellants attached the affidavits of Felt and Wasserberg to their response.
    Felt testified that after Waterhill had committed to construct the Dos’ residence,
    the Dos “decided they did not like many things about their plans,” causing
    “massive timing delays.”       Wasserberg testified that he was the president of
    Wasserberg Investment, Inc., Waterhill’s other general partner. Both Wasserberg
    and Felt testified that they did not make “any misrepresentations to [the Dos]” and
    they had no “intent to deceive the Dos or act in any manner less than forthright and
    honest.”5
    The trial court granted the Dos’ summary-judgment motion in an
    “Interlocutory Judgment” on “liability and actual damages on all claims.”          It
    ordered Waterhill, Wasserberg, and Felt jointly and severally liable for $684,239 in
    damages and $43,575 in attorney’s fees. The trial court denied the Dos summary
    judgment on their claim for punitive damages. After the Dos nonsuited their
    punitive-damages claim, the trial court entered a final judgment.
    5
    In their response, appellants also make reference to an “Email terminating
    contract,” which they asserted established that the Dos first terminated the
    contract. However, this exhibit does not appear in the appellate record and
    appellants make no reference to the exhibit in their briefing to this Court.
    7
    Standard of Review
    To prevail on a summary-judgment motion, a movant has the burden of
    proving that it is entitled to judgment as a matter of law and there is no genuine
    issue of material fact. TEX. R. CIV. P. 166a(c); Cathey v. Booth, 
    900 S.W.2d 339
    ,
    341 (Tex. 1995). When a plaintiff moves for summary judgment on its claim, it
    must establish its right to summary judgment by conclusively proving all the
    elements of its cause of action as a matter of law. Rhone–Poulenc, Inc. v. Steel,
    
    997 S.W.2d 217
    , 223 (Tex. 1999); Anglo–Dutch Petroleum Int’l, Inc. v. Haskell,
    
    193 S.W.3d 87
    , 95 (Tex. App.—Houston [1st Dist.] 2006, pet. denied). When
    deciding whether there is a disputed, material fact issue precluding summary
    judgment, evidence favorable to the non-movant will be taken as true. Nixon v.
    Mr. Prop. Mgmt. Co., 
    690 S.W.2d 546
    , 548–49 (Tex. 1985). Every reasonable
    inference must be indulged in favor of the non-movant and any doubts must be
    resolved in its favor. 
    Id. at 549.
    Summary Judgment
    In their first issue, appellants argue that the trial court erred in granting
    summary judgment against Wasserberg and Felt individually because “the Texas
    Trust Fund Act does not apply to this case.” See TEX. PROP. CODE ANN. § 162.031
    (Vernon Supp. 2012). In their third, fourth, and sixth issues, appellants complain
    that the Dos have not established their claims for fraud, fraudulent transfer,
    8
    conversion, and breach of contract as a matter of law. In their second and fifth
    issues, appellants complain that the evidence is insufficient to hold Wasserberg and
    Felt liable individually as Waterhill’s general partners for damages or attorney’s
    fees. And, in their seventh issue, appellants complain that the trial court erred in
    striking their pleadings.
    Fraud
    In their third issue, appellants argue that the trial court erred in entering
    summary judgment on the Dos’ fraud claim because there is no evidence that Felt
    and Wasserberg “made promises of future performance with no intent of
    performing.”    They note that, in their affidavits, both Felt and Wasserberg
    “specifically denied” having “fraudulent intent.”
    The elements of common law fraud are (1) that a speaker made a material
    representation; (2) the representation was false; (3) when the representation was
    made, the speaker knew it was false or made it recklessly without any knowledge
    of the truth and as a positive assertion; (4) the speaker made the representation
    with the intent that the other party should act upon it; (5) the party acted in reliance
    on the representation; and (6) the party thereby suffered injury. Italian Cowboy
    Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 337 (Tex. 2011).
    An action for fraud pertaining to a promise of future performance requires,
    as relevant here, a showing that the promisor, at the time that the promise was
    9
    made, had no intention of performing the act. Formosa Plastics Corp. USA v.
    Presidio Eng’rs and Contractors, 
    960 S.W.2d 41
    , 48 (Tex. 1988). The mere
    failure to perform under a contract does not constitute sufficient evidence of fraud.
    
    Id. Rather, a
    plaintiff alleging a fraud claim must demonstrate that the defendant,
    at the time that he or she made the representation, had intent to deceive and had no
    intent to perform; the evidence presented must be relevant to the promisor’s intent
    at the time that the representation was made. 
    Id. To support
    their fraud claim, the Dos refer to two draw requests submitted to
    them by Waterhill: one for it to pay KV Weld $58,146 and the other for it to pay
    Boswell $56,100.     The Dos assert that copies of Waterhill’s bank accounts
    establish that appellants “commingled those specific funds into their general bank
    account.”    They argue that appellants made a “material misrepresentation”
    because, prior to execution of the parties’ construction contract, Wasserberg and
    Felt told Y Hoang “that all funds deposited or transferred to them from [the Dos or
    their bank] would be used only on the property located at 12 Farnham Park Drive,
    Houston, Texas.”6 The Dos also note that Arnold testified that he was instructed
    6
    The Dos also cite the Addendum to the Construction Agreement as an example of
    a material misrepresentation that appellants would only apply the Dos’ draw
    requests to work on the Farnham Park Drive property. However, with respect to
    draw requests, the Addendum only provides that “[a]ll draws will be paid upon the
    satisfactory completion of the approved services, jobs, construction phases and/or
    satisfactory delivery of the approved/purchased materials, items, supplies.”
    10
    by Wasserberg to apply a $48,455 payment from the Dos to “prior debts between
    [Waterhill] and KV Weld.”
    The Dos’ only evidence in support of their assertion that appellants
    “commingled” their draw request payments into their “general bank account” are
    statements from a “project account” in Waterhill’s name at Sterling Bank.
    However, these documents only show a list of various wire transfers and deposits,
    with no indication as to who made the transfers or deposits. Furthermore, both
    Wasserberg and Felt testified that they “never made any misrepresentations to [Y
    Hoang]” and did not have “any intent to deceive the Dos or act in a manner less
    than forthright and honest.” In his deposition testimony, Wasserberg denied that
    any “personal checks” or payments from other clients were deposited into the
    project account. Felt also denied that Waterhill “would take money from several
    different clients and deposit it into the same account.” And, most importantly, the
    Dos cite to no evidence that at the time that any alleged misrepresentations were
    made, Wasserberg or Felt knew that the representations were false or recklessly
    made the representations without knowledge of their truth.       See Grainger v.
    Western Cas. Life Ins. Co., 
    930 S.W.2d 609
    , 615 (Tex. App.—Houston [1st Dist.]
    1996, pet. denied) (“Issues of intent and knowledge are not susceptible to being
    readily controverted and are inappropriate for summary judgment.”). We conclude
    that genuine issues of material fact exist regarding whether appellants made any
    11
    misrepresentations or knew that any such misrepresentations were false at the time
    that they were made. Accordingly, we hold that the trial court erred in granting
    summary judgment to the Dos on their fraud claim.
    We sustain appellants’ third issue.
    Fraudulent Transfer and Conversion
    In their fourth issue, appellants complain that the trial court erred in entering
    summary judgment on the Dos’ fraudulent transfer and conversion claims.
    Section 24.005 of Texas Uniform Fraudulent Transfer Act (“TUFTA”)
    provides that:
    (a)    A transfer made . . . by a debtor is fraudulent as to a creditor,
    whether the creditor’s claim arose before or within a reasonable
    time after the transfer was made[,] . . . if the debtor made the
    transfer . . . :
    (1)   with actual intent to hinder, delay, or defraud any creditor
    of the debtor; or
    (2)   without receiving a reasonably equivalent value in
    exchange for the transfer[,] . . . and the debtor:
    (A)    was engaged or was about to engage in a business
    or a transaction for which the remaining assets of
    the debtor were unreasonably small in relation to
    the business or transaction; or
    (B)    intended to incur, or believed or reasonably should
    have believed that the debtor would incur, debts
    beyond the debtor's ability to pay as they became
    due.
    12
    TEX. BUS. & COM. CODE ANN. § 24.005(a) (Vernon 2009).                The purpose of
    TUFTA is to prevent debtors from defrauding creditors by placing assets beyond
    their reach. Tel. Equip. Network, Inc. v. TA/Westchase Place, Ltd., 
    80 S.W.3d 601
    ,
    607 (Tex. App.—Houston [1st Dist.] 2002, no pet.). A creditor has the burden to
    prove a debtor’s fraudulent intent; such intent must be affirmatively shown and
    will not be presumed. Sterquell v. Scott, 
    140 S.W.3d 453
    , 460 (Tex. App.—
    Amarillo 2004, no pet); Mladenka v. Mladenka, 
    130 S.W.3d 397
    , 405 (Tex.
    App.—Houston [14th Dist.] 2004, no pet.).           Direct proof of fraud is often
    unavailable; therefore, circumstantial evidence may be used to prove fraudulent
    intent. 
    Mladenka, 130 S.W.3d at 405
    . Fraudulent intent may be established by the
    “badges” of fraud, which include whether:
    (1)   the transfer . . . was to an insider;
    (2)   the debtor retained possession or control of the property
    transferred after the transfer;
    (3)   the transfer . . . was concealed;
    (4)   before the transfer was made . . . the debtor had been sued or
    threatened with suit;
    (5)   the transfer was of substantially all the debtor’s assets;
    (6)   the debtor absconded;
    (7)   the debtor removed or concealed assets;
    (8)   the value of the consideration received by the debtor was
    reasonably equivalent to the value of the asset transferred . . . ;
    13
    (9)   the debtor was insolvent or became insolvent shortly after the
    transfer was made . . . ;
    (10) the transfer occurred shortly before or shortly after a substantial
    debt was incurred; and
    (11) the debtor transferred the essential assets of the business to a
    lienor who transferred the assets to an insider of the debtor.
    TEX. BUS. & COM. CODE ANN. § 24.005(b).
    To support their fraudulent-transfer claim, the Dos cite Felt’s deposition
    testimony that he received $202,000 of income from Waterhill in 2007. They
    assert that the two draw request payments that they made were used by appellants
    “to either pay other obligations” or “were diverted to Felt,” which “clearly
    hindered or delayed the Dos’ efforts to have their draw payments used to pay sub
    contractors for services performed on their residence.” Again, however, the Dos
    produced scant evidence regarding appellants’ fraudulent intent; of the statutory
    “badges” indicating fraudulent intent, the Dos cite only to the facts that Felt and
    Wasserberg, as general partners of Waterhill, are “insiders” and Waterhill became
    insolvent   See TEX. BUS. & COM. CODE ANN. §§ 24.005(a)(1), 24.005(b)(3),
    24.005(b)(9). And, again, Felt and Wasserberg both denied converting any of the
    Dos’ funds or making any misrepresentations. Viewing the summary-judgment
    evidence in the light most favorable to appellants, we cannot conclude that the Dos
    have established all the elements of fraudulent transfer as a matter of law. See,
    14
    e.g., Coleman Cattle Co., Inc. v. Carpentier, 
    10 S.W.3d 430
    , 434 (Tex. App.—
    Beaumont 2000, no pet.) (stating that if fraudulent intent “is only to be deduced
    from facts and circumstances which the law considers as mere badges of fraud and
    not fraud per se, these must be submitted to the trier of fact, which draws the
    inference as to the fairness or fraudulent character of the transaction”) (quoting
    Quinn v. Dupree, 
    157 Tex. 441
    , 
    303 S.W.2d 769
    , 774 (1957)).
    In regard to conversion, the elements of a such a claim are (1) the plaintiff
    owned or had possession of the property or entitlement to possession; (2) the
    defendant unlawfully and without authorization assumed and exercised control
    over the property to the exclusion of, or inconsistent with, the plaintiff’s rights as
    an owner; (3) the plaintiff demanded return of the property; and (4) the defendant
    refused to return the property. Khorshid, Inc. v. Christian, 
    257 S.W.3d 748
    , 759
    (Tex. App.—Dallas 2008, no pet.).
    To support their claim for conversion, the Dos again argue that appellants
    “converted the specific funds tendered to [it] by the Dos for the specific purpose of
    paying subcontractors working on the Dos’ home.” However, the Dos have not
    established, as a matter of law, that appellants converted the specific funds that the
    Dos provided to appellants, and the Dos point to no summary-judgment evidence
    establishing that they demanded a return of their property or that appellants refused
    to return the property.    Viewing this evidence in the light most favorable to
    15
    appellants, we conclude that the Dos have not established the elements of
    conversion as a matter of law. Accordingly, we hold that the trial court erred in
    granting summary judgment to the Dos on their fraudulent-transfer and conversion
    claims.
    We sustain appellants’ fourth issue.
    Texas Trust Fund Act
    In their first issue, appellants complain that the trial court erred in entering
    summary judgment in favor of the Dos under the Texas Trust Fund Act, which
    provides that,
    A trustee who, intentionally or knowingly or with intent to defraud,
    directly or indirectly retains, uses, disburses, or otherwise diverts trust
    funds without first fully paying all current or past due obligations
    incurred by the trustee to the beneficiaries of the trust funds, has
    misapplied the funds.
    TEX. PROP. CODE ANN. § 162.031(a). In 2005, when the Dos and Waterhill entered
    into their construction contract, a “beneficiary” was defined as an “artisan, laborer,
    mechanic, contractor, subcontractor, or materialman who labors . . . for the
    construction or repair of an improvement on specific real property.” See Act of
    May 28, 1997, 75th Leg., R.S., ch. 1018, § 2, 1997 Tex. Gen Laws 3721 (amended
    2009) (current version at TEX. PROP. CODE ANN. § 162.003 (Vernon Supp. 2012)).
    16
    Thus, at the time that the parties contracted, the Dos did not qualify as a
    “beneficiary” under the statute. 7 See Murphey v. State, 
    86 S.W.3d 283
    , 285 (Tex.
    App.—Amarillo 2002, no pet.) (stating that, in 2002, “the relationship of trustee
    and beneficiary . . . do not apply to an owner/contractor relationship”). And, in
    their briefing, the Dos concede that “the Texas Trust Fund Act does not apply to
    this case.”   Accordingly, we hold that the trial court erred in granting summary
    judgment to the Dos under the Texas Trust Fund Act.
    We sustain appellants’ first issue.
    Breach of Contract
    In their sixth issue, appellants argue that the Dos “failed to prove all
    elements of their breach of contract claim” because they failed to produce
    “competent evidence of damages.” 8 Appellants assert that the Dos did not prove
    that the awarded costs were “reasonable and necessary” or that “the house
    7
    In 2009, the Act was amended to include a property owner as a “beneficiary of
    trust funds . . . in connection with a residential construction contract.” Act of May
    19, 2009, 81st Leg., R.S., ch. 1277, 2009 Tex. Gen. Laws 4030.
    8
    The Dos first argue that appellants have waived their challenge to the evidence of
    damages because they “did not challenge the damages evidence presented under
    the Dos’ tort theories” and the trial court “did not specify the particular grounds
    for granting summary judgment.” The Dos also argue that the entirety of the
    damages awarded by the trial court is supportable under either of their tort theories
    of liability. However, having concluded that the Dos were not entitled to
    summary judgment on their tort theories, the Dos cannot rely on any damages that
    were presumably awarded on those theories in the trial court’s order granting them
    summary judgment.
    17
    completed by [Stahl] was built to the same plans and specifications agreed to by
    Waterhill.”
    The Dos argue that their damages are supported by the summary-judgment
    evidence of “the agreed contract price” and “the price paid for the completion of
    the contract after [appellants] abandoned the premises.”       However, the initial
    contract price of $1,819,320.00, the Stahl contract price of $1,765,506.00, and the
    money paid to appellants in the amount of $569,589.96 account for only
    $524,326.49 of the total damages of $684,239.00 awarded to the Dos.
    Furthermore, the Dos have not established that their contract with Stahl provided
    for the construction of the same or a similar residence that they contracted with
    appellants to build. As such, we cannot conclude, as a matter of law, that the
    damages awarded to the Dos put them “in the same economic position in which
    [they] would have been had the contract not been breached.” See CDB Software,
    Inc. v. Kroll, 
    992 S.W.2d 31
    , 37 (Tex. App.—Houston [1st Dist.] 1998, pet.
    denied). Finally, although the Dos assert that appellants first breached the contract
    after they had “abandoned the premises,” both Wasserberg and Felt testified, in
    their affidavits, that the Dos first breached the contract by delaying the
    construction with unreasonable demands and financing issues.           Viewing the
    summary-judgment evidence in the light most favorable to appellants, we cannot
    conclude that the Dos established all the elements of their breach-of-contract claim
    18
    as a matter of law. Accordingly, we hold that the trial court erred in entering
    summary judgment in favor of the Dos on their breach-of-contract claim.
    We sustain appellants’ sixth issue.
    Conclusion
    Having concluded that genuine issues of material fact exist on all of the
    claims brought forth by the Dos, we need not address appellants’ second, sixth, and
    seventh issues, in which they contend that Wasserberg and Felt cannot be held
    individually liable for damages or attorney’s fees and the trial court erred in
    striking their affirmative defenses.
    We reverse the judgment of the trial court and remand the case for
    proceedings consistent with this opinion.
    Terry Jennings
    Justice
    Panel consists of Justices Jennings, Higley, and Sharp.
    19