Bond Restoration, Inc. v. Ready Cable, Inc. ( 2015 )


Menu:
  •                                   In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-14-00056-CV
    BOND RESTORATION, INC., APPELLANT
    V.
    READY CABLE, INC., APPELLEE
    On Appeal from the County Court at Law No. 3
    Tarrant County, Texas
    Trial Court No. 2012-005498-3, Honorable Mike Hrabal, Presiding
    April 16, 2015
    OPINION
    Before QUINN, C.J., and CAMPBELL and PIRTLE, JJ.
    Bond Restoration, Inc. (Bond) appeals from a final judgment awarding Ready
    Cable, Inc. (Ready) damages related to the cost of materials purportedly used in a
    public works project. The two issues before us involve whether Ready proved that the
    materials were delivered to or used by Bond and whether the trial court’s award of
    consequential damages comported with Chapter 2253 of the Government Code (that is,
    the McGregor Act). We reverse.
    Background
    In 2012 and 2013, E. P. Reyes & Sons purchased supplies from Ready
    purportedly for use in a street improvement project undertaken by the City of Houston.
    Bond allegedly was the prime contractor for the project. Reyes did not pay for the
    materials.   This resulted in Ready requesting from Bond information regarding the
    payment bond securing payment for the project. Bond did not respond. Thereafter,
    Ready sought similar information from the City of Houston. The latter answered by
    informing Ready that it was “unable to identify the City of Houston project or vendor”
    and to furnish “more information, including the complete City of Houston project
    name and project number.” (Emphasis in original). Ready had no project name or
    number.
    Eventually, the deadline to submit a claim against the bond, if any, lapsed. So,
    Ready sued Reyes for breach of contract and Bond under § 2253.024 of the Texas
    Government Code “for failure to provide bond information as required by” that statute.
    A default judgment was entered against Reyes for the sum due Ready.                 After
    conducting a bench trial, the trial court entered judgment against Bond for consequential
    damages or an amount equal to the unpaid invoices that would have been paid had
    Bond timely provided the requisite bond information.
    The McGregor Act or Texas Government Code § 2253.001 et seq.
    Before addressing the issues before us, we briefly mention the provisions of the
    McGregor Act (the Act) relevant here. The first is § 2253.024. It states:
    (a) A prime contractor, on the written request of a person who provides
    public work labor or material . . . shall provide to the person
    2
    (1) the name and last known address of the governmental
    entity with whom the prime contractor contracted for the
    public work;
    (2) a copy of the payment and performance bonds for the
    public work, including bonds furnished by or to the prime
    contractor; and
    (3) the name of the surety issuing the payment bond and
    the performance bond and the toll-free telephone number
    maintained by the Texas Department of Insurance under
    Subchapter B, Chapter 521, Insurance Code, for obtaining
    information concerning licensed insurance companies.
    TEX. GOV’T CODE ANN. § 2253.024(a)(1), (2), & (3) (West 2008). “Public work material”
    is defined as “material used, or ordered and delivered for use, directly to carry out a
    public work; [or] . . . specially fabricated material; [or] . . . reasonable rental and actual
    running repair costs for construction equipment used, or reasonably required and
    delivered for use, directly to carry out work at the project site; or . . . power, water, fuel,
    and lubricants used, or ordered and delivered for use, directly to carry out a public
    work.” 
    Id. § 2253.001(6).
    In turn, “public work labor" is “labor used directly to carry out
    a public work.” 
    Id. § 2253.001(5).
    Next, the statutory obligation imposed on a prime contractor under the Act to
    secure a payment bond arises when the contract between the prime contractor and
    municipality exceeds $50,000. 
    Id. § 2253.021(a)(2)(B)
    (West Supp. 2014). Per statute,
    the payment bond is “solely for the protection and use of payment bond beneficiaries
    who have a direct contractual relationship with the prime contractor or a subcontractor
    to supply public work labor or material . . . .” 
    Id. § 2253.021(c)(1).
                 Finally, a
    subcontractor is “a person, firm, or corporation that provides public work labor or
    material to fulfill an obligation to a prime contractor or to a subcontractor for the
    3
    performance and installation of any of the work required by a public work contract.” 
    Id. § 2253.001(9).
    Application of § 2253.001 et seq.
    We address Bond’s initial contention. Through it, the company posits that “actual
    proof of delivery at the project site or consumption of the materials in the work is
    required for a material supplier to be entitled to establish a valid bond claim on a public
    works project,” and that “proof of neither exists.” In other words, Bond argues that the
    evidence is legally insufficient to satisfy an element of Ready’s claim, that element being
    the provision of material used or ordered and delivered for use in a public work.
    As explained in Ford Motor Co. v. Castillo, 
    444 S.W.3d 616
    (Tex. 2014), a legal
    insufficiency challenge will be upheld if the record illustrates either 1) a complete
    absence of a vital fact, 2) the court is barred by rules of law or of evidence from giving
    weight to the only evidence offered to prove a vital fact, 3) the evidence offered to prove
    a vital fact is no more than a mere scintilla, or 4) the evidence conclusively establishes
    the opposite of the vital fact. 
    Id. at 620.
    Furthermore, we view the evidence in the light
    most favorable to the verdict and assume that the fact finder made all inferences in
    favor of its decision if reasonable minds could. 
    Id. at 620-21.
    In viewing circumstantial
    evidence favoring the decision, we must “‘view each piece of circumstantial evidence,
    not in isolation, but in light of all the known circumstances,’” 
    id., quoting City
    of Keller v.
    Wilson, 
    168 S.W.3d 802
    (Tex. 2005), and when that evidence “is equally consistent with
    either of two facts, then neither fact may be inferred.” 
    Id. However, if
    not so “equally
    consistent with either of two facts, and the inference drawn by the jury is within the
    ‘zone of reasonable disagreement,’ a reviewing court cannot substitute its judgment for
    4
    that of the trier-of-fact.” 
    Id. at 621,
    quoting City of Keller v. Wilson, 
    168 S.W.3d 802
    (Tex. 2005). With this said, we turn to the record before us.
    Bond cites us to authority holding that the claimant in a public works project must
    show that “the materials furnished were actually used on the job . . . and that same were
    consumed or wholly depreciated in the process of the construction work.” John F.
    Buckner & Sons v. Arkansas Fuel Oil Corp., 
    301 S.W.2d 325
    , 327 (Tex. Civ. App.—
    Waco 1957, no writ); accord Sheldon Pollack Corp v. Pioneer Concrete of Texas. Inc.,
    
    765 S.W.2d 843
    , 846 (Tex. App.—Dallas 1989, writ denied) (noting the same); National
    Surety Corp. v. Dabney, 
    282 S.W.2d 70
    , 74 (Tex. Civ. App.—Waco 1955, no writ)
    (stating the same).    Yet, none of the cases cited deal with § 2253.001 of the
    Government Code.
    Moreover, the plain language of the statute contradicts the notion that the
    materials provided must actually be consumed in the project. As previously mentioned,
    § 2253.001(6) of the statute defines “public work material.” In so defining it, the
    legislature utilized phrases such as “material used” and material “ordered and delivered
    for use,” see TEX. GOV’T CODE ANN. § 2253.001(6)(A) (West 2008), and construction
    equipment “used, or reasonably required and delivered for use . . . .”            See 
    id. § 2253.001(6)(C).
    While the word “used” comports with Bond’s argument, the passage
    “delivered for use” does not. Logically, items “delivered for use” need not be used.
    That is, the phrase “delivered for use” says nothing about actual use in the project, just
    delivery, and the purpose for delivery. And, because we must afford meaning and affect
    to all the verbiage in a statute, Jaster v. Comet II Constr., Inc., 
    438 S.W.3d 556
    , 562
    (Tex. 2014), “delivered for use” simply cannot be construed to mean “used,” as Bond
    5
    would have us conclude. So, Ready was not obligated to prove that the materials sold
    to Reyes were actually used in the public works project. Yet, this does not end our task.
    It appears that Bond also argues that the record “lacks sufficient evidence to
    establish actual proof of delivery at the project site.” It is true that Ready’s sole witness
    admitted that the materials were not delivered to Bond or its construction site. Instead,
    the evidence established that Reyes picked them up at Ready’s facility, and that
    suffices to prove delivery. This is so for several reasons. First, the statute says nothing
    about delivery “at the project site,” and we lack authority to rewrite a statute to include
    matter omitted by the legislature. See Stockton v. Offenbach, 
    336 S.W.3d 610
    , 619
    (Tex. 2011).
    Second, the statute must be accorded a comprehensive and liberal construction
    due to its remedial nature. United Fire & Cas. Co. v. Boring & Tunneling Co. of Am.,
    
    321 S.W.3d 24
    , 28 (Tex. App.—Houston [1st Dist.] 2010, pet. denied); Suretec Ins. Co.
    v. Myrex Indus., 
    232 S.W.3d 811
    , 816 (Tex. App.—Beaumont 2007, pet. denied). To
    read into the ambit of “delivery” the requirement that delivery be made at the project site
    is to avoid the liberal construction we must afford the proviso. That is, requiring delivery
    at the project site would mean that the prime contractor could not personally collect the
    material from the supplier, and that seems to be a rather ridiculous restriction.
    Furthermore, the plain meaning of the word “delivered” connotes an act involving the
    bringing or handing over of something, see Merriam-Webster’s Collegiate Dictionary
    330 (11th ed. 2003), but not who performs that act or the location at which it occurs.
    And, it is quite conceivable that supplies may be (if not often are) brought and handed
    over to the prime contractor by the vendor at the vendor’s place of business. So, we
    6
    reject the notion that the phrase “delivered for use” means that the items must actually
    be delivered to the project site by the entity seeking payment under § 2253.001. And,
    here, the record contains some evidence that the supplies for which Ready sought
    compensation were delivered to Reyes at Ready’s facility and Reyes was a
    subcontractor for Bond on the project.1 Accordingly, we overrule Bond’s first issue
    since some evidence of record illustrates delivery.2
    Remedy
    Bond next contends that the trial court erred in creating a private cause of action
    from § 2253.024(e) of the Government Code. According to the trial court, when a
    primary contractor violates that statute, a cause of action arises in favor of the entity
    supplying public work material, and under that cause, the supplier “is liable for all
    consequential damages for failure to provide the payment bond information.”
    Furthermore, the “[c]onsequential damages [for which Bond was liable] include[d] all
    invoices that . . . [were] not paid for which a payment bond would have been timely
    asserted had Bond Restoration timely provided the information as requested.” We
    sustain the issue.
    1
    The evidence about Reyes being a subcontractor for Bond on the project could be viewed as
    inadmissible hearsay. Yet, no one objected to its admission. Thus, we cannot deny it probative value.
    TEX. R. EVID. 802 (stating that inadmissible hearsay admitted without objection cannot be denied
    probative value merely because it is hearsay).
    2
    Assuming arguendo the existence of an actual public works contract between Bond and the City
    of Houston, we found absolutely no evidence of record that the supposed contract exceeded the $50,000
    threshold required by § 2253.021(a)(2)(B) of the Texas Government Code. So too did that prerequisite
    go unmentioned in the trial court’s findings of fact and conclusions of law. This circumstance would be
    problematic if preserved by Bond; it would have established that the statute upon which Ready based its
    claim did not apply. Nonetheless, Bond failed to encompass the matter within a point of error or issue.
    And, we are prohibited from reversing a judgment on unassigned error. Pat Baker Co. v. Wilson, 
    971 S.W.2d 447
    , 450 (Tex. 1998).
    7
    “When a private cause of action is alleged to derive from a constitutional or
    statutory provision, our duty is to ascertain the drafters' intent.” Brown v. De La Cruz,
    
    156 S.W.3d 560
    , 563 (Tex. 2004). That requires us to look at the plain language of the
    statute. Denton County Elec. Coop., Inc. v. Hackett, 
    368 S.W.3d 765
    , 781 (Tex. App.—
    Fort Worth 2012, pet. denied). And, that language must clearly imply one. See Brown
    v. De La 
    Cruz, 156 S.W.3d at 563
    (stating that in the City of Beaumont v. Bouillion, 
    896 S.W.2d 143
    (Tex. 1995), “we held that the Texas Constitution created a private action
    for damages only if the language of the specific provisions involved clearly implied
    one.”).
    Section 2253.024 of the Government Code creates a statutory duty to provide
    certain information. The duty can run from the prime contractor to one who provided
    public work labor or materials. See, e.g., TEX. GOV’T CODE ANN. § 2253.024(a) (West
    2008) (stating that a prime contractor, “on the written request of a person who provides
    public work labor or material . . . shall provide to the person . . . the name and last
    known address of the governmental entity with whom the prime contractor contracted
    for the public work; . . . a copy of the payment and performance bonds for the public
    work, including bonds furnished by or to the prime contractor; and . . . the name of the
    surety issuing the payment bond and the performance bond and the toll-free telephone
    number maintained by the Texas Department of Insurance . . . for obtaining information
    concerning licensed insurance companies”). Or, it can run from a subcontractor to a
    governmental entity, the prime contractor, a surety, or a person providing work under
    the subcontract.     See 
    id. § 2253.024(b)
    (stating that a subcontractor upon written
    request “shall provide to the person requesting the information . . . the name and last
    8
    known address of each person from whom the subcontractor purchased public work
    labor or material, other than public work material from the subcontractor's inventory; . . .
    the name and last known address of each person to whom the subcontractor provided
    public work labor or material; . . . a statement of whether the subcontractor furnished a
    bond for the benefit of its subcontractors and materialmen; . . . the name and last known
    address of the surety on the bond the subcontractor furnished; and . . . a copy of that
    bond.”).
    So too did the legislature specify the time within which the information must be
    provided. See 
    id. § 2253.024(c)
    (stating that “[i]nformation requested shall be provided
    within a reasonable time but not later than the 10th day after the receipt of the written
    request for the information.”). The legislature also allowed the person from whom the
    information was requested the right to “require payment of the actual cost, not to exceed
    $25, for providing the . . . information . . . if the person does not have a direct
    contractual relationship with the person requesting the information. . . .” 
    Id. Finally, those
    drafting § 2253.024 included within it a penalty for the failure to
    provide the requisite information. That penalty appears in § 2253.024(e) wherein the
    legislature stated that a “person who fails to provide information required by this section
    is liable to the requesting person for that person’s reasonable and necessary costs
    incurred in getting the requested information.” TEX. GOV’T CODE ANN. § 2253.024(e)
    (West 2008).
    From the foregoing provisions, we perceive the creation of a statutory duty
    coupled with liability for its breach. So, it can be said that the legislature intended to
    create a cause of action permitting some measure of relief. Yet, nothing was said in the
    9
    statute about the relief encompassing consequential damages. Rather, it described the
    recovery simply as the reasonable and necessary costs incurred in obtaining the
    desired information. This limitation is of import, as we will illustrate.
    In City of Beaumont v. Bouillion, 
    896 S.W.2d 143
    (Tex. 1995), our Texas
    Supreme Court had the chance to determine whether the Texas Bill of Rights created a
    private right of action for damages. While analyzing the matter, it observed that “the
    text of the . . . Bill of Rights cuts against an implied private right of action for damages
    sought because it explicitly announced the consequences of unconstitutional laws.” 
    Id. at 148.
    The consequence alluded to was the avoidance of the law; that is, laws enacted
    in violation of the Bill of Rights are void. 
    Id. at 148-49.
    And, voiding the law “is different
    from seeking compensation for damages, or compensation in money for a loss or
    injury.”     
    Id. at 149.
    It further rejected the notion that a private cause of action for
    damages must be contemplated within the Bill of Rights because Article 1, § 17 of the
    Texas Constitution encompassed the payment of adequate compensation for property
    taken, damaged, destroyed or applied to public use by the government. Though the
    text of the law entitled one who suffered such a taking to relief, it “provide[d] a textual
    entitlement to compensation in its limited context,” and “this language . . . [could not] be
    interpreted beyond its context.” 
    Id. at 149.
    From this discussion by our Supreme Court,
    we learn that because the Bill of Rights provided for a remedy, one could not imply that
    the individuals drafting those laws also intended to create another remedy in the form of
    a private cause of action for damages. And, that analysis and conclusion controls here.
    Like the Bill of Rights and Article 1, § 17 of the Texas Constitution, § 2253.024(e)
    specified a particular remedy for the breach of duty created by the statute.                As
    10
    previously mentioned, that remedy was and is limited to the recovery of reasonable and
    necessary costs incurred in obtaining the desired information. The legislature having
    created a remedy for the failure of a prime contractor to provide the requisite
    information, it did not intend to also create within § 2253.024 a private cause of action
    for consequential damages caused by the breach.
    This is not to say that those in the position of Ready lack alternative means of
    securing payment for outstanding debt. It is clear that the McGregor Act is not the
    exclusive means of redress available to one who provided public work labor or material
    for a public works project. Dealers Elec. Supply Co. v. Scroggins Const., Co., Inc., 
    292 S.W.3d 650
    , 655 (Tex. 2009) (stating that the “history of the McGregor Act, as well as
    the case long cited for the Act's exclusivity -- South Texas Lumber, 
    29 S.W.2d 1009
    --
    clarify that the McGregor Act was intended to be a public-work laborer or materialman's
    exclusive claim only as against the payment bond itself, but not necessarily against
    contractors on a public-work project.”).3 Yet, it is the exclusive means of recovery
    provided for claims asserted against the bond, 
    id., and §
    2253.024 encompasses the
    manner by which a public work laborer or materialman can obtain information to assert
    a claim against the bond.            We choose not to adopt Ready’s position and mutate
    procedures created to impose liability upon a bond into procedures to impose personal
    liability upon a prime contractor for consequential damages when the legislature has
    eschewed that mutation. In sum, the trial court erred in implying a private cause of
    3
    See, e.g., Corpus Christi v. Acme Mechanical Contractors, Inc., 
    736 S.W.2d 894
    , 898 (Tex.
    App.—Corpus Christi 1987, writ denied) (involving recovery via quantum meruit and noting that “[a]s a
    general rule, in the absence of an express contract making the owner liable, the compensation of persons
    who perform labor for or furnish material to a prime contractor is to be paid by the prime contractor. . . .”).
    11
    action for damages under § 2253.024(e) and awarding Ready damages against Bond
    via that cause of action.
    Having sustained Bond’s last issue, we reverse the judgment of the trial court.
    Because Ready sought recovery solely for consequential damages under the purported
    private cause of action, we render judgment denying Ready Cable, Inc. recovery
    against Bond Restoration, Inc.
    Brian Quinn
    Chief Justice
    12