Scott Van Dyke v. Builders West, Inc. , 565 S.W.3d 336 ( 2018 )


Menu:
  • Affirmed and Opinion filed August 14, 2018.
    In The
    Fourteenth Court of Appeals
    NO. 14-16-00686-CV
    SCOTT VAN DYKE, Appellant
    V.
    BUILDERS WEST, INC., Appellee
    On Appeal from the 113th District Court
    Harris County, Texas
    Trial Court Cause No. 2011-54019
    OPINION
    Scott Van Dyke appeals from a final judgment favoring Builders West, Inc.
    Builders West sued Van Dyke for breach of contract, among other causes of action,
    for nonpayment on a home renovation project. Van Dyke counter-sued, alleging
    Builders West overcharged him and performed faulty work. A jury found for
    Builders West on all claims, and the trial court rendered judgment in accordance
    with the verdict, awarding actual damages of $321,368.12. The trial court
    determined that reasonable fees for Builders West’s attorneys amounted to $590,750
    and awarded that sum to Builders West as well.
    In his appeal, Van Dyke contends that (1) the evidence was legally and
    factually insufficient to sustain the jury’s finding that he breached the contract
    because Builders West failed to offer expert testimony that it performed certain
    electrical work in a good and workmanlike manner, (2) the trial court erred in
    refusing to instruct the jury regarding Builders West’s contractual duty to supervise
    the work of subcontractors, and (3) the trial court erred in awarding attorneys’ fees
    to Builders West at a rate of $500 per hour when Builders West’s contract with its
    attorneys required it to pay only $350 per hour unless it was awarded fees at the
    higher rate by the trial court. In a contingent cross-appeal, Builders West asserts that
    the trial court erred in refusing to award any fees for work performed by attorneys
    from a particular firm that represented Builders West.
    Because Van Dyke’s first two issues fail to address portions of the jury charge
    that support the judgment, we overrule those issues. In addition, we conclude that
    the trial court did not err in awarding attorneys’ fees to Builders West at the rate of
    $500 per hour because the relevant statute does not limit Builders West’s recovery
    to fees actually incurred. We therefore overrule Van Dyke’s third issue and need not
    address Builders West’s contingent cross-appeal. We affirm the trial court’s
    judgment.
    BACKGROUND
    In 2008, Van Dyke hired Builders West as general contractor on an extensive
    home renovation project. The parties’ one-page contract stated that Builders West
    would be paid for “labor and materials plus Contractor’s Fee of 20% to cover
    overhead, supervision, and profit.” The contract did not specify the scope of the work
    to be done or a total price to be paid but instead simply set forth hourly rates for
    2
    various subcontractors.
    The project was to be completed in three phases. After several months of
    work, Van Dyke requested an estimate for completion of the first two phases, which
    Builders West provided. Eight months later, Van Dyke refused to pay invoices for
    work performed in August through November 2009. The unpaid invoices totaled
    $335,340.65. Van Dyke particularly complained regarding the amount charged for
    work done by electrical subcontractor Facilities Electric, Inc. (“FEI”).
    After negotiations proved fruitless, Builders West left the job and ultimately
    filed suit against Van Dyke for nonpayment of the invoices. Builders West’s causes
    of action included breach of contract, substantial performance, and quantum meruit.
    Van Dyke counter-sued, alleging breach of contract, violations of the Deceptive
    Trade Practices Act, and breaches of express and implied warranties.
    Key points of contention at trial concerned the nature of the “supervision”
    component of the contract and the sufficiency of Builders West’s performance of
    that component. Kurt Lobpries, a co-owner of Builders West, testified that he
    considered five percent of the amount paid under the contract to be for supervision.
    Day-to-day onsite supervision was actually provided by a carpenter on the job who
    was paid directly by Van Dyke and not by Builders West. There was evidence,
    however, that Lobpries acted as project manager, scheduling and coordinating the
    subcontractors’ work, occasionally making onsite inspections, and communicating
    with the onsite supervisor.
    Another significant dispute at trial concerned the quality of the electrical work
    performed by subcontractor FEI. Van Dyke called an expert witness to testify
    specifically regarding perceived deficiencies in the electrical work. Builders West
    defended the electrical work through several witnesses but did not call its own expert
    witness to testify on this subject.
    3
    At the conclusion of trial, the trial court submitted a 22-question charge to the
    jury that contained each of the causes of action listed above, along with various
    subsidiary issues. Because our disposition of Van Dyke’s first two issues turns on
    the structure of the charge, we explain that structure in some detail.
    Builders West’s claim for breach of contract was submitted in questions 1, 2,
    3, and 6. Question 1 asked whether Van Dyke failed to comply with the parties’ one-
    page agreement. Question 2 was contingent on a “yes” answer to question 1 and
    inquired whether Van Dyke’s failure to comply was excused by a prior failure to
    comply by Builders West. Question 3 asked whether the estimate Builders West
    provided regarding completion of phases 1 and 2 effectively modified the parties’
    agreement. And question 6 was the damages submission for Builders West’s breach
    of contract claim.
    Van Dyke’s claim for breach of contract was submitted in questions 4, 5, and
    9. Question 4 asked whether Builders West failed to comply with the agreement. An
    instruction under question 4 informed the jury that Builders West was required to
    perform its obligations under the agreement “in a good and workmanlike manner.”
    As will be discussed in more detail below, it is important to note that question 2—
    asking whether Van Dyke’s failure to comply was excused by Builders West’s prior
    noncompliance—did not contain a similar instruction. Additionally, Van Dyke
    objected to question 4—but not question 2—on the ground that it failed to instruct
    the jury regarding Builders West’s contractual duty to supervise the work of
    subcontractors. The trial court overruled the objection. Van Dyke did not object to
    question 2 on this ground. Question 5 was contingent on a “yes” answer to question
    4 and asked whether Builders West’s failure to comply was excused by various
    theories, including waiver, ratification, and acceptance of benefits. Question 9 was
    the damages submission for Van Dyke’s breach of contract claim.
    4
    Builders West’s claim of substantial performance was submitted in questions
    7 (“Did Builders West, Inc. substantially perform the Agreement?”) and 8
    (damages). Its claim of quantum meruit was submitted in questions 10 (“Did
    Builders West, Inc. perform compensable work for Scott Van Dyke for which it was
    not compensated?”) and 11 (damages). Van Dyke’s other claims (DTPA violations
    and breaches of warranties) were also submitted but play no role in this appeal.
    The jury found for Builders West on all claims, found against Van Dyke on
    his claims and defenses, and found damages to be $321,368.12 as to each of Builders
    West’s claims for breach of contract, substantial performance, and quantum meruit.
    The trial court subsequently awarded this amount to Builders West as actual
    damages in the judgment.
    Builders West’s entitlement to attorneys’ fees was tried to the court by
    agreement. During the litigation, Builders West was represented by lawyers from
    two different law firms: Rusty Hardin & Associates (“RHA”), with which Builders
    West had a direct contractual relationship, and Langley & Banack, which was paid
    by Builders West’s insurer. In this phase of the trial, Van Dyke did not contest the
    reasonableness of the fees requested for RHA’s services. Instead, Van Dyke argued
    that such fees were not necessarily incurred at a rate of $500 per hour because
    Builders West’s contract with RHA only obligated Builders West to pay at the rate
    of $350 per hour unless the trial court awarded fees at the higher rate. The trial court
    awarded Builders West fees for the services of RHA calculated at the rate of $500
    per hour but did not award any fees for services performed by Langley & Banack.
    ANALYSIS
    I.    Van Dyke’s sufficiency challenge fails because the relevant parts of the
    charge did not require good and workmanlike performance.
    In his first issue, Van Dyke purports to challenge the legal and factual
    5
    sufficiency of the evidence to support Builders West’s recovery on its claim for
    breach of contract. We conclude that Van Dyke’s challenge fails for three reasons.
    First, although Van Dyke contends insufficient evidence was presented of good and
    workmanlike performance, the jury charge regarding this claim did not require that
    evidence. Second, even if Builders West failed to prove its claim for breach of
    contract, Van Dyke failed to challenge in his original brief two other jury findings
    that support the judgment. And third, in any event, Van Dyke’s argument does not
    undermine those other findings because the charge likewise did not require evidence
    of good and workmanlike performance to make those findings.
    A.       The charge questions regarding Builders West’s claim for breach
    of contract did not require good and workmanlike performance.
    According to Van Dyke, Builders West could not prevail on its claim that Van
    Dyke breached the contract by nonpayment because Builders West did not establish
    through expert testimony that its electrical subcontractor, FEI, performed in a good
    and workmanlike manner. Van Dyke points out that a party to a contract generally
    is not permitted to recover for breach unless the party can establish that it tendered
    performance of its own obligations under the contract or was excused from doing
    so. See, e.g., Petroleum Workers Union of the Republic of Mex. v. Gomez, 
    503 S.W.3d 9
    , 39 (Tex. App.—Houston [14th Dist.] 2016, no pet.) (listing elements of
    cause of action for breach of contract). He further notes that home construction
    contracts typically are read to include an implied warranty that all work will be
    completed in a good and workmanlike manner. See, e.g., Gonzales v. Sw. Olshan
    Found. Repair Co., 
    400 S.W.3d 52
    , 56 (Tex. 2013) (explaining that the implied term
    is a “gap-filler” for when parties have not included their own terms regarding the
    quality of the work).1
    1
    Van Dyke additionally argues that expert testimony was necessary to aid the jury in
    6
    Although these statements of the law are generally correct, when a case is
    tried to a jury and the party complaining on appeal did not object to the charge, the
    sufficiency of the evidence is measured against the charge actually submitted, not
    some other law left unidentified in the charge. See Osterberg v. Peca, 
    12 S.W.3d 31
    ,
    55 (Tex. 2000); Critical Path Res., Inc. v. Cuevas, No. 14-16-00036-CV, 
    2018 WL 1532343
    , at *18, 26 (Tex. App.—Houston [14th Dist.] Mar. 29, 2018, no pet. h.).
    Here, none of the questions that comprised the submission of Builders West’s claim
    for breach of contract contained a requirement that Builders West prove its
    subcontractors’ work was done in a good and workmanlike manner, and Van Dyke
    did not object to the absence of such an instruction in these questions.
    To prevail on a claim for breach of contract, a party must establish the
    following elements: (1) a valid contract existed between the plaintiff and the
    defendant, (2) the plaintiff tendered performance or was excused from doing so, (3)
    the defendant breached the terms of the contract, and (4) the plaintiff sustained
    damages as a result of the defendant’s breach. Petroleum 
    Workers, 503 S.W.3d at 39
    . The first element—the existence of a contract—was undisputed in this case.
    Question 1 asked whether Van Dyke breached the agreement. Question 2, which was
    contingent on an affirmative finding in response to question 1, addressed Builders
    West’s performance2 and submitted Van Dyke’s defense of prior material breach by
    assessing the quality of the electrical work at issue, citing Schwartz v. City of San Antonio ex rel.
    City Public Service Board of San Antonio, No. 04-05-00132-CV, 
    2006 WL 285989
    , at *4 (Tex.
    App.—San Antonio Feb. 8, 2006, pet. denied) (mem. op.). Builders West disagrees. Because we
    conclude the jury charge did not require evidence that the electrical work was performed in a good
    and workmanlike manner, we need not address the circumstances in which expert testimony
    regarding the quality of electrical work is necessary. See generally FFE Transp. Servs., Inc. v.
    Fulgham, 
    154 S.W.3d 84
    , 90-91 (Tex. 2004) (explaining that whether a particular matter requires
    expert testimony is a question of law reviewed de novo).
    2
    The jury also found in response to question 7 that Builders West substantially performed
    the agreement. Like question 2, question 7 included no instruction that Builders West and its
    subcontractors were required to perform in a good and workmanlike manner.
    7
    asking whether Van Dyke’s failure to comply was excused by a prior failure to
    comply by Builders West.3 Question 6, which was also contingent on an affirmative
    finding to question 1, asked about damages. As stated, none of these questions
    instructed the jury that Builders West and its subcontractors were required to
    perform in a good and workmanlike manner, and Van Dyke did not object regarding
    the absence of such an instruction.4 See generally Bayer Corp. v. DX Terminals, Ltd.,
    
    214 S.W.3d 586
    , 602 (Tex. App.—Houston [14th Dist.] 2006, pet. denied)
    (discussing preservation of error for charge complaints).
    The only question that inquired whether Builders West and its subcontractors
    performed in a good and workmanlike manner was question 4, which was part of the
    submission of Van Dyke’s claim that Builders West breached the contract. The jury
    answered “no” in response to question 4. Of course, this failure to find that Builders
    West and its subcontractors did not perform in a good and workmanlike manner does
    not amount to an affirmative finding that they did. E.g., Philadelphia Indemnity Ins.
    Co. v. White, 
    490 S.W.3d 468
    , 488 (Tex. 2016). But no such affirmative finding was
    required by the charge questions submitted without objection regarding Builders
    3
    We note that the organization of the breach-of-contract portions of the charge and the
    wording of question 2 were not in keeping with the organization and wording recommended in the
    Texas Pattern Jury Charges. When faced with competing claims of breach, the Pattern Jury
    Charges recommend asking, in sequence, whether each party failed to comply with the agreement
    and then, if the jury answers “yes” to both of those questions, asking which party failed to comply
    first. See Comm. on Pattern Jury Charges, State Bar of Tex., Texas Pattern Jury Charges: Business
    PJC 101.2 cmt. (2016). Here, as explained in the text, the trial court presented the parties’ claims
    for breach of contract in two distinct sets of questions that do not intersect. Van Dyke did not
    object to this manner of submission or to the wording of question 2, nor does he specifically
    complain about them on appeal. See United Scaffolding, Inc. v. Levine, 
    537 S.W.3d 463
    , 481 (Tex.
    2017) (“[A] defendant must preserve error by objecting when an independent theory of recovery
    is submitted defectively.”).
    4
    Cf. Comm. on Pattern Jury Charges, State Bar of Tex., Texas Pattern Jury Charges:
    Business PJC 101.2 cmt. (2016) (recommending inclusion of instructions when there is an
    obligation to perform in a good and workmanlike manner).
    8
    West’s claim that Van Dyke breached the contract by failing to pay.
    Question 4 is not related to Builders West’s claim that Van Dyke breached the
    contract for several reasons. To begin with, question 4 is not made contingent upon
    or otherwise expressly tied to any of the questions concerning Builders West’s claim.
    Furthermore, question 4 does not contain any time element—i.e., it does not ask
    whether any breach by Builders West occurred prior to Van Dyke’s breach. In order
    for any breach by Builders West to have excused a breach by Van Dyke, Builders
    West’s breach must have occurred prior to Van Dyke’s breach. See Petroleum
    
    Workers, 503 S.W.3d at 39
    . In contrast, question 2 is expressly tied to other questions
    submitting Builders West’s claim that Van Dyke breached the contract, and it
    contains the requisite time element.
    In short, question 4 has no relevance to Builders West’s recovery for breach
    of contract, and question 2 did not require performance to be in a good and
    workmanlike manner. Because the charge questions submitting Builders West’s
    claim did not include a requirement of good and workmanlike performance, we may
    not consider that requirement in reviewing the sufficiency of the evidence to support
    the jury’s answers. We therefore reject Van Dyke’s argument that the evidence is
    insufficient because Builders West provided no expert testimony that FEI’s work
    was performed in a good and workmanlike manner.
    B.     Van Dyke’s opening brief does not challenge the jury’s findings for
    Builders West on its other claims.
    Even if Van Dyke were correct that Builders West provided insufficient
    evidence to support recovery for breach of contract, the judgment would still be
    supported by the jury’s findings on Builders West’s substantial performance and
    quantum meruit claims. Van Dyke did not challenge the jury’s affirmative findings
    on these claims in his opening brief. See, e.g., Miller v. Debo Homes, LLC, No. 14-
    9
    15-00004-CV, 
    2016 WL 5399507
    , at *3 (Tex. App.—Houston [14th Dist.] Sept. 27,
    2016, no pet.) (mem. op.) (affirming judgment supported by unchallenged,
    independent jury finding and on that basis overruling challenge to other jury
    findings); Aquarium Env’ts, Inc. v. Elgohary, No. 01–12–01169–CV, 
    2014 WL 1778266
    , at *3 (Tex. App.—Houston [1st Dist.] May 1, 2014, pet. denied) (mem.
    op.) (holding any error in submitting DTPA claim was harmless where appellant did
    not challenge jury finding on breach of contract, which was an independent ground
    supporting liability and damages); see also Melartin v. CR & R, Inc., No. 14-05-
    00519-CV, 
    2009 WL 972484
    , at *1 n.1 (Tex. App.—Houston [14th Dist.] Mar. 24,
    2009, no pet.) (mem. op.) (“We do not consider arguments raised for the first time
    in a reply brief.”). As stated above, the jury found the same amount of damages for
    all three claims. These unchallenged findings therefore support the judgment. See,
    e.g., Miller, 
    2016 WL 5399507
    , at *3; Aquarium Env’ts, 
    2014 WL 1778266
    , at *3.
    C.     The charge questions regarding Builders West’s other claims did
    not require good and workmanlike performance.
    In his reply brief, Van Dyke asserts that his arguments regarding Builders
    West’s claim for breach of contract also apply to its claims regarding substantial
    performance and quantum meruit. In support, he cites authority explaining that briefs
    should be construed liberally and the statement of an issue should be treated as
    covering every subsidiary question fairly included. See Tex. R. App. P. 38.1(f);
    Weeks Marine, Inc. v. Garza, 
    371 S.W.3d 157
    , 162 (Tex. 2012). Although we agree
    with these premises, we disagree that a challenge to Builders West’s success on its
    substantial performance and quantum meruit claims is fairly included in Van Dyke’s
    argument in his opening brief that “Builders West Could Not Prevail On Its Contract
    Claim . . . .” Yet even if we were to apply Van Dyke’s arguments in his opening
    brief to the jury’s substantial performance and quantum meruit findings, Van Dyke
    still could not obtain reversal of the judgment.
    10
    As set forth above, Van Dyke’s argument under his first issue is that Builders
    West could not prevail on its claim for breach of contract because it did not provide
    expert evidence that FEI performed in a good and workmanlike manner. Neither the
    jury question regarding substantial performance (question 7) nor the question
    regarding quantum meruit (question 10) required proof of performance in a good
    and workmanlike manner, and Van Dyke did not object to these omissions in the
    trial court. Therefore, evidence of good and workmanlike performance is not
    necessary to support the jury’s answers to those questions. See 
    Osterberg, 12 S.W.3d at 55
    (“[I]t is the court’s charge, not some other unidentified law, that measures the
    sufficiency of the evidence when the opposing party fails to object to the charge”);
    see also Critical Path, 
    2018 WL 1532343
    , at *18, 26. For the foregoing reasons, we
    overrule Van Dyke’s first issue.
    II.    Van Dyke’s complaint of charge error in refusing to give an instruction
    does not affect the parts of the charge supporting the judgment.
    In his second issue, Van Dyke contends that the trial court erred in refusing to
    instruct the jury in question 4 regarding Builders West’s contractual duty to
    supervise the work of its subcontractors.5 Van Dyke asserts that because the trial
    court instructed the jury in question 4 on the implied requirement that Builders West
    perform in a good and workmanlike manner but did not instruct the jury regarding
    the express obligation to supervise, it incorrectly suggested to the jury that poor work
    quality was the only permissible basis for finding that Builders West breached the
    contract.
    As explained in detail above, question 4 was part of the series of questions
    that submitted Van Dyke’s own claim that Builders West breached the contract. In
    5
    As mentioned, the parties’ contract stated that Builders West was to be paid for “labor
    and materials plus Contractor’s Fee of 20% to cover overhead, supervision, and profit” (emphasis
    added).
    11
    a post-submission letter brief, Van Dyke clarified that he is not appealing the portion
    of the judgment ordering that he take nothing on his affirmative causes of action; he
    is only appealing the part of the judgment awarding damages and attorneys’ fees to
    Builders West. Question 4 is not material to the award of damages and attorneys’
    fees to Builders West. Accordingly, Van Dyke has expressly waived his second
    issue. Cf. Energy Maint. Servs. Gp. I, LLC v. Sandt, 
    401 S.W.3d 204
    , 221 (Tex.
    App.—Houston [14th Dist.] 2012, pet. denied) (giving effect to jury findings where
    appellants conceded in reply brief that they did not challenge the findings in their
    opening brief).
    We further note that the arguments Van Dyke makes in his second issue
    cannot be read as applying to question 2 of the jury charge, which submitted Van
    Dyke’s defense that Builders West had previously breached the contract. Van Dyke
    did not object to question 2 on this basis in the trial court, as he did to question 4,
    and he did not request that an instruction on supervision accompany question 2, as
    he did for question 4. See, e.g., Bayer 
    Corp., 214 S.W.3d at 602
    (discussing
    preservation of error for charge complaints). Moreover, question 2 did not instruct
    the jury regarding good and workmanlike performance, so it did not limit the bases
    on which the jury could have found a breach by Builders West. We overrule Van
    Dyke’s second issue.
    III.   Builders West’s recovery of attorneys’ fees is not limited to the amount
    incurred.
    In his third issue, Van Dyke challenges the trial court’s award of attorneys’
    fees to Builders West at the rate of $500 per hour. In Texas, attorney’s fees are
    recoverable in litigation only if expressly authorized by a contract or statute. Tucker
    v. Thomas, 
    419 S.W.3d 292
    , 295 (Tex. 2013). In this case, Builders West sought fees
    pursuant to chapter 38 of the Texas Civil Practice and Remedies Code. Tex. Civ.
    12
    Prac. & Rem. Code § 38.001-.006. Section 38.001 of that chapter provides, in
    relevant part, that “[a] person may recover reasonable attorney’s fees from an
    individual or corporation, in addition to the amount of a valid claim and costs, if the
    claim is for: (1) rendered services; (2) performed labor; (3) furnished material; . . .
    or (8) an oral or written contract.” 
    Id. § 38.001.
    An award of attorney’s fees must be
    supported by evidence that the fees are reasonable and necessary for the prosecution
    of the suit. See Stewart Title Guar. Co. v. Sterling, 
    822 S.W.2d 1
    , 10 (Tex. 1991).
    As mentioned above, Van Dyke does not contest the reasonableness of the
    fees awarded and he does not contest the necessity of the services performed;
    instead, he specifically complains only that Builders West did not actually incur fees
    at the rate of $500 per hour. In doing so, Van Dyke misreads the requirements for an
    award of attorneys’ fees under Chapter 38.
    Van Dyke’s argument is premised on language in the fee agreement between
    Builders West and RHA, one of the law firms representing it. This agreement
    contains the following paragraph explaining the hourly rate to be charged:
    Even though we are charging $500 per hour for our attorney time, we
    are agreeing to seek payment from Builders West for only $350 per
    hour. We will seek to have the jury and/or judge award Builders West
    the entire $500 per hour fee from Scott Van Dyke. If and when Builders
    West is awarded and paid more than $350 per hour for our legal fees,
    Builders West agrees to pay to RH&A any award for RH&A fees over
    $350 per hour, and $350 per hour will be apportioned to Builders West
    to make the company whole for those amounts already paid to RH&A.
    According to Van Dyke, he should not be required to pay fees at the $500 rate instead
    of the $350 rate because Builders West was not obligated to pay the higher rate
    unless it first received payment from Van Dyke for the higher amount. In other
    words, Van Dyke insists that because Builders West never incurred fees at the higher
    rate, it is only entitled to be awarded fees calculated at the lower rate.
    13
    The parties do not cite, and we have not discovered, any Texas cases
    addressing a request for attorneys’ fees under a contract identical to the one
    presented here. In many contexts, however, Texas courts have held that a party
    entitled to attorneys’ fees need not show that the fees requested were actually
    incurred unless the statute authorizing a fee award requires such proof. See, e.g.,
    Gluck v. Hadlock, No. 02–09–00411–CV, 
    2011 WL 944439
    , at *5 (Tex. App.—Fort
    Worth March 17, 2011, no pet.) (mem. op.) (affirming award of fees even though
    attorney agreed not to charge client); In re Estate of Johnson, 
    340 S.W.3d 769
    , 787
    (Tex. App.—San Antonio 2011, pet. denied) (holding party could recover fees even
    though its fees had been paid by a third-party trust); AMX Enters., L.L.P. v. Master
    Realty Corp., 
    283 S.W.3d 506
    , 517-21 (Tex. App.—Fort Worth 2009, no pet.)
    (affirming award under chapter 38 of in-house counsel fees based on market value
    and stating “proof of fees actually incurred or paid are not prerequisites to the
    recovery of attorney’s fees in Texas”); Brown v. Comm’n for Lawyer Discipline, 
    980 S.W.2d 675
    , 683–84 (Tex. App.—San Antonio 1998, no writ) (holding state bar
    represented by private lawyers on a pro bono basis may recover reasonable
    attorneys’ fees); Beckstrom v. Gilmore, 
    886 S.W.2d 845
    , 847 (Tex. App.—Eastland
    1994, writ denied) (holding attorney representing himself pro se may recover fees
    under chapter 38); Tuberquia v. Jamison & Harris, No. A14–91–00055–CV, 
    1991 WL 260344
    , at *2 (Tex. App.—Houston [14th Dist.] Dec. 12, 1991, no writ) (not
    designated for publication) (holding law firm represented by one of its own attorneys
    was entitled to recover attorney’s fees for the time and effort expended); cf. Cruz v.
    Van Sickle, 
    452 S.W.3d 503
    , 524 & n.36 (Tex. App.—Dallas 2014, pet. denied)
    (distinguishing Gluck, AMX, Brown, and Tuberquia because statute at issue
    expressly required that fees be incurred).
    In keeping with this precedent, we reject Van Dyke’s assertion that Builders
    14
    West must have actually incurred fees at the higher rate in order to recover fees at
    that rate. Chapter 38 contains no such requirement.6 Van Dyke also argues as a
    policy matter that permitting recovery under fee contracts such as that between
    Builders West and RHA would promote fee inflation and untether fees from market
    realities. But potential excesses in a contract such as this are held in check by the
    same requirements that have always held awards of attorney’s fees in check under
    Chapter 38: the fees must be proven reasonable and necessary for the prosecution of
    the suit. See Stewart 
    Title, 822 S.W.2d at 10
    ; Trevino v. City of Pearland, 
    531 S.W.3d 290
    , 297 (Tex. App.—Houston [14th Dist.] 2017, no pet.); see also Arthur
    Andersen & Co. v. Perry Equip. Corp., 
    945 S.W.2d 812
    , 818 (Tex. 1997) (“[W]e
    cannot agree that the mere fact that a party and a lawyer have agreed to a contingent
    fee means that the fee arrangement is in and of itself reasonable.”); Classic C Homes,
    Inc. v. Homeowners Mgmt. Enterprises, Inc., No. 02-14-00243-CV, 
    2015 WL 5461517
    , at *5 (Tex. App.—Fort Worth Sept. 17, 2015, no pet.) (making same point
    in case where fees were sought under Chapter 38). If Van Dyke deems those
    statutory checks insufficient, his recourse is to the Legislature, not this Court.
    Here, Van Dyke conceded that fees of $500 per hour were reasonable and that
    the work performed was necessary. See generally First Bank v. DTSG, Ltd., 
    472 S.W.3d 1
    , 9 (Tex. App.—Houston [14th Dist.] 2015) (assessing evidence for a
    reasonable fee for the necessary services of party’s attorneys), rev’d on other
    grounds sub nom. First Bank v. Brumitt, 
    519 S.W.3d 95
    (Tex. 2017); AMX 
    Enters., 283 S.W.3d at 520
    (same). Because nothing more was required to support the trial
    6
    We further note that because attorney’s fees under chapter 38 are not required to be
    incurred before being awarded, the trial court’s statement in the judgment that the fees were
    “incurred” is mere surplusage. See, e.g., Prime Tree & Landscaping Servs. v. Americon Servs. Co.,
    No. 01-09-00779-CV, 
    2011 WL 947004
    , at *4 (Tex. App.—Houston [1st Dist.] Mar. 17, 2011, no
    pet.) (explaining that harmless surplusage does not affect validity of judgment).
    15
    court’s fee award, we overrule Van Dyke’s third issue.
    CONCLUSION
    Having overruled each of Van Dyke’s issues, we need not reach Builders
    West’s contingent cross-appeal. See Tex. R. App. P. 47.1. We affirm the trial court’s
    judgment.
    /s/    J. Brett Busby
    Justice
    Panel consists of Justices Jamison, Busby, and Brown.
    16