City of San Antonio Acting by and Through City Public Service Board A/K/A CPS Energy v. Public Utility Commission of Texas ( 2016 )


Menu:
  •                                          COURT OF APPEALS
    EIGHTH DISTRICT OF TEXAS
    EL PASO, TEXAS
    CITY OF SAN ANTONIO acting by and                   §
    through City Public Service Board a/k/a                               No. 08-14-00199-CV
    CPS ENERGY,                                         §
    Appellant,                                   Appeal from the
    §
    v.                                                                     261st District Court
    §
    PUBLIC UTILITY COMMISSION OF                                          of Travis County, Texas
    TEXAS,                                              §
    (TC# D-1-GV-13-000988)
    Appellee.            §
    OPINION
    The City of San Antonio, acting by and through City Public Service Board a/k/a CPS
    Energy (CPS Energy), appeals a district court judgment affirming a final order of the Public Utility
    Commission of Texas (PUC), in which the PUC imposed a $25,000 administrative penalty on CPS
    Energy for violating the PUC’s Wholesale Market Oversight Rule (the WMO Rule). CPS Energy
    raises several challenges to the validity of the PUC’s final order, contending, among other things,
    that the PUC misinterpreted the WMO Rule, that its application of the WMO Rule deprived CPS
    Energy of due process, and that the PUC’s final order was not supported by substantial evidence.
    We affirm.1
    1
    This case was transferred from the Third Court of Appeals in Austin, and we decide it in accordance with the
    BACKGROUND
    In order to address the dispute over the proper interpretation and application of the WMO
    Rule, it is necessary to understand the nature of the electricity market in Texas. Prior to the
    adoption of Chapter 39 of the Texas Utilities Code, also known as the Public Utility Regulatory
    Act or PURA, the electricity market in Texas essentially operated as a monopoly.                 TXU
    Generation Co., L.P. v. Pub. Util. Comm'n of Texas, 
    165 S.W.3d 821
    , 827 (Tex.App. – Austin
    2005, pet. denied). When it enacted PURA, the Texas Legislature made the determination to
    deregulate the production and sale of electricity for a large portion of the state, but chose not to
    deregulate the “transmission of energy.” TEX. UTIL. CODE ANN. § 39.001 (West 2016). In
    carving out an exception for the transmission of energy, the Legislature recognized that this aspect
    of the electricity industry is unique, and by its nature must be subject to some form of regulation.
    TXU Generation Co., 
    L.P., 165 S.W.3d at 827
    . In particular, the Legislature recognized that
    because electricity cannot be easily stored once it is generated, the industry must rely on a complex
    transmission grid to provide needed energy to consumers throughout the state.              In turn, it
    recognized that the grid must be constantly balanced by either adding or removing power to ensure
    a smooth and uninterrupted flow of energy to consumers, and that it was therefore necessary to
    assign an entity to be responsible for ensuring that balance. 
    Id. at 828.
    The Legislature assigned the task of overseeing and regulating this aspect of the industry to
    the PUC. TEX. UTIL. CODE ANN. § 35.004 (West 2016). As part of its authority, the PUC is
    authorized to certify independent organizations to perform various functions on its behalf to ensure
    the “reliability and adequacy of the regional electrical network” within a particular power region.
    
    Id. at §
    39.151(a), (c) (West 2016). For most of the state, that independent organization is the
    precedent of that Court to the extent required by TEX. R. APP. P. 41.3.
    2
    Electric Reliability Council of Texas (ERCOT), which manages the flow of electric power to
    approximately 23 million Texas customers within its region. TXU Generation Co. 
    L.P., 165 S.W.3d at 831
    .
    The Utilities Code also authorizes independent organizations, such as ERCOT, to adopt
    rules, subject to the PUC’s oversight and review, to ensure the reliability of the electrical grid
    within its region. TEX. UTIL. CODE ANN. § 39.151(d) (West 2016). Those rules are commonly
    referred to as ERCOT “protocols.” 16 TEX. ADMIN. CODE § 25.503(c)(3). The various entities,
    such as CPS Energy, that choose to participate in the transmission of energy within the ERCOT
    region are referred to as “market participants” and are subject to those protocols. 
    Id. at §
    25.503(c)(5, 6). In particular, the Code provides that market participants must observe all
    ERCOT rules and procedures, and that a failure to comply may, among other things, result in an
    enforcement action and ultimately the imposition of an administrative penalty. TEX. UTIL. CODE
    ANN. § 39.151(j) (West 2016).
    In turn, ERCOT is required to contract with an entity selected by the PUC to act as the
    PUC’s “wholesale electric market monitor” to prevent and detect violations of the ERCOT
    protocols. 
    Id. at §
    39.1515 (West 2016). ERCOT contracted with Texas Reliability Entity, Inc.
    (“Texas RE”) to investigate potential ERCOT protocol violations and report those violations to
    PUC staff.
    Also as part of its duty to oversee and monitor the various participants in this aspect of the
    electricity industry, the PUC adopted a global administrative rule, entitled the “Oversight of
    Wholesale Market Participants,” more commonly known as the “WMO Rule,” which has the
    stated purpose of establishing “the standards that the [PUC] will apply in monitoring the activities”
    3
    of these participants. 16 TEX. ADMIN. CODE § 25.503. The WMO Rule sets forth various duties
    of market participants, and in particular, requires that each “market participant shall be
    knowledgeable about ERCOT procedures,” and expressly requires all market participants to
    “comply with ERCOT procedures and any official interpretation of the Protocols issued by
    ERCOT or the [PUC].” 
    Id. at §
    25.503 (f)(1) and (2).
    The WMO Rule nevertheless provides in subsection (f) that a market participant may be
    “excused” from compliance with ERCOT instructions or Protocol requirements under the
    following relevant circumstances:
       When such non-compliance is due to communication or equipment failure beyond
    the reasonable control of the market participant;
       When compliance would jeopardize public health and safety or the reliability of the
    ERCOT transmission grid, or create risk of bodily harm or damage to the
    equipment;
       When compliance would be inconsistent with facility licensing, environmental, or
    legal requirements[.]
    
    Id. at §
    25.503(f)(2)(C). The Rule, however, states that the market participant is excused under
    this subparagraph only for so long as the condition continues. 
    Id. In addition,
    the WMO Rule contains a separate section providing two affirmative defenses
    to any prohibited act set forth in subsection (f) of the Rule. 
    Id. at §
    25.503(h). In particular,
    subsection (h) of the WMO Rule provides that a market participant may avoid liability for
    engaging in an act prohibited by the Rule, if the participant establishes that: (1) its “conduct
    served a legitimate business purpose . . . and that it did not know, and could not reasonably
    anticipate, that its actions would . . . adversely affect the reliability of the regional electric
    network”; or (2) it “exercised due diligence to prevent the excluded act or practice.” 
    Id. 4 The
    WMO Rule also provides an enforcement structure, which allows the Reliability
    Monitor (in this case Texas RE) to investigate possible ERCOT protocol violations, and provide its
    findings to PUC staff. 
    Id. at §
    25.503(k). The PUC staff is given the discretion to initiate an
    informal fact-finding review to investigate whether a market participant has violated the WMO
    Rule, including the provision requiring compliance with ERCOT protocols. 
    Id. at §
    25.503(o).
    If PUC staff finds that a possible violation exists, it may request that the PUC take appropriate
    enforcement action against the market participant, and may, among other things, recommend an
    administrative penalty against the participant. 
    Id. at §
    25.503(o)(4). The PUC may then initiate
    a formal enforcement proceeding against the market participant. 
    Id. at §
    25.503(o). Following a
    hearing, if a final order is entered against it, the market participant is entitled to judicial review of
    that order. TEX. UTIL. CODE ANN. §§ 15.001 (West 2016), 15.026 (West 2016).
    The ERCOT Protocol
    In the present case, following initial investigations conducted by Texas RE and the PUC
    staff, the PUC initiated an enforcement action against CPS Energy based on its alleged violation of
    an ERCOT Protocol relating to ancillary or reserve energy services, which in turn violated
    subsection (f) of the WMO Rule requiring compliance with all ERCOT protocols. Reserve
    services are used by ERCOT in various situations, including weather emergencies, in which
    reserve energy may be needed to balance the grid to ensure that customers in the ERCOT region
    are provided with sufficient energy on a continuing basis. Market participants, such as CPS
    Energy, who have become certified to offer reserve energy to ERCOT are known as Qualified
    Scheduling Entities (QSEs). When the need for reserve energy is predicted, a QSE may offer the
    use of reserve or standby energy services to ERCOT, including non-spinning reserve services
    5
    (commonly referred to as NSRS services), which are defined as ancillary services that can be
    “ramped to a specified output level within 30 minutes,” and can operate at a specified output level
    for at least an hour. In exchange for a fee, a QSE agrees to stand ready to provide NSRS to
    ERCOT during a specific timeframe, and agrees that it will initiate deployment of NSRS upon
    receiving a deployment instruction by ERCOT. Once the instruction is given to deploy NSRS,
    ERCOT Protocol § 6.5.7.6.2.3(4) provides a precise timeline for deployment of the NSRS by a
    QSE:
       Within 20 minutes of deployment, the generator must update the NSRS
    schedule to indicate the unit’s deployment;
       Within 25 minutes of deployment, the generator must reach its Low
    Sustained Limit [“LSL”]; and
       Within 30 minutes of deployment, the generator must change the
    resource status for the generating unit from offline to “on,” thus
    allowing ERCOT to dispatch it.
    The ERCOT protocol itself contains one relevant exception, providing that: “Except as
    otherwise stated in this Section . . . each QSE shall comply fully and promptly with a Dispatch
    Instruction issued to it, unless in the sole and reasonable judgment of the . . . QSE, such
    compliance would create an undue threat to safety, undue risk of bodily harm or undue damage to
    equipment[.]” ERCOT Protocol § 6.5.7.2(1).
    The February 2011 Cold Weather Event
    On January 27, 2011, in anticipation of predicted record cold temperatures in the ERCOT
    region beginning February 1 and lasting through February 3, ERCOT took steps to address the
    situation by, among other things, notifying its market participants and QSEs of the impending cold
    weather event to allow them to take necessary steps to prepare for it. In addition, ERCOT made
    6
    arrangements with various QSEs, including CPS Energy, to provide reserve NSRS services at a
    specific time during the cold weather event. In particular, CPS Energy agreed to provide 96
    megawatts of NSRS services by utilizing two of its Braunig Combustion Turbines, the Braunig
    CT5 and the Braunig CT8, to be available from 4 to 5 a.m. on the morning of February 2, upon
    receiving a deployment instruction from ERCOT.
    At 4:26 a.m., due to unprecedented demands on the grid due to the cold weather event,
    ERCOT provided instructions to the various QSEs, including CPS Energy, to deploy their NSRS
    services to ensure the ability to continue providing electricity to its customers in the region. CPS
    Energy immediately initiated the start-up sequence of both units two minutes later. The Braunig
    CT8 deployed successfully within the 30-minute timeframe required by the ERCOT Protocols.
    However, the Braunig CT5 failed to deploy within the required 30-minute timeframe, and instead,
    was not deployed until 6:09 a.m., approximately one and a half hours after CPS Energy received
    ERCOT’s initial deployment instruction.
    CPS Energy’s generator was not the only NSRS generator that did not timely deploy that
    morning, and in fact, over half of the NSRS generators that ERCOT attempted to deploy that
    morning either failed to deploy or delayed in deploying. Further, throughout the entire cold
    weather event, 225 generating units experienced a failure to start during freezing conditions, and at
    its lowest point, approximately one-third of the total ERCOT generation fleet was unavailable for
    deployment. This caused ERCOT to take action to reduce demand on the grid, and led to rolling
    blackouts that affected 3.2 million customers in the ERCOT area.
    PUC Proceedings
    Following the February cold weather event, Texas RE initiated an investigation into
    7
    whether CPS Energy had violated ERCOT protocols on the morning of February 2 when the CT5
    unit failed to timely deploy. Texas RE initially notified CPS Energy of the possible violation, but
    when it could not reach an agreement with CPS Energy, it referred the matter to PUC staff.2 PUC
    staff thereafter conducted its own informal investigation of the matter, and ultimately initiated a
    formal enforcement proceeding against CPS Energy for allegedly violating the WMO Rule
    requiring compliance with the ERCOT protocols, and recommended the imposition of an
    administrative penalty of $25,000.              The matter was then referred to the State Office of
    Administrative Hearings (SOAH), and a SOAH Administrative Law Judge (ALJ) held a hearing in
    January 2013.
    At the hearing, there was no debate over whether the Braunig CT5 had failed to timely
    deploy within the time frame set forth in the ERCOT Protocol. However, CPS Energy sought to
    be excused from compliance based on the various exceptions and excuses set forth in the ERCOT
    protocols and the WMO Rule. CPS contended that the CT5’s failure to deploy was caused by an
    equipment failure—a non-functioning damper fan—that was unforeseen and beyond its
    “reasonable control,” and that compliance would have posed health, safety, and environmental
    concerns because deployment of the unit without a functioning damper fan could have caused the
    unit to explode or emit hazardous particles into the air.
    At the hearing, CPS Energy relied primarily on the testimony of two of its employees who
    explained the events leading up to the CT5’s failure to timely deploy on the morning of February 2.
    Samuel Hernandez, the operations manager for the Braunig Plant site, acknowledged that he had
    2
    In its report to the PUC, the Texas RE investigator concluded that an ERCOT violation had occurred, but stated that:
    “Even though the unit did not perform as expected within the required time frame, it is noted that CPS personnel acted
    quickly and effectively to get the unit started during the difficult and hectic morning while dealing with many other
    equipment issues. The Braunig CT5 unit is a 48-megawatt unit; therefore, the impact of being late to start-up was
    minimal to the overall reliability of ERCOT.”
    8
    received “alerts” from ERCOT before February 1 regarding the cold weather event that was
    projected to occur, and that CPS Energy’s management took steps in advance to prepare the plant
    for that event. According to Hernandez, CPS Energy had previously prepared the plant for
    winter, but upon receiving the alerts from ERCOT, it took additional actions to “further reinforce
    winter preparedness procedures” at the plant in general, and in particular, took steps to recheck the
    Braunig CT units to ensure their readiness.3
    Hernandez also testified that in anticipation of the cold weather event, he directed
    additional staff to be present at the Braunig plant site on the night of February 1 through the early
    morning hours of February 2. According to Hernandez, a “normal” operating night consists of six
    operators and one supervisor, but he directed the presence of two additional operators, two
    additional technicians, and an unspecified number of additional electricians. Hernandez further
    explained that many of his staff members had already worked “significant hours” to prepare the
    plant for the cold weather event before February 1, and in order to balance their shifts, he sent
    home an unspecified number of staff members that day, so they would be available for work the
    next day, as the cold weather event was anticipated to last at least three days.
    Hernandez recalled that due to the extreme cold weather, CPS Energy began having issues
    with several of its generating units on the night of February 1, at both the Braunig plant site and
    other sites as well. Hernandez left the Braunig plant site at approximately 10:45 p.m. that night to
    assist with the “cold start” of other units at a different facility. He was therefore not at the
    3
    CPS Energy provided evidence establishing that its maintenance of the Braunig units and the steps it took in
    preparing the units for winter were within industry standards, and neither the ALJ nor the PUC found that CPS Energy
    was negligent in that regard. The ALJ expressly found that CPS Energy was not at fault in how it maintained the units
    or in preparing the units for winter weather. Instead, the ALJ found that the sole issue was whether CPS Energy had
    adequately staffed its plant in preparation for the cold weather event and whether adequate staffing would have
    enabled CPS Energy to comply with the ERCOT deployment instruction.
    9
    Braunig plant site when ERCOT issued its instruction to deploy the two Braunig CT units early the
    next morning.
    The undisputed evidence established that ERCOT provided its instruction to deploy the
    two Braunig CT generators at 4:26 a.m. on February 2, thereby requiring the units to be online at
    the LSL level by 4:51 a.m. Although the Braunig CT8 timely deployed, the Braunig CT5 did not.
    The facts are undisputed that an operator in CPS Energy’s control room made three failed attempts
    to start the CT5 unit as follows:
        4:28: CPS control room staff initiated start sequence of the CT5.
        4:39: Start sequence of the CT5 was interrupted.
        4:41: Start sequence was initiated a second time.
        4:47: Start sequence was again interrupted.
        4:49: Start sequence was initiated a third time.
        5:04: Start sequence was interrupted again.
    At approximately 5:01 a.m., the CPS Energy operator spoke with an ERCOT staff member in a
    recorded conversation, and advised him that the unit was not starting, that it was “tripping
    offline,” and that the unit was indicating a problem with “[l]ow temperature pressures.” The
    ERCOT staff member informed the operator of the urgent need to get the unit online, and advised
    the operator to “keep firing on it.”
    At the hearing, various CPS employees explained that the CT5 unit contained an
    automated computer-based control system built into the unit that was designed and installed by
    CPS Energy and outside experts to monitor conditions during startup to detect unsafe conditions.
    They explained that this automated safety system had automatically shut down the start sequence
    10
    because it had detected an unsafe condition. CPS Energy contended that absent the assistance of
    a technician who could troubleshoot or investigate the cause of the failure, its operator in the
    control room had no choice but to keep trying to start the unit. According to Hernandez, there
    were no technicians available to troubleshoot the problem with the CT5 at the time because the
    other two technicians who were onsite at the time had been assigned to address problems with the
    other larger generating units at the plant site. Hernandez further explained that CPS Energy
    decided to have the two technicians focus on the larger units at the plant site since the larger units
    were capable of providing more needed electricity to the grid than the Braunig CT5.
    Hernandez recalled that he was contacted by a senior plant manager at the Braunig plant
    site at approximately 4:30 a.m. on February 2, requesting that he return to the plant site to address
    the various problems occurring at the plant, shortly after ERCOT gave its instructions to deploy
    the Braunig CT units but before the startup failure occurred. The record reflects that it took
    Hernandez approximately one hour to reach the Braunig plant site after receiving the call, and he
    reported to the control room at approximately 5:30 a.m.        Upon arrival, he was told that there
    were problems with the CT5 unit and at least three other units at the plant site. Hernandez
    immediately directed the control room operator to locate an Instrument and Controls (“I&C”)
    technician to assist in troubleshooting the failed start-up of the CT5 unit.
    The I&C technician who ultimately assisted in troubleshooting the problem with the CT5
    was William L. Warnke, who had been called to come to the plant site at approximately 4 a.m.
    Warnke arrived at the plant site at approximately 5:25 a.m. and reported to the control room where
    he was informed about the problem with the CT5. After discussing the problem with the other
    two onsite technicians, Warnke physically went to the unit itself to investigate the problem at
    11
    approximately 5:46 a.m., and found that a tempering air fan discharge damper and its “associated
    linkage” were frozen and would not move. Warnke was able to break away some of the ice from
    the unit with a large wrench, allowing the damper to open. Shortly thereafter, the start sequence
    was initiated for a fourth time, and by 6:09 a.m. the CT5 was online generating electricity.
    Warnke explained that it would have been impossible for the unit to operate with a frozen
    discharge damper because the damper is necessary for the unit’s tempering air fans to operate; in
    turn, the fans are essential to the unit’s operation because they regulate the temperature control for
    the catalyst in the turbine exhaust duct. Warnke further explained that the built-in safety system
    in the unit is designed to automatically terminate the start-up process if an air fan discharge damper
    fails to open, and acknowledged that the control room operator had received an “alarm” signaling
    that a tempering air fan discharge damper had failed to open, thereby alerting him of the particular
    problem. Warnke testified that several negative outcomes could have occurred if the unit had
    been operated without the tempering air fans, including explosions, equipment damage, and air
    pollution emissions.
    At the hearing, both Warnke and Hernandez expressed their opinions that the unit’s failure
    to start on the morning of February 2 was unforeseeable, asserting that CPS Energy had no reason
    to anticipate that there were be a damper failure of this nature. According to Hernandez, during
    his 33 years of plant operation experience, he had never seen a similar damper failure occur due to
    freezing weather. Warnke testified that “not once in CPS history has a damper of that type
    linkage froze over and caused issues with the damper opening.”
    Both Hernandez and Warnke testified that although the Braunig CT units were only
    designed to operate at 20 degrees and above, the damper fans themselves were rated at zero
    12
    degrees and were therefore designed to open regardless of the temperature. 4                     Warnke did
    acknowledge, however, that “[t]he weather forecast is an important consideration for all units,”
    and that the “ambient temperature surrounding the unit” is a factor to consider in ensuring the
    reliability of plant operations.
    In response to CPS Energy’s arguments regarding the foreseeability of the equipment
    failure, the PUC did not focus simply on whether it was foreseeable for the damper to freeze over
    and fail to open.      Instead, the PUC focused on the more general question whether it was
    foreseeable that the Braunig plant site would experience start-up failures due to the anticipated
    cold weather event, and in turn, whether CPS Energy should have taken steps to ensure that it had
    adequate staff at the plant to address those potential issues. In particular, the PUC presented the
    testimony of Greg D. Graham, a Senior Protocol Compliance Analyst with Texas RE, who was
    responsible for investigating CPS’s violation of the ERCOT protocol. In his testimony, Graham
    focused on the fact that CPS Energy had several days’ advance notice of the severe cold weather
    event, and was therefore on notice that it could experience potential problems with all of its
    generators, including the Braunig CT units. Graham also pointed out that the Braunig CT units
    had just been declared commercial in December 2010, and had not been operated in cold weather,
    therefore rendering the units essentially untested. Graham further pointed out that the weather
    forecast was projecting temperatures below the “design criteria” for the Braunig units for the
    morning of February 2. In light of this forecast, Graham expressed his disagreement with CPS
    Energy’s conclusion that it could not have anticipated that its equipment might freeze, or that it
    4
    After the February 2011 event, CPS Energy fabricated covers to place on the dampers. The ALJ found that CPS
    Energy had adequately prepared the plant for cold weather operations in accordance with industry standards, and
    therefore did not consider the lack of covers in determining whether CPS Energy should be excused for the ERCOT
    violation.
    13
    could not have anticipated that it might experience other start-up failures at the plant.
    Given the known potential for such problems, Graham posited that CPS Energy should
    have had more staff on hand for the cold weather event, and in particular, more technicians to
    troubleshoot and investigate the start-up problems CPS Energy encountered on both February 1
    and 2. Graham found it significant that CPS Energy’s problems with the cold weather at the plant
    site surfaced as early as 10:55 p.m. on the night of February 1, when multiple generators failed to
    startup due to the cold weather. Graham opined that because CPS Energy had already assigned its
    only two technicians at the plant site to work on those failed generators, CPS Energy was on notice
    that it needed additional staff to address potential problems that might occur with the Braunig CT
    units when they would be needed the next morning. Graham pointed out that the entire plant site
    began failing hours before ERCOT gave its instruction to deploy the Braunig CT units, and he
    therefore believed that there was still time for CPS Energy to call in additional staff to remedy the
    situation at that time, but that CPS Energy failed to call for any additional help until hours later,
    when it was essentially too late.
    Graham particularly faulted Hernandez, noting that when he left the Braunig plant site at
    10:45 p.m. on February 1 to address the start-up problems at another plant site, he was already
    aware that the Braunig plant site was having significant issues and that both technicians at the site
    were busy addressing problems with other generators.              Graham therefore believed that
    Hernandez, knowing he had no other available technicians at the plant site to address potential
    problems with the Braunig CT units, could have avoided the ERCOT protocol violation by
    reevaluating his staffing plan at that point and calling in additional personnel to ensure that the CT
    units successfully deployed.
    14
    Graham further emphasized that during the first three failed attempts to start the Braunig
    CT5, which began at 4:28 a.m., CPS Energy admittedly had no technicians available to investigate
    the problem, and took no action to address the issue until almost an hour and a half later when
    Hernandez and Warnke arrived on the scene. Graham believed the ERCOT violation could have
    been avoided if CPS Energy had taken steps to ensure that it had sufficient staff on hand to either
    inspect the CT units before the ERCOT instruction t deploy was given, or at least to enable CPS
    Energy staff to take reasonable steps to investigate the startup failure immediately after it occurred.
    Graham further opined that the need for additional staff was illustrated by the fact that CPS Energy
    “significantly increased” its staff the next day after the failure to deploy occurred.
    Graham concluded that it was CPS Energy’s choice to offer the reserve energy to PUC on
    the morning in question, knowing the weather conditions at hand, and that it was therefore CPS
    Energy’s responsibility to adequately prepare to ensure that it met its obligation, knowing it would
    be subject to administrative penalties if it did not. In his opinion, that responsibility extended not
    only to ensuring that the units were mechanically sound, but also to ensuring that adequate staff
    was on hand to make certain the units deployed in a timely manner.
    At the hearing, the PUC also presented the testimony of Ernest Garcia, the PUC staff
    member who investigated CPS Energy’s alleged protocol violation. Garcia testified that when he
    recommended that the PUC initiate enforcement proceedings against CPS Energy, his focus was
    also on CPS Energy’s failure to adequately staff the Braunig plant site in anticipation of the cold
    weather event, which he viewed as the ultimate cause of the ERCOT violation. Garcia noted that
    it was within CPS Energy’s control to have a technician available to address potential start up
    issues with its units, and he concluded that if the plant had been adequately staffed in anticipation
    15
    of the cold weather event, “we would not be here today.” Garcia further explained that he
    considered CPS Energy’s violation serious, and he therefore recommended the maximum penalty,
    in part to deter future violations of the ERCOT protocol.
    In rebuttal, both Hernandez and Warnke denied that the staffing levels had any effect on
    the equipment failure. Hernandez testified that they did have additional staff on site the morning
    of the incident, which he believed was sufficient under the circumstances known to CPS Energy at
    the time. Warnke also opined that having even more staff on site would not have helped CPS
    Energy avoid the ERCOT protocol violation. In particular, Warnke explained that the Braunig
    CT units typically take 20 minutes to reach LSL levels, and in his opinion, even if a technician had
    been standing at the unit at the time of start-up, it would have been virtually impossible for the
    technician to have investigated, diagnosed, and repaired the unit after it first tripped and to have
    the unit restarted within the required 25-minute period of time.
    Warnke also explained that, as part of its increased staffing, CPS Energy had three
    operators at the plant site during the cold weather event who were specifically assigned to make
    hourly rounds of the plant, checking heat-tracing insulation, enclosures, portable heaters, heat
    lamps, and “anything that’s out there to prevent freezing.” However, he also acknowledged that
    when making their rounds, these operators would not have inspected the damper fans, because
    they were considered mechanical items not likely to freeze, and because they were located
    between two motors in an area that operators would not normally inspect. He therefore concluded
    that having additional operators at the plant would not have changed the outcome.
    CPS Energy also presented the testimony of an industry expert witness, John Allen Moore.
    Moore acknowledged that plant operations may be affected by severe cold weather, and that
    16
    staffing is a factor that a market participant should take into consideration in ensuring reliable plant
    operations when faced with a severe weather event, such as the event in February 2011. He
    therefore acknowledged that in light of the warnings it had received regarding the anticipated cold
    weather event, CPS Energy was obligated to provide “additional preparation and staffing to ensure
    or to help ensure as reliable operations as possible . . . [a]s reasonably possible.” Moore
    expressed his opinion, however, that CPS Energy did in fact take adequate “supplemental steps,”
    by having additional operators and technicians available at the plant to monitor operations and
    address conditions as they arose during the cold weather event. In Moore’s opinion, CPS Energy
    reacted to the CT5’s failure to deploy in an “efficient and responsible manner” in light of the
    conditions that were occurring at the plant site at the time.
    The Ruling
    Following the SOAH hearing, the ALJ issued its Proposal for Decision. The ALJ found
    that CPS Energy had violated the ERCOT Protocol when the CT5 unit admittedly failed to deploy
    within the timeframe required by the Protocol. The ALJ further concluded that CPS Energy had
    failed to establish an excuse under the WMO Rule. In particular, the ALJ concluded that CPS
    Energy had failed to establish that its non-compliance resulted from any health, safety, or
    environmental concerns. The ALJ also concluded that CPS Energy was not excused based on the
    exception in the WMO Rule for “equipment failure beyond the reasonable control of the market
    participant.” In making that determination, the ALJ agreed with CPS Energy that it was not
    negligent in its efforts to protect its equipment during the cold weather event, and that its actions in
    maintaining and winterizing its equipment were “in alignment with industry standards.” Instead,
    the ALJ believed that the sole issue in determining whether the equipment failure was beyond its
    17
    reasonable control was “whether CPS provided adequate staffing in light of the severe weather and
    the effect it might have on the relatively new plant.” The ALJ noted that CPS Energy had
    presented evidence that it had provided additional staffing the morning of the equipment failure,
    but had failed to “establish a benchmark against which to judge its actions.” The ALJ believed
    that without an independent benchmark, it was “impossible to say that the staffing levels employed
    by CPS were reasonable or prudent.” Noting that CPS Energy had the burden to establish a valid
    excuse, and therefore to present evidence on that issue, the ALJ concluded that CPS Energy had
    failed to meet its burden of proving “that the failure to comply with ERCOT Protocols was beyond
    its reasonable control.”
    The ALJ then addressed the serious nature of CPS Energy’s violation in failing to provide
    the NSRS service in a timely manner as promised to ERCOT, noting that “NSRS is an important
    tool that ERCOT uses to ensure the reliability of the ERCOT grid.” The ALJ also noted that CPS
    Energy had obligated itself to provide NSRS electricity during what was essentially an emergency
    situation, and that failing to take reasonable steps to meet its obligations was a “grave violation
    warranting the maximum penalty available to the Commission.” The ALJ further concluded that,
    “CPS’s failure to provide the NSRS it obligated itself to provide on February 2, 2011, contributed
    to the deterioration of the Grid on that morning, which ultimately led to ERCOT shedding load
    (i.e., ordering rolling blackouts) to avoid a total system collapse.”       In recommending the
    maximum penalty, the ALJ factored in the “deterrent effect” the penalty would have to encourage
    other market participants to avoid engaging in similar conduct in the future.
    The PUC subsequently adopted the findings and conclusions of the ALJ. In its final order,
    the PUC found that CPS Energy had violated two ERCOT protocols:
    18
    1) ERCOT Protocol 6.5.7.6.2.3(4), for CPS Energy’s failure to have the CT5 generator
    dispatching electricity within 30 minutes of ERCOT’s dispatch (or deployment)
    instructions.
    2) ERCOT Protocol 8.1.1.4.3(3)(b) for CPS Energy’s failure to provide a specific resource
    status to ERCOT within 25 minutes of ERCOT’s deployment instructions.
    In its final order, the PUC concluded that CPS Energy bore the “burden of proving by a
    preponderance of the evidence that it should be excused from compliance with ERCOT dispatch
    instructions and protocol requirements,” and that CPS Energy had not met its burden to establish
    an excuse under the ERCOT protocols or the WMO rule. The PUC then concluded that CPS
    Energy had not met its burden of establishing any excuse under the ERCOT protocols or the WMO
    Rule. In doing so, the PUC’s order also focused on staffing issues. In particular, the PUC
    concluded that CPS Energy failed to prove that it had provided adequate staffing at the Braunig
    site in “light of its choice to offer NSRS from unproven units” during the cold weather emergency.
    It further concluded that CPS Energy had several opportunities on the morning in question to call
    in additional staffing “to ensure any start-up failures could be promptly addressed,” but failed to
    take any such necessary action.
    Agreeing with the ALJ that the ERCOT protocol violations were serious, particularly
    because they occurred in the midst of an emergency situation, the PUC ordered CPS Energy to pay
    the maximum $25,000 administrative penalty for the violations. As permitted by statute, CPS
    Energy sought judicial review in the Travis County district court in September 2013. See TEX.
    UTIL. CODE ANN. § 15.001 (West 2016). The trial court affirmed the PUC’s final order, and this
    appeal followed.
    DISCUSSION
    On appeal, CPS Energy raises several challenges to the PUC’s final order. In particular,
    19
    CPS Energy claims the PUC misinterpreted or misapplied the WMO Rule in a manner that
    conflicted with a prior decision of the Austin Court of Appeals; that it formulated a new or novel
    interpretation of the WMO Rule and applied that new interpretation during the enforcement
    proceeding without giving CPS Energy “fair notice” of the interpretation; that the PUC applied the
    WMO Rule in a manner that was unreasonable, arbitrary, and capricious; and that the PUC’s order
    was not supported by substantial evidence.
    Standard of Review
    In their challenges to the PUC’s final order, CPS Energy has raised a variety of issues,
    which we review under different standards of review. As a general matter, an appellate court
    must review the PUC’s final order under the “substantial evidence rule,” which requires us to give
    “significant deference to the agency in its field of expertise.” TEX. UTIL. CODE ANN. § 15.001
    (“Any party to a proceeding before the commission is entitled to judicial review under the
    substantial evidence rule.”); see also CenterPoint Energy Houston Elec., LLC v. Pub. Util.
    Comm’n of Texas, 
    408 S.W.3d 910
    , 916 (Tex.App. – Austin 2013, pet denied) (we review a
    Commission order under the Administrative Procedure Act’s (APA) “substantial-evidence”
    standard); City of El Paso v. Pub. Util. Comm’n of Texas, 
    344 S.W.3d 609
    , 618 (Tex.App. – Austin
    2011, no pet.); State v. Pub. Util. Comm’n of Texas, 
    246 S.W.3d 324
    , 331 (Tex.App. – Austin
    2008, pet. denied).
    In conducting our review, we may not substitute our judgment for that of the agency on
    matters committed to agency discretion. TEX. GOV’T CODE ANN. § 2001.174 (West 2016); H.G.
    Sledge, Inc. v. Prospective Inv. & Trading Co., Ltd., 
    36 S.W.3d 597
    , 602 (Tex.App. – Austin 2000,
    pet. denied). Further, we must “presume that the agency’s order is valid and that its findings,
    20
    inferences, conclusions, and decisions are supported by substantial evidence,” and therefore, the
    party challenging the agency’s order has the burden to overcome this presumption. 
    State, 246 S.W.3d at 331-32
    (citing City of El Paso v. Public Util. Comm’n, 
    883 S.W.2d 179
    , 185
    (Tex.1994)).
    Our review under the substantial evidence rule is limited to determining whether the “record
    demonstrates some reasonable basis for the agency’s action.” 
    Id. at 332.
    If “reasonable minds”
    could have reached the same decision, we will affirm the agency’s decision. We will reverse the
    agency’s decision only if it is “not reasonably supported by substantial evidence, in violation of a
    constitutional or statutory provision, in excess of the agency’s statutory authority, made through
    unlawful procedure, affected by other error of law, arbitrary or capricious, or characterized by an
    abuse of discretion.” 
    Id. (citing TEX.
    GOV’T CODE ANN. § 2001.174(2)(A)-(F)).
    Although we are required to defer to the agency’s findings of fact when reviewing an
    agency order, if an issue on appeal involves a question of law, we review that issue de novo. Tex.
    Dep’t of Pub. Safety v. Allocca, 
    301 S.W.3d 364
    , 367 (Tex.App. – Austin 2009, pet. denied). In
    particular, when an issue turns on the construction of a statute or administrative rule, that issue is
    considered a question of law requiring de novo review. 
    State, 246 S.W.3d at 332
    ; see also First
    Am. Title Ins. Co. v. Combs, 
    258 S.W.3d 627
    , 631 (Tex. 2008); CenterPoint Energy Houston Elec.,
    
    LLC, 408 S.W.3d at 916
    (when a dispute centers on the agency’s interpretation of its rules,
    questions of rule construction are reviewed de novo).
    In general, a reviewing court must construe administrative rules, which have the same
    force as statutes, in the same manner as statutes. CenterPoint Energy Houston Elec., 
    LLC, 408 S.W.3d at 916
    (“We interpret administrative rules, like statutes, under traditional principles of
    21
    statutory construction.”). When an administrative rule or statute is unambiguous, it must be
    interpreted based on its plain language, unless that interpretation would produce an absurd result.
    Rodriguez v. Service Lloyds Ins. Co., 
    997 S.W.2d 248
    , 254 (Tex. 1999); see also CenterPoint
    Energy Houston Elec., 
    LLC, 408 S.W.3d at 916
    -17; Fleming Foods of Tex., Inc. v. Rylander, 
    6 S.W.3d 278
    , 284 (Tex. 1999); 
    State, 246 S.W.3d at 332
    . If an agency has failed to follow the
    clear, unambiguous language of its own regulation, we must reverse its action as arbitrary and
    capricious. 
    Rodriguez, 997 S.W.2d at 255
    ; see also CenterPoint Energy Houston Elec., 
    LLC., 408 S.W.3d at 916-17
    ; Pub. Util. Comm’n v. Constellation Energy Commodities Grp., Inc., 
    351 S.W.3d 588
    , 595 (Tex.App. – Austin 2011, pet. denied).
    However, if the rule is ambiguous or leaves room for policy determinations, we defer to the
    agency’s interpretation if the interpretation is reasonable, but not if the agency’s interpretation is
    plainly erroneous or inconsistent with the regulation or its underlying statutes. CenterPoint
    Energy Houston Elec., 
    LLC, 408 S.W.3d at 916
    -17 (citing 
    Rodriguez, 997 S.W.2d at 254
    –55); see
    also City of El Paso v. Pub. Util. Comm’n of 
    Texas, 344 S.W.3d at 618-19
    ; Railroad Comm’n of
    Tex. v. Texas Citizens for a Safe Future & Clean Water, 
    336 S.W.3d 619
    , 624–25 (Tex. 2011)
    (although we must give “serious consideration” to a governmental agency’s construction of a
    statute it is charged with administering, this principle presupposes that the statute is ambiguous
    and the agency’s construction is reasonable and does not conflict with the statute’s language).
    Further, courts “do not defer to administrative interpretation in regard to questions which do not lie
    within administrative expertise, or deal with a nontechnical question of law.” 
    State, 246 S.W.3d at 332
    -33 (citing Rylander v. Fisher Controls Int’l, Inc., 
    45 S.W.3d 291
    , 302 (Tex.App. – Austin
    2001, no pet.)).
    22
    ANALYSIS
    Issue One: Whether the PUC’s Interpretation and Application of the WMO Rule
    Violated CPS Energy’s Due Process Right to Fair Notice
    CPS Energy contends that prior to the current enforcement proceeding, the WMO Rule had
    been interpreted by the Austin Court of Appeals in TXU Generation to mean that a market
    participant could not be held liable for actions resulting from “unforeseen” accidents or
    mechanical failures. CPS Energy believes that the Austin Court gave “assurances” to market
    participants that they would not be subject to liability for any such unforeseen events. CPS
    Energy contends that in the current proceeding, the PUC interpreted and applied the WMO Rule in
    a new and novel manner, which conflicted with TXU Generation. In particular, it argues that,
    without any notice of this interpretation, the PUC initiated enforcement proceedings against it for
    what CPS Energy believes was an unforeseeable mechanical failure on the morning of February 2,
    2011. CPS Energy argues that a regulatory agency is forbidden from giving a new interpretation
    of a rule for the “first time in an enforcement proceeding,” and that by doing so in this proceeding,
    the PUC deprived CPS Energy of any “meaningful, prehearing notice,” which undermined the
    fundamental fairness of the proceeding.
    We agree with CPS Energy that a regulated party must be given “fair notice” of what type
    of conduct will subject it to an enforcement proceeding, and the regulated party must not be forced
    to guess what type of conduct will subject it to an enforcement proceeding or be clairvoyant in
    attempting to divine the agency’s interpretation of the rule in advance. Vista Healthcare, Inc. v.
    Tex. Mut. Ins. Co., 
    324 S.W.3d 264
    , 273 (Tex.App. – Austin 2010, pet. denied); see also
    Christopher v. SmithKline Beecham Corp., __U.S. __, 
    132 S. Ct. 2156
    , 2168, 
    183 L. Ed. 2d 153
    (2012) (it is improper for a regulatory agency to interpret and apply a rule in a novel manner for the
    23
    first time in an enforcement proceeding). However, as explained below, we disagree with CPS
    Energy that it was not on notice that its conduct on the morning of February 2 could subject it to
    liability. We further conclude the PUC interpreted the WMO Rule in a manner that was
    consistent with TXU Generation and with the plain language of the Rule itself.
    TXU Generation
    In TXU Generation, the parties brought a facial challenge to the constitutionality of
    subsection (g) of the WMO Rule, which provides that market participants are subject to
    enforcement actions if they engage in “[a]ny act or practice of a market participant that materially
    and adversely affects the reliability of the regional electric network or the proper accounting for
    the production and delivery of electricity among market participants[.]” 16 TEX. ADMIN. CODE
    § 25.503(g). Subsection (g) of the WMO Rule contains a list of seven “prohibited activities,” all
    of which are aimed at preventing unfair trade practices within a power region. The market
    participants in TXU Generation claimed the WMO Rule was unconstitutionally vague on its face,
    and failed to give market participants fair notice of what type of conduct could subject them to an
    enforcement proceeding. Among other things, the market participants were concerned about the
    seventh prohibited activity in subsection (g), which provides that a “[a] market participant shall not
    engage in market power abuse.” See 
    id. at §
    25.503(g)(7). The market participants noted that the
    Rule did not contain a precise definition of what actions would constitute a “market power
    abuse.”5
    5
    The market participants also contended that the WMO Rule was invalid because it lacked an “intent” element, and
    would allow a market participant to be found liable for a “market power abuse” even if their actions were unintentional
    acts. The market participants argued that the Commission lacked the statutory authority to prohibit unintentional
    conduct, and argued that at the least, the Court should imply an “element of intent” into the Rule. TXU 
    Generation, 165 S.W.3d at 832-34
    . The Austin Court disagreed, noting that the PUC enacted the WMO Rule to protect
    consumers and to ensure a reliable electricity network – a task that the Legislature expressly gave to the PUC. 
    Id. at 834.
    The Court concluded that the “WMO Rule reflects the Commission’s decision, based on its expertise, that both
    24
    The market participants claimed the WMO Rule was unconstitutionally vague because
    subsection (g) did not clearly define the type of activities that would be considered a “market
    power abuse,” claiming that the language in the Rule was too “open-ended,” was “confusing,”
    created “unknown risks,” and generally did not provide enough specificity to allow market
    participants to take measures to avoid violations. TXU Generation Co., 
    L.P., 165 S.W.3d at 838
    -
    40. As one example of their confusion, the market participants questioned whether they could be
    found liable for a “market abuse” under subsection (g)(7) of the Rule for “withholding” electricity
    in situations in which their failure to delivery electricity was due to “accidents or ordinary
    mechanical breakdowns,” such as “mechanical failures and computer glitches,” pointing out that
    such events could have an adverse effect on the electricity market through no fault of the market
    participants. 
    Id. at 839-40.
    In addressing that concern, the Austin Court was unable to point to any provision in
    subsection (g) of the WMO Rule that would excuse the market participants from liability under
    those circumstances. However, the Court concluded that subsection (g) should not be read “in
    isolation,” and that it should instead be interpreted in conjunction with subsection (h) of the WMO
    Rule, which sets forth various affirmative defenses to a violation of subsection (g). 
    Id. at 840.
    In
    particular, subsection (h) expressly provides a market participant with two affirmative defenses to
    a claim of market power abuse if the market participant establishes that its conduct: (1) “served a
    legitimate business purpose consistent with prices set by competitive market forces; and that it did
    not know, and could not reasonably anticipate, that its actions would inflate prices, adversely
    intentional and unintentional actions in the wholesale market that adversely affect reliability must be prohibited in
    order to prevent market power abuse, ensure retail customers ‘safe, reliable, and reasonably priced electricity,’ and
    ensure reasonably priced electric power for ancillary services.” 
    Id. The Court
    therefore expressly concluded that
    the Commission was entitled to bring enforcement actions for both intentional and unintentional conduct. 
    Id. 25 affect
    the reliability of the regional electric network”; and (2) “if applicable, that it exercised due
    diligence to prevent the excluded act or practice.”6 16 TEX. ADMIN. CODE § 25.503(h).
    Paraphrasing subsection (h) as providing a defense when the “adverse effect on reliability,
    price, or accounting was not known or foreseeable with the exercise of due diligence,” the Austin
    Court opined that this “provision gives clear notice that the unforeseen accidents described by
    TXU will not give rise to liability under the [WMO] rule.”7 TXU Generation Co. 
    L.P., 165 S.W.3d at 840
    . In concluding that the WMO Rule thereby gives participants notice of what type
    of conduct will give rise to liability, the Court concluded that the “rule does not require
    clairvoyance as to whether an action will impact price, reliability, or accounting – only diligence.”
    
    Id. at 840.
    Although we agree with CPS Energy that important lessons can be derived from TXU
    Generation, we also note that clear distinctions may be drawn between the issues posed in TXU
    Generation and the questions before this Court. First, TXU Generation was focused on the facial
    constitutionality of subsection (g) involving market power abuses, and whether the language used
    in that section was unconstitutionally vague and failed to give market participants clear notice of
    what type of conduct would cause a violation of subsection (g).
    In the present case, however, CPS Energy was not charged with a violation of subsection
    (g), and was instead found to have violated subsection (f). Subsection (f) clearly and in plain
    6
    As discussed in more detail below, subsection (h) expressly provides that these affirmative defenses can also be
    applicable to subsection (f) violations for failures to comply with ERCOT protocols. 16 TEX. ADMIN. CODE §
    25.503(h).
    7
    The Court also noted that the ERCOT protocols address “issues such as scheduled maintenance and the shutdown of
    plants,” which clearly give market participants guidance on what type of activities are considered prohibited. 
    Id. at 840
    n.10. The Court noted that if an “action is authorized by ERCOT under its protocols, it is not a prohibited
    activity.” 
    Id. 26 language
    informs a market participant that it must “comply with ERCOT procedures and any
    official interpretation of the Protocols issued by ERCOT or the commission.” 16 TEX. ADMIN.
    CODE § 25.503(f). There is no ambiguity in subsection (f), and significantly, we note that CPS
    Energy does not contend that it was unaware of the ERCOT protocols it was found to have
    violated, or that it did not have notice of what type of conduct would cause it to be in violation of
    those protocols. In fact, CPS Energy acknowledges that it was aware that the ERCOT protocols
    set forth a specific timeline for having NSRS services deployed, and that it failed to comply with
    that timeline.
    What is at issue in this case is whether CPS Energy was on notice of what type of situations
    would cause it to be excused from that duty. There are two separate provisions in the WMO Rule
    on which CPS Energy could have relied in seeking to excuse its performance. First, the WMO
    Rule contains the two affirmative defenses set forth in subsection (h), which were specifically
    addressed in the TXU Generation opinion, and which may excuse a market participant’s violation
    if it can demonstrate that it used “due diligence” to avoid the violation. 16 TEX. ADMIN. CODE §
    25.503(h). Second, the WMO Rule contains the specific excuse provisions within subsection (f)
    itself, which provide excuses for “equipment failure beyond the reasonable control of the market
    participant[,]” and the various excuses based on health, safety, and environmental concerns. 
    Id. at §
    25.503(f).
    In its brief, however, CPS Energy makes no mention of the affirmative defense provision
    found in subsection (h) of the WMO Rule, and instead focuses exclusively on whether it was
    entitled to rely on the excuse provisions found in subsection (f) of the Rule. Although TXU
    Generation focused exclusively on the affirmative defenses set forth in subsection (h), CPS
    27
    Energy nevertheless repeatedly attempts to apply the standards set forth in the Austin Court’s
    discussion of subsection (h) to its analysis of the excuse provisions found in subsection (f). As
    discussed in more detail below, however, the particular excuses set forth in subsection (f) are based
    on different considerations, and warrant a separate and distinct discussion—one that the Austin
    Court was not called upon to make in TXU Generation. We believe that much of the confusion in
    this case stems from CPS Energy’s apparent failure to recognize the distinction between these two
    subsections.
    Nevertheless, to the extent that TXU Generation requires us to consider whether the
    equipment failure in this case was “foreseeable,” which appears to be the primary focus of CPS
    Energy’s argument in its brief, we turn our attention to that issue.
    Whether CPS Energy could have Reasonably Anticipated its Actions
    Would Adversely Affect the Electric Network
    CPS Energy argues throughout its brief that it should not be held liable for the equipment
    failure that occurred on February 2, as it was an “unforeseen” occurrence. In particular, CPS
    Energy contends that it presented undisputed evidence during the SOAH hearing that its failure to
    timely deploy the CT5 unit in accordance with the ERCOT protocol was due solely to
    “unforeseeable equipment failure[.]” CPS Energy points out that the evidence established that
    the CT5 unit failed to start due to a frozen damper fan, and claims it had no way of anticipating this
    failure. CPS Energy points out that two of its employees testified that they had never before
    encountered a frozen damper fan in their years of employment at CPS Energy, and that they had no
    reason to anticipate that the damper fan would freeze on the morning in question. CPS Energy
    also finds it significant that the ALJ expressly found that the equipment failure did not occur due to
    any maintenance issues or due to any failure by CPS Energy to prepare its equipment for the cold
    28
    weather event.    CPS Energy essentially believes that because it was not on notice of any
    preexisting mechanical issues with the damper fan, the PUC was required to find that the damper
    fan’s failure to open was an unforeseeable occurrence, absolving it of all blame.
    We believe, however, that CPS Energy’s focus is too narrow, and is in fact contrary to the
    actual language used in the WMO Rule. The first affirmative defense in subsection (h) of the
    WMO Rule (which the Austin Court specifically discussed in TXU Generation) expressly places
    the focus not on whether a particular piece of equipment might fail, but on whether the market
    participant could have “reasonably anticipate[d] that its actions would … adversely affect the
    reliability of the regional electric network[.]” 16 TEX. ADMIN. CODE § 25.503(h).
    The real question then is whether CPS Energy could have “reasonably anticipated” that its
    “actions” leading up to and during the cold weather event would “adversely affect” the grid on the
    morning of February 2. In turn, CPS Energy’s “actions” leading up to the cold weather event
    consisted both of preparing the plant’s equipment for the event and in making staffing decisions.
    As set forth above, the PUC had no issue with the actions CPS Energy took in preparing its
    mechanical equipment for the event, and instead focused exclusively on its actions in staffing its
    plant. We believe that this was a fair and reasonable focus in light of the language used in
    subsection (h).
    As acknowledged by CPS Energy’s own expert witness, staffing decisions are a factor in
    preparing a plant for cold weather events. CPS Energy’s operations manager also recognized this
    when he made the decision to have additional staff on hand in anticipation of the February cold
    weather event. Further, the PUC also provided testimony that staffing can affect the reliability of
    the grid, particularly during severe weather events, as market participants are on notice that they
    29
    may encounter equipment failures due to cold weather and must therefore consider whether they
    have sufficient staff on hand to address those failures. Moreover, there was no dispute among the
    witnesses at the SOAH hearing that CPS Energy could have reasonably anticipated that it would
    encounter equipment failures, at least of a general nature, as the plant was not rated for the
    temperatures projected to occur during the event. And finally, and perhaps most importantly,
    CPS Energy knew that it had promised ERCOT to provide NSRS services during the cold weather
    event from its two untested Braunig CT units, and it knew that if it did not provide those services as
    promised, the grid could be adversely affected during what could have been, and in fact ended up
    being, an emergency situation. Therefore, we conclude that the PUC presented substantial
    evidence that CPS Energy could have “reasonably anticipated” that its actions in staffing its plant
    prior to the cold weather event could have adversely affected the grid.
    Also, the evidence established that CPS Energy did in fact begin experiencing significant
    freezing and consequent equipment failures at its plant site the night before it was required to
    provide the NSRS services to ERCOT, which diverted the attention of its only two technicians at
    the plant, and as CPS Energy admits, rendered them unavailable to address any issues that might
    have arisen, and did in fact arise, with the deployment of the CT5 unit. As the PUC noted, this
    occurred hours before the time CPS Energy had promised to have the CT5 unit ready to deploy,
    and CPS Energy therefore had sufficient time to take additional actions to ensure that it had a
    technician available to address potential problems with the CT5, yet it waited several hours before
    it called in additional staff, and effectively did so at a time when it was too late to avoid the adverse
    effect of the CT5’s failure to deploy.
    Whether CPS Energy Exercised Due Diligence
    30
    These same factors are relevant in determining whether the second affirmative defense set
    forth in subsection (h) of the WMO Rule would apply, i.e., whether CPS Energy “exercised due
    diligence to prevent the excluded act or practice.” 16 TEX. ADMIN. CODE § 25.503(h). Thus, in
    determining whether CPS Energy exercised due diligence to prevent the ERCOT protocol
    violation, the PUC was entitled to consider not only whether CPS Energy took reasonable steps to
    prepare its equipment for the cold weather event, but also whether it took reasonable steps to
    ensure that its plant was adequately staffed for that event. Once again, it is significant to
    remember that CPS Energy had voluntarily promised to provide NSRS services to ERCOT at a
    specific time on the morning of February 2, during an extreme cold weather event, and it was
    therefore incumbent upon CPS Energy to use due diligence to ensure that it would have an
    adequate staff to meet its obligations, and thereby avoid an ERCOT protocol violation.
    In fact, even under normal operating conditions, common sense dictates that market
    participants, and utility providers in particular, must exercise due diligence in ensuring not only
    that their equipment is in sound mechanical condition, but that they have adequately staffed their
    plants to ensure that they are able to comply with the ERCOT protocols so as to avoid WMO Rule
    violations. Utility providers, such as CPS Energy, are subject on a daily basis to numerous
    ERCOT protocols that require them to produce electricity at a certain volume, and market
    participants are aware that they may suffer penalties for overproduction or underproduction at any
    given time. Under CPS Energy’s approach, if a utility provider chose to understaff its plant,
    knowing that this could possibly lead to a complete or partial shutdown of its facilities, the
    provider would be able to escape liability for any consequent ERCOT violation by simply arguing
    that it maintained its equipment in sound condition, without being held accountable for its lack of
    31
    staffing.
    Similarly, there can be no doubt that a QSE in particular must exercise due diligence in not
    only maintaining its equipment, but also in staffing its plant to ensure that it will be able to produce
    NSRS services to ERCOT at a time when promised, if it wishes to avoid an ERCOT protocol
    violation. In this regard, CPS Energy’s obligation to ERCOT was not simply to have an operator
    initiate a startup process when requested by ERCOT. Instead, as discussed in more detail below,
    its duties were many and continuing in nature. Under the express terms of the ERCOT protocol,
    CPS Energy was required to initiate startup within a certain timeframe; ensure that its generator
    reached the LSL level within a certain timeframe; to ensure that its generator started producing
    electricity within a certain time; and to continue to produce electricity for a certain time.
    Therefore, CPS Energy was obligated to have sufficient staff on hand throughout this entire
    process to ensure that it would be able to meet its obligations to ERCOT.
    Further, what constitutes an adequate staff on any given occasion will vary depending on
    the circumstances, and will require the PUC to make a factual determination on a case-by-case
    basis whether due diligence was exercised. At one extreme, there may be some cases where the
    lack of due diligence is obvious, and other cases where the adequate exercise of due diligence is
    unquestioned. In most enforcement cases, however, the facts will not be so clear. In those cases,
    if the market participant desires to excuse its performance, it will be required to present evidence
    that it exercised due diligence in an attempt to meet its obligations.
    In a case involving normal operating conditions, this standard might be fairly low.
    However, the present case involved anything but “normal” operating conditions, and CPS Energy
    was aware days in advance that it would be facing an unprecedented severe weather event that
    32
    called for unique and unusual preparations. As such, we conclude there was substantial evidence
    from which the PUC could have concluded that, in light of the unique facts of this case, CPS
    Energy did not adequately staff its plant to ensure that it would be able to meet its obligations to
    ERCOT.
    CPS Energy, however, argues that allowing the PUC to determine whether it had adequate
    staffing levels at any given time will allow the PUC to “second-guess” a market participant’s
    decision regarding how to staff its plant; will allow the PUC to use “hindsight” in accusing a
    market participant of not having an adequate staff; and will otherwise require market participants
    to engage in “clairvoyance” in trying to anticipate what the PUC might deem to be adequate
    staffing levels on any given occasion. We disagree, and instead conclude that allowing the PUC
    to make this type of determination was within its authority.
    The Legislature expressly gave the PUC the authority in the WMO Rule to determine
    whether a market participant’s conduct was excused based on a due diligence defense, and
    therefore gave the PUC the right to consider all relevant factors in making this determination.
    Further, in order to protect a market participant’s rights, the Legislature gave market participants
    the right to a hearing on this issue, at which the participant is entitled to present evidence whether
    it exercised due diligence, whether its actions were reasonable, and whether its actions met
    industry standards.
    We note that CPS Energy does not contest the PUC’s right in conducting a due diligence
    analysis to consider whether a market participant was negligent in maintaining its equipment, yet it
    appears to believe that allowing the PUC to determine whether it had adequate staffing will
    somehow pose a greater danger that the PUC will act without reference to guiding principles or
    33
    that it will require market participants to have to guess at what the PUC expects of it. However,
    we see no distinction between allowing the PUC to make these two types of determinations, nor do
    we believe that it requires clairvoyance by market participants to know they are required to use
    diligence not only in maintaining their equipment but also in staffing their plants as well. As the
    Austin Court recognized, the WMO Rule makes clear what is expected of a market participant, and
    the “rule does not require clairvoyance as to whether an action will impact price, reliability, or
    accounting – only diligence.” TXU Generation Co., 
    L.P., 165 S.W.3d at 840
    .
    For this same reason, we reject CPS Energy’s contention that the PUC’s interpretation of
    the WMO Rule imposed a “strict liability” standard on market participants that allows the PUC to
    find a violation virtually any time it has a mechanical failure, whether foreseeable or not. Instead,
    as set forth above, in any given case, the PUC will be guided in its decision-making process by the
    principles set forth in the WMO Rule, including the affirmative due-diligence defense provisions
    found in subsection (h) of the Rule, as well as the excuse provisions found in subsection (f) of the
    Rule, to which we now turn our attention. Issue One is overruled.
    Issue Two: Whether the Equipment Failure was Beyond
    CPS Energy’s Reasonable Control
    The primary focus of the parties’ argument in the proceedings below, as well as on appeal,
    is whether CPS Energy was excused from complying with the ERCOT protocol to have its CT5
    generator online in a timely manner under subsection (f)(2)(c) of the WMO Rule, which provides,
    in part, that a market participant may be excused for non-compliance “due to . . . equipment failure
    beyond the reasonable control of the market participant[.]”             16 TEX. ADMIN. CODE §
    25.503(f)(2)(C). In contending that the PUC erred in concluding that it was not excused under
    this provision, CPS Energy raises two fundamental challenges to the PUC’s decision, contending
    34
    that the PUC erroneously applied the Rule when it adopted an “unreasonable interpretation” of this
    provision, and that the PUC’s decision was not supported by substantial evidence.
    Burden of Proof to Establish an Excuse under the WMO Rule
    Initially, we note that the PUC shoulders the initial burden to establish that a market
    participant has violated a WMO Rule; however, once the PUC has met that initial burden, the
    WMO Rule, by its plain language, provides that the burden then shifts to the market participant to
    establish an excuse under subsection (f) of the Rule: “A market participant who does not comply
    with a Protocol requirement or official interpretation of a requirement, or honor a formal
    commitment to ERCOT, has the burden to demonstrate, in any commission proceeding in which
    the failure to comply is raised, why it cannot comply with the Protocol requirement or official
    interpretation of the requirement, or honor the commitment.”              16 TEX. ADMIN. CODE §
    25.503(f)(4). Further, we note that the WMO Rule also places the burden of proof on the market
    participant to establish the affirmative defenses set forth in subsection (h) of the Rule, stating that:
    “A market entity claiming an exclusion or defense under this subsection, or any other type of
    affirmative defense, has the burden of proof to establish all of the elements of such exclusion or
    defense.” 
    Id. at §
    25.503(h).
    The PUC’s Application of the WMO Rule
    CPS Energy correctly points out that the undisputed evidence established that the ERCOT
    protocol violation in this case initially resulted from equipment failure, in the form of a frozen
    damper fan that failed to open during the Braunig CT5’s start-up process. CPS Energy contends
    that it further presented undisputed evidence to establish that the equipment failure was beyond its
    reasonable control, in accordance with the excuse language set forth in subsection (f)(2)(C) of the
    35
    WMO Rule, and that the PUC erred in concluding otherwise.
    CPS Energy’s initial argument centers on its belief that the PUC did not apply the correct
    legal standard for determining whether the equipment failure was within CPS Energy’s reasonable
    control, contending that this is an “unambiguous, well-defined, objective” legal standard that
    requires a court to find both that: (1) the failure itself was caused by the party’s own negligence;
    and (2) that the failure was foreseeable. It contends that the equipment failure in this case was
    neither caused by its own negligence nor was it foreseeable, and concludes therefore that the PUC
    applied the WMO Rule in an unreasonable or arbitrary and capricious manner. We disagree with
    CPS Energy’s interpretation of the Rule.
    Initially, CPS Energy cites a line of cases for the proposition that one of the primary factors
    in determining whether an event is beyond a person’s reasonable control is whether the party “by
    its own negligence, affirmatively caused the condition that prevented performance.”8 Most of the
    cases cited by CPS Energy, however, involve situations in which a court was called upon to
    interpret a contract containing a “force majeure” clause, which excused the party when its
    performance was prevented by a force majeure event, i.e., an act that was outside the party’s
    “reasonable control.” In most of those cases, the party’s own negligence was the cause of its
    8
    See, e.g., Sun Operating Ltd. P’ship v. Holt, 
    984 S.W.2d 277
    , 288, n.4 (Tex.App. – Amarillo 1998, pet. denied) (in
    interpreting “force majeure” clause in party’s contract, court held that if a party’s delay was due to its negligence, it
    could not be viewed as resulting from a “circumstance within its reasonable control” and therefore could not be
    considered a “force majeure event”); Hydrocarbon Mgmt., Inc. v. Tracker Exploration, Inc., 
    861 S.W.2d 427
    , 435
    (Tex.App. – Amarillo 1993, no writ) (party could not invoke the “force majeure clause” in a contract, where it was
    unable to operate a well in compliance with the terms of a lease because the Texas Railroad Commission shut down its
    operations after its multiple failures to comply with the Commission’s orders, rendering the non-compliance to be
    within its “reasonable control”); Moore v. Jet Stream Investments, Ltd., 
    261 S.W.3d 412
    , 420 (Tex.App. – Texarkana
    2008, pet. denied) (lessee who was required to operate an oil and gas lease could not rely on the force majeure clause
    in the parties’ contract, where the Railroad Commission shut down its operations for failure to comply with the
    Commission’s financial assurance regulations). see also Seamless Floors by Ford, Inc. v. Value Line Homes, Inc., 
    438 S.W.2d 598
    , 602-03 (Tex.Civ.App. – Fort Worth 1969, writ ref’d n.r.e.) (in interpreting a contract that placed liability
    on contractor for acts of its own negligence, the court noted that the contractor would only be liable for “negligent acts
    or omissions which would be within its reasonable control”).
    36
    inability to perform the contract, and therefore, it was held that the party’s nonperformance was
    not caused by a “force majeure event” that was outside the party’s reasonable control. See e.g.,
    Hydrocarbon Mgmt., Inc. v. Tracker Exploration, Inc., 
    861 S.W.2d 427
    , 435 (Tex.App. – Amarillo
    1993, no writ) (party could not invoke the “force majeure clause” in a contract, where it was
    unable to operate a well in compliance with the terms of a lease because the Texas Railroad
    Commission had shut down its operations after its multiple failures to comply with the
    Commission’s orders, rendering the non-compliance to be within the party’s “reasonable
    control”). CPS Energy is correct that neither the ALJ not the PUC believed that CPS Energy was
    negligent in causing the initial equipment failure due to any failure on its part in maintaining or
    preparing the equipment for the cold weather event. As CPS Energy points out, the ALJ
    expressly found, and the PUC agreed, that CPS Energy had adequately maintained its equipment,
    that it took all necessary precautions in accordance with industry standards to winterize its
    equipment, and that it generally took steps to “prevent and troubleshoot equipment failures known
    to occur in winter weather conditions.”
    CPS Energy appears to believe that its duties stopped there, and that the PUC was not
    entitled to take into consideration what steps it took once its Braunig plant began experiencing
    significant freeze issues and consequent startup failures starting the night of February 1. Yet, it
    appears that CPS Energy could have taken additional steps at that time to ensure the timely
    deployment of is Braunig units the next morning. For example, as Graham pointed out in his
    testimony, CPS Energy could have called in additional staff once these freeze issues began in order
    to ensure that it had sufficient staff to prevent and address potential startup problems with the
    Braunig CT units the next morning. Further, CPS Energy overlooks that once the entire Braunig
    37
    plant began experiencing freeze problems, it could have assigned one of its operators or
    technicians to inspect the CT units before the anticipated ERCOT instruction to deploy was given,
    which could have prevented the startup failure in the first place. If an operator or technician had
    inspected the unit before the anticipated ERCOT instruction was given, it is likely that the frozen
    damper would have been discovered, and the problem could have been easily addressed by
    knocking the ice off of it as Warnke did hours later, thereby preventing any ERCOT violation.
    Similarly, CPS Energy could have required its staff to start up the CT units earlier in the morning
    of February 2, prior to the anticipated ERCOT deployment instruction, to determine if the units
    were operational, which in turn, would have given staff time to troubleshoot any problems prior to
    the critical moment when ERCOT gave its deployment instruction. In light of the fact that the
    entire Braunig plant site, along with CPS Energy’s other plant sites in the area, were experiencing
    significant freeze issues and multiple startup failures hours before the anticipated ERCOT
    deployment instruction was given, it would not have been unreasonable for the PUC to conclude
    that CPS Energy was required to have adequate staff on hand to ensure a timely deployment and to
    avoid startup failures at the critical time when NSRS energy was needed to balance the grid.
    Moreover, CPS Energy also asks us to overlook the duties that it owed to ERCOT after the
    startup failure occurred, and it appears to believe that the issue of whether it had adequate staff on
    hand to repair the equipment after it failed was irrelevant to the question of whether an ERCOT
    protocol violation occurred. In particular, CPS Energy contends that there is “no statute, rule,
    protocol, or standard regarding the efforts that a market participant must make and resources that
    must be available to repair an equipment failure once it has occurred.” We disagree.
    It is important to recognize the continuing nature of CPS Energy’s duties on the morning of
    38
    February 2, 2011. CPS Energy pledged to stand ready to provide NSRS services to ERCOT upon
    its instruction from 4 to 5 a.m. that morning. It further pledged to have the NSRS services
    available to ERCOT within 30 minutes of its deployment instructions. And, most importantly, it
    pledged to provide the NSRS services to ERCOT for an hour after deployment.
    Although CPS Energy may have been entitled to an excuse for compliance with the
    ERCOT protocol timelines when the equipment failure initially occurred, the language in
    subsection (f) clearly states that the excuse does not last forever. Instead, it states that a “market
    participant is excused under this subparagraph only for so long as the condition continues.” 16
    TEX. ADMIN. CODE § 25.503(f)(2)(C).          This raises two possibilities:     (1) that the excuse
    continues for as long as the “equipment failure” lasts; or (2) the excuse continues for as long as the
    “equipment failure beyond the reasonable control of the market participant[.]” We believe that
    the latter possibility is the only reasonable interpretation of this provision. By its very terms, the
    “condition” that provides the excuse in the WMO Rule is not “equipment failure” standing alone,
    but is instead “equipment failure beyond the reasonable control of the market participant[.]” 
    Id. Any contrary
    interpretation would lead to the untenable position of allowing a market participant
    to simply throw up its hands and absolve itself of any blame once an initial equipment failure
    occurs, with no requirement that it make reasonable efforts to address the failure. Given the
    Legislature’s recognition of the crucial importance of keeping the grid in balance and electricity
    flowing to customers in a reliable manner, we cannot conclude this would be the Rule’s intent.
    We therefore conclude that CPS Energy was allowed to rely on the equipment failure as an excuse
    for its performance under subsection (f) only for as long is the equipment failure was “beyond its
    reasonable control.”
    39
    In turn, we conclude that the PUC was allowed to make the factual determination of
    precisely when the equipment failure was no longer beyond CPS Energy’s “reasonable control,”
    and what steps CPS Energy was required to take to address that failure at that point in time. The
    question of whether CPS Energy adequately staffed its plant to be able to address the equipment
    failure after it initially occurred was a pivotal issue in the PUC’s analysis. And, whether CPS
    Energy had adequate staff on hand to address the failure once it occurred was clearly a factor
    within CPS Energy’s “reasonable control.”
    The “Foreseeability” Factor
    CPS Energy, however, argues that we should include a “foreseeability” analysis in
    determining whether the equipment failure was “beyond its reasonable control.” In particular,
    CPS Energy contends that it was unreasonable for the PUC to determine that it did not properly
    staff its plant in anticipation of an “unforeseeable” event, such as the frozen damper fan, which
    occurred on the morning of February 2. According to CPS Energy, it was unreasonable and
    illogical for the PUC to conclude that it had any reasonable control over an unforeseeable event of
    this nature, and that it should have staffed its plant in advance based on an event that had not even
    occurred. Once again, CPS Energy contends that the PUC’s decision, if allowed to stand, will
    give the PUC the authority to second guess staffing decisions after the fact, and force market
    participants to engage in “clairvoyance” in trying to anticipate staffing needs in advance of
    virtually all unforeseeable and unanticipated events. According to CPS Energy, this will require
    market participants to adhere to an unobtainable standard of perfection and will essentially render
    all of the excuses set forth in subsection (f) meaningless. CPS Energy therefore contends that the
    PUC’s interpretation of the WMO Rule was not only unreasonable, but arbitrary and capricious,
    40
    and made without reference to any guiding principles.
    We disagree with CPS Energy’s “foreseeability” analysis for the same reasons we
    disagreed with its argument that it could not have reasonably anticipated that its actions in failing
    to adequately staff its plant would adversely affect the ERCOT electric network. As set forth
    above, the evidence presented at the SOAH hearing indicated that the February cold weather event
    was highly anticipated for days in advance. Further, all witnesses agreed that it was foreseeable
    that the cold weather event could lead to equipment failures at the Braunig plant site, and that
    adequate staffing was therefore needed to prevent and address those possible failures. And, more
    importantly, CPS Energy knew that it had a continuing duty to take all reasonable steps to ensure
    that the Braunig CT5 was ready to deploy on the morning of February 2, which included the duty
    not only to ensure that the unit was mechanically sound, but also to ensure that it had adequate staff
    to make certain that it would start up properly and continue running for the required period of time.
    As CPS Energy does not deny that staffing its plant at an adequate level was a factor within
    its reasonable control, we believe that the PUC properly considered this factor in determining
    whether the equipment failure—the CT5’s failure to deploy the morning of February 2—was
    beyond CPS Energy’s reasonable control under the excuse provisions of subsection (f).
    The PUC’s Decision was based on Substantial Evidence
    As set forth above, the PUC’s decision that CPS Energy was not excused from compliance
    with the ERCOT protocol under subsection (f) was based on two factors: (1) CPS Energy failed
    to carry its burden to prove that it provided “adequate staffing” at the Braunig plant site on the
    morning of February 2, in “light of its choice to offer NSRS from unproven units;” and (2) CPS
    Energy had several opportunities on the morning in question to “call in additional staffing . . . to
    41
    ensure any start-up failures could be promptly addressed” but failed to do so.
    In contending that this conclusion was not supported by substantial evidence, CPS Energy
    points out that it did in fact provide additional staffing at the plant, adding six additional operators
    and two technicians, which, at the time, it believed was sufficient to address any foreseeable
    problems the plant might encounter. CPS Energy further contends that the record is barren of any
    evidence demonstrating that this was not an “adequate” staffing level, and that the PUC failed to
    present any evidence to demonstrate that having more staff members on hand would have avoided
    the ERCOT violation.
    The PUC did not have the burden of proof on this point, however. Instead, it was CPS
    Energy’s burden to establish an excuse and demonstrate that it took all reasonable steps within its
    control to avoid the ERCOT violation, and in particular to adequately staff its plant to ensure that
    the CT5 would operate as required. As the ALJ found, CPS Energy failed to meet this burden of
    proof because it failed to present any evidence to establish that it staffed its plant in accordance
    with industry standards during the cold weather event. Further, the PUC was entitled to rely on
    the testimony of the PUC’s witness, Greg Graham, who expressed his opinion that, in light of the
    potential for problems that could have occurred during the cold weather event and did in fact occur
    on the morning when CPS Energy had promised to provide NSRS services to ERCOT, CPS
    Energy should have had more staff available to troubleshoot and investigate start-up problems
    CPS Energy encountered on both February 1 and 2. Further, as Graham also pointed out, when
    the entire plant site started to encounter significant problems hours before it was required to deploy
    the Braunig CT5, CPS Energy knew that its two available technicians were assigned to other tasks,
    and that if problems occurred with the CT5, there would be no technicians to assist with the CT5’s
    42
    deployment.
    Further, regardless of the adequacy of its staffing levels, the record raises a significant
    question whether CPS Energy took all of the steps that were within its “reasonable control” to
    prevent the startup failure in the first instance, and to address that failure in a timely manner after it
    occurred. As set forth above, it is not unreasonable to conclude that CPS Energy should have
    required one of its employees to inspect or test the CT units before the anticipated ERCOT
    instruction was given, particularly in light of the significant freeze issues that had been occurring
    several hours beforehand and in light of its knowledge that it would be required to provide NSRS
    power to ERCOT at a specific time the morning of February 2. Taking such actions could have
    detected the frozen damper fan in advance of the ERCOT deployment instruction, and thereby
    avoided the protocol violation in the first instance.
    Moreover, we find it significant that CPS Energy’s own witnesses testified that when the
    CT5 first failed to deploy, the control room operator received an alarm indicating that a tempering
    air fan discharge damper had failed to open, thereby alerting the operator to the particular problem.
    As CPS Energy was on notice there problem with the damper fan, it is unclear why CPS Energy
    did not direct one of the eight operators already at the plant to physically walk to the unit to inspect
    the fan. This is particularly curious, as the record indicated that at least three of these operators
    were expressly tasked with the job of walking around the plant site throughout the cold weather
    event to inspect equipment for freeze damage. Having been alerted to the problem with the fan
    for over an hour before Warnke arrived at the plant and knocked the ice off the damper, it is
    unclear why CPS admittedly did not send one of these operators to the unit earlier to view the fan
    to determine if it was perhaps suffering from freeze damage, which was a distinct possibility in
    43
    light of the weather conditions.
    We also find it significant that although CPS Energy claims that the two technicians at the
    plant site were too busy with other tasks to investigate the problems with the CT5, Warnke
    testified that when he first arrived at the plant, the two technicians took the time to speak with him
    about the problems with the CT5 before Warnke walked out to the unit. In sum, at best, the record
    is in conflict regarding whether those technicians were unavailable to inspect the CT5 unit to
    determine if the damper fan was frozen.
    We therefore conclude that the record adequately demonstrates that at several points in
    time during the morning of February 2, CPS Energy had various options at its disposal, which were
    within its reasonable control, to prevent and address the equipment failure, yet it failed to exercise
    any of those options. Because an equipment failure is excused only for as long as it is beyond a
    market participant’s control, we conclude that any excuse CPS Energy could have initially relied
    upon when the equipment first failed expired long before Warnke arrived at the scene to address
    the problem over an hour after CPS was alerted to the problem.
    Accordingly, we conclude there was substantial evidence to support the PUC’s decision
    that CPS Energy failed to carry its burden of proving that the equipment failure on the morning of
    February 2, 2011 was “beyond its reasonable control,” and that the PUC therefore properly
    determined that CPS Energy was not excused from the ERCOT protocol under subsection (f) of
    the WMO Rule on that basis. Issue Two is overruled.
    Issue Three: Whether CPS Energy was Excused from Complying with the ERCOT
    Protocols Based on the Health, Safety, and Environment Excuses in the WMO Rule
    CPS Energy also relied on two other excuses found in subsection (f)(2)(C) of the WMO
    Rule. First, it relied on the provision in the Rule that allows a market participant to be excused
    44
    from compliance with an ERCOT protocol “if compliance would jeopardize public health and
    safety or the reliability of the ERCOT transmission grid, or create risk of bodily harm or damage to
    the equipment[.]” 16 TEX. ADMIN. CODE § 25.503(f)(2)(C). Second, it relied on the related
    provision that a market participant is excused from compliance with an ERCOT protocol if
    “compliance would be inconsistent with facility licensing, environmental, or legal
    requirements[.]” 
    Id. CPS Energy
    contends that it presented undisputed evidence at the hearing that the events
    that occurred on the morning of February 2 fit within both of these excuses. In particular, it
    contends that it presented undisputed evidence that the Braunig CT5 unit failed to deploy on the
    morning of February 2 because the damper fan would not open, and that if it had attempted to
    operate the unit without the damper fan, this would have created a serious risk of an explosion,
    posing serious health and safety issues, destruction of the unit, and possible air pollution issues,
    which would have, in turn, caused CPS Energy to be in violation of air quality standards or its
    TCEQ-issued air permits.
    The PUC, however, expressly concluded that CPS Energy could not rely on these
    exceptions, primarily because it found that there was no danger of any of these risks occurring,
    since the unit contained a built-in safety system ensuring that the unit would automatically shut
    down when it detected a safety risk, just as it did on the morning of February 2. CPS Energy, on
    the other hand, finds it irrelevant that the unit had a built-in safety system, pointing out that the
    evidence established that a CPS operator could have overridden the control system, and forced the
    unit to operate without the damper fan. CPS Energy points out that the record established that if
    the operator had done so, and the unit had started without an operating damper fan, this would have
    45
    created the very risk to public safety and the environment that subsection (f) sought to avoid.
    According to CPS Energy, the PUC’s “treatment of this undisputed evidence turns the WMO Rule
    on its head,” and in effect, would require a market participant to comply with an ERCOT protocol
    regardless of the risk it might pose, thereby essentially eviscerating the entire excuse provisions
    contained in subsection (f).
    There is nothing in the record, however, to indicate that the control room operator made
    any attempt to override the safety system, or that the ERCOT operator ever suggested that he do
    so. In reality, no safety concerns existed at the time ERCOT gave its instruction to deploy the
    unit, or at any time thereafter when the operator was attempted to start the system. Further,
    overriding the safety system was not CPS Energy’s only option to avoid the protocol violation. It
    had other means at its disposal to comply with the ERCOT protocol. CPS Energy staff could have
    tested or inspected the CT5 unit prior to the anticipated deployment time, which would have given
    it sufficient time to address the problem with the frozen damper prior to the anticipated ERCOT
    deployment instruction. Moreover, once the control room operator received the alarm indicating
    that the damper fan had failed to open, CPS Energy was on notice it needed to take all reasonable
    steps to determine the cause of the failure. We find it significant, as the PUC did, that due to
    inadequate staffing, CPS Energy was unable or unwilling to take any steps to determine the cause
    of that failure until over an hour later when Warnke finally arrived at the plant site to inspect the
    fan.
    CPS Energy also objects that in reaching its conclusion, the ALJ interpreted the WMO
    Rule to imply an “element” requiring a market participant “to have taken all reasonable steps” to
    avoid a WMO Rule violation before the market participant is entitled to rely on the excuse
    46
    provisions set forth in that Rule. In particular, CPS Energy points out that the ALJ found that
    CPS Energy had not taken all reasonable steps to avoid the ERCOT protocol violation due to its
    failure to adequately staff its plant in anticipation of the cold weather event, and therefore
    concluded that CPS Energy was not allowed to rely on the subsection (f) excuses.
    CPS Energy contends this was an erroneous interpretation and “unsound” application of
    the WMO Rule, contrary to the Rule’s plain language. According to CPS Energy, the plain
    language of the Rule makes it clear that the “only relevant factual determination” to be made in
    applying this excuse provision is whether a market participant’s compliance with the ERCOT
    instruction would have posed one of the enumerated dangers to safety, bodily harm, and
    equipment. In CPS Energy’s opinion, the PUC’s decision, in allegedly adding a new element to
    the excuse provision in the Rule, was improper and exceeded its authority. CPS Energy also
    contends that this was a new or novel interpretation of the Rule, and that CPS Energy was therefore
    not on notice of this interpretation prior to the enforcement proceeding, contending that it was once
    again thereby deprived of “fair notice” of the type of conduct that was expected of it in this
    situation. We disagree.
    First, when a rule is ambiguous or otherwise leaves room for policy determinations, we
    defer to the agency’s interpretation if the interpretation is reasonable. CenterPoint Energy
    Houston Elec., 
    LLC, 408 S.W.3d at 916
    -17 (citing 
    Rodriguez, 997 S.W.2d at 254
    –55); see also
    City of El Paso v. Pub. Util. Comm’n of 
    Texas, 344 S.W.3d at 618-19
    . Second, when an
    administrative rule or statute is unambiguous, it must be interpreted based on its plain language,
    but not if such an interpretation would produce an absurd result. Fleming Foods of Tex., 
    Inc., 6 S.W.3d at 284
    ; 
    State, 246 S.W.3d at 332
    .
    47
    In the present case, regardless of whether the WMO Rule is ambiguous, we believe there is
    room for the PUC to make the policy determination that a market participant is obligated to
    exercise due diligence in meeting its duty to comply with an ERCOT protocol before it should be
    allowed to raise an excuse from compliance based on health, safety, or environmental concerns.
    As the PUC points out, to interpret the WMO Rule otherwise would lead to the absurd result that a
    market participant could seek to excuse a failure to comply with an ERCOT protocol or an ERCOT
    instruction to deliver power, based on a health or safety risk, even if that very risk was caused by
    the market provider’s own negligence in not maintaining its equipment or in failing to adequately
    staff its plant. As the PUC points out, the excuses set forth in the WMO Rule do not give market
    providers a “free pass” to act with negligence in violating ERCOT protocols or instructions, and to
    later claim an excuse of this nature; instead the market participant must act with due diligence to
    avoid the potential violation in the first place.
    Contrary to CPS Energy’s claim, this interpretation is not unreasonable, and instead
    promotes the very goals the Legislature sought to achieve in adopting the regulatory and
    enforcement scheme set forth in PURA, i.e., to ensure the “reliability and adequacy of the regional
    electrical network,” and to ensure that market participants comply with ERCOT protocols in
    furtherance of that goal.      TEX. UTIL. CODE ANN. §§ 39.151(a, c), 39.1515(a, c).            Any
    interpretation to the contrary would essentially allow a market participant to avoid an enforcement
    proceeding regardless of whether its negligent conduct adversely affected the reliability of the
    grid, and would be contrary to the legislative intent of ensuring the grid’s reliability. Therefore,
    we conclude the PUC’s interpretation of its own rule was reasonable.
    Moreover, we disagree with CPS Energy’s contention that the PUC adopted a new or novel
    48
    interpretation of the WMO Rule when it read an element of “diligence” into the Rule’s excuse
    provisions. Instead, as pointed out above, the Austin Court spoke on this issue over ten years ago
    in TXU Generation, when it advised market participants that in the final analysis, the WMO Rule
    requires market participants to be guided at all times by the concept of “diligence.” TXU
    
    Generation, 165 S.W.3d at 840
    .
    CPS Energy seeks to rely on the health, safety, and environmental excuses set forth in the
    WMO Rule on the ground its Braunig CT5 Unit failed to deploy due to a safety issue related to the
    damper fan’s failure to open, which could have caused the unit to explode or otherwise be
    damaged if the unit was operated under those conditions. However, this safety issue could have
    been avoided if CPS Energy had exercised due diligence prior to the initial startup by having its
    staff test or inspect the unit before the anticipated time the ERCOT deployment instruction was
    given. Further, even if the safety excuse was valid when the initial startup sequence was first
    interrupted by the safety feature in the unit, CPS Energy’s duty to ERCOT did not end at that point.
    Instead, its duty to ensure that the CT5 unit timely deployed was continuing in nature. Thus, once
    the control room operator received the signal that the unit had shut down because the damper fan
    had failed to open, alerting it that a safety issue existed, it was incumbent upon CPS Energy to
    exercise due diligence to address that problem as quickly as possible, so that it could, in turn,
    comply with the ERCOT instruction to deploy the unit in a timely manner.
    Requiring CPS Energy to take reasonable steps not only to prevent but also to address
    safety issues once they arise, and to do so as quickly and as diligently as possible, is both
    reasonable and consistent with the plain language of the WMO Rule, which allows the market
    participant to rely on an excuse only for as long as the “condition continues.” 16 TEX. ADMIN.
    49
    CODE § 25.503 (f)(2)(C). This language is a clear warning to market participants that they must
    exercise due diligence to detect and correct any underlying problems that may be causing an
    excuse—in this case, the damper fan’s failure to open—as quickly as possible to ensure that they
    are able to meet their ERCOT obligations within a reasonable timeframe. It would lead to an
    absurd result if the WMO Rule were interpreted otherwise, as market participants would then be
    able to rely on an excuse for as long as they might chose, without taking any steps to come into
    compliance with the Rule within a reasonable timeframe.
    Yet, CPS Energy essentially did just that the morning of February 2, waiting for over an
    hour to take any reasonable steps to investigate the cause of the damper fan’s failure to open, either
    because it did not have adequate staff to do so, or because it chose not to assign its available staff to
    perform that task. Either way, at that point, the PUC was entitled to make the determination that
    CPS Energy was no longer entitled to rely on any of the excuse provisions contained in the WMO
    Rule due to its own lack of due diligence.
    Accordingly, we conclude that the PUC did not erroneously interpret the WMO Rule, and
    that it properly rejected CPS Energy’s claim that it was excused from compliance with the ERCOT
    protocol for any health, safety, or environmental concerns. Issue Three is overruled.
    Issue Four: Whether CPS Energy was Excused from Complying with the ERCOT
    Protocols Based on the Exemptions found in the Protocols themselves
    In its last issue, CPS Energy claims that it should be excused from complying with the
    ERCOT protocols based on the exemptions found in the protocols themselves, which CPS Energy
    refers to as “trump” provisions. CPS Energy contends that these exemptions are “safe harbor”
    provisions, and that in effect, if a market participant comes within one of these provisions, it
    cannot be said to have violated another separate ERCOT protocol. While we agree that these
    50
    protocols could, if applicable, exempt a market participant from compliance with another ERCOT
    protocol or instruction, we do not agree that these protocols provide CPS Energy with any relief in
    this case.
    The Operating Limits Protocol
    First, CPS Energy cites to what it refers to as the “operating limits” protocol:
    ERCOT shall consider all equipment operating limits when issuing Dispatch
    Instructions. Except as stated in Section 6.5.9 Emergency Operations, if a Dispatch
    Instruction conflicts with a restriction that may be placed on equipment from time to
    time by a TSP, a DSP, or a Generation Resource’s QSE to protect the integrity of
    equipment, ERCOT shall honor the restriction.
    ERCOT Protocol 6.5.3.(1). CPS Energy believes that its actions on February 2 came within this
    “exemption,” because the CT5 unit failed to deploy due to a “restriction” that was placed on the
    unit—apparently referring to the automated safety system that caused the unit to automatically
    shut down on the morning of February 2, when it detected a safety issue. The PUC, on the other
    hand, contends that this protocol is inapplicable to the facts of this case. We agree with the PUC.
    We note that this particular subsection comes under the Protocol Section, entitled,
    “Equipment Operating Ratings and Limits.” ERCOT Protocol 6.5.3. Two subsections are
    contained within this protocol. The first, which CPS Energy cites, deals with “equipment
    operating limits” and relates to “restrictions” that the market participant itself has placed on its
    own equipment to ensure the safety of its equipment. In turn, the second subsection in the
    protocol provides a list of these various limits, which relate to a generating unit’s operating
    capabilities.9 ERCOT Protocol 6.5.3.(2). The second subsection specifically provides that a
    9
    In particular, this second protocol provides that: “Each TSP shall notify ERCOT of any limitations on the TSP’s
    system that may affect ERCOT Dispatch Instructions. ERCOT shall continuously maintain a posting on the MIS
    Secure Area of any TSP limitations that may affect Dispatch Instructions. Examples of such limitations may include:
    temporary changes to transmission or transformer ratings, temporary changes to range of automatic tap position
    51
    market participant must “notify ERCOT of any limitations on the [participant’s] system that may
    affect ERCOT Dispatch Instructions,” and then requires ERCOT to “continuously maintain a
    posting on the MIS Secure Area of any . . . limitations that may affect Dispatch Instructions.” 
    Id. As the
    PUC points out, these operating protocols are not applicable to the present situation.
    When the CT5 unit failed to deploy, it was not because CPS Energy was addressing any issues
    involving the type of “equipment operating limits” contemplated by these protocols. In other
    words, CPS Energy had not placed any “restrictions” on its equipment of the type contemplated.
    Further, as required by the protocol itself, CPS Energy did not notify the PUC of any “equipment
    operating limits” described by those protocols. As such, we reject CPS Energy’s claim that it was
    entitled to rely on this protocol to excuse its compliance with the ERCOT instruction on the
    morning of February 2.10
    The Compliance Protocol
    Second, CPS Energy cites to what it refers to as the “compliance” protocol:
    Except as otherwise specified in this Section, each TSP and each QSE shall comply
    fully and promptly with a Dispatch Instruction issued to it, unless in the sole and
    reasonable judgment of the TSP or QSE, such compliance would create an undue
    threat to safety, undue risk of bodily harm or undue damage to equipment, or the
    Dispatch Instruction is otherwise not in compliance with these Protocols.
    ERCOT Protocol 6.5.7.9(1). CPS Energy contends that its actions on February 2 came within the
    clear language of this protocol, because it could not comply with the ERCOT instruction to deploy
    the Braunig CT5 unit due to safety concerns, and because the risk that deploying the unit, without
    capabilities on auto-transformers, fixing or blocking tap changer, changes to no-load tap positions or other limitations
    affecting the delivery of energy across the ERCOT Transmission Grid. Any conflicts that cannot be satisfactorily
    resolved may be brought to ERCOT by any of the affected Entities for investigation and resolution.”
    10
    CPS Energy argues that because Protocol 6.5.3 does not itself contain a notice provision, we should not conclude
    that any such notice was required. However, as noted above, these two protocols are found within the same section
    and must be read together.
    52
    a functioning damper fan, would have caused bodily harm or undue damage to equipment. The
    PUC points out, however, that this protocol by its plain language applies only when the market
    participant makes a decision based on its “sole and reasonable judgment” that compliance with an
    ERCOT instruction would cause a risk of that nature. In the present case, CPS Energy made no
    such judgment to refuse to comply with the ERCOT instructions. Instead, after the CT5 unit had
    automatically shut down when it detected a damper fan malfunction, CPS Energy continued to try
    to deploy the unit, and made two additional failed attempts to start it, with no apparent concern that
    it might need to investigate any safety issues before doing so. As such, it cannot be said that CPS
    Energy used its “sole and reasonable judgment” not to comply with the ERCOT protocol that
    morning due to any safety concerns.
    More importantly, however, we note that CPS Energy failed to notify ERCOT that it was
    relying on this provision on the morning in question, as required by ERCOT Protocol 6.5.7.9(2),
    which provides:
    If the recipient of a Dispatch Instruction does not comply because in the sole and
    reasonable judgment of the TSP or QSE, such compliance would create an undue
    threat to safety, undue risk of bodily harm, or undue damage to equipment, then the
    TSP or QSE must immediately notify ERCOT and provide the reason for
    non-compliance.
    CPS Energy contends that this notice provision is inapplicable to the compliance protocol,
    apparently believing that it is in an entirely separate and unrelated protocol, and that it would be
    improper to read the two provisions in conjunction. We disagree. Both of these provisions are
    found under the heading “Compliance with Dispatch Instructions,” and are simply subsections of
    ERCOT Protocol 6.5.7.9. The first subsection provides the exemption itself, and the second
    subsection, mirroring the exemption language used in the first subsection, expressly requires
    53
    market participants relying on the first subsection to provide notice to ERCOT of its intent to do
    so. It is therefore obvious that these two provisions must be read together.
    CPS Energy next contends that even if it were required to provide notice under this
    protocol, it did in fact give sufficient notice to ERCOT during the conversation its control room
    operator had with the ERCOT operator on the morning of February 2, when it first reported the
    unit’s failure to deploy. In particular, CPS Energy points out that its control room operator
    advised the ERCOT operator that the unit was “tripping offline,” and that the reason for the failed
    start was “low tempering pressures.” CPS Energy contends that this should be considered
    sufficient notice that a safety issue existed, and that its operator should not have been required to
    provide the ERCOT operator with a detailed “legalese” account of the failure. CPS Energy
    further contends that requiring a market participant to provide a detailed description of a safety
    issue in order to invoke this protocol is an unreasonable interpretation of the protocol, pointing out
    that fully developed information about a generation unit failure is rarely available in real time, and
    that in an emergency situation, a market participant operator will rarely have the ability to provide
    detailed information about a safety issue to an ERCOT operator on a contemporaneous basis.
    We agree that the ERCOT protocol does not require the market participant to provide a
    highly detailed account of a safety issue during an emergency situation, any more than it requires
    an ERCOT operator to be clairvoyant in attempting to discern whether a market participant is
    attempting to rely on the exemption in the protocol. Instead, what the rule does require, by its
    plain language, is a clear communication from the market participant to ERCOT that it is failing or
    refusing to comply with an ERCOT instruction because it has made a reasonable judgment that
    doing so would create an undue safety threat or risk of harm. As set forth above, CPS Energy did
    54
    not notify ERCOT that it had made any such a judgment because, in point of fact, it had not made
    such a judgment. Instead, the undisputed evidence demonstrated that the CPS Energy control
    room operator agreed with the ERCOT operator to continue trying to start the unit, and expressed
    no concern to the ERCOT operator that doing so might cause any type of safety or health risk.
    These continued attempts to start the unit, before addressing the root cause of the startup failure
    over an hour later, undercuts any contention that CPS Energy believed, in its reasonable judgment,
    that continuing to try to start the unit in compliance with ERCOT instructions would have in fact
    created any undue safety risks.
    Accordingly, we conclude that CPS Energy was not entitled to rely on the provisions of the
    compliance protocol to exempt it from liability for violating the WMO Rule. Issue Four is
    overruled.
    CONCLUSION
    The trial court’s judgment is affirmed.
    STEVEN L. HUGHES, Justice
    November 30, 2016
    Before Rodriguez, J., Hughes, J., and Larsen, J. (Senior Judge)
    Larsen, J. (Senior Judge), sitting by assignment
    55