the Port of Houston Authority of Harris County, Texas v. Zachry Construction Corporation , 2016 Tex. App. LEXIS 13306 ( 2016 )


Menu:
  • Affirmed and Opinion filed December 15, 2016.
    In The
    Fourteenth Court of Appeals
    NO. 14-10-00708-CV
    THE PORT OF HOUSTON AUTHORITY OF HARRIS COUNTY, TEXAS,
    Appellant
    V.
    ZACHRY CONSTRUCTION CORPORATION N/K/A ZACHRY
    INDUSTRIAL, INC., Appellee
    On Appeal from the 151st District Court
    Harris County, Texas
    Trial Court Cause No. 2006-72970
    OPINION ON REMAND
    This contract dispute is before our court for a second time, on remand from
    the Texas Supreme Court. See Port of Houston Auth. of Harris Cty. v. Zachry
    Constr. Corp., 
    377 S.W.3d 841
    , 844 (Tex. App.—Houston [14th Dist.] 2012),
    rev’d, Zachry Constr. Corp. v. Port of Houston Auth of Harris Cty., 
    449 S.W.3d 98
    , 101 (Tex. 2014). Zachry Construction Corporation n/k/a Zachry Industrial,
    Inc. (Zachry) sued the Port of Houston Authority of Harris County, Texas (the
    Port) for breach of contract. Following a three-month jury trial, the trial court
    signed a final judgment awarding Zachry damages of $19,992,697, plus pre- and
    post-judgment interest. On remand from the Texas Supreme Court, numerous
    challenges to the trial court’s judgment remain. We affirm.
    I. Background
    In 2003, the Port solicited bids to construct a wharf at the Bayport Ship
    Channel. The wharf consisted of five sections, each approximately 330 feet in
    length. Zachry’s bid proposed building the wharf “in the dry” by using a U-
    shaped, frozen earthen wall to seal out water from Galveston Bay from the
    construction site. Zachry proposed to freeze the wall by sinking 100–foot pipes
    into the wall and circulating chilled brine through the pipes. Then, Zachry would
    install drilled shafts into the ground, pour a concrete deck on top of the drilled
    shafts and dirt using the ground as the bottom of the concrete form, excavate the
    dirt under the deck, and place revetment to stabilize the slope. After completing
    the wharf, Zachry would breach the freeze wall, flooding the area, and remove the
    remainder of the freeze wall so that ships would be able to dock at the wharf and
    unload their cargo.
    An advantage of working “in the dry” instead of “in the wet” was that fewer
    “NOx” emission credits would be consumed. The Port accepted Zachry’s bid in
    large part because of the environmental benefits of using the freeze wall. On June
    1, 2004, Zachry entered into the Bayport Phase 1A Wharf and Dredging Contract
    (the Contract) with the Port for the construction of a 1,660–foot wharf. The Port
    had concerns about the possible impact of the frozen soil on adjacent structures but
    provided in the Contract that Zachry would be an independent contractor and
    control the means and methods, thus “insulating itself from liability to which it
    2
    would be exposed were it exercising control over Zachry’s work.” Zachry Constr.
    Corp., 449 S.W.3d at 102.
    The Port designated Steve DeWolf as the Chief Engineer for the project.
    The Port additionally hired CH2M Hill as its construction manager; Andy Thiess
    was CH2M Hill’s engineer/construction manager, while Jeff Ely was CH2M Hill’s
    engineer/design manager for this project. Zachry designated Andy Anderson as its
    Project Manager and hired RKK–SoilFreeze Technologies to work on the freeze
    wall. RKK in turn, hired Dan Mageau of GeoEngineers, a geotechnical engineer,
    to design the freeze wall.
    The Contract provided a strict timeline.       Specifically, Zachry was to
    complete construction of the wharf by June 1, 2006. Zachry was also to meet an
    interim deadline of February 1, 2006—Milestone A—by which a portion of the
    wharf would be sufficiently complete to allow delivery of large ship-to-shore
    cranes that were to be shipped from China. The Contract also provided that
    Zachry’s sole remedy for any delay on the project was an extension of time.
    Nine months into the project, the Port realized that it would need longer
    berths to accommodate the ships it expected to service. In March 2005, the Port
    decided to extend the original wharf Zachry was constructing by 332 feet. Zachry
    submitted price quotes for the wharf extension on April 13, May 18, and July 11,
    and described its plan during meetings with, among others, Thiess and Ely.
    Zachry’s proposal was based on using the freeze-wall technology to add this
    additional footage to the wharf. Zachry had Mageau design a frozen cutoff wall, a
    perpendicular wall to the main freeze wall, to split the project into two phases: a
    west side including Area A and an east side, as had been discussed at meetings
    prior to Zachry’s submission of its price quotes. On September 9, Zachry sent the
    frozen cutoff wall design to the Port for “review,” not “approval.” The Port and
    3
    Zachry executed Change Order 4 for the wharf extension on September 27, after
    Zachry had submitted its frozen cutoff wall design to the Port. Change Order 4
    extended the dates for Milestone A to February 15, 2006, and final completion to
    July 15, 2006. Change Order 4 incorporated Zachry’s April 13 proposal as further
    modified by the May 18 and July 11 proposals.
    After entering into Change Order 4, the Port refused to approve Zachry’s
    frozen cutoff wall design and sent Zachry a “revise and resubmit” response (R&R
    response). In this R&R response, the Port noted preliminary indications that the
    design may have an indeterminate effect on up to fourteen shafts and directed
    Zachry either to “present [an] alternative cutoff wall design” or to “present the Port
    of Houston with an alternate means of mitigating risk” to the shafts. Ultimately, in
    late November 2005, after finding no viable alternative to the frozen cutoff wall
    design that would allow it to meet the Contract deadlines, Zachry abandoned the
    frozen cutoff wall and switched to an “in the wet” scenario. Zachry, working in
    the wet, managed to complete the Area A section of the wharf in time to
    accommodate the arrival of the shipment from China.
    In late 2006, Zachry sued the Port for breach of contract, by failing to
    comply with Change Order 4 and section 5.10 of the Contract through the Port’s
    R&R response. As damages, Zachry sought the difference between the cost that
    Zachry would have incurred had it been allowed to complete the wharf “in the dry”
    using the frozen cutoff wall and the actual cost Zachry incurred in completing the
    wharf “in the wet” without the frozen cutoff wall. Zachry also sued the Port for
    withholding liquidated damages for delays in the amount of $2.36 million, and for
    the Port’s withholding of $600,000 as a purported offset for alleged defective
    dredging. The Port filed a counterclaim for attorney’s fees under section 3.10 of
    the Contract, which provided that Zachry was liable for the Port’s attorney’s fees if
    4
    Zachry brought a “claim” against the Port and “d[id] not prevail with respect to
    such claim.” Over two years after suing the Port, Zachry declared the wharf
    complete on January 26, 2009.
    After a three-month trial, the case was submitted to the jury. The jury found
    that the Port had breached the Contract by failing to comply with Change Order 4
    and section 5.10, and found compensatory damages in the amount of $18,602,697
    for the Port’s breach of the Contract.       These damages represented Zachry’s
    increased costs for switching to working “in the wet.” The jury did not find that the
    Port failed to comply with the Contract by withholding $600,000 from the Port’s
    payment on the amounts invoiced by Zachry for defective dredging.
    The trial court instructed the jury that the Port had not complied with the
    Contract by failing to pay Zachry $2.36 million withheld as liquidated damages.
    Thus, the jury needed only to determine whether the Port was entitled to offset; the
    jury found for the Port on an offset defense in the amount of $970,000 for Zachry’s
    defective work on the wharf fenders.
    In its final judgment, the trial court awarded Zachry damages in the amount
    of $19,992,697.00 ($18,602,697.00 plus $2,360,000.00 in liquidated damages, less
    the $970,000.00 offset for the defective fenders), pre-judgment interest of
    $3,451,022.40, post-judgment on the total sum award of $23,443,719.00, and
    taxable costs. The trial court did not award the $600,000.00 withheld for defective
    dredging that the jury refused to award Zachry and did not award attorney’s fees to
    the Port.
    On direct appeal, we held that the no-damages-for-delay provision of the
    Contract barred Zachry’s recovery of delay damages, that Zachry unambiguously
    released its claims to $2.205 million of the liquidated damages withheld, that the
    Port was entitled to the $970,000 found by the jury for the defective wharf fenders,
    5
    and that the Port was entitled to attorney’s fees under the Contract. See Port of
    Houston Auth., 377 S.W.3d at 850–51, 857–58, 861. We reversed the judgment in
    favor of Zachry and rendered judgment for the Port. See id. at 865. However, the
    Supreme Court of Texas reversed this court, holding that (a) the Local Government
    Contract Claims Act waived the Port’s immunity to suit—an issue that this court
    had not reached; (b) the no-damages-for-delay provision of the Contract was void
    and unenforceable as against public policy due to the Port’s arbitrary and
    capricious conduct, active interference, bad faith and/or fraud; (c) Zachry did not
    release its claims to the withheld liquidated damages; (d) the evidence was
    sufficient to support the jury’s finding that the Port was entitled to the $970,000
    offset for defective wharf fenders; and (e) the Port was not entitled to attorney’s
    fees. See Zachry Constr. Corp., 449 S.W.3d at 113–14, 116–18, 119–20. The
    supreme court remanded to this court to address the Port’s remaining issues.
    The Port submitted supplemental briefing, urging the following issues it
    contends are outstanding: (1) the liability findings fail as a matter of law; (2) the
    damages finding fails as a matter of law; (3) Zachry’s “but-for” causation theory
    fails as a matter of law;1 (4) Zachry’s R&R claim fails as a matter of law because
    Zachry did not satisfy contractual conditions precedent; (5) the trial court wrongly
    1
    The Port asserts it is challenging the factual sufficiency of the evidence, as well as the
    legal sufficiency, in its first three issues However, in its briefing, it urges repeatedly that there is
    “no evidence” to support these findings or that “as a matter of law” these findings fail. Thus,
    despite labeling its issues as challenges to the factual sufficiency of the evidence, the Port
    provides no argument in support of a factual sufficiency challenge. Indeed, the Port consistently
    urges that Zachry’s R&R claim should be rendered. See Dongsheng Huang v. Riverstone
    Residential Grp. (Alexan Piney Creek), No.14-11-00009-CV, 
    2011 WL 6003949
    , at *1 (Tex.
    App.—Houston [14th Dist.] Dec. 1, 2011, pet. denied) (mem. op.); see also Tex. R. App. P.
    38.1(i); Garden Ridge, L.P. v. Clear Lake Center, L.P., –S.W.3d–, No. 14-15-00695-CV,
    2016WL 5497501, at *10 (Tex. App.—Houston [14th Dist.] Sept. 29, 2016, no pet. h.) (“Clear
    Lake Center does not refer to the standard of review, cite any other legal authority, or analyze the
    facts of the case under the appropriate legal authority in such a manner to demonstrate that the
    trial court committed reversible error.”). We thus only consider the legal sufficiency of the
    evidence to support the jury’s findings as to breach, causation, and damages.
    6
    excluded evidence of the Port’s harms/losses caused by Zachry; (6) the trial court
    wrongly excluded this evidence of harms/losses even though Zachry opened the
    door to the evidence; (7) charge error in the fraud no-damages-for-delay exception
    requires a new trial; (8) the trial court improperly included apparent authority
    instructions in the jury charge; (9) because Zachry’s R&R claim should be
    rendered, the Port is entitled to attorney’s fees as found by the jury; and
    (10) Zachry erroneously recovered purported “pass-through” damages sustained by
    a Zachry subcontractor.2 We address these issues in turn.
    II. Liability
    The Port couches its first issue as a challenge to the sufficiency of the
    evidence to support the jury’s findings of liability against the Port. Much of its
    argument concerns the jury’s allegedly erroneous interpretation of various
    contractual provisions. We thus begin our analysis of this issue by setting forth the
    appropriate standard of review for a legal sufficiency challenge and then turn to
    general principles governing contract interpretation.               Finally, we consider the
    sufficiency of the evidence to support the jury’s finding in response to Question
    No. 2 that the Port failed to comply with section 5.10.
    A.     Standard of Review and Applicable Law
    In reviewing the legal sufficiency of the evidence, we view the evidence in
    the light most favorable to the verdict, crediting favorable evidence if reasonable
    persons could, and disregarding contrary evidence unless reasonable persons could
    not. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 807 (Tex. 2005); United Nat’l Ins.
    2
    In a final issue, the Port asserts that the jury’s answer of “No” to Question No. 9, which
    asked whether the Port breached the Contract by withholding $600,000 for defective dredging,
    was neither charge error nor against the great weight of the evidence. Zachry did not respond or
    mention this cross-appeal issue in its post-remand supplemental briefing. Indeed, in its prayer, it
    simply requests that the trial court’s judgment be affirmed. It appears that Zachry has abandoned
    its claim to this $600,000. Accordingly, this issue presents nothing for our review.
    7
    Co. v. AMJ Invs., LLC, 
    447 S.W.3d 1
    , 6 (Tex. App.—Houston [14th Dist.] 2014,
    pet. dism’d). We may not sustain a legal sufficiency, or “no evidence,” point
    unless the record demonstrates: (1) a complete absence of a vital fact; (2) the court
    is barred by the rules of law or of evidence from giving weight to the only
    evidence offered to prove a vital fact; (3) the evidence to prove a vital fact is no
    more than a scintilla; or (4) the evidence establishes conclusively the opposite of
    the vital fact. City of Keller, 168 S.W.3d at 810; United Nat’l Ins. Co., 447 S.W.3d
    at 6–7. If the evidence, viewed in the light most favorable to the verdict, would
    enable reasonable and fair-minded people to find the challenged fact, then the
    evidence is legally sufficient. See City of Keller, 168 S.W.3d at 822; see also
    United Nat’l Ins. Co., 447 S.W.3d at 7.
    Because the Port’s first issue concerns the jury’s findings based on its
    interpretation of the Contract, we review the general principles concerning contract
    interpretation. Our primary concern when interpreting a contract is to ascertain
    and give effect to the intent of the parties as expressed in the contract. Seagull
    Energy E & P, Inc. v. Eland Energy, Inc., 
    207 S.W.3d 342
    , 345 (Tex. 2006);
    Bhatia v. Woodlands N. Houston Heart Ctr., 
    396 S.W.3d 658
    , 669 (Tex. App.—
    Houston [14th Dist.] 2013, pet. denied). Contract terms are given their plain,
    ordinary, and generally accepted meanings, and contracts are to be construed as a
    whole in an effort to harmonize and give effect to all provisions of the contract.
    Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 662 (Tex. 2005); Bhatia, 
    396 S.W.3d at
    669–70. Whether a contract is ambiguous is a question of law for the
    court; when a contract is ambiguous, its interpretation becomes a fact issue for the
    jury to resolve. Coker v. Coker, 
    650 S.W.2d 391
    , 394–95 (Tex. 1983); see Dynegy
    Midstream Servs., Ltd. P’ship v. Apache Corp., 
    294 S.W.3d 164
    , 168 (Tex. 2009)
    (stating that a contract is ambiguous when its meaning is uncertain and doubtful or
    8
    is reasonably susceptible to more than one interpretation). Here, by instructing the
    jury to interpret certain provisions of the Contract and Change Order 4, the court
    determined that these provisions were ambiguous and left their interpretation to the
    jury to resolve. See Bowden v. Phillips Petroleum Co., 
    247 S.W.3d 690
    , 705 (Tex.
    2008) (“[B]y sending the interpretation of the [agreements] to the jury, the trial
    court implicitly held the [agreements] were ambiguous.”).
    Finally, because the damages finding was premised on the Port’s liability
    under either Question No. 1, pertaining to Change Order 4, or Question No. 2,
    pertaining to section 5.10 of the Contract, we need only consider whether the Port
    failed to comply with either of these provisions. See, e.g., Soon Phat, L.P. v.
    Alvarado, 
    396 S.W.3d 78
    , 89–90 (Tex. App.—Houston [14th Dist.] 2013, pet.
    denied). We thus focus on whether the Port failed to comply with section 5.10—
    the jury’s finding in response to Question No. 2.
    B.    Application
    We begin our analysis with the language of the charge, which informs the
    sufficiency of the evidence to support the jury’s finding. See Osterberg v. Peca, 
    12 S.W.3d 31
    , 55 (Tex. 2000).       In Question No. 2 the trial court provided the
    following question and instructions to the jury:
    Did the Port fail to comply with § 5.10 of the General
    Conditions?
    In answering this question, it is your duty to interpret §§ 5.10
    and 5.22 and the terms contained therein.
    You must decide the meaning of these provisions of the
    Contract by determining the intent of the parties at the time of the
    agreement. Consider all the facts and circumstances surrounding the
    making of the agreement, the interpretation placed on the agreement
    by the parties, and the conduct of the parties.
    9
    In determining the meaning of these provisions, you may also
    consider a trade custom or usage, if any, if you find that such trade
    custom or usage existed. However, a trade custom or usage, if any,
    cannot vary, control, impair, restrict or enlarge the express language
    of the Contract. A trade custom or usage exists if it is a practice so
    generally or universally well known and used in the industry that the
    parties are charged with knowledge of its existence to such an extent
    as to raise the presumption that the parties contracted with reference
    to it.
    Furthermore, in answering this question, you are instructed that
    nothing in § 5.41 gave the Port the right to issues its October 11, 2005
    response to the September 9, 2005 frozen cutoff wall design.
    Answer “yes” or “no.”
    The jury answered “yes” to this question.
    We next discuss the relevant provisions of the Contract referenced in the
    charge. We begin with section 5.10, which provided the Port with insulation from
    liability:
    5.10 Independent Contractor:
    It is agreed between the parties that the Contractor is and shall
    be an independent contractor. Nothing in the Contract Documents
    shall create a relationship of employer and employee or principal and
    agent between the Port Authority, on the one hand, and the Contractor
    or any of its employees, Subcontractors, Suppliers or agents of any
    thereof, on the other hand. Neither the Contractor nor any of its
    employees, Subcontractors, Suppliers or agents shall have the ability
    to bind or obligate the Port Authority for any purpose whatsoever.
    The Port Authority shall not have the right to control the
    manner in which or prescribe the method by which the Contractor
    performs the Work.[3] As an Independent Contractor, the Contractor
    3
    “Work” is defined by the Contract as:
    The construction and services required by the Contract documents, whether
    commenced or not, or completed or partially completed, and all labor, Materials,
    Equipment and services provided or to be provided by the Contractor to fulfill the
    10
    shall be solely responsible for the supervision of and performance of
    the Work and shall prosecute the Work at such time and seasons, in
    such order or precedence, and in such manner, using such methods as
    the Contractor shall choose; provided, however, that the order, time,
    manner and methods of prosecution shall be in compliance with
    Contractor’s Standard of Care and Work shall be completed within the
    Contract Time and in accordance with the Contract Documents.[4]
    This section of the Contract clearly contemplates that Zachry will control the
    “manner and methods” of its work.                Indeed, the Supreme Court of Texas
    emphasized this fact in its opinion: “The contract made Zachry an independent
    contractor in sole charge of choosing the manner in which the work would be
    conducted. . . . [section 5.10] benefitted the Port, insulating it from the liability to
    which it would be exposed were it exercising control over Zachry’s work.” Zachry
    Constr. Corp., 449 S.W.3d at 102.               The court noted controlling authority,
    explaining that “‘an owner or occupier does not owe a duty to ensure that
    independent contractors perform their work in a safe manner. But one who retains
    a right to control the contractor’s work may be held liable for negligence in
    exercising that right.’” Id. at 102 n.4 (quoting Gen. Elec. Co. v. Moritz, 
    257 S.W.3d 211
    , 214 (Tex. 2008)).
    Yet despite this Contract provision, the Port contends that it was entitled to
    reject Zachry’s freeze-wall design and order Zachry to revise and resubmit its
    Contractor’s obligations pursuant to the Contract Documents. The Work may
    constitute the whole or a part of the Project.
    4
    “Contract Documents” include
    the Contract agreement signed by the Port Authority and Contractor, Addenda (if
    any), Contractor’s Bid/Proposal (including documentation accompanying the
    Bid/Proposal and any post-Bid/Proposal documentation submitted and agreed to
    by the Port Authority prior to commencement of Work), the Bonds, Insurance
    Certificates, these General Conditions, Special Conditions, Specifications and
    Drawings, the Purchase Order, and Modifications.
    “Submittals” are explicitly excluded from the Contract Documents, as noted infra.
    11
    proposed use of the frozen cutoff wall under section 5.22 of the Contract. This
    section, excerpted next, required that Zachry “submit” designs or plans to the Port
    prior to commencing certain “Work” under the contract:
    5.22 Submittals to be Furnished by the Contractor after Award
    The Contractor shall prepare, or cause to be prepared, and
    submit to the person indicated below for such person’s review (which
    review shall be conducted with reasonable promptness so as not to
    delay the Work), complete design and detailed Shop Drawings,
    Product Samples, and other pertinent information showing all
    materials and details of Work to be incorporated into the Project.
    Contractor shall submit such Submittals:
    (a) if there is no Design Consultant responsible for checking
    Submittals in connection with the Work, to the Chief
    Engineer with a copy of the transmittal therewith to the
    Inspector; or
    (b) if there is a Design Consultant responsible for checking
    Submittals in connection with the Work, to such Design
    Consultant with copies of the transmittal letter transmitted
    therewith to the Chief Engineer and the Inspector.
    Submittals of a non-technical nature, such as the Contractor’s
    health and safety plan, spill prevention plan, and appointment of
    Contractor’s superintendent, shall always be submitted to the Chief
    Engineer or such other individual specified in the Contract
    Documents as responsible for reviewing such documents.
    ***
    The person reviewing the Submittal will return them to the
    Contractor marked to indicate whether the Contractor may proceed
    with the Work based on the Submittal as is or with specified changes,
    whether the Contractor must make changes to the Submittal and
    resubmit it, or whether the Submittal is rejected and the Contractor
    must submit another Submittal. The review and/or acceptance of any
    Submittals shall not relieve the Contractor of its full responsibility for
    proper functioning, fit and conformity with the Contract Documents.
    ***
    12
    Submittals are not and, notwithstanding any review and
    acceptance thereof by the Port or any Design Consultant, shall not be
    construed to be Contract Documents.
    The purpose of review and acceptance of Submittals by the Port
    Authority or Design Consultant is merely an effort on the part of the
    Port to determine whether the Contractor is complying with the
    requirements of the Contract Documents and shall in no way operate
    as a waiver of any right of the Port or any obligation of Contractor
    hereunder, nor in any way relieve Contractor of any of its obligations
    hereunder. Review and acceptance of Submittals is not conducted for
    the purpose of determining the accuracy and completeness of other
    details such as dimensions and quantities, or for substantiating
    instructions for installation or performance of equipment or systems,
    all of which remain the responsibility of the Contractor as required by
    the Contract Documents. The Port Authority’s and/or Design
    Consultant’s review and acceptance of the Contractor’s Submittals
    shall not constitute approval of safety precautions or of any
    construction means, methods, techniques, sequences or procedures.
    The Port Authority’s and/or Design Consultant’s review and
    acceptance of a specific item shall not indicate review and approval of
    an assembly of which the item is component.
    (emphasis added).
    As discussed next, we reject the Port’s contention that it was entitled to
    order Zachry to revise and resubmit the use of the frozen cutoff wall to complete
    the expanded wharf as contemplated by Change Order 4. Instead, we conclude that
    legally sufficient evidence supports the jury’s contract interpretation—i.e., that the
    frozen cutoff wall was included in Zachry’s chosen means and methods of
    performing the work.
    The parties agree that Zachry’s original freeze-wall design was part of its
    excavation and shoring safety plan, which is covered by section 4.07 of the
    Contract. This section, entitled “Health and Safety,” provides:
    The Contractor shall submit five (5) copies of a health and
    safety plan for the Work to the Chief Engineer for review at least
    13
    forty-eight (48) hours prior to commencing performance of any Work
    at the site. Prior to beginning any field work at the site, such plan
    shall be certified, by signature of the SHSC [Contractor-designated
    Site Health and Safety Coordinator], that it complies with applicable
    portions of OSHA standards 29 CFR 1910 and 29 CFR 1925. Such
    plan shall provide, at a minimum, for safe working practices, medical
    surveillance, engineering safeguards, personnel protective equipment,
    training, safe operating procedures, emergency planning, reporting
    and sanitation. Notwithstanding the Chief Engineer’s review of the
    health and safety plan, the Contractor, and not the Port Authority,
    shall be responsible for and have control over ensuring the safety of
    its personnel and its Subcontractors, agents, representatives and any
    other person who visits the site in connection with the Work.
    (emphasis added). Thus, the Port was authorized to “review” the plan, but this
    section re-emphasizes that it was Zachry, not the Port, that was responsible for—
    and had control over—ensuring on-site safety. And in fact, the Port did not
    approve or reject the initial freeze-wall plan, which Zachry submitted to the Port as
    Zachry’s shoring-safety-plan addendum to its previously filed health and safety
    plan under Technical Specification 02161 (T.S. 02161).5
    Specifically, T.S. 02161 required Zachry to (1) submit its Proposed Trench
    Excavation and Shoring Safety Plan and (2) submit all modifications of the plan to
    the Port’s Chief Engineer, accompanied by the signed statement of a Registered
    Professional Engineer that the modification is “designed in compliance with the
    Contractor’s Standard of Care” and is in conformance with OSHA. The Port
    counters that because T.S. 02161 requires “submission” of modifications to the
    safety and shoring plan, these “submissions” were subject to the “submittal”
    process provided in section 5.22. Thus, the Port urges that it was authorized to
    order Zachry to revise and resubmit its frozen cutoff wall plan, which is exactly
    5
    Instead, the record reflects that the plan, which had been approved by a Texas
    Professional Engineer as required by T.S. 02161, was provided to the Port and marked
    “Accepted for Records.”
    14
    what it did when it returned Zachry’s plan with the R&R response. We disagree
    with the Port’s proposition, as we explain next.
    T.S. 02161, entitled “Trench Excavation and Shoring Safety Plan,” provides
    in pertinent part as follows:
    C.     Modifications
    All modifications to the CONTRACTOR’S Trench Excavation and
    Shoring Safety Plan or the detailed plans and specifications
    necessitated by the site conditions, CONTRACTOR’S trench
    construction means, methods, techniques or procedures and
    CONTRACTOR’S equipment to be used in construction of project
    facilities to be submitted to the Chief Engineer.             All such
    modifications to be signed and sealed by a Registered Professional
    Engineer licensed in the State of Texas and a statement provided
    stating that the modified plan and/or the modified detailed plans and
    specifications for the trench safety system are designed in compliance
    with the Contractor’s Standard of Care and is in conformance with
    appropriate OSHA standards.                 Such modifications to
    CONTRACTOR’S plan and/or the CONTRACTOR’S detailed plans
    and specifications for the trench safety system to thereafter be
    incorporated into the Construction Contract.
    ***
    1.3    SUBMITTALS
    The successful Contractor to submit its proposed Trench Excavation
    and Shoring Safety Plan after the Award of the Contract. The plan to
    incorporate detailed PLANS and Specifications for a trench safety
    system conforming to OSHA standards that accounts for project site
    conditions, CONTRACTOR’S trench construction means, methods,
    techniques or procedures, the relationship of spoil to edge of trench,
    and CONTRACTOR’S equipment to be used in construction of
    project facilities requiring trench system(s). CONTRACTOR to
    provide a statement signed and sealed by a Registered Professional
    Engineer licensed in the State of Texas stating that the Trench
    Excavation and Shoring Safety Plan and the detailed plans and
    specifications for the trench safety system are designed in compliance
    with the Contractor’s Standard of Care and in conformance with
    15
    appropriate OSHA standards. CONTRACTOR’S plan and the
    detailed PLANS and SPECIFCATIONS for the trench safety system
    to be incorporated into the bid documents and the Construction
    Contract.
    Thus, nothing in the plain language of T.S. 01261 references section 5.22 or
    suggests that the Port could control Zachry’s manner and methods of ensuring the
    safety of the construction site.
    However, the Port asserts that section 1.1(A) of T.S. 01261, which provides
    that it is “subject to” the general and special conditions of the contract, permitted it
    to order Zachry to revise and resubmit the frozen cutoff wall plan under the
    procedures provided in section 5.22 of the Contract. But just as this provision is
    “subject to” section 5.22, it is likewise “subject to” section 5.10, which prohibited
    the Port from exercising control over Zachry’s “manner and methods” of
    performing the work. And the fact that some provisions of the Contract allowed
    the Port to receive means-and-methods-related submittals does not mean that the
    Port was authorized to exercise control over Zachry’s manner and methods.
    Instead, as the Port’s Chief Engineer Steve DeWolf explained, there were
    “activities and other things that [Zachry] would not be required to submit” under
    the revise-and-resubmit portion of section 5.22.        Thus, according to DeWolf,
    Zachry “would not necessarily have to submit [its] means and methods as a capital
    S Submittal.”     DeWolf testified that the Port “would not want to be held
    responsible for some issue that might develop from [Zachry’s] means and
    methods.” DeWolf distinguished between “capital S” submittals subject to the
    revise and resubmit option under section 5.22 and other, non-technical submittals
    that were not subject to that option.
    Indeed, DeWolf’s explanation of the difference between “capital S
    Submittals” and other, non-technical submittals harmonizes sections 5.10 and 5.22
    16
    so that neither is rendered meaningless. See, e.g., J.M. Davidson, 128 S.W.3d at
    229 (a contract should be considered in its entirety, with provisions harmonized so
    that none of them are rendered meaningless). Thus, section 5.22 can be read as
    providing for two types of submittals: (1) technical, “Work”-related submittals (or,
    as DeWolf characterized them, “capital S Submittals”) and (2) other, non-technical
    submittals.   Under this reading of section 5.22, only technical, work-related
    “capital S” submittals would be subject to the revise and re-submit option
    contained therein. Those submittals that related to Zachry’s means and methods of
    completing the work—including the use of the freeze-wall technology—would be
    provided to the Port for its review. In contrast, reading section 5.22 to permit the
    Port to exercise control over Zachry’s means and methods of performing the work
    would vitiate section 5.10.
    And if the Port exercised control over Zachry’s health and safety plan, it
    risked losing the insulation from liability that section 5.10 of the Contract was
    explicitly designed to provide. See Zachry Constr. Corp., 449 S.W.3d at 102 &
    n.4. The Port’s witnesses testified that the Port did not approve or reject the
    original freeze wall to avoid claims it controlled Zachry’s methods and any
    attendant liability.   The record supports an inference that neither party
    contemplated that the Port could approve or order Zachry to revise its main freeze-
    wall plan because Zachry built it and began installing freeze-pipes before
    providing the Port the design. Further, DeWolf agreed that the freeze wall and the
    frozen cutoff wall “would not have been part of the permanent work, so it would
    not be a capital S Submittal” subject to the revise and resubmit process contained
    in section 5.22. De Wolf stated that Port “would not have wanted to be in a
    position of having approved means and methods.” And he acknowledged that
    17
    using the freeze-wall technology “was Zachry’s selected method of performing the
    construction.” (emphasis added).6
    All of this evidence supports the jury’s determination that, despite section
    5.22, many parts of Zachry’s performance under the Contract—including Zachry’s
    submission of its frozen cutoff wall plan under T.S. 01261—were not subject to the
    “revise and resubmit” option therein            Indeed, Zachry bid the entire project,
    including Change Order 4, with the expectation that it would use the freeze-wall
    methodology; the Port selected Zachry for this job based on this innovative and
    environmentally friendly technique. As the Texas Supreme Court explained,
    Zachry’s plan was innovative. It would use soil dredged from the
    channel to construct an 8–foot–wide earthen berm starting from the
    shore at either end of the worksite, extending out toward the center of
    the channel, then running parallel to the shore, forming a long, flat U-
    shaped wall in the channel around the construction area. Zachry
    would install a refrigerated pipe system in the wall and down into the
    channel floor that would carry supercooled brine, freezing the wall to
    make it impenetrable to the water in the channel. Zachry would then
    remove the water from the area between the wall and the shore. In
    this way, Zachry could work “in the dry”, using bulldozers and other
    land equipment for the excavation and revetment work. Another
    advantage to this freeze-wall approach was that it would lower diesel
    emissions and require fewer nitrous oxide credits under environmental
    laws, giving the Port more flexibility in other construction projects.
    Zachry believed this approach would make the work less expensive
    and allow it to be completed more quickly.
    6
    The Port asserts that Zachry “absurdly argues” that “no R&R response could be based
    on risk to the Wharf’s structural integrity.” But the jury was tasked with interpreting the
    Contract as a whole, including whether and to what extent Change Order 4 impacted the “Work”
    under the Contract. And there was conflicting evidence concerning the impact of Zachry’s use
    of the frozen cutoff wall on the structural integrity of the wharf. In fact, there was some
    evidence from which a reasonable juror could determine that the Port manufactured concerns
    about the frozen cutoff wall’s impact on the structural integrity of the wharf. By its answer to
    Question 1, the jury determined that the use of the frozen cutoff wall did not amount to “Work”
    under the Contract. We will not revisit this issue because it rests on the jury’s reasonable
    credibility determinations. See City of Keller, 168 S.W.3d at 816–17, 819–20, 822.
    18
    Id. at 102. Simply put, to permit the Port to later modify Zachry’s manner and
    methods of performance would contravene the clear insulation from liability
    provided by section 5.10. See id.
    In sum, the record supports the jury’s determination that not all submittals
    under the Contract were subject to the revise and resubmit process detailed in
    section 5.22. And there is more than a scintilla of evidence that the frozen cutoff
    wall was Zachry’s chosen method of completing the project (as expanded by
    Change Order 4). Viewing the evidence in the light most favorable to the jury’s
    finding that the Port failed to comply with section 5.10, we conclude that
    reasonable and fair-minded people could find that the Port’s R&R order in
    response to Zachry’s submission of the frozen cutoff wall design violated section
    5.10 of the Contract. Thus the evidence is legally sufficient to support this finding.
    See City of Keller, 168 S.W.3d at 822.
    Because we determine that the evidence is legally sufficient to support the
    jury’s finding that the Port failed to comply with section 5.10, we overrule the
    Port’s first issue.
    III. Damages and Causation
    In the Port’s second and third issues, the Port challenges the damages
    finding. The same standard of review laid out above for legal sufficiency of the
    evidence applies to this issue.
    A.     Damages
    The Port urges in issue two that the jury’s damages findings fail as a matter
    of law.7 These challenges are all based on the Port’s allegation that the testimony
    7
    The pertinent jury question and instructions is as follows:
    19
    and methodology of Zachry’s damages expert, Gary Draper, was unreliable and
    thus no evidence because it was based on assumed facts that were contrary to the
    undisputed facts. See Burroughs Wellcome Co. v. Cyre, 
    907 S.W.2d 497
    , 499–500
    (Tex. 1995) (“When an expert’s opinion is based on assumed facts that vary
    What sum of money, if any, if paid now in cash, would fairly and
    reasonably compensate Zachry for its damages, if any, that resulted from the
    Port’s failure to comply?
    Consider the following elements of damages, if any, and none other.
    A. The balance due and owed by the Port, if any, under the Contract,
    including any amount owed as compensation for any increased cost to
    perform the work as a direct result of Port-caused delays, and
    B. The amount owed, if any, for additional work that Zachry was directed to
    perform by the Port in connection with the Contract.
    You may consider amounts, if any, owed as compensation for increased cost
    to perform the work as a direct result of Port-caused delays, if any, only if you
    find that such increased costs were a natural, probable, and foreseeable
    consequence of the Port’s failure to comply.
    In determining the balance due and owed for the increased cost to perform the
    work under A (above), if any, and the amount owed for additional work under B
    (above), if any, you should include Reimbursable Costs as defined in section 1.1
    of the Management Services Agreement (PX 643), incurred by New Zachry to
    perform Zachry’s obligations under the Contract.
    You are instructed that Zachry was not required to take any of the following
    actions to be able to recover damages for the Port’s failure to comply: (1) obtain a
    written Construction Change Directive or a fully executed Change Order from the
    Chief Engineer under § 5.41 or under § 5.52 to the extent it imposes requirements
    consistent with §5.41; or (2) provide notice that a Contract interpretation by the
    Port constituted a change to the Contract under § 5.42 and that Zachry was
    entitled to an adjustment in the Contract Time and Price. You are instructed that
    you may consider §§ 5.41, 5.42, and 5.52 to the extent it imposes requirements
    consistent with §5.41, only in assessing a party’s state of mind.
    ***
    Do not include in your answer any amount that you find that the Port proved, by a
    preponderance of the evidence, that Zachry could have avoided by the exercise of
    reasonable care.
    The jury answered this question, “$18,602,697.”
    20
    materially from the actual, undisputed facts, the opinion is without probative value
    and cannot support a verdict or judgment.”).
    Draper provided a damages model to the jury that compared Zachry’s actual
    costs to complete the work “in the wet” with a hypothetical model of Zachry’s
    costs had it been able to complete the work “in the dry” as Zachry had planned and
    bid the project. More specifically, Draper (a) identified the construction activities
    the switch impacted; (b) as to each impacted activity, calculated the cost Zachry
    would have incurred working in the dry as long as possible; (c) compared those
    costs to the costs Zachry reasonably incurred as a result of switching to the wet
    earlier than it would have absent the Port’s breach; and (d) excluded all other costs.
    Using this methodology, Draper calculated the costs of the switch to be
    approximately $27 million. After hearing the evidence, the jury awarded Zachry
    $18,602,697, roughly two-thirds of the damages supported by Draper’s model.
    We begin by noting that the Port ignores the evidence supporting Draper’s
    model and instead asserts Draper’s dry schedule “varies drastically” from “dozens
    of schedules” Zachry prepared around the time of the Port’s rejection of the frozen
    cutoff wall method. The record reflects that Draper’s model was based on the use
    of a frozen cutoff wall methodology; in contrast, the schedules the Port relies on
    were not based on a frozen cutoff wall, as they were created after the Port’s
    rejection of this process. Accordingly, these schedules did not project what Draper
    projected—a completion schedule using a frozen cutoff wall. But despite this
    defect in the Port’s general argument, we consider each of the Port’s asserted
    “contrary facts” on which Draper relied in turn.
    1. Removal of Freeze Pipes from Berm
    The Port claims that “Draper erroneously assumed it would take Zachry no
    time (and cost Zachry no money) to remove a thousand freeze pipes from the
    21
    thawed earthen wall (berm).” This faulty assumption, according to the Port, means
    that Draper’s testimony and evidence was unreliable and no evidence of Zachry’s
    damages. But the Port ignores the evidence supporting Draper’s methodology.
    First, Draper’s “in the dry” model—consistent with the evidence—provided
    for freeze-pipe removal to occur concurrently with berm removal. The record
    reflects that Zachry’s dry approach was to remove the berm and freeze-pipes
    simultaneously and using the same equipment. And the Port’s own freeze-wall
    expert at trial, Mageau, concluded at the time of the R&R order that Zachry could
    remove the freeze-pipes and perform the remainder of the work by mid-February
    to mid-March 2006 so the crane-ship could timely dock, even though he was aware
    of issues with the freeze-pipes and other challenges Zachry faced. In fact, Draper’s
    schedule was consistent with the contemporaneous frozen cutoff wall project
    schedule created by Zachry shortly before the Port rejected that method.
    Second, the Port characterizes Draper’s testimony to suggest that Zachry
    could remove all the freeze pipes in one day. Draper did not testify that all the
    freeze pipes could be removed in one day; instead, he stated that the float time in
    his methodology would cover any time necessary to remove these pipes. Finally,
    the Port cross-examined Draper on this point. The jury did not unquestioningly
    accept the testimony of Zachry’s expert but reduced the amount of damages
    presumably based on the challenges made by the Port to Draper’s model. Cf.
    Am.’s Favorite Chicken Co. v. Samaras, 
    929 S.W.2d 617
    , 629 (Tex. App.—San
    Antonio 1996, writ denied) (upholding damages for lost profits in breach of
    contract case despite varying assumptions in the parties’ competing damages
    models).
    For the foregoing reasons, we conclude that Draper’s damages model was
    not unreliable based on the Port’s freeze-pipe removal assertion; conflicting
    22
    evidence was presented on this issue and the jury resolved the conflicts in favor of
    Zachry, although it reduced the damages amount established by Draper’s model.
    Cf. id.
    2. Work on Sheet Pile for Frozen cutoff wall
    The Port urges that, because Draper’s damages model showed Zachry
    working on installing sheet pile8 for the frozen cutoff wall forty days before it
    actually began doing so, Draper’s methodology is unreliable and no evidence of
    damages.       In making this argument, the Port relies on Anderson’s testimony
    referencing a November 15 list of remaining tasks.             Neither that list nor
    Anderson’s testimony references sheet-pile-installation timing for the frozen cutoff
    wall; the Port had rejected the frozen cutoff wall a month earlier. Yet in its
    briefing, the Port inserts “frozen” into Anderson’s testimony “that there was work
    to be done before we were ready for the [frozen] cutoff wall.” Anderson was
    discussing the status as of November 15—when Zachry was considering the
    alternate cutoff wall’s viability. The Port’s argument assumes that, after the
    Port’s October 11 rejection of the frozen cutoff wall, Zachry nonetheless
    proceeded as if Zachry would still be using the frozen cutoff wall.
    Further, even if Anderson were testifying that work remained as of October
    11, he also testified it would take “a couple of days at best.” And although
    Draper’s schedules showed sheet-pile installation starting October 7, it was an
    “early start,” meaning it could start later with no impact on his analysis. Indeed,
    the float allotted for in Draper’s schedule allowed the sheet-pile installation to be
    delayed until November 15 or later.
    8
    “Sheet pile”—steel sheets—would have lined the frozen cutoff wall berm and also
    would have composed Mageau’s alternate cutoff wall.
    23
    Finally, as with the freeze-pipe removal issue, the Port raised this issue
    during cross-examination, and the jury’s damages award––significantly less than
    Draper’s model supported––accounted for any weight the jury gave it. Cf. id. In
    short, the Port’s assertion regarding the sheet piles does not render Draper’s
    testimony unreliable and no evidence.
    For the foregoing reasons, we overrule the Port’s second issue in its entirety.
    B.      Causation
    Next, in its third issue, the Port contends that expert testimony was
    necessary to prove that the Port’s breach caused Zachry to abandon Zachry’s “in
    the dry” construction methods. In support of this proposition, the Port cites Mack
    Trucks v. Tamez, 
    206 S.W.3d 572
    , 583 (Tex. 2006). But Mack Trucks is not a
    breach of contract case; instead, it is a products liability case in which the plaintiff
    failed to present expert testimony regarding the cause of a fuel leak in a tractor’s
    fuel system. See 
    id.
     at 582–83.
    Our research has not revealed a breach of contract case requiring expert
    testimony to establish a causal link between the breach that occurred and the
    resulting damages.9 Because the Port has not cited, nor have we found, any cases
    requiring expert testimony to establish that a party’s breach of contract caused the
    damages awarded by the jury, we decline to impose such a requirement in this
    case.       Cf. Helena Chem. Co. v. Wilkins, 
    47 S.W.3d 486
    , 504 (Tex. 2001)
    (concluding that, in a DTPA case, non-expert testimony may provide legally
    sufficient evidence to establish causation and exclude alternative causes).
    9
    Although numerous cases discuss the necessity of expert testimony to prove damages in
    contract cases, these cases concern the quantification of the damages, rather than the cause of
    damages. See, e.g., Italian Cowboy Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 345 (Tex. 2011); Ginn v. NCI Bldg. Sys., Inc., 
    472 S.W.3d 802
    , 842–43 (Tex. App.—
    Houston [1st Dist.] 2015, no pet.).
    24
    Instead, the evidence must show that the damages are the natural, probable,
    and foreseeable consequence of the defendant’s conduct. Mead v. Johnson Grp.,
    Inc., 
    615 S.W.2d 685
    , 687 (Tex. 1981). Moreover, this court has recognized that a
    contractor is entitled to recover damages from an owner for losses due to delay and
    hindrance of its work if it proves: (1) that its work was delayed or hindered, (2)
    that it suffered damages because of the delay or hindrance, and (3) that the owner
    was responsible for the act or omission that caused the delay or hindrance.
    Shintech Inc. v. Grp. Constructors, Inc., 
    688 S.W.2d 144
    , 148 (Tex. App.—
    Houston [14th Dist.] 1985, no writ) (citing City of Houston v. R.F. Ball Constr.
    Co., 
    570 S.W.2d 75
    , 77 (Tex. Civ. App.—Houston [14th Dist.] 1978, writ ref’d
    n.r.e.)). Here, there is more than a scintilla of evidence to support the finding that
    the Port was responsible for the act that caused the delay to Zachry’s work.
    Anderson and geotechnical expert Hugh Lacy testified that, once the Port rejected
    the frozen cutoff wall, Zachry had no viable alternative method to bifurcate the
    project and complete the wharf in the dry in time for the crane ship to dock. Both
    agreed that Zachry had to switch to working in the wet far earlier than it otherwise
    would have. In fact, the Texas Supreme Court summarized the evidence regarding
    the Port’s breach and the resulting delay damages to Zachry as follows:10
    10
    Although the sufficiency of the evidence was not before the Supreme Court on this
    particular issue, we note that the Court stated its background facts under a legal sufficiency
    standard:
    The evidence in this case was hotly disputed at almost every turn. We do not
    pause in this rehearsal of the proceedings to note each disagreement. In reviewing
    any case tried to a jury, we must view the evidence “in the light most favorable to
    the verdict”—in this case a verdict for the petitioner—“crediting favorable
    evidence if reasonable jurors could, and disregarding contrary evidence unless
    reasonable jurors could not” and so summarize the evidence in that light. Cruz v.
    Andrews Restoration, Inc., 
    364 S.W.3d 817
    , 819 (Tex. 2012) (citing City of Keller
    v. Wilson, 
    168 S.W.3d 802
    , 807 (Tex. 2005)).
    Zachry Constr. Corp., 449 S.W.3d at 101 n.3.
    25
    Nine months into the project, the Port realized that it would
    need two 1,000–foot berths to accommodate the ships it ultimately
    expected to service. A sixth 332–foot section would have to be added
    to the wharf. As a practical matter, only Zachry could perform the
    additional work, and Zachry and the Port began discussions on a
    change order. To complete the two sections of the wharf needed by
    February 2006, and to continue to work “in the dry”, Zachry proposed
    to build another freeze-wall—a cutoff wall—though the middle of the
    project, perpendicular to the shoreline out to the existing wall,
    splitting the project into two parts. Zachry would finish the west end
    where the ship from China would dock, remove the wall barricading
    water from that area, then continue working on the east end “in the
    dry”.
    The Port had reservations about this plan. Near the shore, the
    cutoff wall would have to be built through the area where piers had
    already been driven into the channel floor. The Port’s engineers were
    concerned that freezing the ground near the piers might destabilize
    them, weakening the wharf and making it unsafe. But the Port was
    also concerned that if it rejected Zachry’s plan, Zachry might simply
    refuse to undertake the addition of a sixth section. So the Port did not
    raise its concerns with Zachry. Zachry, for its part, had already
    identified the issue, but its own engineers had concluded that any piers
    that might be affected could be insulated from the frozen ground.
    Change Order 4, using Zachry’s approach to add a sixth section of the
    wharf at a cost of $12,962,800, was finalized September 27, 2005.
    Two weeks later, the Port ordered Zachry to revise and resubmit its
    plans without the cutoff wall. The practical effect of the Port’s order
    was to refuse to allow construction of the cutoff wall. Zachry
    protested that, under Section 5.10 of the contract, the Port had no
    right to determine the method and manner of the work, but the Port
    would not budge. Zachry’s only option was to finish the westmost
    sections in time for the ship from China to dock, then remove the wall
    altogether and continue to work “in the wet”, which would delay
    completion of the project and increase its cost.
    Zachry Constr. Corp., 449 S.W.3d at 102–03 (emphasis added).
    Viewing the evidence in the light most favorable to the verdict, we conclude
    that that the evidence was legally sufficient to support the jury’s verdict. Although
    26
    the Port submitted evidence that tended to contradict Zachry’s evidence, there was
    “more than a mere scintilla” of evidence on which a reasonable jury could find that
    the Port’s failure to comply with the Contract resulted in damages to Zachry. We
    thus overrule Zachry’s third issue.11
    IV. Alleged Conditions Precedent
    In its fourth issues, the Port contends that Zachry failed to comply with two
    provisions of the Contract that the Port urges were conditions precedent—sections
    5.41 and 5.42. As such, according to the Port, judgment in the Port’s favor on
    Zachry’s R&R claim must be rendered. The trial court instructed the jury that
    Zachry did not have to comply with these sections to recover damages; instead, the
    jury was to consider sections 5.41 and 5.42 “only in assessing a party’s state of
    mind.”
    Sections 5.41 and 5.42 set forth procedures that allowed the Port to make
    changes within the scope of the contract work during performance of the Contract.
    Section 5.41 relates to “Changes or Modifications” through change orders, and
    11
    The Port further argues in this issue that CH2M Hill’s Andy Thiess “issued” the R&R
    response, which he lacked authority to do. The Port cites special condition 12(d) of the Contract,
    which provided that CH2M Hill, as the Construction Manager of the project, did not have the
    authority of the Port’s Chief Engineer and had “no authority to . . . change any of the terms and
    conditions of the Contract, including without limitation, issuing Modifications . . . or Change
    Orders.” But the R&R response is not a modification or change order, and nothing on the face of
    the R&R order indicates it was issued by Thiess. Instead, it bears the seal of the Port of Houston.
    And under special condition 12(d), CH2M Hill was tasked with coordinating the paper flow for
    the Project, including Submittals and Change Orders. Zachry was required to submit paperwork
    to CH2M Hill, and CH2M Hill was charged with managing the flow of the paperwork to and
    from the appropriate Port personnel, including the Chief Engineer. CH2M Hill additionally was
    charged with conducting all pre-construction and progress meetings, and it was during these
    progress meetings that CH2M Hill and Zachry personnel discussed the Port’s R&R response to
    Change Order 4. Further, we resolve the Port’s complaint regarding the “apparent authority”
    instruction in the jury charge against the Port infra in section VII of this opinion. Thus, the jury
    properly considered whether CH2M Hill had authority to act on behalf of the Port as regards to
    the R&R response.
    27
    section 5.42 concerns “Changed Conditions or Contract Interpretations.” More
    specifically, section 5.41 applies to “changes and modifications to the Contract
    Documents within the general scope of the Work,” and requires a change order to
    “stipulate the Work to be performed” and “any difference in the Contract Price.”
    Section 5.42,12 on the other hand, required five days’ written notice of any
    “interpretation of the Contract” by the Port that Zachry “believes . . . constitutes a
    change to the Contract,” if Zachry believed it was entitled to an adjustment in the
    Contract time or price. Under section 5.42, the Chief Engineer’s determination of
    whether there should be a “modification” or “equitable adjustment” was “final and
    conclusive,” and Zachry was forbidden from “begin[ning] performing that portion
    of the Work affected by such interpretation” before giving notice.
    Zachry has never asserted that the Port, by denying Zachry the use of the
    frozen cutoff wall as its means and methods of performing Change Order 4,
    effected “changes or modifications” to the Contract or “interpreted” the Contract in
    a manner that constituted a “change” to the Contract as is provided for in these
    sections. Rather, Zachry’s case hinges on the proposition that the Port breached
    the Contract by rejecting the frozen cutoff wall.                 Zachry did not seek the
    “difference in the Contract Price” under section 5.41 or “an adjustment in the . . .
    Contract Price” under section 5.42. Instead, Zachry sought, and the jury awarded,
    damages for the Port’s breach of the Contract. We thus interpret these provisions
    as applying only to changes relating to the “Work” under the Contract, not to
    12
    Pre-trial, the Port unsuccessfully moved for summary judgment on the ground that
    Zachry’s claim for R&R damages was barred by this provision. Zachry, also pre-trial, sought to
    invalidate section 5.42’s notice requirements on the grounds that this section did not apply to
    Zachry’s breach-of-contract claim and, even if it did, it was invalid under Texas Civil Practice &
    Remedies Code section 16.071. The trial court agreed with Zachry and determined that section
    5.42 was “inapplicable” to the facts of this case and “void” under section 16.071 of the Civil
    Practice & Remedies Code.
    28
    Zachry’s methods and means, over which Zachry was explicitly in control under
    section 5.10, as discussed supra.
    Further, the Port’s interpretation of section 5.42 of the Contract would
    require us to read this section as follows: “If the Contractor believes that any
    interpretation of the Contract Documents by [the Port and its agents] constitutes a
    breach of the Contract, the Contractor shall immediately notify the Chief
    Engineer” in writing within five calendar days after the interpretation constituting
    the breach. Such a reading of this provision would run afoul of Texas Civil
    Practice & Remedies Code section 16.071, which provides:
    A contract stipulation that requires a claimant to give notice of a claim
    for damages as a condition precedent to the right to sue on the
    contract is not valid unless the stipulation is reasonable. A stipulation
    that requires notification within less than 90 days is void.
    Tex. Civ. Prac. & Rem. Code § 16.071(a).
    The Port asserts that section 16.071 of the Civil Practice & Remedies Code
    does not apply to section 5.42 because it only “voids contract provisions that
    require, as a condition precedent to suit, less than 90 days’ notice of a claim for
    damages.”       The Port urges that, under American Airlines Employees Federal
    Credit Union v. Martin,13 section 16.071 does not apply where the notice has some
    “other purpose, i.e., a purpose other than giving notice of a claim for damages.”
    But American Airlines does not stand for a proposition so broad; rather the
    Supreme Court of Texas simply explained in American Airlines that “section
    16.071 by its terms does not apply here, when the notice to be given is not notice
    of a claim for damages, but rather notice of unauthorized transactions.           The
    13
    
    29 S.W.3d 86
    , 97–98 (Tex. 2000).
    29
    purpose of this notice requirement, as we have discussed, is to prevent further
    unauthorized transactions.” 
    29 S.W.3d 86
    , 97 (Tex. 2000) (emphasis added).
    Moreover, our interpretation of section 5.42 does not render the provision
    meaningless or invalid, as the Port argues, because not every interpretation of the
    Contract documents by the Port would constitute a breach of the contract. For
    example, if the Port specified the type of a particular material to be used in
    building the Wharf, such as a certain type of concrete, and Zachry believed that
    this interpretation of the Contract entitled it to a change in the Contract time or
    price, then this provision would have provided a valid means of quickly resolving
    the issue.14 Thus, in many circumstances, this provision would not violate section
    16.071 of the Civil Practice & Remedies Code. Conversely, here, Zachry has
    never claimed that the Port interpreted the Contract in such a manner that Zachry
    was entitled to an adjustment in the Contract time or price. Instead, Zachry has
    urged that the Port breached the Contract by controlling Zachry’s methods and
    means—i.e., by rejecting Zachry’s use of the frozen cutoff wall. If section 5.42
    operated, as the Port urges, to require Zachry to provide five days’ written notice
    of this claim for breach and damages, it would be void under section 16.071 of the
    Civil Practice & Remedies Code. Indeed, interpreting section 5.42 as the Port
    suggests would convert nearly any breach of the Contract by the Port into a
    “change” subject to the Chief Engineer’s “final and conclusive” determination as
    14
    As another example, Zachry suggests in its briefing that section “5.42 would apply if
    the specifications required ‘steel,’ and [the Port] interpreted that to mean galvanized steel, but
    Zachry believed black steel complied.” Because section 5.42 could have operated validly in
    some situations, the “circular reasoning” problem identified in Tennessee Gas Pipeline Co. v.
    Technip USA Corp., No. 01-06-00535-CV, 
    2008 WL 3876141
    , at *23 n.11 (Tex. App.—Houston
    [1st Dist.] 208, pet. denied) (mem. op. on reh’g), does not arise in this case. In other words,
    section 5.42 is not rendered meaningless under our interpretation. See 
    id.
     (“We will not construe
    a contract in a way that renders a provision meaningless.”).
    30
    to whether the Port had properly interpreted the Contract and whether Zachry was
    entitled to a change in the Contract time or price.15
    We conclude that section 5.42’s notice provision is inapplicable under the
    circumstances of this case as it applies only to “changes” in the Contract, not to
    “breaches” of the contract. See Criswell v. European Crossroads Shopping Ctr.,
    
    792 S.W.2d 945
    , 948 (Tex. 1990) (“In construing a contract, forfeiture by finding a
    condition precedent is to be avoided when another reasonable reading of the
    contract is possible.”). Further, interpreting this provision under the facts of this
    case as the Port suggests would result in the provision being void under the Civil
    Practice & Remedies Code. See Tex. Civ. Prac. & Rem. Code § 16.071(a); cf.
    Frost Nat’l. Bank v. L & F. Distribs., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005) (per
    curiam) (citing Reilly v. Rangers Mgmt., Inc., 
    727 S.W. 2d 527
    , 530 (Tex. 1987),
    and explaining we avoid when possible a contract construction that is
    “unreasonable, inequitable, and oppressive”).
    Finally, even if these sections applied to a breach-of-contract claim, “[w]hen
    an owner breaches a construction contract, it relinquishes its contractual procedural
    rights concerning change orders and claims for additional costs.” Shintech, 688
    S.W.2d at 151. In other words, breaching owners like the Port are precluded from
    invoking procedural clauses to bar contractors’ claims for damages. See, e.g., West
    v. Triple B. Servs., LLP, 
    264 S.W.3d 440
    , 446–50 (Tex. App.—Houston [14th
    Dist.] 2008, no pet.) (30-day notice requirement); Shintech, 688 S.W.2d at 151
    (written-notice requirement); N. Harris Cty. Jr. Coll. Dist. v. Fleetwood Constr.
    15
    And the Port knew how to draft a provision detailing conditions precedent to suit. In
    section 5.55 of the Contract, the Port detailed the process of dispute resolution, explicitly stating,
    “Participation in non-binding mediation in accordance with this paragraph shall be a condition
    precedent to Contractor having the right to file any legal or equitable action against the Port
    Authority or any of its commissioners, officers, directors, employees or agents.” (emphasis
    added).
    31
    Co., 
    604 S.W.2d 247
    , 254 (Tex. App.—Houston [14th Dist.] 1980, writ ref’d
    n.r.e.) (change-order requirement); Bd. of Regents of Univ. of Tex. v. S & G Constr.
    Co., 
    529 S.W.2d 90
    , 96 (Tex. Civ. App.—Austin 1975, writ ref’d n.r.e.) (change-
    order requirement), overruled on other grounds by Fed. Sign v. Tex. S. Univ., 
    951 S.W.2d 401
     (Tex. 1997).16            Thus, because the Port materially breached the
    Contract, it is barred from invoking sections 5.41 and 5.42 to bar Zachry’s claims
    for damages.17
    Under these circumstances, we overrule the Port’s fourth issue.
    V. Exclusion of Port’s Evidence of Harms/Losses
    The Port asserts in its fifth issue that the trial court abused its discretion by
    excluding evidence of its harm and losses due to Zachry’s failure to perform in
    accordance with the Contract. In its related sixth issue, the Port contends that the
    trial court erred or abused its discretion by continuing to exclude (as a discovery
    sanction) a “subset of evidence” of its harms and losses even after the court held
    16
    The Port argues that this line of cases does not apply if the contractor continued to
    perform after the breach. The Port is simply wrong; in all these cases, the contractors continued
    to perform after the defendants breached. See, e.g., N. Harris Cty. Jr. Coll. Dist., 604 S.W.2d at
    254 (“At the point of the breach, when the College failed to change its specifications to conform
    to the actual soil condition, Fleetwood was given the choice of stopping work and recovering
    under the contract or continuing to work and claiming damages caused by the breach. Fleetwood
    chose to continue and sue for damages, and the College cannot now insist on enforcement of the
    claims provision.”). None of the cases have been overruled on this basis.
    17
    The Port also includes a small subsection in this portion of its argument relating to
    section 5.08 of the Contract, which permitted Zachry to request additional time in certain
    circumstances. This section of the Port’s argument provides in toto as follows:
    The court erred/abused its discretion by excluding evidence that, despite the R&R
    response, Zachry never exercised its §5.08 right to seek more time to perform.
    This evidence went to causation; had Zachry viewed the R&R response as a
    breach causing the switch to “in the wet,” Zachry would have invoked §5.08 and
    sought more time.
    (record citations omitted). The Port has failed to “make a clear and concise argument for the
    contentions made, with appropriate citations to authorities and to the record.” Tex. R. App. P.
    38.1(i). Thus, it has waived this sub-issue by inadequate briefing.
    32
    that Zachry had “opened the door” to evidence of these harms and losses. We
    begin with a brief overview of the pertinent facts.
    A.     Facts Pertinent to Exclusion of Port’s Harms/Losses
    Zachry filed suit against the Port in 2006, seeking, among other things, the
    liquidated damages the Port had withheld from Zachry. On June 3, 2009, the Port
    filed its third amended original answer and counterclaim.                  At that time, the
    discovery deadline had expired on January 16, the pleading deadline had expired
    on January 23, and trial was set to begin on July 20. In this pleading, the Port, for
    the first time, alleged, in pertinent part, the following as a defense:
    Zachry agreed to a Milestone A date and the Final Completion date.
    Zachry agreed to liquidated damages in the event it failed to meet
    these dates. Zachry failed to meet the Milestone A date and the Final
    Completion date. In addition, Zachry failed to properly perform Work
    and the Port Authority had to pay another contractor to correct or
    mitigate harm caused by Zachry’s defective Work. The Port
    Authority’s withholding of monies from payments to Zachry is
    supported by enforceable provisions of the Contract, including the
    right to withhold payments (Section 6.05 of the General Conditions),
    the right of offset (Section 6.17 of the General Conditions),[18] the
    right to liquidated damages (Section 5.05 of the General Conditions),
    the right to actual damages in lieu of liquidated damages (Section 5.06
    of the General Conditions),[19] and the Specification and Proposal
    18
    Section 6.17 states:
    Offset:
    The Port Authority, without waiver or limitation of any of its other rights
    or remedies under this Contract and Applicable Law, shall have the right but not
    the obligation to from time to time deduct from any amounts due or owing by the
    Port Authority to the Contractor or its surety any and all amounts owed by the
    Contractor or its surety to the Port Authority.
    19
    This section provides that the agreed-to liquidated damages are the minimum amount
    of damages suffered by the Port: “If the Port Authority suffers damages in excess of such
    minimum amount due to the Contractor’s failure to complete within the Contract Time, the Port
    Authority shall have the right to recover its actual damages.” (emphasis added).
    33
    (setting forth the concept of reduction of the contract price for late
    performance). The liquidated damages withheld were a reasonable
    forecast of just compensation because the Contract provided for
    liquidated damages in lieu of actual damages and because the Port
    Authority sustained actual damages in an amount that was not
    disproportionate to the liquidated damages.20
    The next day, the Port filed its second amended response to Zachry’s request for
    disclosure, in which it asserted that Zachry was not entitled to recovery against the
    Port for breach of contract because the Port “acted in accordance with the Contract
    provisions, including, but not limited to the right to withhold payments (sections
    6.05, 6.17, 5.05, and 5.06 of the General Conditions).” The Port further repeated
    the above allegations from its amended petition.21
    Zachry responded with an interrogatory on June 11, asking the Port to
    quantify these harms. The Port responded on July 24—Zachry’s interrogatory
    deadline—by quantifying more than $8 million in alleged harms. Yet the Port did
    not disclose that it sought to offset these harms against Zachry’s damages; instead,
    this interrogatory response quantified harms in the context of the Port’s disclosure
    20
    In contrast, in its second amended original answer, the Port had alleged more generally
    as follows:
    Zachry agreed to a Milestone A date and the Final Completion date. Zachry
    agreed to liquidated damages in the event it failed to meet these dates. Zachry
    failed to meet the Milestone A date and the Final Completion date. The Port
    Authority’s withholding of monies from payments to Zachry is supported by
    enforceable provisions of the Contract, including the right to withhold payments
    (Section 6.05 of the General Conditions), the right of offset (Section 6.17 of the
    General Conditions), the right to liquidated damages and actual damages in lieu of
    liquidated damages (Sections 5.05 and 5.06 of the General Conditions), and the
    Specifications and Proposal (setting forth liquidated damages and the concept of
    reduction of the Contract price).
    21
    Meanwhile, Zachry had attacked the Port’s withholding of liquidated damages as an
    invalid penalty when Zachry filed a motion for partial summary judgment on that basis in
    December 2008. Although this motion was later denied, the Port was on notice that Zachry
    would be seeking to invalidate the Port’s withholding of liquidated damages nearly eighteen
    months before the Port set out to quantify its alleged harms/losses.
    34
    that it “sustained actual damages in an amount that was not disproportionate to the
    liquidated damages.”           Later, in September, the Port increased its claimed
    harms/losses to around $10.5 million but continued to make this disclosure in the
    context of proportionality to liquidated damages. The Port did not disclose that it
    intended to submit these harms/losses to the jury as an offset to reduce Zachry’s
    damages. In fact, the Port’s September 17th draft jury charge did not seek any
    findings as to the Port’s actual damages for an offset defense to reduce Zachry’s
    damages award.
    On September 29, 2009, the Port revealed that it intended to seek its alleged
    $10.5 million harms/losses as a defense to reduce any judgment in favor of
    Zachry.22 The next day, Zachry moved to strike the Port’s defense and exclude any
    evidence in support of these damages. After a flurry of responses, replies, and
    hearings, on October 16, the trial court granted in part and denied in part Zachry’s
    motion to strike. In its five-page order, the trial court explained in detail its
    reasoning:
    [The Port] only listed ANY amounts (other than the $600,000.00
    dredging issue) of its actual damages that it proposed to serve as an
    offset in late July 2009. However, the legal theory under which those
    quantities were listed was ONLY the proportionality of its liquidated
    damages offset claim to actual damages. Additionally, [the Port] had
    timely disclosed $600,000.00 in actual damages much earlier as part
    of an offset claim pertaining to certain dredging costs.
    To this day, [the Port] has not enunciated in any discovery
    response any legal theory that it was seeking to defensively offset or
    recoup ANY actual damages other than the $600,000.00 amount.
    Zachry allegedly only learned of [the Port’s] apparent attempt to inject
    first $8 million and then $10.5 million in actual damages (as opposed
    to liquidated damages) as a defensive claim for offset informally, and
    not through any supplementation of discovery, such as a supplement
    22
    At that time, trial was set to begin on October 20.
    35
    to a request for disclosure under Rule 194.2(c). The Court stated at a
    hearing that the surprise to Zachry was not that [the Port] was seeking
    an offset, but that it was seeking to offset a long list of itemized
    damages as opposed to liquidated damages. It is important to note,
    again, that in quantifying its “harms” in July 2009, [the Port] was not
    stating that it would actually be seeking to recover those quantities for
    those specific harms as an offset.
    ***
    [The Port] argues that this Court’s March 2009 ruling denying
    [Zachry’s] motion for summary judgment on the enforceability of the
    liquidated damages clause of the contract excused it from pleading
    and enunciating in its disclosure responses this alternate theory of
    actual damages. The Court wants to be fair, as always, but if
    anything, the suggestion by Zachry by its motion that the liquidated
    damages clause may not be enforceable should have alerted [the Port]
    that it needed to plead this theory and enunciate it in terms of the legal
    theory and amounts in its disclosure responses. Further, Zachry again
    sought to eliminate the liquidated damages claim by its Rule 166g
    Motion on or about July 31, 2009, and [the Port] still has not amended
    its Rule 194.2(c) disclosure response to enunciate an actual damages
    theory of offset or recoupment, nor sought leave to do so, to the
    Court’s knowledge. [The Port’s] inclusion, long ago, of the
    $600,000.00 actual damages figure as part of its offset claim also
    highlights that [the Port] should have included all of the other
    categories and quantities of offsets well before the discovery cutoff.
    ***
    The bottom line is that to inject $10.5 million in actual damages
    or recoupment well after all discovery deadlines have passed would
    dramatically change the landscape of what promises to be a lengthy
    and complicated trial. It is not fair to ask either side to engage in what
    the Court perceives would be extensive discovery (including
    document production, depositions, and potentially additional expert
    witnesses) on the evidentiary bases for the amounts sought to be offset
    by [the Port]. The results of that discovery will not be known until
    long after voir dire and opening statements, and the trial Court will
    not allow that much fluidity and uncertainty into this trial.
    36
    The trial court permitted the Port to offer the following amounts and categories of
    damages as potential offsets to any damages awarded to Zachry: (1) $600,000 for
    dredging; (2) “$1 million or so” for damages to wharf fenders; and (3) “$25,000.00
    or so” for “cleaning and grubbing.”      The trial court excluded the remaining
    categories and evidence of offset harms/losses the Port sought to introduce.
    Later, during trial, testimony concerning an email from Port personnel,
    which was admitted into evidence, was adduced. For example, Zachry’s Anderson
    testified regarding the email and conversation he had with the Port’s personnel.
    Anderson testified and a Port email to the Port’s Chief Engineer DeWolf stated that
    the Port would not charge Zachry the liquidated damages penalty “if no expense or
    loss” to the Port occurred. Anderson testified that Project Engineer Jim McQueen
    told him during a meeting that, although Zachry had sought an extension of time
    due to a concrete shortage, the Port was denying the time extension, but would not
    charge Zachry penalties “since the [crane ship from China] ha[d] been delayed in
    its arrival time” and “there were no damages done.”
    The Port argued that testimony about this email, as well as the email itself,
    opened the door to evidence of its harms/losses that had been excluded pre-trial.
    The trial court agreed that Zachry had opened the door to evidence of harms/losses,
    later clarifying by a written order that Zachry had opened the door to this evidence
    “to a degree” and only up to the date that the Port notified Zachry that it would be
    charging liquidated damages, i.e., May 15, 2006. However, in this same order, the
    trial court concluded that, under Texas Rule of Evidence 403, “any probative value
    of injecting all of the evidence of alleged harms into the trial would be
    substantially outweighed by the danger of (1) unfair prejudice to Zachry, and (2)
    considerations of undue delay.”
    37
    The Port complains about both the trial court’s pre-trial ruling excluding
    evidence of its harms/losses and the trial court’s Rule 403 ruling during trial. With
    this factual background in mind, we consider each of these issues in turn, bearing
    in mind that we apply an abuse of discretion standard to the question of whether a
    trial court erred in an evidentiary ruling. U-Haul Int’l, Inc. v. Waldrip, 
    380 S.W.3d 118
    , 132 (Tex. 2012) (“Evidentiary rulings are committed to the trial court’s sound
    discretion.”).   Further, even if the trial court erred in its evidentiary ruling,
    “reversal is only appropriate if the error was harmful, i.e., it probably resulted in an
    improper judgment.” 
    Id.
    B.    Pre-trial Exclusion
    The Port challenges the pre-trial exclusion of this evidence in its fifth issue.
    Our Rules of Civil Procedure provide that a party may request disclosure of “the
    legal theories and, in general, the factual bases of the responding party’s claims or
    defenses” or “the amount and any method of calculating economic damages.” Tex.
    R. Civ. P. 194.2(c), (d); see also Tex. R. Civ. P. 194.6 cmt. 2 (explaining that a
    defendant in a negligence suit involving a car wreck “would be required to disclose
    his or her denial of . . . any basis for contesting the [plaintiff’s] damage
    calculation”). Further,
    [a] party who failed to make, amend, or supplement a discovery
    response in a timely manner may not introduce in evidence that
    material or information that was not timely disclosed . . . unless the
    court finds that:
    (1) there was good cause for the failure to timely make, amend, or
    supplement the discovery response; or
    (2) the failure to timely make, amend, or supplement the discovery
    response will not unfairly surprise or unfairly prejudice the other
    parties.
    38
    Tex. R. Civ. P. 193.6(a). The party seeking to introduce the evidence bears the
    burden of establishing good cause or lack of unfair surprise or unfair prejudice.
    Tex. R. Civ. P. 193.6(b).     Finally, it is within the trial court’s discretion to
    determine whether the party offering the evidence has abided by the appropriate
    disclosure rule. Cf. Sharp v. Roadway Nat’l Bank, 
    784 S.W.2d 669
    , 671 (Tex.
    1990) (per curiam) (“However, if the trial court finds that the party offering the
    testimony had good cause for failing to supplement, it may, in its discretion, admit
    the testimony.”)
    The Port claims that the trial court “misread” Zachry’s interrogatory and the
    Port’s response. The Port urges that its reference to “offset” in its disclosure and
    later interrogatory response quantifying its harms/losses were sufficiently timely
    such that the trial court “wrongly” excluded this evidence.         Finally, the Port
    suggests that neither Zachry’s interrogatory nor the Port’s response mentioned
    proportionality or limited the relevance of the quantified harms/losses to
    proportionality of the liquidated damages.
    But we do not examine these pleadings in a vacuum. Despite the Port’s
    assertions that neither Zachry’s interrogatory nor the Port’s response mention
    liquidated damages, it is clear from the context of the pleadings at issue that the
    Port was quantifying its alleged damages in an effort to establish proportionality to
    the liquidated damages it had withheld. Further, as the trial court stated in its
    order, the Port did not detail the $8.5 million of actual damages it sought as an
    offset until July 2009, months past the January 2009 discovery deadline. And as
    the trial court opined, the Port was on notice well before the discovery deadline
    that Zachry was seeking to have the liquidated damages provision invalidated. We
    additionally note that the Port admittedly was aware of the amounts and categories
    of its alleged actual harms/losses before the discovery deadline.
    39
    In light of the foregoing, we cannot say the trial court abused its discretion in
    concluding that the Port did not meet its burden to establish good cause or the lack
    of unfair surprise or unfair prejudice. See Tex. R. Civ. P. 193.6(b); Perez v.
    Williams, 
    474 S.W.3d 408
    , 420–21. We overrule the Port’s fifth issue.
    C.     Trial Exclusion of Evidence
    The Port contends in issue six that the trial court’s exclusion of this
    harms/loss evidence after Zachry “opened the door” to this evidence “skewed the
    trial on two of four [no damages for delay] ‘exceptions’—bad faith and
    arbitrary/capricious.” The Port asserts that a trial court must admit “open the door”
    evidence without performing a Texas Rule of Evidence 403 balancing test, relying
    on Horizons/Healthcare v. Auld, 
    34 S.W.3d 887
    , 905–07 (Tex. 2000). Yet no Rule
    403 analysis was performed in Auld, contrary to the Port’s contention. See 
    id.
    Here, the trial court performed a Rule 403 balancing analysis. The trial court
    articulated a basis for its Rule 403 reasoning, including but not limited to the
    absence of any basis to relieve the Port of the prior discovery sanction or to compel
    Zachary to cross examine witnesses on damages for which it had had no discovery
    opportunity—all with little probative value.                The Port has not offered any
    substantive analysis or cited any appropriate authority concerning the propriety of
    the trial court’s analysis.23
    In short, the Port has failed to establish that the trial court’s exclusion of this
    evidence, even if erroneous, probably resulted in an improper judgment. See U-
    Haul Int’l, Inc., 380 S.W.3d at 132; see also Tex. R. App. P. 44.1(a). Under these
    circumstances, the Port’s sixth issue is overruled.
    23
    And the Texas Court of Criminal Appeals has held, in considering the very same rules
    of evidence, that “even if a party opens the door to rebuttal evidence, the trial judge still has the
    discretion to exclude the evidence under Rule 403.” Hayden v. State, 
    296 S.W.3d 549
    , 554 (Tex.
    Crim. App. 2009).
    40
    VI. No-Damages-for-Delay Fraud Instruction
    The Port urges in its seventh issue24 that the fraud definition included in the
    no-damages-for-delay portion of the jury charge was erroneous because it
    permitted the jury to find fraud based on reckless, rather than intentional, behavior.
    The Port complains that the type of fraud at issue—a promise of future
    performance made with no intent to perform—must be intentional, not reckless.
    Yet the Supreme Court explicitly held, “The charge correctly described the
    misconduct that cannot be covered by a no-damages-for-delay provision.” Zachry
    Constr. Corp., 449 S.W.3d at 117. The Port’s argument ignores the law-of-the-
    case doctrine. Under this doctrine, a decision rendered in a former appeal of a case
    is generally binding in a later appeal of the same case. Paradigm Oil, Inc. v.
    Retamco Operating, Inc., 
    372 S.W.3d 177
    , 182 (Tex. 2012) (citing Briscoe v.
    Goodmark Corp., 
    102 S.W.3d 714
    , 716 (Tex. 2003)).
    We are bound by the Texas Supreme Court’s express holding that the charge
    “correctly described the misconduct that cannot be covered by a no-damages-for-
    delay provision.” Thus, this issue is without merit, and we overrule it.
    VII. Apparent Authority Instruction
    In issue eight, the Port raises various challenges to the trial court’s apparent
    authority instruction to the jury, including that Zachry failed to plead that CH2M
    Hill acted with the Port’s apparent authority.25 At bottom, if Zachry pleaded
    apparent authority, then the trial court did not err in instructing the jury on this
    matter so long as it was raised by the evidence. See Tex. R. Civ. P. 278 (“The
    24
    This issue is not presented in the Port’s “issues presented” section of its brief, but is
    urged in the Port’s argument section.
    25
    Importantly, as noted above, nothing on the face of the R&R order indicates it was
    issued by CH2M Hill; instead, it bears the seal of the Port of Houston.
    41
    court shall submit the questions, instructions and definitions in the form provided
    by Rule 277, which are raised by the written pleadings and the evidence.”). The
    Port does not assert that this issue was not raised by the evidence. Indeed, the
    Port’s Chief Engineer DeWolf testified that he had designated CH2M Hill to be his
    “representative” in exchanging information with Zachry.             Other evidence
    established that the Port expected Zachry to rely on CH2M Hill’s communications,
    that CH2M Hill was DeWolf’s representative, that CH2M Hill was the Port’s
    primary contact with Zachry, and that the Port’s executives treated CH2M Hill like
    the Port’s own staff.
    We thus examine Zachry’s pleadings to determine whether it sufficiently
    pleaded apparent authority, bearing in mind that the trial court stated on the record
    that Zachry pleaded apparent authority. Zachry pleaded that the Port “expressly
    charged and designated its Construction Manager, CH2M-Hill, to act on its behalf
    on this critical cutoff-wall issue.” Zachry additionally referred to the CH2M Hill
    as the Port’s designated agent. The purpose of pleadings is to give adversaries
    notice of each party’s claims and defenses, as well as notice of the relief sought.
    Perez v. Briercroft Serv. Corp., 
    809 S.W.2d 216
    , 218 (Tex. 1991). Generally, in
    the absence of special exceptions, a petition will be construed liberally in favor of
    the pleader. Roark v. Allen, 
    633 S.W.2d 804
    , 809 (Tex. 1982). The Port did not
    specially except to Zachry’s pleadings; thus Zachry’s pleadings must be construed
    liberally.
    Although Zachry did not use the term “apparent authority,” Zachry’s
    allegation is sufficient to give notice to the Port that it faced a claim that CH2M
    Hill had apparent authority to act on the Port’s behalf. See Tex. R. Civ. P. 45; see
    also Iron Mountain Bison Ranch, Inc. v. Easley Trailer Mfg., Inc., 
    42 S.W.3d 149
    ,
    157 (Tex. App.—Amarillo 2000, no pet.).         The distinguishing factor between
    42
    actual and apparent authority is to whom such authority is communicated: “An
    agent’s authority to act on behalf of a principal depends on some communication
    by the principal either to the agent (actual or express authority) or to the third party
    (apparent or implied authority).” Gaines v. Kelly, 
    235 S.W.3d 179
    , 182 (Tex.
    2007).      If the Port questioned what was being pleaded, it had the option of
    specially excepting and having the pleading clarified. See Tex. R. Civ. P. 91.
    In sum, we cannot conclude that the trial court abused its discretion in
    determining that Zachry adequately pleaded apparent authority, especially in light
    of the Port’s failure to specially except to Zachry’s petition. We thus overrule the
    Port’s eighth issue.
    VIII. Attorney’s Fees
    In its ninth issue, the Port asserts that it is entitled to attorney’s fees because
    Zachry’s R&R claim “should be rendered.” Because we have determined that
    Zachry’s R&R claim should not be reversed and rendered, there is no basis for the
    Port’s attorney’s fee claim. Accordingly, we overrule the Port’s ninth issue.
    IX. Zachry’s Pass-Through Damages
    In January 2008, Zachry reorganized. The work on this Contract going
    forward was performed by a new Zachry entity, which the parties refer to as the
    “Sub,” a term we will adopt for ease of reference.26 The jury found, in Question
    No. 5, that $8,578,712 of the $18,602,697 R&R damages were costs incurred by
    26
    In 2007, the Sub was formed as ZCC Corporation, Zachry took a new name (Zachry
    Industrial, Inc.), and the Sub changed its name to Zachry Construction Corporation (Zachry’s
    former name). In April 2009, Zachry entered into the subcontract with the Sub, but the
    subcontract was effective January 1, 2008—the date the Sub began performing Zachry’s
    obligations under the Contract. It is undisputed that the Port never consented to Zachry
    assigning the Contract to the Sub. But, the contract between Zachry and the Sub—the
    Management Services Agreement—provides that the contract was not and had not been assigned
    to the Sub, and Zachry remained fully liable to the Port under the terms of the Contract.
    43
    the Sub. In its tenth issue, the Port contends that Zachry cannot recover this
    amount because (1) Zachry did not own the claim for these damages; (2) Zachry
    cannot recover these damages as a purported “pass-through” claim;27 (3) Zachry
    failed to establish its liability to the Sub for these damages; and (4) charge error
    tainted the jury’s finding to Question No. 5.               We consider those arguments
    necessary to resolve this issue next.
    A.     Zachry May Recover these Damages as a Pass-Through Claim
    The Port contends Zachry cannot assert a pass-through claim because it
    hired the Sub after PHA’s breach, and thus the Port’s “breach . . . did not cause
    Zachry to breach the subcontract.” But nothing in the seminal case approving
    pass-through agreements requires a breach by Zachry:
    We hold that Texas recognizes pass-through claims. Consequently, if
    the contractor is liable to the subcontractor for damages sustained by
    the subcontractor, pursuant to a pass-through agreement the contractor
    can bring an action against the owner for the subcontractor’s damages.
    If the owner contests the contractor’s pass-through suit on grounds
    that the contractor is not liable to the subcontractor for the claimed
    damages, the owner bears the burden of proof.
    Interstate Contracting Corp. v. City of Dallas, 
    135 S.W.3d 605
    , 607, 619–20 (Tex.
    2004). Thus, the court in Interstate Contracting required only that Zachry “remain
    liable to the subcontractor for damages sustained by the subcontractor.” Id. at 619.
    The Interstate Contracting court also recognized a general contractor’s decision to
    27
    A pass-through claim is a claim (1) by a party who has suffered damages (in this case,
    the Sub), (2) against a responsible party with whom it has no contract (here, the Port); and
    (3) presented through an intervening party (Zachry) who has a contractual relationship with both.
    Interstate Contracting Corp. v. City of Dallas, 
    135 S.W.3d 605
    , 610 (Tex. 2004) (citing Carl A.
    Calvert, Pass Through Claims and Liquidation Agreements, Construction Lawyer, Oct. 18, 1998,
    at 29; 3 Bruner and O’Connor on Construction Law § 8:51 (2003)). “Instead of one lawsuit
    between a subcontractor and general contractor and another between the general contractor and
    the owner, pass-through claims permit a contractor to pursue its subcontractor’s claims directly
    against the owner.” Id. (citing 3 Bruner and O’Connor on Construction Law § 8:51).
    44
    hire a subcontractor to perform work necessitated by the owner’s breach does not
    preclude the contractor from recovering the cost for the sub.              Id. at 611.
    “Otherwise, the owner could receive a windfall because the subcontractor lacked
    privity with the owner and the contractor lacked standing to sue the owner for
    damages suffered by the subcontractor.” Id. at 615–16.
    Zachry established its continuing liability to the Sub for the costs the jury
    assessed. In the Management Services Agreement (“MSA”) between Zachry and
    the Sub, Zachry promised (1) “to pay to [the Sub] the Reimbursable Costs” the Sub
    incurred while performing services for Zachry, and (2) to pay to the Sub any
    payments it received from the Port. In the Pass-Through Agreement between the
    two, Zachry “agree[d] . . . it is liable to [the Sub], to present the [the Sub’s] Claims
    and remit any recovery from the Port of Houston to [the Sub], in accordance with
    the terms of this Agreement.” The burden therefore shifted to the Port to negate
    this continuing liability: “If the owner disputes that this requirement [of continuing
    liability] has been met, it bears the burden of proving, as an affirmative defense,
    that the pass-through arrangement negates the contractor’s responsibility for the
    costs incurred by the subcontractor.” Id. at 619–20.
    Referencing section 3.2 of the MSA, the Port asserts Zachry might not
    remain liable to the Sub by speculating that owners on other MSA contracts might
    have paid Zachry more than the Reimbursable Costs on their contracts. This
    section provides, in pertinent part,
    Zachry shall have no obligation to pay or reimburse [the Sub] for any
    Reimbursable Costs in excess of the Contract Payments. Therefore, if
    the Contract Payments received by [the Sub] are less than the
    Reimbursable Costs, Zachry will have no liability for any such
    shortfall. If the Contract Payments exceed the Reimbursable Costs,
    the parties shall confer and agree upon a mutually satisfactory
    45
    allocation of any such excess amounts between the Parties consistent
    with the intents and purposes of the Corporate Restructuring.
    According to the Port, any excess payments from any other contracts controlled by
    the MSA would limit Zachry’s liability for reimbursable costs for the Port
    Contract. But the MSA unambiguously states, “Zachry agrees to pay to [the Sub]
    the Reimbursable Costs.” The Port reads section 3.2 of the MSA to limit Zachry’s
    obligation to pay reimbursable costs when contract payments exceed reimbursable
    costs. But this section does not suggest that allocation of “such excess amounts”
    limits any reimbursable costs Zachry must pay to the Sub on other contracts.
    Finally, the Pass-Through Agreement explicitly requires Zachry to “remit any
    recovery from the Port of Houston” to the Sub. Thus, there is simply nothing in
    any of the agreements that limits Zachry’s liability to the Sub, and the Port has not
    born its burden of proving, as an affirmative defense, that the Pass-Through
    Agreement negated Zachry’s responsibility for the costs incurred by the Sub. See
    id.
    Regarding the Port’s assertion that Zachry provided no evidence that it had
    any liability to the Sub, Zachry’s vice president, John Abiassi, confirmed Zachry’s
    continuing liability to the Sub. Abiassi explained that Zachry was liable to the Sub
    for “any costs incurred . . . after January 1 of 2008.” Abiassi further testified that
    Zachry agreed to reimburse the Sub for any costs the Sub incurred after January 1
    and to remit any claims from this lawsuit that are associated with those costs.
    Thus, there is more than a scintilla of evidence that Zachry had continuing liability
    to the Sub for the Sub’s costs incurred after January 1, 2008. See City of Keller,
    168 S.W.2d at 810.
    46
    B.       Governmental Immunity Does Not Bar the Pass-Through Claims
    Finally, the Port further asserts, in two sentences (excluding citations), that
    governmental immunity bars Zachry’s pass-through claim:               “[The Port] has
    immunity for breach of a contract to which [the Port] is not a party. Before
    enactment of Chapter 271, the Court in Interstate said immunity may bar a pass-
    through claim against the government.”           Yet the Texas Supreme Court, in
    Interstate Contracting, explained why it specifically chose not to address the issue
    of sovereign immunity. Id. at 620 (“Although the questions certified do not limit
    our answers, we decline to extend our answers in this case to the issue of sovereign
    immunity, which is well beyond the scope of the questions certified. Doing so
    would require us to venture into the facts of this particular case and analyze the
    merits of the parties’ claims at issue before the Fifth Circuit Court of Appeals,
    rather than provide answers solely as to the status of the Texas law on the
    questions asked.”). Thus, we disagree with the Port’s assertion that the court in
    Interstate Contracting stated that governmental immunity may bar a pass-through
    claim.
    Further, our sister court in San Antonio was squarely presented with the
    issue of whether governmental immunity bars a pass-through claim in City of San
    Antonio v. Valemas, Inc., No. 04-11-00768-CV, 
    2012 WL 2126932
     at *1–7 (Tex.
    App.—San Antonio June 13, 2012, no pet.) (mem. op.). The San Antonio court,
    after a thorough analysis, determined that governmental immunity did not bar the
    pass-through claim of the subcontractor. See id. at *7. In determining this issue,
    the San Antonio court examined the language of section 271.152 of the Local
    Government Code, as well as several other relevant provisions of Chapter 271. See
    id. at *5–6. After examining the language of the statutory provisions, the San
    Antonio court stated, “We find nothing in any of these sections to show the
    47
    Legislature intended to exclude pass through claims from the waiver provision in
    section 271.152.” Id. at *6. The court of appeals then went on to consider the
    legislative history and bill analysis of section 271.152. See id. at *6. The court
    noted that the legislative history “strongly suggests” the Legislature intended to
    enact a “broad waive for local governmental entities in the contractual setting.” Id.
    And the bill analysis suggested that “enactment of section 271.152 was based on
    the Legislature’s recognition of the inherent unfairness in allowing governmental
    entities to enter into contracts, but then avoid [their] obligations under such
    contracts by claiming immunity.” Id.
    Ultimately, the San Antonio court explained:
    It is common knowledge that when a local governmental entity enters
    into a contract for extensive renovations or construction, the general
    contractor with whom it contracts will subcontract with others. If a
    local governmental entity is immune from pass through claims,
    requiring subcontractors to sue the general contractor to recover rather
    than rely on the general contractor to pursue such claims, smaller
    subcontractors will be less likely to risk entering such agreements-
    knowing that in the event the contractor is unable to pay because of
    non-payment by the governmental entity they will be forced to engage
    in expensive litigation, the cost of which they may not be able to bear,
    or simply write the matter off as a loss. This puts subcontractors into
    the same position as contractors, and as recognized by the supporters
    of the bill that proposed section 271.152 in the context of general
    contractors, will make many highly qualified subcontractors,
    especially small businesses, hesitant to enter into such contracts. This
    will discourage and disadvantage a diverse range of bidding
    subcontractors and limit the choices of general contractors in direct
    opposition to what the bill was intended to do.
    Accordingly, we hold that just as it is inconsistent with the
    purpose of section 271.152 to construe it to deny waiver to assignees
    of those who enter into contracts subject to subchapter I, so is it
    inconsistent to deny waiver to pass through claims brought by a
    contractor against a local governmental entity on a subcontractor’s
    behalf. To hold otherwise would subject subcontractors to the same
    48
    risk of non-redressable breach the statue sought to eliminate, resulting
    in subcontractors suffering the same problems once suffered by
    general contractors prior to the enactment of section 271.152.
    Id. at *6–7. We agree with the San Antonio court’s rationale and likewise hold
    that governmental immunity does not bar the pass-through claim at issue here. Cf.
    Galveston Indep. Sch. Dist. v. Clear Lake Rehab. Hosp., L.L.C., 
    324 S.W.3d 802
    ,
    810 (Tex. App.—Houston [14th Dist.] 2010, no pet.) (“[W]hen a governmental
    entity and a contracting party enter into a contract subject to subchapter I and
    denominate a third-party beneficiary of that contract, the third-party beneficiary’s
    claim for breach of contract falls within the waiver of immunity authorized under
    section 271.152.”).
    For the above-described reasons, we overrule the Port’s tenth issue in its
    entirety.28 See Tex. R. App. P. 47.1.
    X. Conclusion
    We have addressed and overruled all the issues the Port raised that are
    necessary to the disposition of this appeal. See Tex. R. App. P. 47.1. For the
    foregoing reasons, we affirm the judgment of the trial court.
    /s/    Sharon McCally
    Justice
    Panel consists of Justices Christopher, Boyce, and McCally.
    28
    The remainder of the Port’s arguments in this section of its brief are contingent upon
    our sustaining one of the issues addressed supra.
    49