Rail v. City National Bank ( 1893 )


Menu:
  • Appellant and one Joe Cain, by a contract in writing, undertook to erect for appellee a stone and brick building in the city of Fort Worth for the sum of $19,000, and to secure the performance of this contract on their part, entered into a bond with sureties. During the progress of the work Cain died. Appellant claims, that soon thereafter a verbal contract was entered into between him and the bank, by which he was released from his written obligation for the performance of the entire contract, but that he was only to complete the stone and brick work and receive therefor the sum of $7300. This is the contract declared upon in this suit. In the petition the appellant alleged, that this new verbal contract was made with appellee through its authorized agent. This issue was met with a denial on the part of appellee, both as to the existence of the new contract and the authority to make it. The evidence was conflicting as to whether any such subsequent contract ever was entered into, and there was little or no evidence that the person who, appellant claims, represented the bank in making the contract, to-wit, John Nichols, vice-president and director at the time, had any authority to make such a contract.

    The court submitted to the jury as grounds of recovery, (1) whether any such contract was made with an authorized agent of appellee as alleged; and if not, (2) whether appellee had afterwards ratified such contract. Upon these issues the jury returned a verdict in favor of appellee; hence this appeal. *Page 559

    Appellant complains, by different assignments of error, that the court should have charged the jury, that if the bank held out Nichols as having authority, it would be liable for his contract, though in fact he was not authorized to make it. No such state of case was set up in his pleadings. To bind the principal for an unauthorized act of the agent, he must not only hold him out, but the apparent authority must be relied on in good faith and in the exercise of reasonable prudence by the party invoking the conclusive presumption of authority. Mech. on Ag., secs. 83, 84. We understand the rule in this State to be, that an estoppel, which is the principle involved, to be available, must be alleged. Scarbrough v. Alcorn, 74 Tex. 358, and cases there cited. We think, therefore, the court did not err in refusing the several requested instructions presenting this theory of the case to the jury.

    We are also of opinion, that the numerous other requested charges were properly refused, because, in so far as they stated in proper form correct propositions of law applicable to the facts of this case, they were given in the main charge; and that the complaint as made by appellant against the court's charge can not be sustained. Fitzhugh v. Franco-Texan Land Co., 81 Tex. 306 [81 Tex. 306]. This disposes of all the assignments, except that one which calls in question the sufficiency of the evidence to support the verdict, which must also be denied, as the evidence was conflicting.

    The judgment will therefore be affirmed.

    Affirmed.