City of Alton, Carter & Burgess, Inc., Turner, Collie & Braden, Inc., and Cris Equipment Company, Inc. v. Sharyland Water Supply Corporation , 2013 Tex. App. LEXIS 6606 ( 2013 )


Menu:
  •                         NUMBER 13-06-00038-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    CITY OF ALTON, CARTER & BURGESS, INC.,
    TURNER, COLLIE & BRADEN, INC., AND
    CRIS EQUIPMENT COMPANY, INC.,                                          Appellants,
    v.
    SHARYLAND WATER SUPPLY CORPORATION,                                    Appellee.
    On appeal from the 206th District Court
    of Hidalgo County, Texas.
    OPINION ON REMAND
    Before Chief Justice Valdez and Justices Rodriguez and Garza
    Opinion on Remand by Justice Rodriguez
    This case involves an appeal from a judgment in a jury trial. It is before us on
    remand to address appellee Sharyland Water Supply Corporation’s (Sharyland)
    negligence claim against appellants Carter & Burgess, Inc. (C&B), Turner, Collie &
    Braden, Inc. (TCB), and Cris Equipment Company, Inc. (Cris) (collectively, the
    contractors).1 See City of Alton, Carter & Burgess, Inc., Turner, Collie, & Braden, Inc. &
    Cris Equip. Co. v. Sharyland Water Supply Corp., 
    277 S.W.3d 132
    , 138–41 (Tex.
    App.—Corpus Christi), aff’d in part, rev'd and rendered in part, and rev’d and remanded in
    part, 
    354 S.W.3d 407
    , 424 (Tex. 2012).2 On remand, the contractors contend that there
    was no evidence to establish that (1) C&B or Cris owed a duty to Sharyland; (2) C&B
    breached any duty owed; and (3) C&B, TCB, or Cris proximately caused Sharyland to
    suffer any damages. By a fourth issue, the contractors challenge the sufficiency of the
    evidence supporting the reasonableness of the jury’s damages award. We affirm in part
    and reverse and render in part.
    I.       BACKGROUND
    In the early 1980s, Alton built a water distribution system and conveyed it to
    Sharyland in exchange for Sharyland’s agreement to provide Alton residents with fresh
    water.3 In the 1990s, Alton received financing to construct a sanitary sewer system.
    Until the construction of the sewer system, Alton residents relied on a sewage disposal
    1
    Since we handed down our original opinion on rehearing, appellant Cris Equipment Co., Inc.
    (Cris) has forfeited its charter and no longer exists. Still, Cris has a right to be heard on appeal. See
    Vanscot Concrete Co. v. Bailey, 
    853 S.W.2d 525
    , 526–27 (Tex. 1993) (per curiam) (holding that a
    corporation that had ceased to exist could nevertheless appeal a trial court's judgment against it); see also
    Suntide Sandpit, Inc. v. H & H Sand & Gravel, Inc., No. 13-11-000323-CV, 2012 Tex. App. LEXIS 5870, at
    *12–13 (Tex. App.—Corpus Christi July 19, 2012, pet. denied) (memo. op.).
    2
    The Texas Supreme Court either affirmed or reversed and rendered all issues involving the City
    of Alton; therefore, the City of Alton is not before this Court on remand. See Sharyland Water Supply Corp.
    v. Alton, 
    354 S.W.3d 407
    , 412–15 (Tex. 2011).
    3
    Other facts involved in this case are more fully set out in this Court's first opinion on rehearing and
    in the supreme court’s opinion. See Sharyland Water Supply 
    Corp., 354 S.W.3d at 410
    –12; City of Alton,
    Carter & Burgess, Inc., Turner, Collie, & Braden, Inc., & Cris Equip. Co. v. Sharyland Water Supply Corp.,
    
    277 S.W.3d 132
    , 138–41 (Tex. App.—Corpus Christi), aff’d in part, rev'd and rendered in part, and rev’d and
    remanded in 
    part, 354 S.W.3d at 424
    .
    2
    system that consisted of septic tanks and open ditches. Part of the septic system was
    built in the public right-of-way and another part connected the septic system from the
    public right-of-way to individual houses.                 For the public right-of-way phase, Alton
    retained the services of L.L. Rodriguez and Associates to design the system, TCB, an
    engineering company, to engineer and inspect the system, and C&B, an engineering
    company, to manage construction of the sewer system.                          Alton also hired Cris, a
    contractor, to build the system. Cris subcontracted with Grab Pipeline Services, Inc. to
    assist in the installation.4 The construction of the sewer system was completed in 1999.
    To reach the houses on one side of the street, the sewer lines had to pass over or
    under the water main. Beginning in late 1999 or early 2000, Sharyland dug up some of
    the sites where the sewer lines crossed the water main. Sharyland expressed a concern
    that service lines crossing over the water main (rather than under the water main) did not
    have the required separation distance from the water main and that the crossings were
    not “centered” so that joints in the sewer service lines were as far from the water main as
    possible. When Sharyland and Alton could not work out an agreement over the service
    line crossings, Sharyland filed this lawsuit against Alton and the contractors. Sharyland
    asserted, among other things, that it was a third party beneficiary of the construction
    contracts because the sewer lines at issue were constructed in a manner which was not in
    conformance with regulatory standards or with the industry, engineering, and common
    law standard of care to be taken when constructing new sewer lines in the proximity of
    water lines. Sharyland also alleged that Alton and the contractors acted negligently in
    4
    The jury found no liability on the part of L.L. Rodriguez and Associates or Grab Pipeline Services,
    Inc., and those entities are not parties to this appeal.
    3
    violating the duties created in contract or in not fulfilling their statutory and common law
    duties created under the law.
    The contractors generally denied Sharyland’s claims. As to Sharyland’s contract
    claim, the contractors specifically pleaded that Sharyland was not a third party beneficiary
    of any contract or agreement with Alton or any other entity. As to Sharyland’s negligence
    claims, the contractors denied that they owed any legal duty to Sharyland and, if there
    was a legal duty, that their breach, if any, did not proximately cause damages. They
    claimed that section 317.13 of title 30 of the Texas Administrative Code, which sets out
    the design criteria for sewerage systems, did not apply to the service connections at
    issue. See 30 TEX. ADMIN. CODE § 317.13(1)(A)–(B), repealed by 33 Tex. Reg. 6938
    (2008).5 They also asserted that any damages were economic and, thus, barred by the
    economic loss doctrine.
    The case was tried to a jury, which found that the contractors failed to comply with
    their contracts with Alton and that Sharyland was a third party beneficiary to all of the
    contracts.    It also found the contractors negligent, proximately causing damages to
    Sharyland (C&B was found 20% responsible, Cris 40%, and TCB 40%).                            The jury
    awarded Sharyland past damages of $14,000 and future damages of $1,125,000 as the
    reasonable cost of repairs necessary to restore the property to its condition immediately
    before the injury. The trial court entered judgment against the contractors.
    On appeal, this Court reversed and rendered judgment that Sharyland take
    5
    “Section 317.13 was repealed and has since been substantially incorporated into section 217.53
    of the Texas Administrative Code.” Sharyland Water Supply 
    Corp., 354 S.W.3d at 421
    n.27 (citing 30 TEX.
    ADMIN. CODE § 217.53; 30 TEX. ADMIN. CODE § 317.13(1)(B), repealed by 33 Tex. Reg. 6938 (2008)). For
    the purposes of this opinion, we will refer to former section 317.13 as the applicable section.
    4
    nothing on its breach of contract claims against the contractors because Sharyland was
    not a third party beneficiary to any construction contracts. City of 
    Alton, 277 S.W.3d at 155
    . We also rendered judgment that Sharyland take nothing on its negligence claims
    against the contractors because Sharyland’s water system had not been damaged, and
    with purely economic damages, the economic loss rule barred Sharyland’s tort claims.
    
    Id. at 154.
    Sharyland appealed to the Texas Supreme Court. See Sharyland Water Supply
    Corp. v. City of Alton, 
    354 S.W.3d 407
    , 411–12 (Tex. 2011). Relevant to this appeal, the
    supreme court reversed our judgment on Sharyland’s negligence claims against the
    contractors. 
    Id. at 420.
    It concluded that “the economic loss rule[, which bars a party
    from recovering in negligence or strict liability for purely economic losses,] does not
    preclude Sharyland’s negligence claim against [the contractors]” because Sharyland’s
    water system was damaged. 
    Id. In other
    words, the supreme court concluded that the
    economic loss rule did not apply because there were damages to Sharyland’s water
    system.       According to the supreme court, Sharyland’s water system was damaged
    because,
    Sharyland's system once complied with the law, and now it does not.
    Sharyland is contractually obligated to maintain the system in accordance
    with state law and must either relocate or encase its water lines. These
    expenses, imposed on Sharyland by the contractors' conduct, were the
    damages the jury awarded. Costs of repair necessarily imply that the
    system was damaged, and that was the case here.
    
    Id. And regarding
    “whether [the economic loss rule] should apply at all in a situation like
    this,” the supreme court reasoned as follows:
    Merely because the sewer was the subject of a contract does not
    5
    mean that a contractual stranger is necessarily barred from suing a
    contracting party for breach of an independent duty. If that were the case,
    a party could avoid tort liability to the world simply by entering into a contract
    with one party.
    
    Id. at 418–19.
    In addition, Sharyland argued before the supreme court “that the contractors failed
    to maintain the required minimum distance between water lines and sewer lines, failed to
    center the sewer pipes, and negligently installed those pipes above the water lines in
    violation of section 317.13.” 
    Id. at 422.
    In response, the contractors contended “that
    section 317.13 applied purely to sewer mains, and not the residential sewer lines[, the
    only portions of Alton’s sewer system] at issue here.” 
    Id. The contractors
    argued “that
    Sharyland’s entire case hinged on the 317.13 violation, and without it, there is no basis for
    finding that the contractors were negligent.” 
    Id. at 421.
    The supreme court disagreed
    with the contractors’ argument. It determined that, as a matter of law, section 317.13
    unambiguously applied to all sewer lines in this case, including the residential sewer
    lines.6 
    Id. at 423.
    It provided the following explanation:
    6
    Section 317.13 provides, in relevant part, that,
    The following rules apply to separation distances between potable water and
    wastewater plants, and waterlines and sanitary sewers.
    (1) Waterline/new sewer line separation. When new sanitary sewers are
    installed, they shall be installed no closer to waterlines than nine feet in all
    directions. Sewers that parallel waterlines must be installed in separate
    trenches. Where the nine-foot separation distance cannot be achieved,
    the following guidelines will apply.
    (A) Where a sanitary sewer parallels a waterline, the
    sewer shall be constructed of cast iron, ductile iron, or
    PVC meeting ASTM specifications with a pressure rating
    for both the pipe and joints of 150 psi. The vertical
    separation shall be a minimum of four feet between
    outside diameters. The sewer shall be located below the
    waterline.
    6
    Nowhere in chapter 317 were residential service connections excluded
    from the general meaning of "sewers" or "sanitary sewers." To the
    contrary, the breadth of the terms implies the definition that dictionaries give
    it: that is, underground pipes carrying domestic or industrial waste. We
    agree with the trial court that section 317.13 applied to the sewer lines in
    this case . . . .
    
    Id. The supreme
    court remanded the case to this Court to address the negligence
    issues involving Sharyland and the contractors, issues we did not reach in our earlier
    opinion. See 
    id. at 424.
    II.     APPLICABLE LAW AND STANDARD OF REVIEW
    A.     Negligence
    “Negligence arises when an actor breaches a legal duty in tort, and the breach
    proximately causes damages.” Columbia Med. Ctr. of Las Colinas, Inc. v. Hogue, 
    271 S.W.3d 238
    , 246 (Tex. 2008).
    1.      Duty
    Because the threshold inquiry in a negligence case is duty, Sharyland must first
    establish that the contractors owed a legal duty to it. See Nabors Drilling, U.S.A., Inc. v.
    Escoto, 
    288 S.W.3d 401
    , 404 (Tex. 2009); Centeq Realty, Inc. v. Siegler, 
    899 S.W.2d 195
    , 197 (Tex. 1995); Yeager v. Drillers, Inc., 
    930 S.W.2d 112
    , 115 (Tex. App.—Houston
    (B) Where a sanitary sewer crosses a waterline and the
    sewer is constructed of cast iron, ductile iron, or PVC with
    a minimum pressure rating of 150 psi, an absolute
    minimum distance of six inches between outside
    diameters shall be maintained. In addition, the sewer
    shall be located below the waterline where possible and
    one length of the sewer pipe must be centered on the
    waterline.
    See 
    id. at 421–22
    (quoting 30 TEX. ADMIN. CODE § 317.13(1)(A)-(B), repealed by 33 Tex. Reg. 6938).
    7
    [1st Dist.] 1996, no writ) (holding that “duty is the threshold question in a negligence
    case”). A duty is a legal obligation that requires a defendant to conform to a certain
    standard of conduct to protect others against unreasonable risks.          See Midwest
    Employers Cas. Co. v. Harpole, 
    293 S.W.3d 770
    , 776 (Tex. App.—San Antonio 2009, no
    pet.). “Actionable negligence presupposes the existence of a legal relationship between
    the parties through which the wrongdoer owed a duty to the injured party. The duty may
    be imposed by contract or, irrespective of privity of contract, by law.” Cook Consultants,
    Inc. v. Larson, 
    700 S.W.2d 231
    , 233–34 (Tex. App.—Dallas 1985, writ ref’d n.r.e.).
    Without a duty, the contractors cannot be held liable to Sharyland for negligence. See
    Kroger Co. v. Elwood, 
    197 S.W.3d 793
    , 794 (Tex. 2006) (per curiam).
    The existence of a duty is a question of law for the courts to decide from the
    essential, undisputed facts surrounding the occurrence in question. Nabors 
    Drilling, 288 S.W.3d at 404
    ; Greater Houston Transp. Co. v. Phillips, 
    801 S.W.2d 523
    , 525 (Tex.
    1990). The existence of duty is also a question of law when the evidence conclusively
    establishes the pertinent facts or when reasonable inferences can be drawn from those
    facts, as in this case. See Bennett v. Span Indus., Inc., 
    628 S.W.2d 470
    , 474 (Tex.
    App.—Texarkana 1981, writ ref'd n.r.e.). In such instances, appellate courts review de
    novo a determination regarding whether a legal duty is owed. Nabors 
    Drilling, 288 S.W.3d at 404
    .
    2.     Breach, Proximate Cause, and Damages
    Sharyland must also establish that the contractors breached a duty owed and that
    their breach, if any, proximately caused damages. See 
    Hogue, 271 S.W.3d at 246
    . On
    8
    appeal, the contractors complain that there was no evidence establishing breach,
    proximate cause, or that the cost of repairs was reasonable.
    We will sustain a legal-sufficiency or no-evidence challenge if the record shows:
    (1) the complete absence of evidence of a vital fact; (2) the court is barred by the rules of
    law or evidence from giving weight to the only evidence offered to prove a vital fact; (3) the
    evidence offered to prove a vital fact is no more than a scintilla; or (4) the evidence
    establishes conclusively the opposite of a vital fact. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 810 (Tex. 2005). When reviewing a no-evidence challenge, we view the evidence
    in the light most favorable to the finding, crediting favorable evidence if a reasonable
    fact-finder could and disregarding contrary evidence unless a reasonable fact-finder
    could not. 
    Id. at 807.
    The ultimate test for legal sufficiency is whether the evidence
    would enable reasonable and fair-minded people to make the finding under review. 
    Id. at 827.
    In reviewing a no-evidence issue, the court indulges every reasonable inference
    in support of that finding. 
    Id. at 822.
    However, a reviewing court cannot disregard
    undisputed evidence that permits only one logical inference. 
    Id. at 814–15.
    Further, a
    finding may not be supported by mere suspicion or surmise. Browning-Ferris, Inc. v.
    Reyna, 
    865 S.W.2d 925
    , 927–28 (Tex. 1993). And incompetent evidence is legally
    insufficient to support a judgment, even if admitted without objection. City of 
    Keller, 168 S.W.3d at 812
    .
    B.     Admissibility of Expert Testimony
    A two-prong test governs whether expert testimony is admissible:
    (1) the expert must be qualified, and (2) the testimony must be relevant and
    based on a reliable foundation. E.I. du Pont de Nemours & Co. v.
    Robinson, 
    923 S.W.2d 549
    , 554 (Tex. 1995)[; see TEX. R. EVID. 702]. "If
    9
    the expert's scientific testimony is not reliable, it is not evidence." Merrell
    Dow Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 713 (Tex. 1997).
    Generally, courts review a challenge to the admission of expert testimony
    under an abuse of discretion standard. Whirlpool Corp. v. Camacho, 
    298 S.W.3d 631
    , 638 (Tex. 2009). . . . "But a party may assert on appeal that
    unreliable scientific evidence or expert testimony is not only inadmissible,
    but also that its unreliability makes it legally insufficient to support a verdict."
    
    Id. . .
    . "[A] no-evidence review encompasses the entire record, including
    contrary evidence tending to show the expert opinion is incompetent or
    unreliable." [Id.] (citing City of 
    Keller, 168 S.W.3d at 814
    ).
    ....
    "Expert testimony lacking a proper foundation is incompetent, City of
    
    Keller, 168 S.W.3d at 813
    , and its admission is an abuse of discretion."
    TXI Transp. Co. v. Hughes, 
    306 S.W.3d 230
    , 239 (Tex. 2010) (citing Cooper
    Tire & Rubber Co. v. Mendez, 
    204 S.W.3d 797
    , 800 (Tex. 2006)). . . . "The
    court's ultimate task, however, is not to determine whether the expert's
    conclusions are correct, but rather whether the analysis the expert used to
    reach those conclusions is reliable and therefore admissible." [Id.] (citing
    Exxon Pipeline Co. v. Zwahr, 
    88 S.W.3d 623
    , 629 (Tex. 2002)).
    . . . . “[I]f an expert’s opinion is based on certain assumptions about the
    facts, we cannot disregard evidence showing those assumptions were
    unfounded.” City of 
    Keller, 168 S.W.3d at 813
    .
    U.S. Renal Care, Inc. v. Jaafar, 
    345 S.W.3d 600
    , 606–07, 610 (Tex. App.—San Antonio
    2011, pet. denied) (op. on reh’g).
    C.     Reasonableness of Cost of Repairs
    A party seeking to recover costs of repair or completion must prove that the
    damages sought are reasonable and necessary. McGinty v. Hennen, 
    372 S.W.3d 625
    ,
    627 (Tex. 2012) (per curiam) (rendering judgment in a breach-of-contract case where
    there was no evidence to support the reasonableness of the remedial damages) (citing
    Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 200 (Tex. 2004) (per
    curiam)); see Allright, Inc. v. Lowe, 
    500 S.W.2d 190
    , 191–92 (Tex. Civ. App.—Houston
    10
    [14th Dist.] 1973, no writ) (addressing the common-law principle that to establish the right
    to recover the cost of repairs made to property wrongfully damaged by another, a
    claimant ordinarily must prove that such repairs were necessary and the costs
    reasonable). “To establish that, the plaintiff must show more than simply ‘the nature of
    the injuries, the character of and need for the services rendered, and the amounts
    charged therefor.’” 
    McGinty, 372 S.W.3d at 627
    (quoting Dallas Ry. & Terminal Co. v.
    Gossett, 
    294 S.W.2d 377
    , 383 (Tex. 1956)). “Instead, some other ‘evidence showing
    that the charges are reasonable’ is required.” 
    Id. (quoting Gossett,
    294 S.W.2d at 383);
    see Fort Worth Hotel Ltd. P'ship v. Enserch Corp., 
    977 S.W.2d 746
    , 762–63 (Tex.
    App.—Fort Worth 1998, no pet.) ("[M]ere proof of amounts charged or paid does not raise
    an issue of reasonableness and such amounts ordinarily cannot be recovered without
    evidence showing the charges were reasonable."). For example, expert testimony about
    estimates for repairs, testimony of the person making the estimates or performing the
    repairs, or approval of the repairs by a third party has been held sufficient to support an
    award of damages based on the cost of repairs. See Ron Craft Chevrolet, Inc. v. Davis,
    
    836 S.W.2d 672
    , 677 (Tex. App.—El Paso 1992, writ denied); Carrow v. Bayliner Marine
    Corp., 
    781 S.W.2d 691
    , 694 (Tex. App.—Austin 1989, no writ); Liptak v. Pensabene, 
    736 S.W.2d 953
    , 958 (Tex. App.—Tyler 1987, no writ); see also Allright, 
    Inc., 500 S.W.2d at 191
    –92 (requiring evidence of the reasonable cost of repairs, placement parts, towing,
    and storage to recover and restore appellee's car that was recovered in a damaged
    condition after it was stolen from a parking lot negligently operated by appellant).
    However, an estimate without the testimony of the person who made it or other expert
    11
    testimony is no evidence of the necessity of the repair or the reasonableness of the cost
    of the repair. Jordan Ford, Inc. v. Alsbury, 
    625 S.W.2d 1
    , 3 (Tex. Civ. App.—San Antonio
    1981, no writ); see 
    Carrow, 781 S.W.2d at 694
    ("When the expert who prepared the
    estimate of repairs does not testify, the jury has no basis on which to evaluate the
    estimate.").
    D.      Law of the Case
    The "law of the case" doctrine is the principle by which questions of law decided on
    appeal to a court of last resort will govern the case throughout its subsequent stages.
    Loram Maint. of Way, Inc. v. Ianni, 
    210 S.W.3d 593
    , 596 (Tex. 2006); Hudson v.
    Wakefield, 
    711 S.W.2d 628
    , 630 (Tex. 1986); see City of Mission v. Cantu, 
    89 S.W.3d 795
    , 809 n.21 (Tex. App.—Corpus Christi 2002, no pet). “[W]e are bound to follow the
    expression of the law as stated by the Texas Supreme Court.” 
    Cantu, 89 S.W.3d at 809
    n.21; see 
    Ianni, 210 S.W.3d at 596
    ; 
    Hudson, 711 S.W.2d at 630
    .
    In this case, the supreme court agreed with this Court that “Sharyland was not a
    third party beneficiary of the agreement between Alton and the contractors,” noting that
    Sharyland is not “mentioned in the contracts” and concluding that there was no “evidence
    that Alton and the contractors intended to confer a direct benefit on Sharyland.”
    Sharyland Water Supply 
    Corp., 354 S.W.3d at 421
    . In addition, because Sharyland’s
    claim for attorney’s fees against the contractors was based on its third party beneficiary
    theory [and not on its declaratory judgment action], the court concluded that “Sharyland
    may not, therefore, recover its attorney’s fees against the contractors.”7 
    Id. at 423–24.
    7
    Sharyland claims that this Court reversed and remanded the trial court’s award of attorney’s fees
    against the contractors for further determination and that the Texas Supreme Court affirmed this action.
    12
    The supreme court also concluded that “[m]erely because the sewer was the
    subject of a contract does not mean that a contractual stranger[, Sharyland,] is
    necessarily barred from suing a contracting party[, the contractors,] for breach of an
    independent duty.” 
    Id. at 419.
    In this regard, as an alternate basis for affirming this
    Court’s reversal on the negligence claim, the contractors urged that the trial court
    incorrectly held that section 317.13 applied to the sewer lines in this case. 
    Id. at 421.
    In
    fact, the contractors argued that “Sharyland’s entire case hinged on the 317.13 violation,
    and without it, there is no basis for finding that the contractors were negligent.” 
    Id. In response,
    the supreme court construed section 317.13 as a matter of law and determined
    that it did apply “to the sewer lines in this case,” which included service connections. 
    Id. at 422–23.
    In addition, the supreme court concluded that Sharyland’s water system had been
    damaged because the “system once complied with the law, and now it does not.” 
    Id. at 420.
    It recognized that “Sharyland is contractually obligated to maintain the system in
    accordance with state law and must either relocate or encase its water lines,” and that the
    “[c]osts of repair necessarily imply that the system was damaged.” 
    Id. at 420.
    The
    supreme court identified the following evidence of damage:
    Sharyland presented evidence that it experiences between 100 and 150
    water system leaks each year. A break in the water line threatens
    However, although we reversed and remanded “the award of attorney's fees for a determination of the
    amount of the award, if any, properly attributable to Sharyland's declaratory judgment,” we did so in light of
    our discussion of Sharyland’s claims against Alton. See City of 
    Alton, 277 S.W.3d at 158
    . As to the
    contractors, we reversed and rendered “judgment that Sharyland take nothing for damages and attorney's
    fees on its contract claims and its negligence claims against C&B, TCB, and Cris.” See 
    id. And the
    supreme court concluded that “Sharyland may not, therefore, recover its attorney's fees against the
    contractors” because those fees were based on Sharyland’s third party beneficiary theory, which the
    supreme court rejected, and not Sharyland’s declaratory judgment action. Sharyland Water Supply 
    Corp., 354 S.W.3d at 423
    .
    13
    contamination. There was evidence that when Sharyland excavated a
    representative sample of sixty-six sewer crossings, sixty of them had been
    illegally installed, and there was at least one leaking sewer pipe located six
    inches above a water pipe. There was also evidence that approximately
    340 locations would require remediation.
    
    Id. Because Sharyland
    suffered property damage, the supreme court further concluded
    the economic loss rule, which “does not govern here,” “does not preclude Sharyland’s
    negligence claim against [the contractors].” See 
    id. at 420,
    424. Finally, regarding
    damages, the supreme court concluded that “[b]ecause none of the contractors was
    attributed a percentage of responsibility greater than 50%, the proportionate
    responsibility statute” did not apply. 
    Id. at 423–24.
    Because the above is the law of the case, we are bound to apply it in this
    proceeding. See 
    Ianni, 210 S.W.3d at 596
    ; 
    Hudson, 711 S.W.2d at 630
    .
    III.    DISCUSSION
    A.     Duty8
    1.        C&B
    By the first issue, among other things, C&B contends that it owes no common law
    duty to Sharyland.9 Relying on the proposition that the scope of any duty owed by C&B
    to Sharyland is determined solely by the contract between C&B and Alton, C&B asserts
    that the Texas Supreme Court has determined that the C&B/Alton contract did not create
    any duty owed by C&B to Sharyland. See, e.g., Dukes v. Philip Johnson/Alan Ritchie,
    Architects, P.C., 
    252 S.W.3d 586
    , 594–95 (Tex. App.—Fort Worth 2008, pet. denied)
    8
    On remand, TCB does not challenge the duty element of Sharyland’s claim.
    9
    Because our common-law analysis is dispositive of this issue, we need not analyze C&B’s
    remaining claims challenging the duty element. See TEX. R. APP. P. 47.1.
    14
    (concluding, in a summary judgment proceeding, that, because there was no evidence
    that the contract between architects Johnson/Ritchie and the City and the contract
    between consultants Johantgen and Johnson/Ritchie required either party to report or
    make safe any hazards detected or to provide a safety review to the City regarding the
    Water Gardens where the Dukes’ family members died, they owed no duty to the Dukes);
    Romero v. Parkhill, Smith & Cooper, Inc., 
    881 S.W.2d 522
    , 527 (Tex. App.—El Paso
    1994, writ denied) (determining that nothing in the contract between the city and the
    engineer gave the engineer the right to control the construction, and accordingly, the
    engineer did not have a duty of care to an employee of a subcontractor to keep the
    premises safe); see also Graham v. Freese & Nichols, Inc., 
    927 S.W.2d 294
    , 295 (Tex.
    App.—Eastland 1996, writ denied) (concluding, in a summary judgment context, that
    “[a]ppellee's contract reflects that appellee had no duty regarding safety at the work site”).
    In this case, however, the supreme court only determined that Sharyland was not a third
    party beneficiary to the C&B/Alton contract. Sharyland Water Supply 
    Corp., 354 S.W.3d at 421
    . It did not determine that C&B owed no duty to Sharyland under a tort theory, as
    C&B argues. Instead, it remanded the negligence issues to this Court, the first of which
    is to determine whether C&B owed a duty to Sharyland. See 
    id. at 424.
    In support of its argument that C&B owes no common-law duty to Sharyland, C&B
    cites Harpole for the proposition that courts apply the risk-utility test in deciding whether a
    common-law duty exists.        
    See 293 S.W.3d at 779
    .         C&B generally identifies the
    following factors courts consider when applying the risk-utility test: risk; foreseeablity;
    likelihood of injury, balanced against the social utility of the actor’s conduct; the
    15
    magnitude of the burden of guarding against the injury; and, the consequences of placing
    this burden on the defendant. 
    Id. C&B notes
    that when these factors are balanced, the
    most important factor to consider is the foreseeability of the risk. See 
    Harpole, 293 S.W.3d at 779
    . Apparently developing its discussion of foreseeability, C&B directs this
    Court to another factor that courts consider in determining duty—whether a party had the
    duty to control the conduct of the person who caused the plaintiff’s alleged injury. See
    Graff v. Beard, 
    858 S.W.2d 918
    , 920 (Tex. 1993); Black + Vernooy Architects v. Smith,
    
    346 S.W.3d 877
    , 892 (Tex. App.—Austin 2011, pet. denied) (en banc). C&B concisely
    argues that the evidence does not establish that, as project manager, it had the right to
    control the manner or method of the construction of the sanitary sewer system, so it owed
    Sharyland no common-law duty. See Black + Vernooy 
    Architects, 346 S.W.3d at 892
    (concluding that the architectural firm did not owe a common-law duty to injured third
    parties because it did not have the right to control the construction of the balcony through
    its contract with the homeowner). We disagree.
    C&B’s Project Management contract with Alton stated that C&B’s scope of
    services included the following:
    Task 3.
    Assure that the project complies with all local, state, and
    federal regulations relevant to the planning, and construction
    of a wastewater collection and transmission system; [and]
    ....
    Task 12.
    Review the Engineer’s recommendation for the Resident
    Project Inspector and advise the Owner . . . .
    C&B contends that the Alton/C&B contract did not obligate C&B to inspect
    16
    construction or completed work. It urges that the contract only obligated C&B to review
    the engineer’s recommendation for a project inspector, as directed by Task 12, and
    therefore, its responsibilities under Task 3 related only to the various documents
    comprising the design drawings for the project and to confirm that a competent design
    engineer and a competent resident inspector had been engaged.               Based on this
    reasoning, C&B asserts that the agreement imposes no duty to direct, oversee, or inspect
    construction of the sewer project.
    The unambiguous language of Task 3 expressly states C&B will assure that the
    project, not just the design drawings, complies with all relevant regulations.         It is
    apparent that the scope of C&B’s duty, as set out in Task 3, included making certain that
    the construction of all aspects of the project was in conformance with the law, engineering
    standards, and industry standards. See Milner v. Milner, 
    361 S.W.3d 615
    , 619 (Tex.
    2010) (citing Chrysler Ins. Co. v. Greenspoint Dodge of Houston, Inc., 
    297 S.W.3d 248
    ,
    252 (Tex. 2009) (per curiam)) (setting out that if the language of a contract can be given a
    certain and definite meaning, it is not ambiguous and the contract’s construction is a
    matter for the court).   We cannot conclude that Task 3 relates only to documents
    comprising the project’s design drawings, as C&B argues. The language is not that
    narrow; the intent of the parties as expressed in this scope of services provision is clear.
    In addition, the method by which C&B was to assure conformance is not set out in the
    contract. Therefore, even though another party inspected the property and, through
    Task 12, C&B was to review TCB’s recommendations for that resident project inspector
    and to advise Alton, we cannot conclude that Task 12 discharged C&B’s duty to make
    17
    certain the project complied with all state regulations, among other things. An on-site
    inspection is not the only method by which C&B could have assured construction
    conformance, as C&B’s argument suggests.
    Moreover,
    [t]he fact that an act is induced by and done pursuant to a contract does not
    shield it from regular tort liability. One who undertakes to perform a
    contract assumes a duty to all persons to take reasonable care not to injure
    them or their property in the performance of that contract, and one who is
    not privy to the contract may assert a claim for negligence for a breach of
    that duty. Thomson [v. Espey Huston & Assoc.], 899 S.W.2d [415,] 421
    [(Tex. App.—Austin 1995, no writ)] (citing Sw. Bell Tel. Co. v. Delanney, 
    809 S.W.2d 493
    , 494 (Tex. 1991) (op. corrected at 
    34 Tex. Sup. Ct. J. 749
    )).
    Goose Creek Consol. Indep. Sch. Dist. of Chambers v. Jarrar's Plumbing, 
    74 S.W.3d 486
    ,
    494 (Tex. App.—Texarkana 2002, pet. denied) ("[T]he injury Goose Creek alleged, the
    invasion of sewage and sewer gas into the school buildings, constitutes an injury to
    property that was not the subject matter of the [plumbing] contract [between Lewis and
    Jarrar’s Plumbing] . . . .   Jarrar's Plumbing owed an independent tort duty to use
    reasonable care in the performance of the contract to install the plumbing so as not to
    injure persons or property, and Goose Creek alleged that such injury to property was
    caused by the failure to use such reasonable care. Therefore, Goose Creek properly
    maintained a tort action for negligence against Jarrar's Plumbing . . . .”); 
    Thomson, 899 S.W.2d at 421
    –22 (finding that, absent clear evidence to the contrary, a property owner is
    not a third party beneficiary to a contract between a contractor and a subcontractor and
    therefore cannot sue on the contract, but that the property owner may assert a claim for
    negligence against a subcontractor based on the subcontractor's performance under the
    contract where the cause of action is independent of the duties imposed by the contract).
    18
    In this case, the Alton/C&B contract imposed a contractual duty on C&B to perform
    specified services for Alton; those services included assuring that the project complied
    with all state regulations relevant to the construction of Alton’s sewer system. See
    
    Milner, 361 S.W.3d at 619
    (citing Chrysler Ins. 
    Co., 297 S.W.3d at 252
    ); 
    Bennett, 628 S.W.2d at 474
    . At the same time, in undertaking to perform its contract with Alton, C&B
    had an independent duty to take reasonable care not to injure Sharyland’s property—not
    to negligently damage Sharyland’s sewer system. See Goose Creek Consol. Indep.
    Sch. Dist. of 
    Chambers, 74 S.W.3d at 494
    (citing 
    Thomson, 899 S.W.2d at 421
    ) (citing
    
    Delanney, 809 S.W.2d at 494
    )). If, as Sharyland alleges, incompetent services on the
    part of C&B damaged its water lines, then C&B may be liable for that negligence in tort.
    See 
    id. 2. Cris
    Also by this first issue, Cris asserts that it owed Sharyland no legal duty in the
    construction of the sewer system at issue in this case. The only argument Cris makes for
    this contention is that section 317.13, the regulation upon which Sharyland relies, “does
    not apply to the service connections [at] issue in this case. Therefore, that regulation
    cannot be the basis of any duty upon which a finding of negligence against Cris may be
    premised.” However, the Texas Supreme Court concluded that section 317.13 does
    apply “to the sewer lines in this case,” which includes the service connections.
    Sharyland Water Supply 
    Corp., 354 S.W.3d at 422
    –23. The law of the case applies, and
    this argument fails. See 
    Ianni, 210 S.W.3d at 596
    ; 
    Cantu, 89 S.W.3d at 809
    n.21.
    And one of the conditions of Cris’s contract with Alton provided that Cris “shall
    19
    observe and comply with all . . . State . . . regulations which in any manner affect the
    conduct of the work.” Also incorporated into the contract was Cris’s assurance to the
    “Texas Water Development Board that it would construct Alton/McAllen Waste Water
    Improvement project at Alton, Texas, in accordance with sound construction practice, all
    laws of the State of Texas, and the rules of the Texas Water Development Board.” Thus,
    the Alton/Cris contract imposed a contractual duty on Cris to perform specified services
    for Alton; services that included observing and complying with all relevant state
    regulations. In undertaking to perform its contract with Alton, Cris had an independent
    duty to take reasonable care not to injure Sharyland’s property—not to negligently
    damage Sharyland’s sewer system. See Goose Creek Consol. Indep. Sch. Dist. of
    
    Chambers, 74 S.W.3d at 494
    (citing 
    Thomson, 899 S.W.2d at 421
    ) (citing 
    Delanney, 809 S.W.2d at 494
    )). If, as Sharyland alleges, Cris’s incompetent construction services
    damaged its water lines, then Cris, too, may be liable for that negligence in tort.
    3.      Summary
    We overrule the first issue, which challenges the duty element of negligence.
    B.     Breach
    By a second issue, only C&B challenges the breach element of Sharyland’s
    negligence claim; TCB and Cris do not. 10              Recognizing that “Texas law restricts
    evaluations of C&B’s activities in this case to the contractual duties [it] assumed in its
    contract with Alton,” C&B contends that Sharyland’s experts, Randy Winston and William
    10
    TCB does not challenge the breach element. And although Cris generally challenges the
    sufficiency of the evidence to support a negligence finding, it addresses only duty and damages.
    Therefore, we need not address the breach element as to either TCB or Cris. See TEX. R. APP. P. 47.1.
    20
    Shea, could have had no reasonable basis for an opinion on C&B’s duties under the Alton
    contract because neither Winston nor Shea read the Alton/C&B contract before trial.
    C&B asserts that any opinion Winston or Shea might have given on the breach of such
    duty was unreliable and, therefore, inadmissible. See U.S. Renal Care, 
    Inc., 345 S.W.3d at 606
    –07 (citing Whirlpool 
    Corp., 298 S.W.3d at 638
    ). C&B further contends that the
    unreliability of the evidence makes it legally insufficient to support a verdict. See 
    id. Although it
    is undisputed that neither expert read the Alton/C&B contract before
    trial, the evidence establishes that each expert had years of experience working in this
    area, taking bids and awarding contracts for similar construction. Sustaining C&B’s
    objections, the trial court did not allow Winston to testify about the Alton/C&B contract.
    Rather, the trial court allowed Winston to testify generally regarding other contracts and
    other projects.
    We also note that the trial court admitted, without objection, the sewer system
    contracts between each contractor or engineer and Alton. And from the C&B/Alton
    contract, Winston read the following language included in its Scope of Services, Task 3:
    C&B would “assure that the project complies with all local, State, and federal regulations
    relevant to the planning and construction of a wastewater collection and transmission
    system.”    Winston and Shea also testified that section 317.13, a sewer system
    regulation, applied in this case.    The supreme court affirmed this conclusion.        See
    Sharyland Water Supply 
    Corp., 354 S.W.3d at 423
    .
    The trial court also allowed Shea to provide, over objection, the following testimony
    about C&B’s contract with Alton:
    21
    Q.     Mr. Shea, my question to you is this: What was your understanding
    of the contract that [C&B] had with the City of Alton?
    A.     As—as a project manager, they would have had overall supervision
    of the work in progress. They would have been responsible for
    seeing that the work was done properly, it was done on time, the
    payments were made for the appropriate work that was done. And
    so they have to have a working knowledge of—of the—the project
    and—and what its progress is and to make sure that—that all the
    rules governing that type of work with—with the public utility is
    observed.
    Q.     Assume with me that their contract provides that they will ensure that
    the project complies with all local, State[,] and federal regulations
    relevant to the planning and construction of a wastewater collection
    and transmission system and that it further provides that they will act
    as the owner’s representative in the administration of construction
    contracts. And based upon your review of the photographs that we
    went through earlier out of Exhibit 1, do you have an opinion as to
    whether or not they met their responsibilities under the contract with
    Alton?
    ....
    Q.     Mr. Shea, my question was: Do you have an opinion?
    A.     Yes, sir.
    Q.     Can you tell us what your opinion is?
    ....
    [A.]   My opinion is that if—in regard to the sewer service connections, and
    in particular the ones that I observed from the excavations that were
    made, the —work was not done properly or according to the plans
    and specifications.
    Q.     Okay. And with respect to—did they meet their requirements under
    their contract with Alton?
    ....
    A.     I don’t—I don’t believe that they fulfilled their duties entirely in regard
    to the project and—concerning particularly the sewer service
    22
    connections that I observed.
    Q.     . . . . Assume with me that their contract provides that they will
    ensure that the project complies with all local and State and federal
    regulations with a wastewater—and also assuming that their
    contract provides that they would act as an owner’s representative in
    the administration of the construction contract. And again, based
    on your review of the—of the photographs and your understanding of
    the Texas Engineering Practices Act, do you believe—what is—do
    you have an opinion with respect to whether or not Carter & Burgess
    met its responsibilities to the public?
    ....
    Q.     Mr. Shea, do you have an opinion?
    A.     Yes, sir, I do.
    Q.     What is your opinion?
    ....
    [A.]   My opinion would be—my opinion is that Carter & Burgess did not
    entirely fulfill their duties under this contract if they were
    knowledgeable of this—the manner in which these sewer service
    connections were being installed in this—in the vicinity of existing
    water lines.
    Shea based his opinions, not on the reading of a particular contract between C&B and
    Alton, but on assumptions.     And there is no evidence that the assumptions were
    unfounded. See City of 
    Keller, 168 S.W.3d at 813
    .
    We cannot conclude that Winston and Shea had no reasonable basis for their
    opinions regarding C&B’s duties under the Alton contract, as C&B argues.         See 
    id. Rather, the
    analysis each expert used to reach his conclusions on the breach of such duty
    was reliable and, therefore, admissible. See TXI Transp. 
    Co., 306 S.W.3d at 239
    (citing
    Exxon Pipeline 
    Co., 88 S.W.3d at 629
    ). We conclude that the trial court did not abuse its
    23
    discretion in admitting the testimony of Winston and Shea. See 
    id. (citing Cooper
    Tire &
    Rubber 
    Co., 204 S.W.3d at 800
    ).
    We also note that engineers employed by the Texas Natural Resource
    Conservation Commission (TNRCC) testified, through deposition testimony, that the
    sewer system was not constructed as required by section 317.13. For example, TNRCC
    engineer Louis C. Herrin testified that “[o]n separation distances [between the sewer line
    and the water line,] it would not meet the separation distances as specified in 317. . . .
    The separation distances are too close.” C&B assured, through its contract with Alton,
    that the project would comply with all state regulations relevant to the planning and
    construction of a wastewater collection and transmission system.           This compliance
    would include section 317.13.
    Thus, viewing the evidence in the light favorable to the finding, we find more than a
    scintilla of evidence that C&B, the engineering company that managed the construction of
    the sewer system, disregarded the appropriate criteria for installation of new sewer lines
    in the proximity of waterlines, a requirement set out in its contract with Alton. See City of
    
    Keller, 168 S.W.3d at 807
    , 810.         We conclude that the evidence would enable
    reasonable and fair-minded people to find that C&B breached the duty owed to
    Sharyland; the evidence is legally sufficient in this regard. See 
    id. at 827.
    We overrule
    the second issue, which addresses the breach element.
    C.     Proximate Cause
    By the third issue, the contractors complain that there was insufficient evidence to
    establish that their actions proximately caused damages. Yet the Texas Supreme Court
    24
    expressly determined the following:
    Sharyland’s [freshwater] system once complied with the law, and now it
    does not. Sharyland is contractually obligated to maintain the system in
    accordance with state law and must either relocate or encase its water
    lines. These expenses, imposed on Sharyland by the contractors’ conduct
    were the damages the jury awarded. Costs of repair necessarily imply that
    the system was damaged, and that was the case here. Sharyland
    presented evidence that it experiences between 100 and 150 water system
    leaks each year. A break in the water line threatens contamination.
    There was evidence that when Sharyland excavated a representative
    sample of sixty-six sewer crossings, sixty of them had been illegally
    installed, and there was at least one leaking sewer pipe located six inches
    above a water pipe. There was also evidence that approximately 340
    locations would require remediation.
    Sharyland Water Supply 
    Corp., 354 S.W.3d at 420
    . We are bound by this determination,
    see 
    Ianni, 210 S.W.3d at 596
    ; 
    Hudson, 711 S.W.2d at 630
    ; 
    Cantu, 89 S.W.3d at 809
    n.21,
    and overrule the third issue, which challenges the proximate cause element of
    Sharyland’s negligence claim.
    D.      Reasonableness of Damages
    By the fourth issue, the contractors argue that the damages award must fail
    because Sharyland offered no competent evidence that the cost of the repairs, past or
    future, was reasonable. The damages question on negligence asked the jury what sum
    of money would fairly and reasonably compensate Sharyland for its damages, if any,
    proximately caused by the contractors’ negligence. That question had one damages
    element, “The reasonable cost of the repairs necessary to restore the property to its
    condition immediately before the injury.”11 The jury awarded Sharyland $14,000 for past
    11
    The contractors do not contend that Sharyland did not prove the repairs sought were necessary.
    See McGinty v. Hennen, 
    372 S.W.3d 625
    , 627 (Tex. 2012) (per curiam). So that issue is not before us.
    See TEX. R. APP. P. 47.1.
    25
    repairs and $1,125,000 for future repairs.
    1.      Past Repair Costs
    The contractors first contend that Sharyland cannot recover for past costs of
    repair. They argue that Sharyland has no past repair costs to recover, only investigative
    costs. They further assert that even the investigative excavation costs were not proven
    reasonable.
    Sharyland called Jim Stuhlman, a twenty-eight-year employee of Sharyland, to
    testify regarding past costs.    Stuhlman testified that, during his investigation, he
    excavated the locations in order to take photographs. When asked what the costs were
    for the seventy crossings he investigated, Stuhlman provided the following answers:
    Q.      . . . When you sent these crews out to investigate these sites, what
    did it cost?
    A.      A guesstimate would be about $15,000.
    Q.      Okay how much did it cost for each—each one?
    A.      In the neighborhood of $200 to $250 for each one.
    Q.      Okay. Is that a pure guess or is that your estimate based on—
    A.      It’s a little of both. We pay a contractor to—to do the work. He
    charges us by the location. That’s $150 on each location, plus there
    is the time and vehicles of my own people while we’re out there.
    ....
    Q.      And for these 70 crossings that you dug up, what did he charge you
    on average?
    A.      He charged—he charged us on average $150.
    Q.      Okay. In addition to that, what costs did Sharyland incur in terms of
    its own personnel?
    26
    A.     That varied with each one because it depended how many people
    went out, how many vehicles were there, whether I went with
    everyone or not.
    Q.     On average, what did it cost?
    A.     Between $50 and $100.
    ....
    Q.     In the cost that the corporation has expended in excavating, was
    there any money at all spent on—on repairing any perceived
    problem?
    A.     No.
    Assuming without deciding that investigative or diagnostic costs are recoverable
    as repair costs, we agree with the contractors that Sharyland did not offer evidence of the
    reasonable cost of past repairs. Stuhlman based his estimate for the excavation costs
    on what a contractor charged Sharyland, “on average.”         This is the only testimony
    regarding the cost of past excavations. The jury simply heard Stuhlman suggest a
    number reached by someone else, without more. He did not tell the jury how the
    average contract charge of $150 to dig up each location may have been reached. The
    contract upon which the figure was based was not entered into evidence. There is no
    evidence showing that the contract charge of $150 was reasonable. See Fort Worth
    
    Hotel, 977 S.W.2d at 762
    –63. In addition, Stuhlman provided general, not specific,
    information regarding Sharyland’s personnel costs for each location—an average cost of
    between $50 and $100. Stuhlman never told the jury why his “guesstimate” of a total
    cost of $15,000 or why an amount “[i]n the neighborhood of $200 to $250 for each
    [excavation]” was reasonable. We conclude that this is no evidence that the charges
    27
    were reasonable. See Mustang Pipeline 
    Co., 134 S.W.3d at 201
    ; Fort Worth Hotel Ltd.
    
    P'ship, 977 S.W.2d at 762
    –63 (concluding that the hotel owner failed to establish the right
    to recover costs of repairs after an explosion damaged the hotel because the hotel owner
    did not present sufficient evidence to justify the jury's finding that costs were reasonable
    and repairs necessary).
    Viewing the evidence in the light favorable to the finding and indulging every
    reasonable inference in support of a reasonableness finding, we conclude the evidence,
    which is based on mere surmise, is not legally sufficient because it would not enable
    reasonable and fair-minded people to find that the cost was reasonable. See City of
    
    Keller, 168 S.W.3d at 807
    , 822, 827; Browning-Ferris, 
    Inc., 865 S.W.2d at 927
    –28. We
    conclude that Sharyland offered no evidence that the excavation costs awarded as past
    repairs in the amount of $14,000 were reasonable.
    2.     Future Repair Costs
    The contractors also contend that Sharyland did not prove the reasonableness of
    future repair costs. TCB specifically asserts that “Winston, Sharyland’s engineering
    expert, had no basis for his estimate of future repair costs because, at bottom, he relied
    on a single price quote, not competitively bid, that he and fellow engineer Shea randomly
    inflated.” It also argues that “[t]he jury, therefore, had no basis for determining whether
    the future repair costs were reasonable.” We disagree.
    Here, Sharyland presented the testimony of its expert Winston, who had
    developed a repair estimate.       Providing a detailed description of his method for
    calculating damages, Winston testified that he (1) utilized his past experience, (2) took
    28
    Shea’s projected 2001 costs that were based on a contractor’s information and some of
    Shea’s known information on how to repair these lines, and (3) applied a price increase
    factor to determine what “a current figure would be to hire a contractor and have it done.”
    On cross-examination, Winston responded to questions regarding the data from the
    contractor that he and Shea had used in developing their repair estimates. According to
    Winston, four years before trial, Shea asked DCR Demolition and Utility for an estimate of
    what it would cost to excavate a crossing and to encase a water main. Winston agreed
    that in response to Shea’s inquiry, DCR estimated that it would cost $400 for each
    excavation and $2,000 per crossing, including the initial excavation, to encase the water
    main with a 10-inch split steel casing, and $1,700 for concrete. Shea increased the
    estimate for an excavation without repairs from $400 to $500; Winston testified he did not
    know how Shea arrived at the increased amount, but was “sure he used his engineering
    judgment and may have talked to other contractors. . . .”
    Winston testified that approximately four years later, he took Shea’s 2001 cost
    estimates and applied a price factor—“a 25 percent price increase”—to bring it to current
    prices due to, among other things, material and labor and the cost of fuel, all of which had
    “really escalated.” Winston reported that his calculations resulted in an excavation cost
    of $625, plus an encasement cost of $2,500 for each water main that was in violation of
    the code. According to Winston, “[t]he $2,500 would reflect going in there and—and
    . . . welding up or taking a steel casing and going around the pipe, welding it up and then
    filling the pipe void, if I recall correctly, with concrete on the ends to seal the ends.”
    In calculating damages, Winston testified that, at the time the plans were drawn,
    29
    there were 440 sewer lines that crossed Sharyland’s water line. According to Winston,
    after checking twenty-two crossings, they found seventeen, or 77 percent, that were in
    violation of the code. Of the 440 crossings, then, there would be 340 (77 percent)
    potentially violating code. Winston testified that, using a statistical model of a 95 percent
    competence level, he was approximately 95 percent confident that the number of
    violations would fall between 252 and 425, with a straight extrapolation or median number
    of 340 crossings in violation. In sum, using a sample of damages that were observed by
    digging up areas where the sewer lines crossed Sharyland’s water lines, Winston
    calculated the percentage of violations requiring repairs at 77 percent with a 95 percent
    competence level and determined a range of crossing in violation from 252 to 425.
    Based on these figures and cost calculations set out above, Winston projected that
    the total cost to dig up the 440 crossings to determine which crossings violated the code,
    at $625 each, would be $275,000. Winston testified that the total encasement cost of the
    projected 340 crossings that would be in violation of the code, at $2,500 each, which he
    acknowledged on cross-examination did not include excavating the crossing, would be
    $875,000, bringing the combined cost to $1,125,000.
    During cross-examination, Winston was questioned regarding Stuhlman’s
    testimony. As detailed above, Stuhlman testified that each excavation cost him $150 to
    dig, which, as defense counsel noted, is approximately one-fourth of what Winston
    estimated the excavation costs to be. Winston responded that the difference between
    Stuhlman’s $150 cost and his $625 estimate “may be that they have got on retainer a
    company to do repairs in this type of work.” At the request of defense counsel, using that
    30
    same calculation, Winston also determined that approximately one-fourth of his $2,500
    estimate to repair the crossing in violation of the code would be $600. And using this
    lower calculation figure for uncovering all 440 crossings and fixing 250, the excavation
    cost would be $66,000 (440 times $150) and the repair costs, $151,200 (252 times $600),
    with a total cost of $217,200. On the high end, the excavation cost would remain
    $66,000 and the repair costs $255,000 (425 times $600), with a total cost of $321,000.
    With those numbers, Winston agreed that the range would be from $217,200 to
    $321,000.
    On re-direct, with regard to the suggested $600 repair cost, Winston testified, over
    objection, that “[f]or the type of repairs needed to—to do what we’re doing, there would
    be—I do not feel like there is any way to do it for the $600 per unit basis the [defense
    counsel] talked about.” Again, over objection, when asked in his professional opinion
    whether he could think of a cheaper way to correct the problems he identified on
    Sharyland’s water lines, Winston responded as follows: “[I]t is an expensive option but
    one that is necessary to correct Sharyland’s water supply lines if the wastewater lines
    themselves are not corrected. This is one of the better alternatives to fix it because we
    would not be shutting down all the individual houses and large amounts of people on that
    water line.   If we were cutting out water lines, lowering them, changing water line
    locations, that cost could be very high.” Winston also testified that he believed that the
    $625 excavation figure was more reasonable than the $150 amount testified to by
    Stuhlman because “of the extensiveness and because of—of the amount that you’d have
    to dig to do [the type of excavation needed]. So that’s why . . . [he] used that number.”
    31
    Having the opportunity to consider this range of figures provided through
    Winston’s testimony, the jury awarded $1,125,000 in future damages. The jury was
    presented with evidence that allowed it to assess the facts and award damages
    accordingly. Sharyland did not just present one amount for damages alone as evidence
    of the amount estimated.      Sharyland provided expert testimony utilizing the DCR
    estimate that was secured and evaluated by Shea and factoring in, among other things,
    the investigation of the twenty-two sewer crossings, the types of available encasements,
    and the increased costs over time. This testimony revealed factors that were considered
    that ensured the reasonableness of the damages awarded by the jury. See 
    McGinty, 372 S.W.3d at 628
    . Sharyland presented evidence from which the jury was able to infer
    reasonableness.    See 
    Carrow, 781 S.W.2d at 694
    .          There was testimony about
    estimated costs for repairing damages to Sharyland’s water system.          These were
    damages that would be incurred in the future if Sharyland were to ensure that its water
    system complied with state regulations. Winston testified as to the number of crossings
    checked and the percentage found to be in violation, the number of crossings to be dug
    up, the estimated number of crossings to be repaired, and the estimated costs for digging
    up each crossing and making those repairs. Winston testified and was cross-examined.
    The evidence was before the jury, allowing the jury to infer the reasonableness of the
    estimates and to award future repairs in the amount of $1,125,000.
    Based on the above, we conclude that the evidence is legally sufficient for
    reasonable and fair-minded jurors to find that the cost of future repairs awarded was
    reasonable. See City of 
    Keller, 168 S.W.3d at 807
    , 822, 827; Browning-Ferris, Inc., 
    865 32 S.W.2d at 927
    –28.
    3.     Summary
    Having concluded that there was no evidence that the cost of past repairs was
    reasonable, we sustain that portion of the fourth issue. But having concluded that the
    evidence is legally sufficient to support the reasonableness of the amount of damages
    awarded for future repairs, we overrule that portion of the fourth issue.
    IV.     CONCLUSION
    We reverse and render that Sharyland take-nothing as to past damages and affirm
    the remainder of the judgment as to Sharyland’s negligence claim against Carter &
    Burgess, Inc., Turner, Collie & Braden, Inc., and Cris Equipment Company, Inc.
    NELDA V. RODRIGUEZ
    Justice
    Delivered and filed the
    30th day of May, 2013.
    33
    

Document Info

Docket Number: 13-06-00038-CV

Citation Numbers: 402 S.W.3d 867, 2013 WL 2353798, 2013 Tex. App. LEXIS 6606

Judges: Garza, Rodriguez, Valdez

Filed Date: 5/30/2013

Precedential Status: Precedential

Modified Date: 11/14/2024

Authorities (34)

Dallas Railway & Terminal Company v. Gossett , 156 Tex. 252 ( 1956 )

Vanscot Concrete Co. v. Bailey , 36 Tex. Sup. Ct. J. 928 ( 1993 )

Dukes v. PHILIP JOHNSON/ALAN RITCHIE ARCH., PC , 252 S.W.3d 586 ( 2008 )

Whirlpool Corp. v. Camacho , 53 Tex. Sup. Ct. J. 179 ( 2009 )

Kroger Co. v. Elwood , 49 Tex. Sup. Ct. J. 623 ( 2006 )

Bennett v. Span Industries, Inc. , 1981 Tex. App. LEXIS 4657 ( 1981 )

Hudson v. Wakefield , 29 Tex. Sup. Ct. J. 445 ( 1986 )

Chrysler Insurance Co. v. Greenspoint Dodge of Houston, Inc. , 53 Tex. Sup. Ct. J. 96 ( 2009 )

Loram Maintenance of Way, Inc. v. Ianni , 49 Tex. Sup. Ct. J. 874 ( 2006 )

Exxon Pipeline Co. v. Zwahr , 88 S.W.3d 623 ( 2002 )

Columbia Medical Center of Las Colinas, Inc. v. Hogue , 51 Tex. Sup. Ct. J. 1220 ( 2008 )

Southwestern Bell Telephone Co. v. DeLanney , 809 S.W.2d 493 ( 1991 )

Fort Worth Hotel Ltd. Partnership v. Enserch Corp. , 1998 Tex. App. LEXIS 4688 ( 1998 )

Cook Consultants, Inc. v. Larson , 1985 Tex. App. LEXIS 12901 ( 1985 )

City of Keller v. Wilson , 48 Tex. Sup. Ct. J. 848 ( 2005 )

Liptak v. Pensabene , 736 S.W.2d 953 ( 1987 )

Ron Craft Chevrolet, Inc. v. Davis , 836 S.W.2d 672 ( 1992 )

Yeager v. Drillers, Inc. , 1996 Tex. App. LEXIS 2008 ( 1996 )

Cooper Tire & Rubber Co. v. Mendez , 49 Tex. Sup. Ct. J. 751 ( 2006 )

Allright, Inc. v. Lowe , 1973 Tex. App. LEXIS 2631 ( 1973 )

View All Authorities »