Sun Development, L.P. v. Larry Hughes and Susan Hughes ( 2014 )


Menu:
  •                                       In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    ____________________
    NO. 09-12-00524-CV
    ____________________
    SUN DEVELOPMENT, L.P., Appellant
    V.
    LARRY HUGHES AND SUSAN HUGHES, Appellees
    _________________________________    ______________________
    On Appeal from the 9th District Court
    Montgomery County, Texas
    Trial Cause No. 09-10-10214 CV
    ____________________________________________                        ____________
    MEMORANDUM OPINION
    This appeal arises from the trial of a case that relates to Sun Development,
    L.P.’s sale of a new home to Larry and Susan Hughes. After they purchased the
    home, the Hugheses learned the home needed significant repairs. They then sued
    Sun, alleging that Sun had breached the parties’ agreements and had engaged in
    deceptive trade practices regarding the sale. At the conclusion of a jury trial, the
    jury found that Sun had engaged in a deceptive trade practice, and that Sun had
    1
    breached a Rule 11 1 agreement, which obligated Sun to do several things in return
    for the Hugheses decision to exercise an option Sun gave them in return for closing
    on the home. After the trial, the Hugheses elected to recover judgment against Sun
    under the jury’s DTPA findings, as those findings allowed the Hugheses a greater
    recovery.
    In eight issues, Sun appeals from the trial court’s judgment. We agree with
    Sun’s argument in its first issue, and hold that the trial court’s decision to deny
    Sun’s request to identify the entity that installed the stucco on the home as a
    responsible third party was error, and we further conclude that the error was
    harmful. We reverse the trial court’s judgment, and we remand the cause for a new
    trial.
    Factual and Procedural Background
    After the Hugheses signed a contract to purchase the home, they identified
    several items that Sun agreed to complete or repair before the date the parties
    selected to close on the sale. Before the closing date arrived, a dispute arose
    regarding whether Sun had completed its work. Claiming that all of the items had
    been substantially repaired, Sun filed a suit for declaratory judgment against the
    1
    Rule 11 of the Texas Rules of Civil Procedure requires agreements touching
    “any suit pending” to be in writing, signed, and filed with the papers as part of the
    record or made in open court to make such agreements enforceable. Tex. R. Civ. P.
    11.
    2
    Hugheses in Galveston. In its suit, Sun asked the court to declare the rights of the
    parties under the agreements relating to the home’s sale. To resolve the declaratory
    judgment suit, the Hugheses and Sun signed a letter of agreement in 2008 that gave
    the Hugheses two alternatives, the right to inspect and close on the home, or the
    right to cancel their agreement to buy the home. The Rule 11 agreement gave the
    Hugheses several days after they signed the agreement to inspect the home and
    decide which of the options they wanted to exercise.
    In August 2008, the Hugheses opted under the agreement to close on the
    home. Under the Rule 11 agreement, given the Hugheses’ decision to purchase the
    home, Sun’s builder and Sun were obligated to perform several future acts. For
    instance, Sun’s builder was required to take “care of normal and customary punch
    list items.” Sun was obligated to provide the Hugheses with a “2-10 warranty[,]” to
    pay the Hugheses $15,000 at closing, and to give them a $12,000 credit for
    landscaping and irrigation. Sun also agreed in the Rule 11 agreement that it would
    dismiss its declaratory judgment action, and both parties agreed they would
    execute mutual releases, which waived “any and all known causes of action that
    either party could assert against the other arising from the home purchase
    transaction.”
    3
    Had the Hugheses opted to cancel the sale, the Rule 11 agreement would
    have required that Sun return the earnest money the Hugheses had paid on the
    home, that Sun pay the Hugheses $45,000 for the expenses the Hugheses incurred
    for items they had “purchased and used at the home[,]”and that Sun dismiss its suit
    for declaratory judgment. Had the cancellation option been selected, the Rule 11
    agreement still required both parties to execute mutual releases.
    Approximately three months after closing on the home, the Hugheses hired
    Lynn DeGeorge, a general contractor, consultant, and inspector to inspect the
    stucco system on their home. DeGeorge holds certifications specific to inspecting
    homes that are clad in stucco. Although the Hugheses had benefitted from several
    inspections by inspectors who examined the home before they exercised the option
    they were given in the Rule 11 to close on the home, none of the inspectors the
    Hugheses utilized before they closed held certifications specific to inspecting
    stucco. DeGeorge advised the Hugheses that the stucco on the home needed
    extensive repair.
    In 2009, the Hugheses filed suit against Sun, claiming that Sun had engaged
    in deceptive trade practices in selling the home and that Sun had breached several
    terms of the parties’ Rule 11 agreement that related to the purchase. The Hugheses’
    live pleading at the time of the trial, their fourth amended petition, alleges that Sun
    4
    knowingly failed to disclose information concerning the home’s construction with
    the intent to induce them to purchase the home. The Hugheses also alleged that
    they would not have purchased the home had Sun fully disclosed information
    about the home that Sun knew about before the sale closed.
    The case was tried to a jury in April 2012. At the conclusion of the trial, the
    jury found that Sun failed to disclose “information concerning construction
    services that was known at the time of the transaction with the intention to induce
    [the Hugheses] into a transaction they otherwise would not have entered into if the
    information had been disclosed.” On appeal, Sun argues that no evidence before
    the jury shows that it knew, on the date the sale closed, of any problems that it did
    not disclose. Additionally, Sun argues that the Hugheses relied solely on their own
    inspections when they closed on the sale, and it argues that the Hugheses did not
    rely on any of the information that it gave them when they finally decided they
    wanted to close on the home.
    During the trial, the respective home inspection reports obtained by the
    Hugheses and Sun were admitted into evidence. The reports that each of the parties
    received are evidentiary of what the parties knew regarding both the type and
    scope of repairs the home needed at various times as the parties negotiated whether
    the sale would close. The various reports and bids that Sun received from its
    5
    inspector and from its contractors were also relevant to the jury’s evaluation of
    whether Sun fully disclosed all it knew about the scope of repairs needed to the
    stucco on the home.
    We will first address the reports the Hugheses obtained from the inspectors
    they hired. The Hugheses had the benefit of reports from three inspectors who had
    looked at the home at various times before the sale closed. In 2007, Gordon Guffin
    inspected the home. Guffin gave the Hugheses a written report regarding his
    inspection, and his report identified several exterior and interior construction
    problems that needed to be addressed. The problems that Guffin reported include
    indoor and outdoor water leaks at various specific locations. The types of problems
    that Guffin reported, however, were matters the jury could have decided that the
    builder addressed through repairs before the date that the sale finally closed.
    In March 2008, George Guajardo, the owner of a restoration and cleaning
    company, inspected the home for the Hugheses. Guajardo’s thermal image report is
    among the evidence the jury considered in determining what the Hugheses learned
    regarding the home’s moisture problems before they decided to close on the home.
    Guajardo’s report noted the existence of “possible moisture or improper
    insulation” in several areas of the home, and he suggested that his company be
    hired to further investigate the existence of any possible moisture problems by
    6
    using a moisture meter to probe the walls in seven areas that his report identifies.
    There was no testimony at the trial showing that Guajardo’s company did any
    further testing at the home or that he ever confirmed that the home had moisture
    problems. The jury could have also concluded that the repairs the builder
    performed after March 2008 and before closing left the Hugheses with the
    impression that the problems Guajardo had identified in his report were resolved.
    In June 2008, the Hugheses hired Gene Montgomery of Island Home
    Inspections to inspect the home. Montgomery’s report includes a punch list, which
    identifies the items he found in his inspection that he felt needed to be repaired.
    Montgomery’s report does not indicate that he performed any tests to evaluate the
    moisture levels in the home or that he confirmed that moisture problems still
    existed at the home. The most significant finding in Montgomery’s report notes
    that the concrete finish on the first floor was substandard. However, the Hugheses
    never complained at trial that Sun knew and failed to disclose that problem, nor did
    they complain that Sun knew and failed to disclose the other cosmetic problems
    that are noted in Montgomery’s report. The repairs that Montgomery
    recommended in his report are largely cosmetic, and none of the repairs
    Montgomery suggested addressed any of the water or moisture problems that were
    referred to in Guffin’s or Guajardo’s reports. Montgomery did note that the air
    7
    conditioning system in the attic was condensing at an abnormal rate, and he noted
    that he saw water dripping from the plenum of the air conditioner onto the attic
    deck. With respect to that issue, Montgomery recommended that the Hugheses
    have a licensed air conditioning technician inspect the air system. Nevertheless, the
    jury could have reasonably concluded that Montgomery’s report did not disclose
    any problems regarding the stucco installation, and that it did not indicate that
    Montgomery identified any problems relating to the presence of excessive
    moisture in the home’s walls. Although there are stucco-related repairs that are
    referenced in Montgomery’s report, the jury could have reasonably viewed the
    items Montgomery mentioned as items the Hugheses reasonably believed the
    builder had repaired before closing as they were all cosmetic.
    Separately, Sun received two reports from its inspector that it did not share
    with the Hugheses before the date the sale closed. The jury could have concluded
    that the undisclosed reports provided Sun with information indicating that the
    problems with the stucco installation were significant and were not just cosmetic.
    The two undisclosed reports were authored by Rhondalyn Riley, the president of
    Exterior Inspections, Inc., who inspected the home at Sun’s request. Riley has
    certifications as a licensed professional real estate inspector through the Texas Real
    Estate Commission and as a moisture analyst for inspecting exterior insulation
    8
    finishing systems (stucco) through the Exterior Design Institute, 2 as well as a
    certification through the Associated Wall and Ceiling Industry. 3 The record reflects
    that Riley was the only certified stucco inspector who provided reports regarding
    the stucco on the home prior to closing. After each inspection, she provided Sun
    with a report addressing the stucco on the home. Riley’s first two reports, her
    March 2008 and her initial June 2008 report, were not disclosed to the Hugheses
    before they closed on the home. Riley’s third and last report of June 26, 2008,
    which notes that the stucco had undergone repairs and was performing, was the
    sole report that Sun provided to the Hugheses. The evidence also showed that Sun
    gave Riley’s last report to the Hugheses during the negotiations over the Rule 11
    agreement. After receiving Riley’s report, and before deciding to exercise the
    option to close on the home, the evidence did not show that the Hugheses obtained
    their own certified stucco inspector to inspect the stucco on the home.
    Riley’s initial report, dated March 2008, states that the purpose of her report
    was to “help determine potential problem areas which may warrant more
    investigation.” Riley’s March report notes that Exterior Inspections was “engaged
    2
    According to Riley, the Exterior Design Institute is a national certifying
    body that certifies people to inspect stucco and to test for moisture.
    3
    Riley explained that the Associated Wall and Ceiling Industry is another
    industry organization that provides training and certifications in the inspection of
    stucco.
    9
    to conduct a visual survey of the condition of the stucco cladding and [do] a
    moisture analysis of the exterior walls[.]” Riley’s March report identified high
    moisture readings at levels of 20% or higher in three specified locations in the
    home’s walls, medium moisture readings at levels of more than 16% but less than
    20% in three other walls, and several additional stucco problems that Riley thought
    were in need of repair. Riley recommended that core sampling be done in areas
    where moisture levels exceeded 25%, and she also recommended core sampling in
    areas where there was no sheathing or soft sheathing on the exterior of the home.
    Although the evidence shows that the Hugheses asked Sun on several occasions
    before they closed on the home for a copy of Riley’s March 2008 report, the
    evidence shows that Sun did not disclose Riley’s March 2008 report before the
    Hugheses decided to close on the home.
    Riley conducted her second stucco inspection on the home on June 9, 2008.
    Riley’s June 9 report notes that some of the deficiencies she found in March had
    been repaired, but she also notes in her second report that most of the items
    identified in her first report had not yet been fixed. Riley’s June 9 report does not
    show that she retested the areas previously tested in March. Riley’s June 9 report
    recommends that core sampling be done in those areas where high moisture
    10
    readings were found. Sun never gave the Hugheses a copy of Riley’s June 9 report
    before they exercised their option to close on the home.
    Riley conducted a third stucco inspection on June 26, 2008, and Sun
    provided the Hugheses a copy of Riley’s June 26 report during the negotiations
    that led the parties to sign the Rule 11 agreement. Riley’s June 26 report
    specifically mentions that moisture testing equipment was not used during her June
    26 inspection. Although Riley’s June 26 report mentions that high moisture levels
    had been found, her June 26 report did not reflect where the high moisture levels
    were found, information contained in both of her earlier reports. Riley’s June 26
    report indicates that she was told that core sampling had been done, as it states:
    “Stucco core samples made, per builder, to investigate high moisture readings[;]”
    however, none of Riley’s reports indicate that Riley personally knew whether core
    sampling had been done or that she knew what the builder and Sun had found
    based on any core sampling that was done. Although the builder testified at the
    trial, he was never asked to address whether he had witnessed any core sampling
    being done, nor was he asked if he knew what the results of any core sampling had
    shown. Riley’s testimony indicates that during her last June 2009 inspection, she
    observed signs on the walls of the home that were consistent with someone having
    11
    done core sampling in the areas where she had reported high moisture levels to be
    present.
    Sun’s corporate witnesses were also relevant to the jury’s resolving why Sun
    might have chosen to provide the Hugheses with only one of Riley’s three reports.
    Sun’s President and CEO indicated during his testimony that the purpose of giving
    the June 26 report to the Hugheses was to show that the stucco on the home met all
    standards. But, Riley’s March report can be viewed as revealing the presence of
    possible serious and extensive stucco problems, and given Riley’s lack of personal
    knowledge about the repairs, her last report when viewed in isolation, as
    potentially misleading. Even Riley agreed during trial that a person purchasing the
    home “[p]erhaps” might have liked to have known that there were very high
    moisture readings in the locations identified in her March report. Riley testified at
    the trial that had she been purchasing the home, she would have wanted to know
    about the moisture problems and the repairs that had been done to address those
    problems. Also, Riley did not dispute that two of the moisture readings that she
    reported in her March report “were off the charts.” Riley’s last report did not
    disclose the moisture readings, as these were reported in her earlier reports.
    While the Hugheses acknowledged during the trial that they knew of various
    problems with the home at closing, they disputed that Sun disclosed the extent of
    12
    the moisture problems related to the installation of the stucco on the home or that
    they were told at closing of the extent of the repairs Sun knew were still needed to
    fix those problems. Before closing, the Hugheses requested that Stuart Lapp, Sun’s
    counsel, provide the March report to them. Lapp advised the Hugheses’ attorney
    that although he had not seen the March report, he understood the June 26 report
    that he provided did not identify any problems with the stucco on the home. The
    evidence shows that Lapp told the Hugheses’ attorney during the negotiations that
    led to the signing of the Rule 11 agreement that “[i]f that is true, I question why
    you or your clients would feel the need to see a prior report rather than rely on the
    report they have that reflects no problems with the stucco.” At trial, Lapp testified:
    “In hindsight, I wish that I had found that report and personally given it to them[.]”
    Lapp also testified that had he disclosed the March report prior to the sale of the
    home, “we wouldn’t be here today.” According to the Hugheses, by choosing to
    disclose only Riley’s last report, Sun led them to believe that all of the stucco-
    related problems had been fixed.
    The jury found in the Hugheses’ favor on their nondisclosure claim, and
    found that Sun had knowingly engaged in the conduct at issue. The jury found the
    Hugheses had actual damages of $647,713 on their DTPA claim, awarded punitive
    damages of $85,000, and found the Hugheses should recover attorneys’ fees from
    13
    Sun for the trial and also gave the Hugheses conditional awards of attorneys’ fees
    in the event the case was appealed.
    Standard of Review
    First, we will address the arguments that Sun has advanced in issues two and
    three, as if these were resolved in Sun’s favor, we would be required to render a
    judgment in Sun’s favor. See Lone Star Gas Co. v. R.R. Comm’n of Tex., 
    767 S.W.2d 709
    , 710 (Tex. 1989) (per curiam). In issue two, Sun argues the evidence is
    legally insufficient to support the jury’s DTPA findings. In issue three, Sun argues
    the evidence before the jury conclusively established that the Hugheses agreed to
    release all of their claims.
    Claims challenging the legal sufficiency of the evidence are characterized as
    either “‘no evidence’” challenges or “‘matter of law’” challenges, depending on
    which party has the burden of proof. Raw Hide Oil & Gas, Inc. v. Maxus
    Exploration Co., 
    766 S.W.2d 264
    , 275 (Tex. App.—Amarillo 1988, writ denied).
    Because Sun did not have the burden of proof on the DTPA issue, Sun must
    demonstrate in its appeal that no evidence supports the jury’s DTPA findings to
    prevail on the arguments that it advances in issue two. See Croucher v. Croucher,
    
    660 S.W.2d 55
    , 58 (Tex. 1983); Christus St. Mary Hosp. v. O’Banion, 
    227 S.W.3d 868
    , 873 (Tex. App.—Beaumont 2007, pet. denied).
    14
    With respect to the arguments Sun raises in issue three, which concern the
    enforcement of the Rule 11 agreement, the law also required the Hugheses to prove
    that they were entitled to avoid their obligations under the parties’ Rule 11
    agreement. See Williams v. Glash, 
    789 S.W.2d 261
    , 264 (Tex. 1990) (explaining
    that burden of proving that a claim was unknown, once defense of release of
    known claims is shown and there is evidence that the parties agreed to release
    known claims, is on the party attempting to avoid the release under a claim of
    mutual mistake). Although the jury was not asked to specifically resolve an issue
    that included an instruction about all of the elements relevant to a claim of mutual
    mistake, we are required to assume the trial court found any of the omitted
    elements on the question of mutual mistake in a manner that supports the trial
    court’s judgment. See Tex. R. Civ. P. 279 (providing that omitted elements of a
    claim “shall be deemed found by the court in such manner as to support the
    judgment”); Tri v. J.T.T., 
    162 S.W.3d 552
    , 558 (Tex. 2005). In this case, one of the
    implied findings is that the Hugheses were unaware at the time they exercised their
    option to close on the home that the various repairs which had been done by the
    builder were inadequate. See Tex. R. Civ. P. 279. Thus, Sun must also demonstrate
    that there is no evidence supporting the trial court’s implied findings to prevail on
    15
    the arguments it has advanced in issue three. See 
    Croucher, 660 S.W.2d at 58
    ; Raw
    Hide Oil & 
    Gas, 766 S.W.2d at 276
    .
    We use an objective standard to evaluate whether the evidence presented to
    a jury is legally sufficient to support a verdict. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex. 2005). If the evidence being reviewed allowed reasonable
    and fair-minded people to reach the verdict being reviewed, the appeals court is
    required to uphold the judgment. 
    Id. In a
    legal sufficiency review, appellate courts
    are to “credit favorable evidence if reasonable jurors could, and disregard contrary
    evidence unless reasonable jurors could not.” Id.; see also Kroger Tex. Ltd. P’ship
    v. Suberu, 
    216 S.W.3d 788
    , 793 (Tex. 2006). A legal sufficiency challenge will be
    sustained “when, among other things, the evidence offered to establish a vital fact
    does not exceed a scintilla.” 
    Suberu, 216 S.W.3d at 793
    . “Evidence does not
    exceed a scintilla if it is ‘so weak as to do no more than create a mere surmise or
    suspicion’ that the fact exists.” 
    Id. (citing Ford
    Motor Co. v. Ridgway, 
    135 S.W.3d 598
    , 601 (Tex. 2004)).
    Analysis — Legal Sufficiency Issues
    To prevail on a DTPA claim, DTPA plaintiffs are required to show (1) that
    they were consumers with respect to the purchase at issue; (2) that the defendant
    engaged in false, misleading, or deceptive acts; and (3) that the defendant’s acts
    16
    were a producing cause of their damages. See Tex. Bus. & Com. Code Ann. §
    17.50(a) (West 2011); Doe v. Boys Clubs of Greater Dallas, Inc., 
    907 S.W.2d 472
    ,
    478 (Tex. 1995); Main Place Custom Homes, Inc. v. Honaker, 
    192 S.W.3d 604
    ,
    623 (Tex. App.—Fort Worth 2006, pet. denied). In this case, the trial court defined
    a “‘[f]alse, misleading, or deceptive act or practice’” as:
    Failing to disclose information concerning construction services that
    was known at the time of the transaction with the intention to induce
    Plaintiffs into a transaction they otherwise would not have entered
    into if the information had been disclosed.
    See Tex. Bus. & Com. Code Ann. § 17.46(b)(24) (West 2011).
    The Hugheses submitted and prevailed under a failure to disclose claim.
    Under the DTPA, an actionable failure to disclose a claim requires the plaintiff to
    show that the defendant knew of the information, that the defendant failed to bring
    the information to the plaintiff’s attention, and that the information was withheld
    with the intent to induce the consumer to engage in a transaction. See 
    Doe, 907 S.W.2d at 479
    ; Willowbrook Foods, Inc. v. Grinnell Corp., 
    147 S.W.3d 492
    , 507
    (Tex. App.—San Antonio 2004, pet. denied). Information is material if a
    reasonable person would attach importance to it and would be induced to act on it
    to determine whether to make the transaction in question. See Citizens Nat’l Bank
    v. Allen Rae Invs., Inc., 
    142 S.W.3d 459
    , 478-79 (Tex. App.—Fort Worth 2004, no
    pet.).
    17
    To demonstrate that the nondisclosure of known facts was a producing cause
    of a plaintiff’s DTPA damages, the nondisclosure at issue must be shown to have
    been a substantial factor that brought about the plaintiff’s injury, without which the
    injury would not have occurred. See 
    Doe, 907 S.W.2d at 481
    . Given the issue
    submitted to the jury in this case, the jury was required to find that Sun knowingly
    failed to disclose information concerning Sun’s construction services that induced
    the Hugheses to purchase a home they would not have purchased had such
    information been disclosed. The primary focus of the trial concerned the
    Hugheses’ stucco-installation claim. With respect to their nondisclosure recovery
    under that claim, the Hugheses were required to prove that before closing, Sun
    failed to disclose that it knew the stucco repairs done on the home had not fixed the
    problems that it had identified before the Hugheses exercised their option to close
    on the home, and that had those problems about which it knew been disclosed, the
    Hugheses would not have exercised their option to purchase the home.
    The jury in Sun’s case considered a variety of alleged nondisclosure claims
    submitted in a broad form charge. The jury found that Sun failed to disclose
    information concerning its construction services, that the Hugheses had relied to
    their detriment on the nondisclosure, and that the nondisclosure of the information
    was a producing cause of the Hugheses’ damages. In issue two, Sun argues that its
    18
    alleged nondisclosures about the stucco could not have been a producing cause of
    the Hugheses’ damages because there was no evidence supporting the jury’s
    determination that the Hugheses were unaware at closing that the home had stucco
    problems. But, Sun’s argument largely ignores the inferences that a jury could
    reasonably draw from the evidence, as the evidence, when viewed in the light most
    favorable to the jury’s verdict, allowed the jury to conclude that differences existed
    in what each of the parties knew regarding what was wrong with the stucco on the
    home. Sun’s argument also ignores the reasonable inference from the evidence
    tending to show that the parties did not have the same level of knowledge about
    what had been done to repair the stucco before the Hugheses exercised their option
    to purchase the home. Additionally, Sun’s argument ignores evidence that tends to
    show the Hugheses were unaware that Sun had received a bid to repair the stucco
    several times larger than what it spent on repairs.
    On the evidence before the jury, the jury could have reasonably concluded
    that Sun had encouraged the Hugheses to rely on Riley’s third report in deciding
    that the stucco had been adequately repaired, as Sun’s representatives presented it
    as a report indicating that the stucco problems had been fully repaired. Sun agrees
    that it reached that same conclusion from Riley’s third report, and it contends that
    the jury could not have rejected its claim as unreasonable. But, Sun’s argument
    19
    ignores the other evidence that allowed the jury to infer that it knew the report did
    not mean the repairs that it paid for were adequate to fix the problems with the
    stucco on the home, and the repairs that Sun paid to have done to the stucco were
    largely cosmetic.
    For example, Riley’s June 26 report states the stucco was performing as
    intended at that time; the report does not necessarily support Sun’s claim that the
    problems that Riley had identified in her earlier reports had been fully repaired.
    Essentially, Sun disputes the inferences that reasonable jurors could draw from the
    conflicting evidence addressing what Sun knew about the stucco and what repairs
    were needed to the stucco before the sale closed. The evidence demonstrates that
    both parties learned generally that there had been problems associated with the
    stucco installation and that both parties were aware that Sun had its builder do
    something to repair problems with the stucco on the home. However, the evidence
    also provided the jury with conflicting inferences on whether Sun reasonably
    believed all of the problems with the stucco were fully repaired by the repairs that
    it authorized. For example, the jury was entitled to conclude on this record that Sun
    selectively provided the Hugheses with Riley’s June 26 report and that it did not
    provide them with her earlier reports to mislead them about the nature and extent
    of the problems with the stucco on the home. The jury could also have reasonably
    20
    inferred from all of the evidence that a full disclosure by Sun of what it knew about
    the stucco problems on the home would have revealed to the Hugheses that the
    repairs Sun authorized were insufficient to address the scope and extent of the
    problems identified by Riley in her two undisclosed reports.
    Circumstantial evidence also allowed the jury to infer that Sun was aware
    that the repairs it authorized were insufficient to address the scope of the problems
    that Riley had identified regarding the installation of the stucco on the home. The
    evidence before the jury includes evidence showing that before closing, Sun’s
    builder received a bid for repairing the stucco from Robert Territo, the owner of
    Allstar Stucco. Territo’s bid to repair the stucco was based on the problems that
    Riley noted in her March report, and his bid was substantially more than the
    amount Sun proved that it paid to address the problems identified by Riley in her
    reports. According to Territo, he submitted a bid of approximately $100,000 to
    repair the stucco, a bid that he testified he based on Riley’s initial report. During
    the trial, Territo explained that after giving the initial bid, Sun’s builder asked that
    he revise his bid because he was told that they wanted to “control some of the costs
    themselves[.]” After providing Sun’s builder a revised bid, Territo explained that
    he “[n]ever heard back from [Sun’s builder].” There was evidence that Sun
    received a copy of Territo’s bid, and nothing showed that the Hugheses were aware
    21
    before they closed on Territo’s bid. Under the circumstances, the jury could have
    reasonably inferred that Sun was aware that the costs to repair the items identified
    by Riley would be approximately $100,000. Additionally, at trial Territo testified
    that during construction, he told Sun’s builder there were major defects and flaws
    in the stucco. Territo testified that the entire stucco system on the home, in his
    opinion, was flawed from the start. Territo recommended that Sun hire a certified
    inspector to inspect the home. According to Territo, the home’s stucco-related
    issues at the time of the trial were all due to the original application of stucco.
    Sun did not spend anything approaching $100,000 to repair the stucco on the
    home. The evidence before the jury indicates that Sun spent approximately
    $21,550 before closing in an effort to repair the problems Riley identified with the
    stucco on the home. Several months after the Hugheses purchased the property,
    Territo saw the home again. According to Territo, the repairs that he saw “[l]ooked
    like somebody put a band-aid on a bullet wound[,]” and he described the repairs as
    a “patch-and-coverup job of all the existing conditions that were done
    improper[ly].” The disparity between the bid that Sun received from Territo and
    the amount that it paid to repair the stucco, together with Territo’s description
    about the repairs that he saw done to the home, is some of the evidence from which
    the jury could reasonably conclude that Sun knew, at closing, that the repairs it
    22
    authorized were inadequate to fix the problems that it knew existed. Given the
    inferences available from the conflicting evidence regarding the parties’ respective
    levels of knowledge on the problems and what had been done to remedy them as of
    closing, the jury’s conclusion that Sun failed to disclose material information that
    was material to the transaction was not unreasonable.
    There was also legally sufficient evidence to support the jury’s conclusion
    that Sun’s material nondisclosure of what it knew caused the Hugheses’ damages.
    Riley, Sun’s inspector, indicated during her testimony at trial that she would have
    wanted to have the information found in her reports before deciding to purchase a
    home. See Citizens Nat’l 
    Bank, 142 S.W.3d at 478-79
    (noting that “‘[m]aterial’
    information is that which a reasonable person would attach importance to and
    would be induced to act on in determining his choice of actions in the transaction
    in question”). Lapp essentially admitted in his testimony that the suit would not
    have resulted had Riley’s first report been disclosed.
    Also, the conflicting inferences in the evidence cause us to reject Sun’s
    argument that the Hugheses relied solely on their own inspectors in deciding to
    purchase the home. First, the Hugheses never testified that they relied solely on
    their own inspections or their own inspectors in deciding to close on the home.
    Additionally, the Hugheses testified that they would not have purchased the home
    23
    had Sun provided them with the information it had about the problems with the
    stucco on the home. While there is evidence that the Hugheses had knowledge
    about some of the home’s stucco problems, the jury could have reasonably inferred
    that the Hugheses thought Sun had repaired those problems before closing with the
    exception of several minor cosmetic items, items they were also led to believe that
    Sun would fix in the course of completing a punch list of items that Sun agreed to
    repair after the Hugheses exercised their option to close on the home. In this case,
    the damage evidence does not indicate that the jury’s damage award was based on
    the items on their punch list. Lynn DeGeorge, the certified stucco inspector the
    Hugheses hired to inspect their home approximately three months after they closed
    on the home, testified at trial that the stucco problems that still needed to be
    repaired related to the original stucco installation. According to DeGeorge, Sun’s
    repairs were of “very poor quality,” and he explained that when the stucco was
    installed, there were a “lot of things that were overlooked or omitted that [he]
    considered to be contributing factors to some of the damage[.]”
    We conclude that the record contains legally sufficient evidence from which
    the jury could reasonably conclude that Sun’s nondisclosures were both material
    and a producing cause of the Hugheses’ damages. See Kupchynsky v. Nardiello,
    
    230 S.W.3d 685
    , 689 (Tex. App.—Dallas 2007, pet. denied) (rejecting seller’s
    24
    causation argument in a DTPA case where there was no evidence that buyer relied
    solely on the opinion of his inspector in purchasing a home where problems related
    to leaks were more extensive than the problems identified by the buyer’s
    inspector); Kessler v. Fanning, 
    953 S.W.2d 515
    , 519 (Tex. App.—Fort Worth
    1997, no pet.) (rejecting seller’s argument that buyer’s inspection report was an
    intervening factor that broke the causal connection where the evidence showed the
    buyer relied on several factors, including the seller’s honesty in presenting the
    property). The evidence shows that Sun possessed superior information about the
    nature and extent of the stucco problems and the repairs needed to fix them. See
    Bernstein v. Thomas, 
    298 S.W.3d 817
    , 822-23 (Tex. App.—Dallas, no pet.)
    (affirming judgment in favor of buyer based on seller’s failure to disclose report
    recommending foundation repair when both parties were aware of floor slope but
    only seller was aware of the extent of the repairs needed to remedy the problem).
    Considering the entire record, the evidence allowed the jury to reasonably
    conclude that a causal connection existed between Sun’s failure to fully disclose
    what it knew about the stucco repairs that were still needed at closing, the
    Hugheses’ decision to close on the home, and the Hugheses’ damages. See
    
    Honaker, 192 S.W.3d at 619-20
    . We overrule all of the legal sufficiency arguments
    that Sun has advanced in issue two.
    25
    In issue three, Sun argues the Hugheses agreed in the Rule 11 agreement to
    release the claims on which the jury’s DTPA finding is based. Essentially, Sun
    contends it is entitled to have the Rule 11 agreement enforced. But, under the Rule
    11 agreement, Sun promised to provide the Hugheses with certain repairs and to
    provide a homeowner warranty in consideration for the Hugheses’ agreement to
    release their claims. And, the jury found that Sun failed to comply with its
    obligations under the Rule 11 agreement, a finding that is supported by the record.
    The evidence before the jury allowed the jury to conclude that after closing, Sun
    failed to fully complete the punch list and to provide the Hugheses the 2-10
    warranty referenced in the Rule 11 agreement.
    Viewed in the light most favorable to the jury’s verdict, we conclude the
    evidence allowed the jury to reasonably conclude that Sun had breached the
    parties’ Rule 11 agreement. See Roberts v. Clark, 
    188 S.W.3d 204
    , 209 (Tex.
    App.—Tyler 2002, pet. denied) (“A breach of contract occurs when a party fails or
    refuses to perform an act that it expressly promised to do.”); see also City of
    
    Keller, 168 S.W.3d at 827
    . Moreover, even had the Hugheses signed a release, the
    Rule 11 agreement only required the Hugheses to release their “known claims.”
    See D.R. Horton-Texas, Ltd. v. Savannah Properties Assocs., L.P., 
    416 S.W.3d 217
    , 226 (Tex. App.—Fort Worth 2013, no pet.) (“Claims not clearly within the
    26
    subject matter of the release are not discharged, even if those claims exist when the
    release is executed.”).
    Because the jury found that Sun breached the Rule 11 agreement, the
    Hugheses were excused from performing their obligation under the agreement to
    sign a release of their known claims. See Mustang Pipeline Co. v. Driver Pipeline
    Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004) (“It is a fundamental principle of contract
    law that when one party to a contract commits a material breach of that contract,
    the other party is discharged or excused from further performance.”). Additionally,
    the trial court’s judgment creates an implied finding that the stucco problems that
    existed at closing were not “known claims” at closing. See Tex. R. Civ. P. 299
    (Omitted Findings). Because the record contains evidence that allowed the jury to
    reasonably conclude that Sun had breached the Rule 11 agreement, and because the
    evidence allowed the factfinder to conclude that the stucco problems at closing
    were not known to the Hugheses when the parties closed on the home, we reject
    the legal sufficiency arguments advanced by Sun in issue three.
    Analysis — Responsible Third Parties
    In issue one, Sun argues that it should receive a new trial because the trial
    court erred when it denied Sun’s requests to designate several entities and
    individuals as responsible third parties: Sonrise Homes, Inc., Shamrock Stucco and
    27
    Construction, Alpine Air, Inc., Sullivan, Stevens, Henry, Oggero & Associates,
    Inc., John Loudermilk, and Iron Access. See Tex. R. Civ. P. 38 (Third-Party
    Practice). We review the trial court’s decision denying Sun’s motion to designate
    Shamrock Stucco as a responsible third party for abuse of discretion. See MCI
    Sales & Serv., Inc. v. Hinton, 
    272 S.W.3d 17
    , 35 (Tex. App.—Waco 2008), aff’d,
    
    329 S.W.3d 475
    (Tex. 2010); see also In re Unitec Elevator Servs. Co., 
    178 S.W.3d 53
    , 58 (Tex. App.—Houston [1st Dist.] 2005, orig. proceeding); In re
    Arthur Anderson LLP, 
    121 S.W.3d 471
    , 483-85 (Tex. App.—Houston [14th Dist.]
    2003, orig. proceeding).
    According to Sun, the jury should have been asked to apportion the
    responsibility for the damages the Hugheses recovered between it and “the
    homebuilder, the designer, the inspector, the stucco contractor, the HVAC
    contractor, and the ironworks contractor.” However, no apportionment issue was
    submitted to the jury because the trial court denied Sun’s pretrial motions asking
    the trial court to designate these various individuals and entities as responsible
    third parties.
    The Hugheses argue that any error with respect to the trial court’s rulings
    regarding these designations was harmless. According to the Hugheses, Sun was
    not harmed by the trial court’s ruling because it may still sue these individuals and
    28
    entities for contribution. They also argue that Sun could have avoided any harm it
    suffered had it joined the individuals and entities to the case as third-party
    defendants. See Tex. R. App. P. 44.1(a) (Standard for Reversible Error); see
    Ingersoll-Rand Co. v. Valero Energy Corp., 
    997 S.W.2d 203
    , 210 (Tex. 1999)
    (explaining that a claim for indemnity accrues when the defendant’s “liabilities
    become fixed and certain by judgment”). Alternatively, the Hugheses contend that
    the affirmative finding on the DTPA issue resulted solely from Sun’s
    nondisclosures, and not any nondisclosures of the responsible third parties that Sun
    sought to designate. The Hugheses conclude that alleged error, if any, from the
    trial court’s rulings on Sun’s motions to designate were harmless.
    That Sun had a right to seek contribution by joining other defendants,
    however, does not mean it cannot show that it was harmed by the trial court’s
    rulings on the motions at issue. Contribution is a claim for damages, and generally,
    the third-party plaintiff joins the contribution defendant as a party to the suit. See
    Tex. R. Civ. P. 38. While the Rules of Civil Procedure allow defendants to seek
    contribution, the right to designate responsible third parties is statutory and does
    not require the defendant to join the responsible third party to the suit. Tex. Civ.
    Prac. & Rem. Code Ann. § 33.004(a) (West Supp. 2014) (“A defendant may seek
    29
    to designate a person as a responsible third party by filing a motion for leave to
    designate that person as a responsible third party.”).
    In DTPA cases, by statute, defendants have the right to designate others as
    responsible third parties. 
    Id. § 33.002(a)(2)
    (West 2008). The motion to designate a
    responsible third party must be filed “on or before the 60th day before the trial date
    unless the court finds good cause to allow the motion to be filed at a later date.” 
    Id. § 33.004(a).
    A “[r]esponsible third party” is defined as follows:
    [A]ny person who is alleged to have caused or contributed to causing
    in any way the harm for which recovery of damages is sought,
    whether by negligent act or omission, by any defective or
    unreasonably dangerous product, by other conduct or activity that
    violates an applicable legal standard, or by any combination of these.
    
    Id. § 33.011(6)
    (West 2008). A defendant may designate a responsible third party
    even though the third party has defenses to liability, cannot be joined as a third-
    party defendant, and is not liable to the parties who are involved in the suit. See
    Galbraith Eng’g Consultants, Inc. v. Pochucha, 
    290 S.W.3d 863
    , 868-69 (Tex.
    2009). We conclude that the statute governing a defendant’s right to identify
    responsible third parties creates a right to do so that does not depend on a
    defendant’s ability to join others on claims for contribution. We are not persuaded
    by the Hugheses argument that Sun was required to join others as parties to
    demonstrate harm when the trial court’s ruling deprived Sun of a statutory right it
    30
    was given to pursue a strategy that did not require that it join others as parties to
    the suit. Additionally, the Hugheses could have just as easily avoided any question
    of harm by agreeing to Sun’s motions to designate the responsible third parties at
    issue. In our opinion, Sun preserved its right to complain of the trial court’s alleged
    error by filing timely motions to designate several individuals and entities as
    responsible third parties and by obtaining rulings on its requests. See Tex. R. App.
    P. 33.1(a).
    We are also not persuaded by the Hugheses’ argument that all of their
    damages are attributable solely to Sun’s nondisclosures. The Legislature, through
    Chapter 33 of the Civil Practice and Remedies Code, enacted legislation that
    allows juries to apportion the responsibility for the damages between “each
    person’s causing or contributing to cause in any way the harm for which recovery
    of damages is sought[.]” Tex. Civ. Prac. & Rem. Code Ann. § 33.003(a) (emphasis
    added). With respect to the stucco installer, for example, the evidence before the
    jury would have allowed the jury to apportion some of the fault for repairing the
    stucco to the entity that installed the stucco on the home. The alleged problems
    with the installation, on this record, were clearly caused or contributed in some
    way to the damages the jury awarded for the cost of repairing the stucco on the
    home.
    31
    To demonstrate that the trial court erred in its rulings and that Sun was
    harmed by the rulings, Sun must show that it filed a timely motion to designate the
    others it sought to designate as responsible third parties, and that had a
    proportionate responsibility issue been submitted, the jury, in all likelihood, would
    have decided to apportion fifty percent or more of the responsibility for the
    damages awarded by the jury to the others. See Tex. Civ. Prac. & Rem. Code Ann.
    § 33.013(a), (b)(1) (providing that a defendant is jointly and severally liable for the
    claimant’s damages if “the percentage of responsibility attributed to the defendant
    with respect to a cause of action is greater than 50 percent”). To assess whether the
    trial court’s rulings harmed Sun, we first assess whether Sun was harmed by the
    trial court’s decision to deny Sun’s motion to designate the stucco installer,
    Shamrock Stucco, as a responsible third party.
    The record shows that Sun’s request to designate Shamrock Stucco as a
    responsible third party was timely. See Tex. Civ. Prac. & Rem. Code Ann. §
    33.004(a). When a defendant files a timely motion, Chapter 33 provides that “[a]
    court shall grant leave to designate the named person as a responsible third party
    unless another party files an objection to the motion for leave on or before the 15th
    day after the date the motion is served.” 
    Id. § 33.004(f)
    (West Supp. 2014). The
    Hugheses did not file a timely objection to Sun’s motion to designate Shamrock
    32
    Stucco as a responsible third party. We conclude the trial court erred by denying
    Sun’s timely request to designate Shamrock Stucco as a responsible third party.
    See id.; In re Smith, 
    366 S.W.3d 282
    , 287 (Tex. App.—Dallas 2012, orig.
    proceeding) (noting that “[u]nder [section 311.016(2)4 of] the Code Construction
    Act, the word ‘shall’ ‘imposes a duty’ unless context necessarily requires a
    different meaning or express statutory text provides otherwise”).
    We are also persuaded that, based on the evidence before the jury, the jury
    would likely have found the stucco installer responsible for the majority of the
    damages the jury awarded to correct the stucco problems on the Hugheses’ home.
    The jury awarded $647,613 in actual damages, but the jury’s award included
    expenses for repairing a number of items that are unrelated to the stucco on the
    home. Nonetheless, the evidence before the jury indicated that it would cost
    $407,232 to replace the stucco on the home. Given the evidence on the amount
    needed to repair the stucco, the amount the jury decided to award in actual
    damages, and the evidence in the record tending to show that the stucco installer
    bore significant responsibility for the problems that required repair, we hold that
    the trial court’s error likely resulted in a judgment against Sun that made it pay an
    amount for which it would not have been required to pay had the jury been asked
    4
    Tex. Gov’t Code Ann. § 311.016(2) (West 2013).
    33
    to answer an issue that apportioned the damages that stemmed from the stucco
    installation between Sun and Shamrock Stucco.
    We conclude the trial court’s decision to deny Sun’s request to designate
    Shamrock Stucco as a responsible third party was harmful. See Tex. R. App. P.
    44.1(a)(1). We further conclude that the error prevented Sun from properly
    presenting its case on appeal by depriving it of the ability to conclusively show that
    the jury would have answered an apportionment issue that would cast it in
    judgment for an amount that differs from the amount it must pay under judgment
    the trial court rendered. See 
    id. 44.1(a)(2); see
    also In re Broker Logistics, Ltd.,
    
    320 S.W.3d 402
    , 408 (Tex. App.—El Paso 2010, orig. proceeding); In re Arthur
    Anderson 
    LLP, 121 S.W.3d at 485-86
    .
    Sun argues that it is entitled to a retrial as to all parties and all issues due to
    the trial court’s error. Under the circumstances, we agree that the proper remedy is
    to remand the case for another trial. On retrial, given that a new trial date is
    required, we assume that a new docket control order will be entered, and that the
    new docket control order will designate and control the date Sun will be required
    to file its motions designating others as responsible third parties. The Hugheses
    will then have an opportunity to object to Sun’s motions. Because another trial is
    required, evaluating the trial court’s remaining rulings regarding the other
    34
    responsible third parties is unnecessary, given our conclusion that Sun was harmed
    by the trial court’s decision denying Sun’s request as to Shamrock Stucco.
    Therefore, we need not reach Sun’s remaining arguments in issue one,5 nor do we
    need to reach the other arguments that Sun has advanced in its other issues. See
    Tex. R. App. P. 47.1. Because the trial court erred in denying Sun’s request to
    designate Shamrock Stucco as a responsible third party and its error was harmful,
    the judgment is reversed, and the case is remanded on all issues for a new trial.6
    REVERSED AND REMANDED.
    ________________________________
    HOLLIS HORTON
    Justice
    Submitted on November 21, 2013
    Opinion Delivered September 25, 2014
    Before McKeithen, C.J., Kreger and Horton, JJ.
    5
    With respect to Sun’s requests to designate Sonrise Homes, Inc., Alpine
    Air, Inc., and Sullivan, Stevens, Henry, Oggero & Associates, Inc., as responsible
    third parties, the record shows that Sun’s requests were timely and that the
    Hugheses’ objections were untimely.
    6
    We also need not address the Hugheses’ cross-point challenging the trial
    court’s failure to submit a jury question, as the resolution of that issue would not
    result in any greater relief. See Tex. R. App. P. 47.1.
    35
    DISSENTING OPINION
    I would sustain issue two in part, and reverse the jury’s decision finding that
    Sun’s failure to disclose Rhondalyn Riley’s March 2008 Stucco Report was a
    producing cause of the Hugheses’ damages.
    A failure to disclose material information requires that the defendant knew
    the information, intentionally failed to bring it to the plaintiff’s attention, and
    withheld the information with the intent of inducing the consumer to engage in a
    transaction. Doe v. Boy Clubs of Greater Dallas, Inc., 
    907 S.W.2d 472
    , 479 (Tex.
    1995); Willowbrook Foods, Inc. v. Grinnell Corp., 
    147 S.W.3d 492
    , 507 (Tex.
    App.—San Antonio 2004, pet. denied). Information is material if a reasonable
    person would attach importance to the information and would be induced to act on
    it when determining his choice of actions. Citizens Nat’l Bank v. Allen Rae Invs.,
    Inc., 
    142 S.W.3d 459
    , 478-79 (Tex. App.—Fort Worth 2004, no pet.). The plaintiff
    must establish that the defendant’s action was a substantial factor that brought
    about the plaintiff’s injury and without which the injury would not have occurred.
    
    Doe, 907 S.W.2d at 481
    .
    At trial, Stuart Lapp admitted that the Hugheses did not see Riley’s March
    2008 stucco report before closing, but he testified that he did not know the report
    existed. However, Pamela Brand, a Sun representative, testified that she had told
    36
    Lapp about Riley’s March report. According to the record, Lapp subsequently told
    the Hugheses that he was unaware of an initial report. Lapp explained that Sun was
    not under contract with the Hugheses when Riley authored the March report and
    that once the parties reached an agreement, Sun furnished Riley’s more recent June
    report. Lapp told the Hugheses that, although he had not seen the June report, it did
    not identify problems with the stucco.
    Riley testified that the property was not functioning as intended in March
    and that, as a buyer, she would want to “know that the stucco or that the property is
    functioning as intended.” Lapp and Kirk Harrington testified that the June report
    reflected that items on the March report had been cured. John Cook, Sun’s
    president, testified that he saw no purpose for furnishing the March report. Larry
    and Susan both testified that they never would have closed had they received
    Riley’s March report. Lapp also admitted that “we wouldn’t be here[]” had the
    report been produced.
    Larry admitted that he was aware of moisture issues before closing and had
    concerns about moisture penetration during construction. According to the record,
    as early as 2007, Guffin Construction issued a report identifying the potential for
    future leaks and moisture intrusion, as well as the presence of mold and leaks. In
    January 2008, at the Hugheses’ request, the Hugheses’ realtor provided the
    37
    Hugheses with the name of a moisture detection service. In early March 2008,
    Genesis Restoration and Cleaning conducted thermal imaging, which revealed
    possible moisture, the potential for moisture damage in the near future, and the
    need for probing with a moisture meter to determine the moisture content. After
    Sun made repairs, Island Home Inspections identified problems such as water
    stains, possible water damage, inadequate insulation, substandard construction,
    leaks, excessive condensation, and damaged ductwork. According to the report,
    certain areas needed to be sealed to prevent moisture problems, the “A/C systems
    in the west attic [were] condensating at an abnormal rate[,]” and “[d]ucts in contact
    with each other [were] sweating sufficiently to drip on the flooring.” Before
    closing, Island Home Inspections issued a re-inspection report and found that an
    ongoing “excessive condensation problem” existed, that attempts to alleviate the
    problem did not appear to address the root cause, that the failure to remedy the
    problem could prove costly, and that the stucco was an ongoing project.
    The record demonstrates that, before closing and even without Riley’s
    March report, the Hugheses knew that the home had a history of moisture issues,
    that the repairs Sun made had not cured the moisture issues, that the moisture
    issues were serious and ongoing, and that failure to remedy the issues could prove
    costly. Because the Hugheses received information indicating that Sun’s repairs
    38
    were inadequate to remedy the moisture issues, we reject the Hugheses’ contention
    that Sun’s failure to disclose the report amounts to nondisclosure of the extent and
    nature of repairs. Sun could not be held liable for failing to disclose information
    about moisture issues when the Hugheses had actual notice of those issues. See
    Gill v. Boyd Distrib. Ctr., 
    64 S.W.3d 601
    , 604 (Tex. App.—Texarkana 2001, pet.
    denied). Viewing the evidence in the light most favorable to the jury’s verdict, the
    evidence presented at trial would not enable reasonable and fair-minded people to
    find that Sun’s failure to disclose Riley’s March 2008 stucco report was a
    producing cause of the Hugheses’ damages. 7 See 
    Doe, 907 S.W.2d at 481
    ; see also
    
    Gill, 64 S.W.3d at 604
    . For these reasons, I would sustain issue two in part and not
    reach Sun’s factual sufficiency challenge. See Tex. R. App. P. 47.1.
    ____________________________
    Steve McKeithen
    Chief Justice
    Dissent Delivered
    September 25, 2014
    7
    The Hugheses contend that Sun’s actions amount to more than mere non-
    disclosure and constitute active concealment. However, the record does not
    indicate that the Hugheses pleaded active concealment, or presented that issue to
    the jury.
    39