Stan Martin and Roma Martin v. Cottonwood Creek Construction, LLC ( 2018 )


Menu:
  •                                   IN THE
    TENTH COURT OF APPEALS
    No. 10-17-00005-CV
    STAN MARTIN AND ROMA MARTIN,
    Appellants
    v.
    COTTONWOOD CREEK CONSTRUCTION, LLC,
    Appellee
    From the 249th District Court
    Johnson County, Texas
    Trial Court No. C201300177
    OPINION
    Stan and Roma Martin contracted with Cottonwood Creek Construction, LLC to
    build the Martins a house. The estimated cost was over $880,000, and Cottonwood’s
    estimated fees were over $120,000.     When the Martins failed to pay two draws,
    Cottonwood suspended further work on the project. The Martins then retained another
    contractor to finish the house.
    Cottonwood sued the Martins for breach of contract.     The Martins filed a
    counterclaim against Cottonwood and a claim against a third party.1 After a jury trial,
    the trial court rendered judgment against the Martins on all the claims alleged by the
    parties.
    On appeal, the Martins raise five issues. Because we overrule each issue, the trial
    court’s judgment is affirmed.
    ANTICIPATORY REPUDIATION/LOST PROFITS
    In their first issue, the Martins assert the trial court erred in submitting Question 3
    and in refusing to submit their Requested Question 4 on what they believed to be
    Cottonwood’s claim of anticipatory repudiation. Specifically, the Martins assert that the
    inclusion of the ability to recover damages for lost profits in Question 3 without another
    question submitted about repudiation, was error. Alternatively, the Martins argue in
    their second issue that if there was no error in the wording of Question 3, nevertheless
    there was error in submitting it because there was no evidence to support the value
    damages found by the jury.
    Initially, we note that a request for submission is the method of preserving the
    right to complain of the omission of, or failure to submit, an issue or question which is
    relied on by the complaining party. Lyles v. Tex. Employers' Ins. Asso., 
    405 S.W.2d 725
    , 727
    (Tex. Civ. App.—Waco 1966, writ ref’d n.r.e.). An objection, on the other hand, is the
    proper method to preserve a complaint as to (1) an issue or question actually submitted,
    but claimed to be defective; or (2) the failure to submit, where the ground of recovery or
    1
    The Martins have no issue on appeal regarding the third-party claim.
    Martin v. Cottonwood Creek Construction, LLC                                               Page 2
    defense is relied on by the opposing party. 
    Id. See Religious
    of Sacred Heart v. Houston, 
    836 S.W.2d 606
    , 614 (Tex. 1992).
    At the charge conference, the Martins made the following objection to Question 3:
    Objection is made to Pattern Jury Charge Question No. 3 for the reason that
    it says, Cottonwood Creek may not recover – may recover not only for the
    value of the work actually done. There's been no evidence of the value of
    the work performed before this jury, and that assumes there was a value for
    work performed. Objection is further made that … for any profit
    Cottonwood Creek would have made had it been permitted to complete the
    contract. That assumes that the Martins repudiated the contract and
    stopped Cottonwood Creek from completing the contract. And that
    assumes a fact that has not been established, although pled by the Plaintiff.
    The Plaintiff has not submitted an issue for that. Therefore, I submit Issue
    No. 4, Question No. 4 for the jury on anticipatory repudiation.
    ***
    Objection is made to the lost profits, 12 percent fee for remaining contract
    balance. It assumes as an anticipatory repudiation by the Martins which
    requires an unconditional repudiation of which there's no evidence of and
    nevertheless assumes that before asking the jury to receive a lost profit.
    The Martins objected to the submission of Question 3 because, according to the Martins,
    the question was defective in that it included the ability to recover damages for lost
    profits which assumed repudiation by the Martins.
    The Martins’ request for submission of Requested Question 4 regarding
    anticipatory repudiation, however, did not preserve their complaint for appellate review
    because anticipatory repudiation was not an issue relied upon by the Martins, i.e. the
    complaining party. The Martins were required to object to the trial court’s failure to
    submit a question on anticipatory repudiation because it was, arguably, a ground of
    recovery relied on by Cottonwood. The Martins did not object. Thus, any complaint
    about the trial court’s failure to submit the Martins’ Requested Question 4 on anticipatory
    Martin v. Cottonwood Creek Construction, LLC                                           Page 3
    repudiation is not preserved; and we need not decide that part of the Martin’s first issue.2
    As to the lost profits portion of the Martins’ first issue, they complain that the trial
    court improperly included lost profits in Question 3. In substance, the Martins argue on
    appeal that the damages question improperly mixed breach of contract damages with
    damages only recoverable under quantum meruit. Question 3 provided, in relevant part:
    What amount of money, if paid in cash today, would fairly and reasonably
    compensate Cottonwood Creek for the Martins’ failure to comply with the
    Agreement?
    You are instructed that Cottonwood Creek may recover not only for the
    value of the work actually done, but also for any profit Cottonwood Creek
    would have made had it been permitted to complete the contract.
    Therefore, in answering Question No. 3, consider the following elements of
    damages, if any, and none other.
    ***
    Lost Profit (12% Fee) for Remaining Contract Balance: $65,514.35
    The Martins argue that an attempt to recover lost profits is an attempt to recover on the
    contract; but because the trial court instructed the jury that Cottonwood could recover
    for the “value” of the work done, this was a recovery in quantum meruit for which
    Cottonwood could not recover in addition to lost profits. The Martins contend the Court
    should have used the phrase “work done” rather than the phrase “value of the work
    done.”
    2
    Additionally, we note that the jury was asked whether the Martins failed to comply with the Agreement,
    which was Question 1, and answered, “Yes.” In Question 2, the jury was asked whether the failure to
    comply with the Agreement was excused by a prior material breach by Cottonwood, which the jury
    answered, “No.” Under the conditional submission of Question 3, the jury was then asked about damages.
    Thus, while the Martins complain about the failure to submit a question on anticipatory repudiation of a
    contract, which is one method of establishing a breach of contract, it is not the only type of breach. The
    Martins fail to address why Question 1 and Question 2 do not properly set up Question 3 for damages for
    their breach of contract as found by the jury.
    Martin v. Cottonwood Creek Construction, LLC                                                       Page 4
    But that was not the objection the Martins made to the trial court. There, the
    Martins only objected that there was “no evidence of the value of the work performed
    before this jury, and that assumes there was a value for work performed.” The Martins
    did not object that “value” corresponded to a recovery in quantum meruit which is
    inconsistent with a recovery for breach of contract. In order to preserve error for
    appellate review, a party's argument on appeal must comport with its argument in the
    trial court. See In re D.E.H., 
    301 S.W.3d 825
    , 829 (Tex. App.—Fort Worth 2009, pet.
    denied); Kershner v. State Bar of Tex., 
    879 S.W.2d 343
    , 347 (Tex. App.—Houston [14th Dist.]
    1994, writ denied). Because the objection asserted at trial does not comport with the
    complaint argued on appeal, the second portion of the Martins’ first issue that an
    improper measure of damages was submitted is not preserved. See TEX. R. APP. P. 33.1(a).
    Accordingly, the Martins’ first issue is overruled.
    VALUE
    Next, the Martins assert there is no evidence in the record to support the amounts
    awarded by the jury of the “value of the work actually done” in response to the first eight
    elements of damages in Question 3.
    As discussed above, the Martins equate the word “value” in Question 3 with
    “value” for a recovery in quantum meruit. Quantum meruit is an equitable theory of
    recovery which is based on an implied agreement to pay for benefits received. Heldenfels
    Bros., Inc. v. Corpus Christi, 
    832 S.W.2d 39
    , 41 (Tex. 1992). The correct measure of damages
    to recover on quantum meruit is the “reasonable value” of work performed and the
    materials furnished. M.J. Sheridan & Son Co. v. Seminole Pipeline Co., 
    731 S.W.2d 620
    , 
    625 Mart. v
    . Cottonwood Creek Construction, LLC                                          Page 5
    (Tex. App.—Houston [1st Dist.] 1987, no pet.). But Cottonwood did not sue on quantum
    meruit, it sued for breach of contract. Where a valid express contract covering the subject
    matter exists, there can be no quantum meruit; and thus, recovery on both is inconsistent.
    
    Id. at 624.
    Thus, that there may be no evidence of “value” as would be necessary for a
    recovery in quantum meruit is of no consequence. There was no need for Cottonwood
    to prove the type of “reasonable value” as required to recover in quantum meruit.3
    The Martins’ second issue is overruled.
    ABATEMENT
    In their third issue, the Martins contend the trial court erred in abating the
    underlying case pursuant to Chapter 27 of the Texas Property Code (Residential
    Construction Liability Act; the “RLCA”), refusing to entirely lift the abatement, and
    refusing to submit all of the Martins’ defect claims to the jury.4 We divide this issue into
    two parts: the abatement and the submission of the defect claims.
    Abatement under the RCLA
    In this part of the issue, we are called upon to determine, as an issue of first
    impression, the manner in which a counterclaim for construction defects affects the
    procedures for abatement and settlement under the RCLA. We review a trial court's
    3
    While perhaps not the best language to use, the instruction comes directly from a construction breach of
    contract case, Tower Contracting Co. v. Flores, 
    294 S.W.2d 266
    , 272-73 (Tex. Civ. App.—Galveston 1956)
    modified on other grounds, 
    302 S.W.2d 396
    (1957) (“the proper measure of damages, where the contractor sues
    on the contract, is … the contract value of the work actually done plus any profit the contractor would
    have made had he been permitted to complete the performance of his contract”).
    4
    The Martins only complain about the abatement of their counterclaims against Cottonwood. They do not
    complain about the abatement of their third-party claim. Thus, we will not discuss the propriety of the
    abatement of the third-party claim.
    Martin v. Cottonwood Creek Construction, LLC                                                        Page 6
    action on a plea in abatement for abuse of discretion. Dolenz v. Cont'l Nat'l Bank of Fort
    Worth, 
    620 S.W.2d 572
    , 575 (Tex. 1981); F&S Constr., Inc. v. Saidi, 
    131 S.W.3d 94
    , 98 (Tex.
    App.—San Antonio 2003, pet. denied).
    Generally, the RCLA requires a claimant to provide written notice to a contractor
    "specifying in reasonable detail the construction defects that are the subject of the
    complaint" at least 60 days before the claimant “initiates an action” against the contractor.
    TEX. PROP. CODE ANN. § 27.004(a) (West 2014). In addition to the notice requirement, the
    contractor must be given (1) a reasonable opportunity to inspect the property that is the
    subject of the complaint and (2) the opportunity to make a reasonable offer of settlement,
    including an agreement by the contractor to repair or have repaired any construction
    defect described by the claimant. See 
    id. The notice
    provision activates a timetable for an
    inspection of the property and the offer of settlement which, if reasonable, affects the
    claimant's potential recovery under the Act. See id.; In re Anderson Constr. Co., 
    338 S.W.3d 190
    , 192 (Tex. App.—Beaumont 2011, orig. proceeding).
    A trial court is required to abate an action if, after a hearing, the court finds the
    claimant failed to (1) provide the required notice, (2) give the contractor a reasonable
    opportunity to inspect the property, or (3) follow the procedures specified in 27.004(b)
    (regarding the offer of settlement and its related procedures). See TEX. PROP. CODE ANN.
    § 27.004(a), (d) (West 2014). An action is automatically abated without a court order
    beginning the eleventh day after the date a verified motion to abate is filed if the motion
    is not controverted by an affidavit filed by the claimant. See 
    id. (d). Cottonwood
    filed a verified motion to abate the Martins’ counterclaim alleging
    Martin v. Cottonwood Creek Construction, LLC                                           Page 7
    they “failed to comply with the notice, inspection and settlement procedures of the
    RCLA.” The Martins did not file a controverting affidavit. After a hearing, the trial court
    ordered the counterclaim abated because the Martins failed to file a controverting
    affidavit but also noted that the counterclaim had been automatically abated because of
    the same failure.
    The Martins, however, were not required to controvert the motion to abate with
    an affidavit. The Martins did not “initiate an action” as provided by subsection (a). See
    TEX. PROP. CODE ANN. § 27.004(a) (West 2014). They filed a counterclaim which is
    governed by subsection (c). 
    Id. (c). Under
    subsection (c), notice is not required, and the
    timetables for the opportunity to inspect and the offer of settlement are recalculated.5 
    Id. Further, the
    abatement procedure in subsection (d) does not apply to actions governed
    by subsection (c).
    Subsection (d) provides, in relevant part:
    The court … shall abate an action governed by this chapter if Subsection (c)
    does not apply and the court … after a hearing, finds that the contractor is
    entitled to abatement because the claimant failed to…provide the notice or
    failed to give the contractor a reasonable opportunity to inspect the
    property as required by Subsection (a), or failed to follow the procedures
    specified by Subsection (b). An action is automatically abated without the
    order of the court … beginning on the 11th day after the date a motion to
    abate is filed if the motion: … (2) is not controverted by an affidavit filed
    by the claimant before the 11th day after the date on which the motion to
    abate is filed.
    TEX. PROP. CODE ANN. § 27.004(d) (West 2014) (emphasis added).                            Thus, because
    5
    The pleadings of the counterclaim act as notice and are required to “specify in reasonable detail each
    construction defect that is the subject of the complaint.” 
    Id. (c). Cottonwood
    did not, and does not, contend
    the Martins failed to reasonably detail each of the construction defects in their counterclaim.
    Martin v. Cottonwood Creek Construction, LLC                                                          Page 8
    subsection (c) applies to the Martins’ counterclaim, subsection (d) does not.
    Cottonwood disputes this interpretation of subsection (d).       Relying on In re
    Anderson Constr. Co., 
    338 S.W.3d 190
    (Tex. App.—Beaumont 2011, orig. proceeding),
    Cottonwood contends that while the Martins were excused from providing notice under
    subsection (c), they were not excused from giving Cottonwood an opportunity to inspect
    the alleged defects or offer a settlement. Thus, its argument continues, the Martins were
    still subject to the automatic abatement provision of subsection (d) because they did not
    file a controverting affidavit.
    However, Cottonwood’s reliance on In re Anderson is misplaced. In re Anderson
    was not a counterclaim case and cannot be used as support for the procedure to be used
    when defects are raised in a counterclaim; i.e. when subsection (c) applies.
    Further, in construing a statute, words and phrases are read in context and
    construed according to the rules of grammar and common usage. TEX. GOV'T CODE ANN.
    § 311.011(a) (West 2013). Initially, we note that subsection (d) is one full paragraph
    composed of two sentences. In the first sentence, an abatement by court order is limited
    to actions where “Subsection (c) does not apply.” The very next sentence discusses an
    automatic abatement. There is no need to repeat the phrase “if Subsection (c) does not
    apply” because a basic rule of thumb in paragraph construction is to keep one idea to one
    paragraph.           See    Purdue       Online   Writing     Lab,     On       Paragraphs,
    https://owl.english.purdue.edu/owl/resource/606/01/.          Our interpretation might
    have been different had the second sentence been in a new paragraph. See 
    id. (“If you
    begin to transition into a new idea, it belongs in a new paragraph.”). It was not. Thus,
    Martin v. Cottonwood Creek Construction, LLC                                         Page 9
    reading the words and phrases of the statute in context and construing them according
    to the rules of grammar and common usage as required, we find the statute is clear: the
    entirety of subsection (d) does not apply when construction defects are raised in a
    counterclaim.
    Subsection (d) was the only basis upon which Cottonwood sought an abatement.6
    Thus, the trial court abused its discretion in issuing an abatement order because the
    subsection (d) abatement procedure did not apply to the Martins’ counterclaim. For the
    same reason, the trial court also abused its discretion in finding that the Martins’
    counterclaim was automatically abated and in refusing to lift the abatement in its entirety.
    Failure to Submit All Claims
    We next determine what, if any, effect the abatement had on the presentation of
    the Martins’ counterclaim to the jury. Rule 278 of the Texas Rules of Civil Procedure
    requires the submission of questions to the jury raised by the written pleadings and the
    evidence. TEX. R. CIV. P. 278; Grohman v. Kahlig, 
    318 S.W.3d 882
    , 888 (Tex. 2010); Elbaor v.
    Smith, 
    845 S.W.2d 240
    , 243 (Tex. 1992). A court may refuse to submit a requested jury
    question if no evidence exists to warrant its submission. 
    Grohman, 318 S.W.3d at 888
    ;
    
    Elbaor, 845 S.W.2d at 243
    . A judgment will not be reversed for charge error, however,
    unless the error was harmful because it probably caused the rendition of an improper
    verdict or probably prevented the petitioner from properly presenting the case to the
    appellate court. Columbia Rio Grande Healthcare, L.P. v. Hawley, 
    284 S.W.3d 851
    , 856 (Tex.
    6
    Subchapter (c) has its own provisions for abatement which do not include automatic abatement.
    Martin v. Cottonwood Creek Construction, LLC                                                        Page 10
    2009); see TEX. R. APP. P. 44.1.
    According to the pleadings, the Martins alleged that the retaining wall was
    installed improperly, the concrete slab failed to match with the wooden floor, the concrete
    slab in the garage tilted backwards and water puddled in the garage, the soffit over the
    front door was incorrectly placed, the bay window was built without a ledge, and several
    windows were damaged or would not open or shut. The Martins requested a question
    to be submitted to the jury on all of those claims except the claim regarding the soffit.7
    The request was refused. Instead, the trial court submitted Question 8 which identified
    three general types of claimed construction defects. Those three types were: 1) the north
    retaining wall; 2) the foundation; and 3) the installation of the windows.
    Assuming without deciding evidence supported the Martins’ requested jury
    question, we find the trial court did not err because the jury question as submitted did
    not differ in substance from the Martins’ requested jury question. First, the claim
    regarding the retaining wall was clearly submitted in Question 8. Second, the parties,
    witnesses, and counsel used the word “foundation” interchangeably with the word
    “slab.” Thus, substantively, the claims regarding the slab, the slab’s match-up with the
    wooden floor, and the slope in the garage floor were submitted in Question 8 under the
    general label of “foundation.” Third, the majority of the testimony about the windows
    dealt with the installation, or lack thereof, of a brick ledge for the bay window while a
    7
    Specifically, the Martins’ proposed question listed the alleged defects as “the retaining wall,” “the brick
    ledge in the bay window,” “the concrete slab,” “the concrete slab matched the wooden floor,” “the garage
    floor,” and “windows.”
    Martin v. Cottonwood Creek Construction, LLC                                                         Page 11
    minority of the testimony dealt with the installation of windows that were cracked or
    unable to be opened. Thus, the window claims were substantively submitted in Question
    8 under the general category of “installation of windows.”
    A judgment shall not be reversed because of the failure to submit other and
    various phases or different shades of the same question. TEX. R. CIV. P. 278. Because
    Question 8 does not differ in substance from the Martins' requested question, we cannot
    say the trial court’s failure to submit the Martins’ defect claims in the form of the question
    requested by the Martins was error. See 
    id. The Martins’
    third issue is overruled.
    GOOD AND WORKMANLIKE MANNER
    We next address whether the trial court erred in refusing to submit the Martins’
    Requested Question 8. The Martins contend that Question 8 as submitted to the jury—
    “Did Cottonwood Creek fail to perform its work in a good and workmanlike manner?”—
    was incomplete. The Martins’ Requested Question 8 asked whether Cottonwood “failed
    to design and build the house pursuant to the plans in a good and workmanlike manner[.]”
    (Emphasis added). Submission of the Requested Question 8 was refused by the trial
    court.
    The Martins’ pleadings defined “good and workmanlike manner” in terms of
    “work” and “buil[d].” The term “design” was not used. Further, the Martins alleged in
    their pleadings that the contract between the parties defined “good and workmanlike
    manner” in terms of “work” rather than “design and build.”               Thus, the Martin’s
    Requested Question 8 was not raised by the written pleadings, and the trial court did not
    Martin v. Cottonwood Creek Construction, LLC                                           Page 12
    err in refusing to submit it. See TEX. R. CIV. P. 278; Grohman v. Kahlig, 
    318 S.W.3d 882
    , 888
    (Tex. 2010); Elbaor v. Smith, 
    845 S.W.2d 240
    , 243 (Tex. 1992).8
    The Martins’ fourth issue is overruled.
    ATTORNEY’S FEES
    In their fifth, and final, issue, the Martins request that, if this Court reverses the
    damages judgment, we also reverse the award of attorney’s fees. Since we did not reverse
    the damages judgment, we do not reverse the attorney’s fees award.
    The Martins’ fifth issue is overruled.
    CONCLUSION
    Having overruled each issue raised on appeal, we affirm the trial court’s judgment.
    TOM GRAY
    Chief Justice
    Before Chief Justice Gray,
    Justice Davis, and
    Justice Scoggins
    Affirmed
    Opinion delivered and filed October 3, 2018
    [CV06]
    8
    Additionally, the question as requested by the Martins is nothing more than a different shade of the
    question actually submitted and thus, was not error. See TEX. R. CIV. P. 278.
    Martin v. Cottonwood Creek Construction, LLC                                                 Page 13