Ricardo G. Cedillo, Jason C. Zehner, J. Russell Davis and Davis, Cedillo & Mendoza, Inc. v. Immobiliere Jeuness Establishment , 2015 Tex. App. LEXIS 9017 ( 2015 )


Menu:
  • Reversed and Remanded and Opinion filed August 27, 2015.
    In The
    Fourteenth Court of Appeals
    NO. 14-15-00101-CV
    RICARDO G. CEDILLO, JASON C. ZEHNER, J. RUSSELL DAVIS AND
    DAVIS, CEDILLO & MENDOZA, INC., Appellants
    V.
    IMMOBILIERE JEUNESS ESTABLISSEMENT, Appellee
    On Appeal from the 215th District Court
    Harris County, Texas
    Trial Court Cause No. 2012-45412
    OPINION
    In this legal malpractice case, a company asserts claims derivatively against
    the lawyers and law firm that represented two partnerships in which the company
    was a partner. The lawyers and law firm represented the partnerships pursuant to a
    written representation agreement, which contained a broad arbitration clause.
    After the company filed suit, the lawyers and law firm sought to compel arbitration
    under the arbitration clause.    The trial court denied the motion to compel
    arbitration. In this interlocutory appeal, the lawyers and law firm assert in a single
    issue that the trial court erred in denying their motion to compel. We reverse and
    remand.
    I. BACKGROUND
    Appellants J. Russell Davis, Ricardo G. Cedillo, Jason C. Zehner,1 and
    Davis, Cedillo & Mendoza, Inc. (collectively, DCM) are attorneys and a San
    Antonio-based law firm. Appellee Immobiliere Jeuness Establissement (IJE) is a
    Lichtenstein entity and a limited partner of 29 Kuykendahl Road, Ltd. (29
    Kuykendahl), which in turn is a limited partner of 9.2 Louetta Road, Ltd. (9.2
    Louetta). 29 Kuykendahl and 9.2 Louetta (collectively, the Original Partnerships)
    are Texas limited partnerships. From March 24, 2009 to June 6, 2011, DCM
    represented the Original Partnerships in litigation initiated by IJE in a Harris
    County district court involving a series of transactions relating to the development
    of an affordable housing complex called “Villages at Louetta,” constructed on land
    previously owned by the Original Partnerships (the Louetta litigation).         DCM
    represented the Original Partnerships in the Louetta litigation under a Legal
    Representation Agreement (the representation agreement) dated March 24, 2009.
    The representation agreement contains the following arbitration clause:
    Arbitration: Any disputes arising out of the relationship between
    Firm [DCM] and Client [the Original Partnerships] shall be submitted
    to binding arbitration, and both Firm and Client agree to be bound by
    the results of arbitration. The arbitration shall be governed by the
    Commercial Arbitration Rules of the American Arbitration
    Association. San Antonio, Bexar County, Texas shall be the
    exclusive venue, and any disputes submitted to arbitration shall be
    governed by the laws of the State of Texas.
    1
    Zehner is a former associate and shareholder of the firm.
    2
    Pursuant to the representation agreement, DCM also represented several
    other defendants in the Louetta litigation: Radnor Joint Venture, Inc. (Radnor), the
    general partner of the Original Partnerships; Villages at Louetta Apartments, Ltd.
    (VLA), the partnership to which the Original Partnerships transferred the land for
    the Villages at Louetta development; Louetta Villages, LLC (LV LLC), the general
    partner of VLA; and Michael Beucler. Beucler is the president of Radnor.
    IJE initially sought an order compelling the Original Partnerships to produce
    records concerning the Villages at Louetta transation in the Louetta litigation. But
    it amended its petition to assert claims for breach of contract and breach of
    fiduciary duty against Radnor and Michael Beucler regarding loan transactions
    totaling $1.4 million that allegedly benefited Beucler to the detriment of the
    Original Partnerships. In its third amended petition, IJE alleged additional facts
    and asserted derivative claims on behalf of the Original Partnerships against
    Radnor and Beucler, creating a potential conflict of interest between DCM’s
    clients. On June 6, 2011, the trial court in the Louetta litigation granted DCM’s
    motion to withdraw based on non-payment of fees and the potential conflict of
    interest arising out of IJE’s assertion of derivative claims on behalf of the Original
    Partnerships.
    After DCM withdrew, on May 30, 2013, the trial court in the Louetta
    litigation entered an order requested by IJE, granting IJE the right to wind-up the
    affairs of the Original Partnerships and authorizing it to maintain derivative actions
    on their behalf for “any existing claims the Partnerships may have against third
    parties.” IJE and the Original Partnerships then entered into an agreed judgment
    with Beucler and Radnor in the Louetta litigation in which there was no finding
    that Beucler or Radnor committed fraud.
    3
    Meanwhile, IJE filed this legal malpractice suit on August 8, 2012, against
    DCM on behalf of the Original Partnerships. In IJE’s live pleading, IJE alleges
    that DCM, through its legal work on the Villages at Louetta transaction and
    representation of the Original Partnerships in the Louetta litigation, assisted
    Beucler in concealing Radnor’s improper use of loan proceeds. Specifically, IJE
    alleges that DCM represented Beucler and the Original Partnerships through June
    6, 2011 (the date DCM’s motion to withdraw from the Louetta litigation was
    granted). IJE further claims that, during this time, DCM was simultaneously
    representing the interests of the Original Partnerships, Beucler, and other entities
    involved in the Louetta Village transaction. According to IJE’s pleading, Beucler
    and DCM placed their interests above those of the Original Partnerships, which
    adversely affected the partnerships.
    Following the lifting of a seventeen-month abatement on August 15, 2014,
    DCM began producing documents in response to IJE’s discovery requests. DCM
    provided the representation agreement containing the arbitration clause to its
    attorneys on October 1; DCM’s attorneys reviewed the document for production to
    IJE and discovered the arbitration clause. On December 5, 2014, DCM filed a
    motion to compel arbitration and stay litigation pursuant to the Federal Arbitration
    Act (FAA) or, alternatively, under the Texas General Arbitration Act (TGAA).
    Shortly before the hearing on the motion to compel, IJE filed an opposition brief
    asserting numerous grounds for denying the motion: (1) there was insufficient
    evidence that the Original Partnerships agreed to the representation agreement; (2)
    IJE’s claims fall outside the scope of the agreement; (3) even if the Original
    Partnerships would have been required to arbitrate their claims against DCM, IJE
    could not be compelled to arbitrate derivative claims on the Original Partnerships’
    behalf because IJE was not a party to the representation agreement; (4) the
    4
    arbitration provision in the representation agreement is unconscionable; and (5)
    DCM waived its right to arbitration.
    The trial court denied DCM’s motion to compel arbitration on January 15,
    2015. In early February, the court issued an amended order clarifying that it was
    denying the motion on the ground that “IJE was not a party to the Representation
    Agreement and therefore cannot be compelled to arbitrate the derivative claims
    asserted on behalf of 29 Kuykendahl Road, Ltd. and 9.2 Louetta Road, Ltd.” DCM
    timely noticed its appeal of the order and amended order denying its motion to
    compel arbitration. See Tex. Civ. Prac. & Rem. Code Ann. § 51.016 (authorizing
    interlocutory appeal of denial of motion to compel arbitration under the FAA);
    
    id. § 171.098(a)(1)
    (permitting interlocutory appeal of denial of motion to compel
    arbitration under the TGAA).
    II. ANALYSIS
    In a single issue, DCM asserts that the trial court erred in denying its motion
    to compel arbitration.2 First, we evaluate the validity of the arbitration agreement.
    Once we determine that DCM established that a valid arbitration agreement exists,
    we ascertain whether IJE is bound to that arbitration agreement and whether IJE’s
    claims fall within the scope of the arbitration agreement. After examining IJE’s
    factual allegations in its petition, we determine that IJE is bound to the arbitration
    agreement and further determine that we cannot say with positive assurance that
    the arbitration clause is not susceptible to an interpretation which would cover this
    dispute. Finally, we turn to the remaining arguments presented by IJE in its
    2
    The parties agree that, although the trial court clarified that the basis for its denial of the
    motion to compel arbitration was that IJE was not a signatory to the agreement, we should
    consider the alternate grounds raised by IJE in resisting the motion to compel. As a matter of
    judicial economy, we have done so in this opinion.
    5
    response to the motion to compel arbitration and conclude that none of them
    provide a legal basis for the trial court’s denial of DCM’s motion.
    A.     Standard of Review3
    We review de novo whether an arbitration agreement is enforceable. Rachal
    v. Reitz, 
    403 S.W.3d 840
    , 843 (Tex. 2013) (citing In re Labatt Food Serv., L.P.,
    
    279 S.W.3d 640
    , 643 (Tex. 2009) (orig. proceeding)). When reviewing the denial
    of a motion to compel arbitration, we defer to the trial court’s factual
    determinations that are supported by evidence but review the trial court’s legal
    determinations de novo. 
    Id. The issues
    raised in this appeal all involve the
    enforceability of the arbitration agreement; thus we review them de novo.
    B.     Validity of Arbitration Agreement
    A party seeking to compel arbitration must first establish that a valid
    arbitration agreement exists. In re Rubiola, 
    334 S.W.3d 220
    , 223 (Tex. 2011)
    (orig. proceeding). If the relevant parties did not sign the contract in which the
    arbitration agreement is found, addressing the first prong includes analysis of
    whether a non-signatory is bound by or can enforce the arbitration agreement. See
    
    id. at 223–24;
    see also PAK Foods Houston, LLC v. Garcia, 
    433 S.W.3d 171
    , 178
    (Tex. App.—Houston [14th Dist.] 2014, pet. dism’d) (holding that even if claims
    3
    When an arbitration agreement is silent about whether the FAA or the TGAA applies
    and neither party asserts the FAA applies or preempts the TGAA, we need not address whether
    the FAA applies. See Branch Law Firm, L.L .P. v. Osborn, 
    447 S.W.3d 390
    , 394 n.10 (Tex.
    App.—Houston [14th Dist.] 2014, no pet.); Osornia v. AmeriMex Motor & Controls, Inc., 
    367 S.W.3d 707
    , 711 (Tex. App.—Houston [14th Dist.] 2012, no pet.). The FAA and TGAA address
    the same underlying substantive principles. Forest Oil Corp. v. McAllen, 
    268 S.W.3d 51
    , 56
    n.10 (Tex. 2008) (noting the similarities of the acts and relying interchangeably on cases
    discussing the FAA and TGAA). Because the substantive principles applicable to our analysis
    are the same under either act, we cite cases decided under the FAA and TGAA interchangeably.
    See id.; Branch Law Firm, 
    L.L.P., 447 S.W.3d at 394
    n.10.
    6
    were derivative, because there is no valid agreement to arbitrate, Labatt is
    inapplicable).
    Arbitration cannot be ordered in the absence of an agreement to arbitrate.
    Freis v. Canales, 
    877 S.W.2d 283
    , 284 (Tex. 1994). Arbitration is favored under
    public policy, but it also is a creature of contract. In re Poly–Am., L.P., 
    262 S.W.3d 337
    , 348 (Tex. 2008) (orig. proceeding). We do not resolve doubts or
    indulge a presumption in favor of arbitration in deciding whether the parties have
    agreed to arbitrate. See In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 732
    , 737
    (Tex. 2005) (orig. proceeding). Instead, through the neutral application of state
    contract law, we decide whether an enforceable agreement exists in the first
    instance and whether generally applicable contract defenses may be applied to
    invalidate the arbitration agreement. See In re Poly–Am., 
    L.P., 262 S.W.3d at 348
    .
    Under Texas law, the trial court conducts a summary proceeding to
    determine the applicability of an arbitration clause. In re Weekley Homes, L.P.,
    
    180 S.W.3d 127
    , 130 (Tex. 2005) (orig. proceeding).           A motion to compel
    arbitration is similar to a motion for partial summary judgment and is subject to the
    same evidentiary standards. In re Jebbia, 
    26 S.W.3d 753
    , 756–57 (Tex. App.—
    Houston [14th Dist.] 2000, orig. proceeding). The party alleging an arbitration
    agreement must present summary proof that an agreement to arbitrate requires
    arbitration of the dispute. Jack B. Anglin Co. v. Tipps, 
    842 S.W.2d 266
    , 269 (Tex.
    1992) (orig. proceeding); 
    Jebbia, 26 S.W.3d at 757
    .
    Here, the arbitration clause relied on by DCM is contained in the
    representation agreement between DCM and the Original Partnerships. Although
    DCM signed the representation agreement, the representative of the Original
    7
    Partnerships, David Beucler, did not sign the agreement.4 “But neither the FAA
    nor Texas law requires that arbitration clauses be signed, so long as they are
    written and agreed to by the parties.” In re AdvancePCS Health L.P., 
    172 S.W.3d 603
    , 606 (Tex. 2005) (orig. proceeding) (per curiam). Further, if one party signs a
    contract, the other party’s acceptance may be demonstrated by its conduct. Smart
    Call, LLC v. Genio Mobile, Inc., 14-13-00223-CV, 
    2014 WL 3955083
    , at *5 (Tex.
    App.—Houston [14th Dist.] Aug. 14, 2014, pet. denied) (citing Hearthshire
    Braeswood Plaza Ltd. P’ship v. Bill Kelly Co., 
    849 S.W.2d 380
    , 392 (Tex. App.—
    Houston [14th Dist.] 1993, writ denied)).
    DCM alleged in its motion to compel arbitration that (1) it had executed and
    performed under the representation agreement in reliance on its terms and (2) an
    email from Beucler’s son, Reid Beucler, established the Original Partnership’s
    agreement to the arbitration clause contained in the representation agreement.
    DCM attached a declaration from J. Russell Davis,5 which incorporated numerous
    attachments and supported the motion. The email from Reid Beucler was attached
    to Davis’s declaration. IJE objected to this email as hearsay and additionally made
    numerous hearsay objections to Davis’s declaration, as well as objections to
    specific statements that it asserted were conclusory or lacked foundation.
    However, IJE failed to obtain a ruling on any of its objections. Thus, IJE’s hearsay
    objections were not preserved. See Tex. R. App. P. 33.1(a); cf. Hou-Tex, Inc. v.
    Landmark Graphics, 
    26 S.W.3d 103
    , 112 (Tex. App.—Houston [14th Dist.] 2000,
    no pet.).
    4
    IJE attached numerous engagement letters between various entities represented by
    Beucler and DCM to its response. These letters range in date from January 21, 1997 to March
    25, 2009. Many of these engagement letters are not signed by Beucler. And none of these
    letters reference the Original Partnerships.
    5
    See Tex. Civ. Prac. & Rem. Code Ann. § 132.001(a), (c).
    8
    In his declaration, Davis stated:
    In my dealings with Michael Beucler, Reid Beucler often acted as a
    representative for Michael and his affiliate companies. Based on prior
    experience, I expected that Reid Beucler was authorized to act as
    Michael Beucler and his companies’ representative with respect to
    DCM’s representation of the Defendants in the Original Dispute. On
    or about March 24, 2009, I gave Michael and Reid Beucler a copy of
    the Representation Agreement signed on behalf of DCM by Mr.
    Cedillo. I later received an email from Reid Beucler agreeing to the
    Representation Agreement.
    Even if we disregard the portion of this excerpt, underlined above, that IJE asserted
    was conclusory, Davis’s declaration supports DCM’s contention that the Original
    Partnerships agreed to the representation agreement. Specifically, Davis stated that
    Reid Buecler acted as a representative for Michael Buecler’s companies and that
    he received an email from Reid agreeing to the representation agreement. In an
    email from Reid also attached to the motion, Reid stated that “the engagement and
    memo look fine.” He requested that DCM provide these documents electronically
    so that he could forward them to the Louetta entities’ representative, John White,
    “for signature and review.” The representation agreement contained in our record
    is signed by John White.
    Moreover, it is undisputed that the Original Partnerships were represented by
    DCM during the Louetta litigation until the date that DCM withdrew.              An
    unobjected-to copy of the letter from DCM notifying David Beucler of its
    withdrawal was attached to DCM’s motion to compel. In this May 25, 2011 letter,
    DCM reminded Beucler that it represented Beucler, 9.2 Louetta, 29 Kuykendahl,
    Radnor, VLA, Louetta Villages, and Beucler in the Louetta litigation.          DCM
    explained:
    From the outset, we advised the Clients that our representation is
    contingent on our ability to exercise independent professional
    9
    judgment on behalf of each client. If we find there are conflicting
    interests between any of the Clients, such that we cannot impartially
    represent each client, then it is our duty to withdraw from representing
    all of the Clients.
    The allegations plead in this litigation, if proved, create a
    conflict of interest between certain Clients and/or the various
    Principals. As a result this firm is compelled to withdrawal [sic] as
    counsel of record to the Clients.
    The letter provides that a motion to withdraw was being filed on the same date as
    the letter. And it is undisputed that DCM withdrew from representing the Original
    Partnerships in June 2011.
    Under these circumstances, the fact that the representation agreement
    containing the arbitration provision is unsigned by the Original Partnerships does
    not indicate that the Original Partnerships did not intend to be bound by it. To the
    contrary, the uncontroverted evidence establishes that the partnerships did, in fact,
    accept the representation agreement by their conduct: they accepted DCM as their
    counsel in the Louetta litigation until DCM withdrew due, in part, to a potential
    conflict. See Hearthshire Braeswood Plaza Ltd. 
    P’ship, 849 S.W.2d at 392
    . And
    by accepting the representation agreement, they also accepted the arbitration clause
    contained therein. See Greenberg Traurig, LLP v. Nat’l Am. Ins. Co., 
    448 S.W.3d 115
    , 121–22 (Tex. App.—Houston [14th Dist.] 2014, no pet.). We, therefore,
    conclude that a valid arbitration agreement exists between the Original
    Partnerships and DCM.
    C.    IJE is bound by the Arbitration Agreement
    As discussed above, there is no dispute that IJE is suing derivatively on
    behalf of the Original Partnerships.       Generally, a plaintiff bringing claims
    derivatively “steps into the shoes” of the party on behalf of whom the derivative
    plaintiff sues and is bound by any agreements to which that party has agreed. See,
    10
    e.g., In re Labatt Food Serv., 
    L.P., 279 S.W.3d at 644
    –46 (determining that
    wrongful death beneficiaries are placed in the exact “legal shoes” as the decedent
    and thus are bound by any arbitration agreement entered into by the decedent);
    Richardson v. Newman, 
    439 S.W.3d 538
    , 542 (Tex. App.—Houston [1st Dist.]
    2014, no pet.) (explaining that shareholder who brings a derivative suit “steps into
    the shoes of the corporation and asserts the corporation’s claims for damages
    against the directors”); Ross v. Union Carbide Corp., 
    296 S.W.3d 206
    , 217 (Tex.
    App.—Houston [14th Dist.] 2009, pet. denied) (“Because of the derivative nature
    of their claims, wrongful-death beneficiaries are generally bound by the injured
    family member’s contract releasing the alleged tortfeasor from liability.”).
    IJE urges that the mere fact that it is suing derivatively and “steps into the
    shoes” of the Original Partnerships, standing alone, is irrelevant. Instead, IJE
    urges that the only question presented is whether liability “arises from or relates to
    the contract containing the arbitration provision.” We conclude that IJE is bound
    to the provision because (a) it is bringing derivative claims for the Original
    Partnerships and (b) we cannot say with “positive assurance” that those claims are
    beyond the scope of the arbitration clause.
    1. IJE steps into the shoes of the Original Partnerships
    First, we note that the general principle discussed in In re Labatt Food
    Service—derivative plaintiffs “step into the shoes” and are bound by contracts
    entered into by the party on whose behalf they are suing—is a principle that has
    been applied to arbitration agreements. Specifically, courts, including this court,
    have held that derivative plaintiffs are bound by the arbitration agreements entered
    into by the party for whom they are suing. See, e.g., In re Labatt Food Serv., 
    L.P., 279 S.W.3d at 644
    –46 (wrongful death beneficiaries bound by arbitration
    agreement entered into by decedent); Zaporozhets v. Ct. Appointed Receiver in
    11
    Cause No. 12-DCV-199496, No. 14-14-00143-CV, 
    2014 WL 5148151
    , at *1, 9
    (Tex. App.—Houston [14th Dist.] Oct. 14, 2014, no pet.) (receiver asserting claims
    derivatively on behalf of companies against companies’ former accountant
    required to arbitrate those derivative claims falling within the scope of arbitration
    agreement between companies and accountant); Stanford Dev. Corp. v. Stanford
    Condo. Owners Ass’n, 
    285 S.W.3d 45
    , 49–50 (Tex. App.—Houston [1st Dist.]
    2009, no pet.) (“[I]n this case, the individual owners bound themselves to arbitrate
    their claims with Stanford. Thus, the Association, when suing on the owners’
    behalf, is also bound to arbitrate. . . .”).
    We see no reason to depart from the well-established principle that a
    plaintiff suing derivatively on behalf of another party is bound to any relevant
    agreements to which that party agreed, including a valid arbitration agreement.
    Thus, to the extent the trial court denied the motion to compel arbitration solely
    because IJE was not a party to the arbitration agreement, the trial court erred.6
    2. IJE’s derivative claims fall within the scope of the arbitration provision
    Once an arbitration agreement is found to exist, we resolve doubts regarding
    an agreement’s scope in favor of arbitration because of the strong presumption
    favoring agreements to arbitrate. In re Kellogg Brown & 
    Root, 166 S.W.3d at 737
    .
    This policy favoring arbitration is so compelling that a court should not deny
    arbitration “unless it can be said with positive assurance that an arbitration clause
    is not susceptible of an interpretation which would cover the dispute at issue.”
    Prudential Secs. Inc. v. Marshall, 
    909 S.W.2d 896
    , 899 (Tex. 1995) (orig.
    proceeding) (per curiam) (internal quotation marks and emphasis omitted). The
    6
    In its brief, IJE appears to concede the trial court erred in denying the motion to compel
    arbitration solely on this basis: “To the extent the trial court denied arbitration based solely on
    the single ground that IJE was not a party to the Representation Agreement, doing so was error.”
    12
    burden is on parties opposing arbitration to show their claims fall outside the scope
    of the arbitration agreement. 
    Id. at 899–900;
    see also Osornia v. AmeriMex Motor
    & Controls, Inc., 
    367 S.W.3d 707
    , 712 (Tex. App.—Houston [14th Dist.] 2012, no
    pet.) (where an arbitration clause is broad, burden is on party opposing arbitration
    to show that its claims fall outside scope of clause). If the scope of an arbitration
    clause is fairly debatable or reasonably in doubt, it will be construed in favor of
    arbitration. FD Frontier Drilling (Cyprus), Ltd. v. Didmon, 438 SW.3d 688, 694
    (Tex. App.—Houston 1st Dist.] 2014, pet. denied). In determining whether a
    claim falls within the scope of an arbitration agreement, we focus on the factual
    allegations of the complaint rather than the legal causes of action asserted. See
    Prudential Secs. 
    Inc., 909 S.W.2d at 900
    .
    “The presumption of arbitrability is particularly applicable when the clause
    is broad; that is it provides for arbitration of ‘any dispute arising between the
    parties,’ or ‘any controversy or claim arising out of or relating to the contract
    thereof,’ or ‘any controversy concerning the interpretation, performance, or
    application of the contract.’” Baty v. Bowen, Miclette & Britt, Inc., 
    423 S.W.3d 427
    , 440 (Tex. App.—Houston [14th Dist.] 2013, pet. denied).              Here, the
    arbitration agreement is broad in scope: it covers “any dispute arising out of the
    relationship” between DCM and, as is relevant here, the Original Partnerships.
    The term “relationship” is not defined by the representation agreement; however,
    the term “representation” is defined to include only the legal representation of the
    client’s interests in the Louetta litigation.   The parties used the broader term
    “relationship” in the arbitration provision, rather than the defined term
    “representation.” Thus, the presumption of arbitrability is particularly applicable
    in this case. See 
    id. 13 IJE
    asserts that because the underlying facts of this lawsuit all arose before
    the representation agreement was entered into by the Original Partnerships, the
    arbitration agreement does not apply to this litigation. But in its live pleading, IJE
    alleged the following facts:
     [S]ometime between December of 2001 and March 2002 Beucler
    closed on two separate loans respectively in the amount of a
    $1,000,000.00 and $400,000.00 (collectively the “$1.4 Million
    Loan). Both of these loans were personal to Beucler and the
    proceeds were all used for non-partnership purposes.
     Beucler, with the knowledge and assistance of his attorneys . . .
    helped collaborate [sic] a scheme whereby the Original
    Partnerships lost at least $1.4 Million in partnership assets.
    Specifically, Beucler with the help of his attorneys . . .
    collateralized partnership tracts of land that were at one time free
    and clear of any liens so that Beucler could be approved for the
    $1.4 Million Loan and/or the refinance of that loan. . . . The loan
    proceeds were then used for a non-partnership purpose: namely, to
    enhance the balance sheet of an unrelated company, FAS
    Construction Management Coimpany, Inc. (“FAS”), which was
    owned by Beucler. FAS was in the business of providing
    construction risk management for banks, developers, and
    contractors and was in dire financial straits and in need of a quick
    capital infusion. To accomplish this goal, Beucler . . . put up the
    Tracts of partnership land as collateral for the $1.4 Milllion Loan
    in partnership proceeds which in turn went directly . . . to FAS’[s]
    operating account. The loan was never taken out in the name of
    the Original Partnerships, the proceeds of the loan never went to
    any Partnership account nor served any partnership purpose. . . .
     When the maturity date on the [$1.4 Million Loan] was
    approaching, Beucler managed, with the assistance and guidance
    of his attorneys, to have the Loan refinanced. . . The aim of the
    [refinancing] was simply to bridge the payment of the loan to
    receiving project financing for the development of the Tracts into
    an Affordable-Housing/multi-family project known as Villages at
    Louetta Apartments (the “Project”). Before the maturity date of
    14
    the . . . loan, Beucler and his lawyers were able to secure Project
    financing . . . around February 13, 2004.
     Part of the proceeds from the Project financing . . . went to pay off
    the $1.4 Million Loan. None of that money was repaid by . . .
    Beucler but came out of Partnership Funds. . . . Beucler and his
    attorneys then used the elaborate refinancing scheme as a means of
    masking the real purpose on how the proceeds of the $1.4 Million
    Loan were actually used. Instead of complying with their fiduciary
    duties, the lawyers helped Beucler hide the truth by concocting a
    partnership purpose for the use of the loan proceeds which they all
    knew to be untrue.
     Specifically, IJE was told by J. Russell Davis (“Davis”) of [DCM]
    that the loan proceeds were used “In order to fund [the]
    development process, of 29 Kuykendahl and 9.2 Louetta” which
    money “went to FAS to apply as development costs to develop a
    viable/finance-able model for Affordable Housing development”.
    Further Davis went on to state that “FAS did formulate such
    model which resulted in the development of the 12 Acre Tract
    and the 6.7 Acre properties for Affordable Housing”. As result
    “FAS received a fee for assistance in the development of the
    project, out of the construction financing of $1.4 Million, which
    was applied to fully extinguish the Loan.”
     The lawyers representing Beucler and the Original Partnerships in
    this transaction through June 6, 2011 were [attorneys at DCM].
    During this time and on information and belief, the lawyers were
    simultaneously representing the interest of the Original
    Partnerships as well as Beucler and other entities involved on the
    [affordable housing] project. In the transactions, the lawyers
    would review the partnership agreements and other transaction
    documents and advise Beucler individually and as GP to the
    Original Partnerships on numerous matters including whether or
    not he had authority to close the $1.4 million loan or go through
    with other various transactions related to the housing project and
    whether the interests of the Original Partnerships were protected.
    (emphasis in original).
    15
    Focusing on these factual allegations and construing the arbitration
    agreement broadly, at least some portion of IJE’s allegations fall within the scope
    of the arbitration clause. Indeed, many of these facts are not associated with any
    date at all, and IJE did not identify when the Louetta project was started or
    completed.    Further, IJE acknowledges that DCM represented the Original
    Partnerships until June 6, 2011 and alleges that “during this time,” DCM was
    simultaneously representing the interest of the Original Partnerships and other
    entities. At least some of this time was after the Original Partnerships entered into
    the representation agreement containing the arbitration provision. Further, there is
    no doubt that the claims made by IJE arise from the “relationship” between the
    Original Partnerships and DCM; as explained above, the arbitration provision at
    issue in this case focuses on the “relationship” between the parties rather than the
    “representation” of the Original Partnerships by DCM. In other words, it cannot be
    said with positive assurance that the arbitration clause here is not susceptible of an
    interpretation that would cover the dispute at issue. Prudential Secs. 
    Inc, 909 S.W.2d at 899
    .
    Nonetheless, IJE asserts that this issue has already been determined in its
    favor by our sister court in Bristow v. Jameson, No. 01-96-00113-CV, 
    1996 WL 277138
    , at *1 (Tex. App.—Houston [1st Dist.] May 22, 1996, no pet.) (not
    designated for publication). First, this opinion lacks precedential value because it
    was not designated for publication. See Tex. R. App. P. 47.7(b) (“Opinions and
    memorandum opinions designated “do not publish” under these rules by the courts
    of appeals prior to January 1, 2003 have no precedential value but may be cited
    with the notation, ‘(not designated for publication).’”). Moreover, this case is
    readily distinguishable from the present circumstances. In Bristow, the parties had
    a prior representation contract that did not contain an arbitration provision.
    16
    Bristow, 
    1996 WL 277138
    , at *1. During the course of the suit in Bristow, the
    parties entered into a second representation contract, which did contain an
    arbitration provision. 
    Id. at *1–2.
    The arbitration provision in the second contract
    stated, “Any disputes relating to this Contract or arising in connection with
    Attorney’s representation of Client will be subject to binding arbitration . . . .” 
    Id. at *5.
          The First Court of Appeals concluded that the trial court correctly
    determined that the arbitration provision in the second contract applied only to
    matters relating to that contract, not to matters relating to the first contract. 
    Id. Here, as
    noted above, IJE provided no evidence that the Original Partnerships had
    any prior representation agreement with DCM.7 Thus, the rationale in Bristow is
    inapplicable to this situation.
    For the foregoing reasons, we conclude that IJE failed in its burden to
    establish, with positive assurance, that the arbitration provision here is not
    susceptible of an interpretation that would cover the claims at issue here. See
    Prudential Secs. 
    Inc, 909 S.W.2d at 899
    . Thus, we conclude that the claims8
    brought by IJE on behalf of the Original Partnerships fall within the scope of the
    arbitration provision contained in the representation agreement.
    In sum, we conclude that DCM established a valid arbitration agreement and
    the claims at issue fall within its scope. Thus, we turn to the other defenses to
    arbitration raised by IJE in its response to the motion to compel arbitration.
    7
    None of the engagement letters provided by IJE were between DCM and the Original
    Partnerships. See supra note 4.
    8
    IJE made no effort in the trial court or on appeal to establish that any of its individual
    claims against DCM fall outside the scope of the arbitration provision.
    17
    D.    Unconscionability of Arbitration Agreement
    IJE further asserted that the arbitration provision is unconscionable.
    Unconscionable agreements, whether relating to arbitration or not, are
    unenforceable under Texas law.         In re Poly-Am., 
    L.P., 262 S.W.3d at 348
    .
    “Because the law favors arbitration, the party opposing arbitration bears the burden
    to prove unconscionability.” TMI, Inc. v. Brooks, 
    225 S.W.3d 783
    , 792 (Tex.
    App.—Houston [14th Dist.] 2007, pet. denied). Arbitration agreements are not per
    se unconscionable, including arbitration agreements between attorneys and clients.
    See In re Pham, 
    314 S.W.3d 520
    , 526 (Tex. App.—Houston [14th Dist.] 2010,
    orig. proceeding, pet. struck).
    In its response to DCM’s motion to compel arbitration, IJE sought to place
    the burden on DCM to prove that the arbitration agreement at issue here is not
    unconscionable. IJE presented no evidence in support of its unconscionability
    argument, aside from the existence of the agreement between a law firm and its
    clients. In short, IJE failed to meet its burden to prove the arbitration agreement
    here is unconscionable.           TMI, 
    Inc., 225 S.W.3d at 792
    .         Thus, IJE’s
    unconscionability defense provides no basis for denying DCM’s motion to compel
    arbitration.
    F.    Waiver of Arbitration
    IJE also urged that DCM waived its right to arbitration. A party waives a
    right to arbitration by substantially invoking the judicial process to the other
    party’s detriment. Richmont Holdings, Inc. v. Superior Recharge Sys., L.L.C., 455
    SW.3d 573, 574–75 (Tex. 2014) (per curiam); 
    Baty, 423 S.W.3d at 433
    . Because
    of the strong presumption against waiver of arbitration, IJE has the difficult burden
    of proving that DCM waived its right to arbitrate. See 
    Baty, 423 S.W.3d at 433
    .
    “Whether a party has substantially invoked the judicial process depends on the
    18
    totality of the circumstances; key factors include the reason for delay in moving to
    enforce arbitration, the amount of discovery conducted by the movant, and whether
    the movant sought disposition on the merits.”                  Richmont Holdings, 
    Inc., 455 S.W.3d at 575
    . Any doubts regarding waiver are resolved in favor of arbitration.
    See 
    Baty, 423 S.W.3d at 433
    –34.
    Here, DCM and two other defendants filed a motion to transfer venue in
    September 2012. But filing a motion to transfer venue does not waive arbitration.
    See Richmont Holdings, 
    Inc., 455 S.W.3d at 576
    . Further, although twenty-eight
    months passed between the filing of this lawsuit and the motion to compel
    arbitration, the case was abated for over half that time.9 DCM moved to compel
    arbitration on December 5, 2014, less than five months after the abatement was
    lifted on August 15, 2014. DCM claims that its attorneys discovered the existence
    of the arbitration clause covering this dispute only when it began producing
    documents in response to IJE’s requests for production. Although this explanation
    may be implausible, “mere delay in moving to compel arbitration is not enough for
    waiver.” 
    Id. (citing In
    re Fleetwood Homes of Tex., L.P., 
    257 S.W.3d 692
    , 694
    (Tex. 2008) (orig. proceeding) (per curiam) (eight-month delay); In re Vesta Ins.
    9
    On February 26, 2013, DCM moved to abate the case on the ground that IJE lacked
    capacity to maintain this suit because (1) the charters of the Original Partnerships had been
    forfeited for nonpayment of taxes, and (2) IJE was not registered to do business in Texas and
    therefore lacked capacity to assert derivative claims on behalf of the Original Partnerships. The
    trial court granted the motion to abate on March 8, 2013. IJE filed a motion for clarification and
    two motions for reconsideration of the abatement order before filing a petition for mandamus
    relief with this court. After hearing oral argument, we denied the petition with respect to the trial
    court’s abatement due to IJE’s failure to register to do business in Texas and granted the petition
    with respect to the lapsing of the Original Partnerships’ charters. In re Immobiliere Jeuness
    Establissement, 
    422 S.W.3d 909
    , 918 (Tex. App.—Houston [14th Dist.] 2014, orig. proceeding).
    Six months later, IJE moved to lift the abatement on the ground that it had registered to
    do business in Texas. The trial court lifted the abatement on August 15, 2014, issued a
    scheduling order on September 4, 2014, and granted the parties’ joint motion for a protective
    order on October 21, 2014. In total, the case was abated for seventeen months.
    19
    Group, Inc., 
    192 S.W.3d 759
    , 763 (Tex. 2006) (orig. proceeding) (per curiam)
    (two-year delay)).
    Further, very little discovery has occurred in this case: no depositions have
    been formally noticed or taken; no third-party discovery has taken place; no
    motions to compel have been filed. DCM issued one set of requests for production
    to which IJE has not responded, and DCM issued one set of interrogatories to IJE
    to which IJE provided written responses.       IJE issued one set of requests for
    production and one set of interrogatories to DCM.           DCM provided written
    responses to the interrogatories and produced nearly 15,000 pages of documents in
    response to IJE’s request for production.       This level of discovery does not
    substantially invoke the judicial process.     See, e.g., 
    Baty, 423 S.W.3d at 436
    (holding that party did not substantially invoke the judicial process by serving four
    sets of requests for production, four sets of interrogatories, four subpoenas duces
    tecum, and taking seven depositions). Finally and importantly, DCM has not filed
    any motions seeking a ruling on the merits. See Richmont Holdings, 
    Inc., 455 S.W.3d at 575
    (noting that whether movant sought disposition on merits is “key
    factor” in determining if party “substantially invoked” judicial process).
    Under the circumstances presented here, considered as a whole, IJE has not
    established that DCM substantially invoked the judicial process See, e.g., 
    id. at 576;
    Baty, 423 S.W.3d at 436
    –38. Having reached this conclusion, we need not
    consider whether IJE was prejudiced by the delay. See Richmont Holdings, 
    Inc., 455 S.W.3d at 576
    Thus, IJE’s waiver arguments offer no support for the trial
    court’s denial of the motion to compel arbitration.
    III. CONCLUSION
    DCM established that (1) a valid arbitration agreement exists between DCM
    and the Original Partnerships, and (2) IJE is bound by that agreement because it is
    20
    suing derivatively and the claims at issue are within the scope of the agreement.
    IJE provided no valid basis for denying the motion to compel arbitration. For the
    reasons stated above, we reverse the trial court’s denial of the motion to compel
    arbitration and remand for proceedings consistent with this opinion.
    /s/    Sharon McCally
    Justice
    Panel consists of Justices Boyce, McCally, and Donovan.
    21