Vassar Group, Inc. v. Heeseon Ko ( 2019 )


Menu:
  • REVERSE and REMAND; and Opinion Filed August 9, 2019.
    In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-18-00814-CV
    VASSAR GROUP, INC., Appellant
    V.
    HEESEON KO, Appellee
    On Appeal from the 14th Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-17-02575
    MEMORANDUM OPINION
    Before Justices Schenck, Osborne, and Reichek
    Opinion by Justice Schenck
    Vassar Group, Inc. d/b/a Dawn Energy Consulting (“DEC”) appeals the trial court’s order
    granting summary judgment in favor of Heeseon Ko (“Ko”) on her breach of contract claim in a
    dispute over commission payments. DEC urges the trial court erred in granting summary judgment
    in favor of Ko, and in impliedly denying its own counter motion for summary judgment, on Ko’s
    breach of contract claim. More particularly, DEC claims Ko failed to prove her entitlement to
    commissions and DEC conclusively established it has no obligation to pay Ko post termination of
    her employment. We conclude, as a matter of law, neither party proved its position as it relates to
    Ko’s breach of contract claim. Thus, the trial court erred in granting summary judgment in favor
    of Ko. We reverse the trial court’s judgment granting Ko summary judgment on her breach of
    contract claim and remand the cause to the trial court for further proceedings consistent with this
    opinion. Because all issues are settled in law, we issue this memorandum opinion. TEX. R. APP.
    P. 47.4.
    BACKGROUND
    DEC sells long-term energy contracts and subsequently receives monthly recurring
    revenue from its customers over the life of the contracts. On June 1, 2015, DEC hired Ko as an
    administrative assistant and she entered into a Confidentiality, Nondisclosure, and Invention
    Agreement (“NDA”) with DEC. In addition to confidentiality and nondisclosure obligations, the
    NDA addresses compensation. The compensation provision provides Ko, as “Contractor,” would
    be paid a salary and commissions. More particularly, the NDA states:
    Contractor and DEC agree that DEC shall pay Contractor: an annual salary of
    $50,000.00 payable semi-monthly on the first (lst) day and the fifteenth (15th) day
    of the month and subject to applicable federal, state, and local withholding. Upon
    termination of this Contract, payments under this paragraph shall cease;
    provided, however, that Contractor shall be entitled to payments for periods
    or partial periods that occurred prior to the date of termination and for which
    Contractor has not yet been paid, and for any commission earned in
    accordance with DEC’s customary procedures, if applicable. This section of the
    Contract is included only for accounting and payroll purposes and should not be
    construed as establishing a minimum or definite term of employment. In addition,
    DEC will make commission payments to Contractor based on the following: 30%
    of NEW closed deals or 10% of RENEWAL closed deals of DEC by Claele Smith
    capped at $35,000.00 for the period June 1, 2015 - May 31 , 2016 and capped at
    $50,000.00 for the period June I, 2016 - May 31, 201 7. 70% of ALL closed deals
    of Contractor will be paid, which shall be calculated separately from the
    commission paid on DEC deals and shall not have a yearly cap. This commission
    will be paid in accordance with the existing payment terms agreed upon by DEC
    and suppliers. If Contractor dies during the term of this Contract, Contractor's
    beneficiary shall be entitled to payments and commission payments for the period
    ending with the date of Contractor’s death.
    (emphasis added).
    In early 2017, Claele Smith (“Smith”), DEC’s President, provided Ko with a revised
    version of the NDA (“Proposed Agreement”). The Proposed Agreement contained terms Ko was
    not willing to agree to, including a compensation package that was less favorable than the prior
    one, and what Ko considered to be onerous termination terms. Ko expressed concerns to DEC
    –2–
    over the Proposed Agreement. The parties reached an impasse on the form of the new agreement
    and, on February 15, 2017, Ko emailed Smith stating “[s]ince you’ve given me no choice but to
    either sign the new agreement . . . or you would terminate me, I will consider myself to be
    terminated effective immediately.” Ko demanded payment of commissions she claimed were
    owed.
    When it became apparent DEC was not going to make any further payments, Ko sued DEC
    asserting claims for breach of contract, quantum meruit, and unjust enrichment. DEC responded
    with a general denial and counterclaimed alleging breach of contract, misappropriation of trade
    secrets, and unlawful access of DEC’s computer network and system under Chapter 33 of the
    Texas Penal Code and section 143.002 of the Texas Civil Practice & Remedies Code. DEC later
    nonsuited its counterclaims. DEC filed a motion for traditional summary judgment on Ko’s breach
    of contract, quantum meruit, and unjust enrichment claims. Ko filed her own motion for summary
    judgment on her breach of contract claim only.
    In its motion for summary judgment, DEC argued it was entitled to summary judgment on
    Ko’s breach of contract claim claiming the evidence showed it did not breach the agreement
    because, under the express language of the NDA and DEC’s customary procedures, Ko is not
    entitled to commissions after termination of her employment. In support of its motion, and
    response to Ko’s motion, DEC attached Ko’s original petition; the NDA; Ko and Smith’s email
    correspondence concerning the Proposed Agreement; the transcript of Smith’s deposition; the
    transcript of Smith’s then boyfriend, Nick Parker’s, deposition; and Smith’s affidavit in which she
    states the basic facts of the case, describing Ko as an entry-level employee who sold only one
    contract before she resigned in 2017, and for which Ko had already been compensated.
    In her motion for summary judgment, and in response to DEC’s motion, Ko raised three
    grounds for summary judgment in her favor and in defense of DEC’s motion: (1) the parties never
    –3–
    terminated the NDA, meaning Ko was still entitled to receive the payments specified therein; (2)
    even if the NDA terminated upon the termination of her employment, the NDA provides that Ko
    is still entitled to commissions owed for “periods or partial periods that occurred prior to the date
    of termination and for which Ko has not yet been paid;” and (3) Ko is entitled to commissions
    under DEC’s customary procedure of paying commissions to terminated contractors.1 In support
    of her motion, and her response to DEC’s motion, Ko attached the NDA; the Proposed Agreement;
    excerpts from Smith’s deposition, in which she acknowledges that DEC was often paid months
    after a deal closed; excerpts from the deposition of Parker, explaining he, Eduard Cheney, and
    Sebastian Esquivel ran some deals through DEC; email correspondence between Ko and Smith;
    and Ko’s affidavit in which she gives further background information, specifically stating DEC
    never notified her the NDA was terminated, indicating that payments from energy providers would
    not be received for months after DEC performed work for the provider, meaning commissions
    would be paid many months after work was actually performed, and citing DEC’s “unwritten
    policy” of paying employees (Parker, Cheney, and Esquivel) commissions after termination.
    Additionally, in support of her claim DEC’s customary procedure was to pay commissions post
    termination, Ko attached NDAs of former DEC contractors, and excerpts from the deposition of
    Parker.
    The trial court granted summary judgment in favor of Ko on the liability portion of her
    breach of contract claim. The trial court granted summary judgment in favor of DEC on Ko’s
    quantum meruit and unjust enrichment claims. Thereafter, the parties, by Rule 11 agreement,
    stipulated to the amount of damages. Following a bench trial on attorney’s fees, the trial court
    1
    DEC challenges each of these grounds on appeal.
    –4–
    entered a final judgment awarding Ko actual damages of $12,679.30, trial-court attorney’s fees of
    $74,322.00, and conditional appellate attorney’s fees. This appeal followed.
    DISCUSSION
    In its first issue, DEC challenges the trial court’s grant of summary judgment in favor of
    Ko and denial of DEC’s motion for summary judgment as to Ko’s breach of contract claim.
    We review the granting of a summary judgment de novo. Learners Outline, Inc. v. Dallas
    Indep. Sch. Dist., 
    333 S.W.3d 636
    , 640 (Tex. App.—Dallas 2009, no pet.). The standard of review
    for a traditional summary judgment motion pursuant to Texas Rule of Civil Procedure 166a(c) is
    threefold: (1) the movant must show there is no genuine issue of material fact and he is entitled to
    judgment as a matter of law; (2) in deciding whether there is a disputed, material fact issue
    precluding summary judgment, we must take as true evidence favorable to the nonmovant; and (3)
    we must indulge every reasonable inference from the evidence in favor of the non-movant and
    resolve any doubts in the nonmovant’s favor. 
    Id. When, as
    here, both parties move for summary judgment, each party bears the burden of
    establishing that it is entitled to judgment as a matter of law; neither party can prevail because of
    the other’s failure to discharge its burden. City of Garland v. Dallas Morning News, 
    969 S.W.2d 548
    , 552 (Tex. App.—Dallas 1998) (en banc), aff’d, 
    22 S.W.3d 351
    (Tex. 2000). A reviewing
    court may determine all questions presented; it may affirm the summary judgment entered, reverse
    and render a judgment for the other party, if appropriate, or reverse and remand if neither party
    has met its summary judgment burden. Hackberry Creek Country Club, Inc. v. Hackberry Creek
    Home Owners Ass’n, 
    205 S.W.3d 46
    , 50 (Tex. App.—Dallas 2006, pet. denied).
    In granting summary judgment in favor of Ko, the trial court did not specify the basis for
    its ruling. Consequently, DEC, as the challenger of the trial court’s order, must show that each of
    the independent grounds alleged in Ko’s motion is insufficient to support the order. See McMahon
    –5–
    Contracting, L.P. v. City of Carrollton, 
    277 S.W.3d 458
    , 468 (Tex. App.—Dallas 2009, pet.
    denied). In order to obtain reversal of the trial court’s denial of its motion for summary judgment,
    DEC must establish there is no genuine issue of material fact and it is entitled to judgment as a
    matter of law. See Ohio Cas. Ins. Co. v. Time Warner Entm’t Co., 
    244 S.W.3d 885
    , 887–88 (Tex.
    App.—Dallas 2008, pet. denied).
    DEC argues the trial court erred in granting Ko’s motion for summary judgment and in
    denying its motion because Ko failed to prove her entitlement to commissions, the NDA mandated
    that payment of commissions ended at termination except for commissions already earned, which
    DEC claims it paid, and DEC’s customary procedure was not to pay commissions to contractors
    after termination of their employment. These arguments challenge each of the grounds Ko asserted
    for summary judgment and touch upon the arguments DEC made in support of its motion for
    summary judgment on Ko’s breach of contract claim.
    Ko’s breach of contract claim focuses on the NDA and its application to the facts presented
    in this case. To prove a claim for breach of contract, a party must establish: (1) the existence of a
    valid contract; (2) performance or tendered performance by the plaintiff; (3) breach of the contract
    by the defendant; and (4) damages sustained by the plaintiff as a result of the breach. McGraw v.
    Brown Realty Co., 
    195 S.W.3d 271
    , 276 (Tex. App.—Dallas 2006, no pet.). A breach of contract
    occurs when a party fails to perform an act that it has promised to perform. Hackberry 
    Creek, 205 S.W.3d at 55
    .
    In construing a written contract, we must ascertain and give effect to the parties’ intentions
    as expressed in the instrument. Stephens v. Beard, 
    485 S.W.3d 914
    , 916 (Tex. 2016). To do so,
    we consider the instrument as a whole. 
    Id. We presume
    that the words of a contract reflect the
    parties’ intent, but we must construe words in the context in which they are used. URI, Inc. v.
    Kleberg Cty., 
    543 S.W.3d 755
    , 764 (Tex. 2018).
    –6–
    If, after the pertinent rules of construction are applied, the contract can be given a definite
    or certain legal meaning, it is unambiguous and courts should construe it as a matter of law. Frost
    Nat’l Bank v. L & F Distribs., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005) (per curiam). If a contract
    is susceptible to more than one reasonable interpretation, it is ambiguous. Reilly v. Rangers Mgmt.,
    Inc., 
    727 S.W.2d 527
    , 530 (Tex. 1987). Whether a contract is ambiguous is a question of law for
    the court to decide by looking at the contract as a whole in light of the circumstances existing at
    the time the contract was entered into. 
    Id. at 529.
    A court may conclude a contract is ambiguous
    even in the absence of such a pleading by either party. Sage St. Assocs. v. Northdale Constr. Co.,
    
    863 S.W.2d 438
    , 445 (Tex. 1993). When a contract contains an ambiguity, granting summary
    judgment based on the contract is improper because the intent of the contracting parties is an issue
    of fact. Coker v. Coker, 
    650 S.W.2d 391
    , 394 (Tex. 1983).
    I.     Termination of the NDA
    DEC maintains the trial court erred in granting Ko summary judgment and in denying its
    motion for summary judgment on her breach of contract claim because the summary judgment
    evidence negates the existence of an agreement that could be the subject of a breach of contract
    claim. More particularly, DEC contends that when Ko’s employment was terminated the NDA’s
    compensation provision terminated as well. Thus, asserts DEC, the agreement upon which Ko
    relies does not exist. Ko responds claiming the NDA was not terminated simply because her
    employment terminated, so the cessation of payments terms in the compensation provision did not
    take effect. Ko also contends DEC is estopped from claiming the NDA terminated because it
    sought to enforce the NDA’s nondisclosure provisions after her employment terminated.
    We recognize DEC filed a counterclaim seeking to enforce the confidentiality obligations
    under the NDA. To consider DEC’s attempt to enforce the nondisclosure obligations under the
    NDA to be a judicial admission the agreement remains in full force and effect it must be a clear,
    –7–
    deliberate, and unequivocal statement to that effect. Horizon/CMS Healthcare Corp. v. Auld, 
    34 S.W.3d 887
    , 905 (Tex. 2000). We conclude that by asserting a counterclaim for an alleged
    violation of the NDA, DEC made no clear and unequivocal assertion that the payment obligations
    set forth in the NDA continued. See, e.g., Bliss & Glennon, Inc. v. Ashley, 
    420 S.W.3d 379
    , 393
    (Tex. App.—Houston [1st Dist.] 2014, no pet.) (“It is the nature of an admission that by intention
    it be act of waiver, and not merely a statement of assertion or concession, made for some
    independent purpose”). Consequently, we turn to the NDA to determine whether it establishes, as
    a matter of law, the agreement either remained in effect or terminated upon the termination of Ko’s
    employment.
    The NDA does not contain any provision for how and when any part of the agreement
    would terminate. The compensation provision states “this section of the Contract is included only
    for accounting and payroll purposes and should not be construed as establishing a minimum or
    definite term of employment.” Consequently, the NDA itself does not answer the question
    presented here and would require extrinsic evidence of the parties’ intent. In such a case, an
    ambiguity exists, raising a fact issue for jurors to resolve. See Fless v. State Farm Lloyds, 
    202 S.W.3d 744
    , 748 (Tex. 2006).
    Consequently, there is a genuine issue of material fact as to whether termination of Ko’s
    employment terminated any part of the NDA. Thus, a fact issue remains as to what effect Ko’s
    termination has on her right to receive the compensation specified in the NDA. See Fulcrum Cent.
    v. Auto Tester, Inc., 
    102 S.W.3d 274
    , 278 (Tex. App.—Dallas 2003, no pet.).
    II.    Earned Commissions
    DEC further challenges the trial court’s grant of summary judgment in favor of Ko, and
    denial of its motion for summary judgment, on Ko’s breach of contract claim based on Ko’s
    –8–
    assertion that, even if the NDA terminated upon the termination of her employment, the NDA
    provided for payment post termination.
    As to post termination of the agreement, the NDA provides: “Upon termination of this
    Contract, payments under this paragraph shall cease; provided, however, that Contractor shall be
    entitled to payments for periods or partial periods that occurred prior to the date of termination and
    for which Contractor has not yet been paid, and for any commission “earned” in accordance with
    DEC’s customary procedures, if applicable.” The parties have differing theories as to when a
    commission is “earned” and payable post termination.
    DEC’s theory is that a commission is earned when DEC receives payment from the client,
    not when the client enters into an agreement requiring it to make future payments. In support of
    this theory, DEC relies on portions of Smith’s deposition in which she maintains that DEC’s
    independent contractors receive their commissions when DEC receives payments from its
    customers and that commissions are not earned at the closing of the deals. Thus, DEC urges it
    only owed Ko commissions from customer payments received before Ko’s employment
    terminated.   DEC claims that while DEC may receive payments post termination of Ko’s
    employment from deals Ko worked on, those are not payments that Ko “earned” prior to the
    termination of her employment.
    In contrast, Ko’s theory is that a commission is earned once she or Smith closed a deal and
    that the timing of the payment was just a function of when DEC received payment from the
    provider. Ko established through her affidavit that DEC would receive recurring payment from a
    single sale resulting in a revenue stream from which commissions would be paid months after the
    work was actually contracted for and performed. She further established that DEC was still
    receiving client payments from deals Ko helped Smith close prior to the termination of her
    –9–
    employment and that she had not been paid her commission on those payments. Ko contends she
    is entitled to commissions on those payments DEC received after her employment terminated.
    The term “earned” is not defined in the NDA and the parties have presented plausible and
    conflicting evidence on the meaning of the term. Accordingly, the contract is susceptible to at
    least two reasonable interpretations. Consequently, the contract is ambiguous, creating a fact issue
    on the parties’ intent. See United Protective Servs. Inc. v. W. Vill. Ltd. P’ship, 
    180 S.W.3d 430
    ,
    432 (Tex. App.—Dallas 2005, no pet.) (holding that genuine issue of material fact as to parties’
    intent regarding requirement for notice to terminate contracts precluded entry of summary
    judgment); 
    Coker, 650 S.W.2d at 393
    (“When a contract contains an ambiguity, the granting of a
    motion for summary judgment is improper because the interpretation of the instrument becomes a
    fact issue”). Accordingly, neither party has established their entitlement to summary judgment on
    the cessation of payment terms of the compensation provision.
    III.   DEC’s Customary Procedure for Post-Termination Payments
    DEC further claims the trial court erred in granting summary judgment in favor of Ko, and
    in denying its motion, on Ko’s breach of contract claim because its customary procedure was not
    to pay former contractors after their employment terminated.
    With respect to DEC’S “customary procedure,” Ko presented evidence that three
    individuals, namely Parker, Cheney, and Esquivel, signed NDAs with DEC, containing
    compensation provisions, and received commission payments post termination. DEC countered
    with Smith’s testimony denying that the three contractors were operating under DEC’s customary
    procedures. She claimed Parker was starting his own company and, while he was in the process
    of doing so, asked Smith to let him, and his sales persons—Cheney and Esquivel—run deals
    through DEC’s accounting system. Smith claimed DEC paid Parker the funds from any deals that
    he or his employees closed, and Parker distributed the money to Cheney and Esquivel based on
    –10–
    agreements he had with them. DEC argues that commission payments to Parker, Cheney, and
    Esquivel, post termination of their contracts with DEC, are the result of Parker’s agreement with
    his contractors and do not reflect DEC’s customary procedures. DEC further established through
    Smith’s testimony that another administrative employee, similar to Ko, who received flat-fee
    bonuses of ten to fifteen dollars for every deal that Smith closed, received no further payment after
    his employment terminated.
    While Smith essentially denies a direct relationship between DEC and Parker, Cheney, and
    Esquivel, seeking to negate a customary procedure, the summary judgment record includes NDAs
    between DEC and Parker, Cheney, and Esquivel, and there is evidence they received payments
    post termination. The fact that one administrative employee, who was receiving flat-fee bonuses,
    not commissions, did not receive payment post termination does not conclusively establish a
    “customary” procedure with respect to commissions payable to Ko. Consequently, based on the
    record before us, there is at least a fact issue concerning DEC’s customary procedure concerning
    commission payments. Accordingly, neither Ko nor DEC conclusively established their right to
    summary judgment by virtue of the company’s customary procedures. See Hightower v. Baylor
    Univ. Med. Ctr., 
    251 S.W.3d 218
    , 221–22 (Tex. App.—Dallas 2008, pet. struck).
    Given we have determined the summary evidence presents a genuine issue of material fact
    for determination by the trier of fact, we conclude the trial court erred in granting Ko’s motion for
    summary judgment and did not err in denying DEC’s motion for summary judgment on Ko’s
    breach of contract claim. We sustain DEC’s first issue as to summary judgment in favor of Ko on
    her breach of contract claim. We overrule DEC’s second issue as to the denial of its motion for
    summary judgment on Ko’s breach of contract claim.
    –11–
    Because summary judgment in favor of Ko was improper, it was likewise improper to
    award her attorney’s fees. To recover attorney’s fees a party must prevail on its cause of action.
    Sharifi v. Steen Auto., L.L.C., 
    370 S.W.3d 126
    , 152 (Tex. App.—Dallas 2012, no pet.).
    CONCLUSION
    We reverse the trial court’s judgment granting summary judgment in favor of Ko and
    remand the cause to the trial court for further proceedings consistent with this opinion.
    /David J. Schenck/
    DAVID J. SCHENCK
    JUSTICE
    180814F.P05
    –12–
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    VASSAR GROUP, INC., Appellant                      On Appeal from the 14th Judicial District
    Court, Dallas County, Texas
    No. 05-18-00814-CV         V.                      Trial Court Cause No. DC-17-02575.
    Opinion delivered by Justice Schenck.
    HEESEON KO, Appellee                               Justices Osborne and Reichek participating.
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    REVERSED and this cause is REMANDED to the trial court for further proceedings consistent
    with this opinion.
    It is ORDERED that appellant VASSAR GROUP, INC. recover its costs of this appeal
    from appellee HEESEON KO.
    Judgment entered this 9th day of August, 2019.
    –13–