Gulf Coast Fiber Services, LLC v. BMF Drilling, LLC ( 2022 )


Menu:
  •                                 In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    __________________
    NO. 09-20-00037-CV
    __________________
    GULF COAST FIBER SERVICES, LLC, Appellant
    V.
    BMF DRILLING, LLC, Appellee
    __________________________________________________________________
    On Appeal from the 410th District Court
    Montgomery County, Texas
    Trial Cause No. 18-09-12951-CV
    __________________________________________________________________
    MEMORANDUM OPINION
    This appeal arose from a lawsuit filed by BMF Drilling, LLC, (BMF)
    to collect a debt over the work it performed on a construction project
    where BMF buried around 10,000 linear feet of 2 inch and smaller
    conduit at the defendant, Gulf Coast Fiber Services, LLC’s, request. Gulf
    Coast responded to the suit by filing an answer that included several
    affirmative defenses and a counterclaim, which alleged that BMF is the
    party who first breached the parties’ written agreement.
    1
    The parties tried the case before a jury, which found: (1) Gulf Coast
    “fail[ed] to comply with the Agreement”; (2) “BMF fail[ed] to comply with
    the Agreement”; (3) BMF “failed to comply with the Agreement first”; (4)
    BMF’s “failure to comply was not excused”; and (5) BMF “substantially
    perform[ed] all of its obligations in the Agreement.” As to damages, the
    jury awarded BMF $17,409 in compensation for the work BMF performed
    based on its finding that BMF substantially performed its obligations
    under the Agreement. Additionally, the jury found the attorneys for each
    party was entitled to recover a reasonable amount on that party’s
    respective claim seeking to recover for attorney’s fees. 1
    When the jury announced its verdict, neither party pointed out to
    the trial court the conflict that existed between the jury’s findings on the
    breach of contract questions and the substantial performance questions
    before the trial court discharged the jury from its duties to the court. That
    said, after the trial court discharged the jury, Gulf Coast filed a motion
    for JNOV, which extended the time Gulf Coast had to file its notice that
    it wanted to appeal. Gulf Coast later filed a timely notice of appeal.
    1We   rounded all amounts referenced in the opinion to the nearest
    dollar.
    2
    In three appellate issues, Gulf Coast argues the trial court erred in
    rendering judgment that favors BMF. First, Gulf Coast argues the trial
    court erred in relying on the jury’s finding of substantial performance in
    its judgment, findings based on jury questions seven and eight, when in
    other findings the jury found BMF breached the Agreement first, that its
    breach was material, and that BMF’s breach was unexcused. Second,
    Gulf Coast argues the evidence is legally and factually insufficient to
    support the jury’s award of $17,409 in damages. According to Gulf Coast,
    BMF’s evidence is insufficient because it failed to introduce evidence
    establishing what the reasonable costs were to repair and correct the
    errors the jury determined existed with the work it completed at Gulf
    Coast’s request. Third, Gulf Coast argues the trial court erred in
    awarding BMF attorney’s fees for two reasons, first because BMF was
    not the prevailing party in the trial given the jury’s answers to the
    questions that BMF breached the Agreement and that its breach was
    unexcused, and second because under the terms of the written
    Agreement, BMF’s waived its right to sue Gulf Coast on a claim seeking
    to recover attorney’s fees.
    3
    As to Gulf Coast’s argument that BMF cannot recover based on the
    jury’s answers to the questions the trial court submitted to the jury, we
    conclude Gulf Coast failed to preserve its complaint about the conflict
    between the jury’s answer to the breach of contract issues and the
    substantial performance issue for the purpose of having the argument
    reviewed in its appeal. As to remaining arguments Gulf Coast relies on
    to support the issues it raises in the appeal, we conclude its arguments
    lack merit. For the reasons explained below, we conclude the trial court’s
    judgment should be affirmed.
    Background
    Gulf Coast—a company that bores horizontal holes under the
    ground—was hired by a commercial telecommunications company to
    place a fiber-optic cable within an easement and underground. Gulf Coast
    subcontracted some of its work to BMF, a company that specializes in
    horizontal-directional drilling. While Gulf Coast and BMF signed a
    written agreement (Agreement), the Agreement is incomplete as it
    reflects other documents are incorporated in the Agreement by reference.
    Based on the Agreement’s terms, the Agreement includes the “Prime
    Contract between the Owner and Contractor as well as, and including,
    4
    any and all other documents, drawings and specifications enumerated
    therein[.]” But even though the Agreement references several other
    documents, none of the documents referenced in the Agreement were
    admitted into evidence during the trial. For instance, the evidence the
    jury considered did not include the Prime Contract, the drawings, or the
    specifications, evidence that possibly might have identified and detailed
    the requirements that Gulf Coast (and its subcontractors) were required
    to follow in performing the work. These details might have included
    details like how deep the horizontally drilled holes had to be drilled,
    whether the depths of the holes were required to be uniform throughout
    their length, or whether the conduit, after it was placed inside the holes,
    had to be protected from mud (or if infiltrated with mud, cleaned out). As
    to these types of details, Gulf Coast’s Agreement is also silent. Instead,
    BMF’s Agreement with Gulf Coast apparently contemplated the details
    would be specified in written authorizations Gulf Coast provided BMF to
    perform the work Gulf Coast subcontracted out. As to the written
    authorizations, the Agreement states: “Upon execution of this
    Agreement, [Gulf Coast] will, from time to time, issue to [BMF] written
    authorizations to proceed with specific work, at a certain price and upon
    5
    such other terms and conditions [as] may be set forth in a purchase order
    (hereinafter ‘Purchase Order’).” (emphasis added).
    But in the trial, Gulf Coast never introduced any of the written
    authorizations into evidence. Nor did it introduce any of the other
    extrinsic documents that we mentioned before that might have specified
    details pertinent to BMF’s work, such as (1) how deep it was required to
    drill the horizontally drilled holes; (2) whether the holes were to be drilled
    at uniform depths; and (3) whether BMF had to protect the conduit from
    being infiltrated by mud or to clean the mud out should mud enter the
    conduit on being inserted into the holes.
    BMF worked for Gulf Coast for around four months before Gulf
    Coast terminated BMF from the fiber-optic cable project, ending the work
    BMF performed for Gulf Coast as of early July 2018. When BMF did
    perform its work on the project, Gulf Coast’s onsite supervisor, Ryan
    Pemberton, supervised BMF’s work. Pemberton, however, did not testify
    in the trial. Instead, Gulf Coast presented its case through one of its
    owners and its Director of Operations, Earl Epps.
    According to Epps, shortly after BMF started the project, Gulf
    Coast began complaining that it was finding mud in conduit that BMF
    6
    had laid in the horizontally drilled holes that it drilled. And according to
    Epps, about a month after BMF began its work, Gulf Coast (apparently
    though Pemberton) began to complain the conduit that BMF had inserted
    into the holes needed to be deeper and that some of the conduit had
    become infiltrated with mud. Lee Winters, the owner of BMF,
    acknowledged that BMF had on about five occasions borrowed Gulf
    Coast’s air compressor to correct problems that Gulf Coast identified
    regarding mud it found in conduit that BMF inserted in holes. However,
    when Winters was asked how deep the Agreement required the fiber-
    optic cable to be buried, he testified: “There’s no industry standard for
    depth.” And when asked whether Epps told BMF the conduit was to be
    buried at least three feet deep, Winters testified: “I don’t recall that. It -
    - there is no contract document stating that.” Winters also said that when
    the job started, Pemberton didn’t tell him the holes needed to be drilled
    to at least a three-foot depth.
    Over the four months BMF worked on the project, it submitted
    eight invoices to Gulf Coast, which total $90,950 for its work. Of these,
    Gulf Coast paid the first five invoices it received in full. But even though
    Gulf coast paid the first five invoices, Earl Epps testified Gulf Coast did
    7
    so only because Gulf Coast “believe[d] that everything had been properly
    done.” He claimed that after Gulf Coast paid the invoices, it discovered
    the deficiencies with BMF’s work. According to Epps, after Gulf Coast
    terminated BMF, it used its own employees to correct some of BMF’s
    work and hired outside contractors to correct what Epps described as
    other work BMF performed that failed to comply with the specifications
    in the Agreement Gulf Coast had with BMF. So while it’s undisputed that
    Gulf Coast paid BMF $48,357 for its work, it’s also undisputed that Gulf
    Coast refused to pay BMF for the balance of the work it completed in the
    three invoices in evidence that represent an additional $42,592 of work if
    payable under the Agreement based on Winters’ testimony about the
    work BMF completed on the fiber-optic cable project before it was
    terminated from all Gulf Coast’s projects in July 2018.
    During the trial, Epps described how he determined that Gulf Coast
    owed BMF nothing more for the work BMF performed under the invoices
    Gulf Coast refused to pay. According to Epps, of the total BMF charged
    for its work, $90,950, BMF performed only about 53 percent of the work
    properly—an amount that equaled exactly what Gulf Coast had already
    paid BMF, $48,357. Since Gulf Coast determined that it paid BMF what
    8
    it owed, Epps decided Gulf Coast owed BMF nothing more when, in July
    2018, he notified BMF of Gulf Coast’s decision to terminate the parties’
    Agreement.
    In September 2018, BMF sued Gulf Coast alleging it owed BMF the
    remaining $42,592 that it had not paid BMF for its work. In its petition,
    BMF alleged that Gulf Coast failed to pay the last three of its eight
    invoices on the fiber-optic project. In BMF’s live pleading, which BMF
    filed months before the trial, BMF alleged that if it was not entitled to
    the full amount owed under the Agreement with Gulf Coast, it was
    entitled to be paid what it billed less the cost to correct any non-
    conforming work since it substantially performed the work Gulf Coast
    requested of it on the project. Specifically, in its live petition, BMF alleged
    that because it substantially performed its obligations under its
    Agreement with Gulf Coast it was “entitled to full payment of the
    contract sum min[us] the cost of completion or remediation.”
    In Gulf Coast’s response to BMF’s live pleading, Gulf Coast
    asserted a general denial and a laundry list of affirmative defenses, but
    most of its defenses are irrelevant to the issues Gulf Coast has raised in
    its appeal. That said, in its live pleading, Gulf Coast asserted BMF’s
    9
    “prior material breach of the contract for construction services” excused
    its obligation to pay BMF any additional consideration for any work it
    completed under the Agreement.
    Turning to Gulf Coast’s arguments supporting it claim of excuse,
    we observe that at two different points in the trial, Gulf Coast failed to
    preserve the arguments it presents in its brief for the purpose of its
    appeal. First, when the parties objected to the charge, Gulf Coast’s
    attorney failed to object to the predicate instruction that accompanied
    BMF’s substantial performance question (Question 7). The predicate to
    Question 7 instructed the jury that if it answered “No” to the question
    that asked the jury to decide if BMF’s failure to comply with the
    Agreement (Question 5) was excused, to answer Question 7. 2 Second,
    when the jury returned with its verdict, Gulf Coast failed to point out
    that a fatal conflict existed between the jury’s answers to the questions
    on the breach of contract questions (Questions 2, 3, and 5) and the jury’s
    answer to the substantial performance question (Question 7). Even more,
    2Stated another way, the trial court conditioned the jury’s answer
    to Question 7, the substantial performance question, on a “No” answer to
    Question 5, the question asking whether BMF’s failure to comply with
    the Agreement was excused.
    10
    Gulf Coast failed to ask the trial court to instruct the jury further on
    answering these four issues and to send the jury back to deliberate
    further on its verdict.
    Several weeks later (but after the trial court had discharged the
    jury) Gulf Coast filed a Motion for JNOV. In the motion, Gulf Coast asked
    the trial court to disregard the jury’s answer to the substantial
    performance question. In the Motion for JNOV, Gulf Coast argued the
    jury’s answer to the substantial performance question was immaterial.
    That was so, it argued, because the jury found that BMF breached the
    contract first, that BMF’s breach was material, and that its breach was
    unexcused. Gulf Coast argued the trial court should consider these as the
    controlling findings and disregard the jury’s other finding inconstant
    with these findings where the jury found BMF substantially performed
    its obligations under the parties’ Agreement. Additionally, Gulf Coast
    argued that BMF failed to meet its burden to prove what the reasonable
    costs were to remedy “the defects due to BMF’s errors and omissions.”
    Finally, Gulf Coast’s Motion for JNOV asked the trial court to disregard
    the jury’s findings awarding BMF attorney’s fees for three reasons: first,
    according to Gulf Coast, BMF did not prevail on its breach of contract
    11
    claim; second, according to Gulf Coast, the Agreement allowed Gulf Coast
    to “cancel and terminate the Agreement, without liability to [Gulf
    Coast,]” a provision that Gulf Coast interprets as a waiver of BMF’s right
    to recover attorney’s fees; and third, Gulf Coast claimed a party cannot
    collect attorney’s fees when recovering on a claim of substantial
    performance under Texas law.
    The trial court denied Gulf Coast’s motion and signed a judgment
    awarding BMF $17,409. The trial court also awarded BMF $15,000 in
    attorney’s fees, plus conditional awards of additional attorney’s fees the
    trial court made contingent on BMF’s success if Gulf Coast pursued but
    then lost in future appeals. 3 After the trial court signed the judgment,
    Gulf Coast filed a post-judgment motion seeking to modify the judgment
    the trial court signed. In the post-judgment motion, Gulf Coast argued
    that a conflict exists between the jury’s findings on a cluster of issues that
    addressed BMF’s breach of the Agreement (Questions 2, 3, and 5) and the
    substantial performance question (Question 7). In its post-judgment
    3While the judgment awards attorney’s fees to Gulf Coast, BMF has
    not challenged that award in the appeal. As to the award of attorney’s
    fees, we express no opinion about whether Gulf Coast was (or was not)
    entitled to an attorney’s fees award.
    12
    motion, Gulf Coast noted that “it is factually and legally impossible that
    [BMF] substantially performed [under the Agreement] given the [jury’s]
    findings on Question Nos. 1-5.” In the same motion, Gulf Coast re-urged
    the arguments that it raised earlier in its Motion for JNOV, claiming
    BMF was not entitled to recover attorney’s fees.
    Analysis
    Substantial Performance
    In Gulf Coast’s first issue, it argues that because the jury found
    BMF failed to comply with material terms of the Agreement first and that
    its failure to comply with the Agreement was unexcused, the trial court
    should have disregarded the jury’s finding that BMF substantially
    performed the Agreement when rendering judgment, which it concludes
    should have caused the trial court to render judgment in favor of Gulf
    Coast, not BMF.
    While the trial court could have chosen to resolve the conflict in the
    jury’s findings in a manner that favored Gulf Coast, it did not. And Gulf
    Coast’s failure to recognize the conflict between the jury’s findings on the
    issues until after the trial court discharged the jury prevents this Court
    from correcting the conflict on appeal. Had Gulf Coast brought the
    13
    conflict in the findings to the trial court’s attention promptly when the
    issue could have been addressed by the jury—meaning before the jury
    was discharged—the trial court could have given the jury additional
    instructions to guide its deliberations, and perhaps the jury with the
    additional instructions could have answered the issues in a way that
    would have been consistent. Then, the jury could have resolved the
    conflict as the finder of fact. 4 But since Gulf Coast failed to point the
    conflict in the findings out when it had an opportunity to correct the
    problem, its sole remedy now is to prove the record conclusively
    established that BMF breached a material term of the contract, that BMF
    breached the contract first, and that BMF’s breach was unexcused.
    Gulf Coast does raise those arguments in its appeal, noting that
    under Texas law, “a party to a contract who is himself in default cannot
    maintain a suit for its breach.” 5 But the fact the jury return findings in
    Gulf Coast favor does not conclusively establish the elements required to
    4See  Los Compadres Pescadores, L.L.C. v. Valdez, 
    622 S.W.3d 771
    ,
    787-88 (Tex. 2021) (“Because Los Compadres did not object to the jury’s
    allegedly conflicting answers before the trial court discharged the jury, it
    cannot now complain that the conflicting answers undermine the
    judgment based on the jury’s verdict.”).
    5Dobbins v. Redden, 
    785 S.W.2d 377
    , 378 (Tex. 1990) (per curiam).
    14
    prove BMF defaulted on its obligations given that the same jury found
    BMF substantially performed its contractual obligations except for minor
    variances to Gulf Coast. When the case involves a construction contract,
    as is the case here, a contractor who hasn’t fulfilled the obligations of his
    contract may still “sue on the contract, but his recovery is decreased by
    the cost of remedying those defects for which he is responsible.” 6 The trial
    court relied on that theory in rendering the judgment in BMF’s favor that
    Gulf Coast complains about in its appeal.
    In part, Gulf Coast argues the findings the jury returned on the
    cluster of issues tied to BMF’s breach of the Agreement (Questions 2, 3,
    and 5) are in fatal conflict with the jury’s answer to the substantial
    performance question, Question 7. We agree with Gulf Coast that the
    findings on the cluster of breach of contract issues that favor Gulf Coast
    and the substantial performance issue that favors BMF fatally conflict.
    But Gulf Coast failed to point out the conflict promptly before the jury
    was discharged when it was before the trial court. It’s settled that a
    party’s failure to point out a conflict in a jury’s findings to the trial court
    6Vance v. My Apartment Steak House of San Antonio, Inc., 
    677 S.W.2d 480
    , 482 (Tex. 1984).
    15
    in a timely manner prevents the party from complaining later “that the
    conflicting answers undermine the judgment based on the jury’s
    verdict.” 7 To the extent Gulf Coast complains that findings the jury
    returned on the breach of contract issues and the substantial
    performance issue are in conflict, we hold it waived its complaint by
    failing to point the problem out to the trial court in a timely manner.
    Legal and Factual Sufficiency
    Although Gulf Coast included some arguments complaining about
    the insufficiency of the evidence with the arguments it included with its
    first issue, for convenience we will address all legal and factual
    sufficiency arguments in discussing Gulf Coast’s second issue. We
    address Gulf Coast’s legal sufficiency arguments first since Gulf Coast
    preserved those arguments by filing a Motion for JNOV.
    On appeal, Gulf Coast argues the evidence admitted in the trial
    conclusively establishes that BMF breached the material terms of the
    Agreement first and without excuse. We disagree. At trial, Gulf Coast
    argued BMF breached material terms of the parties’ Agreement by failing
    to bury the conduit to specified depths, failing to provide Gulf Coast with
    7Valdez,   622 S.W.3d at 787-88; Tex. R. App. P. 33.1(a).
    16
    the location of the conduit after burying it, and by failing to keep the
    buried conduit clear of debris. But we find nothing in the four corners of
    the Agreement that specifies how deep BMF was to bury the conduit,
    whether BMF was to keep the conduit free of mud, or whether BMF was
    to clean the mud from the conduit after inserting it into a hole. And we
    find no other written documents, such as purchase orders or written
    authorizations that required it to do so either. And while their possibly
    might have been specifications like the ones Epps testified about in some
    of the documents referenced in the Agreement, Epps never identified
    what document the specifications were in, nor did Gulf Coast’s attorneys
    bother to introduce the written specifications that controlled BMF’s work
    into evidence during the trial.
    The Agreement references several documents as “Subcontract
    Documents” that possibly contained specifications requiring Gulf Coast’s
    subcontractors to bury conduit to specified depths and likely contained a
    number of other requirements relevant to BMF’s work. The Agreement
    specified the Subcontract Documents “consist of:
    (1) this Agreement;
    (2) the Prime Contract;
    (3) Extra Work Orders generated subsequent to the execution of
    the Agreement;
    17
    (4) Purchase Orders as may be generated from time to time; and
    (5) Modifications to this subcontract issued after execution of this
    Agreement.”
    In legal terms, the Agreement BMF signed with Gulf Coast is
    integrated only as to the matters the Agreement addressed. 8 That said,
    the Agreement’s terms don’t address the depth of the conduit, whether
    BMF was required to prevent debris from entering the conduit after
    running the conduit into the horizontally drilled holes, or whether BMF
    was responsible for paying to clean out the mud from contaminated lines
    after running the conduit into a hole. And the evidence the parties
    provided the jury did not include the written work authorizations that
    Gulf Coast’s Agreement contemplated, any purchase orders, or other
    documents specifying the details like those Epps described when
    explaining what he expected of BMF. But given the fact the Agreement
    does not specify the depth of the holes or the details relevant to the issues
    in dispute together with the failure of the parties to develop a record that
    includes the documents referenced in the Agreement, we cannot now say
    8See    West v. Quintanilla, 
    573 S.W.3d 237
    , 244 (Tex. 2019)
    (explaining that although a partially integrated contract is “complete and
    final as to its subject matter, it does not purport to address or supersede
    agreements related to other matters”).
    18
    that Epps’ testimony conclusively established BMF’s failure to bury the
    conduit to the depths Epps described, to keep the conduit clean, and to
    clean the mud out of the conduit were material breaches of the terms of
    the parties’ Agreement as a matter of law.
    Next, Gulf Coast argues the evidence is legally insufficient to
    support the jury’s finding that BMF substantially performed its
    Agreement with Gulf Coast and is legally insufficient to support the jury
    award of $17,409 in damages based on the jury’s finding of substantial
    performance. The test for legal sufficiency is “whether the evidence at
    trial would enable reasonable and fair-minded people to reach the verdict
    under review.”9 In reviewing for legal sufficiency, we “must credit
    favorable evidence if reasonable jurors could, and disregard contrary
    evidence unless reasonable jurors could not.” 10
    Here, there were no objections to the charge over the definitions
    accompanying the question on substantial performance (Question 7). The
    instruction tied to Question 7 advised the jury that
    [t]he term substantial performance, as used in the charge,
    means that there has been no willful departure from the
    terms of the agreement and no omission in essential points
    9Del Lago Partners, Inc. v. Smith, 
    307 S.W.3d 762
    , 770 (Tex. 2010).
    10City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex. 2005).
    19
    and that the agreement has been honestly and faithfully
    performed in its material and substantial particulars and the
    only variance from the strict and literal performance consists
    of technical or unimportant omissions or details.
    Without an objection to a definition in a charge, we measure the evidence
    admitted in the trial against the charge and decide whether legally
    sufficient evidence supports the jury’s finding on the issue the appellant
    is challenging in the appeal. 11
    At trial, the jury heard Lee Winters, BMF’s owner, and Earl Epps,
    Gulf Coast’s Director of Operations, address their respective expectations
    about BMF’s work under the Agreement. The Agreement required Gulf
    Coast to pay BMF a unit price for each linear foot of conduit BMF buried
    underground. Winters testified that Gulf Coast gave BMF project sheets,
    sheets in which Gulf Coast designated where the conduit was to be
    buried. While the project sheets are in evidence, they lack specifications
    identifying how deep the conduit had to be buried, they do not specify
    whether BMF is to clean the conduit or to protect its worksite to prevent
    the conduit from being contaminated with mud, and we find nothing in
    11See   St. Joseph Hosp. v. Wolff, 
    94 S.W.3d 513
    , 530 (Tex. 2002).
    20
    the project sheets requiring BMF to provide Gulf Coast with as-built
    drawings after it placed the conduit underground.
    When Epps testified, he didn’t dispute that BMF buried conduit in
    the locations specified in the project sheets; instead, he said BMF didn’t
    bury the conduit based on the standards required under the parties’
    Agreement. But as already noted, the Agreement is not fully integrated—
    it doesn’t specify the depths for the lines, whether BMF had to protect
    the conduit during its work, or whether BMF was to provide Gulf Coast
    with as-built drawings after completing its work.
    Since the terms Epps claims the parties agreed to are not among
    the writings in evidence, we must disregard Epps’ testimony criticizing
    BMF’s work in reviewing the evidence relevant to the jury’s finding that
    BMF substantially performed its obligations under the Agreement. And
    when the evidence favoring the jury’s finding of substantial performance
    is viewed in the light that favors the judgment, the finding Gulf Coast
    seeks to overturn is reasonable given the jury’s discretion to determine
    what the Agreement required BMF to do and what constituted a material
    breach under a partially integrated contract that involved a project
    where BMF buried around 10,000 feet of conduit, a small part of which
    21
    the jury may have decided that BMF failed to bury at a sufficient depth.
    We overrule Gulf Coast’s argument that the evidence is legally
    insufficient to support the jury’s answer to the substantial performance
    question, Question 7.
    Next, we address Gulf Coast’s argument that the evidence is legally
    insufficient to support the jury’s award of $17,409 in damages. Generally,
    juries may decide to award damages within the range of evidence the
    parties present in the trial when a rational basis exists supporting the
    jury’s award. 12 On appeal, “[t]he evidence need not correspond to the
    precise amount found by the jury.” 13
    The amount the jury awarded falls within the range of evidence the
    parties presented to the jury during the trial. As a reviewing court, we
    may not speculate about how the jury arrived at the award. 14 At trial, the
    parties presented conflicting testimony about what the Agreement
    required, whether BMF complied with the Agreement’s terms, who was
    12Sw.  Energy Prod. Co. v. Berry-Helfand, 
    491 S.W.3d 699
    , 713 (Tex.
    2016); Gulf States Utils. Co. v. Low, 
    79 S.W.3d 561
    , 566 (Tex. 2002).
    13Sam Rayburn Mun. Power Agency v. Gillis, No. 09-16-00339-CV,
    
    2018 Tex. App. LEXIS 5743
    , at *44-45 (Tex. App.—Beaumont July 26,
    2018, pet. denied).
    14Id.
    22
    responsible for correcting the work that Gulf Coast criticized after BMF
    ran the conduit into the holes, and whether what Gulf Coast spent was
    reasonable for correcting the work Gulf Coast claimed was deficient.
    We turn to BMF’s evidence first. During the trial, BMF established
    that Gulf Coast paid $48,357 for work that BMF performed on the fiber-
    optic project before Gulf Coast began disputing the invoices BMF was
    submitting to Gulf Coast for its work. Even after Gulf Coast started
    complaining about deficiencies in BMF’s work, Gulf Coast allowed BMF
    to continue to work on the project. And BMF, based on the work it claimed
    to have completed on the project, submitted additional invoices to Gulf
    Coast claiming Gulf Coast owed it another $42,593 for laying another
    5,782 feet of conduit at Gulf Coast’s request. The $42,593 of unpaid work
    is reflected in invoice numbers 105-107. Gulf Coast refused to pay BMF
    for $42,593 of work, but not because BMF did not do the work reflected
    in those invoices. Instead, Gulf Coast presented evidence in the trial
    showing it spent $37,377 to correct what it claimed were deficiencies and
    errors in the work BMF did from the time it started working on the
    project. While we can’t speculate about exactly how the jury arrived at
    its award, we note the jury’s award is substantially less than the $42,593
    23
    that BMF billed in the invoices that Gulf Coast didn’t pay. And of the
    $37,377 that Epps claims Gulf Coast spent to correct what he
    characterized as BMF’s nonconforming work, part of the work that
    accounts for Gulf Coast’s $37,377 calculation was completed by Gulf
    Coast’s own employees. As to the work Gulf Coast’s employees performed,
    the jury may have chosen to allocate some or all of the cost of that work
    to Gulf Coast rather than BMF given the terms of the partially integrated
    Agreement relevant to the issues in dispute, particularly since the
    Agreement does not cover all of the disputed issues that the parties asked
    the jury to consider when resolving the disputed issues in the trial.
    In the end, by its verdict the jury struck a balance between the
    testimony about what the Agreement required and who was responsible
    for the problems BMF encountered after it signed the subcontract
    agreement with Gulf Coast. 15 Based on the manner the parties conducted
    the trial and the evidence the parties introduced, we conclude the record
    Mayberry v. Tex. Dep’t of Agric., 
    948 S.W.2d 312
    , 317 (Tex.
    15See
    App.—Austin 1997, writ denied).
    24
    contains legally sufficient evidence to support the jury’s award of $17,409
    in damages.
    Last, we turn to Gulf Coast’s factual insufficiency arguments. In
    these, Gulf Coast argues the evidence is factually insufficient to support
    the jury’s substantial performance finding, Question 7, and damages
    award for substantial performance, Question 8. To preserve factual
    sufficiency complaints—a complaint that a jury finding is against the
    great weight of the evidence, or a complaint about the inadequacy or
    excessiveness of damages—the complaining party must raise its
    complaint in a motion for new trial. 16 While Gulf Coast did file several
    motions after the jury returned its verdict, its post-judgment motions all
    asked the trial court to render judgment in Gulf Coast’s favor; none of
    Gulf Coast’s motions complain the evidence is factually insufficient to
    support the jury’s findings. And in these motions, Gulf Coast never asked
    the trial court to award it a new trial.
    We conclude that Gulf Coast failed to preserve its factual
    sufficiency arguments for the purposes of having them reviewed on
    appeal. We overrule Gulf Coast’s factual insufficiency arguments in
    16See   Tex. R. Civ. P. 324(b)(2), (3), (4).
    25
    issues one and two. And having now addressed all the arguments that
    Gulf Coast raised in its first two issues, we overrule issues one and two.
    Attorney’s Fees
    In Gulf Coast’s third issue, it argues that because BMF’s recovered
    on its claim for substantial performance, it had no right to recover against
    BMF on its claim for attorney’s fees. Alternatively, Gulf Coast argues
    BMF “contracted away its right to recover attorney’s fees” in the
    Agreement.
    Whether a party may recover attorney’s fees is a legal question, so
    we review whether attorney’s fees are recoverable under a de novo
    standard. 17 “Texas follows the American rule on attorney’s fees, which
    provides that, generally, a party may not recover attorney’s fees unless
    authorized by statute or contract.” 18 And awards of attorney’s fees are
    “limited by the wording of the statute or contract.” 19
    A statute provides a right to recover attorney’s fees based on the
    record before us here. Under the Texas Civil Practice and Remedies Code,
    17Holland v.  Wal-Mart Stores, Inc., 
    1 S.W.3d 91
    , 94 (Tex. 1999).
    18Rohrmoos   Venture v. UTSW DVA Healthcare, LLP, 
    578 S.W.3d 469
    , 484 (Tex. 2019).
    19JCB, Inc. v. Horsburgh & Scott Co., 
    597 S.W.3d 481
    , 491 (Tex.
    2019).
    26
    the legislature authorized individuals to recover reasonable attorney’s
    fees in addition to the amount of a valid claim and costs when the
    individual’s claim is for, among other things, (1) services rendered, (2)
    labor performed, (3) materials furnished, or (4) an oral or written
    contract. 20 To be awarded attorney’s fees under that statute, however,
    the party must prevail on its claim under the statute and recover
    damages on its claim. 21
    Under the trial court’s judgment and on appeal, BMF was the
    prevailing party under the trial court’s judgment on its substantial
    performance claim. Even though claims for substantial performance
    presume a quasi-contract theory, BMF’s claim is tied to a written
    contract. And the contract required BMF to perform services, labor and
    to provide materials to Gulf Coast. Given that Gulf Coast failed to
    promptly object to the conflict in the jury’s findings, it may not now
    complain of the conflict in the findings. And we hold that the trial court
    did not abuse its discretion by awarding BMF attorney’s fees under
    section 38.001 of the Texas Civil Practice and Remedies Code when, in
    20Tex. Civ. Prac. & Rem. Code Ann. § 38.001(b).
    21MBM Fin. Corp. v. Woodlands Operating Co., L.P., 
    292 S.W.3d 660
    , 666 (Tex. 2009).
    27
    its discretion, it decided to sign a judgment favoring BMF that made BMF
    the prevailing party in the suit. 22
    Last, Gulf Coast argues that under the Agreement it signed with
    Gulf Coast, BMF contracted away its right to recover attorney’s fees. Gulf
    Coast points to section 14.3 of the Agreement to support its argument, a
    paragraph that explains when Gulf Coast may, at its option, terminate
    or suspend BMF’s work. Section 14.3 of the Agreement gave Gulf Coast
    the right to stop BMF’s work “and take all necessary action to stop cost
    commitment and protect any property in [BMF’s] possession which [Gulf
    Coast] has or may acquire an interest.” The Agreement then states:
    In any event, the total payments set forth above, together
    with payments made pursuant to this Agreement prior to
    termination shall not exceed the Contract Amount. In no
    event shall [Gulf Coast] be liable for the loss of anticipated
    profits or any special or consequential damages arising from
    said termination. [BMF’s] remedies hereunder shall be
    subject to the remedies provided by Owner to [Gulf Coast,] as
    contained in the terms and conditions of the Prime Contract.
    22See,e.g., 
    Tex. Civ. Prac. & Rem. Code Ann. § 38.001
     (stating a
    party who prevails on a breach of contract claim is entitled to attorney’s
    fees); Weitzul Constr., Inc. v. Outdoor Environs, 
    849 S.W.2d 359
    , 366
    (Tex. App.—Dallas 1993, writ denied) (noting that “[a] party may recover
    attorney’s fees for claims arising out of written contracts or quantum
    meruit”).
    28
    Once again, we face the same problem we’ve already addressed—
    Gulf Coast failed to establish what the Prime Contract says since it failed
    to introduce the Prime Contract in the trial. Yet Gulf Coast insists the
    that through the above language, BMF waived its statutory right to
    recover attorney’s fees from Gulf Coast, a statutory right created by
    section 38.001 of the Texas Civil Practice and Remedies Code.23
    To be sure, had the Agreement contained language waiving BMF’s
    right to attorney’s fees, we would have no quarrel with Gulf Coast’s claim
    that BMF waived its recovery since in Texas a party may “waive
    statutory rights including constitutional rights.” 24 But to establish that
    a party waived its rights, the record must show the party intentionally
    surrendered a right through a contract provision before a court will find
    a provision in a contract operates as a waiver of a statutory right. 25
    23Tex.   Civ. Prac. & Rem. Code Ann. 38.001(b).
    24Moayedi    v. Interstate 35/Chisam Rd., L.P., 
    438 S.W.3d 1
    , 6 (Tex.
    2014).
    25We  note that Gulf Coast pled waiver in its answer and in arguing
    waiver, it argues BMF forfeited its right to recover attorney’s fees as a
    matter of law.
    29
    In Texas, waiver is the “intentional relinquishment of a known
    right or intentional conduct inconsistent with claiming that right.”26
    When deciding whether the provisions in a contract resulted in waiving
    of a party’s right to recover attorney’s fees, the Fifth Circuit Court of
    Appeals in a case interpreting Texas law observed that the contract must
    “specifically preclude [the claimant’s] statutory claim to an award of
    attorney’s fees under Section 38.001.” 27 The provision that Gulf Coast
    relies on here doesn’t meet that test.
    Nothing in this record shows that when BMF signed the
    Agreement, it intentionally relinquished its statutory rights under
    section 38.001 to recovery attorney’s fees. For example, while the
    Agreement mentions anticipated profits and consequential damages,
    Gulf Coast has not argued that recovering attorney’s fees under a statute
    26Shepherd   v. Ledford, 
    962 S.W.2d 28
    , 36 (Tex. 1998) (quoting Sun
    Expl. & Prod. Co. v. Benton, 
    728 S.W.2d 35
    , 37 (Tex. 1987)).
    27Tex. Nat’l Bank v. Sandia Mortg. Corp., 
    872 F.2d 692
    , 701 (5th
    Cir. 1989) (interpreting Texas law); see also Bank of Am., N.A. v. Hubler,
    
    211 S.W.3d 859
    , 865 (Tex. App.—Waco 2006, pet. granted, judgm’t
    vacated w.r.m.) (holding that the claimant did not waive her statutory
    right to attorney’s fees because the contract provision that the bank
    would not be liable “for attorney’s fees incurred,” was “too general to
    apprise [the claimant] of what right she [was] relinquishing, namely her
    statutory right to attorney’s fees under Chapter 38”).
    30
    is a consequential damage or that the parties understood it to be a
    consequential damage when they entered the Agreement. Because the
    arguments Gulf Coast relies on to support its third issue lack merit, its
    third issue is overruled.
    Conclusion
    Having overruled Gulf Coast’s issues, the trial court’s judgment is
    AFFIRMED.
    _________________________
    HOLLIS HORTON
    Justice
    Submitted on September 1, 2021
    Opinion Delivered July 28, 2022
    Before Golemon, C.J., Kreger and Horton, JJ.
    31