the City of San Antonio v. KGME Inc. ( 2011 )


Menu:
  •                                              OPINION
    No. 04-10-00263-CV
    CITY OF SAN ANTONIO,
    Appellant
    v.
    KGME, INC.,
    Appellee
    From the 57th Judicial District Court, Bexar County, Texas
    Trial Court No. 2008-CI-06449
    Honorable Peter Sakai, Judge Presiding
    Opinion by:       Sandee Bryan Marion, Justice
    Sitting:          Catherine Stone, Chief Justice
    Sandee Bryan Marion, Justice
    Steven C. Hilbig, Justice
    Delivered and Filed: March 30, 2011
    AFFIRMED
    In an opinion and judgment dated February 16, 2011, we affirmed the trial court’s order
    denying the City of San Antonio’s plea to the jurisdiction in a suit filed by appellee, KGME, Inc.
    The City of San Antonio (“the City”), the defendant below and appellant here, filed a motion for
    rehearing. We deny the motion, withdraw our opinion and judgment of February 16, 2011, and
    issue this opinion and judgment in its place.
    04-10-00263-CV
    BACKGROUND
    In May 2004, the City contracted with KGME for construction of a drainage ditch with
    hydromulched vegetation. In February 2006, the parties determined KGME could not complete
    the project as called for in the contract. Thereafter, the City ordered cessation of work on the
    project and withheld the portion of the contract retainage due to KGME upon completion and
    acceptance of performance.
    KGME brought two causes of action against the City: a claim for breach of contract and a
    claim for violation of the Texas Prompt Payment Act (“PPA”). 1                        KGME alleged the City
    breached the parties’ contract by failing to: (1) pay for work performed on the project; (2) pay
    for additional work completed pursuant to City-ordered changes in the scope of the project; (3)
    pay for additional costs incurred due to City-caused delays; and (4) approve change orders
    necessary for KGME to complete performance. For its breach of contract claim, KGME sought
    all damages allowed under Texas Local Government Code section 271.153, as well as all
    damages available at common law. 2 For its PPA claim, KGME requested attorneys’ fees and
    interest accruing on the unpaid contract retainage.
    1
    The parties argue on appeal that KGME is pursuing two separate causes of action against the City for breach of
    contract: a common law claim and a Texas Local Government Code section 271.152 claim. However, section
    271.152 expressly waives sovereign immunity from suit for breach of contract, thereby permitting KGME to bring
    its common law breach of contract claim. TEX. LOC. GOV’T. CODE ANN. § 271.152 (West 2005) (“A local
    governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a
    contract subject to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for
    breach of the contract, subject to the terms and conditions of this subchapter.”). Common law breach of contract
    and section 271.152 are not distinct claims; section 271.152 is merely the vehicle by which KGME brings its
    common law breach of contract claim.
    2
    It is unclear whether KGME made a claim for attorneys’ fees under section 271.153(a)(3). Regardless, section
    271.153 was only recently amended in 2009 to permit recovery for reasonable and necessary attorneys’ fees. Act of
    May 31, 2009, 81st Leg., R.S., ch. 1266, § 8, 2009 Tex. Gen. Laws 4006, 4007. The attorneys’ fees provision is not
    retroactive—it applies only to contracts executed after the amendment’s effective date: June 19, 2009. Harris
    County Flood Control Dist. v. Great Am. Ins. Co., 
    309 S.W.3d 614
    , 618 (Tex. App.—Houston [14th Dist.] 2010,
    pet. dism’d). Because the parties in this case executed their contract in 2004, KGME cannot recover attorneys’ fees
    under section 271.153.
    -2-
    04-10-00263-CV
    On October 1, 2009, the City countersued for breach of contract, alleging KGME failed
    to fully perform its obligations under the parties’ contract. The City later filed a plea to the
    jurisdiction based on its sovereign immunity from suit. The trial court denied the City’s plea to
    the jurisdiction, and the City filed this accelerated appeal.
    STANDARD OF REVIEW
    A plea to the jurisdiction is a dilatory plea by which a party challenges the court’s
    authority to determine the subject matter of the cause of action. Bland Indep. Sch. Dist. v. Blue,
    
    34 S.W.3d 547
    , 554 (Tex. 2000). We review de novo the trial court’s ruling on a plea to the
    jurisdiction. Tex. Dep’t of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 226 (Tex. 2004).
    A plea to the jurisdiction can make two types of challenges: a challenge to the existence
    of jurisdictional facts or a challenge to the sufficiency of the pleadings. 
    Id. at 226–27.
    When a
    plea to the jurisdiction challenges the existence of jurisdictional facts, the trial court must
    consider relevant evidence submitted by the parties to resolve the jurisdictional issues raised. 
    Id. at 227.
    If this consideration requires examination of evidence, the trial court has discretion to
    decide whether the jurisdictional determination should be made in a preliminary hearing or after
    more development of the case. 
    Id. If the
    evidence raises a fact question regarding jurisdiction,
    the trial court must deny the plea to the jurisdiction and leave resolution of the question to the
    fact finder. 
    Id. at 227–28.
    In contrast, if the evidence is undisputed or fails to raise a fact
    question regarding jurisdiction, the trial court must rule on the plea to the jurisdiction as a matter
    of law. 
    Id. at 228.
    When a plea to the jurisdiction challenges the sufficiency of the pleadings, we determine
    if the plaintiff has met its burden by pleading facts affirmatively demonstrating the trial court’s
    -3-
    04-10-00263-CV
    subject matter jurisdiction. 
    Id. at 226.
    We construe the pleadings liberally in favor of the
    plaintiff and look to the plaintiff’s intent. 
    Id. Here, the
    City’s plea to the jurisdiction challenges both the existence of jurisdictional
    facts and the sufficiency of KGME’s pleadings. We discuss each separately.
    EXISTENCE OF JURISDICTIONAL FACTS
    The City argues the evidence establishes it did not breach the parties’ contract because it
    had no contractual obligation to make the requested change orders. The City also argues it was
    not the cause of KGME’s failure to perform because KGME neglected its duty to inspect the
    premises before making its bid. The City contends there is no balance due and owing to KGME
    under the contract because, by no fault of the City, KGME failed to complete performance,
    which is a prerequisite for payment under the contract.
    In contrast, KGME argues it did not breach the contract because it encountered “newly
    discovered” conditions at the work site that precluded its performance. According to KGME, the
    contract required the City to make change orders to accommodate KGME’s performance should
    the parties discover any such conditions after performance began. KGME contends the City’s
    failure to issue the change orders breached the contract and directly caused KGME’s failure to
    perform; therefore, according to KGME, the City is estopped from asserting KGME’s failure to
    complete performance as justification for its refusal to pay the balance of the contract retainage.
    We believe the evidence raises fact issues as to which party, if any, breached the contract
    and whether there is a balance due and owing to KGME. The parties invite us to review the
    evidence and resolve these fact issues in their respective favors, but resolution of disputed
    jurisdictional facts implicating the merits of a claim or defense is a matter reserved for the fact
    finder. 
    Miranda, 133 S.W.3d at 227
    –28. Therefore, because the evidence raises fact questions
    -4-
    04-10-00263-CV
    regarding jurisdiction, the trial court properly denied the City’s plea to the jurisdiction on this
    ground. See 
    id. SUFFICIENCY OF
    THE PLEADINGS
    The City’s plea to the jurisdiction also challenges the sufficiency of KGME’s pleadings
    on two grounds. First, the City argues the trial court has no jurisdiction to award KGME
    common law breach of contract damages beyond those expressly permitted by the Local
    Government Code. Second, the City argues the trial court has no jurisdiction to hear KGME’s
    claim for violation of the PPA. We discuss each argument separately.
    KGME’s Breach of Contract Claim
    Texas Local Government Code section 271.152 expressly waives sovereign immunity
    from suit for breach of contract. TEX. LOC. GOV’T CODE ANN. § 271.152 (West 2005) (“A local
    governmental entity that is authorized by statute or the constitution to enter into a contract and
    that enters into a contract subject to this subchapter waives sovereign immunity to suit for the
    purpose of adjudicating a claim for breach of the contract . . . .”). Section 271.153 limits the
    types of damages recoverable for a breach of contract claim brought under section 271.152 as
    follows:
    (a) The total amount of money awarded in an adjudication brought against
    a local governmental entity for breach of a contract subject to this subchapter is
    limited to the following:
    (1) the balance due and owing by the local governmental entity
    under the contract as it may have been amended, including any amount
    owed as compensation for the increased cost to perform the work as a
    direct result of owner-caused delays or acceleration;
    (2) the amount owed for change orders or additional work the
    contractor is directed to perform by a local governmental entity in
    connection with the contract;
    (3) reasonable and necessary attorney’s fees that are equitable and
    just; and
    (4) interest as allowed by law.
    -5-
    04-10-00263-CV
    (b) Damages awarded in an adjudication brought against a local
    governmental entity arising under a contract subject to this subchapter may not
    include:
    (1) consequential damages, except as expressly allowed under
    Subsection (a)(1);
    (2) exemplary damages; or
    (3) damages for unabsorbed home office overhead.
    
    Id. § 271.153.
    “The provisions [of sections 271.152 and 271.153] waiving immunity and limiting
    damages ‘apply to a claim that arises under a contract executed before the effective date of
    [sections 271.152 and 271.153] only if sovereign immunity has not been waived with respect to
    the claim before’ . . . September 1, 2005.” Tooke v. City of Mexia, 
    197 S.W.3d 325
    , 344–45
    (Tex. 2006). Here, the parties formed the construction contract in May 2004, prior to the
    effective date of sections 271.152 and 271.153. Because the City did not waive its sovereign
    immunity before September 1, 2005, KGME is entitled to sue under section 271.152. See 
    id. KGME now
    seeks all damages permitted under section 271.153 for unpaid sums due and owing
    for work performed on the project, payment for increased costs of performance resulting from
    City-caused delays, and payment for change orders and additional work the City ordered KGME
    to perform.
    In addition, KGME requests common law damages, including actual, consequential,
    incidental, and compensatory damages, as well as pre- and post-judgment interest, costs of court,
    litigation expenses, and reasonable and necessary attorneys’ fees. 3 Some of these common law
    3
    KGME’s Second Amended Petition requests attorneys’ fees as an element of common law damages, but the
    general rule in Texas is attorneys’ fees are available only if expressly permitted by contract or by statute. Tony
    Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    , 310 (Tex. 2006). The parties’ contract does not provide for
    attorneys’ fees; therefore, KGME relies on the PPA as its statutory authority for recovering attorneys’ fees in this
    case. Alternatively, KGME requested attorneys’ fees under Texas Civil Practice and Remedies Code section
    38.001. However, section 38.001 provides for recovery of attorneys’ fees only for claims brought against
    individuals and corporations, not governmental entities. Therefore, KGME is not entitled to recover attorneys’ fees
    under section 38.001.
    -6-
    04-10-00263-CV
    damages cannot be recovered under section 271.153. For this reason, the City contends the trial
    court does not have jurisdiction to award KGME common law damages for its breach of contract
    claim beyond those expressly permitted by section 271.153. However, citing Reata Construction
    Corp. v. City of Dallas, KGME argues that by countersuing, the City waived sovereign immunity
    from all common law breach of contract damages, regardless of the limitations imposed by
    section 271.153. In Reata, the Supreme Court held that when a governmental entity asserts its
    own affirmative claims for monetary relief, sovereign immunity does not bar adverse parties
    from asserting, “as an offset, claims germane to, connected with, and properly defensive to those
    asserted by the governmental entity.”      
    197 S.W.3d 371
    , 376–77 (Tex. 2006).           The Court
    reasoned:
    [I]f the governmental entity interjects itself into or chooses to engage in litigation
    to assert affirmative claims for monetary damages, the entity will presumably
    have made a decision to expend resources to pay litigation costs. If the opposing
    party’s claims can operate only as an offset to reduce the government’s recovery,
    no tax resources will be called upon to pay a judgment, and the fiscal planning of
    the governmental entity should not be disrupted. Therefore, a determination that a
    governmental entity’s immunity from suit does not extend to a situation where the
    entity has filed suit is consistent with the policy issues involved with immunity.
    In this situation, we believe it would be fundamentally unfair to allow a
    governmental entity to assert affirmative claims against a party while claiming it
    had immunity as to the party’s claims against it.
    
    Id. at 375–76.
    Applying Reata, we must decide if KGME’s claims for common law breach of contract
    damages are sufficiently related to the City’s counterclaim.        “In common usage, the term
    ‘germane’ means ‘closely akin,’ ‘being at once relevant and appropriate,’ ‘closely or
    significantly related,’ ‘relevant,’ and ‘pertinent.’” Sweeny Cmty. Hosp. v. Mendez, 
    226 S.W.3d 584
    , 592 (Tex. App.—Houston [1st Dist.] 2007, no pet.) (quoting City of Dallas v. Redbird Dev.
    Co., 
    143 S.W.3d 375
    , 381 (Tex. App.—Dallas 2004, no pet.)); Merriam-Webster’s Collegiate
    -7-
    04-10-00263-CV
    Dictionary 525 (11th ed. 2003); Random House Webster’s Unabridged Dictionary 800 (2d ed.
    2001)). “In common usage, the term ‘connected’ means ‘united, joined or linked’ and ‘joined
    together in sequence; linked coherently’ and ‘having parts or elements logically linked
    together.’” 
    Id. (quoting Merriam-Webster’s
    Collegiate Dictionary 525 (11th ed. 2003); Random
    House Webster’s Unabridged Dictionary 800 (2d ed. 2001)).
    Here, KGME’s claims and the City’s counterclaim arise from the same facts and
    controversy. Both parties request damages stemming from the other’s purported breach of the
    same contract, and both claims rely on the trial court’s resolution of similar disputed facts.
    Therefore, we hold KGME’s claims for common law breach of contract damages are germane to,
    connected with, and properly defensive to the City’s counterclaim for common law breach of
    contract.
    KGME contends Reata permits it to seek, in addition to those damages expressly
    permitted by section 271.153, common law breach of contract damages up to the amount of the
    City’s countersuit. We agree. Section 271.153 limits the extent of the statutory waiver created
    by section 271.152. However, when the City counterclaimed against KGME, it affirmatively
    waived any remaining sovereign immunity from suit for “germane” claims up to the amount of
    its counterclaim. Thus, by countersuing KGME for breach of contract, the City opened itself up
    to KGME’s claims for common law breach of contract damages otherwise barred by section
    271.153. KGME’s recovery for these claims will be limited to the recovery awarded to the City
    on its counterclaim.
    Because we conclude the common law breach of contract damages KGME requests are
    “germane to, connected with, and properly defensive to” the City’s counterclaim for breach of
    -8-
    04-10-00263-CV
    contract, we hold the trial court has jurisdiction to hear KGME’s claims for common law breach
    of contract damages.
    KGME’s PPA Claim
    The PPA provides that if a governmental entity does not make timely payments under a
    contract with a vendor of goods or services, the vendor may suspend performance and recover
    interest accruing on any undisputed late payments. TEX. GOV’T CODE ANN. §§ 2251.025,
    2251.051 (West 2008). In addition, the PPA provides: “In a formal administrative or judicial
    action to collect an invoice payment or interest due under this chapter, the opposing party, which
    may be the governmental entity or the vendor, shall pay the reasonable attorney fees of the
    prevailing party.” 
    Id. § 2251.043.
    However, the existence of a bona fide dispute regarding
    whether an amount is due and owing under a contract precludes operation of the interest
    provision of the PPA. 
    Id. § 2251.002(1);
    Port Neches-Groves Indep. Sch. Dist. v. Pyramid
    Constructors, L.L.P., 
    281 S.W.3d 142
    , 150 (Tex. App.—Beaumont 2009, pet. denied).
    The plaintiff has the burden of pleading facts affirmatively demonstrating the court’s
    subject matter jurisdiction for a claim against a governmental entity. McMahon Contracting,
    L.P. v. City of Carrollton, 
    277 S.W.3d 458
    , 464 (Tex. App.—Dallas 2009, pet. denied). The
    State waives its immunity from liability by voluntarily entering into contracts and binding itself
    to contractual terms. 
    Id. However, even
    if the State waives its immunity from liability by
    contracting with private parties, immunity from suit is not waived except by legislative mandate.
    
    Id. “It is
    settled in Texas that for the Legislature to waive the State’s sovereign immunity, a
    statute or resolution must contain a clear and unambiguous expression of the Legislature’s
    waiver of immunity.” Wichita Falls State Hosp. v. Taylor, 
    106 S.W.3d 692
    , 696 (Tex. 2003);
    see also TEX. GOV’T CODE ANN. § 311.034 (West 2005).
    -9-
    04-10-00263-CV
    At least three of our sister courts have held that although the PPA waives sovereign
    immunity from liability for attorneys’ fees and accrued interest on undisputed late payments, it
    does not contain “clear and unambiguous” language expressly waiving sovereign immunity from
    suit.   Great Am. Ins. 
    Co., 309 S.W.3d at 618
    ; 
    McMahon, 277 S.W.3d at 465
    ; Pyramid
    
    Constructors, 281 S.W.3d at 147
    . We, too, must conclude the PPA does not waive sovereign
    immunity from suit for attorneys’ fees and interest. In this case, therefore, the City initially
    retained sovereign immunity from suit for KGME’s claim for violations of the PPA. However,
    because of the City’s counterclaim, our analysis does not end here.
    Pursuant to the rule in Reata, the City may have waived its sovereign immunity from
    KGME’s PPA claim by countersuing. The question for us to resolve is whether KGME’s PPA
    claim is “germane to, connected with, and properly defensive to” the City’s counterclaim. We
    conclude it is. As previously discussed, KGME’s claims and the City’s counterclaim arise from
    the same facts and controversy. Both KGME’s PPA claim and the City’s counterclaim allege
    breach of the parties’ contract and require resolution of the same facts. Thus, KGME’s PPA
    claim is germane to, connected with, and properly defensive to the City’s counterclaim. We hold
    the City, by countersuing KGME for breach of contract, waived its sovereign immunity from suit
    for KGME’s PPA claim up to the recovery awarded to the City on its counterclaim.
    As for the City’s contention that a bona fide dispute exists regarding the unpaid retainage,
    thereby precluding operation of the interest provision of the PPA, we note the parties dispute
    whether a bona fide dispute exists in this case. According to the City, there is no balance due
    and owing because KGME never completed performance, which was a prerequisite to payment
    under the contract. KGME contends the City intentionally thwarted performance by failing to
    issue certain change orders to the contract that would have permitted KGME to perform. KGME
    - 10 -
    04-10-00263-CV
    claims the City’s refusal to issue the change orders precludes it from now claiming a bona fide
    dispute regarding the amount due and owing. Because the fact finder has not yet had an
    opportunity to determine what amount, if any, is due and owing under the parties’ contract, we
    decline to decide whether a bona fide dispute exists so that the parties may resolve the issue
    before the trial court.
    Accordingly, we hold the trial court has jurisdiction to hear KGME’s PPA claim for
    attorneys’ fees and interest up to the amount of the City’s counterclaim.
    CONCLUSION
    For these reasons, we overrule all issues on appeal and affirm the trial court’s denial of
    the City’s plea to the jurisdiction.
    Sandee Bryan Marion, Justice
    - 11 -