Oncor Electric Delivery Company LLC v. Giovanni Homes Corporation , 2014 Tex. App. LEXIS 3596 ( 2014 )


Menu:
  •                         COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-11-00237-CV
    ONCOR ELECTRIC DELIVERY                           APPELLANT AND APPELLEE
    COMPANY LLC
    V.
    GIOVANNI HOMES CORPORATION                        APPELLEE AND APPELLANT
    ----------
    FROM THE 48TH DISTRICT COURT OF TARRANT COUNTY
    ----------
    OPINION
    ----------
    I. Introduction
    In three issues, appellant Oncor Electric Delivery Company LLC appeals
    the trial court’s judgment on the jury verdict for appellee Giovanni Homes
    Corporation on Giovanni Homes’s breach-of-contract claim and award of
    attorneys’ fees and argues that Giovanni Homes’s trespass claim cannot serve
    as an alternative basis for judgment against it. In a single issue in its cross-
    appeal, Giovanni Homes appeals the trial court’s judgment notwithstanding the
    verdict (JNOV) in favor of Oncor on the jury’s award of interest payments on
    construction loans to Giovanni Homes.
    Having encountered a jurisdictional defect in the case,1 we do not reach
    the merits of these issues. We reverse the trial court’s judgment and remand this
    case to the trial court with instructions to abate the case to allow Giovanni Homes
    a reasonable opportunity to cure the jurisdictional defect if possible. See Am.
    Motorists Ins. Co. v. Fodge, 
    63 S.W.3d 801
    , 805 (Tex. 2001) (stating that the
    court may abate proceedings to allow a reasonable opportunity to cure a
    jurisdictional impediment if the impediment is one that can be cured).
    II. Factual and Procedural Background
    Giovanni Homes had to work with Oncor2 to obtain electricity for some
    parcels of real property that it was developing in Fort Worth. Giovanni Homes
    wanted to secure a new single-phase electrical line to serve the development;
    after discovering a three-phase electrical line on its property on April 27, 2007, it
    1
    The parties filed supplemental briefs regarding the jurisdictional issue in
    response to the court’s request for additional briefing, and the court heard
    supplemental oral argument on the issue on February 11, 2014.
    2
    As recognized by the supreme court, Oncor “owns and operates the
    largest electric distribution and transmission system in Texas, delivering power
    over some 117,000 miles of lines to about three million homes and businesses.”
    Oncor Elec. Delivery Co. v. Dallas Area Rapid Transit, 
    369 S.W.3d 845
    , 847
    (Tex. 2012).
    2
    also wanted to relocate that line and transformer box from its property.3 The
    single-phase line was not installed until June 2008, and the three-phase line was
    not relocated until February 2009.       Ultimately, the parties went to trial in
    December 2010 on Giovanni Homes’s claims arising from the parties’
    interactions in 2007 and 2008.4
    Giovanni Homes’s breach-of-contract theory was based primarily on
    Plaintiff’s Exhibit 80, a July 23, 2007 letter from Richard Hildebrand, an Oncor
    employee, to a Giovanni Homes secretary, which states,
    Oncor Electric Delivery intends to reroute the existing
    underground primary cable currently installed through the lot in
    question into a new easement along the private drive to be provided
    by Giovanni Homes. The relocation will reconnect the existing
    service necessary to provide service to the existing customers along
    with serving the new proposed development.
    Vincent Piras, Giovanni Homes’s owner, testified that in exchange for the lines’
    installation and relocation, Giovanni Homes was to obtain the easements across
    neighboring properties for Oncor and that he had obtained all of those
    easements and delivered them to Oncor by December 6, 2007.
    The trial court submitted Question No. 1 to the jury:
    3
    Neither party disputes that the line was located outside of the platted utility
    easement at the direction of a previous owner or that it supplied electricity to an
    adjacent landowner.
    4
    In 2008, Giovanni Homes sued Oncor for trespass, negligence, and
    conspiracy; it added a breach-of-contract claim against Oncor in 2010. Prior to
    the case’s submission to the jury, the other parties involved in the case either
    settled or were severed from it, and Giovanni Homes’s only remaining claims
    against Oncor at trial were for trespass and breach of contract.
    3
    Did Giovanni Homes and Oncor agree on July 23, 2007 that:
    a.    Oncor would relocate the three-phase underground primary
    cable from the Residential Lots and the Commercial Lot to a new
    easement?
    b.    Oncor would supply electrical power via single-phase line to
    the Townhome Lots, Residential Lots, and Commercial Lot?
    In deciding whether the parties reached an agreement,
    you may consider what they said and did in light of the
    surrounding circumstances, including any earlier course
    of dealing.     You may not consider the parties’
    unexpressed thoughts or intentions.
    Answer “Yes” or “No” for each:
    a.    Relocate the three-phase line:
    b.    Supply electrical power via single-phase line:
    The jury unanimously answered “Yes” to both 1.a. and 1.b. and concluded in a
    10–2 vote that Oncor had breached the agreement by failing to timely comply
    with it.   The jury also unanimously concluded that Oncor had trespassed on
    Giovanni Homes’s commercial lot, through which the three-phase line ran.
    The jury awarded to Giovanni Homes over a million dollars in damages on
    the contract claim, including $189,611 for construction loan interest payments,
    and attorneys’ fees. It awarded to Giovanni Homes $60,000 in damages on the
    trespass claim. Giovanni Homes elected to recover under its breach-of-contract
    theory, and Oncor sought a JNOV.
    The trial court entered judgment in favor of Giovanni Homes except for
    recovery of the construction loan interest payments and awarded to Giovanni
    4
    Homes $949,061 under its breach-of-contract theory, as well as prejudgment and
    postjudgment interest, attorneys’ fees, and costs; it denied Oncor’s JNOV motion
    except as to the construction loan interest payments. This appeal and cross-
    appeal followed.
    III. Jurisdiction
    In the initial briefing in this case, Oncor argued, among other things, that its
    tariff (the Tariff), which Giovanni Homes offered into evidence and which the trial
    court admitted, required Giovanni Homes to provide easements to Oncor and
    that those easements therefore could not be consideration to support the alleged
    agreement between the parties.       Oncor further argued that the law “forbade
    Oncor from changing or ignoring the terms of the Tariff.”
    Upon examining the Tariff and the utilities code, we discovered a potential
    jurisdictional issue requiring supplemental briefing and requested that each party
    file a brief to (1) address whether the Public Utility Commission of Texas (the
    PUC)5 had exclusive jurisdiction over Giovanni Homes’s breach-of-contract claim
    5
    Although our reference was to the PUC, the Public Utility Regulatory Act
    (PURA) specifically provides that the PUC has exclusive original jurisdiction over
    the rates, operations, and services of an electric utility in (1) areas outside a
    municipality; and (2) areas inside a municipality that surrenders its jurisdiction to
    the commission under section 33.002. See Tex. Util. Code Ann. § 32.001(a)
    (West 2007). However, when a municipality has not surrendered its jurisdiction
    to the PUC, the municipality has exclusive original jurisdiction over the rates,
    operations, and services of an electric utility, and the PUC then has exclusive
    appellate jurisdiction to review the municipality’s order. 
    Id. §§ 32.001(b),
    32.002,
    33.001(a) (West 2007). Therefore, our references here to the PUC encompass
    the municipality (City of Fort Worth) to the extent that it has not surrendered its
    jurisdiction to the PUC. See 
    id. § 32.004
    (West 2007) (stating that upon a
    5
    and (2) explain the role of the Tariff and the filed-rate doctrine in light of the 1999
    deregulation amendments to the Public Utility Regulatory Act. See City of Allen
    v. Pub. Util. Comm’n of Tex., 
    161 S.W.3d 195
    , 199 (Tex. App.—Austin 2005, no
    pet.) (stating that the question of jurisdiction is fundamental and can be raised at
    any time in the trial of a case or on appeal).
    In its supplemental briefing, Oncor argued that the breach-of-contract claim
    directly related to Oncor’s provision of “Delivery Services” covered by the Tariff
    and that the PURA placed exclusive original jurisdiction over issues covered by
    the Tariff in the pertinent regulatory authorities, while Giovanni Homes countered
    that the contract was “a private, non-administrative, non-regulatory agreement
    that does not fall within the PURA’s stated purpose for enactment.”6 Giovanni
    Homes contends that the Tariff does not govern its claims and so does not
    trigger the PURA’s exclusive jurisdiction provisions. We therefore review the
    PURA and the Tariff to determine whether Giovanni Homes’s contract claim falls
    within their purview.
    municipality’s request, the PUC may advise and assist the municipality with
    respect to a question or proceeding arising under the PURA).
    6
    Although the parties disagree about the application of the Tariff and the
    filed-rate doctrine, both agreed that the PUC continues to regulate Oncor even
    after deregulation.
    6
    A. Exclusive Jurisdiction
    An agency has exclusive jurisdiction when the legislature has granted that
    agency the sole authority to make an initial determination in a dispute and when
    a pervasive regulatory scheme indicates that the legislature intended for the
    regulatory process to be the exclusive means of remedying the problem to which
    the regulation is addressed. In re Entergy Corp., 
    142 S.W.3d 316
    , 321–22 (Tex.
    2004) (orig. proceeding). If an agency has exclusive jurisdiction, a party must
    exhaust all administrative remedies before seeking review of the agency’s action.
    
    Id. at 321.
    Until the party has exhausted all administrative remedies, the trial
    court lacks subject matter jurisdiction and must dismiss any claim within the
    agency’s exclusive jurisdiction. 
    Id. at 321–22;
    see also GuideOne Ins. Co. v.
    Cupps, 
    207 S.W.3d 900
    , 904 (Tex. App.—Fort Worth 2006, pet. denied).
    B. Public Utility Regulatory Act
    The utilities code governs electric, telecommunications, and gas utilities.
    See Tex. Util. Code Ann. §§ 11.004, 31.002, 51.002, 101.003, 181.001 (West
    2007 & Supp. 2013). The PURA—located in utilities code title 2—contains the
    provisions that apply to the jurisdictional issue before us.7 See State v. Pub. Util.
    7
    Title 3 contains the Gas Utility Regulatory Act (GURA). See Tex. Util.
    Code Ann. §§ 101.001–124.002 (West 2007). Title 4, subtitle A, addresses
    cooperatives, joint power agencies, and joint ownership of electric facilities by
    public entities. 
    Id. §§ 161.001–164.006
    (West 2007). Subtitle B of title 4
    contains provisions regulating delivery of services, including the condemnation
    power; the authority to own, hold, or use land, a right-of-way, an easement, a
    franchise, or a building or other structure as necessary; the power to generate,
    transport, and sell electric current, to impose reasonable charges, and to
    7
    Comm’n of Tex., 
    883 S.W.2d 190
    , 196 (Tex. 1994) (stating that in ascertaining
    the scope of the PUC’s authority, “we must read PURA as a whole to ascertain
    the underlying legislative intent”). Within title 2, chapters 11, 14, and 17 of the
    general PURA provisions8 and chapters 31, 32, 33, and 38 of the specific PURA
    provisions applicable to electric utilities are pertinent to our discussion.9 See
    construct, maintain, and operate power plants, substations, and other machinery
    as necessary to operate lines. See 
    id. §§ 181.004,
    .007–.008 (West 2007).
    Within title 4, sections 181.041 through 181.047 specifically apply to
    electric utilities but do not affect our discussion on the facts of this case. 
    Id. §§ 181.041–.047
    (West 2007 & Supp. 2013). For example, under section
    181.046(b), the Texas Transportation Commission or a county commissioners
    court may require an electric utility to relocate a line at the utility’s own expense
    to allow for widening of a right-of-way, changing a traffic lane, improving a road
    bed, or improving a drainage ditch located on a right-of-way. 
    Id. § 181.046(b).
    Various other provisions in title 4 apply to telephone and telegraph companies,
    meter testing, deposits, and solar energy device ratings, among other items not
    pertinent to the disposition of the issue before us. 
    Id. §§ 181.081–185.005
    (West
    2007 & Supp. 2013). Title 5 addresses facility damage prevention and safety.
    
    Id. §§ 251.001–.203
    (West 2007 & Supp. 2013).
    8
    Chapter 12 pertains to the organization of the PUC, chapter 13 pertains to
    the office of public utility counsel, chapter 15 covers judicial review of
    administrative proceedings, including enforcement and penalties; and chapter 16
    covers commission financing. See Tex. Util. Code Ann. §§ 12.001–.255,
    13.001–.064, 15.001–.052, 16.001–.044 (West 2007).
    9
    Chapter 34 has been repealed, chapter 35 addresses alternative energy
    providers, and chapter 36 pertains exclusively to rates—how they are computed,
    procedures for proposed rate changes, cost recovery and rate adjustment, rates
    for governmental entities, and securitization for recovery of system restoration
    costs. Tex. Util. Code Ann. §§ 35.001–.152, 36.001–.406 (West 2007 & Supp.
    2013). Chapter 37 involves certificates of convenience and necessity. 
    Id. §§ 37.001–.157
    (West 2007 & Supp. 2013). Chapter 39 addresses deregulation
    and procedures that have no bearing on the breach-of-contract issue in this case.
    
    Id. §§ 39.001–.916
    (West 2007 & Supp. 2013). Chapter 40 addresses
    competition for municipally owned utilities and river authorities, chapter 41
    8
    Tex. Util. Code Ann. §§ 11.001–.009, 14.001–.207, 17.001–.203, 31.001–43.152
    (West 2007 & Supp. 2013).
    In construing the PURA, our objective is to determine and give effect to the
    legislature’s intent, looking at the plain and common meaning of the statute’s
    words. 
    Entergy, 142 S.W.3d at 322
    . When a statute’s meaning is unambiguous,
    we interpret the statute according to its plain language. Id.; see also In re Sw.
    Bell Tel. Co., 
    235 S.W.3d 619
    , 624–25 (Tex. 2007) (orig. proceeding). Further,
    “[i]n determining the meaning of a statute, a court must consider the entire act, its
    nature and object, and the consequences that would follow from each
    construction.” Benish v. Grottie, 
    281 S.W.3d 184
    , 193 (Tex. App.—Fort Worth
    2009, pet. denied) (citing Sharp v. House of Lloyd, Inc., 
    815 S.W.2d 245
    , 249
    (Tex. 1991)); see generally Tex. Gov’t Code Ann. §§ 311.001–.034 (West 2013)
    (setting out presumptions and matters to be considered in construing statutes).
    1. General Provisions
    The legislature enacted the PURA “to protect the public interest inherent in
    the rates and services of public utilities.” Tex. Util. Code Ann. § 11.002(a). The
    PURA’s purpose is “to establish a comprehensive and adequate regulatory
    system for public utilities to assure rates, operations, and services that are just
    and reasonable to the consumers and to the utilities.” 
    Id. It grants
    to the PUC
    involves electric cooperatives, and chapter 43 involves use of the electric delivery
    system for access to broadband and other enhanced services. 
    Id. §§ 40.001–
    .104 (West 2007 & Supp. 2013), §§ 41.001–.104 (West 2007 & Supp. 2013),
    §§ 43.001–.152 (West 2007). There is no chapter 42.
    9
    the authority to make and enforce rules necessary to protect electric services for
    customers consistent with the public interest. 
    Id. § 11.002(c).
    Under the PURA, “service” has its “broadest and most inclusive meaning,”
    which includes “any act performed, anything supplied, and any facilities used or
    supplied by a public utility in the performance of the utility’s duties under this title
    to its patrons, employees, other public utilities, an electric cooperative, and the
    public.”   
    Id. § 11.003(19).
      “Rate” is likewise broadly defined to include “any
    compensation, tariff, charge, fare, toll, rental, or classification that is directly or
    indirectly demanded, observed, charged, or collected by a public utility for a
    service, product, or commodity described in the definition of utility in Section
    31.002 or 51.002,” and “a rule, practice, or contract affecting the compensation,
    tariff, charge, fare, toll, rental, or classification.”10   
    Id. § 11.003(16)(A)–(B).
    10
    Section 31.002(15), which pertains specifically to electric utilities,
    contains the same definition of “rate” but adds a restrictive clause after
    classification:
    a compensation, tariff, charge, fare, toll, rental, or classification that
    is directly or indirectly demanded, observed, charged, or collected by
    an electric utility for a service, product, or commodity described in
    the definition of electric utility in this section and a rule, practice, or
    contract affecting the compensation, tariff, charge, fare, toll, rental,
    or classification that must be approved by a regulatory authority.
    Tex. Util. Code Ann. § 31.002(15) (emphasis added); see Tex. W. Oaks Hosp.,
    L.P. v. Williams, 
    371 S.W.3d 171
    , 184–85 (Tex. 2012) (“Scrutinizing grammar in
    interpreting statutes, we are cognizant of the rule that ‘[m]odifiers should come, if
    possible, next to the words they modify.’”) (quoting William Strunk, Jr. & E.B.
    White, The Elements of Style R. 30 (4th ed. 2000)). Chapter 31 does not include
    a separate definition for services, and neither chapter 11 nor chapter 31 defines
    “operations.”
    10
    Further, we are directed to liberally construe the PURA to promote the
    effectiveness and efficiency of regulation of public utilities to the extent that this
    construction preserves the validity of the PURA and its provisions. 
    Id. § 11.008.
    Government code chapter 2001 (the Administrative Procedure Act) applies to a
    proceeding under the PURA “except to the extent inconsistent with this title.” 
    Id. § 11.007(a).
    The PURA provides that public agencies regulate utility rates, operations,
    and services as a substitute for competition, 
    id. § 11.002(b),
    and the PUC
    “exercises the jurisdiction and powers conferred” by the PURA. 
    Id. § 12.001.
    Despite the 1999 deregulation amendments, the PUC is still charged with
    regulating utilities as required to facilitate competition, free market operation, and
    customer choice. Compare Oncor Elec. Delivery Co. v. Pub. Util. Comm’n of
    Tex., 
    406 S.W.3d 253
    , 256 (Tex. App.—Austin 2013, no pet.) (noting that Oncor,
    as a regulated electric utility company, applies to the PUC for authorization to
    change its system-wide rates), Nucor Steel-Tex. v. Pub. Util. Comm’n of Tex.,
    
    363 S.W.3d 871
    , 873 (Tex. App.—Austin 2012, no pet.) (stating that under the
    PURA, the PUC was required to analyze whether the acquisition of a regulated
    utility is in the public interest), and Sw. Elec. Power Co. v. Pub. Util. Comm’n,
    
    419 S.W.3d 414
    , 423(Tex. App.—Amarillo 2011, pet. denied) (quoting section
    25.1 of the administrative code pertaining to PUC’s purpose), with Double
    Diamond, Inc. v. Hilco Elec. Co-op., Inc., 
    127 S.W.3d 260
    , 263 & n.6 (Tex.
    App.—Waco 2003, no pet.) (stating that on September 1, 1999, the Hilco electric
    11
    cooperative ceased to be regulated by the PUC), subseq. disp., 
    195 S.W.3d 336
    (Tex. App.—Waco 2006, pet. denied).
    The PUC “has the general power to regulate and supervise the business of
    each public utility within its jurisdiction and to do anything specifically designated
    or implied by [the PURA] that is necessary and convenient to the exercise of that
    power and jurisdiction.” Tex. Util. Code Ann. § 14.001. The PUC may also
    decide a dispute involving a private agreement that directly affects the public
    interest. Pub. Util. Comm’n of Tex. v. Sw. Bell Tel. Co., 
    960 S.W.2d 116
    , 122–23
    (Tex. App.—Austin 1997, no writ) (op. on reh’g) (stating that attorneys’ fee
    agreement was more than a private agreement because it directly affected the
    public interest). Under the PURA, the PUC and individual municipalities share
    jurisdiction over the regulation of utilities, including the establishment and
    regulation of utility rates. Oncor 
    Elec., 406 S.W.3d at 256
    & n.3 (citing Tex. Util.
    Code Ann. §§ 32.001(a)–(b), 33.001–.002).
    Further, chapter 17 of the PURA specifically covers “Customer Protection,”
    the purpose of which is to establish retail customer protection standards and
    confer on the PUC “authority to adopt and enforce rules to protect retail
    customers from fraudulent, unfair, misleading, deceptive, or anticompetitive
    practices.”   Tex. Util. Code Ann. § 17.001(b).      Section 17.004 states that all
    buyers of retail electric services are entitled to “impartial and prompt resolution of
    disputes with . . . an electric utility,” and that the PUC may adopt and enforce
    rules as necessary and appropriate to carry out customer protection standards.
    12
    
    Id. § 17.004(a)(5),
    (b).   Section 17.157 provides that the PUC may resolve
    disputes between a retail customer and an electric utility. 
    Id. § 17.157(a).
    It may
    also order the utility to produce information or records, require that all contracts
    display a working toll-free number that customers can call with complaints and
    inquiries, require a utility to refund or credit overcharges or unauthorized charges
    with interest if it has failed to comply with PUC rules or a contract with the
    customer, and “investigate an alleged violation.” 
    Id. § 17.157.
    Section 17.157(c)
    requires the PUC to adopt procedures to resolve disputes in a timely manner, not
    to exceed sixty days. 
    Id. § 17.157(c).
    As noted by the supreme court,
    The PUC has broad regulatory authority to ensure utilities provide
    safe, adequate, efficient, and reasonable service. Several PUC
    regulations provide remedies to consumers and penalize utilities for
    unsafe or inadequate service. For example, the PUC may institute a
    formal investigation against a utility on its own initiative or upon a
    customer’s complaint. A customer may complain to the PUC about
    an electric utility’s acts or omissions that violate the PURA or PUC
    regulations. The PUC resolves these complaints either through an
    informal proceeding or through a formal complaint process.
    The PUC also imposes administrative penalties on utilities that
    do not provide safe, adequate, reasonable, and efficient service to
    customers.    These penalties can include lowering a utility’s
    reasonable return on investment capital, adopting minimum
    performance target levels the utility must meet, adopting customer-
    service performance benchmarks, requiring quality assurance
    through independent audits and consultants, and requiring the utility
    to provide notice to customers about a utility’s service quality
    requirements.
    Sw. Elec. Power Co. v. Grant, 
    73 S.W.3d 211
    , 221 (Tex. 2002) (internal citations
    omitted.)
    13
    2. Specific Provisions
    The PUC has exclusive original jurisdiction over the rates, operations, and
    services of an electric utility in areas outside a municipality and areas inside a
    municipality that surrenders its jurisdiction to the PUC. Tex. Util. Code Ann.
    § 32.001(a); Ellis v. Reliant Energy Retail Servs., L.L.C., 
    418 S.W.3d 235
    , 244
    (Tex. App.—Houston [14th Dist.] 2013, no pet.) (stating that “the plain language
    of sections 31.001 and 32.001 clearly expresses the Legislature’s intent that
    PURA be the exclusive means of regulating, and the PUC exercise exclusive
    jurisdiction with regard to, electric utilities”); City of Hous. v. Centerpoint Energy
    Hous. Elec., LLC, No. 01-11-00885-CV, 
    2012 WL 6644982
    , at *4 (Tex. App.—
    Houston [1st Dist.] Dec. 20, 2012, no pet.) (mem. op.) (“PURA sections 32.001
    and 33.001 expressly grant ‘exclusive original jurisdiction’ over the rates and
    services of an electric utility to the governing body of the municipality or to the
    Public Utilities Commission, if a municipality’s jurisdiction is not implicated.”); see
    also Hyde v. Ray, 
    181 S.W.3d 835
    , 841, 843 (Tex. App.—Fort Worth 2005, no
    pet.) (interpreting temporary injunction order directly related to water service as
    invading the TCEQ’s exclusive jurisdiction under water code section 13.042(e));
    Meekey v. Rick’s Cabaret Int’l, Inc., 
    171 S.W.3d 394
    , 398–99 (Tex. App.—
    Houston [14th Dist.] 2005, pet. denied) (op. on reh’g) (stating that examples of
    statutory language conferring exclusive jurisdiction are found in section 32.001 of
    the PURA; article 4413(36), section 3.01(a) of the Texas Revised Civil Statutes;
    tax code section 111.104(b–f); and in the water code).
    14
    The legislature enacted chapters 31 through 43 of the PURA “to protect
    the public interest inherent in the rates and services of electric utilities” and “to
    establish a comprehensive and adequate regulatory system for electric utilities to
    assure rates, operations, and services that are just and reasonable to the
    consumers and to the electric utilities.” Tex. Util. Code Ann. § 31.001(a). Except
    as otherwise provided by the PURA, “[p]ublic agencies regulate electric utility
    rates, operations, and services.” 
    Id. § 31.001(b);
    see 
    Entergy, 142 S.W.3d at 323
    (stating that the PURA’s statutory description as “comprehensive” showed
    the legislature’s belief that it “would comprehend all or virtually all pertinent
    considerations involving electric utilities operating in Texas”).
    Under section 32.101, an electric utility shall file with the PUC a tariff
    showing each rate that is subject to the PUC’s original or appellate jurisdiction
    and in effect for a utility service, product, or commodity offered by the utility. Tex.
    Util. Code Ann. § 32.101(a). As part of the tariff, it shall also file each rule that
    relates to or affects a rate of the utility or a utility service, product, or commodity
    furnished by it.    
    Id. § 32.101(b).
        Accordingly, under the utilities code, the
    provision of any service by Oncor is governed by its tariff. See 
    id. § 32.101.
    The
    tariff is filed with and approved by the PUC, which adopts “just and reasonable
    standards, classifications, rules, or practices an electric utility must follow in
    furnishing a service.” 
    Id. § 38.002(1);
    see also CenterPoint Energy Hous., 
    2012 WL 6644982
    , at *1 (observing that a tariff governs the terms and conditions of
    services provided by an electric utility).
    15
    Maintaining the uniformity of rates and services is essential to the PURA’s
    regulatory scheme. See Tex. Util. Code Ann. § 36.002 (stating that an electric
    utility may not charge or receive a rate for utility service except as provided by
    this title); § 36.004(a) (stating that an electric utility may not directly or indirectly
    charge, demand, or receive from a person a greater or lesser compensation for a
    service provided or to be provided by the utility than the compensation prescribed
    by the applicable tariff filed under section 32.101). And under section 38.002, the
    regulatory authority, on its own motion or on complaint and after reasonable
    notice and hearing, may adopt just and reasonable standards, classifications,
    rules, or practices an electric utility must follow in furnishing a service. 11 
    Id. § 38.002(1);
    see also 
    id. § 38.021
    (stating that in providing a service to persons
    in a classification, an electric utility may not either grant an unreasonable
    preference or advantage or subject a person to an unreasonable prejudice or
    disadvantage).
    3. The PUC’s Administrative Rules
    Administrative rules have the same force as statutes and are generally
    construed in the same way. See 
    Ellis, 418 S.W.3d at 248
    . The PUC’s rules
    state that its mission is “to assure the availability of safe, reliable, high quality
    services that meet the needs of all Texans at just and reasonable rates” by
    11
    Chapter 38 provides for the regulation of electric services in terms of
    safety, adequacy, and efficiency of service. Tex. Util. Code Ann. §§ 38.001–
    .101.
    16
    establishing a comprehensive system with respect to electric service and “to
    establish the rights and responsibilities of the electric utilities . . . and electric
    customers.” 16 Tex. Admin. Code § 25.1 (2003) (Pub. Util. Comm’n, Purpose
    and Scope of Rules). The PUC’s rules set out time limits for items such as
    requests for construction of line extensions.12 
    Id. § 25.22(3)
    (1999) (Pub. Util.
    Comm’n, Request for Service). Under the rules, a customer may file a complaint
    in person, by letter, or by telephone with the electric utility, which “shall promptly
    investigate and advise the complainant of the results within 21 days.”             
    Id. § 25.30(a)
    (1999) (Pub. Util. Comm’n, Complaints). The customer has the right
    to request a supervisory review if unsatisfied with the electric utility’s response to
    the complaint.    
    Id. § 25.30(b).
    The results of the supervisory review must be
    provided in writing to the customer within ten days of the review, and customers
    who are dissatisfied with the supervisory review must be informed of their right to
    file a complaint with the PUC. 
    Id. § 25.30
    (b)(3), (4), (c).
    12
    The PUC’s time limit for completing requests for new residential service
    such as line extensions is within ninety days or within a time period agreed to by
    the customer and the utility if the applicant has met credit requirements, made
    satisfactory payment arrangements for construction charges, and complied with
    all applicable state and municipal regulations. 16 Tex. Admin. Code § 25.22(3)
    (1999) (Pub. Util. Comm’n, Request for Service).
    17
    4. Oncor’s Tariff
    Oncor’s Tariff, comprised of “Rate Schedules, Riders, and service rules
    and regulations,” contains numerous definitions and states that it covers “any
    Service Agreements made pursuant to the Tariff.”            Therefore, if the alleged
    agreement between Giovanni Homes and Oncor was a “Service Agreement,”
    then it falls under the Tariff.
    The Tariff defines “Service Agreement” as “[a]ny Commission-approved
    agreement between Company and a Retail Customer . . . which sets forth certain
    information, terms, obligations and/or conditions of Delivery Service pursuant to
    the provisions of this Tariff.”    It defines “Delivery Service” as “[t]he service
    performed by Company pursuant to this Tariff for the Delivery of Electric Power
    and Energy.       Delivery Service comprises Delivery System Services and
    Discretionary Services.” “Delivery System Services” are defined as “all Tariffed
    Delivery Services provided by the Company that are not specifically defined as
    Discretionary Services,” while “Discretionary Services” are defined as “Customer-
    specific services for which costs are recovered through separately priced Rate
    Schedules specified in Chapter 6.” Chapter 6 of the Tariff covers “Construction
    Service Charges.”
    Under the Tariff, line installations and relocations fall under the definition of
    “Construction Services,” as “[s]ervices related to the construction, extension,
    installation, modification, repair, upgrade, conversion, relocation, or removal of
    18
    Delivery System facilities,[13] including temporary facilities.” [Emphasis added.]
    “Whenever used in the context of Construction Services, the term Retail
    Customer also includes property owners, builders, developers, contractors,
    governmental entities, or any other organization, entity, or individual that is not a
    Competitive Retailer making a request for such services to the Company.”
    [Emphasis added.]
    Section 6.1.2.2 of the Tariff applies to all retail customers requesting
    construction services from Oncor under section 5.7, the Tariff’s “Facilities
    Extension Policy.” The facilities extension policy covers the extension of service
    at a retail customer’s request for the installation of standard facilities and the
    removal and relocation of facilities. It states that Oncor is responsible for the
    construction of delivery system facilities necessary to connect a retail customer
    to the delivery system but that payments in the form of a contribution in aid of
    construction or an advance for construction may be required prior to
    commencement of construction, in accordance with sections 5.7.4, 5.7.5, and
    6.1. Further, section 5.7.2 provides that Oncor may require an executed facility
    extension agreement, in the form approved by the PUC and specified in section
    6.3, which covers agreements and forms, before it constructs delivery system
    facilities. When any payments are required, Oncor “will provide a detailed cost
    13
    The Tariff defines “Delivery System” as “[t]he electric lines, and other
    equipment, including transformers, owned by Company and the Meters, including
    Non-Company Owned Meters, used in the Delivery of Electric Power and
    Energy.”
    19
    estimate for the entity requesting the service to determine the special contractual
    arrangements required before Construction Service is provided.”
    Section 5.7.3, “Processing of Requests for Construction of Delivery
    System,” is particularly relevant and states,
    Requests for new residential Delivery Service requiring Construction
    Service, such as line extensions, shall be completed within 90 days
    of execution of the Facility Extension Agreement, or within a time
    period agreed to by the entity requesting the Construction Service
    and Company, and after the entity requesting Construction Service
    has made satisfactory payment arrangements for Construction
    Service Charges. For all other extensions requiring construction,
    request should be completed within the time estimated by
    Company. . . . Unless mutually agreed to by Company and Retail
    Customer, within ten Business Days of Company’s receipt of a
    detailed request, Company shall give the entity requesting
    Construction Service an estimated completion date and an
    estimated cost for all charges to be assessed.
    Unless a delay is beyond the reasonable control of Company, a
    delay of more than 90 days beyond execution of the Facility
    Extension Agreement for new residential Delivery Service shall
    constitute failure to serve, unless the entity requesting the service
    has agreed to a longer term. The Commission may conduct
    enforcement action and seek penalties and other remedies for
    unreasonable delays.
    [Emphasis added.] Section 5.7.8, pertaining to the removal and relocation of
    Oncor’s facilities and meters, requires the entity requesting the removal or
    relocation to pay Oncor “the total cost of removing or relocating such Delivery
    System facilities in accordance with Chapter 6.”
    Section 6.1.2.2.1.4, “Space Requirements,” provides that with regard to
    delivery system facilities,
    20
    Retail Customer grants to or secures for Company, at Retail
    Customer’s expense, any rights-of-way or easements on property
    owned or controlled by Retail Customer that are necessary for
    Company to install Delivery System facilities for the purpose of
    delivering Electric Power and Energy to the Retail Customer. Such
    easement will be in a form acceptable to Company, including but not
    limited to, the form of easement agreements set forth in Section 6.3
    of this Tariff.
    With respect to distribution facilities, Retail Customer shall provide
    any necessary rights-of-way on property not owned or controlled by
    Retail Customer. If Retail Customer is unable to secure for
    Company any necessary rights-of-way or easements on property not
    owned or controlled by Retail Customer, Retail Customer shall be
    responsible for the actual costs incurred by Company in obtaining
    and clearing such rights-of-way or easements.
    [Emphasis added.]
    Chapter 6 includes another set of specific definitions, including
    “CONTRIBUTION IN AID OF CONSTRUCTION” (CIAC), which is a payment by
    the customer to Oncor “for facilities extensions, upgrades, or expansions in
    excess of allowable expenditures, or for nonstandard service facilities, removals
    or   relocations.”     Additional   fees    for   “Delivery   System     Facilities
    Relocation/Removal” and a study on that relocation and removal are covered by
    a “Discretionary Service Agreement,” while a Delivery Systems Facility
    Installation is covered by a “Facility Extension Agreement.” Section 6.3 contains
    the form agreements.    Sections 6.3.6, 6.3.7, 6.3.8, 6.3.9, 6.3.10, and 6.3.11
    contain forms entitled “Easement and Right of Way.”
    Under section 5.11.2, “Complaints,” a retail customer “may submit written
    complaints about Delivery Service” to Oncor and may call Oncor to lodge oral
    21
    complaints, and Oncor “shall inform Retail Customer of its right to file a complaint
    with” the PUC and provide the PUC’s contact information to the customer.
    5. Oncor’s Work Request Authorizations
    The parties’ exhibits show the progression of the two line requests made to
    Oncor—one for relocation and the other for installation.
    a. Work Request #2812378
    Work Request #2812378 corresponds to the installation of the single-
    phase line requested by Giovanni Homes. Plaintiff’s Exhibit 73 is the May 2006
    work request authorization by TXU (Oncor’s predecessor) setting out that
    $19,412 was authorized of the $22,233 expenditure for “provid[ing] service to a
    residential subdivision as requested by the developer. It is proposed to install the
    necessary distribution facilities to meet the customer[’]s load requirements as
    shown on this W[ork] R[equest] per Operational memo 2002, revised Oct. 2,
    2002.” The justification of expenditure sets out the formulas to calculate the
    allowable expenditure, associated costs, and CIAC charges to the customer.
    Plaintiff’s Exhibit 77 is a February 22, 2007 CIAC Detail Report for Work Request
    #2812378 stating that “[i]n accordance with TXU ED’s 2002 Line Extension
    Policy and tariffs on record with the Public Utility Commission of Texas, this
    extension may be provided at a total cost of $6236.24 to the Retail Customer,”
    and explaining the CIAC calculations. Plaintiff’s Exhibit 84 is an October 18,
    2007 CIAC Detail Report for Work Request #2812378, stating that
    22
    [i]n accordance with TXU ED’s 2002 Line Extension Policy and tariffs
    on record with the Public Utility Commission of Texas, this extension
    may be provided at no cost to the Retail Customer through the use
    of least cost design, cleared ROW, and standard facilities at a cost
    that does not exceed standard allowances.
    Plaintiff’s Exhibit 83 is a September 14, 2007 email from an Oncor representative
    to Giovanni Homes that states, “Construction to install facilities at Water Chase
    will saw cut area to install transformer and bore parking lot to install conduit to
    the north.” Defendant’s Exhibit 19 is an internal email showing Oncor’s February
    4, 2008 calculations for Work Request #2812378 and the subsequent April 28,
    2008, May 7, 2008, and May 9, 2008 recalculations for Work Request #2812378
    due to design change.
    b. Work Request #2898038
    Work Request #2898038 corresponds to the relocation of the three-phase
    line.
    Plaintiff’s Exhibit 79 is a July 19, 2007 email from one of Oncor’s
    representatives to Giovanni Homes in which the Oncor representative states,
    “The cable that exists on the property in question will be relocated when we
    complete the paperwork necessary to relocate the line as requested. Oncor
    Electric Delivery intends to relocate the primary cable crossing lot 3 Block 1 of
    The Academy At Waterchase.” Plaintiff’s Exhibit 80 is the July 23, 2007 letter
    relied upon by Giovanni Homes in support of its contract claim and set out in our
    factual recitation above.
    23
    Plaintiff’s Exhibit 5 is the January 2008 work request authorization (Work
    Request #2898038) by Oncor stating that $73,843 was authorized along with the
    following justification: “The developer of Academy at Waterchase Subdivision
    has request [sic] a section of underground and a three phase transformer out of
    easement be relocated.       This w[ork] r[equest] will cover the cost to relocate
    underground facilities into a new easement and clear area for development.
    Voucher is for travel yard/time adder.”       The work request authorization listed
    material, labor, and other items that were factored into the authorized
    expenditure.    Plaintiff’s Exhibits 87, 88, and 89 contain lists of the materials
    required for the activity.
    Plaintiff’s Exhibit 283, the easement that Giovanni Homes granted to
    Oncor on September 20, 2007, is in substantially the same format as the
    easement form in the Tariff, as is Plaintiff’s Exhibit 281, the easement that K.
    Hovnanian Homes-DFW, LLC granted to Oncor that same day. Also in the same
    format are Plaintiff’s Exhibit 285, the easement that Links at Waterchase LLC
    granted to Oncor on November 15, 2007; Plaintiff’s Exhibit 284, the easement
    that Jim McLean Enterprises, Inc. granted to Oncor on November 19, 2007; and
    Plaintiff’s Exhibit 282, the easement that Dorcas Benson granted to Oncor on
    December 6, 2007. Plaintiff’s Exhibits 283, 284, and 285 are stamped “Return
    to: Oncor Electric Delivery Company Right of Way Department” and reference
    Work Request #2898038. The K. Hovnanian Homes easement also references
    24
    Work Request #2898038, while the Benson easement references Work Request
    #2812378.
    c. Giovanni Homes’s Conversation with the PUC
    Piras testified that when he found out that the three-phase line ran through
    Giovanni Homes’s property, he called the PUC to find out what his rights were
    and discussed the fact that there was an electric line on his property for over an
    hour. He said that the PUC told him that it could not help him and that he had to
    deal with the matter civilly.14 Piras said that when he spoke to the PUC, he
    asked as a hypothetical, “I have lines on my property, and this company, Oncor,
    won’t take the lines off my property. What can I do?”
    During cross-examination, the following conversation occurred:
    Q. Well, you know the Public Utility Commission is the
    watchdog—the governmental watchdog over the public utilities,
    right?
    A. That’s what I assume, yes.
    Q. Okay. Have—have you ever looked and seen on the Web
    sites or talked to these people about the fact that you can file a
    complaint, the electric company has to answer within 21 days, there
    is an investigation done, and both parties get a result of that
    investigation?
    Did you find that information out?
    A. I was told by them directly, sir, that my only avenue I could
    take is taking it up civilly.
    14
    Piras also said that he did not tell the PUC who he was when he called
    because he wanted to find out what the law was and what it regulated but did not
    want Oncor to find out and cause trouble for his company.
    25
    Q. All right. So—so you made an anonymous call. And—and
    you’re—you’re a developer. You say you have done multiple
    developments, hundreds and hundreds of homes.
    You have dealt with all these situations, right, as far as
    developing property?
    A. I have developed properties, yes.
    Q. And you call the Public Utility Commission because you
    are having all these horrendous problems with Oncor, and you don’t
    leave your name, you don’t make a complaint, you don’t do anything
    except, according to you, make a phone conversation; is that right?
    A. I had a phone conversation to find out what the legalities
    were, and I found out that there is no governing over you, Oncor,
    being able to have utility lines on somebody else’s property. There
    is nothing there.
    Q. So the PUC said there is nothing that governs Oncor
    having lines on the property where they were?
    A. On—on other people’s property out of easement. There is
    no details of this situation anywhere.
    Q. Okay. Nothing governs it, then, is your understanding?
    A. Nothing governs it from my understanding of what I was
    told.
    During the supplemental oral arguments in this case, Oncor’s counsel
    pointed out that Piras would have called the PUC in 2007 or 2008, after
    discovering the three-phase line and encountering delay, but that Giovanni
    Homes did not add its breach-of-contract claim to its lawsuit until 2010. Until
    adding that breach-of-contract claim in 2010, all of Giovanni Homes’s claims
    against Oncor—negligence, conspiracy, and trespass—had sounded in tort. See
    infra n.19.
    26
    C. Analysis
    Although Giovanni Homes argues that the PUC’s exclusive jurisdiction
    does not apply to this case because the Tariff does not address the dispute at
    issue, based on the provisions of the PURA, the PUC’s administrative
    regulations, and the Tariff set out above, we disagree.
    The PURA sets out a comprehensive regulatory scheme, with broad and
    inclusive definitions of “rates” and “services” and a requirement that every rate or
    service provided by an electric utility be furnished and filed in a tariff.       In
    compliance with the PURA, the PUC’s administrative rules set out time limits for
    the kinds of services Giovanni Homes sought from Oncor and a complaint
    process. Oncor’s Tariff is also comprehensive, and Giovanni Homes, a retail
    customer under the Tariff, sought relocation of one electric utility line and
    installation of another, both of which fall under the Tariff’s definitions of
    “Construction Services” and “Service Agreement.”               The work request
    authorizations that correspond to Giovanni Homes’s requested services follow
    the Tariff’s requirements, as do the easements Giovanni Homes claims were
    consideration, which it was required to obtain under the Tariff.
    When claims pertain to “services” and “rates” under the PURA, the PUC
    has exclusive original jurisdiction. Compare CenterPoint Energy Hous., 
    2012 WL 6644982
    , at *2–3, *8 (concluding that regulatory authority had exclusive original
    jurisdiction over dispute concerning overcharges for street light services), Tara
    Partners, Ltd., v. CenterPoint Energy Res. Corp., 
    371 S.W.3d 441
    , 447 (Tex.
    27
    App.—Houston [1st Dist.] 2012, no pet.) (holding plaintiff failed to exhaust
    administrative remedies in its lawsuit against gas company for overbilling), and
    City of 
    Allen, 161 S.W.3d at 197
    , 212 (stating that when a city’s municipal
    ordinance conflicts with Oncor’s tariff, the PURA, or the PUC’s rules, the PUC
    has jurisdiction under the PURA to review and invalidate the ordinance), 15 with
    Jenkins v. Entergy Corp., 
    187 S.W.3d 785
    , 791–92, 800–01 (Tex. App.—Corpus
    Christi 2006, pet. denied) (concluding that the PUC did not have exclusive
    jurisdiction because the retail rate structure was not the object of appellant’s
    pleadings and the suit was inherently judicial because appellant had brought
    state law tort claims based on interstate purchasing and allocation decisions),
    cert. denied, 
    552 U.S. 1224
    (2008).      To hold otherwise would contradict the
    PURA’s standardization and nondiscrimination purposes and the point of having
    a tariff. See Tex. Util. Code Ann. §§ 32.101, 36.004, 38.002, 38.021. Therefore,
    we conclude that the PUC had exclusive jurisdiction over Giovanni Homes’s
    contract claim.
    15
    The supreme court “has implicitly recognized that municipalities
    sometimes contract with third parties by way of ordinance” and when an
    ordinance evidences a contract and is sought to be enforced as one, the court
    has construed it as any other contract. City of Hous. v. Williams, 
    353 S.W.3d 128
    , 136–37 (Tex. 2011). We see no reason why the PUC, which has exclusive
    jurisdiction to review an ordinance that might conflict with the Tariff, the PURA, or
    the PUC’s rules, see City of 
    Allen, 161 S.W.3d at 212
    , should not also have
    exclusive jurisdiction to review a contract that might do so. See City of 
    Hous., 353 S.W.3d at 136
    –37.
    28
    Further, although Giovanni Homes argues that the Tariff does not apply
    because Terry Ariail, Oncor’s corporate representative, testified that the Tariff did
    not apply, we disagree with this interpretation of his testimony, which was less
    than clear. Ariail’s testimony was as follows:
    Q. Okay. Now, let me ask you this: Would you agree with
    me that when Oncor laid the line, the three-phase line, that line was
    laid outside of the easement?
    A. Yes, ma’am.
    Q. All right. And it is against Oncor’s policies and procedures
    to lay a line such as that outside of an easement and never obtain
    an easement from the property owner?
    A. That’s not exactly correct.
    Q. Why is that not correct, Mr. Ariail?
    A. Well, it’s against our policies and procedures not to—well,
    let me back up.
    It is our policy to—to get an easement where we can and—
    and we prefer to have easements covering all of our three-phase
    facilities that are underground. However, not all three-phase
    facilities and not all underground lines get easements, and that’s
    appropriate that they don’t all get easements.
    Q. Let me ask you this: If a three-phase electrical line is built
    outside of an easement and an easement is never obtained, that
    would be against Oncor’s policies, would it not?
    A. Yes, that would—that would not be what—that would not
    be our desire.
    Q. It would be against Oncor’s policies?
    A. Against our policy in particular situations. Again, not in
    every situation, but, yes.
    29
    Q. Now, the tariff that the Public Utility Commission has in the
    State of Texas that Oncor has to abide by, they don’t even discuss
    Oncor’s failure to install electrical lines outside of easements, do
    they?[16]
    A. Not—not—they do not.
    Q. And you have never been directly involved in a situation
    where an electrical line was installed outside of an easement, have
    you?
    A. No, I have not.
    Q. But you do know and you have heard that with Oncor, that
    happens several times a year?
    A. I think when I made that statement, I may have been a little
    glib about how often it happens, but it—it does happen on occasion.
    Q. When you say you made that statement, that’s what you
    said in your deposition?
    A. Right. That’s—that’s correct.
    ....
    Q. All right. And would you agree, Mr. Ariail, that Oncor
    doesn’t have a written policy and procedure as to how they should
    handle a situation where an electrical line is placed outside of an
    easement?
    A. We do not.
    Q. Okay. It makes common sense what Oncor should do
    under those situations, does it not?
    A. Yes, do the right thing.
    16
    We infer from context that the question Giovanni Homes’s counsel meant
    to ask was something along the lines of whether the Tariff discusses Oncor’s
    installing electrical lines outside of easements.
    30
    Q. And the common sense approach and what Oncor has the
    duty to do when they have laid a line outside of an easement and it’s
    brought to their attention is they should handle that situation as
    expeditiously or as quickly as possible, should they not?
    A. As quickly as the conditions will allow.
    Q. Absolutely. So when Oncor is notified by a customer such
    as Vincent Piras or Giovanni Homes, I bought some property and I
    just learned that there is a three-phase wire running smack-dab
    through my property, common sense alone and the duties of Oncor
    would dictate that Oncor has the responsibility to fix that problem as
    ]
    quickly as the circumstances will allow[17 . . . correct?
    A. We’re obligated to find a solution to fix it. It wouldn’t
    necessarily be to move the line. There are several options to do
    that.
    [Emphasis added.]
    While Ariail testified that Oncor did not have a written policy and procedure
    to handle a situation in which an electrical line is placed outside of an easement,
    no one disputes that the property’s previous owner instructed Oncor to place the
    line outside of the platted easement, and, as set out above, section 5.7.8 of the
    Tariff contains specific provisions to address removing and relocating lines. 18
    Although Giovanni Homes argues that this provision “does not address removal
    and relocation of trespassing electrical lines and applies only when the customer
    requests removal or relocation of Oncor’s facilities at the customer’s expense,”
    17
    Oncor’s counsel objected to this question, but the trial court overruled it.
    18
    Ariail also agreed with the following statement: “Oncor is going to do
    what they think they should do to service the customer but also obey your [sic]
    rules and regulations and the tariffs in the State of Texas.”
    31
    here, Giovanni Homes, a retail customer under the Tariff, specifically requested
    the removal and relocation of the three-phase line, actions covered by the Tariff
    regardless of their location or characterization as “trespassers.” Cf. Oncor 
    Elec., 369 S.W.3d at 847
    –48 (recounting PUC approval process to construct a new
    transmission line and landowner participation and negotiations regarding need
    for aerial easement and right-of-way); Oncor Elec. Delivery Co. v. Schunke, No.
    04-13-00067-CV, 
    2013 WL 6672494
    , at *1 (Tex. App.—San Antonio Dec. 18,
    2013, pet. filed) (mem. op.) (reviewing judgment on special commissioners’
    award in condemnation case involving Oncor); Oncor Elec. Delivery Co. v.
    Brockriede, Nos. 02-13-00071-CV, 02-13-00072-CV, 
    2013 WL 6564276
    , at *1
    (Tex. App.—Fort Worth Dec. 12, 2013, no pet.) (mem. op.) (same); Fuqua v.
    Oncor Elec. Delivery Co., 
    315 S.W.3d 552
    , 557–58, 561 (Tex. App.—Eastland
    2010, pet. denied) (affirming in part Oncor’s injunction against property owner for
    violating electrical easement by flying small plane under high voltage power line
    when landing on airstrip).19
    19
    Further, as pointed out by Oncor, the cases Giovanni Homes cites to
    support its argument that the trial court had jurisdiction over its claim—Fuqua
    (cited above), Wooldridge v. TXU Electric Delivery Co., 
    236 S.W.3d 484
    (Tex.
    App.—Dallas 2007, no pet.), Roberts v. TXU Energy Retail Co., 
    171 S.W.3d 901
    (Tex. App.—Beaumont 2005, no pet.), and Oncor Electric Delivery Co. v. Murillo,
    No. 01-10-01123-CV, 
    2014 WL 1056471
    (Tex. App.—Houston [1st Dist.] Mar. 18,
    2014, no pet. h.)(op. on reh’g)—do not involve a “retail customer,” Oncor’s tariff,
    the PUC, the PURA, or a contract claim, much less a contract claim covered by
    Oncor’s Tariff. Wooldridge, Roberts, and Murillo all involved tort claims. Murillo,
    
    2014 WL 1056471
    , at *1; 
    Wooldridge, 236 S.W.3d at 485
    , 488; 
    Roberts, 171 S.W.3d at 903
    ; see Lynn v. Hous. Lighting & Power Co., 
    820 S.W.2d 57
    , 58 (Tex.
    App.—Houston [14th Dist.] 1991, no writ) (stating that when appellant’s claims
    32
    Giovanni Homes also argues that the Tariff does not apply because its
    breach-of-contract claim did not involve a dispute over Oncor’s regulated utility
    rates, pricing, or services; because its claim did not seek to enforce alleged rights
    that contradict the Tariff’s provisions; and because it is not a suit over issues that
    the Tariff’s terms govern. Giovanni Homes states, “Claims that do not arise out
    of the [T]ariff or that are not expressly governed by the [T]ariff or the PURA fall
    outside the PUC’s exclusive jurisdiction.”
    However, as set out above, the alleged agreement between the parties
    here was governed by the Tariff’s express terms, which is governed in turn by the
    PURA and its purpose of protecting the public interest inherent in the rates and
    services of electric utilities. See CenterPoint Energy Hous., 
    2012 WL 6644982
    ,
    at *7 (observing that the tariff had been filed with and approved by the PUC such
    that it was a natural extension of the PUC’s authority for it to decide, as a
    regulatory matter, a dispute arising from the tariff). And contrary to Giovanni
    Homes’s argument that no provision of the PURA or the Tariff addresses an
    award of damages to a customer when Oncor places its line out of an easement,
    a request for such damages cannot operate to vest the trial court with jurisdiction
    when there was none before. See Sw. Bell Tel. 
    Co., 235 S.W.3d at 625
    –26
    (concluding that the PUC had exclusive jurisdiction to hear telephone customers’
    were tort claims for actual and exemplary damages that did not concern rates
    and regulations governed by the PURA, the trial court had jurisdiction to address
    them); see also 
    Grant, 73 S.W.3d at 219
    –22 (reviewing tariff’s reasonableness
    with regard to provision limiting liability for personal injuries).
    33
    rate change dispute because of the specific grant of “exclusive original
    jurisdiction over the business and property of a telecommunications utility” and
    the comprehensive regulatory scheme set out in the utilities code).
    Because we conclude that the PUC has exclusive jurisdiction over the
    breach-of-contract claim, Giovanni Homes had to exhaust its administrative
    remedies before it could sue Oncor in district court on that claim.20
    IV. Conclusion
    Based on our conclusion above, we reverse the trial court’s judgment and
    remand this case to the trial court with instructions to abate the case to allow
    Giovanni Homes a reasonable opportunity to cure the jurisdictional defect, if
    possible. See 
    Fodge, 63 S.W.3d at 805
    .
    /s/ Bob McCoy
    BOB MCCOY
    JUSTICE
    PANEL: WALKER, MCCOY, and GABRIEL, JJ.
    DELIVERED: April 3, 2014
    20
    Having concluded that the PURA and the Tariff apply, we do not reach
    the parties’ filed-rate doctrine arguments. See 
    Grant, 73 S.W.3d at 216
    –17
    (explaining that the filed-rate doctrine is a novel aspect of cases involving utilities
    that precludes claims seeking to enforce contracts that contradict a filed tariff’s
    terms); see also In re Birch Telecom, Inc., No. 05-12237 (PJW), 
    2009 WL 1531792
    , at *2 (Bankr. D. Del. June 2, 2009) (“Extensive case law makes it clear
    that in Texas, as elsewhere, filed tariffs govern utilities’ relationships with their
    customers, and not any contradictory provisions of contracts that may have been
    executed.”).
    34
    

Document Info

Docket Number: 02-11-00237-CV

Citation Numbers: 438 S.W.3d 644, 2014 Tex. App. LEXIS 3596, 2014 WL 1320943

Judges: Walker, McCoy, Gabriel

Filed Date: 4/3/2014

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (17)

Guideone Insurance Co. v. Cupps , 2006 Tex. App. LEXIS 9775 ( 2006 )

Fuqua v. Oncor Electric Delivery Co. , 2010 Tex. App. LEXIS 2323 ( 2010 )

Sharp v. House of Lloyd, Inc. , 815 S.W.2d 245 ( 1991 )

In Re Entergy Corp. , 47 Tex. Sup. Ct. J. 729 ( 2004 )

Double Diamond, Inc. v. Hilco Electric Cooperative, Inc. , 2006 Tex. App. LEXIS 4433 ( 2006 )

Meekey v. RICK'S CABARET INTERN., INC. , 171 S.W.3d 394 ( 2005 )

Hyde v. Ray , 2005 Tex. App. LEXIS 10284 ( 2005 )

Roberts v. TXU Energy Retail Co. LP , 2005 Tex. App. LEXIS 6905 ( 2005 )

Public Utility Commission v. Southwestern Bell Telephone Co. , 960 S.W.2d 116 ( 1997 )

Double Diamond, Inc. v. Hilco Electric Cooperative, Inc. , 2003 Tex. App. LEXIS 10656 ( 2003 )

City of Allen v. Public Utility Commission , 2005 Tex. App. LEXIS 1990 ( 2005 )

Jenkins v. Entergy Corp. , 187 S.W.3d 785 ( 2006 )

Wooldridge v. TXU Electric Delivery Co. , 2007 Tex. App. LEXIS 8390 ( 2007 )

Benish v. Grottie , 2009 Tex. App. LEXIS 1195 ( 2009 )

Nucor Steel-Texas v. Public Utility Commission , 2012 Tex. App. LEXIS 2108 ( 2012 )

Southwestern Electric Power Co. v. Grant , 45 Tex. Sup. Ct. J. 502 ( 2002 )

In Re Southwestern Bell Telephone Co. Lp , 50 Tex. Sup. Ct. J. 1178 ( 2007 )

View All Authorities »