Pools Unlimited, Inc. Randy Lee Morrow And Rhonda Jean Morrow v. John Houchens and Brenda Houchens ( 2022 )


Menu:
  •        TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    ON MOTION FOR REHEARING
    NO. 03-21-00046-CV
    Pools Unlimited, Inc.; Randy Lee Morrow; and Rhonda Jean Morrow, Appellants
    v.
    John Houchens and Brenda Houchens, Appellees
    FROM THE 207TH DISTRICT COURT OF COMAL COUNTY
    NO. C2017-2079B, THE HONORABLE DIB WALDRIP, JUDGE PRESIDING
    MEMORANDUM OPINION
    After considering the motion for rehearing filed by John and Brenda Houchens,
    we deny the motion for rehearing but withdraw our June 3, 2022 opinion and judgment and
    substitute the following opinion and judgment in their place.
    The suit underlying this appeal concerns a dispute over residential pool
    construction and includes competing claims for breach of contract between the pool builder,
    Pools Unlimited, Inc., and the homeowners, John Houchens and Brenda Houchens. Before trial,
    the trial court granted a partial summary judgment in favor of the Houchenses on their claim
    that Pools Unlimited filed a fraudulent mechanic’s lien. During trial, the trial court dismissed
    Pools Unlimited’s breach-of-contract claim against the Houchenses on directed verdict. Finally,
    after trial, the trial court disregarded the jury’s finding that the Houchenses sustained zero
    damages as a result of Pools Unlimited’s breach and, instead, awarded the Houchenses $58,500
    in actual damages on their breach-of-contract claim and $20,000 in statutory damages on their
    fraudulent-lien claim.
    On appeal, we affirm the trial court’s directed verdict and dismissal of Pools
    Unlimited’s breach-of-contract claim. However, because we conclude that the trial court erred in
    granting summary judgment on the Houchenses’ fraudulent-lien claim and in awarding damages
    on their breach-of-contract counterclaim, we will reverse the trial court’s judgment and remand
    for a new trial on those claims.
    BACKGROUND
    In May 2017, Pools Unlimited contracted with John for the construction of a
    swimming pool at his home in Comal County, which he shares with his wife, Brenda.1 In
    October 2017, after John failed to pay what Pools Unlimited claimed was the remaining balance
    owed on the contract, Pools Unlimited filed a mechanic’s lien pursuant to Chapter 53 of the
    Texas Property Code. See Tex. Prop. Code §§ 53.251-.260 (procedures for perfecting lien on
    residential construction projects). In December 2017, Pools Unlimited sued John for breach of
    contract, seeking to recover the unpaid balance. John then countersued Pools Unlimited for
    breach of contract, alleging that the construction by Pools Unlimited was deficient, and for
    fraudulently filing a mechanic’s lien.2 See Tex. Civ. Prac. & Rem. Code § 12.002(a) (prohibiting
    1
    Because many of the parties share the same last name, for clarity we will refer to the
    parties by their first name when referring to them individually.
    2
    The parties brought other claims for affirmative relief. Pools Unlimited brought claims
    for quantum meruit, fraud, and fraudulent inducement, which the trial court dismissed on
    summary judgment. The Houchenses sued Pools Unlimited and the Morrows for violations of
    the Texas Deceptive Trade Practices Act but failed to obtain jury findings in their favor as to
    2
    filing of fraudulent lien). Pools Unlimited later added Brenda as an involuntary counter-plaintiff;
    the Houchenses added Randy “Ryan” Morrow and Rhonda Morrow, the owners of Pools
    Unlimited, as third-party defendants.3
    In February 2018, the Houchenses moved for partial summary judgment on their
    fraudulent-lien claim. After sustaining the Houchenses’ objections to evidence submitted by
    Pools Unlimited in response, the trial court granted the motion for summary judgment as to
    Pools Unlimited’s liability but withheld ruling on the issue of fraudulent-lien damages. See id.
    § 12.002(b) (providing that liability for filing of fraudulent lien includes “greater of:
    (A) $10,000; or (B) actual damages caused by violation”).
    The parties’ competing breach-of-contract claims were tried to a jury in October
    2020.   At trial, the parties presented conflicting testimony as to the agreed price for the
    contracted work. Ryan testified that he and John first discussed the scope of the project in
    April 2017 and that while the initial proposal totaled $58,711, John later selected options
    not included in the initial proposal, including the construction of a “custom rock grotto
    waterfall” with a slide. According to Ryan, the final contract price with these selected options
    was $69,151, payable over six draws. Ryan also testified that John requested additional work
    after construction commenced (concrete coating, additional rock work, and a ladder), which
    brought the total cost to approximately $74,000, of which $31,900 remained unpaid.
    these alleged violations. Because no party has appealed the trial court’s judgment with respect to
    these other claims, we will limit our discussion of the underlying facts and procedural history to
    that which is relevant to the claims that are the subject of this appeal.
    3
    In this opinion, we will refer to the claims brought by John as being brought by
    the Houchenses. In addition, any reference to Pools Unlimited includes the Morrows, unless
    otherwise noted.
    3
    Conversely, John testified that the “proposal” for $58,711 was the only contract
    that he ever signed with Pools Unlimited. Although he acknowledged that he had agreed to the
    selected options (including the custom rock grotto waterfall and slide), he explained that this
    work was included in the contract price of $58,711. John also testified that although on May 16,
    2017, Ryan sent him an updated contract for $69,151, he refused to sign it because they had
    already “agreed on a price.”
    The undisputed evidence at trial showed that the pool was constructed over the
    summer of 2017 and filled with water on August 18 and that the Houchenses began using the
    pool soon after. In addition, while the parties disagreed as to the exact amount, at least some
    amount on the contract remained unpaid. In his testimony, John explained that he stopped
    paying Pools Unlimited in August 2017 because the work performed, primarily construction of
    the custom rock grotto waterfall and the spa, was defective and because automation of the pool’s
    heater and chiller failed to operate properly, due to the installation of incompatible equipment.
    John refused to make further payments on the contract until the defective work was corrected by
    Pools Unlimited.
    In his testimony, Ryan did not dispute that at least some complained-of issues
    existed and that repairs were necessary, including on the custom rock grotto waterfall. Ryan
    considered the needed repairs to be “warranty work,” however, and informed John that Pools
    Unlimited would perform whatever work was necessary to correct the issues upon receipt of
    payment. As of trial, no additional payments had been tendered, and no repairs had been made.
    At the close of Pools Unlimited’s case in chief, the Houchenses moved for a
    directed verdict on Pools Unlimited’s breach-of-contract claim. Upon considering the arguments
    of counsel, the trial court determined that Pools Unlimited had breached the construction contract
    4
    and granted the directed verdict in favor of the Houchenses, effectively rendering judgment that
    Pools Unlimited take nothing on its breach-of-contract claim.
    At the close of trial, the Houchenses’ counterclaim for breach of contract was
    submitted to the jury. In its charge, the trial court instructed the jury that “Pools Unlimited, Inc.
    and the Houchens[es] did have an agreement” and that “Pools Unlimited, Inc. failed to comply
    with that agreement.” The jury returned a verdict in favor of Pools Unlimited, finding that the
    Houchenses had sustained zero damages as a result of Pools Unlimited’s conduct.
    The Houchenses later filed a motion to disregard the jury findings and to enter a
    judgment notwithstanding the verdict, “awarding them damages in the uncontroverted amount
    of $58,500.” The trial court granted the Houchenses’ motion and signed a final judgment
    awarding the Houchenses $78,500 in actual damages, including $20,000 in statutory damages
    on their fraudulent-lien claim; $1,000 in exemplary damages; $151,000 in attorney’s fees,
    through the date of judgment; $38,500 in expenses; and $16,000 in pre-judgment interest. This
    appeal followed.
    DISCUSSION
    In six issues, Pools Unlimited challenges the trial court’s (1) summary judgment
    and award of damages in favor of the Houchenses on their fraudulent-lien claim; (2) directed
    verdict in favor of the Houchenses, dismissing Pools Unlimited’s breach-of-contract claim;
    (3) decision to disregard the jury’s zero-damages finding and, instead, award the Houchenses
    relief on their breach-of-contract claim against Pools Unlimited, including attorney’s fees
    and expenses.
    5
    Fraudulent-lien claim
    We first consider Pools Unlimited’s challenge to the trial court’s grant of
    summary judgment in favor of the Houchenses on their fraudulent-lien claim against
    Pools Unlimited.
    To prevail on a summary-judgment motion, the movant must demonstrate that
    there are no genuine issues of material fact and that it is entitled to judgment as a matter of law.
    Tex. R. Civ. P. 166a(c); Tarr v. Timberwood Park Owners Ass’n, Inc., 
    556 S.W.3d 274
    , 278
    (Tex. 2018). When, as in this case, a movant seeks a traditional summary judgment on its own
    cause of action, the movant has the initial burden of establishing its entitlement to judgment as a
    matter of law by conclusively establishing each element of its cause of action. Texas Ass’n of
    Acupuncture & Oriental Med. v. Texas Bd. of Chiropractic Exam’rs, 
    524 S.W.3d 734
    , 738
    (Tex. App.—Austin 2017, no pet.). Evidence is conclusive only if reasonable people could not
    differ in their conclusions. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 816 (Tex. 2005). Once the
    movant meets this burden, the burden shifts to the non-movant to present evidence creating a
    genuine issue of material fact precluding summary judgment. Trudy’s Tex. Star, Inc. v. City of
    Austin, 
    307 S.W.3d 894
    , 905 (Tex. App.—Austin 2010, no pet.). We review a trial court’s
    decision to grant summary judgment de novo. Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005). When reviewing the decision, we consider the evidence in the light
    most favorable to the nonmovant, and we indulge every reasonable inference and resolve all
    doubts in the nonmovant’s favor. Id.; Provident Life & Acc. Ins. v. Knott, 
    128 S.W.3d 211
    ,
    215 (Tex. 2003).
    To obtain summary judgment on their fraudulent-lien claim, the Houchenses were
    required to present evidence conclusively establishing that Pools Unlimited (1) made, presented,
    6
    or used a document with knowledge that it was a fraudulent lien; (2) intended the document to be
    given legal effect as a court document evidencing a valid lien; and (3) intended to cause injury or
    distress. See Tex. Civ. Prac. & Rem. Code § 12.002(a); Serafine v. Blunt, 
    466 S.W.3d 352
    , 363
    (Tex. App.—Austin 2015, no pet.) (listing elements). Because Pools Unlimited filed its lien
    pursuant to Chapter 53 of the Texas Property Code, the Houchenses also were required to show
    that Pools Unlimited intended to defraud them. See Tex. Civ. Prac. & Rem. Code § 12.002(c).
    In support of their motion for summary judgment, the Houchenses submitted
    John’s affidavit, which included as attachments (1) a copy of the Texas Homestead Designation
    that he and Brenda had filed in the Comal County real property records; (2) a copy of the
    lien filed by Pools Unlimited; and (3) a letter dated October 13, 2017, from Pools Unlimited’s
    attorney, transmitting a copy of the lien to the Houchenses. In his affidavit, John states that he
    and Brenda have been married since 2002 and have owned the Property since 2007 and that
    the Property has been continuously designated as their homestead. Further, according to John’s
    affidavit, when he initially met with Ryan in April 2017, he informed Ryan that he and his wife
    resided at the Property. John introduced Ryan to Brenda, but “[a]t no time did [Brenda] ever
    sign a contract with Pools Unlimited.” In addition, John states, neither he nor Brenda ever
    received the version of the contract attached to the Pools Unlimited’s lien (reflecting a total price
    of $69,151), and he never executed a contract with Pools Unlimited that included a provision
    informing him of his right to rescind. The Houchenses also submitted an affidavit from their
    attorney, Bryan Woods, in support of their motion for summary judgment. In his affidavit,
    Woods states, and attached supporting documentation showing, that Pools Unlimited’s corporate
    charter with the Secretary of State had been forfeited prior to its filing of the lien.          The
    Houchenses argue that the trial court did not err in granting their motion for summary judgment
    7
    because this evidence establishes that Pools Unlimited knew that the lien was invalid when
    it was filed.
    We agree that the Houchenses’ summary-judgment evidence suggests that Pools
    Unlimited’s lien was invalid and unenforceable because Texas law required both John and
    Brenda to sign the contract on which the lien was based, see Tex. Prop. Code §§ 41.007(b),
    53.254(a), (c), and because the contract failed to include certain statutorily mandated language,
    informing them of their rights to rescind, see id. § 41.007(a). We cannot agree, however, that
    the evidence conclusively establishes that the lien filed by Pools Unlimited was fraudulent.
    This Court has recognized that in the context of Section 12.002(a) of the Civil Practice and
    Remedies Code, “fraudulent” means “a knowing misrepresentation of the truth or concealment
    of a material fact to induce another to act to his or her detriment.” MFG Fin., Inc. v. Hamlin,
    No. 03-19-007160-CV, 
    2021 Tex. App. LEXIS 4331
    , at *12 (Tex. App.—Austin June 3, 2021,
    pet. denied) (mem. op.) (citing state and federal cases, including Walker & Assocs. Surveying,
    Inc. v. Roberts, 
    306 S.W.3d 839
    , 849 (Tex. App.—Texarkana 2010, no pet.)). Consequently, we
    explained, “an important distinction may be drawn between a document that ‘is factually
    inaccurate in some respect and one that is attempting to perpetrate a fraud’—in other words,
    a lien may be invalid and unenforceable but not necessarily fraudulent.’” Id. at *13 (quoting
    Walker & Assocs., 
    306 S.W.3d at 849
    ). Moreover, “[i]ntent is a fact question uniquely within
    the realm of the trier of fact because it so depends upon the credibility of the witnesses and the
    weight to be given to their testimony.” Spoljaric v. Percival Tours, Inc., 
    708 S.W.2d 432
    , 434
    (Tex. 1986). Therefore, whether a lien filer intended to defraud is ordinarily a question of fact.
    See Hahn v. Love, 
    321 S.W.3d 517
    , 525 (Tex. App.—Houston [1st Dist.] 2009, pet. denied)
    8
    (noting that question of whether debtor conveyed property with intent to defraud is ordinarily
    question of fact).
    In this case, the summary-judgment evidence submitted by the Houchenses fails
    to conclusively establish that Pools Unlimited actually knew that the lien was invalid and
    unenforceable at the time it was filed and that they filed it with the intent to harm or defraud.
    See Walker & Assocs., 
    306 S.W.3d at 847-50
     (concluding that trial court erred in granting
    summary judgment on fraudulent-lien claim because although there was evidence that lien was
    invalid, fact issues existed as to knowledge and intent); Aland v. Martin, 
    271 S.W.3d 424
    ,
    431-32 (Tex. App.—Dallas 2008, no pet.) (concluding that even if there was evidence of
    knowledge by defendant “that a valid lien could not be placed on community property without
    consent of both parties,” it was legally insufficient to prove “intent to cause injury”). While the
    lien filed by Pools Unlimited may be invalid and unenforceable, we conclude that there is a fact
    issue as to whether it is fraudulent.4 See Walker & Assocs., 
    306 S.W.3d at 849
    ; see also Tex.
    Prop. Code §§ 53.160-.162 (providing summary procedure to remove invalid or unenforceable
    mechanic’s lien). The trial court erred in granting summary judgment in favor of the Houchenses
    4
    On appeal, the Houchenses also point to evidence presented at trial that, they contend,
    shows that Pools Unlimited knew that the amount claimed in the lien was incorrect because “it
    did not account for credits owed to the Houchenses.” See Progressive Cnty. Mut. Ins. v. Boyd,
    
    177 S.W.3d 919
    , 921 (Tex. 2005) (“[A] trial court’s erroneous decision on summary judgment
    can be rendered harmless by subsequent events in the trial court.”). Assuming that we may
    consider this later-presented evidence, we disagree that it is sufficient, either alone or in totality,
    to establish the Houchenses’ fraudulent-lien claim as a matter of law. See Gray v. Entis Mech.
    Servs., L.L.C., 
    343 S.W.3d 527
    , 530 (Tex. App.—Houston [14th Dist.] 2011, no pet.)
    (concluding that evidence of refusal to remove lien for disputed amount did not establish intent
    to cause harm as a matter of law).
    9
    on their fraudulent-lien claim against Pools Unlimited. We sustain Pools Unlimited’s second
    appellate issue.5
    Pools Unlimited’s breach-of-contract claim
    In its fifth issue, Pools Unlimited asserts that the trial court erred in granting
    the Houchenses’ motion for directed verdict on its claim for breach of contract against the
    Houchenses.
    A directed verdict is warranted when the evidence is such that no other verdict
    can be reached, and the moving party is entitled to a judgment as a matter of law. Byrd v.
    Delasacha, 
    195 S.W.3d 834
    , 836 (Tex. App.—Dallas 2006, no pet.).                Consequently, in
    reviewing a directed verdict, we apply a legal-sufficiency standard of review. City of Keller,
    168 S.W.3d at 827. When a party moves for directed verdict on an issue on which it does not
    have the burden of proof, we examine the evidence in the light most favorable to the nonmovant
    and decide whether there is any evidence of probative value to raise an issue of material fact
    on the question presented. Exxon Corp. v. Emerald Oil & Gas Co., 
    348 S.W.3d 194
    , 217 (Tex.
    2011). “If the evidence . . . would enable reasonable and fair-minded people to differ in their
    conclusions, the jurors must be allowed to do so.” City of Keller, 168 S.W.3d at 822.
    The Houchenses moved for a directed verdict on Pools Unlimited’s breach-of-
    contract claim on the ground that Pools Unlimited had failed to present legally sufficient
    evidence as to the element of damages. See Elness Swenson Graham Architects, Inc. v. RLJ II-C
    5
    Because we conclude that the Houchenses failed to meet their initial burden on
    summary judgment to present evidence conclusively establishing each element of their
    fraudulent-lien claim, we need not decide Pools Unlimited’s first issue on appeal, that is, whether
    the trial court erred in striking its responsive summary-judgment evidence. See Tex. R. App.
    P. 47.1.
    10
    Austin Air, LP, 
    520 S.W.3d 145
    , 166 (Tex. App.—Austin 2017, pet. denied) (noting that “an
    essential element of breach-of-contract claim is the existence and amount of damages resulting
    from the alleged breach”). Specifically, the Houchenses argued that the evidence presented
    established that Pools Unlimited breached the contract by failing to fully perform and that it
    could not recover under the doctrine of substantial performance because it had failed to present
    any evidence as to the cost of remedying its incomplete or deficient performance.
    As a general rule, a contracting party who is in breach cannot maintain a suit for
    breach. Dobbins v. Redden, 
    785 S.W.2d 377
    , 378 (Tex. 1990); see Mustang Pipeline Co. v.
    Driver Pipeline Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004) (noting that it is “a fundamental principle
    of contract law that when one party commits a material breach of that contract, the other party
    is discharged or excused from further performance”). In the context of construction disputes,
    however, the doctrine of substantial performance provides that a contractor who has
    substantially, although not fully, performed may still sue to enforce an agreement. See Vance v.
    My Apartment Steak House of San Antonio, Inc., 
    677 S.W.2d 480
    , 481 (Tex. 1984); 4922
    Holdings, LLC v. Rivera, 
    625 S.W.3d 316
    , 329 (Tex. App.—Houston [14th Dist.] 2021, pet.
    denied). Because the doctrine of substantial performance, by definition, recognizes that the
    contractor has breached his obligations under the contract, although not materially, “[t]he
    doctrine does not permit the contractor to recover full consideration provided in the contract.”
    4922 Holdings, 625 S.W.3d at 329. Instead, the contractor’s recovery is decreased by the cost of
    remedying the defects or omissions for which he responsible. Id. Therefore, to prevail on a
    theory of substantial performance, the contractor has the burden to prove (1) that he did
    substantially perform, (2) the unpaid amount due to him under the contract, and (3) the cost of
    remedying his incomplete or deficient performance. Vance, 677 S.W.2d at 483.
    11
    In support of their motion for directed verdict, the Houchenses argued that Pools
    Unlimited could not recover for breach of contract based on substantial performance because
    Pools Unlimited had breached the contract and had not presented any evidence as to the cost of
    repairing its defective work. In response, Pools Unlimited did not deny that it had not presented
    evidence as to the cost of repairing any of the complained-of defects. Instead, Pools Unlimited
    explained that it was seeking to recover the full amount of the unpaid invoices under “a straight
    contract theory,” not a substantial-performance theory. In other words, Pools Unlimited argued
    that it was not required to present evidence as to the cost of remedying any incomplete or
    deficient work because it fully performed its obligations under the contract. Based on the record
    before us, we disagree.
    A party breaches a contract when it fails to perform an act that it has contractually
    promised to perform.6 Greene v. Farmers Ins. Exch., 
    446 S.W.3d 761
    , 765 (Tex. 2014). In this
    case, although there was conflicting evidence as to the agreed price for the construction, both
    parties presented evidence establishing that Pools Unlimited had agreed to construct a custom
    rock grotto waterfall with a slide and a spa. The jury was also presented with evidence,
    including John’s testimony and video evidence presented by the Houchenses’ expert, showing
    that the pool was leaking from inside the grotto and in the area between the spa and the pool.
    John also testified that although he and his family have been using the pool, they have not been
    able to use the slide because the plaster on the slide was “cracking” and “too rough.” In addition,
    the updated proposal for $69,151 (which Pools Unlimited contends constitutes the parties’
    6
    The question of what duties exist under a contract is usually a question of law, but any
    dispute concerning the failure of a party to comply with its duties is a fact question for the jury.
    Vast Constr., LLC v. CTC Contractors, LLC, 
    526 S.W.3d 709
    , 718 (Tex. App.—Houston
    [14th Dist.] 2017, no pet.); Trinity Materials, Inc. v. Sansom, No. 03-11-00483-CV, 
    2014 Tex. App. LEXIS 13884
     (Tex. App.—Austin Dec. 31, 2014, pet. denied) (mem. op.).
    12
    contract) shows that Pools Unlimited agreed to install a separate Pentair heater and chiller,
    operational by an “Easy Touch 8 wireless controller.” According to John, because a Pentair
    brand of chiller was not installed, the pool’s electrical and automation systems failed to integrate
    with the Easy Touch wireless controller, as promised. Pools Unlimited did not present any
    evidence to contradict the Houchenses’ claims as to the existence of incomplete or deficient
    work. We conclude that the record conclusively demonstrates that Pools Unlimited failed to
    deliver certain contracted-for pool features to the Houchenses and therefore as a matter of law
    breached at least some of its obligations under the contract.
    On appeal, Pools Unlimited argues that the trial court erred to the extent that it
    relied on evidence of leaks or similar defective construction to conclude Pools Unlimited failed
    to fully perform under the contract. Pools Unlimited asserts that any remaining work on the pool
    was “warranty work” and that Pools Unlimited was excused from performing this work as a
    result of John’s failure to pay the outstanding invoices. Ryan testified that when John informed
    him of the issues, he told John that Pools Unlimited was willing to make any repairs needed after
    he paid the balance of the contract. According to his testimony, Ryan could have repaired the
    leaks using sealants and corrected the appearance of the waterfall by adding additional rocks.
    Further, Ryan told the jury, he could have resolved the issue with the automation system and the
    EasyTouch remote by “add[ing] a relay to turn the unit off and on” after manually setting the
    temperature. Ryan did not make these repairs, however, because John refused to make any
    additional payment.
    Although its argument is not entirely clear, Pools Unlimited seems to contend
    that, despite its incomplete or deficient construction, it fully performed under the contract
    because any further obligation it had to complete or correct its construction was excused by
    13
    the Houchenses’ breach by non-payment. The doctrine of excuse by prior material breach
    provides a theory of recovery, separate from the doctrine of substantial performance, upon which
    a contractor who has failed to fully perform under a construction contract may rely. Another
    Attic, Ltd. v. Plains Builders, Inc., No. 07-08-0312-CV, 
    2010 Tex. App. LEXIS 9620
    , at *8 (Tex.
    App.—Amarillo Dec. 6, 2010, no pet.) (mem. op.). Under this doctrine, a contractor’s failure to
    complete full performance is excused when the other party to the contract has materially
    breached the contract. See 
    id.
     (citing Mustang Pipeline Co., 134 S.W.3d at 196). Nevertheless,
    “[i]n cases where a contractor has not fully performed his obligations under the contract, neither
    the doctrine of substantial performance nor the doctrine of excused performance permits the
    breaching contractor to recover the full consideration provided for in the contract.” Id. at *9.
    Like the doctrine of substantial performance, when a contractor seeks to recover based on a
    theory that his full performance was excused by the other party’s prior material breach, the
    contractor’s recovery is limited to the unpaid amount owed on the contract less the cost of
    remedying the incomplete or deficient performance. Emerson Constr. Co. v. Ranger Fire, Inc.,
    No 03-09-00567-CV, 
    2013 Tex. App. LEXIS 10913
    , *20 (Tex. App.—Austin Aug. 29, 2013,
    no pet.) (mem. op.). Therefore, to the extent Pools Unlimited sought to recover for breach of
    contract based on a theory that its incomplete or deficient performance was excused, it was
    required to present evidence of remediation or repair costs.
    Pools Unlimited sought to recover the full amount of the unpaid invoices, i.e.,
    without any deduction for costs of remedying any incomplete or deficient performance, by
    proceeding on a theory that it fully performed all of its obligations under the construction
    14
    contract or, alternatively, that its performance was excused.7 The undisputed evidence, however,
    conclusively established that Pools Unlimited did not fully perform, but instead provided
    incomplete or deficient performance as to at least some of its contractual obligations. As a
    result, to defeat the Houchenses’ motion for directed verdict, Pools Unlimited was required to
    present at least some probative evidence as to the cost of remedying these defects. Because it
    did not meet this burden, the trial court did not err by granting a directed verdict on Pools
    Unlimited’s breach-of-contract claim. We overrule Pools Unlimited’s fifth issue on appeal.
    The Houchenses breach of contract claim
    In its sixth issue on appeal, Pools Unlimited argues that the trial court erred by
    granting the Houchenses’ motion to disregard the jury’s finding that they sustained zero damages
    and, instead, rendering a judgment notwithstanding the verdict on their breach-of-contract claim
    for $58,500.
    A trial court may disregard a jury finding if the evidence is legally insufficient to
    support it or if a directed verdict would have been proper because a legal principle precludes
    recovery. Ginn v. NCI Bldg. Sys., 
    472 S.W.3d 802
    , 843 (Tex. App.—Houston [1st Dist.] 2015,
    no pet.) (citing Tex. R. Civ. P. 301). In this case, the Houchenses moved to disregard the jury’s
    finding on damages, an issue on which they had the burden of proof at trial, on the ground
    7
    In its third issue, Pools Unlimited asserts that the trial court erred in imposing a
    sanction that prohibited Pools Unlimited from presenting any evidence at trial demonstrating that
    it had commercial general liability (CGL) insurance. Pools Unlimited further argues that the trial
    court erred to the extent its decision to grant the directed verdict was based on Pools Unlimited’s
    failure to maintain CGL insurance during construction of the pool, a requirement under the
    contract. See Tex. R. App. P. 44.1(a). Because we have concluded that other evidence—
    unrelated to whether Pools Unlimited maintained CGL insurance—establishes as a matter of law
    that Pools Unlimited failed to fully perform under the contract, we need not decide this issue.
    See 
    id.
     R. 47.1.
    15
    that there was legally insufficient evidence to support the finding. Consequently, to succeed
    on their motion to disregard, the Houchenses were required to show that there was no evidence
    to support the jury’s zero-damages finding and that the evidence conclusively established the
    damages which they sought, $58,500. See AZZ Inc. v. Morgan, 
    462 S.W.3d 284
    , 291 (Tex.
    App.—Fort Worth 2015, no pet.) (citing Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241
    (Tex. 2001)); Ginn, 
    472 S.W.3d at 843
     (“Specifically, in regard to damages, a trial court
    may render a judgment notwithstanding the verdict and substitute its own judgment only if the
    evidence conclusively proves the damages sought by the movant.” (citing State v. Huffstutler,
    
    871 S.W.2d 955
    , 906-61 (Tex. App.—Austin 1994, no writ))). On review, we employ this
    same legal-sufficiency standard. Republic Petrol., LLC v. Dynamic Offshore Res. NS, LLC,
    
    474 S.W.3d 424
    , 429 (Tex. App.—Houston [1st Dist.] 2015, pet. denied).
    We begin our analysis of the evidence with the charge as submitted to the jury.8
    In Question No. 3 of the court’s charge, the jury was asked to determine:
    What sum of money, if any, if paid now in cash would fairly and reasonably
    compensate the Houchenses for their damage, if any, which resulted from any
    such conduct? Consider the following elements of damage, if any, and none
    other.
    8
    Because the Houchenses sought to recover remedial damages, they were required to
    prove the cost to complete or repair the construction less the unpaid balance on the contract
    price. McGinty v. Hennen, 
    372 S.W.3d 625
    , 627 (Tex. 2012) (explaining that one measure of
    damages for “breach of a construction contract [is] remedial damages, which is the cost to
    complete or repair less the unpaid balance on the contract price”). In addition, the Houchenses
    were required to prove that the damages sought were reasonable and necessary. 
    Id.
     (citing
    Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 200 (Tex. 2004)). Although there
    was evidence of an unpaid balance on the contract, and the jury charge failed to properly instruct
    the jury to deduct any unpaid balance on the contract price, no party objected to the omission.
    See, e.g., Osterberg v. Peca, 
    12 S.W.3d 31
    , 55 (Tex. 2000) (absent preserved meritorious
    complaint of charge error, challenges to sufficiency of evidence supporting jury findings are
    evaluated in light of charge as submitted).
    16
    ...
    1.     The reasonable and necessary cost to repair the pool and its related
    features? $___
    The jury answered this question: “$0.”
    In support of their claim for cost-to-repair damages, the Houchenses presented
    testimony from Michael Jentsch, whom they had designated as an expert in pool-repair
    methodology and costs. After explaining his qualifications in pool-construction repair, Jentsch
    discussed the various deficiencies he observed with the Houchenses’ pool. In part, he testified
    that he examined the chiller installed by Pools Unlimited and that he called the manufacturer of
    the automation-system controller. According to Jentsch’s testimony, the manufacturer informed
    him that the brand of chiller installed by Pools Unlimited would not integrate with the
    automation system. Jentsch told the jury that, in his opinion, the only way to correct this issue
    would be to remove the chiller installed by Pools Unlimited and replace it with a Pentair chiller,
    which in his opinion would cost $7,000.
    In addition, Jentsch testified that he observed “water leaking underneath the
    spillway of the spa,” “calcium deposits on the face of the rock [grotto],” and “calcium
    deposits . . . and minor cracking” on the slide.        Jentsch detailed his observations using
    photographs of the leaks in the spa and the rock grotto. As to the slide, he testified that it was
    dangerous due to “separation of the exterior veneer where the plaster met that veneer.” Jentsch
    told the jury that proper repair of the “spa to spillway leak” would include removing the coping
    and exterior stone and installing supplemental steel and that the reasonable and necessary cost to
    make these repairs was $9,000. Similarly, according to Jentsch, repair of the leaks in the rock
    grotto would require removing the stones, slide, and veneers, demolishing a portion of the
    17
    grotto to make “more of a round bowl,” and then rebuilding the grotto. Jentsch testified that, in
    his opinion, the reasonable and necessary cost to repair the custom rock grotto and waterfall
    was $25,000 to $30,000.       Finally, Jentsch testified that there would be about $10,000 in
    miscellaneous costs associated with the repair work, such as clean up and teaching the
    homeowners how to “run the pool, how to run the equipment.” In summary, Jentsch testified
    that the reasonable and necessary cost to repair the pool, in total, was $58,500.
    In their motion to disregard, and now on appeal, the Houchenses contend that
    Jentsch’s testimony constitutes uncontradicted and conclusive evidence on the issue of damages.
    As a general rule, opinion testimony is not conclusive or binding on the factfinder. McGalliard
    v. Kuhlmann, 
    722 S.W.2d 694
    , 697 (Tex. 1986). Instead, the jury as the trier of fact is the sole
    judge of the credibility of the witnesses and the weight to be given their testimony. Id. at 696.
    Moreover, a jury is generally afforded considerable discretion in evaluating evidence on the issue
    of damages. Id. at 697.
    Expert testimony is permitted when the expert’s scientific, technical, or other
    specialized knowledge will assist the trier of fact to understand the evidence or to determine a
    fact in issue. Tex. R. Evid. 702. However, uncontroverted expert testimony is only conclusive
    on an issue if the nature of the subject matter requires the factfinder to be guided solely by the
    opinion of experts and the evidence is otherwise credible and free from contradictions. Uniroyal
    Goodrich Tire Co. v. Martinez, 
    977 S.W.2d 328
    , 338 (Tex. 1998); Liberty Mut. Ins. v. Burk, 
    295 S.W.3d 771
    , 797 (Tex. App.—Fort Worth 2009, no pet.); Flores v. Cuellar, 
    269 S.W.3d 657
    ,
    660 (Tex. App.—San Antonio 2008, no pet.). Whether expert testimony is necessary on a
    contested issue is a question of law which courts review de novo. Mack Trucks, Inc. v. Tamez,
    
    206 S.W.3d 572
    , 583 (Tex. 2004).
    18
    This Court has previously recognized that in some cases, the reasonable cost to
    repair real property, including residential pool construction, may be established through lay
    testimony. See Seasha Pools, Inc. v. Hardister, 
    391 S.W.3d 635
    , 641 (Tex. App.—Austin 2012,
    no pet.) (concluding that contractor’s bids and lay testimony from property owner that bids to
    repair pool and light fixture were reasonable “were competent evidence from which factfinder
    could determine the reasonable cost of repairing the pool and light fixture”); see also
    McGalliard, 722 S.W.2d at 697 (“We do not believe the subject of house repairs to be one for
    experts or skilled witnesses alone.”). In addition, the record in this case does not suggest that
    the proposed repairs of the Houchenses’ pool were so technical or complex that the issue of
    reasonable cost of repair required expert testimony.9 While Jentsch’s “scientific, technical, or
    9
    The Houchenses contend that expert testimony was required in this case because “[the]
    repairs require technical knowledge and skills if performed correctly.” In support of their
    argument, the Houchenses rely on a case from this Court, Paschal v. Engle, in which we stated,
    “The necessity and reasonableness of repair costs are issues that require specialized or technical
    knowledge falling within the exclusive domain of an expert.” No. 03-16-00043-CV, 
    2016 Tex. App. LEXIS 9161
    , *5 (Tex. App.—Austin Aug. 23, 2016, no pet.) (mem. op.). However,
    whether expert testimony was required was not at issue in Paschal, and this Court did not
    establish a bright-line rule that expert testimony is required to prove reasonableness of repair
    costs in every case. See id. at *6 (noting that “the parties do not dispute that the Paschals were
    required to adduce expert witness testimony to prove the amount of the reasonable and necessary
    cost to repair damages to their buildings and piano caused by Engle’s alleged negligence”).
    Instead, expert testimony may only be required when the issue of cost of repair is especially
    technical or complex, which depends on the unique circumstances of each case. See McGalliard
    v. Kuhlmann, 
    722 S.W.2d 694
    , 696 (Tex. 1986) (noting that “the subject of house repairs [is not]
    one for experts or skilled witnesses alone”); see also Stevens v. Avent, No. 07-20-00265-CV,
    
    2022 Tex. App. LEXIS 961
    , *14 (Tex. App.—Amarillo Feb. 9, 2022, no pet.) (mem. op.)
    (declining to establish a “bright-line rule that expert testimony is required to support an award of
    remedial damages” and concluding that non-expert testimony and exhibits were sufficient to
    support award of repair costs in dispute over home renovations); Seasha Pools, Inc. v. Hardister,
    
    391 S.W.3d 635
    , 641 n. 8 (Tex. App.—Austin 2012, no pet.) (concluding that expert testimony
    was not required to establish cost to repair plaintiff’s pool because “[t]here is nothing in the
    record to indicate that the cost associated with replastering a pool is so technical or complex that
    it required expert testimony”). But see Pjetrovic v. Home Depot, 
    411 S.W.3d 639
    , 649 (Tex.
    App.—Texarkana 2013, no pet.) (determining that reasonableness of cost to perform major home
    19
    specialized knowledge” may have been helpful to the jury and thus admissible under Rule 702,
    the Houchenses were not required to rely on expert testimony to prove the necessary and
    reasonable cost to repair their pool. Consequently, the jury was not bound to accept Jentsch’s
    opinion as conclusive. See McGalliard, 722 S.W.2d at 697 (“[T]he judgments and inferences of
    experts or skilled witnesses, even when uncontroverted, are not conclusive on the jury or trier of
    fact, unless the subject is one for experts or skilled witnesses alone . . . .”). The jury could
    instead consider all of the testimony and evidence presented to assess the credibility and weight
    to be given to Jentsch’s opinion. See id. at 696.
    Prior to Jentsch’s testimony, the jury was presented with evidence showing that
    the price to construct the entire pool, including the spa and custom rock grotto, was $69,151,
    according to Pools Unlimited, or $58,711, according to the Houchenses.           In light of this
    evidence, the jury could have discredited Jentsch’s opinion that $58,500 constitutes a reasonable
    cost to repair the rock grotto waterfall, slide, spa, and automation system. In addition, Jentsch
    acknowledged on cross examination that although the leaks were first observed when the pool
    was filled with water in 2017, the repairs still had not been made, more than three years later.
    Although Jentsch did not concede that the cost of repairs would have been less had the repairs
    been made earlier, he acknowledged that the delay may have resulted in the need for additional
    repairs. Id. at 697 (expert’s testimony that he had not seen house until almost two years after
    leaking began and, therefore, could not testify as to cost of repairs at time, “raised a question
    concerning [his] credibility”).
    renovations required expert testimony). We conclude that the reasonableness of the costs at
    issue in this case, which largely concern repair of a rock-grotto feature and the purchase of
    equipment, is not so specialized or technical that expert testimony was required.
    20
    Viewing the evidence in the light most favorable to the jury’s finding, we
    conclude that Jentsch’s testimony does not conclusively establish that the reasonable and
    necessary cost to repair the Houchenses’ pool is $58,500. See Dow Chem., 46 S.W.3d at 241.
    As a result, the trial court erred in awarding $58,500 in damages to the Houchenses on their
    breach-of-contract claim. We sustain Pools Unlimited’s sixth appellate issue.10
    By conditional cross-point, the Houchenses assert that even if we conclude that
    the trial court erred in granting the judgment notwithstanding the verdict, we cannot render
    judgment on the verdict because the evidence is factually insufficient to support the jury’s
    finding that the Houchenses suffered zero damages.11 When a party challenges the factual
    sufficiency of an adverse finding on which it had the burden of proof, the party must demonstrate
    that the adverse finding is against the great weight and preponderance of the evidence. Id.
    at 242. In assessing whether this burden has been met, we consider all evidence presented to
    the jury, including evidence in favor of and contrary to the challenged finding. Cain v. Bain,
    
    709 S.W.2d 175
    , 176 (Tex. 1986). Because it is the jury’s role to evaluate the credibility of the
    witnesses and reconcile any inconsistencies, Anderson v. Durant, 
    550 S.W.3d 605
    , 616 (Tex.
    2018), we must not substitute our judgment for the jury’s merely because we would have
    10
    In its fourth appellate issue, Pools Unlimited contends that the trial court erred in
    allowing Jentsch to testify as to the cost of repairs and that the testimony resulted in an
    improper judgment. Because we conclude that the trial court erred in rendering a judgment
    notwithstanding the verdict based on the evidence before it, including Jentsch’s testimony, we
    need not decide this issue. See Tex. R. App. P. 47.1.
    11
    Ordinarily, when we determine on review that the trial court erred in granting a
    judgment notwithstanding the verdict, the proper remedy is to reverse and render a judgment on
    the jury’s verdict. Dudley Constr., Ltd. v. ACT Pipe & Supply, Inc., 
    545 S.W.3d 532
    , 537-38
    (Tex. 2018). However, when the appellee presents by cross-point sufficient grounds, including
    factual sufficiency, to vitiate the verdict or prevent an affirmance of the judgment had one been
    entered on the verdict, the cause should instead be remanded for further proceedings. 
    Id.
     (citing
    Tex. R. App. P. 38.2(b)).
    21
    weighed the evidence differently or reached a differed conclusion, Golden Eagle Archery, Inc. v.
    Jackson, 
    116 S.W.3d 757
    , 761 (Tex. 2003).
    As previously discussed, the jury was presented with evidence, including
    testimony from John and Jentsch, demonstrating that (1) the pool was leaking from inside the
    custom rock grotto and between the spa and the pool; (2) the plaster on the slide was “cracking”
    and “too rough” to use; and (3) the automation system was not fully compatible with the chiller
    installed by Pools Unlimited. Although the evidence is not conclusive as to the necessity of the
    repair methods proposed by Jentsch or as to the reasonableness of the cost of repairs as sought by
    the Houchenses, there is nothing in the record contradicting the existence of the defects, Pools
    Unlimited’s construction as the cause of the defects, or the need for repairs. As a result, the
    jury’s finding that “the reasonable and necessary cost to repair the pool and its related features”
    is zero is against the great weight and preponderance of the evidence. See Seasha Pools,
    391 S.W.3d at 642 (concluding that evidence was factually insufficient to support finding of zero
    damages on cost-of-repair damages because nothing contradicted written bids and testimony that
    those bids represented reasonable cost of repair). We sustain the Houchenses’ cross-point.
    CONCLUSION
    Having concluded that the trial court did not err in granting a directed verdict on
    Pools Unlimited’s claim for breach of contract, we affirm the trial court’s judgment that Pools
    Unlimited take nothing on this claim.      Because the trial court erred by granting summary
    judgment in favor of the Houchenses on their fraudulent-lien claim and by rendering a judgment
    notwithstanding the verdict on their breach-of-contract claim, we reverse the trial court’s
    judgment as to these claims, including the trial court’s award of actual damages, exemplary
    22
    damages, attorney’s fees, and expenses, all which were predicated on these claims. See Tex.
    Civ. Prac. & Rem. Code § 12.002 (actual damages, attorney’s fees, exemplary damages for
    fraudulent lien), § 38.001 (attorney’s fees for breach of contract); Seasha Pools, 391 S.W.3d.
    at 643 (reversing for further proceedings on issue of damages and for further consideration of
    attorney’s fees).
    Because there is a fact issue as to whether Pools Unlimited’s mechanic’s lien was
    fraudulent, we remand the Houchenses’ fraudulent-lien claim for a new trial. Also, because the
    evidence is factually insufficient to support the jury’s finding of zero damages, we remand the
    Houchenses’ breach-of-contract claim for a new jury trial. See Tex. R. App. P. 44.1(b); Rancho
    La Valencia, Inc. v. Aquaplex, Inc., 
    383 S.W.3d 150
    , 152 (Tex. 2012) (per curiam) (explaining
    that appellate court could not remand for new trial on damages only; under Rule 44.1(b), “it must
    remand for a new trial on both liability and damages”).
    __________________________________________
    Chari L. Kelly, Justice
    Before Chief Justice Byrne, Justices Triana and Kelly
    Affirmed in Part; Reversed and Remanded in Part on Motion for Rehearing
    Filed: November 9, 2022
    23