Javier Solis and Maria Solis D/B/A J. Solis Maintenance and Welding Service v. City of Laredo ( 2011 )


Menu:
  •                                              OPINION
    No. 04-10-00751-CV
    Javier SOLIS and Maria Solis d/b/a J. Solis Maintenance and Welding Service,
    Appellants
    v.
    CITY OF LAREDO,
    Appellee
    From the 49th Judicial District Court, Webb County, Texas
    Trial Court No. 2009CVF001270-D1
    Honorable Jose A. López, Judge Presiding
    Opinion by:       Catherine Stone, Chief Justice
    Sitting:          Catherine Stone, Chief Justice
    Phylis J. Speedlin, Justice
    Marialyn Barnard, Justice
    Delivered and Filed: September 21, 2011
    AFFIRMED
    This appeal of an order granting a plea to the jurisdiction arises from a lawsuit alleging
    breach of contract and intentional tort claims against the City of Laredo. Javier Solis and Maria
    Solis d/b/a J. Solis Maintenance and Welding Service appeal the trial court’s order granting the
    City of Laredo’s plea to the jurisdiction, contending the trial court erred in concluding that the
    City retained its sovereign immunity because: (1) the City sued Solis for payment under a bid
    04-10-00751-CV
    bond; and (2) the parties had entered into a contract thereby waiving the City’s immunity from
    suit. We affirm the trial court’s order.
    BACKGROUND 1
    Solis submitted a bid to the City for a public works project. In his submission of the bid,
    Solis included a bid bond in the amount of 5% of Solis’s bid. The bid bond listed Solis as
    principal and Acstar Insurance Company as surety. The bid bond was designed to ensure that
    Solis would promptly enter into a contract for the performance of the work if the City accepted
    Solis’s bid.
    In April of 2006, the City accepted Solis’s bid in the amount of $1,644,759.00, but by
    letter dated May 1, 2006, Solis forfeited the project and declined to enter into the contract due to
    difficulty in obtaining the necessary bonds. On May 15, 2006, the City rescinded the award of
    the contract to Solis for failure to enter into the contract. Shortly thereafter, the City sent formal
    demand for payment on the bid bond in the amount of $80,396.95. In December of 2006, the
    City sued Solis and Acstar in cause number 2006CVF002054-D4 seeking payment on the bond.
    Although Solis initially filed counter-claims against the City for fraud, negligent
    misrepresentation, breach of good faith and fair dealing, and breach of contract, Solis later
    dropped his counter-claims against the City.
    In July of 2009, Solis filed a separate lawsuit against the City in the underlying cause
    (number 2009CVF001270-D1), asserting claims for breach of contract, common law fraud, fraud
    by nondisclosure, and breach of fiduciary duty. After a hearing, the trial court granted the City’s
    plea to the jurisdiction. Solis appeals.
    1
    The factual recitations included in this section are based, in part, on the trial court’s findings of fact.
    -2-
    04-10-00751-CV
    STANDARD OF REVIEW
    A trial court’s ruling on a plea to the jurisdiction is reviewed de novo. City of Waco v.
    Lopez, 
    259 S.W.3d 147
    , 150 (Tex. 2008). In reviewing the ruling, an appellate court must
    determine whether facts have been alleged that affirmatively demonstrate jurisdiction in the trial
    court. 
    Id. The court
    must also consider evidence tending to negate the existence of jurisdictional
    facts when necessary to resolve the jurisdictional issues raised. 
    Id. The court
    construes the
    pleadings liberally in favor of the plaintiff, and a fact question regarding jurisdiction precludes a
    trial court from granting a plea to the jurisdiction. 
    Id. WAIVER OF
    IMMUNITY UNDER REATA
    In his first issue, Solis asserts that the City is not immune from his intentional tort claims
    because the City waived its immunity by asserting an affirmative claim for relief against Solis in
    the prior lawsuit. In support of his assertion, Solis cites Reata Const. Corp. v. City of Dallas,
    
    197 S.W.3d 371
    (Tex. 2006). The City responds that the waiver found in Reata is inapplicable
    because the City did not seek any affirmative relief in the underlying cause. The City argues that
    its prior lawsuit involving the bid bond was a separate lawsuit, and the affirmative claims filed in
    the prior lawsuit have no effect on the City’s immunity in the underlying cause.
    In Reata, the City of Dallas issued a temporary license for the installation of fiber optic
    cable to Dynamic Cable Construction 
    Corporation. 197 S.W.3d at 373
    . Dynamic subcontracted
    with Reata Construction Corporation to perform the drilling for the project.             
    Id. Reata inadvertently
    drilled into a water main, flooding a nearby building. 
    Id. The building
    owner sued
    Dynamic and Reata for negligence. 
    Id. Reata filed
    a third-party claim against the City, alleging
    that the City negligently misidentified the water main’s location. 
    Id. The City
    intervened in the
    case, ultimately asserting negligence claims against Dynamic and Reata. 
    Id. The City
    also filed
    -3-
    04-10-00751-CV
    a plea to the jurisdiction asserting governmental immunity from suit. 
    Id. The trial
    court denied
    the City’s plea, and the court of appeals reversed, holding that the City’s intervention did not
    result in a waiver of immunity. 
    Id. at 374.
    The Texas Supreme Court noted that courts generally defer to the Legislature to waive
    immunity. 
    Id. at 375.
    This deference is based on the position that the absence of immunity may
    “hamper governmental functions requiring tax resources to be used for defending lawsuits and
    paying judgments rather than using those resources for their intended purposes.” 
    Id. The court
    also noted, however, that if a governmental entity “interjects itself into or chooses to engage in
    litigation to assert affirmative claims for monetary damages, the entity will presumably have
    made a decision to expend resources to pay litigation costs.” 
    Id. “If the
    opposing party’s claims
    can operate only as an offset to reduce the government’s recovery, no tax resources will be called
    upon to pay a judgment, and the fiscal planning of the governmental entity should not be
    disrupted.” 
    Id. Accordingly, the
    court held once a governmental entity asserts affirmative
    claims for monetary recovery, the entity must participate in the litigation process as an ordinary
    litigant; provided, however, that: (1) the claims against the governmental entity must be germane
    to, connected with, and properly defensive to those asserted by the governmental entity; and (2)
    the governmental entity continues to have immunity from affirmative damage claims against it
    for monetary relief exceeding amounts necessary to offset the governmental entity’s claims. 
    Id. at 377.
    Under those circumstances, the trial court does not acquire jurisdiction over a claim for
    damages against the governmental entity in excess of the damages recovered by the
    governmental entity, if any. 
    Id. One of
    the key requirements to a waiver under the holding in Reata is that the damages
    sought against the governmental entity are limited to an offset against the entity’s recovery.
    -4-
    04-10-00751-CV
    Because the damages must be offset, it necessarily follows that both the claims by the
    governmental entity and the claims against it must be filed in the same cause. Requiring both
    claims to be asserted in the same cause allows the governmental entity to continue to evaluate
    whether pursuing the affirmative claims in a particular case is worthwhile given the distraction
    and expense of litigation.          See 
    id. at 382-83
    (Brister, J., concurring) (noting “when the
    government brings its own affirmative claims, it has obviously concluded that the distraction and
    expense of litigation is worthwhile in that particular case.”) Thus, the waiver of immunity is
    limited to “that particular case” in which the governmental entity decides to assert affirmative
    claims. See 
    id. In this
    case, the City never had any pending affirmative claims; therefore, Solis’s claim
    for damages could not be in the nature of an offset, which is the only type of claim for which
    immunity is waived under Reata. Although the City asserted affirmative claims in the prior case,
    its waiver of immunity was limited to “that particular case” in which it asserted affirmative
    claims. See 
    Reata, 197 S.W.3d at 382-83
    (Brister, J., concurring). Accordingly, the City’s
    immunity was not waived based on Reata. 2
    WAIVER UNDER 271.152
    If a local governmental entity enters into an authorized contract, it waives sovereign
    immunity from suit for the purpose of adjudicating a claim for breach of contract. TEX. LOC.
    GOV’T CODE ANN. § 271.152 (West 2005). The term “contract” as used in section 271.152 is
    defined as “a written contract stating the essential terms of the agreement for providing goods or
    services to the local governmental entity that is properly executed on behalf of the local
    2
    We note that Solis relied on the holding in Reata as his only basis for arguing immunity was waived with regard to
    his intentional tort claims. We further note that the Texas Tort Claims Act does not waive sovereign immunity for
    intentional torts. City of San Antonio v. Polanco & Co., L.L.C., No. 04-07-00258-CV, 
    2007 WL 3171360
    (Tex.
    App.—San Antonio Oct. 31, 2007, pet. denied) (mem. op.).
    -5-
    04-10-00751-CV
    governmental entity.” 
    Id. at §
    271.151(2). Solis asserts the trial court erred in finding the parties
    did not enter into a contract, asserting the Notice of Award, which was signed by both parties,
    was a valid written contract. The City counters that although it accepted Solis’s bid in the Notice
    of Award, Solis forfeited the project before a contract was executed.
    In order for immunity to be waived under section 271.152, “the entity must in fact have
    entered into a contract.” City of Houston v. Williams, No. 09-0770, 
    2011 WL 923980
    , at *4
    (Tex. Mar. 18, 2011). “Section 271.151(2) effectively states five elements a contract must meet
    in order for it to be a contract subject to section 271.152’s waiver of immunity: (1) the contract
    must be in writing, (2) state the essential terms of the agreement, (3) provide for goods or
    services, (4) to the local governmental entity, and (5) be executed on behalf of the local
    governmental entity.”     
    Id. “‘[A] court
    may determine, as a matter of law, that multiple
    documents comprise a written contract.’” 
    Id. at *6
    (quoting Fort Worth Indep. Sch. Dist. v. City
    of Fort Worth, 
    22 S.W.3d 831
    , 840 (Tex. 2000)). Stated differently, a written contract may be
    embodied in multiple documents. 
    Id. at *8.
    In this case, the parties disagree as to whether the Notice of Award sent to Solis by the
    City constitutes a contract when coupled with Solis’s bid proposal. The fact that parties to an
    informal agreement contemplate a formal writing does not necessarily prevent the formation of a
    binding contract. See Scott v. Ingle Bros. Pac., Inc., 
    489 S.W.2d 554
    , 556 (Tex. 1972); WTG
    Gas Processing, L.P. v. ConocoPhillips Co., 
    309 S.W.3d 635
    , 645 (Tex. App.—Houston [14th
    Dist.] 2010, pet. denied). Whether the parties intended to make a binding agreement is the
    determinative issue. Foreca, S.A. v. GRD Dev Co., 
    758 S.W.2d 744
    , 746 (Tex. 1988); Medistar
    Corp. v. Schmidt, 
    267 S.W.3d 150
    , 157-58 (Tex. App.—San Antonio 2008, pet. denied).
    Although the parties’ intent to be bound is often a question of fact, the court may decide, as a
    -6-
    04-10-00751-CV
    matter of law, that there existed no immediate intent to be bound. Foreca, 
    S.A., 758 S.W.2d at 746
    ; WTG Gas Processing, 
    L.P., 309 S.W.3d at 643
    ; Medistar 
    Corp., 267 S.W.3d at 158
    .
    In this case, the bid proposal form contemplated a formal signed agreement. The bid
    proposal form stated, “The undersigned BIDDER proposes and agrees, if this BID is accepted, to
    enter into an agreement with OWNER in the form included in the Contract Documents.”
    Moreover the Notice of Award notifies Solis that his bid “[h]as been favorable [sic] considered
    for the project by the City Council.” However, the Notice of Award requires Solis to sign the
    proposed Contract and return it with the required proof of insurance and bonds within ten days
    “for the approval and signature of the City Manager.” Moreover, the Notice of Award states that
    for purposes of an effective date for the bonds and insurance, “the date of April 3, 2006 may be
    considered the date of the Contract, if the Documents are approved by the City Manager.”
    Finally, the Notice of Award states, “If you fail to submit the proposed Contract and the
    Performance and Payment Bonds and the Certificates of Insurance within ten (10) days from
    your receipt of this Notice, your bid will be considered withdrawn and your bid bond will be
    forfeited.” Solis subsequently sent written notice forfeiting his right to proceed with the project
    without ever signing and returning the Contract. Accordingly, the language within the Notice of
    Award conclusively establishes that the City had no intent to be bound until the Contract was
    executed. Because the Contract was never executed by the City, the City’s immunity was never
    waived under section 271.152.
    -7-
    04-10-00751-CV
    CONCLUSION
    The City asserted no claims for affirmative relief in the underlying lawsuit, and the
    record established that no contract was entered into by the City and Solis. Accordingly, the City
    retained its immunity. The trial court’s order is affirmed.
    Catherine Stone, Chief Justice
    -8-