CSL Property Management Co. and Greatland Investments, Inc. v. Thyssenkrupp Elevator ( 2013 )


Menu:
  • Opinion issued January 31, 2013.
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-11-00665-CV
    ———————————
    CSL PROPERTY MANAGEMENT CO. AND GREATLAND
    INVESTMENTS, INC., Appellants
    V.
    THYSSENKRUPP ELEVATOR COMPANY, Appellee
    On Appeal from the 11th District Court
    Harris County, Texas
    Trial Court Case No. 2009-75846
    MEMORANDUM OPINION
    This is a dispute between an elevator contractor and the manager and owner
    of a building over the work performed and payments owed under the parties’
    contracts. CSL Property Management Co. and Greatland Investments, Inc. appeal
    from the trial court’s summary judgment in favor of ThyssenKrupp Elevator
    Company. We affirm the trial court’s judgment.
    Background
    Greatland owns the Sterling Center, a commercial building managed by
    CSL. Hurricane Ike caused damage to the Sterling Center, including its elevator.
    Greatland hired Emergency Services 24, Inc. to repair the building, and Emergency
    Services subcontracted the elevator work to ThyssenKrupp. The subcontract
    provided for upfront payment of 30% of the contract price ($31,393.50), with the
    remainder of the contract price (originally $96,558) to be paid later. Emergency
    Services paid ThyssenKrupp the $31,393.50 initial payment on a credit card in the
    name of Micah Bass, Emergency Services’ owner. After receiving the initial
    payment, ThyssenKrupp started work on the elevator. Emergency Services
    subsequently had a dispute with Greatland and left the project in December 2008.
    After   Emergency Services      left   the project,   CSL   requested   that
    ThyssenKrupp remain on the job. CSL and ThyssenKrupp executed a change order
    that adjusted ThyssenKrupp’s compensation under the elevator subcontract from
    $96,558 to $92,269. At ThyssenKrupp’s request, CSL also sent ThyssenKrupp a
    letter, signed by CSL’s president, in which CSL “hereby assum[ed] all terms,
    conditions, and obligations of the elevator modernization contract previously held
    2
    by Emergency Services 24, Inc.” In the letter, CSL stated, “ThyssenKrupp will
    retain the $31,393.50 as initial payment toward the contract price.”
    In January 2009, Bass and Emergency Services disputed the $31,393.50
    credit card payment to ThyssenKrupp.
    In March, CSL and ThyssenKrupp executed an assumption agreement, under
    which CSL assumed Emergency Services’ rights and obligations under the
    subcontract. In the assumption agreement, CSL and ThyssenKrupp modified the
    subcontract’s price provision to provide for compensation in the amount of
    $60,875.50 (the modified contract price of $92,269 less the initial payment of
    $31,293.50 from Emergency Services). The assumption agreement also contained
    an indemnity provision:
    3.4    Indemnification
    In addition to the indemnification provision of the Subcontract CSL
    further agrees to defend, indemnify and hold harmless ThyssenKrupp,
    its parents, subsidiaries, affiliates, employees, subcontractors,
    insurers, attorneys, and agents, from any and all claims, demands,
    suits, and/or proceedings brought or made by [Emergency Services],
    or any of their parents, subsidiaries, affiliates, employees,
    subcontractors, insurers, attorneys, and agents arising out of or related
    to this Assumption Agreement, the Subcontract, ThyssenKrupp
    Elevator’s retention of the Initial Payment and ThyssenKrupp’s
    performance pursuant to the Subcontract from February 20, 2009
    forward, excluding any claim(s) by [Emergency Services] for
    improper Elevator Work provided by ThyssenKrupp pursuant to the
    Subcontract, prior to February 20, 2009. . . .
    3
    An early draft of the agreement included an “additional compensation”
    provision stating, “As consideration for entering into this Assumption Agreement
    and in the event that ThyssenKrupp is required to return the $31,293.50 to
    [Emergency Services], CSL shall compensate ThyssenKrupp for the full contract
    value: $92,269.” This provision was rejected by CSL and not included in the final
    written agreement. The parties assert that they were not aware that Bass had
    disputed the $31,293.50 payment with his credit card company at the time they
    executed the assumption agreement.
    In June, Bass’s credit card company charged-back the $31,393.50 payment
    to ThyssenKrupp. ThyssenKrupp appealed the chargeback with the credit card
    company but lost due to a lack of documentation of the transaction.1 After the
    chargeback became final, Greatland sued Bass and Emergency Services seeking to
    recover the $31,393.50 payment. In the lawsuit, Greatland alleged that Bass and
    Emergency Services “rushed to Houston” from Florida in the wake of Hurricane
    Ike and “targeted Hurricane Ike victims who were property owners,” particularly
    “business owners in Houston’s local Vietnamese community,” by “promising to
    make emergency repairs at no cost” and by obtaining insurance proceeds for the
    repairs, which Bass and Emergency Services never intended to complete. With
    1
    Both parties blame the other party for failing to adequately document Emergency
    Services’ role in the project.
    4
    respect to the subject matter of this lawsuit, Greatland alleged that Bass and
    Emergency Services had obtained insurance proceeds from Greatland’s insurer to
    cover the $31,393.50 payment to ThyssenKrupp and had retained the insurance
    proceeds despite having secured a chargeback of the payment. The court ultimately
    dismissed that suit by agreement of the parties to the suit.
    In August, ThyssenKrupp demanded that CSL reimburse the $31,393.50
    chargeback pursuant to the indemnity provision in the assumption agreement. CSL
    disputed any indemnity obligation and also did not pay ThyssenKrupp the
    $60,875.50 balance owed under the subcontract for ThyssenKrupp’s elevator work.
    ThyssenKrupp initiated this suit in November 2009 to recover both
    indemnification for the $31,393.50 initial payment and payment of the $60,875.50
    for the elevator work performed. CSL and Greatland filed counterclaims and
    “cross-claims” against ThyssenKrupp asserting that ThyssenKrupp had failed to
    deliver functioning elevators. According to ThyssenKrupp, the elevators were
    completed but not turned on due to CSL’s nonpayment. A few months after
    ThyssenKrupp filed suit, CSL sent ThyssenKrupp a check for $60,875.50 but
    labeled the check, “Final payment in complete satisfaction of assumption of the
    subcontract agreement.” ThyssenKrupp returned the check to CSL’s attorneys.
    5
    Shortly before trial, the parties filed cross-motions for summary judgment.2
    The trial court granted summary judgment in favor of ThyssenKrupp on all of its
    claims, awarding ThyssenKrupp $92,269 on its claims against CSL, plus attorneys’
    fees and interest, and entering a take-nothing judgment on CSL’s and Greatland’s
    claims against ThyssenKrupp. This appeal followed.
    ThyssenKrupp’s Claims
    CSL’s and Greatland’s first three issues challenge the trial court’s judgment
    in favor of ThyssenKrupp on its claims against CSL. ThyssenKrupp sought and
    obtained summary judgment against CSL on its claims for breach of contract and
    suit on verified account, each of which sought recovery of damages in the amount
    of $92,269—the full contract price, including reimbursement for the initial
    payment. The trial court granted ThyssenKrupp’s summary judgment motion and
    awarded ThyssenKrupp $92,269 in damages.
    A.    Standard of review
    The parties filed cross-motions for traditional summary judgment on
    ThyssenKrupp’s claims against CSL. We review summary judgments de novo.
    Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005); City of
    Galveston v. Tex. Gen. Land Office, 
    196 S.W.3d 218
    , 221 (Tex. App.—Houston
    2
    ThyssenKrupp moved for summary disposition of all claims, including CSL’s and
    Greatland’s claims against it. CSL and Greatland moved for traditional summary
    judgment on ThyssenKrupp’s claim for contractual indemnity only.
    6
    [1st Dist.] 2006, pet. denied). When, as here, the parties file cross-motions for
    summary judgment on overlapping issues, and the trial court grants one motion and
    denies the other, we review the summary judgment evidence supporting both
    motions and “render the judgment that the trial court should have rendered.” FM
    Props. Operating Co. v. City of Austin, 
    22 S.W.3d 868
    , 872 (Tex. 2000).
    ThyssenKrupp was entitled to summary judgment on its claims against CSL
    if it conclusively established each element of its claims. See TEX. R. CIV. P.
    166a(c); Frost Nat’l Bank v. Fernandez, 
    315 S.W.3d 494
    , 508–09 (Tex. 2010);
    City of 
    Galveston, 196 S.W.3d at 221
    . CSL was entitled to summary judgment on
    ThyssenKrupp’s claims if it conclusively negated at least one essential element of
    the claims or conclusively established each element of an affirmative defense to
    the claims. See TEX. R. CIV. P. 166a(c); Frost Nat’l 
    Bank, 315 S.W.3d at 508
    –09.
    Because the summary judgment does not specify the grounds on which it was
    granted, CSL and Greatland must demonstrate that none of the proposed grounds is
    sufficient to support the judgment. See Rogers v. Ricane Enters., 
    772 S.W.2d 76
    ,
    79 (Tex. 1989); Tilotta v. Goodall, 
    752 S.W.2d 160
    , 161 (Tex. App.—Houston [1st
    Dist.] 1988, writ denied); West v. SMG, 
    318 S.W.3d 430
    , 437 (Tex. App.—
    Houston [1st Dist.] 2010, no pet.). Conversely, we will affirm the judgment if any
    one of the theories advanced in the motion is meritorious. Joe v. Two Thirty Nine
    Joint Venture, 
    145 S.W.3d 150
    , 157 (Tex. 2004); 
    West, 318 S.W.3d at 437
    .
    7
    B.    ThyssenKrupp’s indemnity claim
    In their first issue, CSL and Greatland challenge the trial court’s traditional
    summary judgment in favor of ThyssenKrupp on its contractual indemnity claim
    for the $31,393.50 initial payment.
    1.     The parties’ arguments
    CSL and Greatland contend that CSL’s indemnity obligation applies only to
    claims “brought or made . . . from February 20, 2009 forward,” and therefore does
    not apply to the $31,393.50 chargeback, which CSL asserts was first initiated with
    the credit card company in January 2009. Alternatively, CSL and Greatland
    contend that the $31,393.50 charge dispute falls within the indemnity clause’s
    exclusion of claims by Emergency Services “for improper Elevator Work provided
    by ThyssenKrupp” before February 20, 2009. CSL and Greatland further argue that
    the indemnity provision should be construed against ThyssenKrupp, as the drafter,
    and should not be construed as applying to the initial payment because CSL
    rejected the “additional compensation” draft provision that required CSL to
    compensate ThyssenKrupp for the full contract price in the event that
    ThyssenKrupp was required to return the initial payment. Finally, CSL contends
    that it is ThyssenKrupp’s fault that Bass’s credit card company approved the
    chargeback, and therefore ThyssenKrupp seeks indemnification for its own
    negligence and is subject to the express negligence doctrine.
    8
    ThyssenKrupp responds that the indemnity provision expressly contemplates
    indemnification relating to “ThyssenKrupp Elevator’s retention of the Initial
    Payment” from Emergency Services; that it agreed to deletion of the “additional
    compensation” provision only because the assumption agreement contained the
    indemnity provision; that January 2009 is not the relevant date for the chargeback,
    which the parties were not aware of until April 2009 and which did not actually
    occur until June 2009; and that the chargeback did not arise out of “improper
    Elevator Work” but rather out of Greatland’s removal of Emergency Services as
    general contractor on the project. ThyssenKrupp also disputes that it was the
    drafter of the assumption agreement, asserting that the parties worked together to
    reach a mutually agreeable contract, and that it was at fault for the chargeback.
    2.     The summary judgment evidence of Bass’s claim
    CSL identifies January 30, 2009 as the relevant date based on a letter to Bass
    from his credit card company that Bass filled out and returned. The letter from the
    credit card company, dated January 29, 2009, states that it relates to Bass’s
    “inquiry about the transaction dated 11/11/2008 in the amount of $31,393.50.” The
    letter requests that Bass provide the credit card company with specific information
    about when “the order was (CIRCLE ONE) cancelled/ returned,” why the “order
    was cancelled,” and “the merchant’s response when you attempted to resolve your
    dispute.” The letter also states that a “conditional credit has been issued in your
    9
    account while we investigate this matter on your behalf.” Handwritten on the letter
    is Bass’s response: he circled that the “order” was “returned” and provided the
    return date as December 1, 2008. In the blank next to the sentence beginning, “This
    order was cancelled because,” he wrote, “cancelled not my contract.” In response
    to the request for details about “the merchant’s response when you attempted to
    resolve your dispute,” he wrote, “The owner of elevator is to pay for this.” Bass
    signed the letter and dated his signature January 30, 2009. The evidence does not
    conclusively establish when the credit card company received Bass’s response, but
    the letter bears a “received” stamp dated February 12, 2009.
    The record also contains a letter from Bass to his credit card company dated
    March 3, 2009, with the subject line “re: Unauthorized charge on Personal Account
    for Micah D. Bass.” In this letter, Bass asserted that ThyssenKrupp’s contract was
    with Emergency Services, not Bass personally, and ThyssenKrupp did not have
    authority to charge the initial payment to his personal credit card.
    Bass’s credit card company executed an “Expedited Billing Dispute
    Resolution Process Form” on April 15, 2009. ThyssenKrupp and CSL each assert
    that this is the date on which they became aware of the chargeback procedure.
    Bass’s credit card company charged-back the initial payment on June 23, 2009,
    and sent ThyssenKrupp notice of the chargeback on the same date.
    10
    3.    Rules of construction
    We construe indemnity provisions pursuant to the ordinary principles of
    contract interpretation. See Gulf Ins. Co. v. Burns Motors, Inc., 
    22 S.W.3d 417
    , 423
    (Tex. 2000). Our primary purpose is to give effect to ThyssenKrupp’s and CSL’s
    intent, as expressed in their agreement. See id.; Houston Exploration Co. v.
    Wellington Underwriting Agencies, Ltd., 
    352 S.W.3d 462
    , 469 (Tex. 2011); Don’s
    Bldg. Supply, Inc. v. OneBeacon Ins. Co., 
    267 S.W.3d 20
    , 23 (Tex. 2008). We
    construe the assumption agreement in light of the facts and circumstances
    surrounding its execution, but we may not consider parol evidence to vary the
    terms of the agreement or to create ambiguity where the language of the agreement
    is clear and unambiguous. See Houston 
    Exploration, 352 S.W.3d at 469
    ; Don’s
    Bldg. 
    Supply, 267 S.W.3d at 23
    ; David J. Sacks, P.C. v. Haden, 
    266 S.W.3d 447
    ,
    450–51 (Tex. 2008). If the contract uses unambiguous language, we enforce it as
    written. See David J. 
    Sacks, 266 S.W.3d at 450
    –51; Fiess v. State Farm Lloyds,
    
    202 S.W.3d 744
    , 753 (Tex. 2006). This is because the parties’ intent is “governed
    by what they said in the agreement, not by what one side or the other alleges they
    intended to say but did not.” Gilbert Tex. Const., L.P. v. Underwriters at Lloyd’s
    London, 
    327 S.W.3d 118
    , 127 (Tex. 2010).
    11
    4.    Construction of the indemnity provision
    Under the assumption agreement’s indemnity provision, CSL agreed to
    indemnify ThyssenKrupp “from any and all claims, demands, suits, and/or
    proceedings . . . brought or made by” Emergency Services and its agents “arising
    out of or related to . . . ThyssenKrupp Elevator’s retention of the Initial Payment
    . . . from February 20, 2009 forward.” The central issue here is whether the
    chargeback of the initial payment was brought or made “from February 20, 2009
    forward.” The February 20 date used in the indemnity provision is also used
    throughout the assumption agreement, demonstrating the parties’ intent that CSL
    would effectively step into Emergency Services’ shoes with respect to the elevator
    subcontract, but only from February 20 forward. For example, CSL “accept[ed]
    and assume[d] the terms and conditions of the Subcontract from [Emergency
    Services] and assume[d] all of the rights, benefits and obligations of [Emergency
    Services], from February 20, 2009 forward and covenant[ed] and agree[d] to
    observe and perform all of the duties and obligations including but not limited to
    the payment directly to ThyssenKrupp for Elevator Work pursuant to the
    Subcontract.” The parties do not specify in their briefing why they chose February
    20 as the pivotal date. The evidence indicates that the assumption agreement,
    which was ultimately executed in March, initially bore a February execution date.
    12
    Unlike the remainder of the contract, under which CSL’s obligations to
    ThyssenKrupp generally arose on February 20 and continue forward in time,
    CSL’s obligations under the indemnity provision may extend to events and
    occurrences before February 20. So long as a “claim[], demand[], suit[], and/or
    proceeding[]”is brought on or after February 20, and the subject matter is within
    the scope of the indemnity provision, it does not matter when the events giving rise
    to the claim, demand, suit, or proceeding occurred; the exception to this is the
    exclusion for “improper” elevator work, discussed below.3 Relatedly, while the
    remainder of the contract focuses on CSL’s assumption of pre-existing right and
    obligations previously afforded to Emergency Services, the indemnity provision
    3
    The terms “claim,” “demand,” and “proceeding” are not defined in the assumption
    agreement. We therefore give those terms their ordinary meaning, and may look to
    dictionaries for commonly accepted usages. See, e.g., Gilbert Tex. 
    Const., 327 S.W.3d at 127
    ; E.I. Du Pont De Nemours & Co. v. Shell Oil Co., 
    259 S.W.3d 800
    ,
    806 (Tex. App.—Houston [1st Dist.] 2007, pet. denied). Black’s Law Dictionary’s
    definitions of “claim” include: “[t]he aggregate of operative facts giving rise to a
    right enforceable by a court,” “[t]he assertion of an existing right; any right to
    payment or to an equitable remedy, even if contingent or provisional,” “[a]
    demand for money or property to which one asserts a right,” “[a]n interest or
    remedy recognized at law; the means by which a person can obtain a privilege,
    possession, or enjoyment of a right or thing,” and “[a] right to payment or to an
    equitable remedy for breach of performance if the breach gives rise to a right to
    payment.” BLACK’S LAW DICTIONARY 240–41 (7th ed. 1999). It defines a
    “demand” as “[t]he assertion of a legal right” and “[a] request for payment of a
    debt or an amount due.” 
    Id. at 441.
    Finally, it defines a “proceeding” as “[t]he
    regular and orderly progression of a lawsuit, including all acts and events between
    the time of commencement and the entry of judgment,” “[a]ny procedural means
    for seeking redress from a tribunal or agency,” “[a]n act or step that is part of a
    larger action,” and “[t]he business conducted by a court or other official body; a
    hearing.”
    13
    imposes a new duty on CSL, not defined by Emergency Services’ rights or
    obligations under the subcontract.
    A primary purpose of the assumption agreement, as evidenced on the face of
    the agreement, is to protect ThyssenKrupp from the risks associated with
    Greatland’s removal of Emergency Services as the general contractor for the
    project after the project commenced, especially with respect to payment of the
    contract price. References to this can be found throughout the agreement: “CSL
    hereby . . . covenants and agrees to observe and perform all of the duties and
    obligations including but not limited to the payment directly to ThyssenKrupp for
    Elevator Work pursuant to the Subcontract”; “CSL further acknowledges and
    agrees with ThyssenKrupp that, subject to the applicable provision(s) of the
    Subcontract, CSL is responsible for the payment of any and all compensation to
    ThyssenKrupp for services and/or materials provided or to be provided by
    ThyssenKrupp per the subcontract.” And the indemnity provision evidences a
    specific intent to protect ThyssenKrupp with respect to the risk that Emergency
    Services would seek to rescind the initial payment as a result of Emergency
    Services’ removal from the project by requiring CSL to indemnify ThyssenKrupp
    “from any and all claims, demands, suits, and/or proceedings brought or made by”
    Emergency Services or its agents “arising out of or relating to . . . ThyssenKrupp
    Elevator’s retention of the Initial Payment[.]”
    14
    Additionally, the contract documents demonstrate the parties’ intent that
    ThyssenKrupp would receive the full contract price―$92,269―for its elevator
    work, as modified by the first change order. The change order executed between
    Emergency Services and CSL after Emergency Services left the project reflects a
    contract price of $92,269. The assumption agreement recites that CSL requested
    that ThyssenKrupp “retain” the $31,393.50 initial payment made by Emergency
    Services and that CSL “owe[d] ThyssenKrupp the balance remaining under the
    Subcontract . . . $60,875.50.” CSL admits that it submitted the ThyssenKrupp
    subcontract to its insurer, and its insurer issued payment “for that full price, the
    [$]92,000.”
    In light of these provisions, the contract unambiguously establishes the
    parties’ intent that CSL would indemnify ThyssenKrupp from Emergency
    Services’ revocation of the initial payment. CSL’s alternative interpretation of the
    provision would allow CSL to avoid one of its principle obligations to
    ThyssenKrupp under the contract by relating the chargeback back to the date on
    which Bass filled out one of his credit card company’s charge dispute forms.
    Nothing in the contract supports a contention that the parties intended the February
    20 date in the indemnity provision to relieve CSL of its indemnity obligation in the
    event that, purportedly unbeknownst to the parties, Emergency Services or Bass
    15
    had contacted his credit card company about the charge before February 20 and the
    execution of the agreement.
    Instead, we read the February 20 date as excluding any disputes that had
    developed into a claim, demand, proceeding or lawsuit between Emergency
    Services and ThyssenKrupp before that date. This is consistent with the indemnity
    provision’s exclusion, which carves out pre-February 20 disputes between
    Emergency Services and ThyssenKrupp relating to ThyssenKrupp’s elevator work
    under the subcontract. CSL is obligated under the assumption agreement to
    indemnify ThyssenKrupp for claims, demands, proceedings, and suits relating to
    the initial payment “from February 20, 2009 forward,” and that obligation was in
    effect in April 2009 when the Bass’s credit card company initiated its expedited
    billing dispute resolution process and in June 2009 when the credit card company
    demanded chargeback of the initial payment. Because the assumption agreement is
    unambiguous as to the parties’ intent with respect to ThyssenKrupp’s retention of
    the initial payment, we need not consider extrinsic evidence. See Houston
    
    Exploration, 352 S.W.3d at 469
    –70 (stating that contract negotiations “may have
    some relevance in ascertaining the dominant purpose and intent of the parties
    embodied in the contract interpreted as a whole”).
    We reject CSL’s contention that the chargeback falls within the indemnity
    provision’s exclusion for “improper Elevator Work.” There is no evidence in the
    16
    record that the chargeback related to the nature or quality of ThyssenKrupp’s
    elevator work. To the contrary, the evidence establishes that the chargeback is the
    result of Bass’s representations to his credit card company that he did not receive
    the merchandise for which he paid. The chargeback notice repeatedly represents
    that the reason for the charge back was “Non-Receipt of Merchandise” and that
    “[t]he chargeback occurred because your customer claims they have paid for items
    that were to be delivered from your establishment but have not yet been received.”
    Although CSL and Greatland assert that this is evidence that ThyssenKrupp “failed
    to install an elevator at the Sterling Center,” it is clear that the customer referenced
    by the credit card company is Bass, not CSL or Greatland.
    We likewise reject CSL’s reliance on the express negligence doctrine.
    Because indemnification of a party for its own negligence is an extraordinary
    shifting of risk, indemnity provisions that require one party to indemnify another
    for losses caused by the other party’s own negligence are subject to special notice
    requirements. See, e.g., Dresser Indus., Inc. v. Page Petroleum, Inc., 
    853 S.W.2d 505
    , 508 (Tex. 1993). One such notice requirement is the express negligence
    doctrine. 
    Id. This doctrine
    states that “a party seeking indemnity from the
    consequences of that party’s own negligence must express that intent in specific
    terms within the four corners of the contract.” Id.; see Audubon Indem. Co. v.
    Custom Site-Prep, Inc., 
    358 S.W.3d 309
    , 319 (Tex. App.—Houston [1st Dist.]
    17
    2011, pet. denied) (“The express negligence doctrine dictates that a party’s intent
    to be released or indemnified from its own future negligence must be clear and
    unambiguous.”).
    The express negligence doctrine applies when the claim for which indemnity
    is owed is based on the negligence of the party seeking indemnity; it does not
    apply to CSL’s obligation to indemnify ThyssenKrupp from the chargeback when
    Bass did not assert that ThyssenKrupp was negligent in obtaining the chargeback
    and the credit card company did not rely on any allegation of negligence by
    ThyssenKrupp in processing the chargeback. See, e.g., Dresser 
    Indus., 853 S.W.2d at 508
    ; Audubon 
    Indem., 358 S.W.3d at 319
    . The only allegation of negligence on
    the part of ThyssenKrupp is CSL’s allegation that ThyssenKrupp was negligent in
    failing to better document the initial payment charge and would have prevailed in
    the chargeback appeal if it had provided better documentation. CSL has not
    identified any Texas case extending the express negligence doctrine to such
    circumstances, and we decline to do so here. Cf. Audubon 
    Indem., 358 S.W.3d at 319
    (declining to apply express negligence doctrine when claim against indemnitee
    was not based on indemnitee’s negligence).
    We overrule CSL’s and Greatland’s first issue.
    18
    C.    ThyssenKrupp’s breach of contract claim
    In their second issue, CSL and Greatland challenge the trial court’s summary
    judgment in favor of ThyssenKrupp on its breach of contract claim, arguing that
    “ThyssenKrupp refused to fulfill its contractual obligations even though CSL had
    offered and had tendered payment of the full amount required under the
    Assumption Agreement for the turnover of a working elevator.” Because we have
    held that CSL was obligated to indemnify ThyssenKrupp for the chargeback of the
    initial payment, CSL’s “tendered payment” necessarily was not fulfillment of
    CSL’s contractual obligations to ThyssenKrupp. See Baucum v. Great Am. Ins. Co.
    of N.Y., 
    370 S.W.2d 863
    , 866 (Tex. 1963) (“A tender is an unconditional offer by a
    debtor or obligor to pay another . . . a sum not less in amount than that due . . . .”).
    Moreover, the evidence in the record shows an offer of payment only after this
    lawsuit was filed and expressly conditioned the payment on acceptance in
    “complete satisfaction” of the parties’ dispute.4 See C. R. Bean Corp. v. Rodriguez,
    4
    In their reply brief, CSL and Greatland contend that there is evidence in the record
    that they made an offer of payment before the settlement offer made in the course
    of this lawsuit, but the evidence they cite in support of this contention does not
    establish any pre-lawsuit offers of settlement. First, they cite to affidavit testimony
    that does not provide any dates or otherwise establish the timing of payment
    offers, and that is not inconsistent with the evidence that CSL and Greatland
    offered a check to ThyssenKrupp only once, after the lawsuit was filed and in
    complete satisfaction of all claims. Second, they cite to deposition testimony from
    Isabell Howard who, when asked whether Ms. Le (of CSL) “[]ever told you that
    they were refusing to pay the payment,” responded, “She didn’t say ‘refused.’ She
    wasn’t going to pay this until there was resolution on the – that initial 31,000 and
    change.” This testimony supports ThyssenKrupp’s contention that CSL refused to
    19
    
    583 S.W.2d 900
    , 901 (Tex. App.—Corpus Christi 1979, no writ) (“A tender, to be
    effective, must be legally valid; it must be unconditional; it is without legal effect
    if it is accompanied by conditions which the debtor has no right to impose.”)
    (citing Baucum, 
    370 S.W.2d 863
    ; Plasky v. Gulf Ins. Co., 
    335 S.W.2d 581
    (Tex.
    1960)). Thus, we reject CSL’s contention that its post-lawsuit, conditional offer of
    $60,875.50 fulfilled its contractual obligations to ThyssenKrupp or constituted a
    valid tender of payment that imposed on ThyssenKrupp a duty to turn over the
    elevator.
    In their reply brief, CSL and Greatland contend that there is no evidence that
    ThyssenKrupp ever completed the elevator work or arranged for a final inspection.
    But the record does contain evidence that the elevator work was completed—it
    contains deposition testimony, affidavit testimony, invoices, and records showing
    the elevator parts and services rendered by ThyssenKrupp and the amounts due in
    payment for these parts and services under the contract. The record also establishes
    that the parties never arranged for the final turnover meeting—at which the
    inspection would be performed, payment of any outstanding amounts due under
    the contract would be made, and the elevator would be turned on—and that CSL
    refused to make payment. This is not limited to CSL’s refusal to indemnify
    make any payment unless ThyssenKrupp dropped its demand for indemnity of the
    $31,393.50 initial payment.
    20
    ThyssenKrupp for the $31,393.50 initial payment—CSL had not paid any of
    ThyssenKrupp’s invoices and made no payment or offer of payment until after this
    lawsuit was filed.
    Although there is also evidence in the record that ThyssenKrupp was not
    willing to turn over the elevator until CSL paid the full contract price, including the
    initial payment, we have held that ThyssenKrupp was entitled to recover this
    amount from CSL under the contracts. Additionally, the subcontract does not place
    the burden of arranging for turnover of the elevator on ThyssenKrupp, as opposed
    to CSL. The only specific duty imposed by the contract with respect to
    arrangements for turning over the elevator are imposed on CSL: “Upon notice
    from [ThyssenKrupp] that the installation of the elevator has been completed,
    [CSL] will arrange to have present at the installation site a person duly authorized
    to make the final inspection and to provide a written acceptance.” Moreover, as
    CSL and Greatland point out in their briefing, CSL and Greatland demanded that
    ThyssenKrupp remove the elevator from the premises.
    We overrule CSL’s and Greatland’s second issue.
    D.    ThyssenKrupp’s suit on sworn account
    In their third issue, CSL and Greatland challenge the trial court’s summary
    judgment in favor of ThyssenKrupp on its suit on sworn account. Because we have
    affirmed the trial court’s summary judgment on the basis of ThyssenKrupp’s
    21
    breach of contract suit, we need not determine whether the summary judgment
    could also be affirmed on the basis of ThyssenKrupp’s suit on sworn account.
    We overrule CSL’s and Greatland’s third issue.
    CSL’s and Greatland’s Claims against ThyssenKrupp
    In their live pleadings, CSL asserted counterclaims against ThyssenKrupp
    for “breach of contract, fraud, fraud in the inducement, violations of the Texas
    Deceptive Trade Practices – Consumer Protection Act, breach of express and
    implied warranties of merchantability, of fitness for a particular purpose, of good
    and workmanlike services, and unreasonable collection efforts,” and Greatland
    asserted “cross-claims” against ThyssenKrupp for “violations of the Texas
    Deceptive Trade Practices – Consumer Protection Act, breach of express and
    implied warranties of merchantability, of fitness for a particular purpose, of good
    and workmanlike services, and unreasonable collection efforts.” They also asserted
    defenses based on, among other things, fraud and estoppel theories. ThyssenKrupp
    moved for no-evidence summary judgment on each of CSL’s and Greatland’s
    claims and affirmative defenses.
    A.    Standard of review
    ThyssenKrupp was entitled to a no-evidence summary judgment on each of
    CSL’s and Greatland’s claims and affirmative defenses as to which (1)
    ThyssenKrupp asserted in its motion that there was no evidence of one or more
    22
    specified elements and (2) CSL and Greatland produced no summary judgment
    evidence raising a genuine issue of material fact on those elements. See TEX. R.
    CIV. P. 166a(i); Frost Nat'l 
    Bank, 315 S.W.3d at 508
    –09; LMB, Ltd. v. Moreno,
    
    201 S.W.3d 686
    , 688 (Tex. 2006); City of 
    Galveston, 196 S.W.3d at 221
    ; Wilson v.
    Shanti, 
    333 S.W.3d 909
    , 916 (Tex. App.—Houston [1st Dist.] 2011, pet. denied).
    To avoid summary judgment, CSL and Greatland were required to file a timely
    response identifying evidence in the record sufficient to raise an issue of fact on
    each challenged element of their claims and affirmative defenses. See TEX. R. CIV.
    P. 166a(i); Imkie v. Methodist Hosp., 
    326 S.W.3d 339
    , 343 (Tex. App.—Houston
    [1st Dist.] 2010, no pet.) (“If a nonmovant wishes to assert that, based on the
    evidence in the record, a fact issues exists to defeat a no-evidence motion for
    summary judgment, the nonmovant must timely file a response to the motion
    raising this issue before the trial court.”).
    B.     Fraud claims and defenses
    In their fourth issue, CSL and Greatland argue,
    The trial court erred in granting no-evidence summary judgment for
    ThyssenKrupp on CSL’s and Greatland’s affirmative claims and
    defenses of fraud, fraud in the inducement, promissory estoppel, and
    equitable estoppel. ThyssenKrupp moved for no-evidence [summary
    judgment] on these claims contending that (1) there was no evidence
    of a misrepresentation or promise; and (2) there was no evidence of
    any reliance on the misrepresentation or promise. The summary
    judgment record[] presents evidence as to each of these challenged
    elements. ThyssenKrupp represented and promised that it would
    deliver a functional elevator upon payment of $60,875.50[].
    23
    ThyssenKrupp further represented that CSL would only be
    responsible for payment of $60,875.50[]. ThyssenKrupp never
    disclosed that it would take steps to hold CSL hostage with an
    inoperable elevator in the event [Emergency Services’] credit card
    payment was returned. CSL and Greatland relied on these
    representations and nondisclosures in the execution of the Assumption
    Agreement. ThyssenKrupp’s representations were however false.
    Accordingly, ThyssenKrupp’s motion for no-evidence summary
    judgment should have been denied.
    (record citations omitted). CSL and Greatland made the same argument in their
    response to ThyssenKrupp’s motion for summary judgment.
    CSL and Greatland do not accurately portray ThyssenKrupp’s grounds for
    summary judgment on their fraud-related claims. ThyssenKrupp specifically
    challenged CSL’s and Greatland’s evidence of each element of fraud, including the
    elements that ThyssenKrupp (1) made a false representation with knowledge that
    the representation was false or recklessly made a positive assertion without
    knowledge as to the truthfulness of the representation and (2) intended that CSL
    and Greatland rely on the representation. See Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 242 (Tex. 2001) (identifying elements of fraud). These elements are
    likewise necessary to a fraudulent inducement claim. See Coastal Bank SSB v.
    Chase Bank of Tex., N.A., 
    135 S.W.3d 840
    , 843 (Tex. App.—Houston [1st Dist.]
    2004, no pet.). Knowledge of falsity and intent are also necessary elements of
    24
    CSL’s and Greatland’s equitable estoppel defense.5 See Schroeder v. Texas Iron
    Works, Inc., 
    813 S.W.2d 483
    , 489 (Tex. 1991) (identifying elements of equitable
    estoppel), overruled on other grounds by In re United Servs. Auto. Ass’n, 
    307 S.W.3d 299
    (Tex. 2010).
    Because CSL and Greatland failed to identify, in their summary judgment
    response and on appeal, evidence raising an issue of fact on these necessary
    elements of their fraud claims and defenses, we must affirm the trial court’s
    summary judgment. See TEX. R. CIV. P. 166a(i); 
    Imkie, 326 S.W.3d at 343
    , 347.
    We overrule CSL’s and Greatland’s fourth issue.
    C.    Breach of contract and prior breach
    In their fifth issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on their breach of contract claim and
    prior-breach defense because the summary judgment evidence “conclusively
    establish[ed] that ThyssenKrupp was required to provide a working elevator upon
    5
    CSL’s and Greatland’s promissory estoppel defense is not applicable to the claims
    at issue here. Promissory estoppel is an exception to the statute of frauds that
    allows the enforcement of an otherwise unenforceable promise. See Nagle v.
    Nagle, 
    633 S.W.2d 796
    , 800 (Tex. 1982) (holding that Texas Supreme Court had
    narrowed promissory estoppel doctrine “to cases where the promise was ‘to sign a
    written agreement which itself complies with the Statute of Frauds.’”) (quoting
    “Moore” Burger, Inc. v. Phillips Petroleum Co., 
    492 S.W.2d 934
    , 934 (Tex.
    1973); Dodson v. Kung, 
    717 S.W.2d 385
    , 389 (Tex. App.—Houston [14th Dist.]
    1986, writ ref’d n.r.e.) (“Promissory estoppel operates only in those cases where
    the promise is to sign a written agreement which complies with the Statute of
    Frauds.”).
    25
    payment of $60,875.50, the agreed-upon purchase price” and that “CSL repeatedly
    offered and did make payment of the purchase price.” We have already held that
    ThyssenKrupp was also entitled to indemnity from CSL for the initial payment
    charged-back by Bass’s credit card company and that CSL’s offer of $60,875.50 in
    satisfaction of all of ThyssenKrupp’s claims after ThyssenKrupp filed this lawsuit
    was not a full and proper tender under the assumption agreement. These holdings
    defeat CSL’s and Greatland’s argument on their breach of contract claim and prior-
    breach defense.
    We overrule CSL’s and Greatland’s fifth issue.
    D.    Express negligence rule
    In their sixth issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on the express negligence rule because
    it is not an affirmative defense but, rather, a rule of contract construction. We have
    already addressed the applicability of express negligence rule to this case.
    We overrule CSL’s and Greatland’s sixth issue.
    E.    Comparative or proportionate responsibility
    In their seventh issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on their defense of proportionate
    responsibility because the chargeback was based on ThyssenKrupp’s negligence.
    ThyssenKrupp did not seek, and the trial court did not grant, a no-evidence
    26
    summary judgment on proportionate responsibility, which is not an independent
    cause of action but, rather, the law governing apportionment of liability in certain
    tort actions. See TEX. CIV. PRAC. & REM. CODE ANN. § 33.001–.003 (West 2008).
    We overrule CSL’s and Greatland’s seventh issue.
    F.    DTPA claims
    In their eighth issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on their DTPA claims. CSL’s and
    Greatland’s DTPA claims are all founded on ThyssenKrupp’s purported failure to
    deliver a functioning elevator to CSL upon payment of $60,875.50, pursuant to the
    assumption agreement. We have already held that CSL and Greatland were in
    breach of the assumption agreement because they failed to honor their indemnity
    obligations under the agreement and that CSL’s offer to pay ThyssenKrupp
    $60,875.50 “in complete satisfaction of the assumption of the subcontract
    agreement” during the course of this litigation was not a proper tender of CSL’s
    payment obligations under the agreement. The trial court therefore did not err in
    granting a no-evidence summary judgment on CSL’s and Greatland’s DTPA
    claims.
    We overrule CSL’s and Greatland’s eighth issue.
    27
    G.    Unreasonable collection efforts
    In their ninth issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on their unreasonable collection efforts
    claims. CSL and Greatland assert that ThyssenKrupp “exceeded the bounds of
    reason or moderation” by “burden[ing] the Sterling Center with an inoperable
    elevator until [ThyssenKrupp] received payment of the chargeback.” Specifically,
    CSL and Greatland assert that, in the event CSL failed to make payments due to
    ThyssenKrupp under the subcontract, ThyssenKrupp was contractually obligated to
    remove its elevator from the building. CSL and Greatland cite page ten of the
    elevator subcontract to support this contention. Page ten of the subcontract
    contains a “Title and ownership” clause. This clause provides that ThyssenKrupp
    retains title to all equipment supplied under the subcontractor until CSL fulfills all
    payment obligations, that “ThyssenKrupp may take immediate possession of the
    equipment and enter upon the premises where it is located (without legal process)
    and remove such equipment or portions thereof,” and that the parties agree that the
    equipment “can be removed without material injury to the real property.”
    By providing that ThyssenKrupp retains ownership over its equipment and
    may remove the equipment in the event of non-payment, the contract authorized
    ThyssenKrupp to remove and retain the equipment but did not require
    ThyssenKrupp to do so. Given its plain and common meaning, the term “may” is
    28
    generally permissive rather than mandatory. See Nalle v. Taco Bell Corp., 
    914 S.W.2d 685
    , 687 (Tex. App.—Austin 1996, writ denied) (“The word ‘may’ means
    possibility, permission, liberty, or power; it does not indicate a mandatory
    requirement.”) (citing BLACK’S LAW DICTIONARY 979 (6th ed. 1990)); see also
    McCarty v. Montgomery, 
    290 S.W.3d 525
    , 534 (Tex. App.—Eastland 2009, pet.
    denied) (holding that contract providing, “Buyer may terminate this contract,”
    “described [termination] permissively,” and did not limit buyer’s remedies to
    termination of contract). Construing the “Title and ownership” provision as giving
    ThyssenKrupp a right in the event of default by CSL, rather than imposing an
    additional obligation on ThyssenKrupp in the event of default by CSL, is
    consistent with the tenor of the provision and with the subcontract agreement as a
    whole. “We interpret a word in a contract according to its usual grammatical
    meaning unless it clearly appears that the parties intended otherwise.” 
    Nalle, 914 S.W.2d at 687
    (holding that lease provision stating that lessee “may” use leased
    premises for particular purpose did not obligate lessee to use premises for that
    purpose).
    Because the elevator subcontract did not require ThyssenKrupp to remove
    the elevator from Sterling Center upon CSL’s failure to make payments, and
    because CSL identifies no other basis for imposing a duty on ThyssenKrupp to
    remove the elevator, ThyssenKrupp’s failure to do so does not constitute an
    29
    unreasonable collection effort. See Montgomery Ward & Co. v. Brewer, 
    416 S.W.2d 837
    , 844 (Tex. Civ. App.—Waco 1967, writ ref’d n.r.e.) (describing
    conduct giving rise to common law tort for unreasonable collection efforts as
    “efforts that amount to a course of harassment that was willful, wanton, malicious,
    and intended to inflict mental anguish and bodily harm.”).
    We overrule CSL’s and Greatland’s ninth issue.
    H.    Trespass
    In their tenth issue, CSL and Greatland contend that the trial court erred in
    granting a no-evidence summary judgment on Greatland’s claim for trespass. Like
    its unreasonable collection efforts claim, Greatland’s claim for trespass is founded
    on ThyssenKrupp’s failure to remove the elevator from Sterling Center after CSL
    failed to make payment. We have already held that ThyssenKrupp was not
    obligated to remove the elevator from Greatland’s premises. The trial court
    therefore did not err in granting summary judgment on Greatland’s trespass claim.
    We overrule CSL’s and Greatland’s tenth issue.
    I.    Damages
    In their eleventh issue, CSL and Greatland contend that the trial court erred
    in granting a no-evidence summary judgment on the grounds that CSL and
    Greatland failed to present evidence of damages. Because we have affirmed the
    trial court’s summary judgment on each of CSL’s and Greatland’s claims on other
    30
    grounds, we need not address whether summary judgment was also proper on the
    ground that there was no evidence of damages. See 
    Joe, 145 S.W.3d at 157
    ; 
    West, 318 S.W.3d at 437
    .
    We overrule CSL’s and Greatland’s eleventh issue.
    Conclusion
    We hold that the trial court did not err in granting a traditional summary
    judgment in favor of ThyssenKrupp on its breach of contract claims against CSL.
    We further hold that the trial court did not err in granting a no-evidence summary
    judgment in favor of ThyssenKrupp on CSL’s and Greatland’s claims and
    affirmative defenses against it. Accordingly, we affirm the trial court’s judgment.
    All outstanding motions are dismissed as moot.
    Harvey Brown
    Justice
    Panel consists of Justices Keyes, Massengale, and Brown.
    31
    

Document Info

Docket Number: 01-11-00665-CV

Filed Date: 1/31/2013

Precedential Status: Precedential

Modified Date: 10/16/2015

Authorities (29)

Plasky v. Gulf Insurance Company , 160 Tex. 612 ( 1960 )

West v. SMG , 2010 Tex. App. LEXIS 4040 ( 2010 )

Joe v. Two Thirty Nine Joint Venture , 47 Tex. Sup. Ct. J. 1058 ( 2004 )

Montgomery Ward & Co. v. Brewer , 1967 Tex. App. LEXIS 2431 ( 1967 )

Imkie v. Methodist Hospital , 2010 Tex. App. LEXIS 7526 ( 2010 )

Dodson v. Kung , 1986 Tex. App. LEXIS 8179 ( 1986 )

Houston Exploration Co. v. Wellington Underwriting Agencies,... , 54 Tex. Sup. Ct. J. 1683 ( 2011 )

Tilotta v. Goodall , 1988 Tex. App. LEXIS 1055 ( 1988 )

City of Galveston v. Texas General Land Office , 2006 Tex. App. LEXIS 3140 ( 2006 )

Audubon Indemnity Co. v. Custom Site-Prep, Inc. , 358 S.W.3d 309 ( 2011 )

Wilson v. Shanti , 2011 Tex. App. LEXIS 116 ( 2011 )

Don's Building Supply, Inc. v. Onebeacon Insurance Co. , 51 Tex. Sup. Ct. J. 1367 ( 2008 )

Frost National Bank v. Fernandez , 53 Tex. Sup. Ct. J. 609 ( 2010 )

Valence Operating Co. v. Dorsett , 48 Tex. Sup. Ct. J. 671 ( 2005 )

Coastal Bank SSB v. Chase Bank of Texas, N.A. , 2004 Tex. App. LEXIS 1463 ( 2004 )

Rogers v. Ricane Enterprises, Inc. , 32 Tex. Sup. Ct. J. 458 ( 1989 )

Baucum v. Great American Insurance Co. of New York , 370 S.W.2d 863 ( 1963 )

C. F. Bean Corp. v. Rodriguez , 1979 Tex. App. LEXIS 3848 ( 1979 )

Schroeder v. Texas Iron Works, Inc. , 813 S.W.2d 483 ( 1991 )

LMB, LTD. v. Moreno , 49 Tex. Sup. Ct. J. 1019 ( 2006 )

View All Authorities »