Andrew Segal v. Norman Bock, Individually and as Independent of the Estate of Elizabeth H. Bock John Alan Bock and Patricia Sue Bock ( 2011 )


Menu:
  • Opinion issued December 15, 2011

      

    In The

    Court of Appeals

    For The

    First District of Texas

    ————————————

    NO. 01-10-00445-CV

    ———————————

    Andrew Segal, Appellant

    V.

    Norman Bock, Individually and as Independent Executor of the Estate of Elizabeth H. Bock, John Alan Bock and Patricia Sue Bock, Appellees

     

     

    On Appeal from the 80th District Court

    Harris County, Texas

    Trial Court Case No. 2008-45062

     

     

    MEMORANDUM OPINION

    Appellant, Andrew Segal, challenges the trial court’s rendition of summary judgment in favor of appellees, Norman Bock, individually and as independent executor of the estate of Elizabeth H. Bock, John Alan Bock, and Patricia Sue Bock, on the Bocks’ claim for breach of contract.  In two issues, Segal argues that the trial court erred in granting summary judgment in favor of the Bocks because (1) the breach of contract cause of action was not supported by the pleadings; (2) the trial court should have granted him a continuance to conduct discovery on the breach of contract claim; (3) the relevant settlement agreement was not a part of the summary judgment evidence; and (4) the settlement agreement could not dispose of all claims because the two cases concerning the incident had not been consolidated.

    We affirm.

    Background

    On January 26, 2008, an automobile accident occurred between Segal and the Bocks, with Norman Bock as the driver of the Bocks’ vehicle.

    Seeking to recover property damages arising from the accident, Segal retained David Castaneda as his attorney and filed a lawsuit in Harris County Civil Court at Law Number 1 against Norman Bock on July 21, 2008.  Unaware of this pending lawsuit, the Bocks filed a wrongful death lawsuit against Segal four days later in the 80th District Court in Harris County for the death of Elizabeth Bock, a passenger in the Bocks’ vehicle.

    Although Castaneda originally answered for Segal in the district court case, William Book was substituted as attorney for Segal in defense of the Bocks’ wrongful death claims on October 10, 2008.  At this point, Castaneda represented Segal for his affirmative property damage claims in the county court at law case, while Book represented him in defense of the Bocks’ claims in the district court case.

    On September 24, 2008, the Bocks filed with the district court a motion to consolidate the two suits, which was presented to the trial court as unopposed on October 10, 2008. Norman Bock subsequently filed a motion to consolidate the two cases with the county court at law on October 16, 2008.  The county court at law signed an order on October 21, 2008, indicating that it desired the two suits to be consolidated.  Thereafter, all parties proceeded in the case at the district court, and the trial court issued a docket control order.  The trial court did not formally sign an order consolidating the two cases until January 8, 2010.

    On March 30, 2009, the pleadings deadline set by the docket control order expired.  On April 1, 2009, Segal filed a cross-action against Norman Bock, alleging that Bock’s negligence was the cause or a contributing factor to the Bocks’ claimed damages. On April 17, 2009, the Bocks filed their second amended petition.

    On May 14, 2009, the parties conducted an initial round of mediation.  The parties were unable to reach a conclusion, but agreed to a second mediation on August 11, 2009.  At this mediation, neither Segal nor Castaneda was present, and Book alone was present to represent Segal.  A settlement agreement was executed, which purported to dispose of all claims concerning the accident, including Segal’s claims.

    On August 17, 2009, John Alan Bock and Patricia Sue Bock filed their third amended petition, which did not include Norman Bock.  On September 4, 2009, Segal filed his first amended petition and counterclaims, adding new causes of action for negligence and negligence per se against Norman Bock and slander claims against all of the Bocks.  The Bocks subsequently filed an “Emergency Motion to Enforce Settlement Agreement and Render Judgment” on September 21, 2009, purporting to assert a breach of contract action in this motion.  As an exhibit to this motion, the Bocks filed a copy of the settlement agreement. Then, while their motion to enforce was still pending, on September 25, 2009, the Bocks filed a motion to dismiss with prejudice all of their claims against Segal.  This motion was granted on October 6, 2009, dismissing all of the Bocks’ claims.

    A hearing was held on the motion to enforce on October 16, 2009, with a rehearing on November 13, 2009. Following this hearing, on November 17, 2009, the Bocks filed a supplement to their motion to enforce, again purporting to assert a breach of contract cause of action.

    On November 23, 2009, the Bocks filed a motion for summary judgment seeking summary judgment against Segal for breach of the settlement agreement.  They subsequently filed an amended motion for summary judgment on December 1, 2009, again seeking summary judgment for breach of the settlement agreement.  In both motions, the Bocks quoted from the previously filed settlement agreement and incorporated the agreement by reference. 

    In their motion, the Bocks argued that Segal breached the settlement agreement by filing his first amended petition and counterclaims as the settlement agreement was intended to dispose of all issues related to the accident.  In his response, Segal argued that the settlement agreement was invalid because Book did not have the authority to settle his claims.  He also argued that, because his claims were not part of the agreement, he did not breach the agreement by adding a new cause of action against the Bocks.

    A hearing on the amended motion was set for December 28, 2009, and there is some indication in the record that the hearing took place.  Nevertheless, the motion was not resolved, and a second hearing was set for March 2, 2010.  On December 28, 2009, the Bocks filed a “Supplement to Plaintiff’s Third Amended Original Petition”—this time including Norman Bock—and adding a breach of contract claim to their previously dismissed wrongful death and negligence claims. Then, on January 22, 2010, the Bocks filed a motion for leave to file their supplemental petition. 

    On March 2, 2010, the Court granted the Bocks leave to file their supplemental petition.  On the same date, Patricia Sue Bock and John Alan Bock filed a “Second Amended Original Answer of Counter-Defendant Patricia Sue Bock and First Amended answer of John Bock and Special Exceptions of Patricia Bock and John Bock.” 

    On March 4, 2010, the trial court signed an order granting and rendering final summary judgment on all causes of action in this suit in favor of the Bocks.  The judgment did not award the Bocks any damages in the suit but did award attorneys’ fees.

    Standard of Review

    The summary-judgment movant must conclusively establish its right to judgment as a matter of law.  See MMP, Ltd. v. Jones, 710 S.W.2d 59, 60 (Tex. 1986).  Because summary judgment is a question of law, we review a trial court’s summary judgment decision de novo.  Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding, 289 S.W.3d 844, 848 (Tex. 2009).

    To prevail on a “traditional” summary-judgment motion, asserted under Rule 166a(c), a movant must prove that there is no genuine issue regarding any material fact and that it is entitled to judgment as a matter of law.  See Tex. R. Civ. P. 166a(c); Little v. Tex. Dep’t of Criminal Justice, 148 S.W.3d 374, 381 (Tex. 2004).  A matter is conclusively established if reasonable people could not differ as to the conclusion to be drawn from the evidence.  See City of Keller v. Wilson, 168 S.W.3d 802, 816 (Tex. 2005).

    When a party moves for summary judgment on a claim for which it bears the burden of proof, it must show that it is entitled to prevail on each element of its cause of action.  See Parker v. Dodge, 98 S.W.3d 297, 299 (Tex. App.—Houston [1st Dist.] 2003, no pet.). The party meets this burden if it produces evidence that would be sufficient to support an instructed verdict at trial.  Id. 

    Pleading Breach of Contract

    In part of his first issue, Segal contends that the trial court erred in granting summary judgment in favor of the Bocks on their breach of contract claim on the basis that the cause of action was not supported by the pleadings.

    Prior to filing their motion for summary judgment, the Bocks filed a motion to dismiss with prejudice all of their claims against Segal.  The trial court granted this motion on October 6, 2009.  The Bocks filed a motion for summary judgment on November 23, 2009, and their amended motion for summary judgment on December 1, 2009.  On December 28, 2009, the Bocks filed a “Supplement to Plaintiff’s Third Amended Petition,” which asserted a claim of breach of contract against Segal.  The Bocks filed a motion for leave to file the supplemental petition on January 22, 2010. The trial court granted leave on March 2, 2010, during the second hearing on the amended motion for summary judgment.  On March 4, 2010, the trial court signed an order granting summary judgment in favor of the Bocks on all grounds.

    Segal argues that because the trial court had dismissed all of the Bocks’ causes of action prior to their motion for summary judgment, there were no pleadings on file for them to supplement when they filed their supplemental petition, rendering it null and void.  We note that the dismissal order signed by the trial court did not dispose of the entire case, but only those claims that the Bocks had asserted against Segal at the time. Thus, while the Bocks had no live claims remaining, the case was still pending.  Segal provides no authority for the proposition that, once a party dismisses all of its claims from a suit that remains pending, it is prevented from asserting any new claims while the suit is still being prosecuted.

    Assuming without deciding that a petition cannot be supplemented when all the previous claims have been dismissed in an interlocutory order, the trial court had the ability to treat the supplemental petition as a pleading asserting a new cause of action against the Bocks, either in an original or amended petition.  See Tex. R. Civ. P. 71 (stating that when a party has mistakenly designated any pleading, the court shall treat it as if it had been properly designated). Regardless of how the post-dismissal petition should be characterized, we hold the Bocks’ pleading properly asserted a breach of contract cause of action.

    Segal also contends that the Bocks’ failure to obtain leave to file for the supplemental petition until the March 2, 2010 hearing renders the pleading improper for purposes of summary judgment.  A party may amend its pleadings after it files a motion for summary judgment until seven days before trial.  Tex. R. Civ. P. 63.  A summary judgment proceeding is a trial within the meaning of Rule 63.  Goswami v. Metro. Sav. & Loan Ass’n, 751 S.W.2d 487, 490 (Tex. 1988).  The key date for purposes of Rule 63 is the date of the final hearing from which the summary judgment sprang.  Cantu v. Holiday Inns, Inc., 910 S.W.2d 113, 115 (Tex. App.—Corpus Christi 1995, writ denied) (citing Rose v. Kober Fin. Corp., 874 S.W.2d 358, 361 (Tex. App.—Houston [14th Dist.] 1994, no writ)).

    The Bocks filed their supplemental petition on December 28, 2009.   This is the date on which the summary judgment hearing was originally scheduled to occur, but the motion was not resolved at this time and another summary judgment hearing was set for March 2, 2010.  Accordingly, the March 2, 2010 hearing is the relevant hearing date for purposes of Rule 63.  See Cantu, 910 S.W.2d at 115; Tex. R. Civ. P. 63.  It follows that the Bocks’ supplemental petition was filed well outside the seven-day deadline and did not require leave of court for filing.[1] 

    Moreover, even assuming leave was required, the trial court gave leave on March 2, 2010.  This was sufficient.  See Tex. R. Civ. P. 166a(c) (providing pleadings amended after summary judgment hearing can be considered with permission of court if filed before judgment is rendered).  We hold the Bocks’ “Supplement to Plaintiff’s Third Amended Petition,” which contained a cause of action of breach of contract against Segal, was properly before the court at the time summary judgment was granted.

    Continuance

    In the remainder of Segal’s first issue, Segal argues the trial court abused its discretion by not allowing him a continuance when it allowed the Bocks to amend their pleadings to include a breach of contract claim.

    In response to the Bocks’ amended motion for summary judgment, Segal argued he should be allowed a continuance to conduct discovery on their newly pleaded claim.    The trial court did not rule on the request, however. To preserve error on a motion for continuance, the movant must obtain the trial court’s ruling on the motion.  Direkly v. ARA Devcon, Inc., 866 S.W.2d 652, 656 (Tex.App.—Houston [1st Dist.] 1993, writ dism’d w.o.j.).  As there is no ruling in the record on his request for continuance, the issue has not been properly preserved for review.

    We overrule Segal’s first issue.

    Summary Judgment Evidence

    In the first part of his second issue, Segal argues that the trial court erred in granting summary judgment in favor of the Bocks on the basis that the Bocks’ summary judgment evidence is factually insufficient.  Segal argues that by failing to properly attach and authenticate the settlement agreement as evidence for their summary judgment motion, the Bocks failed to prove the first element of a breach of contract action, making the evidence factually insufficient.

    The Bocks attached the settlement agreement to their motion to enforce.  In their motion for summary judgment, the Bocks quoted provisions from the settlement agreement and stated specifically that they were incorporating it by reference.  The agreement was signed and on file with the court.  Failure to attach summary judgment evidence to the motion must be raised and ruled on by the trial court before a party can complain about it on appeal. Cluett v. Med. Protective Co., 829 S.W.2d 822, 825 (Tex. App.—Dallas 1992, writ denied).  Segal did not object.  Accordingly, any error has been waived.  Id. 

    Segal suggests that the Bocks’ failure to attach the settlement agreement to their motion for summary judgment was a substantive defect that requires reversal.  To support this contention, he relies on Sorrels v. Giberson, 780 S.W.2d 936 (Tex. App.—Austin 1989, writ denied).  This reliance is misplaced.  In Sorrels, the lender of a promissory note moved for summary judgment against the borrower, but did not attach the note to either the summary judgment motion or any other properly filed instrument in the record.  Id. at 937.  The court held that, because the note was completely absent from the record, it could not serve as a basis for summary judgment and that the borrower’s failure to object was irrelevant to the issue of sufficiency of summary judgment evidence.  Id. at 937–38.  The complete lack of evidence in Sorrels was the substantive defect, however, not the failure to physically attach it to the motion.

    Segal also contends that the settlement agreement, even if properly included, was not properly authenticated at the time it was filed with the motion to enforce.  Defects in the authentication of attachments in support of a summary judgment motion, however, are waived without a proper objection.  Watts v. Hermann Hosp., 962 S.W.2d 102, 105 (Tex.App.—Houston [1st Dist.] 1997, no pet.).  To complain on appeal, appellants are required not only to object but to obtain a ruling from the trial court on his objections.  Id.  As he neither objected to the authentication of the document at the trial level nor secured a ruling on such an objection, Segal has waived any complaints concerning the authenticity of the document.

    Consolidation of Causes

    In the second portion of his second issue, Segal argues that summary judgment should not have been granted because, at the time of the hearing, the county court at law and district court cases had not been consolidated.  Segal contends that the settlement agreement could only have dismissed the Bocks’ claims against him as the county court at law cause, which contained his causes of action, was still separate from the district court cause at the time the agreement was signed.

    Assuming without deciding that the two causes had not been effectively consolidated at the time of the summary judgment hearing, Segal has not explained why the consolidation or continued separation of the causes impacts the effect of the settlement agreement. A settlement agreement can govern more than one case.  See Gallagher Headquarters Ranch Dev., Ltd. v. City of San Antonio, 303 S.W.3d 700, 701–02 (Tex. 2010) (determining whether the provisions of a settlement agreement applied to two or three separate cases).  The settlement agreement here states in multiple sections that the agreement disposes of “all claims and causes of action of any kind whatsoever which the parties have of may have arising out of the transaction or occurrence which is the subject of this litigation.”  The language is unambiguous in settling all claims related to the accident, and the consolidation or non-consolidation of the cases at this time is, therefore, irrelevant.

    We overrule Appellant’s second issue.


     

    Conclusion

    We affirm the judgment of the trial court.

     

                                                                       Laura Carter Higley

                                                                       Justice

     

    Panel consists of Justices Keyes, Higley, and Massengale.

     



    [1]           Segal also argues that the “Second Amended Original Answer of Counter-Defendant Patricia Sue Bock and First Amended answer of John Bock and Special Exceptions of Patricia Bock and John Bock,” which also contained a claim of breach of contract and which was not filed until March 2, 2010 was not timely filed.  Because we have determined that the Bocks’ “Supplement to Plaintiff’s Third Amended Petition” was timely filed, we do not need to address this argument. See Tex. R. App. P. 47.1 (requiring appellate courts to issue opinions addressing every issue raised that is necessary to final disposition).