EPGT Texas Pipeline, L.P. v. Harris County Flood Control District , 176 S.W.3d 330 ( 2004 )


Menu:
  • 176 S.W.3d 330 (2004)

    EPGT TEXAS PIPELINE, L.P., Successor to PG & E Texas Pipeline, L.P., Appellant,
    v.
    HARRIS COUNTY FLOOD CONTROL DISTRICT, Appellee.

    No. 01-02-01056-CV.

    Court of Appeals of Texas, First District, Houston.

    August 12, 2004.
    Rehearing Overruled September 24, 2004.

    *333 Jack D. Ballard, Mary Jo Cantu, The Ballard Law Firm, Houston, TX, for Appellant.

    Dennis S. Dresden, Benckenstein, Norvell & Nathan, LLP, Mark Allen, Tekell Book, Robin T. Pickle, Frank E. Sanders, Assistant County Attorney, Houston, TX, for Appellee.

    Panel consists of Justices ALCALA, HIGLEY, and BLAND.

    OPINION

    JANE BLAND, Justice.

    EPGT Texas Pipeline, L.P., successor to PG & E Texas Pipeline, L.P. (PG & E)[1] appeals a final summary judgment granted in favor of the appellee, Harris County Flood Control District ("HCFCD"). PG & E seeks damages resulting from the herniation and displacement of its gas pipeline in the City of South Houston, as a result of HCFCD's nearby drainage excavation project. We conclude that (1) the Texas Tort Claims Act ("TTCA") governs sovereign immunity for claims in tort against the State and the political subdivisions of the State, and PG & E does not allege a claim in tort for which the TTCA provides a waiver of immunity; and (2) the Water Code waives HCFCD's immunity as to PG & E's breach of contract claim, but the trial court properly granted summary judgment, because PG & E is not an intended third party beneficiary to the contract upon which it bases its claim. We therefore affirm the summary judgment as to PG & E's tort and contract claims. We reverse and render the summary judgment on PG & E's inverse condemnation claim, however, as the Harris County Courts at Law have exclusive jurisdiction over such a claim, and the trial court thus lacked jurisdiction to enter summary judgment on the claim.

    The Facts and the Procedural History

    In 1961, HCFCD acquired an easement and a perpetual license from the Galveston, Houston, and Henderson Railroad Company (the "Railroad"), for real property located in Berry Bayou, Harris County. PG & E owns, operates, and maintains a natural gas pipeline lying in an adjacent right of way, acquired from its predecessor-in-interest, the Lo-Vaca Gathering Company.

    In 1997, HCFCD executed a construction contract with Ramex Construction Company (Ramex), to improve drainage in the existing Berry Bayou ditch. PG & E's pipeline runs across and parallel to the Ramex construction site. During construction, Ramex used motor-driven vehicles to remove two concrete double-box culvert structures that ran parallel to the PG & E pipeline. Ramex also removed soil supporting both the concrete double-box culverts and PG & E's pipeline. Ramex's actions removed the lateral support of the pipeline, causing it to shift sideways and downward four feet. The pipeline sustained a lateral bulge of approximately twelve and one-half feet along a 500 foot portion of the pipeline. Because of these events, PG & E had to remove the pipeline from service and repair it.

    *334 In November 1998, PG & E sued both HCFCD and Ramex for breach of contract, declaratory judgment, strict liability for removal of naturally necessary support, and negligence. PG & E also asserted an inverse condemnation claim solely against HCFCD. In a second amended petition, PG & E pleaded that the TTCA conferred jurisdiction upon the trial court. In a later supplemental amended petition, PG & E further alleged that HCFCD had consented to suit for breach of contract, based upon section 49.006 of the Texas Water Code. PG & E sought $488,251.78 in actual damages for repairs and lost profits, and $500,000 in exemplary damages, as well as attorney's fees and interest. HCFCD counterclaimed for trespass and negligence, alleging that PG & E damaged the bayou, resulting in additional project costs to it of up to $401,699.65.

    In December 2001, HCFCD filed a traditional and a no-evidence motion for summary judgment. In March 2002, the trial court granted HCFCD's motions. PG & E appeals the trial court's final judgment granting HCFCD's motions for summary judgment.[2]

    HCFCD's Sovereign Immunity

    A motion for summary judgment may raise a challenge to a trial court's subject-matter jurisdiction. City of Hedwig Village Planning & Zoning Comm'n v. Howeth Invs., Inc., 73 S.W.3d 389, 391 (Tex.App.-Houston [1st Dist.] 2002, no pet.). A plaintiff then bears the burden of alleging facts affirmatively showing that a trial court has subject-matter jurisdiction. Tex. Dep't of Parks & Wildlife v. Miranda, 133 S.W.3d 217, 226 (Tex.2004); Bland ISD v. Blue, 34 S.W.3d 547, 554 (Tex.2000); Tex. Ass'n of Bus. v. Tex. Air Control Bd., 852 S.W.2d 440, 446 (Tex.1993). A court should take the plaintiff's allegations to be true and construe all inferences in favor of jurisdiction. Tex. Ass'n of Bus., 852 S.W.2d at 446. The question whether a trial court has subject-matter jurisdiction over a claim is one of law, and thus we review it de novo. Miranda, 133 S.W.3d at 226.

    Under the common-law doctrine of sovereign immunity, a unit of government cannot be sued without its consent. State v. Terrell, 588 S.W.2d 784, 785 (Tex.1979); Dillard v. Austin Indep. Sch. Dist., 806 S.W.2d 589, 592 (Tex.App.-Austin 1991, writ denied). Sovereign immunity protects a governmental unit in two basic ways. First, the state is immune from suit against it, regardless of the state's liability. Federal Sign v. Tex. Southern Univ., 951 S.W.2d 401, 405 (Tex.1997); Dillard, 806 S.W.2d at 592. Second, the state also is immune from liability, even if the state otherwise has consented to be sued. Federal Sign, 951 S.W.2d at 405; Dillard, 806 S.W.2d at 592. "Immunity from suit bars a suit against the State unless the State expressly gives its consent to the suit," while "[i]mmunity from liability protects the State from judgments even if the Legislature has expressly given consent to the suit." Federal Sign, 951 S.W.2d at 405. If applicable, sovereign immunity shields governmental entities from liability, including protection from suit for the vicarious acts of government agents or employees acting in the scope of their employment. Bennett v. Tarrant County Water & Control Imp. Dist. No. 1, 894 S.W.2d 441, 450 (Tex.App.-Fort Worth 1995, writ denied). Those governmental entities immune from suit include statutorily created special purpose districts like HCFCD. Id. The TTCA waives sovereign immunity from liability *335 in certain circumstances, and correspondingly waives immunity from suit, to the extent immunity from liability has been waived under the Act. TEX. CIV. PRAC. & REM.CODE ANN. § 101.021, .025 (Vernon 1997).

    Here, HCFCD moved for summary judgment claiming immunity from suit. PG & E thus must allege facts sufficient to show that HCFCD waived immunity to the causes of action PG & E asserts. PG & E maintains that HCFCD has waived immunity from suit pursuant to section 101.021(1) of the TTCA and section 49.006 of the Texas Water Code. See TEX. CIV. PRAC. & REM.CODE ANN. § 101.021; TEX. WATER CODE ANN. § 49.006 (Vernon 2000).

    Standard of Review

    Summary judgment for a defendant is proper if the defendant negates at least one element of each of the plaintiff's theories of recovery, or pleads and conclusively establishes each element of an affirmative defense. Science Spectrum, Inc. v. Martinez, 941 S.W.2d 910, 911 (Tex.1997). A "no evidence" motion for summary judgment is proper if, after adequate time for discovery, the movant shows that the nonmovant has produced no evidence on at least one essential element of the nonmovant's theory of recovery. See TEX.R. CIV. P. 166a(I); Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp., 994 S.W.2d 830, 834 (Tex.App.-Houston [1st Dist.] 1999, no pet.). When reviewing a summary judgment, we view all evidence in a light favorable to the nonmovant, and indulge every reasonable inference in the nonmovant's favor. Science Spectrum, 941 S.W.2d at 911. Sovereign immunity is an affirmative defense. Harris County v. Louvier, 956 S.W.2d 106, 107 (Tex.App.-Houston [14th Dist.] 1997, no pet.).

    Thus, as movant on the affirmative defense of sovereign immunity, HCFCD has the burden to establish all the essential elements of the defense as a matter of law. Montgomery v. Kennedy, 669 S.W.2d 309, 310-11 (Tex.1984). Once a movant establishes sovereign immunity as a matter of law, the burden of production shifts to the non-movant to establish a waiver of immunity. See Medrano v. City of Pearsall, 989 S.W.2d 141, 144 (Tex.App.-San Antonio 1999, no pet.); Ager v. Wichita Gen. Hosp., 977 S.W.2d 658, 660 (Tex.App.-Fort Worth 1998, no pet.); see also Casso v. Brand, 776 S.W.2d 551, 556 (Tex.1989) (burden does not shift to non-movant unless movant establishes defense as matter of law). Though the burden of production shifts, the burden of proof remains with the movant to conclusively establish its entitlement to summary judgment on its affirmative defense as a matter of law. See Zale Corp. v. Rosenbaum, 520 S.W.2d 889, 891 (Tex.1975); Garza v. Williams Bros. Constr. Co., 879 S.W.2d 290, 295 (Tex.App.-Houston [14th Dist.] 1994, no writ); see also Jenkins v. Guardian Indus. Corp., 16 S.W.3d 431, 439 (Tex.App.-Waco 2000, pet. denied); Rios v. Texas Commerce Bancshares, Inc., 930 S.W.2d 809, 818 (Tex.App.-Corpus Christi 1996, writ denied).

    The Negligence Claim

    The TTCA waives sovereign immunity for property damage in the following circumstances: (1) an injury caused by a government employee's operation or use of a motor-driven vehicle or motor-driven equipment and (2) the government employee would be personally liable to the claimant according to Texas law. TEX. CIV. PRAC. & REM.CODE ANN. § 101.021(1)(A)-(B) (Vernon 1997). Relying on these provisions, PG & E contends that the Legislature has waived HCFCD's sovereign immunity as to PG & E's negligence claim for property damage. HCFCD responds *336 that it did not waive its sovereign immunity as to PG & E's negligence claims, because the undisputed facts show that no State employee operated a motor-driven vehicle that caused the damage to PG & E's pipeline. Rather, Ramex, an independent contractor, operated the motor-driven vehicles. The waiver of immunity provision in the TTCA thus does not apply under these facts. PG & E replies that a fact issue exists regarding whether Ramex acted as HCFCD's independent contractor — as HCFCD contends — or whether Ramex was a de facto state "employee," — as PG & E contends-thus falling within the TTCA waiver of immunity.

    Section 101.021 of the TTCA provides that a governmental unit is liable for:

    property damage, personal injury, and death proximately caused by the wrongful act or omission or the negligence of an employee acting within his scope of employment. . . .

    TEX. CIV. PRAC. & REM.CODE ANN. § 101.021(1) (emphasis added).

    The TTCA further defines "employee" as

    a person, including an officer or agent, who is in the paid service of a governmental unit by competent authority, but does not include an independent contractor, an agent or employee of an independent contractor, or a person who performs tasks the details of which the governmental unit does not have the legal right to control.

    Id. § 101.001(2) (Vernon Supp.2004) (emphasis added). Thus, whether the trial court properly granted summary judgment on PG & E's tort claims depends on whether fact issues exist as to Ramex's status as an independent contractor.

    In determining whether a worker is an employee or an independent contractor, the focus is on who has the right to control the details of the work. Exxon Corp. v. Tidwell, 867 S.W.2d 19, 21 (Tex.1993). In determining whether Ramex is an independent contractor, we examine: (1) the independent nature of its business; (2) its obligation to supply necessary tools, supplies, and materials; (3) its right to control the progress of the work; (4) the duration of its employment; and (5) the method by which it is paid, whether by the time or by the job. Duran v. Furr's Supermarkets, Inc., 921 S.W.2d 778, 786 (Tex.App.-El Paso 1996, writ denied). A "possibility" of control is not evidence of a right to control. Coastal Marine Serv. of Tex., Inc. v. Lawrence, 988 S.W.2d 223, 226 (Tex.1999). Determining whether a contract gives a right of control is generally a question of law for the court, rather than a question of fact for the jury. Dow Chem. Co. v. Bright, 89 S.W.3d 602, 606 (Tex.2002). If the controlling facts are undisputed, the question whether the relationship which exists is that of an employee or of an independent contractor is a question of law. Sherard v. Smith, 778 S.W.2d 546 (Tex.App.-Corpus Christi 1989, writ denied).

    HCFCD presented the following undisputed evidence to show that Ramex was an independent contractor on the Berry Bayou Project: (1) Ramex furnished the equipment and supplies to perform the job, including the motor-driven vehicles at issue; (2) HCFCD hired Ramex by the job, as a result of a bid process; and (3) HCFCD paid Ramex by the job, according to its bid. HCFCD further provided deposition testimony from Rosbell Ramos, a Ramex employee, that his company decided the means and methods used to remove the double-box culverts, and that no one from Harris County told him how to do it. We hold that HCFCD presented competent summary judgment evidence to establish *337 Ramex's status as an independent contractor.

    In response, PG & E points out that Brenda Trevino, the HCFCD Berry Bayou project manager, stated in deposition testimony that PG & E's pipeline must be "field-located," by HCFCD before construction commences. Ms. Trevino also testified that HCFCD made the decision to install sheetpile walls to provide additional lateral support to the pipeline. Trevino noted, however, that no one from HCFCD evaluated "the sufficiency of Ramex's work in connection with the removal of the original section of box culvert." When asked about what she relied on in determining whether Ramex's work was sufficient, she testified, "I'm relying on the fact that the construction project is put in place as per the plans and on the expertise of the field inspection crew and the experts that have been employed." She further stated that the field inspection crew consisted of HCFCD personnel that observed Ramex's activities.

    In determining independent contractor status, the focus is on the right to control the details of the work. Exxon Corp., 867 S.W.2d at 21 (emphasis added). Although PG & E presented evidence that HCFCD participated in the construction plans and specifications, and made inspections as to the completion of the work according to the plans, Trevino's testimony does not create a fact issue that HCFCD had a right to control, or did control, the details of Ramex's work with respect to the operation of a motor-driven vehicle, the only type of activity for which HCFCD waives its immunity in tort. Thus, we hold that Trevino's testimony does not create a fact issue regarding HCFCD's waiver of immunity under the TTCA.

    In addition to Trevino's testimony, PG & E relies on conditions in the HCFCD/Ramex contract to establish that Ramex is not an independent contractor. These provisions acknowledge that a county-designated engineer may furnish specifications to, supervise, and ask Ramex to discharge, any Ramex employees who do not "perform work in a proper and skillful manner." PG & E contends that the authority granted in these contract provisions establishes a fact issue as to whether HCFCD retained control over Ramex. These contract provisions, however, indicate control over the general requirements of the project, and its proper completion, but do not show control over the details of Ramex's work with regard to Ramex employees use of motor-driven vehicles — the standard for determining whether a party is an employee or independent contractor within the scope of section 101.021. See TEX. CIV. PRAC. & REM.CODE ANN. § 101.021; Exxon Corp., 867 S.W.2d at 21; see also St. Joseph Hosp. v. Wolff, 94 S.W.3d 513, 542 & n. 91 (Tex.2003); Hoechst Celanese Corp. v. Compton, 899 S.W.2d 215, 220 (Tex. App.-Houston [14th Dist.] 1994, no writ) (finding off-duty officers hired by private corporation to be independent contractors because, in part, they furnished their own equipment). In particular, the fact that the engineer reserved the right to ask Ramex to remove an objectionable worker does not mean that HCFCD controlled the details of Ramex's work. See Thomas v. Harris County, 30 S.W.3d 51, 54 (Tex.App.-Houston [1st Dist.] 2000, no pet.) (holding physicians who treated inmates at county jail were not county employees because county merely contracted with their employer for medical services, and physicians were paid by employer rather than county). As the contract acknowledges, Ramex is the ultimate decision-maker to hire and to fire — not the county or its engineer.

    PG & E further relies on a project manual HCFCD sent to Ramex and all other *338 bidders for the project. PG & E contends that this manual requires Ramex to remove the double-box culverts that provided the lateral support to the soil surrounding the pipeline. In the manual, section B of the Work Sequence states that "a major work activity" includes removing an existing 2-12'×12'×600 concrete box. PG & E also directs us to a manual provision dictating that HCFCD decide the controls Ramex is to employ, including erosion and sediment controls. Project specifications, however, do not show a right to control the details of the work. For example, the manual does not direct HCFCD to use motor-driven equipment to remove the double-box culverts supplying the lateral support. Moreover, PG & E has not presented any evidence to show that the manual provisions and directions are in fact attributable to HCFCD. The manual on which PG & E relies indicates that TSC Engineering prepared it. PG & E neither disputes the manual's author, nor does it allege that TSC Engineering also served as HCFCD's employee for purposes of the TTCA. Accordingly, PG & E has not established a fact issue concerning HCFCD's requisite right of control over the details of Ramex's work, based on the project manual's provisions.

    After reviewing the summary judgment evidence in a light most favorable to PG & E, including the contract, the deposition testimony, and the manual, we agree with the trial court that PG & E did not raise a genuine issue of fact as to whether HCFCD exerted sufficient control over the details of Ramex's work.[3] If no dispute exists as to the controlling facts and only one reasonable conclusion can be inferred, the question of whether the relationship which exists is that of an employee or an independent contractor is a question of law. Bright, 89 S.W.3d at 606; Sherard, 778 S.W.2d at 548. We therefore conclude that the trial court properly granted summary judgment to HCFCD on PG & E's negligence claim.

    Strict Liability

    PG & E contends that the trial court erred in granting summary judgment on its strict liability claims for removal of the pipeline's lateral and subjacent support. HCFCD moved for summary judgment, contending that PG & E did not allege any waiver of immunity from suit on this ground. PG & E responds that TTCA section 101.021(1) waives HCFCD's sovereign immunity. See TEX. CIV. PRAC. & REM. CODE ANN. 101.021(1). Although some authority exists for strict liability claims for removal of lateral and subjacent support,[4] we disagree that section 101.021(1) waives HCFCD's immunity from suit for such claims.

    HCFCD is immune from suit unless the Legislature has waived immunity in plain and unambiguous terms. Kerrville State Hosp. v. Fernandez, 28 S.W.3d *339 1, 3 (Tex.2000); Fed. Sign, 951 S.W.2d at 405. As PG & E's strict liability claim does not allege a wrongful act or omission distinct from its negligence claims, PG & E's cause of action does not fall within the exception to sovereign immunity under section 101.021(1). Moreover, it is not within our authority to establish such an exception — such a function falls to the Legislature. See Kerrville State Hosp., 28 S.W.3d at 3; TEX. GOV'T CODE ANN. § 311.034 (Vernon Supp.2004) ("[A] statute shall not be construed as a waiver of sovereign immunity unless the waiver is effected by clear and unambiguous language.").

    PG & E has failed to present any authority, and we find none, allowing a party to pursue a claim of strict liability for removal of lateral and subjacent support against a governmental entity cloaked with sovereign immunity. At least one other court has held that strict liability claims do not fall within the waiver provisions in section 101.021. See Univ. of N. Tex. v. Harvey, 124 S.W.3d 216 (Tex.App.-Fort Worth 2003, pet. filed). In Harvey, the Fort Worth Court of Appeals held that the Legislature did not waive strict liability claims under TTCA section 101.021(2). Under these facts, we agree, and conclude that the trial court properly granted HCFCD's summary judgment on PG & E's strict liability claim.

    Breach of Contract

    The trial court granted HCFCD's summary judgment and no-evidence summary judgment on PG & E's breach of contract claim. HCFCD moved for summary judgment on the grounds that (1) it is immune from suit, and (2) PG & E is not a third party beneficiary of the contract it claims HCFCD breached. PG & E responds that the trial court has jurisdiction over contract claims against HCFCD based on section 49.066 of the Texas Water Code and section 262.001 of the Local Government Code. PG & E further contends that it is an intended third party beneficiary of the HCFCD/Railroad contract. We first address whether PG & E pleaded a basis for waiving HCFCD's sovereign immunity.

    The Texas Water Code provides:

    A district may sue and be sued in the courts of this state in the name of the district by and through its board. A suit for contract damages may be brought against a district only on a written contract of the district approved by the district's board. All courts shall take judicial notice of the creation of the district and of its boundaries.

    TEX. WATER CODE ANN. § 49.006(a).

    Courts have construed similar language in other statutes to waive immunity from suit. See Missouri Pac. R. Co. v. Browns Navigation Dist., 453 S.W.2d 812, 813-14 (Tex.1970); United Water Serv. v. City of Houston, 137 S.W.3d 747 (Tex.App.-Houston [1st Dist.] 2004, pet. filed); Loyd v. ECO Res., Inc., 956 S.W.2d 110, 122 (Tex.App.-Houston [14th Dist.] 1997, no pet.). We hold that the "sue and be sued" statutory language waives HCFCD's immunity from suit by legislative consent.[5] Accordingly, we address whether PG & E raises a fact issue as to its status as a third party beneficiary.

    To claim third party beneficiary status, PG & E relies on language in the HCFCD/Railroad contract that obligates *340 HCFCD not to interfere with the activities of the Railroad's licensees, in particular:

    It is expressly agreed and understood that this license is made and given on condition that [HCFCD's] use of the property under this license shall not interfere with the [Railroad's] and its successors', licensees', invitees' and assigns' operations over, or upon said property, nor with maintenance of or repairs to its tracks or any of its facilities upon said property.

    PG & E argues that this section confers enforceable third party rights upon a limited class of persons, including the Railroad's other licensees. PG & E contends that the contract affords it rights as the successor of a Railroad licensee, namely, the Lo-Vaca Gathering Company, to which the Railroad granted a pipeline license in 1964.

    PG & E further relies on the HCFCD/Railroad contract's non-waiver clause:

    It is expressly covenanted and agreed that no waiver by Licensor, its successors or assigns, of any condition herein set forth shall extend to or affect or be deemed to waive any other breach (whether prior or subsequent) of such condition herein set forth.

    PG & E contends that these clauses together demonstrate an intent to confer legally enforceable benefits upon the Railroad's licensees, particularly because the contract does not disclaim any third party beneficiary rights. HCFCD responds that the Railroad contract obligates HCFCD to the Railroad for conduct that interferes with the Railroad's other licensees, but it does not elevate PG & E to an intended beneficiary, with authorization to sue HCFCD directly for a breach.

    Unambiguous contracts — as the parties agree this one to be — are construed as a matter of law. Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983). We read and consider the entire contract to determine the true intent of the parties. Dedier v. Grossman, 454 S.W.2d 231, 234 (Tex.Civ.App.-Dallas 1970, writ ref'd n.r.e.); see also Cook Composites, Inc. v. Westlake Styrene Corp., 15 S.W.3d 124, 132 (Tex.App.-Houston [14th Dist.] 2000, pet. dism'd). A court should employ the plain and generally accepted meaning of the contract terms, unless the instrument defines them in a technical or different sense. Heritage Res., Inc. v. NationsBank, 939 S.W.2d 118, 121 (Tex.1996).

    In determining whether a third party has a right to enforce a contract, courts look to the express intent of the contracting parties. MCI Telecomms. Corp v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 651 (Tex.1999); Whitten v. Vehicle Removal Corp., 56 S.W.3d 293, 311 (Tex.App.-Dallas 2001, pet. denied). A court should not imply or create third party beneficiary rights unless they are expressly intended by the contracting parties, and plainly and fully spelled out in the four corners of the contract. MCI Telecomms., 995 S.W.2d at 651; Whitten, 56 S.W.3d at 311. Thus, courts should presume that an agreement confers no third party enforcement rights unless it "clearly appears" that the contract intends a third party to benefit, to the point of suing upon the contract. MCI Telecomms., 995 S.W.2d at 651; Whitten, 56 S.W.3d at 311. Accordingly, a court will not interpret a contract to confer third party beneficiary rights unless: (1) the contract plainly expresses the third party obligation of the bargain-giver, (2) it is unmistakable that a benefit to the third party is within the contemplation of the primary contracting parties, and (3) the primary parties contemplate that the third party would be vested with the right to sue for enforcement of the contract. Whitten, 56 S.W.3d at 311. The *341 fact that a third party receives incidental benefits from a contract does not establish a right of action to enforce the contract. MCI Telecomms., 995 S.W.2d at 650; Young Ref. Corp. v. Pennzoil Co., 46 S.W.3d 380, 387 (Tex.App.-Houston [1st Dist.] 2001, pet. denied).

    In MCI, Texas Utilities (TU) sought to recover attorney's fees for a breach of a contract between MCI and the Missouri Pacific Railroad (MoPac). TU claimed it was a third party beneficiary of the MCI/MoPac contract as a licensee, and that MCI had damaged TU's poles in laying fiber optic cable along the easement. The MCI/MoPac contract explicitly provided, however, that "neither this Agreement, nor any term or provision hereof, nor any inclusion by reference, shall be construed as being for the benefit of any party not in signatory hereto." Id. at 649-50. The Texas Supreme Court held that the contract's disclaimer provision reflected that the parties had no intent to confer third party benefits under the contract. Id. at 652. The Court further observed that nothing in the contract indicated that MCI and MoPac ever intended to confer a direct benefit to TU. Id. at 652.

    Although the non-interference language TU relied upon in the MCI case corresponds to the contract in this case, PG & E distinguishes MCI from the present facts on the basis that the HCFCD/Railroad contract does not contain a provision expressly disclaiming any third party rights. PG & E ignores, however, the affirmative requirement that HCFCD and the Railroad expressly contract directly for PG & E's benefit. See id. at 651-52. An express disclaimer is not necessary to deny third party rights; instead, an express obligation is necessary to confer them. See Union Pac. R.R. Co. v. Novus Int'l, Inc., 113 S.W.3d 418, 422-23 (Tex.App.-Houston [1st Dist.] 2003, pet. denied) (concluding that the contract did not clearly spell out an intent on behalf of the contracting parties to confer a direct benefit to a non-contracting party). We conclude that the HCFCD/Railroad contract does not evidence an intent to directly benefit PG & E or its predecessor. Thus, PG & E is not a third party beneficiary of the contract as a matter of law. See MCI Telecomms., 995 S.W.2d at 652; Union Pac., 113 S.W.3d at 422-23 ("Nowhere in the rail contract is it stated that the parties are contracting for the benefit of Carbide's customers.") (emphasis in original); Young Ref., 46 S.W.3d at 387-88 ("[N]et profits agreement contains no indication of an intent to benefit Young Refining. Young Refining is not mentioned in the agreement, and all of the obligations flow between [the parties to the agreement]. Young Refining would have benefitted, but only incidentally, by the contract."). Accordingly, the trial court properly granted summary judgment on PG & E's contract claim.

    In connection with its contract claim, PG & E contends that the trial court erred in granting summary judgment on its declaratory judgment claim. In its second amended petition, PG & E sought to have the trial court declare the parties' rights as to the HCFCD/Railroad agreement and PG & E's third party beneficiary status. As we have concluded that PG & E has no right to sue as an intended third party beneficiary on the HCFCD/Railroad contract, the trial court properly granted summary judgment on PG & E's declaratory judgment claim.

    Inverse Condemnation

    PG & E contends that the trial court erred in granting summary judgment on its inverse condemnation claim.

    The Texas Constitution provides that, "No person's property shall be taken, *342 damaged or destroyed for or applied to public use without adequate compensation being made, unless by the consent of such person. . . ." TEX. CONST. art. I, § 17. Inverse condemnation occurs when property is taken, damaged, or destroyed for public use without process or without proper condemnation proceedings, and the property owner attempts to recover compensation. City of Abilene v. Burk Royalty Co., 470 S.W.2d 643, 646 (Tex.1971); Allen v. City of Texas City, 775 S.W.2d 863, 864 (Tex.App.-Houston [1st Dist.] 1989, writ denied). Under section 17, a landowner may recover for damages to his property even though there is no transfer of property rights. TEX. CONST. art. I, § 17; State v. Biggar, 848 S.W.2d 291, 297-98 (Tex.App.-Austin 1993), aff'd, 873 S.W.2d 11 (Tex.1994); Steele v. City of Houston, 603 S.W.2d 786, 790 (Tex.1980).

    Jurisdiction over such claims is exclusively vested with the Harris County Courts at Law, pursuant to section 25.1032(c) of the Texas Government Code. See TEX. GOV'T CODE ANN. § 25.1032(c) (Vernon 2004) ("A county civil court at law has exclusive jurisdiction in Harris County of eminent domain proceedings, both statutory and inverse, regardless of the amount in controversy.").

    In Taub v. Aquila Southwest Pipeline Corp., 93 S.W.3d 451 (Tex.App.-Houston [14th Dist.] 2002, no pet.), our sister court held that, based on this section and its history, the Harris County Civil Courts at Law have exclusive jurisdiction over a party's claims for inverse condemnation seeking condemnation damages. Based upon the plain language contained in § 25.1032(c), we agree with HCFCD and our sister court. The trial court did not have subject matter jurisdiction over PG & E's inverse condemnation claims. Accordingly, we reverse the trial court's judgment on PG & E's inverse condemnation claim, as it should have been dismissed without prejudice. See TEX. CIV. PRAC. & REM.CODE ANN. § 16.064(a)(1) (Vernon 2004); City of Houston v. Boyle, 148 S.W.3d 171 (Tex.App.-Houston [1st Dist.] 2004, no pet. h.).

    HCFCD further contends that we should dismiss PG & E's other claims because they are inherently intertwined with the inverse condemnation claim, relying on Taub. In Taub, however, the court of appeals observed that "the Harris County Civil Courts at Law have jurisdiction, but not exclusive jurisdiction, over a landowner's claims, regardless of the amount in controversy. . . ." Taub, 93 S.W.3d at 458 (emphasis added). We conclude that PG & E's remaining claims were properly brought in the district court-save the fact that HCFCD is immune from two of them. Accordingly, we hold that the trial court had jurisdiction to grant summary judgment on PG & E's other claims.

    Conclusion

    We affirm the judgment of the trial court as to PG & E's negligence, strict liability, breach of contract, and declaratory judgment claims. We reverse the judgment insofar as it disposes of the claim for inverse condemnation, and render that PG & E's claim for inverse condemnation be dismissed without prejudice. We deny all other outstanding motions.

    NOTES

    [1] EPGT Texas Pipeline, L.P., a subsidiary of El Paso Corporation, acquired PG & E during the pendency of this lawsuit. This is the second appeal in this case. See Harris County Flood Control Dist. v. PG & E Tex. Pipeline, L.P., 35 S.W.3d 772 (Tex.App.-Houston [1st Dist.] 2000, pet. dism'd w.o.j.) (op. on reh'g). We use "PG & E" for continuity in reference.

    [2] The trial court's March 12 judgment also granted PG & E's summary judgment on HCFCD's counterclaim. HCFCD did not appeal.

    [3] At oral argument, PG & E contended for the first time that HCFCD waived its sovereign immunity as to all of PG & E's claims by asserting a counterclaim in which it sought actual damages. PG & E relies upon the Texas Supreme Court's recent decision in Reata Constr. Corp. v. City of Dallas, No. 02-1031, 2004 WL 726906, ___ S.W.3d ___ (Tex. Apr.2, 2004). We note that in Reata, however, the Texas Supreme Court appeared to limit its holding to find such a waiver in connection with a governmental plea in intervention for affirmative relief and for money damages. We decline to address the issue, as neither party briefed it, and PG & E did not raise it in the trial court. TEX.R.APP. P. 33.1, 38.1(e)(h).

    [4] See Corley v. Exxon Pipeline Co., 821 S.W.2d 435 (Tex.App.-Houston [14th Dist.] 1991, writ denied); San Jacinto Sand Co. v. Southwestern Bell, 426 S.W.2d 338, 345 (Tex.App.-Houston [14th Dist.] 1968, writ ref'd n.r.e.).

    [5] HCFCD contends that PG & E cannot raise this basis for waiver of immunity from suit for the first time on appeal because it was not before the trial court. The trial court signed its judgment on March 12, 2002. PG & E filed a second supplemental petition alleging waiver based on the Texas Water Code's sections 49.001(a)(1) and 49.066(a) on January 14, 2002. Thus, PG & E presented this ground to the trial court.

Document Info

Docket Number: 01-02-01056-CV

Citation Numbers: 176 S.W.3d 330, 2004 WL 1794715

Judges: Jane Bland

Filed Date: 9/24/2004

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (19)

Dow Chemical Co. v. Bright , 46 Tex. Sup. Ct. J. 35 ( 2002 )

Whitten v. Vehicle Removal Corp. , 2001 Tex. App. LEXIS 5429 ( 2001 )

Coastal Marine Service of Texas, Inc. v. Lawrence , 42 Tex. Sup. Ct. J. 352 ( 1999 )

Medrano v. City of Pearsall , 1999 Tex. App. LEXIS 670 ( 1999 )

Union Pacific Railroad v. Novus International, Inc. , 113 S.W.3d 418 ( 2003 )

State v. Biggar , 848 S.W.2d 291 ( 1993 )

Young Refining Corp. v. Pennzoil Co. , 2001 Tex. App. LEXIS 2403 ( 2001 )

City of Hedwig Village Planning & Zoning Commission v. ... , 73 S.W.3d 389 ( 2002 )

Texas Department of Parks & Wildlife v. Miranda , 47 Tex. Sup. Ct. J. 386 ( 2004 )

United Water Services, Inc. v. City of Houston , 2004 Tex. App. LEXIS 3988 ( 2004 )

Flameout Design & Fabrication, Inc. v. Pennzoil Caspian ... , 1999 Tex. App. LEXIS 4007 ( 1999 )

MCI Telecommunications Corp. v. Texas Utilities Electric Co. , 1999 Tex. LEXIS 50 ( 1999 )

Cook Composites, Inc. v. Westlake Styrene Corp. , 2000 Tex. App. LEXIS 426 ( 2000 )

St. Joseph Hospital v. Wolff , 46 Tex. Sup. Ct. J. 142 ( 2002 )

City of Houston v. Boyle , 2004 Tex. App. LEXIS 6077 ( 2004 )

Bland Independent School District v. Blue , 44 Tex. Sup. Ct. J. 125 ( 2000 )

Taub v. Aquila Southwest Pipeline Corp. , 93 S.W.3d 451 ( 2003 )

Harris County Flood Control District v. PG & E Texas ... , 2000 Tex. App. LEXIS 8579 ( 2000 )

Thomas v. Harris County , 2000 Tex. App. LEXIS 6704 ( 2000 )

View All Authorities »

Cited By (41)

City of Houston v. Young Ran Kim ( 2021 )

emily-farlow-individually-and-as-next-friend-of-andrew-joseph-farlow-and ( 2009 )

emily-farlow-individually-and-as-next-friend-of-andrew-joseph-farlow-and ( 2009 )

the-city-of-houston-v-maria-zuniga-ranjel-individually-and-as-guardian-of ( 2013 )

emily-farlow-individually-and-as-next-friend-of-andrew-joseph-farlow-and ( 2009 )

zuleima-olivares-individually-and-as-the-representative-of-the-estate-of ( 2013 )

Glen Sumner v. Board of Adjustments of City of Spring ... ( 2016 )

Heartland Holdings, Inc. v. U.S. Trust Co. of Texas N.A. , 316 S.W.3d 1 ( 2010 )

amtech-elevator-services-company-v-csfb-1998-p1-buffalo-speedway-office ( 2007 )

Tabor, Chhabra & Gibbs, P.A. and Darryl Gibbs v. Medical ... ( 2007 )

Michelle Leigh Conkle v. Rachelle Chery AutoNation, Inc., ... ( 2009 )

City of Elgin, Texas v. John William Reagan, as Next Friend ... ( 2009 )

Rebecca Hernandez v. the City of Lubbock and Blake ... ( 2007 )

Rebecca Hernandez v. the City of Lubbock and Blake ... ( 2007 )

Rebecca Hernandez v. the City of Lubbock and Blake ... ( 2007 )

Heartland Holding, Inc v. U.S. Trust Company of Texas, N.A. ... ( 2010 )

Hetul Bhakta DBA Budget Inn v. Texas Department of ... ( 2015 )

Electro Sales and Services, Inc. and Salim Merchant v. the ... ( 2017 )

Bray Abarca and Juan Carlos Sanchez v. Scott Morgan ... ( 2009 )

Gallagher Healthcare Insurance Services, Inc. v. Page M. ... ( 2009 )

View All Citing Opinions »