Brent Timmerman D/B/A Timmerman Custom Builders v. Richard Dale, J. , 2013 Tex. App. LEXIS 3906 ( 2013 )


Menu:
  • REVERSED and RENDERED, REMANDED; Opinion Filed March 27, 2013
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-11-01690-CV
    BRENT TIMMERMAN D/B/A TIMMERMAN CUSTOM BUILDERS, Appellant
    V.
    RICHARD P. DALE, JR., Appellee
    On Appeal from the 160th Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-09-03283
    OPINION
    Before Justices Francis, Lang, and Evans
    Opinion by Justice Francis
    In this breach of contract suit, Brent Timmerman d/b/a Timmerman Custom Builders
    appeals the trial court’s order denying his motion for summary judgment and awarding Richard
    P. Dale, Jr. damages for lost rental value for failing to proceed with reasonable diligence in
    remodeling Dale’s homestead residence.     In a single issue, Timmerman contends Dale’s claim
    falls under the Residential Construction Liability Act and the damages awarded are not allowable
    under the statute. See TEX. PROP. CODE ANN. § 27.001 et seq. For reasons set out below, we
    agree. We reverse the trial court’s order and remand for further proceedings consistent with this
    opinion.
    In May 2006, Dale hired Timmerman to remodel his upscale condominium. As part of
    the parties’ written contract, Timmerman agreed to begin construction “forthwith and to continue
    such construction with reasonable diligence in substantial conformity with the Plans and
    Specifications.”   In addition, the contract contained a provision in which both parties
    acknowledged that the RCLA “applies to construction defects and any disputes or claims
    regarding construction defects in connection with the improvements.”
    In January 2008, Dale terminated the contract and refused to pay Timmerman’s invoices.
    Timmerman then filed mechanic’s and materialman’s lien affidavits claiming liens on the
    residence. Dale filed suit, which he later amended, alleging claims for poor workmanship,
    overpayment of fees, and unreasonable delay in completing the project.                  Timmerman
    counterclaimed for unpaid amounts due and owing under the contract.
    After the case was set for trial, the parties settled all issues except for Dale’s delay claim
    in which Dale sought the fair market rental value of his homestead after the time remodeling
    should have been completed, which Dale estimated was thirteen months. At a hearing, the
    parties agreed the trial court would decide by summary judgment “whether or not delay, under a
    claim for delay in the construction of a residence, is governed by the RCLA, and whether or not
    reasonable rental value can be recovered on an issue of delay under the RCLA.” The parties
    further agreed that the trial court would render judgment for Dale for $100,000 unless it granted
    Timmerman’s forthcoming motion for summary judgment based on the application of the
    RCLA. Finally, the parties agreed that the “winning side” would be entitled to attorney’s fees
    beginning from the date of the hearing, September 13, 2011.
    Timmerman filed a motion for summary judgment. In the motion, he asserted Dale’s
    claim was governed by the RCLA, and rental value of the home under construction is not
    recoverable as damages under the statute.       Dale countered that a “common law claim for
    unreasonable delay has long existed” in this state. Relying on Muller v. Light, 
    538 S.W.2d 487
    ,
    2
    488 (Tex. Civ. App.—Austin 1976, writ ref’d n.r.e.); Ryan v. Thurmond, 
    481 S.W.2d 199
    , 206
    (Tex. Civ. App.—Corpus Christi 1972, writ ref’d n.r.e.); and Hill v. Willett, 
    281 S.W. 1110
    , 1111
    (Tex. Civ. App.—Texarkana 1926, no writ), Dale contended his damages are the rental value of
    his homestead for the period of delay. Dale argued that his claim for lost rental value was not
    “preempted” by the RCLA because his claim is not governed by the RCLA. The trial court
    ultimately agreed with Dale and awarded him agreed damages of $100,000 for unreasonable
    delay and attorney’s fees. 1 Timmerman appealed.
    The summary judgment rule provides a method of summarily ending a case that involves
    only a question of law and no fact issue. TEX. R. CIV. P. 166a(c); Nixon v. Mr. Property Mgmt.
    Co., 
    690 S.W.2d 546
    , 548-49 (Tex. 1985). Determining the proper construction of a statute and
    the propriety of a ruling on a motion for summary judgment are both questions of law. Berry v.
    State Farm Mut. Auto Ins. Co., 
    9 S.W.3d 884
    , 890 (Tex. App.—Austin 2000, no pet.).
    Our review of the summary judgment here turns on the construction of the RCLA. Our
    primary objective in construing a statute is to give effect to the legislature’s intent. State v.
    Shumake, 
    199 S.W.3d 279
    , 284 (Tex. 2006). We seek that intent “first and foremost” in the
    statutory text. Lexington Ins. Co. v. Strayhorn, 
    209 S.W.3d 83
    , 85 (Tex. 2006). We rely on the
    plain meaning of the text, unless a different meaning is supplied by legislative definition or is
    apparent from the context, or unless such a construction leads to absurd results. City of Rockwall
    v. Hughes, 
    246 S.W.3d 621
    , 625-26 (Tex. 2008); see TEX. GOV’T CODE ANN. § 311.011 (West
    2005). We read every word, phrase, and expression in a statute as if it were deliberately chosen.
    1
    We recognize the parties agreed to the procedure in the trial court. Nevertheless, the trial court did not have competing motions for
    summary judgment before it because Dale did not move for summary judgment. Because of our disposition of this appeal, we need not decide
    the propriety of the trial court awarding damages and attorney’s fees to a party who has not moved for summary judgment.
    3
    Cordillera Ranch, Ltd. V. Kendall County Appraisal Dist., 
    136 S.W.3d 249
    , 254 (Tex. App.—
    San Antonio 2004, no pet.).
    If the meaning of the statutory language is unambiguous, we adopt, with few exceptions,
    the interpretation supported by the plain meaning of the provision’s words and terms. Fitzgerald
    v. Advanced Spine Fixation Systems, Inc., 
    996 S.W.2d 864
    , 865 (Tex. 1999). Further, if a statute
    is unambiguous, rules of construction or other extrinsic aids cannot be used to create an
    ambiguity. 
    Id. The Texas
    Legislature enacted Chapter 27 of the Texas Property Code, known as the
    RCLA, in 1989 as a reaction to construction industry claims that the Deceptive Trade Practices
    Act was “used as a sword to litigate against builders.” Justin Jackson, Unlicensed to Drill
    Proposed Renovations to the Texas Residential Construction Commission Act, 36 ST. MARY’S L.
    J. 753, 754 (2005). Its intent was to “provide an ‘appropriate balance’ between the residential
    contractor and owner, with respect to the resolution of construction disputes.” 
    Id. at 761.
    The RCLA modifies causes of action for damages resulting from construction defects in
    residences by limiting and controlling causes of action that otherwise exist. Gentry v. Squires
    Constr., Inc., 
    188 S.W.3d 396
    , 404 (Tex. App.—Dallas 2006 no pet.). It provides defenses,
    limitations on damages, and determines the standard of causation. See TEX. PROP. CODE ANN. §
    27.003, 27.004, 27.006 (West 2000 & Supp. 2013); 
    Gentry, 188 S.W.3d at 404
    . It also sets out
    notice provisions and encourages settlement through its procedures. See TEX. PROP. CODE ANN.
    § 27.004; 
    Gentry, 188 S.W.3d at 404
    . The RCLA does not create a cause of action or derivative
    liability. TEX. PROP. CODE ANN. § 27.005. It does, however, prevail over any conflict between it
    and any other law, including the DTPA or a common law cause of action, except in
    circumstances that do not apply here. 
    Id. at §
    27.002(b).
    4
    The RCLA applies to “any action to recover damages or other relief arising from a
    construction defect, except a claim for personal injury, survival, or wrongful death or for damage
    to goods[.]” TEX. PROP. CODE ANN. § 27.002(a)(1) (West Supp. 2012). A “construction defect”
    means “a matter concerning the design, construction, or repair of a new residence, of an
    alteration of or repair or addition to an existing residence, or of an appurtenance to a residence,
    on which a person has a complaint against a contractor.” 
    Id. at §
    27.001(4). Thus, the question
    here is whether a claim for damages based on Timmerman’s unreasonable delay in completing
    the construction of Dale’s residence is an action arising from a matter concerning the
    construction of Dale’s residence and, thus, is governed by the RCLA. We conclude it is.
    Initially, we note the statute is broadly written to encompass “any action” that arises from
    a construction defect. See In re NEXT Fin. Group, Inc., 
    271 S.W.3d 263
    , 268 (Tex. 2008, orig.
    proceeding) (per curiam) (recognizing when construing contracts generally, “‘arising out of’ are
    words of . . . broad[] significance. . . .”). Similarly, “construction defect” is broadly defined.
    Under the statute’s express definition of construction defect, the complaint against the contractor
    must merely arise from a matter that concerns the construction of a new or existing residence. In
    re Wells, 
    252 S.W.3d 439
    , 448 (Tex. App.—Houston [14th Dist.] 2008, orig. proceeding). It need
    not necessarily involve defective construction or repair. 
    Id. While “construction
    defect” is defined in the statute, the term “construction” is not. To
    properly construe an undefined statutory term, we begin with the plain meaning of the word. In
    common parlance, construction means “the act of putting parts together to form a complete
    integrated object.”   WEBSTER’S THIRD NEW INT’L DICTIONARY 489 (1981).               Dale alleges
    Timmerman failed to use reasonable diligence in completing the remodeling of his
    condominium. Giving the statute its plain meaning, we conclude a claim regarding delay in
    5
    constructing a residence is an action arising from a matter concerning its construction, that is, the
    act of putting the parts together to form a complete object. In other words, while Dale’s
    complaint may not go to the quality of construction, it clearly concerns the manner in which
    Timmerman performed the construction and is thus governed by the RCLA.
    In reaching this conclusion, we have considered Dale’s argument that his claim is not
    amenable to the provisions of the RCLA. Dale accepts the “basic premise” that a construction
    defect “does not always involve defective work under the RCLA.” According to Dale, the
    statute’s “fundamental tenets” are its notice, inspection, and repair provisions found in section
    27.004. He argues the RCLA provides no procedure for resolving a delay dispute nor does the
    statute provide any compensation for damages for unreasonable delay. We do not agree.
    The purpose of the RCLA’s notice requirements “is to encourage pre-suit negotiations to
    avoid the expense of litigation.” In re 
    Wells, 252 S.W.3d at 448
    . A dissatisfied owner can just
    as easily give notice of unreasonable delay as he can of an item of defective work so that the
    builder has an opportunity to cure. As Timmerman asserts, if such notice is given, a builder can
    offer to pay for replacement housing, double the crew to finish more quickly, provide a rebate on
    the contract, or any combination of these measures.
    Dale also asserts that if the RCLA applies, he is left without any measure of damage.
    Except in circumstances not applicable here, the RCLA limits a claimant’s recovery to
    specifically prescribed economic damages proximately caused by the construction defect. See
    TEX. PROP. CODE ANN. § 27.004(g). One such damage is “the reasonable expenses of temporary
    housing reasonably necessary during the repair period[.]” 
    Id. at §
    27.004(g)(4). So while a
    claimant seeking damages for unreasonable delay is not entitled to recover lost rental value of
    6
    the property under the statute, he may be entitled to the reasonable expenses of temporary
    housing. In this case, Dale did not seek those damages.
    We conclude the RCLA applies to Dale’s claim for delay damages. Further, we conclude
    the statute does not provide for the measure of damages sought by Dale and awarded by the trial
    court. We therefore sustain Timmerman’s sole issue.
    We reverse the trial court’s judgment and render judgment that Dale take nothing on his
    claim. The parties previously agreed that the “winning side” would be entitled to attorney’s fees
    beginning from the date of the stipulation hearing, September 13, 2011. We therefore remand
    this cause to the trial court to determine the amount of attorney’s fees to be awarded to
    Timmerman.
    /Molly Francis/
    MOLLY FRANCIS
    JUSTICE
    111690F.P05
    7
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    BRENT TIMMERMAN D/B/A                              On Appeal from the 160th Judicial District
    TIMMERMAN CUSTOM BUILDERS,                         Court, Dallas County, Texas
    Appellant                                          Trial Court Cause No. DC-09-03283.
    Opinion delivered by Justice Francis;
    No. 05-11-01690-CV         V.                      Justices Lang and Evans participating.
    RICHARD DALE, JR., Appellee
    In accordance with this Court’s opinion of this date, the judgment of the trial
    court is REVERSED and judgment is RENDERED that RICHARD P. DALE, JR. take nothing
    on his claim for unreasonable delay. We REMAND this cause to the trial court to determine the
    amount of attorney’s fees to be awarded to appellant BRENT TIMMERMAN D/B/A
    TIMMERMAN CUSTOM BUILDERS.
    It is ORDERED that appellant BRENT TIMMERMAN D/B/A TIMMERMAN
    CUSTOM BUILDERS recover his costs of this appeal from appellee RICHARD P. DALE, JR.
    Judgment entered March 27, 2013.
    /Molly Francis/
    MOLLY FRANCIS
    JUSTICE
    8