in Re Pilgrim's Pride Corporation, Christopher Bentley, and Kyle Martin ( 2022 )


Menu:
  •                                   IN THE
    TENTH COURT OF APPEALS
    No. 10-21-00305-CV
    IN RE PILGRIM'S PRIDE CORPORATION,
    CHRISTOPHER BENTLEY, AND KYLE MARTIN
    Original Proceeding
    From the 170th District Court
    McLennan County, Texas
    Trial Court No. 2021-1030-4
    MEMORANDUM OPINION
    In this original proceeding, Relators Pilgrim’s Pride Corporation (Pilgrim’s Pride),
    Christopher Bentley (Bentley), and Kyle Martin (Martin) have filed a petition seeking
    mandamus relief from the trial court’s October 21, 2021 discovery order. We will
    conditionally grant the petition in part and deny it in part.
    Factual and Procedural Background
    Jonathan Barrett died, and Daniel Kendall and Brandon Lawler both suffered
    serious injuries, when a ceiling panel on which they were standing collapsed beneath
    them at Pilgrim’s Pride’s poultry plant in Waco, Texas, on or about January 26, 2021.
    Thereafter, in April 2021, Daniel Kendall (Kendall) and his wife Lauren (together, the
    Kendalls) took a Rule 202 deposition of Bentley, the head of engineering at the Pilgrim’s
    Pride plant. See generally TEX. R. CIV. P. 202. The Kendalls subsequently filed a negligence
    suit against Pilgrim’s Pride, Bentley, and Martin, the complex manager at the Pilgrim’s
    Pride plant. The Kendalls later amended their pleadings to add NBMC, Inc. (NBMC) as
    a defendant.
    The Kendalls made the following allegations in their live pleading at the time of
    the trial court’s complained-of ruling: Pilgrim’s Pride decided to have some renovations
    done at its Waco plant. Pilgrim’s Pride had a company policy prohibiting the use of a
    general contractor for projects at the plant; instead, Pilgrim’s Pride took on the tasks
    normally assigned to a general contractor. Pilgrim’s Pride assigned Bentley as the
    “Project Engineer” for this renovation project; therefore, Bentley assumed the duties
    normally undertaken by a general contractor’s superintendent at a renovation project.
    The Kendalls alleged that Pilgrim’s Pride contracted with Baker Refrigeration
    Systems Inc. (Baker Refrigeration) to perform the refrigeration portion of the renovation
    project. The Baker Refrigeration crew, of which Kendall was a member, was assigned to
    work in an area above the ceiling of a large storage room. The storage room ceiling panels
    served as the floor for the Baker Refrigeration crew as they worked. The Kendalls alleged
    that Pilgrim’s Pride also contracted with NBMC to perform the demolition of equipment,
    the concrete work, and the replacement of walls and ceilings for the renovation project.
    In re Pilgrim's Pride Corp.                                                           Page 2
    Before the ceiling panel collapsed, NBMC performed demolition work in the Baker
    Refrigeration crew’s work area above the ceiling of the storage room.
    The Kendalls alleged that the Baker Refrigeration crew had been working for
    several days at the plant in the designated work area before the ceiling panel collapsed.
    The day before the collapse, Bentley was in the storage room below the area where the
    Baker Refrigeration crew was working when he saw the storage room ceiling “flexing
    and bowing.” Bentley therefore knew that the storage room ceiling panels that served as
    the floor for the Baker Refrigeration crew as they worked were dangerous. Bentley,
    however, did not notify the Baker Refrigeration crew of the dangerous condition, did not
    lock the gate to the area, and did not put up a caution sign or tape. Instead, without
    notifying others at Pilgrim’s Pride and without completing a feasibility analysis, Bentley
    specifically approved a plan to use a scissor lift as a brace to support the ceiling panels so
    that the Baker Refrigeration crew could continue to work. But the collapse occurred
    before any such plan was implemented.
    The Kendalls alleged that as part of the renovation project, Pilgrim’s Pride had
    implemented a procedure requiring Baker Refrigeration to apply for a “hot works
    permit” whenever it needed to engage in welding, cutting, or grinding inside the
    building. On the morning of the day that the ceiling panel collapsed, Pilgrim’s Pride
    issued a “hot works permit” authorizing the Baker Refrigeration crew to cut pipe that
    needed to be removed in the designated work area above the storage room ceiling.
    Martin also came into the work area that morning and observed the Baker Refrigeration
    crew working in the designated work area above the storage room ceiling. Martin did
    In re Pilgrim's Pride Corp.                                                             Page 3
    not warn the crew of the dangerous condition. The Kendalls alleged that while the Baker
    Refrigeration crew was then working on the pipes, a ceiling panel collapsed and fell out
    from under Kendall’s feet, creating a hole where the panel had been. Three workers fell
    through the hole in the ceiling and onto the concrete floor of the storage room below. As
    a result, Kendall was severely injured, and his supervisor was killed. 1
    Pilgrim’s Pride, Bentley, and Martin jointly answered the Kendalls’ pleading with
    a general denial of the Kendalls’ allegations. Pilgrim’s Pride, Bentley, and Martin further
    asserted that the Kendalls’ factual allegations produced “an inaccurate picture of the
    incident” and inaccurately represented Bentley’s Rule 202 deposition testimony.
    Accordingly, Pilgrim’s Pride, Bentley, and Martin put forward their own factual
    allegations in their answer as follows: The incident was a “tragic accident” that occurred
    in the attic space above where the “Waco Line 4 Freezer Replacement Project” was taking
    place. Before the bidding process for the renovation began, Baker Refrigeration inspected
    the facility. Furthermore, after being selected to complete the project, Baker Refrigeration
    inspected the jobsite a second time before beginning its work.
    Pilgrim’s Pride, Bentley, and Martin alleged that a few days after the work began,
    and the day before the ceiling panel collapsed, Bentley noticed that “the ceiling above
    Line 4 (which also served as the attic floor) was bowing and flexing to an unacceptable
    extent” because several of Baker Refrigeration’s employees/subcontractors were
    1 Shortly after the Kendalls filed suit, Brandon Lawler and his wife Kimberly Stone filed a petition in
    intervention asserting negligence claims against Pilgrim’s Pride, Bentley, Martin, and Baker Refrigeration.
    Additionally, Summer Barrett, individually and as the surviving spouse and representative of the estate of
    Jonathan Barrett, filed a petition in intervention asserting negligence claims against Pilgrim’s Pride,
    Bentley, and Martin.
    In re Pilgrim's Pride Corp.                                                                         Page 4
    concentrated in a relatively small area where they were removing old, heavy
    piping/valves.         Bentley thereafter notified Jonathan Barrett (Barrett), Baker
    Refrigeration’s supervisor, that the work needed to stop because the excessive weight
    that the Baker Refrigeration workers were placing on the ceiling panels while performing
    their jobs was creating an unsafe situation. Bentley further suggested that a safer,
    alternate way for the Baker Refrigeration employees/subcontractors to complete the
    removal of the pipes/valves would be to take out the whole ceiling and use scissor lifts
    and forklifts to remove the pipes. But Baker Refrigeration rejected the idea. Barrett told
    Bentley that he felt like it would be unsafe to use scissor lifts in that way.
    Pilgrim’s Pride, Bentley, and Martin alleged that Baker Refrigeration instead
    developed its own plan. After discussing the situation with his boss, Barrett told Bentley
    that, before the workers would continue working, Baker Refrigeration was going to use
    scissor lifts to “crib up” the area under the ceiling panels where the Baker Refrigeration
    employees/subcontractors were removing the pipes. Bentley approved the plan because
    he felt like Baker Refrigeration was the expert, not him.          Baker Refrigeration also
    informed others of the plan because NBMC employees showed Bentley the area where
    Barrett had shown them that the scissor lifts would be located. The next morning,
    however, Barrett ordered his workers to begin working before the arrival and
    implementation of the scissor lifts, in violation of the plan that he had devised. Based on
    the foregoing factual allegations, Pilgrim’s Pride, Bentley, and Martin further moved to
    designate Baker Refrigeration and Barrett as responsible third parties.
    In re Pilgrim's Pride Corp.                                                          Page 5
    On June 29, 2021, the Kendalls served their first requests for production of
    documents and first sets of interrogatories on Pilgrim’s Pride, Bentley, and Martin.
    Subsequently, Pilgrim’s Pride, Bentley, and Martin each timely provided their objections
    and responses to the Kendalls’ first requests for production of documents. On September
    30, 2021, Pilgrim’s Pride, Bentley, and Martin then filed a motion for protection from the
    Kendalls’ discovery requests, and on October 1, 2021, the Kendalls filed a motion to
    compel Pilgrim’s Pride to respond to their Requests for Production Nos. 3, 12, 33, 43, and
    55. The Kendalls later supplemented their motion to compel. Pilgrim’s Pride, Bentley,
    and Martin also jointly filed a response to the Kendalls’ motion to compel and a reply in
    support of their own motion for protection.
    On October 15, 2021, the trial court held a hearing on Pilgrim’s Pride’s, Bentley’s,
    and Martin’s motion for protection and on the Kendalls’ motion to compel. At the end of
    the hearing, the trial court stated: “I will grant [the Kendalls’] motion to compel in full.”
    On October 21, 2021, the trial court then signed its “Order on Plaintiffs’ Motion to
    Compel Defendant Pilgrim’s Pride Corporation to Produce Documents Responsive to
    Plaintiffs’ First Requests for Production Nos. 3, 12, 33, 43, and 55.” In the order, the trial
    court granted the Kendalls’ motion to compel Pilgrim’s Pride to respond to their Requests
    for Production Nos. 3, 12, 33, 43, and 55 and overruled Pilgrim’s Pride’s objections to
    those discovery requests. The trial court then ordered Pilgrim’s Pride to provide all
    responsive documents and further answers or supplementations to the Kendalls’
    Requests for Production Nos. 3, 12, 33, 43, and 55 within thirty days of the date of the
    In re Pilgrim's Pride Corp.                                                             Page 6
    order.2 Finally, the trial court denied Pilgrim’s Pride’s, Bentley’s, and Martin’s motion
    for protection from the Kendalls’ discovery requests.
    Discussion
    Mandamus is an extraordinary remedy that is available only when (1) the trial
    court clearly abused its discretion and (2) the relator lacks an adequate remedy by appeal.
    In re K & L Auto Crushers, LLC, 
    627 S.W.3d 239
    , 247 (Tex. 2021) (orig. proceeding) (citing
    In re Prudential Ins. Co. of Am., 
    148 S.W.3d 124
    , 135–36, 138 (Tex. 2004) (orig. proceeding)).
    A.     Clear Abuse of Discretion
    We begin with whether the trial court clearly abused its discretion in denying
    Pilgrim’s Pride’s, Bentley’s, and Martin’s motion for protection from the Kendalls’
    discovery requests. Rule of Civil Procedure 192.6(a) provides: “A person from whom
    discovery is sought, and any other person affected by the discovery request, may move
    within the time permitted for response to the discovery request for an order protecting that
    person from the discovery sought.” TEX. R. CIV. P. 192.6(a) (emphasis added). Pilgrim’s
    Pride, Bentley, and Martin did not file their motion for protection from the Kendalls’
    discovery requests until after the time permitted to respond to the Kendalls’ first requests
    for production of documents and first sets of interrogatories had expired. The trial court,
    therefore, did not clearly abuse its discretion in denying Pilgrim’s Pride’s, Bentley’s, and
    Martin’s motion for protection. See 
    id.
    2   We have stayed the trial court’s October 21, 2021 order, pending further order of this Court.
    In re Pilgrim's Pride Corp.                                                                         Page 7
    We next address whether the trial court clearly abused its discretion in granting
    the Kendalls’ motion to compel Pilgrim’s Pride to respond to their Requests for
    Production Nos. 3, 12, 33, 43, and 55 and in overruling Pilgrim’s Pride’s objections to
    those discovery requests.
    “‘The trial court abuses its discretion by ordering discovery that exceeds that
    permitted by the rules of procedure.’” In re USAA Gen. Indem. Co., 
    624 S.W.3d 782
    , 787
    (Tex. 2021) (orig. proceeding) (quoting In re CSX Corp., 
    124 S.W.3d 149
    , 152 (Tex. 2003)
    (orig. proceeding) (per curiam)). Rule of Civil Procedure 192.3(a) provides that the
    parties to a lawsuit may generally obtain discovery of information that “is not privileged
    and is relevant to the subject matter of the pending action.” TEX. R. CIV. P. 192.3(a). “Such
    evidence is discoverable even if it would not be admissible at trial so long as it ‘appears
    reasonably calculated to lead to the discovery of admissible evidence.’” USAA Gen.
    Indem. Co., 624 S.W.3d at 787–78 (quoting TEX. R. CIV. P. 192.3(a)). Rule of Civil Procedure
    192.4 provides, however, that the trial court “should” limit otherwise permissible
    discovery if:
    (a)   the discovery sought is unreasonably cumulative or duplicative, or is
    obtainable from some other source that is more convenient, less
    burdensome, or less expensive; or
    (b)   the burden or expense of the proposed discovery outweighs its likely
    benefit, taking into account the needs of the case, the amount in
    controversy, the parties’ resources, the importance of the issues at
    stake in the litigation, and the importance of the proposed discovery
    in resolving the issues.
    TEX. R. CIV. P. 192.4. Rule of Civil Procedure 192.4 imposes a proportionality standard
    that requires “a case-by-case balancing of jurisprudential considerations.” K & L Auto
    In re Pilgrim's Pride Corp.                                                            Page 8
    Crushers, 627 S.W.3d at 253 (quoting In re State Farm Lloyds, 
    520 S.W.3d 595
    , 599 (Tex. 2017)
    (orig. proceeding)).
    Pilgrim’s Pride challenges the propriety of the Kendalls’ Requests for Production
    Nos. 3, 12, 33, 43, and 55 on both relevance and proportionality grounds.
    1.    Relevance
    We first address Pilgrim’s Pride’s contention that the Kendalls’ Requests for
    Production Nos. 3, 12, 33, 43, and 55 are overbroad and seek irrelevant documentation.
    . . . Although [the Rules of Civil Procedure] must be “liberally
    construed to allow the litigants to obtain the fullest knowledge of the facts
    and issues prior to trial,” Axelson, [Inc. v. McIlhany,] 798 S.W.2d [550,] 553
    [(Tex. 1990) (orig. proceeding)], “even these liberal bounds have limits, and
    discovery requests must not be overbroad.” In re Nat’l Lloyds Ins. Co., 
    449 S.W.3d 486
    , 488 (Tex. 2014) (orig. proceeding) (per curiam). In essence, an
    overbroad discovery request is one that seeks irrelevant information. In re
    Allstate Cnty. Mut. Ins. Co., 
    227 S.W.3d 667
    , 670 (Tex. 2007) (orig.
    proceeding) (per curiam). But a request is not overbroad simply because it
    “may call for some information of doubtful relevance,” Texaco, Inc. v.
    Sanderson, 
    898 S.W.2d 813
    , 815 (Tex. 1995) (orig. proceeding) (per curiam),
    and “the sheer volume of a discovery request does not in itself render the
    request irrelevant or overbroad as a matter of law,” In re Alford Chevrolet–
    Geo, 
    997 S.W.2d 173
    , 180 n.1 (Tex. 1999) (orig. proceeding).
    K & L Auto Crushers, 627 S.W.3d at 251–52. Whether a request for discovery is overbroad
    is distinct from whether it is burdensome or harassing. Allstate, 227 S.W.3d at 670.
    Instead, discovery requests and orders are overbroad if they are not
    properly “tailored with regard to time, place, or subject matter,” In re Nat’l
    Lloyds Ins. Co., 
    507 S.W.3d 219
    , 226 (Tex. 2016) [(orig. proceeding)] (per
    curiam), or otherwise require production of information that is not
    reasonably calculated to lead to the discovery of admissible evidence, Nat’l
    Lloyds, 449 S.W.3d at 490.
    K & L Auto Crushers, 627 S.W.3d at 252 (footnote omitted). “A central consideration in
    determining overbreadth is whether the request could have been more narrowly tailored
    In re Pilgrim's Pride Corp.                                                              Page 9
    to avoid including tenuous information and still obtain the necessary, pertinent
    information.” CSX Corp., 124 S.W.3d at 153.
    a.    Requests for Production Nos. 3 and 33
    The Kendalls’ Request for Production No. 3 states: “Produce all documents
    reflecting all incidents, including but not limited to any near-miss reports, at the Worksite
    for the sixty (60) days before and including the date of the Incident.” Similarly, the
    Kendalls’ Request for Production No. 33 provides: “Produce any Documents that reflect
    any concerns and/or complaints received by You regarding safety deficiencies and/or
    operation of Worksite from January 1, 2016 through the date of the Incident.” The term
    “Worksite” is defined as “the building where the Waco Line 4 Freezer Replacement
    project was being conducted at the Pilgrim’s Pride Corporation located at 2500 E Lake
    Shore Drive, Waco, Texas, where the incident resulting in the bodily injury of Daniel
    Kendall” occurred.
    Pilgrim’s Pride contends that, regarding these discovery requests, because of the
    definition of the term “Worksite,” the Kendalls are seeking information that encompasses
    the entire poultry processing plant. Pilgrim’s Pride further points out that, regarding
    Request for Production No. 33 specifically, the Kendalls are seeking discovery that covers
    a period spanning more than five years before the incident involving Kendall occurred.
    Pilgrim’s Pride asserts, however, that Baker Refrigeration was working on the Waco Line
    4 Freezer Replacement Project as an independent contractor, not as an employee; that the
    project involved only a small area of the attic located above Line 4, where the routine
    operation of the poultry processing plant had been shut down; and that the project had
    In re Pilgrim's Pride Corp.                                                           Page 10
    begun only a few days before the incident involving Kendall occurred. Pilgrim’s Pride
    argues that the Kendalls’ Requests for Production Nos. 3 and 33 are therefore fishing
    expeditions. See generally Alford Chevrolet–Geo, 997 S.W.2d at 181 (“[D]iscovery may not
    be used as a fishing expedition or to impose unreasonable discovery expenses on the
    opposing party.”).
    Pilgrim’s Pride also argues that a premises owner has a very limited duty to an
    employee of an independent contractor. The Texas Supreme Court stated in General
    Electric Company v. Moritz that a premises owner does not owe a duty to ensure that
    independent contractors perform their work in a safe manner. 
    257 S.W.3d 211
    , 214 (Tex.
    2008). The court further stated:
    Generally, a landowner is liable to employees of an independent contractor
    only for claims arising from a pre-existing defect rather than from the
    contractor’s work, and then only if the pre-existing defect was concealed:
    “With respect to existing defects, an owner or occupier has a duty to inspect
    the premises and warn of concealed hazards the owner knows or should
    have known about.”
    Id. at 215 (footnote omitted) (quoting Shell Oil Co. v. Khan, 
    138 S.W.3d 288
    , 295 (Tex. 2004)
    (emphasis added)).            Pilgrim’s Pride then states in its petition that it “has already
    stipulated that it had notice of the condition of the [ceiling panels] in the exact area where
    the accident occurred, and that it advised Baker Refrigeration of same, prior to the
    accident.” Pilgrim’s Pride, relying on In re USAA General Indemnity Company, argues that
    there is therefore “no need to conduct discovery on what Pilgrim’s Pride should have
    known when Pilgrim’s Pride admits that it actually knew.” See generally 624 S.W.3d at 793
    (“Considering USAA’s coverage concessions and the narrow scope of the ‘car crash’
    In re Pilgrim's Pride Corp.                                                             Page 11
    issues in dispute, we hold that some, but not all, of Wearden’s noticed deposition topics
    exceed the rules’ permissible scope.”).
    In many instances, “evidence of other accidents, near accidents, or related similar
    events is probative evidence in Texas courts.” In re Sun Coast Res., Inc., 
    562 S.W.3d 138
    ,
    148 (Tex. App.—Houston [14th Dist.] 2018, orig. proceeding). But before such evidence
    may be admitted, an adequate predicate must be established. 
    Id.
     The plaintiff must
    establish: “(1) a predicate of similar or reasonably similar conditions; (2) connection of
    the conditions in some special way; or (3) that the incidents occurred by means of the
    same instrumentality.” 
    Id.
     We accordingly conclude that, at a minimum, the Kendalls’
    Requests for Production Nos. 3 and 33 are not properly tailored with regard to subject
    matter. See K & L Auto Crushers, 627 S.W.3d at 252 (“[D]iscovery requests and orders are
    overbroad if they are not properly ‘tailored with regard to time, place, or subject matter.’”
    (quoting Nat’l Lloyds, 507 S.W.3d at 226)). Even though the scope of discovery is much
    broader than the scope of admissible evidence, In re Exmark Mfg. Co., 
    299 S.W.3d 519
    , 528
    (Tex. App.—Corpus Christi–Edinburg 2009, orig. proceeding), the Kendalls are not
    entitled to discover documents reflecting incidents and concerns regarding Pilgrim’s
    Pride’s entire poultry processing operation. See, e.g., Texaco, Inc. v. Sanderson, 
    898 S.W.2d 813
    , 815 (Tex. 1995) (orig. proceeding) (per curiam) (where principal issue was whether
    defendants were grossly negligent in exposing plaintiffs’ decedents to asbestos, benzene,
    and other such toxic substances, and where plaintiffs wanted to prove a general
    “corporate strategy to ignore safety law,” court explained that “[w]hile plaintiffs are
    entitled to discover evidence of defendants’ safety policies and practices as they relate to
    In re Pilgrim's Pride Corp.                                                           Page 12
    the circumstances involved in their allegations, a request for all documents authored by
    [the corporate safety director] on the subject of safety, without limitation as to time, place
    or subject matter, is overbroad”).
    The Kendalls argue, in part, that they did not arbitrarily choose to define
    “Worksite” as the entire building but that they instead defined it as it is defined in the
    contract between Pilgrim’s Pride and Baker Refrigeration. The Kendalls further assert
    that defining “Worksite” as the entire building “simply reflects the actual scope of the
    work being done when the [ceiling panel] collapsed.” To support their assertion, the
    Kendalls point to Bentley’s deposition, in which he stated: “So theoretically, when
    they’re in the attic area dealing with pipes, [Baker Refrigeration’s work area] actually
    covers the majority of the section of the attic, as well as up on the roof of the building
    where they’re running their new ammonia pipes.” But even though these arguments
    may explain why the Kendalls’ Requests for Production Nos. 3 and 33 are properly
    tailored with regard to place, these arguments do not establish how the Kendalls’ Requests
    for Production Nos. 3 and 33 are properly tailored with regard to subject matter
    considering that Baker Refrigeration was an independent contractor that was not
    involved in the poultry processing operation of the plant.
    The Kendalls’ Requests for Production Nos. 3 and 33 are therefore overbroad, and
    the trial court clearly abused its discretion to the extent that it granted the Kendalls’
    motion to compel Pilgrim’s Pride to produce documents responsive to those discovery
    requests.
    In re Pilgrim's Pride Corp.                                                            Page 13
    b.     Request for Production No. 12
    The Kendalls’ Request for Production No. 12 states: “Produce any Documents
    reflecting the job descriptions and identities of the workers at the Worksite, including
    Defendant’s employees, agents and/or contractors at the Worksite, on the date of the
    Incident.”
    Pilgrim’s Pride again contends regarding this discovery request that because of
    the definition of the term “Worksite,” the Kendalls are improperly seeking information
    that encompasses the entire poultry processing plant. More specifically, Pilgrim’s Pride
    argues that the job descriptions and identities of the more than 545 Pilgrim’s Pride
    employees are irrelevant considering that Baker Refrigeration was an independent
    contractor that was hired only to conduct a freezer remodel and that Pilgrim’s Pride’s
    employees were not involved in the work being performed by Baker Refrigeration at the
    time of the incident that injured Kendall.
    In support of its argument, Pilgrim’s Pride relies on In re Pioneer Natural Resources
    USA, Inc., in which the defendant company challenged a discovery request seeking
    “production of the hiring, disciplinary, and employment files of all employees who
    performed work at the accident site at any time on the day of the accident.” No. 05-20-
    00536-CV, 
    2020 WL 5107284
    , at *1–2 (Tex. App.—Dallas Aug. 31, 2020, orig. proceeding)
    (mem. op.). The defendant company argued that the discovery request “exceed[ed] the
    bounds of discovery authorized by the rules of procedure” because the discovery request
    sought “information concerning employees who were not present at the time of the
    accident and did not participate in the events leading up to the accident.” Id. at *3. The
    In re Pilgrim's Pride Corp.                                                           Page 14
    Dallas Court of Appeals agreed, holding that the trial court abused its discretion in
    ordering the defendant company to produce documents responsive to the discovery
    request. Id. The court reasoned that the “only connection these employees had to the
    accident is that they arrived at the scene in the accident’s aftermath” and that the
    discovery request “could have easily been more narrowly tailored to include only
    employees who had some conceivable role in the injury-causing events.” Id.
    The Kendalls respond, in part, that Pilgrim’s Pride’s emphasis on the number of
    people it employs is a red herring. The Kendalls point to the fact that “’the sheer volume
    of a discovery request does not in itself render the request irrelevant or overbroad as a
    matter of law.’” K & L Auto Crushers, 627 S.W.3d at 251–52 (quoting Alford Chevrolet–Geo,
    997 S.W.2d at 180 n.1). Similar to In re Pioneer Natural Resources USA, Inc., however, the
    Kendalls’ Request for Production No. 12 applies to many people who would have no
    knowledge of any relevant facts regarding the circumstances involved in the Kendalls’
    allegations, including many who simply arrived at the scene in the incident’s aftermath.
    See 
    2020 WL 5107284
    , at *3. The discovery request could have been more narrowly
    tailored to apply to only those employees, agents and/or contractors at the Worksite, on
    the date of the incident, before the incident occurred. See CSX Corp., 124 S.W.3d at 153
    (“A central consideration in determining overbreadth is whether the request could have
    been more narrowly tailored to avoid including tenuous information and still obtain the
    necessary, pertinent information.”).
    We therefore conclude that the Kendalls’ Request for Production No. 12 is
    overbroad and that the trial court clearly abused its discretion to the extent that it granted
    In re Pilgrim's Pride Corp.                                                            Page 15
    the Kendalls’ motion to compel Pilgrim’s Pride to produce documents responsive to the
    discovery request.
    c.        Request for Production No. 43
    The Kendalls’ Request for Production No. 43 states:
    Produce any correspondence, emails, text messages or other Documents
    reflecting communication between Defendant and the following entities
    (specifically including any employees, officers, or representatives of same)
    concerning Plaintiff Daniel Kendall, the Incident, the Worksite, and/or any
    safety issues or matters related to same:
    a.   Baker Refrigeration;
    b.   Abacus Engineering Inc;
    c.   Midland Industrial; and
    d.   NBMC, Inc.
    Pilgrim’s Pride again contends regarding this discovery request that because of
    the definition of the term “Worksite,” the Kendalls are improperly seeking information
    that encompasses the entire poultry processing plant. Pilgrim’s Pride also argues that
    this discovery request is overbroad on its face because it contains no temporal limits.
    The Kendalls respond that this is a routine request for communications between
    Pilgrim’s Pride and the contractors involved in the project. Regarding the lack of
    temporal limits, specifically, the Kendalls assert that this discovery request is inherently
    limited in time in that it is necessarily limited to the period when each of the contractors
    worked at the Pilgrim’s Pride plant. See generally In re Nolle, 
    265 S.W.3d 487
    , 493 (Tex.
    App.—Houston [1st Dist.] 2008, orig. proceeding) (upholding discovery requests that
    were inherently limited as to relevant time period). The Kendalls further contend that
    this discovery request is important to clarify the expectations between Pilgrim’s Pride
    In re Pilgrim's Pride Corp.                                                            Page 16
    and its contractors, especially the amount of control that Pilgrim’s Pride exercised over
    its contractors.
    We conclude, however, that the discovery request is not properly tailored with
    regard to time or subject matter. The discovery request encompasses communications
    beyond those related to this renovation project and the circumstances involved in the
    Kendalls’ allegations. Instead, the discovery request includes communications related to
    other projects, if any, in which these contractors have participated at the poultry
    processing plant. The Kendalls’ Request for Production No. 43 is therefore overbroad,
    and the trial court clearly abused its discretion to the extent that it granted the Kendalls’
    motion to compel Pilgrim’s Pride to produce documents responsive to the discovery
    request.
    d.    Request for Production No. 55
    Finally, the Kendalls’ Request for Production No. 55 states:           “Produce all
    documents pertaining to or referencing all repairs or work or modifications to any
    portion of the Floor including but not limited to work orders, invoices, receipts.” The
    term “Floor” is defined as “the floor of room where Plaintiff was located at the time the
    fatal collapse occurred.”
    Pilgrim’s Pride’s contention regarding this discovery request is similar to its
    argument with regard to the Kendalls’ Requests for Production Nos. 3 and 33. Pilgrim’s
    Pride contends in its petition that
    this request is not reasonably calculated to lead to the discovery of
    admissible evidence, when Pilgrim’s Pride has already stipulated that it
    knew of the [ceiling panels’] condition in the exact area where the accident
    In re Pilgrim's Pride Corp.                                                            Page 17
    occurred, communicated it to Baker Refrigeration and its onsite supervisor,
    Barrett, and that Baker Refrigeration was responsible for developing a
    course of action to remedy the [ceiling panels’] condition, and then
    implementing said plan.
    Pilgrim’s Pride further asserts in its reply to the Kendalls’ response to its petition that
    there is “no need to conduct discovery on what Pilgrim’s Pride should have known when
    Pilgrim’s Pride admits that it actually knew about the floor.”
    As stated above, the Texas Supreme Court explained in General Electric Company v.
    Moritz:
    Generally, a landowner is liable to employees of an independent contractor
    only for claims arising from a pre-existing defect rather than from the
    contractor’s work, and then only if the pre-existing defect was concealed:
    “With respect to existing defects, an owner or occupier has a duty to inspect
    the premises and warn of concealed hazards the owner knows or should
    have known about.”
    257 S.W.3d at 215 (footnote omitted) (quoting Shell Oil Co., 138 S.W.3d at 295 (emphasis
    added)).     But there are some situations when an otherwise adequate warning is
    insufficient to discharge the landowner’s duty to make the premises reasonably safe.
    Austin v. Kroger Tex., L.P., 
    465 S.W.3d 193
    , 204 (Tex. 2015). One such exception is the
    necessary-use exception, i.e., “when the invitee necessarily must use the unreasonably
    dangerous premises, and despite the invitee’s awareness and appreciation of the dangers,
    the invitee is incapable of taking precautions that will adequately reduce the risk.” 
    Id.
    The Kendalls have also sued NBMC, alleging that before the ceiling panel
    collapsed, NBMC negligently performed demolition work in the Baker Refrigeration
    crew’s work area above the ceiling of the storage room. The trial court could have
    reasonably concluded that the Kendalls’ Request for Production No. 55 was reasonably
    In re Pilgrim's Pride Corp.                                                             Page 18
    calculated to lead to the discovery of admissible evidence regarding these issues. We
    therefore conclude that the Kendalls’ Request for Production No. 55 is not overbroad.
    2.    Proportionality
    Having concluded that the Kendalls’ Request for Production No. 55 is not
    overbroad, we next address Pilgrim’s Pride’s proportionality concerns.
    As explained above, Rule of Civil Procedure 192.4 imposes a proportionality
    standard that requires “a case-by-case balancing of jurisprudential considerations.” K &
    L Auto Crushers, 627 S.W.3d at 253 (quoting State Farm Lloyds, 520 S.W.3d at 599). The
    Texas Supreme Court has said, however, that “parties ‘must “support [such]
    proportionality complaints with evidence”’ and may not rely on conclusory allegations.”
    See USAA Gen. Indem. Co., 624 S.W.3d at 792 (quoting K & L Auto Crushers, 627 S.W.3d at
    253 (quoting State Farm Lloyds, 520 S.W.3d at 614)). The Kendalls argue that Pilgrim’s
    Pride has not supported its proportionality concerns with sufficient evidence. We agree.
    Pilgrim’s Pride argues generally that the Kendalls already have the benefit of a
    significant amount of discovery, including Bentley’s Rule 202 deposition. Pilgrim’s Pride
    further asserts in its petition that it “has already stipulated that it had notice of the
    condition of the [ceiling panels] in the exact area where the accident occurred, and that it
    advised Baker Refrigeration of same, prior to the accident.” Pilgrim’s Pride also attached
    the “Declaration of Kyle Martin” to its motion for protection from the Kendalls’ discovery
    requests. Martin stated in his Declaration that the “Pilgrim’s Pride facility has one
    building with a total of 309,000 square feet, which is just over seven acres.” Martin further
    stated, “There are 545 employees that work for Pilgrim’s Pride at this location.”
    In re Pilgrim's Pride Corp.                                                           Page 19
    But, as pointed out by the Kendalls, Pilgrim’s Pride did not connect the facts in
    Martin’s Declaration to the burdensomeness of responding to the Kendalls’ discovery
    requests.    See In re Energas Co., 
    63 S.W.3d 50
    , 55 (Tex. App.—Amarillo 2001, orig.
    proceeding) (“The fact that a discovery request is burdensome is not enough to justify
    protection, ‘it is only undue burden that warrants nonproduction.’” (quoting ISK Biotech
    Corp. v. Lindsay, 
    933 S.W.2d 565
    , 568 (Tex. App.—Houston [1st Dist.] 1996, orig.
    proceeding)). Accordingly, we conclude that the trial court did not clearly abuse its
    discretion to the extent that it granted the Kendalls’ motion to compel Pilgrim’s Pride to
    produce documents responsive to the Kendalls’ Request for Production No. 55.
    B.    No Adequate Remedy by Appeal
    We have held that the trial court clearly abused its discretion to the extent that it
    granted the Kendalls’ motion to compel Pilgrim’s Pride to produce documents responsive
    to the Kendalls’ Requests for Production Nos. 3, 12, 33, and 43.           To determine if
    mandamus is available to Pilgrim’s Pride, we must then determine whether Pilgrim’s
    Pride lacks an adequate remedy by appeal. See K & L Auto Crushers, 627 S.W.3d at 247.
    A trial court order that allows discovery not permitted under procedural rules is subject
    to mandamus relief because “parties lack an adequate appellate remedy from orders
    compelling discovery beyond what the rules allow.” In re Millwork, 
    631 S.W.3d 706
    , 714
    (Tex. 2021) (orig. proceeding) (per curiam). Accordingly, we conclude that Pilgrim’s
    Pride lacks an adequate remedy by appeal.
    In re Pilgrim's Pride Corp.                                                           Page 20
    Conclusion
    We lift our stay of the trial court’s October 21, 2021 discovery order and
    conditionally grant in part the petition for writ of mandamus filed by Pilgrim’s Pride,
    Bentley, and Martin. A writ will issue only if the trial court fails to vacate those portions
    of the October 21, 2021 order granting the Kendalls’ motion to compel Pilgrim’s Pride to
    produce documents responsive to the Kendalls’ Requests for Production Nos. 3, 12, 33,
    and 43, and to notify this Court in writing that it has done so within twenty-one days of
    the date of this opinion. We otherwise deny the mandamus petition. 3
    MATT JOHNSON
    Justice
    Before Chief Justice Gray,
    Justice Johnson, and
    Justice Smith
    Petition granted in part and denied in part
    Opinion delivered and filed August 3, 2022
    [OT06]
    3On January 28, 2022, Pilgrim’s Pride, Bentley, and Martin filed a “Motion for Leave to File Supplemental
    Brief in Support of Petition for Writ of Mandamus.” The motion is granted to the extent that the
    supplemental brief has been filed. However, we are prohibited from issuing advisory opinions. See Tex.
    Ass’n of Bus. v. Tex. Air Control Bd., 
    852 S.W.2d 440
    , 444 (Tex. 1993).
    In re Pilgrim's Pride Corp.                                                                      Page 21
    

Document Info

Docket Number: 10-21-00305-CV

Filed Date: 8/3/2022

Precedential Status: Precedential

Modified Date: 8/5/2022