Hassell Construction Co. Inc., Derivatively by and Through Its Shareholder, Royce Hassell R. Hassell & Company, Inc., and R. Hassell Builders, Inc. v. Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District 18, Walter P. Moore & Associates, Inc., D/B/A Walter P. Moore and Costello, Inc. ( 2023 )


Menu:
  • Opinion issued March 7, 2023.
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-17-00822-CV
    ———————————
    HASSELL CONSTRUCTION CO. INC., DERIVATIVELY BY AND
    THROUGH ITS SHAREHOLDER, ROYCE HASSELL; R. HASSELL &
    COMPANY, INC., AND R. HASSELL BUILDERS, INC., Appellants
    V.
    SPRINGWOODS REALTY COMPANY, SPRINGWOODS REALTY, INC.,
    HARRIS COUNTY IMPROVEMENT DISTRICT #18, AND WALTER P.
    MOORE & ASSOCIATES, INC., D/B/A WALTER P. MOORE, Appellees
    On Appeal from the 333rd District Court
    Harris County, Texas
    Trial Court Case No. 2016-85276
    MEMORANDUM OPINION
    Appellants Hassell Construction Co. Inc., derivatively by and through its
    shareholder, Royce Hassell, R. Hassell & Company, Inc., and R. Hassell Builders,
    Inc. (collectively, “Appellants”) appeal the trial court’s summary judgment in favor
    of Appellees Springwoods Realty Company, Springwoods Realty, Inc., Harris
    County Improvement District #18, and Walter P. Moore & Associates, Inc., d/b/a
    Walter P. Moore (collectively, “Appellees”). In two issues, Appellants argue (1) the
    trial court erred by granting summary judgment in favor of Appellees based on
    limitations because Appellees failed to prove conclusively when Appellants’ causes
    of action accrued or, alternatively, there is a genuine issue of material fact regarding
    the accrual dates precluding summary judgment; and (2) the trial court abused its
    discretion by denying Appellants’ motion to abate the case in favor of Appellate
    Cause No. 01-17-00154-CV, an appeal involving the same set of facts and claims
    for damages, which another Panel of this Court previously decided. See R. Hassell
    & Co., Inc. v. Springwoods Realty Co., No. 01-17-00154-CV, 
    2018 WL 1864627
    (Tex. App.—Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem. op.).
    We affirm the trial court’s judgment.
    Background1
    This appeal is one of the latest judicial proceedings arising from three lawsuits
    involving the same construction project and contract. In August 2011, the Harris
    County Improvement District #18 (“District”) awarded Hassell Construction
    1
    The facts in this section are taken directly from this Court’s opinion in R. Hassell &
    Co., Inc. v. Springwoods Realty Co., No. 01-17-00154-CV, 
    2018 WL 1864627
    , at
    *1–4 (Tex. App.—Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem. op.).
    2
    Company, Inc. (“HCCI”) a contract for roadway construction of a project in Harris
    County, Texas (“Contract”). The project involved the construction of Springwoods
    Village Parkway and related water and sanitary sewer lines, paving, and traffic and
    drainage improvements in connection with ExxonMobil Corporation’s campus in
    Houston, Texas (“Project”).
    HCCI and the District entered into the Contract 2 with HCCI acting as the
    “Contractor” and the District as the “Owner.” Pursuant to an attached “Special
    Condition” document, Springwoods Realty Company (“Springwoods”), the Project
    developer, was also considered an “Owner” for certain purposes under the Contract. 3
    Springwoods was an “Owner” for purposes of approving requests for, and making
    payments to, the Contractor for any portion of the Contract price and “for paying all
    or any damages that might ever be due, including any costs associated with any
    change orders to the Contract.” Costello, Inc. (“Costello”), an engineer on the
    2
    The Contract also includes the Contract Documents attached to the Contract,
    including the Standard General Conditions of the Construction Contract.
    3
    On December 31, 2014, Springwoods Realty Company (1) quitclaimed its interest
    in the subject Project to a newly formed entity, Springwoods Realty, Inc., and (2)
    transferred and assigned to the new entity the right, title, and interest in and to all
    contracts to which Springwoods Realty Company was a party and delegated all
    duties and obligations owed by Springwoods Realty Company under those contracts
    to Springwoods Realty, Inc. In 2015, Springwoods Realty Company, which had
    changed its name to Springwoods Old Realty Company, voluntarily dissolved. For
    purposes of this opinion, we refer to Springwoods Realty Company n/k/a
    Springwoods Old Realty Company and Springwoods Realty, Inc. collectively as
    “Springwoods.”
    3
    Project, designed the water and sanitary sewer systems and was tasked with
    approving or denying any submitted change orders.4 Walter P. Moore & Associates,
    Inc. (“WPM”), who also provided engineering and design services for the Project,
    designed all other improvements on the Project.
    According to HCCI, the Contract contained material provisions integral to the
    timely completion of the Project’s scope of work, including provisions that “time
    was of the essence” and that “HCCI would be paid for the performance of the Scope
    of Work required by the drawings.” HCCI alleged that, after its work on the Project
    started, the District and Springwoods made over 500 revisions to the construction
    plans, which materially changed the scope of work, the Contract price, and the
    timeline of the Project. Appellants contend that although they properly submitted
    delay claims based on these revisions to WPM and Costello pursuant to the dispute-
    resolution procedures in the Contract, the District and Springwoods refused to pay
    for the changes and further accelerated the work, resulting in damage to HCCI. The
    parties attempted to resolve their disputes through the Contract’s dispute-resolution
    process. After their attempts proved unsuccessful, Appellants elected to submit their
    4
    Hassell also named Costello as a defendant in the underlying lawsuit, but it later
    nonsuited its claims against Costello prior to the trial court’s final judgment.
    Consequently, the trial court did not rule on Costello’s motion for summary
    judgment, and Costello is not a proper party to this appeal. See Gray v. Allen, 
    41 S.W.3d 330
    , 331 n.2 (Tex. App.—Fort Worth 2001, no pet.) (stating “appellee”
    must be party to final judgment and someone against whom appellant raises issues
    or points of error in its appellate brief).
    4
    payment claims to mediation, as permitted under the Contract. The parties mediated
    their delay claims unsuccessfully on July 2, 2012.
    On July 26, 2012, HCCI sued the District and Springwoods based on their
    refusal to pay HCCI’s delay claims. Appellants contend that although HCCI filed
    suit on July 26, 2012, none of the parties to the lawsuit acted as if negotiations were
    at an impasse or that the Contract had been terminated. According to Appellants,
    they kept performing under the Contract through December 28, 2012. Appellants
    allege that they continued to negotiate their delay claims even after mediation proved
    unsuccessful, citing to correspondence exchanged between various parties from July
    2012 until July 2013, when Appellants were officially removed from the Project.
    A.    First Lawsuit (Trial Court Case Number 2012–42981)
    On July 26, 2012, HCCI filed suit against the District and Springwoods (“First
    Lawsuit”). HCCI asserted claims against Springwood and the District for breach of
    contract and against Springwoods for fraud. In the alternative, HCCI asserted claims
    against the District under Texas Local Government Code section 271.153(a)(2), 5 and
    against Springwoods for assumpsit, quantum meruit, and unjust enrichment. The
    District and Springwoods each filed a third-party petition against WPM, who had
    provided engineering and design services on the Project. The District brought claims
    5
    TEX. LOC. GOV’T CODE § 271.153(a)(2) (governing breach-of-contract damages
    against local governmental entities, including amounts owed for change orders).
    5
    against WPM for breach of contract, breach of warranty, and negligence seeking
    indemnity. Springwoods asserted a negligence claim against WPM, also seeking
    indemnity. WPM, in turn, filed a third-party petition against Costello seeking
    contribution.
    On September 15, 2014, R. Hassell & Company, Inc. (“RHC”) and Hassell
    Builders, Inc. (“RHB”)6 filed their First Petition in Intervention, alleging that RHC,
    RHB, and HCCI were partners, noting that its “joint venture relationship” with HCCI
    was disclosed to the District and Springwoods. RHC and RHB asserted that they
    provided project management and performed work on the Project using RHC’s and
    RHB’s equipment and personnel, and HCCI submitted RHC’s and RHB’s progress-
    payment reports to the District and Springwoods. HCCI, RHC, and RHB then split
    the proceeds received from the Project, with “99% to RHC [and RHB] and 1% to
    HCCI.”
    RHC and RHB further alleged that HCCI had filed suit against Springwoods
    and the District “under the name HCCI representing the partnership.” RHC and
    RHB asserted that, “as a partner of HCCI,” they had a justiciable interest in HCCI’s
    6
    The First Petition in Intervention also included as intervenors: R. Hassell Holding
    Company, Inc. and Royce and Sylvia Hassell. The intervenors explained that RHC,
    RHB, and R. Hassell Holding Company, Inc. are corporations owned by Royce and
    Silvia Hassell and managed by Royce Hassell, who is President of each of the
    companies. HCCI is also owned by various Hassell family members, including
    Royce Hassell. RHB, RHC, and HCCI, derivatively and through its purported
    shareholder Royce Hassell, are the Appellants in the present appeal.
    6
    lawsuit, because they could have brought all or part of the original suit in their own
    name and RHC’s and RHB’s claims “ar[o]se from the claims” made by HCCI. RHC
    and RHB also added conspiracy claims against the District, Springwoods, and the
    law firm of Coats Rose, which previously represented HCCI. RHC and RHB alleged
    that Coats Rose had tortiously interfered with RHC’s and HRC’s relationship with
    HCCI.    RHC and RHB also filed “cross-claims” against HCCI for breach of
    fiduciary duty and asserted that HCCI, “acting in concert with” Coats Rose, had
    intentionally inflicted emotional distress on the Hassell family.
    HCCI filed a general denial to RHC’s and RHB’s First Petition in
    Intervention, including a verified denial that a partnership existed between HCCI,
    RHB, and RHC. HCCI also moved to strike RHC’s and RHB’s intervention arguing
    that (1) RHC and RHB had waited over two years to intervene in the suit, (2) RHC
    and RHB lacked a justiciable interest in the lawsuit because HCCI, and not RHC or
    RHB, had been awarded the Contract and designated as Contractor on the Project,
    (3) RHC and RHB lacked standing because they were not a party to the Contract and
    could not bring suit in their own name, (4) even if RHC or RHB had damages apart
    from HCCI, those claims would still need to be asserted by HCCI as pass-through
    claims and could not be asserted directly by RHC or RHB, and (5) RHC’s and RHB’s
    intervention multiplied the issues excessively by inserting RHC and RHB and their
    partnership allegations into the lawsuit. On October 20, 2014, after a hearing, the
    7
    trial court struck RHC’s and RHB’s First Petition in Intervention. RHC and RHB
    did not appeal the trial court’s order on their First Petition in Intervention.
    On February 2015, RHC and RHB filed a suggestion of bankruptcy on behalf
    of the “Hassell 2012 Joint Venture and Springwoods Joint Venture,” seeking to stay
    HCCI’s lawsuit in the trial court.          In the following months, the District,
    Springwoods, and WPM filed motions for summary judgment against HCCI, and a
    hearing was set for May 29, 2015.7 On May 27, 2015, the United States Bankruptcy
    Court for the Southern District of Texas sent a “Request for Abatement” to the trial
    court requesting abatement of the underlying proceedings. On May 29, 2015, the
    trial court abated the case.
    In April 2016, the Bankruptcy Court granted RHC’s motion to dismiss its
    bankruptcy petition. The trial court then reinstated the case and reset the hearing on
    the pending motions for summary judgment for October 7, 2016. A week prior to
    the hearing, RHC and RHB filed their Second Petition in Intervention, asserting they
    had a “right to intervene as principal on the contract at issue.”8 RHC and RHB
    asserted that they, and not HCCI, had received and reviewed the bid package
    7
    Costello joined in the motions for summary judgment against HCCI, but HCCI
    voluntarily nonsuited its claims against Costello prior to the trial court’s final
    judgment. As such, the trial court did not rule on Costello’s motion for summary
    judgment.
    8
    Although RHC, RHB, and Royce and Silvia Hassell filed the First Petition in
    Intervention, only RHC and RHB filed the Second Petition in Intervention.
    8
    information for the Project and had submitted the winning bid in the name of HCCI.
    RHC and RHB asserted that HCCI had “pretend[ed] it performed as contractor.”
    According to RHC and RHB, after RHC and RHB 9 were awarded the Contract,
    HCCI confirmed to the District that RHC and RHB were “the Contractor[s]
    performing the Contract under the name of [HCCI].” Although the Contract had
    been awarded “in the name of HCCI,” RHC and RHB claimed they mobilized their
    equipment and employees, communicated with Springwoods, the District, Costello,
    and WPM, and controlled all the work on the Project. After RHC and RHB
    encountered delays, they retained counsel, who filed suit “on behalf of and in
    consultation with HCCI.” RHC and RHB alleged that they “filed the petition
    because [they were] the Contractor[s] on the Project and held a good-faith belief that
    [they were], at a minimum, a partner with HCCI in the [Project]; or alternatively,
    that HCCI served as RHC’s [and RHB’s] agent in bidding and securing the
    [Contract], as HCCI had done on other projects.”
    RHC and RHB argued that they had a justiciable interest in the suit because
    they could have brought the same action, or any part thereof, in their own names.
    They asserted that they had acted as principals, with HCCI as agent, in bidding and
    securing the Contract. RHC and RHB further argued that their intervention would
    9
    RHB and RHC were referred to collectively as RHC in the Second Petition for
    Intervention.
    9
    not complicate the case because they sought to recover their damages “from the same
    defendants that HCCI alleged [had] caused it harm.” RHC and RHB argued that
    their intervention was essential to protect their interests because the defendants had
    argued in their summary judgment motions that they were entitled to judgment as a
    matter of law because HCCI could not establish it had suffered any damages and,
    instead, the damages had been suffered by RHC and RHB. RHC and RHB asserted
    that the defendants, through their summary judgment motions, sought a judgment
    that would prejudice their rights to recover.
    Like HCCI, RHC and RHC asserted claims for breach of contract against the
    District and Springwoods in their Second Petition in Intervention, and alternative
    claims against the District under Texas Local Government Code section 271.153.
    Additionally, RHC and RHB asserted claims against the District and Springwoods
    for assumpsit, quantum meruit, and unjust enrichment. RHC and RHB also brought
    new claims against the District, Springwoods, WPM, and Costello for common law
    fraud, fraud by nondisclosure, fraudulent inducement, and conspiracy alleging they
    each knew that the construction plans RHC and RHB had relied upon to submit their
    bid for the Project were not intended to be the actual plans, and the District,
    Springwoods, WPM, and Costello had “secretly agreed with each other to delay
    payment [for change orders] to force RHC [and RHB] to bear the costs.” RHC and
    RHB also brought a breach of warranty claim against the District, Springwoods,
    10
    WPM, and Costello, alleging they had “breached their warranty that the plans
    provided to bidders were suitable to bid and build the Project.”
    HCCI nonsuited its claims against Springwoods and the District.
    Springwoods, the District, WPM, and Costello then moved to strike RHC’s and
    RHB’s Second Petition in Intervention as untimely, moot, and barred by judicial
    admissions. They noted that RHC and RHB had waited over four years after the
    inception of the lawsuit to file their Second Petition in Intervention, just one week
    before the scheduled hearing on the pending summary judgment motions.
    Springwoods, the District, WPM, and Costello further asserted that RHC’s and
    RHB’s allegation of a principal-agent relationship with HCCI was contradicted by
    RHC’s and RHB’s allegations in their First Petition in Intervention that RHC, RHB,
    and HCCI had performed the Project as part of a “joint venture” and were “partners”
    on the Project.10 They asserted that an intervention by RHC and RHB would
    excessively multiply the issues by requiring litigation of various new issues, and that
    “[h]ad RHC [and RHB] been allowed to intervene, [they] would have become a new
    and the only plaintiff[s]” and “would have created an entirely new lawsuit.”
    After a hearing, the trial court granted the motion to strike RHC’s and RHB’s
    Second Petition in Intervention. Springwoods, the District, and WPM filed a joint
    10
    Royce Hassell, Silvia Hassell, and R. Hassell Holding Company, Inc. were also
    intervenors with respect to the First Petition in Intervention.
    11
    motion and notice of nonsuit, nonsuiting all pending claims against one another
    without prejudice.11 The trial court signed a final judgment dismissing all claims
    and parties consistent with the parties’ nonsuit notices.
    RHC and RHB filed a notice of appeal challenging the trial court’s order
    striking their Second Petition in Intervention.       See R. Hassell & Co., Inc. v.
    Springwoods Realty Co., No. 01-17-00154-CV, 
    2018 WL 1864627
     (Tex. App.—
    Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem. op.). On appeal, RHC and
    RHB argued the trial court erred in granting the motion to strike their Second Petition
    in Intervention because RHC and RHB established they had a justiciable interest in
    the suit. They argued the striking of their petition prejudiced RHC and RHB as a
    matter of law because they were deprived of the benefit of the relation-back doctrine
    to respond to limitation challenges and the “thousands of pages of discovery
    accumulated between 2012 and 2016. Id. at *5.
    On April 19, 2018, this Court held the trial court had not abused its discretion
    by granting the motion to strike RHC’s and RHB’s Second Petition in Intervention
    because RHC and RHB had not shown that the trial court acted without reference to
    any guiding rules or principles based on evidence of delay and multiplicity of claims.
    Id. at *8. This Court did not reach the question of “whether RHC [and RHB] could
    11
    Costello was not a party to the motion because it had not asserted any claims in the
    First Lawsuit.
    12
    have brought the same action, or any part thereof, in [their] own name or whether
    the intervention [was] essential to effectively protect RHC’s [and RHB’s] interest.”
    Id. at *7. RHC and RHB subsequently filed a petition for review, which the Texas
    Supreme Court denied on April 23, 2021.
    In December 2016—a little more than a week after the trial court struck
    RHC’s Second Petition in Intervention—two new lawsuits were filed involving the
    same parties and mostly the same set of facts at issue in the First Lawsuit. HCCI
    filed suit against Springwoods and the District (“Second Lawsuit”), and Appellants
    separately filed the lawsuit giving rise to the present appeal against Springwoods,
    the District, Costello, and WPM (“Third Lawsuit”).
    B.    Second Lawsuit (Trial Court Case Number 2016-84811-7)
    On December 9, 2016, HCCI refiled the First Lawsuit as a new lawsuit in the
    333rd Judicial District Court, Harris County, Texas. The case was styled Cause No.
    2016-84811, Hassell Construction Co., Inc. v. Springwoods Realty, Inc. and Harris
    County Improvement District #18. As in the First Lawsuit, HCCI asserted claims
    against Springwood and the District for breach of contract and against Springwoods
    for fraud. In the alternative, HCCI asserted claims against the District under Texas
    Local Government Code section 271.153(a)(2), and against Springwoods for
    assumpsit, quantum meruit, and unjust enrichment. Springwoods counterclaimed
    against HCCI for “misrepresentation and omission liability” and breach of contract.
    13
    Springwoods filed a third-party petition against Costello and WPM for negligence
    and contribution and the District filed a third-party petition against Costello and
    WPM for indemnity, breach of contract, breach of express or implied warranty,
    negligence, and contribution.
    Springwoods and the District moved for summary judgment on HCCI’s
    claims based on the statute of limitations. On September 5, 2017, the trial court
    granted both motions, in part, and dismissed HCCI’s claims with prejudice, except
    for HCCI’s claim stemming from an invoice dated December 28, 2012.
    Springwoods and the District nonsuited their claims against Costello and WPM on
    December 27, 2017 and January 9, 2018, respectively.
    On June 24, 2018, Springwoods, the District, and HCCI executed a Release
    and Settlement Agreement (“Settlement Agreement”) resolving their claims with
    respect to the Contract and the Project. Pursuant to the Settlement Agreement,
    Springwoods, the District, and HCCI filed a Joint Motion to Dismiss with Prejudice
    in the Second Lawsuit. The trial court signed an Order for Dismissal with Prejudice
    on July 10, 2018. As relevant here, the Settlement Agreement states, “This is
    intended to be a global release of HCCI’s claims against the Owner/Developer
    Releasees [Springwoods and the District] with respect to the Contract and the
    Project, including all of HCCI’s claims against the Owner/Developer Releasees
    [Springwoods and the District] that could be asserted by HCCI itself or that could
    14
    be asserted derivatively on its behalf.” “HCCI is not acting for R. Hassell, as defined
    in paragraph 8(B), below, and this release does not release or affect any direct claims
    that R. Hassell may have against [Springwoods and the District], as opposed to
    derivative claims through HCCI, the existence of which direct claims is denied by
    Springwoods and the District.”12
    On May 13, 2022, Springwoods moved to dismiss parts of the present appeal
    as moot based on the Settlement Agreement.13
    C.    Third Lawsuit (Trial Court Case Number 2016-85276)
    On December 12, 2016, Appellants RHC, RHB, and HCCI, derivatively by
    and through its shareholder Royce Hassell (“Hassell”),14 filed suit against
    Springwoods, the District, Costello, and WPM seeking to recover damages for
    increased costs they allegedly incurred in performing the Contract. This Third
    Lawsuit is the subject of the present appeal.
    Appellants Hassell, RHB, and RHC asserted claims against all defendants for
    breach of contract, common law fraud, fraud by nondisclosure, fraudulent
    inducement, conspiracy, assumpsit, quantum meruit, unjust enrichment, and
    12
    The Settlement Agreement defines “R. Hassell” as “Royce Hassell, Sylvia Hassell,
    R. Hassell & Company, Inc., or R. Hassell Builders, Inc.[,] together with any and
    all affiliated persons or entities.”
    13
    We address the motion to dismiss in further detail later in this opinion.
    14
    We refer to HCCI, the party in the Third Lawsuit and in this appeal, as “Hassell”
    because HCCI sued derivatively by and through its purported shareholder Royce
    Hassell. We refer to Royce Hassell by his full name.
    15
    attorney’s fees. Appellants also asserted they are entitled to recover from the District
    for breach of contract under Texas Local Government Code section 271.153(a)(2).
    Appellees answered the Third Lawsuit advancing limitations as an affirmative
    defense.
    Springwoods moved for summary judgment on Appellants’ claims based on
    the statute of limitations. Springwoods also asserted it was entitled to summary
    judgment on Appellants’ quantum meruit claim because there is a written Contract
    precluding the claim.
    After Springwoods moved for summary judgment, Appellants moved to abate
    the Third Lawsuit pending resolution of RHC’s and RHB’s appeal to this Court of
    the trial court’s order in the First Lawsuit striking their Second Petition in
    Intervention. Appellants argued that abatement was necessary because RHC’s and
    RHB’s appeal “involve[d] the same claims and parties, and was filed earlier in time,
    it occupie[d] the dominant position with respect to these claims,” and alternatively,
    “an outcome favorable to Appellants in the [First Lawsuit] would render any action
    by th[e trial court in the Third Lawsuit] an advisory opinion.”
    The District then moved for summary judgment joining and incorporating “by
    reference, as though fully set forth herein, the Motion for Summary Judgment of
    16
    Springwoods Realty Company and Springwoods Realty, Inc.,” asking the trial court
    to enter judgment in its favor “and against Plaintiffs on all causes of action.”15
    WPM also moved for summary judgment on Appellants’ causes of action
    “based on the arguments presented in Springwoods’ Motion and the additional
    factual and legal issues identified below.”          In addition, WPM asserted that
    Appellants’ “contract claims must be dismissed because there is no contract between
    [Appellants] and WPM.” Costello also filed a motion for summary judgment in
    which it stated that it “join[ed] and adopt[ed], by reference, as though fully set forth
    herein,” WPM’s motion for summary judgment.
    On April 20, 2017, the trial court denied Appellants’ motion to abate.
    Appellants subsequently nonsuited their claims against Costello without prejudice
    and the trial court granted Springwoods’ and the District’s motions for summary
    judgment on Appellants’ claims based on limitations. As a result, only Appellants’
    claims against WPM and WPM’s corresponding motion for summary judgment
    remained pending. On September 27, 2017, the trial court issued a final judgment
    granting WPM’s motion for summary judgment thus disposing of the only remaining
    15
    The District also filed a reply stating that it “hereby joins and adopts by reference,
    as though fully set forth herein, Springwoods’ Reply to Plaintiffs’ Opposition to
    Springwoods’ [Defendants’] Motion for Summary Judgment.”
    17
    claims in the lawsuit.16 The trial court’s prior summary judgment orders merged
    into the September 27, 2017 judgment. See Bonsmara Nat. Beef Co., L.L.C. v. Hart
    of Tex. Cattle Feeders, L.L.C., 
    603 S.W.3d 385
    , 390 (Tex. 2020) (“When a trial court
    renders a final judgment, the court’s interlocutory orders merge into the judgment. .
    .”).
    Appellants filed a notice of appeal on October 27, 2017, challenging the trial
    court’s final judgment and the trial court’s denial of Appellants’ motion to abate.
    The appeal was set for submission on May 17, 2018.
    On July 3, 2018, Appellants filed a Suggestion of Bankruptcy advising this
    Court that RHC had filed a bankruptcy petition in the Southern District of Texas and
    an automatic stay precluded the prosecution of the appeal. See 
    11 U.S.C. Section 362
    (a). This Court abated the appeal on July 10, 2018. On November 24, 2020, this
    Court granted Springwoods’ motion to reinstate the appeal and advised the parties:
    The appellate record and the parties’ brief were filed prior to the
    abatement. The parties are instructed to inform the Court by December
    21, 2020 if they intend to rely upon their prior briefing or file a
    supplemental brief.
    On March 1, 2021, Appellants filed a supplemental brief in which they raised
    issues and arguments not previously raised in their original briefing. Appellants
    16
    The trial court’s order granting summary judgment in favor of WPM on Appellants’
    breach of contract claims does not specify whether it granted summary judgment
    based on limitations or lack of privity.
    18
    argued for the first time in their supplemental brief that the trial court erred in
    granting summary judgment on their claims because (1) Appellants’ causes of action
    never accrued under Texas Property Code § 53.053(b)(2), (2) Appellants’ causes of
    action are governed by the ten-year statutes of repose in Texas Civil Practice &
    Remedies Code §§ 16.008 and 16.009, and (3) the legal authority the trial court
    relied on with respect to the length of the statute of limitations for their civil
    conspiracy claim changed during the pendency of this appeal. Appellants did not
    assert error based on Texas Property Code § 53.053(b)(2) or Texas Civil Practice &
    Remedies Code §§ 16.008 and 16.009 in their opening brief or their reply brief, nor
    did they challenge the trial court’s granting of summary judgment on their civil
    conspiracy claim in their opening brief. Thus, these issues are waived. See Los
    Compadres Pescadores, L.L.C. v. Valdez, 
    608 S.W.3d 829
    , 838 n.10 (Tex. App.—
    Corpus Christi–Edinburg 2019), aff’d, 
    622 S.W.3d 771
     (Tex. 2021) (“We need not
    address a new issue not raised by the appellant in the original brief.”) (citing
    Donaldson v. Tex. Dep’t of Criminal Justice-Corr. Insts. Div., 
    355 S.W.3d 722
    , 727
    (Tex. App.—Tyler 2011, pet. denied)); see also Champion v. State, 
    126 S.W.3d 686
    ,
    691–92 (Tex. App.—Amarillo 2004, no pet.) (declining to consider new issues
    raised in supplemental brief).
    Appellants also raised two arguments in their supplemental brief challenging
    the appropriateness of the nonsuits filed in the First Lawsuit. They argue that
    19
    HCCI’s nonsuit of its claims against Springwoods and the District in the First
    Lawsuit violated Texas Rule of Civil Procedure 162 and was ineffective because it
    failed to name the real party in interest. RHC’s and RHB’s appeal from the final
    judgment in the First Lawsuit, however, has been finally adjudicated in a separate
    appeal filed in this Court. 17 This Court held that the trial court did not abuse its
    discretion by granting the motion to strike the Second Petition in Intervention filed
    by RHB and RHC in the First Lawsuit, and the Texas Supreme Court denied RHC’s
    and RHB’s petition for review on April 23, 2021. See R. Hassell & Co., 
    2018 WL 1864627
    , at *8. Thus, Appellants’ issues regarding the nonsuits filed in the First
    Lawsuit are not properly before this Court and we decline to revisit those issues,
    which Appellants raised for the first time in their supplemental brief. See Los
    Compadres Pescadores, L.L.C., 608 S.W.3d at 838 n.10; see also Champion, 
    126 S.W.3d at
    691–92.
    D.    Contract Terms
    The Contract includes the contract documents attached to the Contract,
    including the Standard General Conditions of the Construction Contract (“General
    Conditions”). Article 6 of the Contract and Article 14 of the General Conditions,
    which are attached to the Contract and incorporated by reference, set forth the
    17
    See R. Hassell & Co., Inc. v. Springwoods Realty Co., No. 01-17-00154-CV, 
    2018 WL 1864627
     (Tex. App.—Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem.
    op.).
    20
    parties’ agreed upon payment procedures.         Paragraph 14.01.A of the General
    Conditions requires HCCI to prepare and maintain a schedule “allocating portions
    of the Contract Price to various portions of the Work.” The schedule will “serve as
    the basis for progress payments [made to HCCI].”
    Under Paragraph 14.02 of the General Conditions, HCCI may submit payment
    applications to WPN and Costello, who will then review the applications and make
    a recommendation of payment to Springwoods. Specifically, Paragraph 14.02 states
    that “not more often than once a month[, HCCI] shall submit to [either WPM or
    Costello]18 for review an Application for Payment filled out and signed by [HCCI]
    covering the Work completed as of the date of the Application and accompanied by
    such supporting documentation as is required by the Contract Documents.
    Generally, payment of any recommended amount is due to HCCI ten days after
    Costello or WPM issue its payment recommendation to Springwoods. Paragraph
    8.04 states that Springwoods “shall make payments to [HCCI] when they are due as
    provided in Paragraphs 14.02.C.” Article 6 of the Contract, which contains similar
    provisions, also states that Springwoods “shall make progress payments on account
    of the Contract Price on the Basis of [HCCI’s] Applications for Payment during the
    performance of the Work.”
    18
    Under the Contract, Costello was tasked with approving or denying any applications
    for payment associated with the water and sanitary sewer system, and WPM was
    responsible for approving or denying all other applications for payment.
    21
    The Contract also includes a mechanism through which either party may
    request an adjustment to the Contract Price. If the parties are unable to agree on the
    proper disposition of the request, “a Claim may be made thereof as provided in
    Paragraph 10.05.” Paragraph 10.05(a) requires the parties to submit “all Claims” to
    WPM or Costello and states that “[a] decision [by WPM or Costello] shall be
    required as a condition precedent to any exercise by [Springwoods or HCCI] of any
    rights or remedies either may otherwise have under the Contract or the Laws and
    Regulations in respect of such Claims.” A “claim” is defined as a “demand or
    assertion by Owner or Contractor seeking an adjustment of Contract Price . . . or
    other relief with respect to the terms of the Contract.” Any Claim must be delivered
    to WPM or Costello no later than 30 days after the start of the event precipitating the
    Claim.
    The Contract also states that WPM’s or Costello’s decision becomes final and
    binding unless a party invokes the Contract’s dispute resolution procedure set forth
    in Article 16. Paragraph 16.01 states that either party “may request mediation of any
    Claim submitted [to Costello or WPM] for a decision under Paragraph 10.05 before
    such decision becomes final and binding.” Paragraph 16.01.A–B states the “process
    shall be concluded within 60 days of the request. The date of termination of the
    mediation shall be determined by application of the” Construction Industry
    Mediation Rules of the American Arbitration Association.          Paragraph 16.01.C
    22
    further states that if a Claim is not resolved by mediation, WPM’s or Costello’s
    decision becomes final and binding within 30 days after “termination of mediation,”
    unless (1) a party “elects in writing to invoke any dispute resolution process provided
    for the Supplementary Conditions,” (2) the parties agree to submit their claims to
    another dispute resolution process, or (3) one of the parties gives written notice to
    the other party of its intent to submit the Claim to a court of competent jurisdiction.
    Paragraph 16.18 states that HCCI “shall carry on the Work and adhere to the
    Progress Schedule during all disputes or disagreements with [Springwoods]. No
    work shall be delayed or postponed pending resolution of any disputes or
    disagreements.”
    Paragraph 17.03 further provides, “The duties and obligations imposed by
    these General Conditions and the rights and remedies available hereunder to the
    parties hereto are in addition to, and are not to be construed in any way as a limitation
    of, any right and remedies available to any or all of them which are otherwise
    imposed or available by Laws or Regulations . . . .”
    Motion to Dismiss
    On May 13, 2022, Springwoods filed a partial motion to dismiss Hassell’s
    present appeal for want of jurisdiction. The District joined the motion and adopted
    23
    Springwoods’ arguments by reference.19 Springwoods and the District argue that
    Hassell’s claims, which are claims Royce Hassell seeks to assert derivatively on
    behalf of HCCI, are moot because HCCI, Springwoods, and the District executed a
    Settlement Agreement on June 24, 2018, settling all claims among HCCI,
    Springwoods, and the District associated with the Contract and the Project. They
    explain that HCCI, Springwoods, and the District moved to dismiss their claims with
    prejudice in the Second Lawsuit, and the trial court granted the motion and signed
    an Order for Dismissal with Prejudice on July 10, 2018.
    Springwoods and the District also argue that Appellants’ challenge of the trial
    court’s refusal to abate the Third Lawsuit pending disposition of RHC’s and RHB’s
    appeal from the First Lawsuit is moot because RHC’s and RHB’s appeal from the
    First Lawsuit has been finally resolved. 20 On May 24, 2022, Appellants filed a
    motion for extension of time to respond to the motion to dismiss.
    After hearing oral argument in this appeal on May 25, 2022, this Court
    requested supplemental briefing from the parties addressing Springwoods’ and the
    District’s motion to dismiss and corresponding jurisdictional arguments.             We
    19
    Although Costello also joined the motion, Costello was nonsuited before the final
    judgment was issued and thus, Costello is not a party to this appeal.
    20
    Springwoods and the District also argued that “Appellants’ Points of Error in Their
    Supplemental Brief [filed on March 1, 2021], Which Address Alleged Errors in the
    First Lawsuit, Are Improper and Rendered Moot by the Disposition of the First
    Appeal.” As previously discussed, the arguments raised in Appellant’s March 1,
    2021 supplemental brief are either waived or not pending before this Court.
    24
    directed the parties to address the impact, if any, the July 10, 2018 Order for
    Dismissal with Prejudice in the Second Lawsuit has on Appellants’ issues in this
    appeal relative to Appellants’ claims against Springwoods, the District, and WPM.
    A.    Settlement Agreement21
    On June 24, 2018, Springwoods, the District, and HCCI executed the
    Settlement Agreement that purportedly resolved the parties’ claims with respect to
    the Project and the Contract. Relevant here, the Settlement Agreement states, “This
    is intended to be a global release of HCCI’s claims against [Springwoods and the
    District] with respect to the Contract and the Project, including all of HCCI’s claims
    against [Springwoods and the District] that could be asserted by HCCI itself or that
    could be asserted derivatively on its behalf.” The Settlement Agreement further
    states, “HCCI is not acting for [Royce Hassell, Sylvia Hassell, R. Hassell &
    Company, Inc., RHC, or RHB] and this release does not release or affect any direct
    claims that [Royce Hassell, Sylvia Hassell, R. Hassell & Company, Inc., RHC, or
    RHB] may have against [Springwoods and the District], as opposed to derivative
    21
    The complicated history of the parties’ ongoing disputes presents unique and
    challenging procedural issues. Over the last 10 years, there have been multiple
    overlapping lawsuits presenting the same or similar issues arising from the Contract
    and the Project and several bankruptcy proceedings initiated while these lawsuits,
    and this appeal, have been pending. Of particular note, the Second Lawsuit was
    purportedly resolved well after the trial court granted summary judgment in the
    Third Lawsuit, the subject of this appeal. It is the resolution of the Second Lawsuit
    after this appeal was filed that forms the basis of much of Springwood’s and the
    District’s motion to dismiss and jurisdictional arguments.
    25
    claims through HCCI, the existence of which direct claims is denied by Springwoods
    and the District.”
    B.    Post Oral Argument Briefing
    In their post oral argument briefing, Appellants argue that RHC and RHB
    were parties to the Second Lawsuit because they “timely intervened in [the Second
    Lawsuit] twice claiming that jurisdiction was improper,” and there are fact issues
    over whether (1) the claims the Second Lawsuit are the same as the claims involved
    in this appeal, (2) Springwoods, the District, and WPM violated the automatic stay
    imposed by Appellants’ bankruptcy proceedings by executing the Settlement
    Agreement and moving to dismiss the Second Lawsuit with prejudice, and (3) the
    “Order for Dismissal with Prejudice” is a valid and existing final judgment or that it
    disposed of issues in this case.22 Appellants further contend that “[t]he lower courts’
    actions created an unusual procedural posture which, in equity and good conscience,
    cannot be undone by a jurisdictional plea in this appeal on limitations.”
    22
    Appellants argue that the “Order for Dismissal with Prejudice” is not a valid final
    judgment because RHC and RHB intervened in the Second Lawsuit and the order
    does not dispose of their affirmative claims for relief. Although Springwoods
    contends that the judgment in the Second Lawsuit is final because RHB and RHC
    “never properly intervened” in that suit, we need not decide whether RHB and
    RHC intervened in the Second Lawsuit or whether there is a final judgment in that
    case because, even assuming the judgment is final, the issues presented in this
    appeal are not moot for the reasons we discuss.
    26
    In its post oral argument briefing, Springwoods argues that the July 10, 2018
    Order for Dismissal with Prejudice in the Second Lawsuit is a final adjudication of
    all of HCCI’s claims with respect to the Project and Contract, and any further
    litigation over such claims by Hassell is barred by the doctrine of res judicata. The
    Settlement Agreement purports to release HCCI’s claims against Springwoods and
    the District “with respect to the Contract and the Project, including all of HCCI’s
    claims against [Springwoods and the District] that could be asserted by HCCI itself
    or that could be asserted derivatively on its behalf.” In a footnote, Springwoods
    contends that the term “derivative” means “all claims asserted by Appellants that
    derive from Springwoods’ contract” with HCCI and “ [ i ] n addition to traditional
    shareholder derivative claims asserted by Royce Hassell or perhaps one or more
    of the other Appellants.”      Springwoods further contends that the Settlement
    Agreement released HCCI’s claims against it, including any claims that could be
    asserted derivatively on HCCI’s behalf, and therefore, HCCI’s issues on appeal are
    moot. The District joined Springwoods’ post oral argument briefing and adopted
    Springwoods’ arguments by reference.
    In its post oral argument brief, WPM adopts Springwoods’ briefing and
    further asserts that RHC’s and RHB’s claims against it are barred by collateral
    estoppel because the trial court granted WPM’s motion for summary judgment in
    the Second Lawsuit on the grounds that HCCI’s claims were barred by the statute of
    27
    limitations and this finding is binding on Hassell and its privities, including RHC
    and RHB. Alternatively, WPM argues that RHC’s and RHB’s claims against it are
    “mooted by the Settlement Agreement and the economic loss rule.” According to
    WPM, RHC and RHB are “not in privity of contract with WPM and without HCCI’s
    claims against the District or Springwoods, [they] cannot recover in any capacity,
    nor can [RHC or RHB] hope to recover through HCCI as its subcontractor[s] on the
    Project.” WPM argues:
    HCCI has no viable claim against WPM because HCCI has released
    Springwoods and the District—the only parties HCCI had contractual
    privity with on this Project. Because Appellants had no contractual
    privity with WPM—a finding below which Appellants have not
    challenged—they cannot recover against WPM in contract. Further,
    Appellants cannot recover in tort because of the economic loss rule.
    In their reply brief, Appellants argue that Appellees “have not met their
    heightened burden to show that [the Order of Dismissal with Prejudice in the Second
    Lawsuit] would, in any case, moot any of the claims before this Panel.” According
    to Appellants, Appellees are relying on “unpleaded, undecided affirmative defenses
    disguised as jurisdictional pleas which were not presented to the Trial Court, which
    implicate multiple fact-issues, and which, resultingly, could not be covered by the
    summary judgment pleadings and the resulting Final Judgment.” Appellants further
    contend that Appellees’ affirmative defenses—such as res judicata, collateral
    estoppel, lack of privity, limitations, or settlement—“are not jurisdictional pleas, but
    pleas that must be raised under the normal pleading protocols for summary judgment
    28
    motions.” Appellants argue their due process rights would be violated if they were
    forced to “address affirmative defenses raised for the first time on appeal without an
    opportunity to address such affirmative defenses to the Trial Court and present
    evidence why there exist genuine issues of material fact,” and, “[i]f necessary,
    Appellants should be allowed to re-plead and not be denied that right by the raising
    of an affirmative defense for the first time before this Panel such that responsive
    pleadings were not called for in the Trial Court and are, therefore, not part of the
    appellate record.” According to Appellants, Appellees did not move for summary
    judgment on any of these newly asserted affirmative defenses, and, thus, it would be
    improper to affirm the granting of summary judgment on these grounds. 23
    23
    WPM moved for summary judgment on Appellants’ breach of contract claim based
    on limitations and lack of privity. In its responsive brief, WPM argues that
    Appellants are not challenging on appeal WPM’s argument that it was entitled to
    summary judgment because there was no privity of contract between Appellants and
    WPM and because the trial court did not specify the grounds upon which it was
    granting summary judgment, we must affirm the grant of summary judgment. See
    Rosetta Res. Operating, LP v. Martin, 
    645 S.W.3d 212
    , 226 (Tex. 2022) (“When a
    trial court’s order granting summary judgment does not specify the grounds on
    which its order is based, the appealing party must negate each ground upon which
    the judgment could have been based.”); see also Ellis v. Precision Engine
    Rebuilders, Inc., 
    68 S.W.3d 894
    , 898 (Tex. App.—Houston [1st Dist.] 2002, no pet.)
    (“If summary judgment may have been rendered, properly or improperly, on a
    ground not challenged, the judgment must be affirmed.”). We address this issue
    later in the opinion. Appellants, who did not address this argument in their reply
    brief, argue for the first time in their post oral argument brief that WPM’s motion
    for summary judgment was granted exclusively on the basis of limitations.
    Appellants further assert that WPM “did not plead affirmative defenses involving
    contractual privity in its answer. . ., and did not adequately raise, brief or present
    summary judgment evidence except on limitations.” To the extent Appellants raise
    29
    Appellants also argue that Appellees’ arguments are inconsistent with their
    arguments that the Order of Dismissal with Prejudice in the Second Lawsuit was a
    final judgment and thus Appellees are estopped from raising these affirmative
    defenses. Appellants contend they “sufficiently plead jurisdictional facts which for
    purposes of this inquiry must be accepted as true with every reasonable inference
    and any doubt being resolved in favor of Appellants.” According to Appellants, the
    “pleadings of Appellants demonstrate continuing jurisdiction because the claims are
    based on a nucleus of facts which have not been resolved by a full trial on the merits,
    and in any event are not the same claims as have been plead” in the Second Lawsuit.
    Appellants further contend that they asserted in their pleadings that Royce Hassell
    “is a shareholder of HCCI; that Appellants performed the work on the Springwoods
    Project as Contractor; that RHC/RHB were in partnership with HCCI; that HCCI
    acted as agent for RHC/RHB; and that the contract of RHC/RHB has the aspects of
    a sham contract while the [Settlement Agreement], for its validity, appears to require
    new arguments challenging the granting of summary judgment in favor of WPM for
    the first time in their post oral argument brief, which by order we limited to the
    jurisdictional questions, we decline to address these new arguments. See Los
    Compadres Pescadores, L.L.C. v. Valdez, 
    608 S.W.3d 829
    , 838 n.10 (Tex. App.—
    Corpus Christi–Edinburg 2019), aff’d, 
    622 S.W.3d 771
     (Tex. 2021) (“We need not
    address a new issue not raised by the appellant in the original brief.”); see also
    Champion v. State, 
    126 S.W.3d 686
    , 691–92 (Tex. App.—Amarillo 2004, no pet.)
    (declining to consider new issues raised in supplemental brief).
    30
    opposite representations and warranties which in no way moot issues in this case.”24
    Appellants contend that these disputed issues of fact “could be decided in favor of
    Appellants thereby making Appellants’ claims live and not moot.”
    C.    Applicable Law
    This Court has no jurisdiction over a case that has become moot.             See
    Heckman v. Williamson Cty., 
    369 S.W.3d 137
    , 162 (Tex. 2012); see also Elec.
    Reliability Council of Tex., Inc. v. Panda Power Generation Infrastructure Fund,
    LLC, 
    619 S.W.3d 628
    , 634 (Tex. 2021) (stating mootness doctrine prevents courts
    from rendering advisory opinions, which are outside jurisdiction conferred by Texas
    Constitution article II, section 1). “A case becomes moot if, since the time of filing,
    there has ceased to exist a justiciable controversy between the parties—that is, if the
    issues presented are no longer ‘live,’ or if the parties lack a legally cognizable
    interest in the outcome.” Heckman, 369 S.W.3d at 162. In other words, “a case is
    moot when the court’s action on the merits cannot affect the parties’ rights or
    interests.” Id. “If a case is or becomes moot, the court must vacate any order or
    judgment previously issued and dismiss the case for want of jurisdiction.” Id.
    A case, however, “is not rendered moot simply because some of the issues become
    moot during the appellate process.” In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 24
    For example, the Settlement Agreement states that Royce Hassell is not a
    shareholder in HCCI.
    31
    732, 737 (Tex. 2005) (orig. proceeding). If only some claims or issues become moot,
    the case remains “live,” at least as to other claims or issues that are not moot. See
    
    id.
    D.    Release, Collateral Estoppel, and Res Judicata
    Springwoods, the District, and WPM’s arguments based on release, collateral
    estoppel, and res judicata stemming from the Settlement Agreement do not render
    the present appeal moot. Release, collateral estoppel, and res judicata are affirmative
    defenses and the party asserting them has the burden of pleading and proving these
    defenses. TEX. R. CIV. P. 94 (“In pleading to a preceding pleading, a party shall set
    forth affirmatively estoppel, . . . release, res judicata, . . . and any other matter
    constituting an avoidance or affirmative defense.”). To establish the affirmative
    defense of release, the party asserting it must “prove the existence of an effective
    and valid release.” Raider Ranch, LP v. Lugano, Ltd., 
    579 S.W.3d 131
    , 134 (Tex.
    App.—Amarillo 2019, no pet.); Barras v. Barras, 
    396 S.W.3d 154
    , 170 n.5 (Tex.
    App.—Houston [14th Dist.] 2013, pet. denied) (citing Williams v. Glash, 
    789 S.W.2d 261
    , 264 (Tex. 1990)). The elements of res judicata, or claim preclusion,
    are: “(1) a prior final judgment on the merits by a court of competent jurisdiction;
    (2) identity of parties or those in privity with them; and (3) a second action based on
    the same claims that were raised or could have been raised in the first action.” Eagle
    32
    Oil & Gas Co. v. TRO-X, L.P., 
    619 S.W.3d 699
    , 705–06 (Tex. 2021) (quoting
    Citizens Ins. Co. of Am. v. Daccach, 
    217 S.W.3d 430
    , 449 (Tex. 2007)).
    Collateral estoppel, or issue preclusion, bars the relitigation of identical issues
    of fact or law decided in a prior suit. Texas Dep’t of Pub. Safety v. Petta, 
    44 S.W.3d 575
    , 579 (Tex. 2001). A party seeking to assert the bar of collateral estoppel must
    establish that (1) the issue of fact or law sought to be litigated in the second action
    was fully and fairly litigated in the first action, (2) those issues were essential to the
    judgment in the first action, and (3) the party against whom the doctrine is asserted
    was a party or was in privity with a party in the first action. Sysco Food Servs., Inc.
    v. Trapnell, 
    890 S.W.2d 796
    , 801 (Tex. 1994).
    As affirmative defenses, collateral estoppel, res judicata, and release are pleas
    in bar, not jurisdictional pleas. See Texas Highway Dep’t v. Jarrell, 
    418 S.W.2d 486
    , 488 (Tex. 1967) (stating res judicata is plea in bar); FLCT, Ltd. v. City of Frisco,
    
    493 S.W.3d 238
    , 260 (Tex. App.—Fort Worth 2016, pet. denied) (“As an affirmative
    defense, collateral estoppel is a plea in bar, not a jurisdictional plea.”). While theses
    defenses may prevent a plaintiff from recovering on a cause of action, they do not
    effect whether a court has subject matter jurisdiction. See Jarrell, 418 S.W.2d at
    488 (stating “a plea to the jurisdiction, if sustained, would require a dismissal; . . .
    and a plea in bar, if sustained, would require a judgment that the claimant take
    nothing”) (citation omitted); see also FLCT, Ltd., 
    493 S.W.3d at 260
     (stating that
    33
    because collateral estoppel is plea in bar, it “would not support the trial court’s
    dismissal for want of jurisdiction”) (internal citations omitted); Whallon v. City of
    Houston, 
    462 S.W.3d 146
    , 155 (Tex. App.—Houston [1st Dist.] 2015, pet. denied)
    (rejecting argument trial court was deprived of jurisdiction based on res judicata and
    noting “argument conflates the separate and distinct concepts of res judicata and
    subject-matter jurisdiction”). Thus, even assuming any of these affirmative defenses
    apply, they would not deprive this Court of jurisdiction over the present appeal.
    WPM’s jurisdictional arguments with respect to RHC and RHB regarding
    lack of privity and the economic loss rule are also unpersuasive. According to WPM,
    RHC’s and RHB’s claims against it are moot and we are thus deprived of jurisdiction
    because WPM moved for summary judgment based on limitations and lack of
    privity, and because RHC and RHB do not challenge the granting of summary
    judgment based on lack of privity, “they cannot recover against WPM in contract.”
    Lack of privity, however, is a contractual defense, not a jurisdictional issue. See
    Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215 (Tex. 2003)
    (recognizing lack of privity as contractual defense).
    WPM further contends we lack jurisdiction because RHC and RHB “cannot
    recover in tort because of the economic loss rule.” “[A] duty in tort does not lie
    when the only injury claimed is one for economic damages recoverable under a
    breach of contract claim.” Wansey v. Hole, 
    379 S.W.3d 246
    , 248 (Tex. 2012) (per
    34
    curiam); see also Jim Walter Homes, Inc. v. Reed, 
    711 S.W.2d 617
    , 618 (Tex. 1986)
    (“When the injury is only the economic loss to the subject of a contract itself, the
    action sounds in contract alone.”); Chapman Custom Homes, Inc. v. Dallas
    Plumbing Co., 
    445 S.W.3d 716
    , 718 (Tex. 2014) (discussing economic-loss rule and
    stating “a party states a tort claim when the duty allegedly breached is independent
    of the contractual undertaking and the harm suffered is not merely the economic loss
    of a contractual benefit”). The economic loss rule, however, “is a consideration in
    measuring damages,” not a jurisdictional bar. See Equistar Chems., L.P. v. Dresser-
    Rand Co., 
    240 S.W.3d 864
    , 868 (Tex. 2007).
    We thus hold that Appellants’ challenges to the trial court’s granting of
    summary judgment in favor of Appellees on Appellants’ claims against
    Springwoods, the District, and WPM are not moot and do not deprive this Court of
    jurisdiction to consider Appellants’ appeal.
    To the extent Springwoods, the District, and WPM attempt to raise their
    affirmative defenses of collateral estoppel, res judicata, and release in their motion
    to dismiss or post oral argument briefs, these affirmative defenses are waived for
    purposes of this appeal. See TEX. R. CIV. P. 94; In re S.A.P., 
    156 S.W.3d 574
    , 576
    (Tex. 2005); see also Izen v. Laine, 
    614 S.W.3d 775
    , 796 (Tex. App.—Houston [14th
    Dist.] 2020, pet. denied). The District, Springwoods, and WPM did not plead those
    affirmative defenses in their pleadings nor did they present those affirmative
    35
    defenses in their motions for summary judgment filed in the trial court. 25 We thus
    cannot consider the propriety of the trial court’s summary judgment ruling on
    Appellants’ claims based on such grounds. As the Texas Supreme Court explained
    in State Farm Fire & Casualty Company v. S.S., 
    858 S.W.2d 374
     (Tex. 1993):
    Affirming a summary judgment on an independent ground not
    specifically considered by the trial court usurps the trial court’s
    authority to consider and rule on issues before it and denies the
    appellate court of the benefit of the trial court’s decision on the issue.
    Such a practice results in appellate courts rendering decisions on issues
    not considered by the trial court and voiding the trial court’s decision
    without allowing it to first consider the alternate grounds. Usurping the
    trial court’s authority does not promote judicial economy, but instead
    serves as an encouragement for summary judgment movants to obtain
    a specific ruling from a trial judge on a single issue and then try again
    with other alternate theories at the court of appeals, then assert the same
    or additional alternate theories before this Court. Our system of
    appellate review, as well as judicial economy, is better served when
    appellate courts only consider those summary judgment issues
    contemplated and ruled on by the trial court.
    
    Id.
     at 381–82.
    E.    Denial of Motion to Abate
    In their second issue, Appellants argue the trial court abused its discretion by
    denying their motion to abate the Third Lawsuit pending resolution of their appeal
    of the trial court’s judgment in the First Lawsuit. Appellants contend the trial court’s
    refusal to abate “exposed them to the dangers of inconsistent judgments being
    25
    As noted in the background section, the parties did not execute the Settlement
    Agreement and the trial court did not issue its order of dismissal in the Second
    Lawsuit until after the trial court granted summary judgment in favor of Appellees
    in the Third Lawsuit and Appellants filed their notice of appeal in this case.
    36
    rendered on the same set of facts.” In their motion to dismiss, Springwoods and the
    District argue that Appellants’ challenge to the trial court’s refusal to abate the Third
    Lawsuit is moot because Appellants’ appeal from the First Lawsuit has been finally
    resolved. We agree.
    On February 5, 2018, Appellants filed their opening brief in this appeal. On
    April 19, 2018, this Court affirmed the trial court’s striking of RHC’s and RHB’s
    Second Petition in Intervention in the First Lawsuit and the Texas Supreme Court
    denied RHC’s and RHB’s petition for review in that case. See R. Hassell & Co.,
    Inc., 
    2018 WL 1864627
    , at *8. This Court issued the mandate on May 7, 2018, thus
    finally disposing of RHC’s and RHB’s appeal of the First Lawsuit. Because RHC’s
    and RHB’s appeal from the First Lawsuit is final, any decision this Court would
    render on the merits of this issue “cannot affect the parties’ rights or interests.”
    Heckman, 369 S.W.3d at 162. Thus, Appellants’ second issue challenging the denial
    of their motion to abate is moot.
    F.    Conclusion
    We deny Appellants’ partial motion to dismiss. Even though Appellants’
    challenge to the denial of their motion to abate is moot, the case remains “live” as to
    Appellants’ other challenges to the trial court’s order granting summary judgment
    in favor of Appellees. See In re Kellogg Brown & Root, Inc., 166 S.W.3d at 737
    (stating if only some claims or issues become moot, case remains “live” with respect
    37
    to other claims or issues that are not moot). Therefore, we will address the merits of
    Appellants’ remaining challenges to the trial court’s granting of summary judgment
    on Appellants’ breach of contract, fraud, fraudulent inducement, fraud by non-
    disclosure, conspiracy to defraud, assumpsit, quantum meruit, and unjust-
    enrichment claims.
    Summary Judgment
    Appellants argue the trial court abused its discretion by granting summary
    judgment in favor of Appellees in the Third Lawsuit because (1) limitations had not
    expired on each of Appellants’ claims before they filed suit; (2) limitations was
    tolled on all of Appellants’ claims; and (3) Appellees did not conclusively establish
    the accrual dates for each of Appellants’ claims or, alternatively, Appellants raised
    a question of material fact over the accrual date for each claim.
    A.    Standard of Review
    We review a summary judgment ruling based on the affirmative defense of
    limitations de novo. Schlumberger Tech. Corp. v. Pasko, 
    544 S.W.3d 830
    , 833 (Tex.
    2018). When reviewing a summary judgment ruling, we take as true all evidence
    favorable to the nonmovant. See 
    id.
     We indulge every reasonable inference and
    resolve any doubts in the nonmovant’s favor. See 
    id.
     On appeal, the movant still
    bears the burden of showing there is no genuine issue of material fact and that it is
    entitled to judgment as a matter of law. See TEX. R. CIV. P. 166a(c); M.D. Anderson
    38
    Hosp. & Tumor Inst. v. Willrich, 
    28 S.W.3d 22
    , 23 (Tex. 2000). The evidence raises
    a genuine issue of material fact if reasonable and fair minded jurors could differ in
    their conclusions in light of all of the summary judgment evidence. Goodyear Tire
    & Rubber Co. v. Mayes, 
    236 S.W.3d 754
    , 755 (Tex. 2007). If the trial court does
    not specify the grounds on which it granted a summary judgment, the appellant must
    defeat all grounds presented in the summary judgment motion. See Rosetta Res.
    Operating, LP v. Martin, 
    645 S.W.3d 212
    , 226 (Tex. 2022) (“When a trial court’s
    order granting summary judgment does not specify the grounds on which its order
    is based, the appealing party must negate each ground upon which the judgment
    could have been based.”).
    A party moving for summary judgment based on limitations must
    conclusively establish the bar of limitations. See Schlumberger Tech. Corp., 544
    S.W.3d at 833 (citing KPMG Peat Marwick v. Harrison Cty. Hous. Fin. Corp., 
    988 S.W.2d 746
    , 748 (Tex. 1999)). To meet its burden, the movant must prove the
    accrual date for each challenged cause of action conclusively and negate any tolling
    doctrines the nonmovant has pleaded or otherwise raised. See Schlumberger Tech.
    Corp., 544 S.W.3d at 834 (citing KPMG Peat Marwick, 988 S.W.2d at 748). An
    issue is conclusively proven if reasonable minds would necessarily agree regarding
    the conclusion to be reached from the evidence. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 816 (Tex. 2005) (“Evidence is conclusive only if reasonable people
    39
    could not differ in their conclusions. . .”). If the movant establishes that limitations
    bars a challenged cause of action, the nonmovant must then present evidence raising
    a fact issue to avoid the statute of limitations. KPMG Peat Marwick, 988 S.W.2d at
    748.
    A party who seeks summary judgment based on limitations need not negate a
    tolling doctrine that has not been pled. Via Net v. TIG Ins. Co., 
    211 S.W.3d 310
    ,
    313 (Tex. 2006). When a party asserts a tolling doctrine for the first time in response
    to a summary judgment motion, the movant may either object that the tolling
    doctrine has not been pleaded or respond on the merits and try the issue by consent.
    
    Id.
     If the movant does not object and elects to respond on the merits, the tolling
    doctrine’s applicability is placed squarely before the trial and appellate courts. 
    Id.
    B.     WPM’s Motion for Summary Judgment
    WPM moved for summary judgment on all of Appellants’ causes of action
    asserted against it. WPM stated that it was moving for summary judgment “based
    on the arguments presented in Springwoods’ Motion and the additional factual and
    legal issues identified below.”     WPM also attached Springwoods’ motion and
    exhibits to its motion and “incorporate[d] the [Springwoods’] Motion and exhibits
    as if expressly stated herein.” Specifically, WPM argued that Appellants’ claims for
    breach of contract, fraud, conspiracy, assumpsit, quantum meruit, and unjust
    enrichment were barred by the applicable statutes of limitations “for the same
    40
    reasons identified in Springwoods’ Motion for Summary Judgment.” WPM also
    argued in the alternative that it was entitled to summary judgment on Appellants’
    breach of contract claims because Appellants did not enter into any contractual
    agreement with WPM and thus, Appellants cannot establish the elements of its
    breach of contract actions. The trial court granted WPM’s motion in its final
    judgment without specifying the basis for its ruling.
    Appellants argue the trial court abused its discretion by granting WPM’s
    motion for summary judgment with respect to all claims pending against WPM
    because WPM’s motion incorporated another party’s motion by reference and did
    not expressly set out any grounds in support of WPM’s Rule 166(c) motion.26
    Appellants’ argument is not persuasive. First, Appellants did not challenge the
    appropriateness of summary judgment in favor of WPM on this basis in the trial
    court and therefore the issue is waived. See Mallory v. Arctic Pipe Inspection Co.,
    Inc., No. 01-12-00979-CV, 
    2014 WL 701123
    , at *6 (Tex. App.—Houston [1st Dist.]
    Feb. 20, 2014, pet. denied) (mem. op.) (holding nonmovant waived right to challenge
    appropriateness of summary judgment that adopted codefendant’s motion by not
    specially excepting to motion and obtaining ruling on special exception). Second,
    even if Appellants had challenged WPM’s motion for summary judgment on this
    26
    Although the District’s motion for summary judgment also joined and adopted
    Springwoods’ motion for summary judgment, Appellants do not challenge the
    summary judgment granted in favor of the District on this basis.
    41
    ground, Texas courts, including this Court, “have recognized [the] adoption of co-
    party’s motion for summary judgment as a procedurally legitimate practice.”
    Lockett v. HB Zachry Co., 
    285 S.W.3d 63
    , 72–73 (Tex. App.—Houston [1st Dist.]
    2009, no pet.); see also TEX. R. CIV. P. 58 (“Statements in a pleading may be adopted
    by reference in a different part of the same pleading or in another pleading or in any
    motion. . .”). A defendant can adopt by reference the summary judgment grounds,
    argument, and evidence of a codefendant when both defendants have a community
    of interest and identical defenses. See 
    id.
     (permitting adoption by reference of
    codefendant’s summary-judgment grounds); see also Chapman v. King Ranch, Inc.,
    
    41 S.W.3d 693
    , 699–700 (Tex. App.—Corpus Christi 2001), rev’d on other grounds,
    
    118 S.W.3d 742
     (Tex. 2003). Here, Springwoods and WPM asserted limitations as
    an affirmative defense to all of Appellants’ claims and Springwoods moved for
    summary judgment on this defense. See generally McDaniels v. Mittemeyer, No.
    07-03-0234-CV, 
    2004 WL 578581
    , at *1 (Tex. App.—Amarillo Mar. 24, 2004, pet.
    denied) (mem. op.) (affirming grant of summary judgment on statute-of-limitations
    grounds in favor of defendant who adopted and incorporated by reference
    codefendant’s motion for summary judgment on statute of limitations grounds). We
    thus reject Appellants’ argument that the trial court abused its discretion by granting
    WPM’s motion because it adopted and incorporated Springwoods’ motion for
    summary judgment.
    42
    C.    Appellants’ Breach-of-Contract Claims
    1.     WPM
    In addition to its statute of limitations defense, WPM also argued it was
    entitled to summary judgment on Appellants’ breach of contract claim because
    Appellants did not have a contractual agreement with WPM and thus, they could not
    establish privity of contract. Because the trial court did not specify the grounds on
    which it granted WPM’s motion for summary judgment on Appellants’ breach of
    contract claim, Appellants must defeat all grounds presented in WPM’s motion,
    including WPM’s lack of privity argument. See Rosetta Res. Operating, LP, 645
    S.W.3d at 226.
    On appeal, Appellants only challenge WPM’s argument that it was entitled to
    summary judgment on Appellants’ breach of contract claim based on limitations;
    they do not challenge WPM’s alternate argument that it was entitled to summary
    judgment based on lack of privity between Appellants and WPM.               Because
    Appellants do not challenge this alternate ground on which the trial court could have
    based its summary judgment ruling in favor of WPM, we must affirm the judgment
    with regard to Appellants’ breach of contract claim against WPM.27 See id.
    27
    The summary judgment may have been rendered, properly or improperly, on this
    unchallenged ground. See Ellis, 
    68 S.W.3d at 898
     (“If summary judgment may have
    been rendered, properly or improperly, on a ground not challenged, the judgment
    must be affirmed.”). Thus, we need not address the limitations argument with
    respect to WPM.
    43
    We overrule Appellants’ first issue with respect to their breach of contract
    claims against WPM.
    2.     Springwoods and the District
    To establish their entitlement to summary judgment on Appellants’ breach of
    contract claims based on limitations, Springwoods and the District were required to
    prove the accrual date for the claims conclusively and negate any applicable tolling
    doctrines plead by Appellants. See Schlumberger Tech. Corp., 544 S.W.3d at 834
    (citing KPMG Peat Marwick, 988 S.W.2d at 748). “As a general rule, a cause of
    action accrues and the statute of limitations begins to run when facts come into
    existence that authorize a party to seek a judicial remedy.” Knott, 128 S.W.3d at
    221. A cause of action “accrues when a wrongful act causes a legal injury, regardless
    of when the plaintiff learns of that injury or if all resulting damages have yet to
    occur.” Id.; see also Exxon Corp. v. Emerald Oil & Gas Co., 
    348 S.W.3d 194
    , 202
    (Tex. 2011) (“Causes of action accrue and statutes of limitations begin to run when
    facts come into existence that authorize a claimant to seek a judicial remedy.”).
    A breach of contract claim accrues when the contract is breached. Via Net,
    211 S.W.3d at 314. Texas common law, however, recognizes an exception to this
    rule in situations involving a continuing contract. A continuing contract is one under
    which “the contemplated performance and payment is divided into several parts or,
    where the work is continuous and indivisible, the payment for work is made in
    44
    installments as the work is completed.” Hubble v. Lone Star Contracting Corp., 
    883 S.W.2d 379
    , 381–82 (Tex. App.—Fort Worth 1994, writ denied) (citing Godde v.
    Wood, 
    509 S.W.2d 435
    , 441 (Tex. Civ. App.—Corpus Christ 1974, writ ref’d
    n.r.e.)); City & Cty. of Dall. Levee Improvement Dist. v. Halsey, Stuart & Co., Inc.,
    
    202 S.W.2d 957
    , 961 (Tex. Civ. App.—Amarillo 1947, no writ)). For purposes of a
    continuing contract, the accrual date for a breach of contract cause of action is the
    earlier of (1) the completion of the work; (2) the termination of the contract under
    its own terms; or (3) the anticipatory repudiation of the contract by one party and the
    adoption of the repudiation by the other party. Hubble, 
    883 S.W.2d at 382
    ; see
    Godde, 
    509 S.W.2d at 441
    .
    Appellants argue that the Contract is a continuing Contract and thus, their
    breach of contract claims did not accrue until the earlier of (1) when the work was
    completed; (2) when the Contract was terminated in accordance with its terms; or
    (3) when the Contract is anticipatorily repudiated by one party and the repudiation
    is adopted by the other party. They claim that because no party contends Appellants
    completed the Contract, Springwoods and the District were required to demonstrate
    repudiation or that the Contract ended in accordance with its terms. Springwoods
    and the District argue that, even if the Contract were a continuing contract, the
    continuing contract rule does not determine the accrual date for Appellants’ breach
    of contract claim because the Contract modifies the common law rules regarding the
    45
    accrual date for a breach of contract claim. Springwoods and the District argue that,
    because mediation of a disputed claim under the Contract is a condition precedent
    to filing suit, the parties intended that a cause of action for breach would accrue upon
    satisfaction of that condition precedent. They further contend that Appellants’
    causes of action for breach of contract accrued when the parties unsuccessfully
    mediated their payment claims on July 2, 2012. Thus, they argue, Appellants’ breach
    of contract claims, which they filed in this case on December 12, 2016, are barred.
    “Texas has a strong public policy favoring freedom of contract.” James
    Constr. Group, LLC v. Westlake Chem. Corp., 
    650 S.W.3d 392
    , 403 (Tex. 2022);
    see also Philadelphia Indem. Ins. Co. v. White, 
    490 S.W.3d 468
    , 471 (Tex. 2016)
    (“Texas’s strong public policy favoring freedom of contract is firmly embedded in
    our jurisprudence.”). Thus, “parties have the right to contract as they see fit as long
    as their agreement does not violate the law or public policy.” In re Prudential Ins.
    Co. of Am., 
    148 S.W.3d 124
    , 129 (Tex. 2004). Absent compelling reasons, we must
    respect and enforce the terms of a contract that the parties have freely and voluntarily
    entered. Philadelphia Indem. Ins. Co., 490 S.W.3d at 471; see also Gym-N-I
    Playgrounds, Inc. v. Snider, 
    220 S.W.3d 905
    , 912 (Tex. 2007) (“Freedom of contract
    allows parties to bargain for mutually agreeable terms and allocate risks as they see
    fit.”).
    46
    The Contract provides a comprehensive mechanism for the parties to resolve
    their payment disputes. Paragraph 14.02 states that HCCI may submit monthly
    applications for payment to WPM or Costello, who will review the applications and
    make a recommendation of payment to Springwoods. Payment of any recommended
    amounts are due to HCCI ten days after WPM or Costello tenders its payment
    recommendation to Springwoods. The Contract also includes a mechanism through
    which either party may request an adjustment to the Contract price. If the parties are
    unable to agree on the proper disposition of a payment request, a party may submit
    the claim to WPM or Costello, and their determination of the claim “shall be required
    as a condition precedent to any exercise by Owner or Contractor of any rights or
    remedies either may otherwise have under the Contract or the Laws and Regulations
    in respect of such Claims.” WPM’s or Costello’s decision becomes final and binding
    within thirty days unless a party invokes the Contract’s dispute resolution procedure
    set forth in Article 16.
    Paragraph 16.01 states that either party may request to mediate a claim before
    WPM’s or Costello’s decision becomes final and binding. The mediation process
    must be “concluded within 60 days of the request.” Paragraph 16.01.C further states
    that if a claim is not resolved by mediation, WPM’s or Costello’s decision becomes
    final and binding within thirty days after the mediation terminates, unless (1) a party
    “elects in writing to invoke any dispute resolution process provided for the
    47
    Supplementary Conditions,” (2) the parties agree to submit their claims to another
    dispute resolution process, or (3) one of the parties gives written notice to the other
    party of its intent to submit the Claim to a court of competent jurisdiction. Thus, to
    summarize, if the parties have a payment dispute, the Contract first requires the
    parties to submit their payment claims to the engineer for determination as a
    condition precedent to filing suit. If the parties disagree with the engineer’s decision,
    they may request mediation within thirty days of the decision or else the engineer’s
    decision become final and binding.        If the payment claim is not resolved by
    mediation, the engineer’s decision with respect to that claim becomes final and
    binding within thirty days after the mediation terminates, unless the party advancing
    the payment claim takes one of three steps, one of which is to give written notice of
    its intent to submit the payment claim to a court of competent jurisdiction.
    Following the parties’ unsuccessful mediation on July 2, 2012, HCCI chose
    to submit its payment claims to a court of competent jurisdiction by filing suit. On
    July 26, 2012, it filed the First Lawsuit advancing the same breach of contract claims
    against Springwoods and the District that HCCI, derivatively and through Royce
    Hassell, now asserts in the present appeal.28 Appellants, who do not dispute that
    HCCI filed the same breach of contract claims in July 26, 2012 against Springwoods
    28
    Indeed, Appellants’ note in their opening brief that they “timely provided that
    notice by filing suit on July 26, 2012.”
    48
    and the District based on the same payment claims they now present here,29 assert
    that their claims did not accrue in July 2012, and further argue that because the
    Contract does not use the terms “accrual,” “causes of action,” or limitations, the
    Contract did not intend to alter any common law rules regarding accrual. Appellants’
    arguments lack merit.
    While the Contract does not use the terms “accrual,” “causes of action,” or
    “limitations,” as Appellants argue, the Contract dictates when a breach of contract
    accrues because it informs the parties when a payment claim becomes ripe for
    dispute resolution, when a decision on the claim becomes final, and when the
    disputing party has a right to sue on the claim for breach of contract. See Knott, 128
    S.W.3d at 221 (“As a general rule, a cause of action accrues and the statute of
    limitations begins to run when facts come into existence that authorize a party to
    seek a judicial remedy.”).
    Appellants argue that the parties did not intend for the Contract to modify or
    preempt the common law on limitations because Paragraph 17.03, “Cumulative
    29
    In the First Lawsuit, HCCI asserted claims against Springwood and the District for
    breach of contract and against Springwoods for fraud. In the alternative, HCCI
    asserted claims against the District under Texas Local Government Code section
    271.153(a)(2), and against Springwoods for assumpsit, quantum meruit, and unjust
    enrichment. In their Second Petition in Intervention, filed in the First Lawsuit, RHC
    and RHC asserted claims for breach of contract against the District and
    Springwoods, and alternative claims against the District under Texas Local
    Government Code section 271.153.
    49
    Remedies,” states that the “duties and obligations imposed by these General
    Conditions and the rights and remedies available hereunder to the parties hereto are
    in addition to, and are not to be construed in any way as a limitation of, any right
    and remedies available to any or all of them which are otherwise imposed or
    available by Laws or Regulations . . . .” This argument is not persuasive. The
    Contract does not limit Appellants rights and remedies. Rather, the Contract dictates
    the time frame in which Appellants must file suit to preserve their rights and
    remedies on any payment claims because it authorizes the parties to submit any
    disputed claim to mediation within 30 days of the engineer’s decision on payment,
    and to sue for breach of contract within 30 days after the mediation ends.
    Based on the summary judgment record and the applicable standard of review,
    we hold that Springwoods and the District met their burden to establish conclusively
    that Appellants’ breach of contract claims accrued at the latest on July 2, 2012, when
    mediation of the parties’ payment claims terminated unsuccessfully, because at that
    time, the express terms of the Contract authorized Appellants to pursue their breach
    of contract claims in litigation, which they in fact did on July 26, 2012, when HCCI
    filed the First Lawsuit against Springwoods and the District asserting the same
    breach of contract claims Appellants now assert in the Third Lawsuit. We thus hold
    the trial court did not abuse its discretion by granting summary judgment in favor of
    Springwoods and the District on Appellants’ breach of contact claims filed on
    50
    December 12, 2016. See Schlumberger Tech. Corp., 544 S.W.3d at 834 (citing
    KPMG Peat Marwick, 988 S.W.2d at 748).
    3.     Conclusion
    We overrule Appellants’ first issue with respect to their breach of contract
    claims against Springwoods, the District, and WPM.
    D.    Appellants’ Fraud, Fraud-by-Nondisclosure, Fraudulent-Inducement,
    and Conspiracy Claims
    In their December 2016 petition filed in the Third Lawsuit, Appellants
    asserted separate claims for fraud, fraud by nondisclosure, fraudulent inducement,
    and conspiracy to commit fraud against Appellees.            According to Appellees,
    Appellants’ fraud and fraud by nondisclosure claims are barred by the four-year
    statute of limitations because Appellants knew by no later than the July 2, 2012
    unsuccessful mediation that Appellants would not recover all of their alleged costs.
    Appellees also alleged that Appellants’ conspiracy claim was time barred because
    their “cause of action for conspiracy accrued when [Appellants] claim they sustained
    an alleged injury as a result of Springwoods’ alleged fraudulent act,” and therefore,
    Appellants’ “cause of action for conspiracy accrued no later than at the conclusion
    of the mediation on July 2, 2012.” The trial court granted summary in Appellees’
    favor on these claims based on the statute of limitations.
    Fraud has a four year statute of limitations. TEX. CIV. PRAC. & REM. CODE
    § 16.004(a)(4); Exxon Corp., 348 S.W.3d at 216; Seureau v. ExxonMobil Corp., 274
    
    51 S.W.3d 206
    , 226 (Tex. App.—Houston [14th Dist.] 2008, no pet.). The statute of
    limitations for civil conspiracy, which is a vicarious liability theory and not an
    independent cause of action, is governed by the underlying tort. See Agar Corp.,
    Inc. v. Electro Circuits Int’l, LLC, 
    580 S.W.3d 136
    , 143–44 (Tex. 2019). Thus, the
    statute of limitations for Appellants’ conspiracy claim is also four years.
    “As a general rule, a cause of action accrues and the statute of limitations
    begins to run when facts come into existence that authorize a party to seek a judicial
    remedy.” Knott, 128 S.W.3d at 221. A cause of action “accrues when a wrongful
    act causes a legal injury, regardless of when the plaintiff learns of that injury or if all
    resulting damages have yet to occur.” Id. Generally, a cause of action for fraud
    accrues “when the fraud is perpetrated, or if the fraud is concealed, from the time it
    is discovered or could have been discovered by the exercise of reasonable diligence.”
    Woods v. William M. Mercer, Inc., 
    769 S.W.2d 515
    , 517 (Tex. 1988); see generally
    Seureau, 274 S.W.3d at 226 (stating cause of action for fraud accrues on date that
    defendant makes allegedly false representations). The same accrual date rule applies
    with respect to fraudulent inducement and fraud by omission or nondisclosure.
    Hooks v. Samson Lone Star, Ltd. P’ship, 
    457 S.W.3d 52
    , 57 (Tex. 2015)
    (“Fraudulent inducement is a subspecies of fraud . . . [L]imitations does not start to
    run until the fraud with respect to the contract is discovered or the exercise of
    reasonable diligence would discover it”); see generally Solutioneers Consulting, Ltd.
    52
    v. Gulf Greyhound Partners, 
    237 S.W.3d 379
    , 385 (Tex. App.—Houston [14th Dist.]
    2007, no pet.) (stating fraud by omission or nondisclosure is subcategory of fraud).
    Appellants asserted that Appellees committed fraud, fraudulent inducement,
    and fraud by nondisclosure by misrepresenting to Appellants that the plans and
    specifications requested for the Project bid were complete, and by failing to disclose
    to Appellants that the plans were not final, complete, or intended to be constructed
    as shown. Appellants further alleged that, had they known that the “bid plans and
    specifications [for the Project] were intended to be changed, were not complete and
    contained inaccuracies, [Appellants] would not have bid the Project at the costs it
    did.”
    Appellants also alleged that Appellees made misrepresentations to them after
    the Project began and “insisted work continue while representing an intention to pay
    for the continued performance, notwithstanding the added costs and delays.”
    According to Appellants, Appellees misrepresented “to [Appellants] that they were
    aware of the extensive delays and were negotiating in good faith for payment
    adjustments to the Contract [Appellees] did not intend to perform.” Appellants
    further alleged that:
    [H]ad [Appellees] not strung [Appellants] along to cause them to
    believe [Appellees] intended to pay for the delays, work would not have
    continued and the additional costs incurred could have been avoided .
    At all times [Appellees] knew or should have known that [Appellants]
    were relying upon, in good faith, [Appellees] impartiality in decisions
    on claims for additional costs. Further, upon information and belief, at
    53
    the time [Appellees] represented to [Appellants] that they were aware
    of the extensive delays and were negotiating in good faith for payment
    adjustments to the Contract, [Appellees] did not intend to perform.
    For the reasons stated below, we find Appellants claims are barred.
    Springwoods attached to its motion for summary judgment the original
    petition HCCI filed in the First Lawsuit on July 26, 2012. In that petition, HCCI
    alleged many of the same facts giving rise to Appellants’ fraud claims in the Third
    Lawsuit. Royce Hassell, who is the owner and President of RHB and RHC,
    oversaw the claim resolution process and attended the July 2012 mediation on
    HCCI’s behalf. He also hired HCCI’s legal counsel and directed counsel to file
    HCCI’s original petition in the First Lawsuit.
    In the original petition filed in the First Lawsuit, HCCI alleged that the
    District and Springwoods solicited bids for the Project in 2011. After HCCI won
    the bid, it executed the Contract with Springwoods that included “the bid drawings
    [which were provided to HCCI as part of the bidding process] and specifications
    brought forward as the construction drawings and specifications (the ‘drawings’).”
    The drawings defined the scope of HCCI’s work on the Project. HCCI alleged that
    it “notified Springwoods and the District [about] problems with the drawings” from
    the time HCCI began working on the Project, “Costello submitted construction
    drawings which contained unilateral revisions not made under the Contract,” and
    54
    Springwoods and the District made “over five-hundred (500) such revisions to the
    drawings.” According to HCCI:
    Throughout the revisions to the drawings and the project, Springwoods
    and the District . . . have directed HCCI to perform the expanded Scope
    of Work without delay.
    Springwoods and the District . . . have required HCCI to perform more
    work in less time or in an accelerated manner which has resulted in
    material inefficiencies and loss of productivity. Springwoods and the
    District . . . seek to unilaterally revoke, rescind or revise previously
    executed Change Orders without due compensation to HCCI.
    HCCI alleged that it continued “to fully perform” and is “entitled to be paid
    for the full work performed and to be performed under the original scope of work
    and any agreed-to additional scope of work.”       “Despite each such obligation,
    Springwoods has not paid HCCI all amounts due and owing.” HCCI further alleged
    that it “filed a series of claims for changes in the Contract Price and the Contract
    Time [that were necessitated by the revisions to the drawings] which Springwoods
    and the District asked to be treated as a consolidated claim.” According to HCCI:
    Springwoods and the District have refused to respond properly to
    HCCI’s consolidated claim. They have refused to meet with HCCI to
    discuss the details of HCCI’s consolidated claim. Springwoods and the
    District functionally refused to address HCCI’s consolidated claim.
    Instead, they have simply deferred ruling, rather than making an
    impartial, good faith decision required under the Contract.
    HCCI also alleged that:
    Springwoods and the District, moreover, now rely upon a pretext to try
    to defer further HCCI’s consolidated claim. Springwoods and the
    District now claim that they cannot decide HCCI’s consolidated claim
    55
    because HCCI allegedly failed to respond to an earlier request by
    Costello to HCCI for HCCI to supply certain documents. Yet, HCCI
    has supplied, what even Springwoods and the District has characterized
    as, volumes of pages after the request by Costello. During that time
    that HCCI supplied its documents, neither Springwoods nor the District
    complained that HCCI failed to supply the documents requested by
    Costello. Further during that time, HCCI expressly requested
    Springwoods and the District to identify any problems with the
    documents submitted, and neither Springwoods nor the District
    identified any problem.
    HCCI further alleged that the Contract contains “a mechanism for an
    impartial, unbiased, and independent Engineer to make decisions critical to HCCI’s
    performance under the Contract.”       WPM and Costello, who were chosen by
    Springwoods and the District to serve as “independent Engineer[s]” for the Contract,
    were obligated to act in “good faith, impartially and without preference to
    Springwoods, the District or HCCI” when making “interpretations and changes in
    Contract Price and Contract Time, or both.” HCCI relied “upon this agreed-to
    mechanism and [WPM’s and Costello’s] accompanying independent duties” and
    filed a consolidated claim pursuant to this process.
    According to HCCI’s petition filed in the First Lawsuit, HCCI “learned that
    this agreed-to mechanism has been and is illusory and non-existent” because
    “decisions submitted to an independent Engineer review involve the problems
    created by the revisions to the drawings prepared by [WPM and WPM] is principally
    motivated by the self-interest to try to cover-up or protect against its insufficient
    drawings.” According to HCCI, WPM “cannot ever be impartial or unbiased
    56
    because of [this] fundamental conflict of interest” and “[i]t appears that Costello has
    preferred the perceived economic benefit of its other joint venture projects with
    [WPM] over its independent obligations” under the Contract.
    The allegations HCCI made in its original petition filed in the First Lawsuit
    thus indicate that by July 26, 2012, Appellants believed Appellees had
    misrepresented to Appellants that: (1) the Project’s bid drawings provided to HCCI
    as part of the bidding process were complete and final; (2) Appellees intended to pay
    Appellants for their continued work on the Project; and (3) Appellees were
    “negotiating in good faith for payment adjustments to the Contract.” Appellants
    were also aware by July 26, 2012, of their purported injuries resulting from these
    alleged misrepresentations. See Seureau, 274 S.W.3d at 226 (stating cause of action
    for fraud accrues on date that defendant makes allegedly false representations). To
    the extent Appellants claim Appellees concealed any information concerning the
    scope of the Project causing them to bid on the Project to their detriment, HCCI’s
    allegations in its July 26, 2012 petition also indicate that Appellants knew or should
    have known that the Project plans were not final, complete, or intended to be
    constructed as shown during the bidding process and that HCCI and RHB and RHC,
    as HCCI’s alleged principals or partners, had been injured as a result of these
    substantial revisions. See Woods, 
    769 S.W.2d 515
    , 517 (stating cause of action for
    fraud accrues “when the fraud is perpetrated, or if the fraud is concealed, from the
    57
    time it is discovered or could have been discovered by the exercise of reasonable
    diligence”).
    The following communications between Royce Hassell, Springwoods, the
    District, WPM, and Costello between July 18, 2012, and September 12, 2012 also
    demonstrate that Appellants’ fraud claims are time-barred because they accrued
    more than four years before Appellants filed the present suit in December 2016.
    In a July 18, 2012 letter to Springwoods, the District, WPM, and Costello,
    Royce Hassell provided information about HCCI’s post-mediation claims and
    requested data, compilations, engineering reports, analysis, and correspondence
    WPM and Costello provided to Springwoods and the District regarding HCCI’s
    claims.30 Royce Hassell also asked Springwoods and the District to explain “how
    they can have participated in mediation in good faith as required under the Article
    16.01B of the Agreement since they were advised and assisted at mediation by
    Engineers who owe Hassell a duty of ‘impartiality’ in connection with any
    interpretations or decisions under the Agreement.” Finally, he also requested that
    WPM and Costello be removed from the Project “for conflicts of interest associated
    with decisions under the Agreement in light of the plan deficiencies.”
    30
    This letter was included in the summary judgment record and was thus before the
    trial court when it ruled on Appellees’ motions for summary judgment.
    58
    On August 1, 2012, Royce Hassell sent a letter to Springwoods and the
    District in which he addressed the District’s request to waive mediation for a
    particular claim, stating that such a request “ignore[d] the purpose of the alternative
    dispute process in the contract which is intended to reduce the cost of litigation by
    encouraging settlement of disputes before litigation.” 31       Royce Hassell noted,
    however, that “[a]t the same time, HCCI does not want to pursue a mediation claim
    which will just be a total waste of time like the [July 2012] mediation because of the
    posture assumed by the District and Springwoods.”
    On August 24, 2012, Royce Hassell sent a letter to Costello’s Engineer Bill
    Zollman (“Zollman”) in which he responded to Zollman’s request for additional
    information regarding the claims HCCI submitted on July 18, 2012, and reiterated
    his prior requests for information. 32 Royce Hassell also stated that Springwoods and
    the District “still refuse to meet with us” and “[a]lthough we have no reason to
    believe that [Springwoods and the District] will change their uncommunicative
    posture, we still can hope that [Springwoods and the District] will join us and work
    under the terms of the construction agreement in an effort to try to resolve the current
    disputes like business parties.”
    31
    This letter was included in the summary judgment record and was thus before the
    trial court when it ruled on Appellees’ motions for summary judgment.
    32
    This letter was included in the summary judgment record and was thus before the
    trial court when it ruled on Appellees’ motions for summary judgment.
    59
    On September 12, 2012, Royce Hassell emailed Zollman in response to
    Zollman’s request for HCCI’s “position on Contract Quality Adjustments.” 33 In his
    email, Royce Hassell noted that HCCI had been forced to file the First Lawsuit
    “because of [WPM’s and Costello’s] failure to impartially assess [HCCI’s] claims
    (which would have allowed a fair resolution of [HCCI’s] damages and increased
    costs).” Royce Hassell stated that HCCI “does not agree that these contract quality
    adjustments take into account the delay, interruption, and interference costs to
    [HCCI] caused by the adjustments or the over 1500 plan revisions.” Royce Hassell
    further stated:
    As you are aware, the over 1500 plan revisions have caused [HCCI] to
    be on the project months after the work should have been completed at
    enormous losses and costs to us. The contract adjustments do not take
    into account our daily rate for having our labor and equipment out on
    the project, our having to borrow funds from third parties to finance the
    project for [Springwoods and the District] because of [Springwoods’
    and the District’s] refusal to pay us as agreed under the contract. . . .
    Like the petition filed in the First Lawsuit on July 26, 2012, the July 18, 2012,
    August 1, 2012, and August 24, 2012 letters, and the September 12, 2012 email
    demonstrate that Appellants’ fraud claims are time-barred. These communications
    reflect that Appellants knew or should have known more than four years before they
    filed their original petition in the Third Lawsuit in December 2016, that Appellees
    33
    This email was included in the summary-judgment record and before the trial court
    when it ruled on Appellees’ motions for summary judgment.
    60
    allegedly had misrepresented to Appellants, during the bidding process in 2011, that
    the Project plans set forth in the bid drawings were complete and final. Royce
    Hassell—who handled HCCI’s claims and is the owner and president of RHC and
    RHB—also knew or should have known by no later than September 12, 2012 that
    Appellees allegedly had misrepresented to Appellants, after the Project began, that
    Appellees intended to pay for Appellants’ work on the Project and were “negotiating
    in good faith for payment adjustments to the Contract” and that Appellants had been
    harmed by these misrepresentations. See Woods, 
    769 S.W.2d 515
    , 517 (stating cause
    of action for fraud accrues “when the fraud is perpetrated, or if the fraud is concealed,
    from the time it is discovered or could have been discovered by the exercise of
    reasonable diligence”).
    Appellants argue Appellees did not conclusively establish that their fraud,
    fraudulent inducement, and fraud by nondisclosure claims accrued more than four
    years before they filed suit on December 12, 2016, because Appellants worked on
    the Project until as late as December 28, 2012, and they submitted an application for
    payment in January 2013 for work on the Project they performed between October
    and December 2012. Appellants further contend that they were attempting to
    negotiate all their claims with Appellees until as late as March 2013. Even taking
    as true all evidence favorable to Appellants, indulging every reasonable inference in
    their favor, and resolving any doubts in Appellants’ favor, as we must, this evidence
    61
    does not alter the fact that Appellants knew or should have known by July 26, 2012,
    or at the latest by September 12, 2012, that Springwoods and the District had not
    paid Appellants’ payment claims as of that date, that Springwoods and the District
    negotiated the payment claims allegedly in bad faith, that Springwoods and the
    District were refusing to meet with HCCI, and that any future attempts to mediate
    Appellants’ claims with Springwoods and the District would be, as Royce Hassell
    argued, futile. (“HCCI does not want to pursue a mediation claim which will just be
    a total waste of time like the [July 2012] mediation because of the posture assumed
    by the District and Springwoods.”) That Appellants continued to work on the Project
    and incurred additional losses does not change these facts. See Knott, 128 S.W.3d
    at 221 (stating cause of action “accrues when a wrongful act causes a legal injury,
    regardless of when the plaintiff learns of that injury or if all resulting damages have
    yet to occur”).
    Taking as true all evidence favorable to Appellants, indulging every
    reasonable inference in their favor, and resolving any doubts in Appellants’ favor,
    as we must, we conclude Appellees established that Appellants discovered the
    alleged fraudulent conduct or could have discovered the alleged fraudulent conduct
    62
    with reasonable diligence by no later than September 12, 2012. See Schlumberger
    Tech. Corp., 544 S.W.3d at 833.34
    We overrule Appellants’ first issue with regard to their fraud, fraudulent
    inducement, fraud by nondisclosure, and conspiracy to defraud claims and we affirm
    the trial court’s grant of summary judgment in Appellees’ favor with respect to these
    claims.
    E.    Appellants’ Assumpsit, Quantum-Meruit, and Unjust-Enrichment
    Claims
    In their original petition, Appellants pleaded a combined claim for “assumpsit,
    quantum meruit, and unjust enrichment” against Springwoods, the District, and
    WPM alleging they owed Appellants “for the full value of the work performed” and
    seeking “to recover that full value of work less amounts, if any, already paid.”
    Appellants also asked the court “to reform the Contract, imply a promise or render
    such relief to prevent the unjust enrichment of [Springwoods] and/or the District, to
    disgorge any ill-gotten enrichment, and to grant full restitution to Plaintiffs.” They
    alleged that “[b]ased upon the foregoing facts and in the alternative, Defendants
    directed and required performance of a scope of work outside the scope of work
    34
    Appellants did not challenge the trial court’s summary judgment on their claim of
    conspiracy to commit fraud in their opening brief and therefore, this issue has been
    waived. See Los Compadres Pescadores, L.L.C., 608 S.W.3d at 838 n.10 (“We
    need not address a new issue not raised by the appellant in the original brief.”); see
    also Champion, 
    126 S.W.3d at
    691–92 (declining to consider new issues raised in
    supplemental brief).
    63
    under the construction contract knowing that Plaintiffs expected to be paid for such
    work and would not have performed such work gratuitously. Plaintiffs performed
    the work as directed to the benefit of Defendants and to its detriment.” Alternatively,
    Appellants alleged that “Defendants owe[d] Plaintiffs for the full value of the work
    performed. Plaintiffs sue to recover that full value of work less amounts, if any,
    already paid.”
    The related equitable theories of unjust enrichment, quantum meruit, and
    assumpsit generally allow restitution of benefits conferred on a party when it would
    be unjust for that party to retain them. See generally Vortt Expl. Co., Inc. v. Chevron
    U.S.A., Inc., 
    787 S.W.2d 942
    , 944 (Tex. 1990) (stating “quantum meruit is founded
    on unjust enrichment”); Bashara v. Baptist Mem’l Hosp. Sys., 
    685 S.W.2d 307
    , 310
    (Tex. 1985) (stating quantum-meruit theory of recovery “founded in the principle of
    unjust enrichment”); Tri-State Chems., Inc. v. W. Organics, Inc., 
    83 S.W.3d 189
    ,
    194 (Tex. App.—Amarillo 2002, pet. denied) (stating quantum meruit is category of
    assumpsit). Although Appellants used the word “assumpsit” in their pleadings, they
    did not plead a claim for assumpsit. See Excess Underwriters at Lloyd’s, London v.
    Frank’s Casing Crew & Rental Tools, Inc., 
    246 S.W.3d 42
    , 49 (Tex. 2008)
    (“[A]cause of action [for assumpsit] arises when money is paid for the use and
    benefit of another.”) (citing King v. Tubb, 
    551 S.W.2d 436
    , 442 (Tex. Civ. App.—
    Corpus Christi 1977, no writ)). Thus, we construe Appellants’ pleadings to allege
    64
    claims for quantum meruit and unjust enrichment. See generally Tri-State Chems.,
    
    83 S.W.3d at 194
     (stating “the substance of what is pled controls, not the label or
    name appended to the claim”).
    1.    Unjust Enrichment
    The statute of limitations for unjust enrichment is two years. TEX. CIV. PRAC.
    & REM. CODE § 16.003(a); see Elledge v. Friberg-Cooper Water Supply Corp., 
    240 S.W.3d 869
    , 871 (Tex. 2007) (per curiam). In their motion for summary judgment,
    Appellees argued that Appellants’ unjust enrichment claims accrued in July 2012
    because Appellants knew by no later than the conclusion of parties’ mediation on
    July 2, 2012, that they had sustained an injury and Appellees were not going to pay
    them in accordance with Appellants’ damage calculations. See Clark v. Dillard’s,
    Inc., 
    460 S.W.3d 714
    , 719 (Tex. App.—Dallas 2015, no pet.) (stating claim for
    unjust enrichment accrues “when facts come into existence that authorize a claimant
    to seek a judicial remedy”) (citing Schneider Nat’l Carriers, Inc. v. Bates, 
    147 S.W.3d 264
    , 279 (Tex. 2004)).
    Appellees filed the Third Lawsuit on December 12, 2016. Thus, to avoid the
    applicable two-year statute of limitations, Appellees’ claim for unjust enrichment
    had to accrue on or after December 12, 2014. See TEX. CIV. PRAC. & REM. CODE §
    16.003(a); Elledge, 240 S.W.3d at 871. In their response to the motions for summary
    judgment and in their appellate brief, Appellants argue that “for the same reasons
    65
    expressed above [with respect to their breach of contract claim], Defendants have
    not conclusively demonstrated that Plaintiffs knew by no later than July 2, 2012, that
    Plaintiffs would not recover all of their alleged costs.”
    On July 26, 2012, HCCI filed the First Lawsuit. In its petition, HCCI alleged
    claims for quantum meruit and unjust enrichment based on the same facts asserted
    by Appellants in the Third Lawsuit. On September 15, 2014, Royce Hassell and
    Appellants RHC and RHB, filed their First Petition in Intervention in the First
    Lawsuit in which they alleged their claims “ar[o]se from the claims” made by HCCI
    in the First Lawsuit.35 Thus, the record reflects that Appellants had sufficient facts
    to seek a judicial remedy for unjust enrichment, at the earliest, on July 26, 2012,
    when HCCI filed the First Lawsuit, or at the latest on September 15, 2014, when
    RHC, RHB and Royce Hassell first attempted to intervene in the First Lawsuit. See
    Clark, 
    460 S.W.3d at 719
     (stating claim for unjust enrichment accrues “when facts
    come into existence that authorize a claimant to seek a judicial remedy”). Because
    Appellants’ claim for unjust enrichment accrued on or before September 15, 2014,
    the unjust enrichment claim filed by Appellants in the Third Lawsuit on December
    12, 2016 is barred by the two-year statute of limitations. See 
    id.
    35
    The First Petition in Intervention also included as intervenors: R. Hassell Holding
    Company, Inc. and Sylvia Hassell.
    66
    2.     Quantum Meruit
    Citing to Vortt Exploration Company v. Chevron U.S.A., Inc., 
    787 S.W.2d 942
    (Tex. 1990), Springwoods argued in its motion for summary judgment that it was
    entitled to summary judgment on Appellants’ quantum meruit claim because the
    Contract governed the services and materials Appellants provided with respect to
    the Project. Id. at 944 (“Generally, a party may recover under quantum meruit only
    when there is no express contract covering the services or materials furnished.”).
    The District and WPM adopted Springwoods’ motion and moved for summary
    judgment on the same grounds, including the existence of an express contract
    covering the services or materials Appellants furnished.
    Generally, the presence of an express contract bars recovery under quantum
    meruit. In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 732
    , 740 (Tex. 2005); Pepi
    Corp. v. Galliford, 
    254 S.W.3d 457
    , 462 (Tex. App.—Houston [1st Dist.] 2007, pet.
    denied); see generally Fortune Prod. Co. v. Conoco, Inc., 
    52 S.W.3d 671
    , 684 (Tex.
    2000) (stating “when a valid, express contract covers the subject matter of the
    parties’ dispute, there can be no recovery under a quasi-contract theory,” such as
    unjust enrichment). This rule not only applies when a plaintiff is seeking to recover
    in quantum meruit from the party with whom he expressly contracted, but also when
    a plaintiff is seeking to recover “from a third party foreign to the original but who
    benefited from its performance.” Pepi Corp., 
    254 S.W.3d at 462
     (quoting Hester v.
    67
    Friedkin Cos., Inc., 
    132 S.W.3d 100
    , 106 (Tex. App.—Houston [14th Dist.] 2004,
    pet. denied)).
    Appellants argue that “[a]lthough a party may not recover on an express
    contract and a quantum meruit claim, parties are permitted to plead alternative
    theories of recovery, such as express contract and quantum meruit.” While a plaintiff
    may plead alternative claims for breach of contract and quantum meruit, this does
    not alter the fact that a plaintiff cannot recover on its claim for quantum meruit if
    there is an express contract covering the subject matter of the parties’ dispute. Thus,
    Appellants’ argument is insufficient to raise a question of fact with respect to
    whether Appellants’ quantum meruit claim is barred because the Contract covers the
    services and materials Appellants furnished. In re Kellogg Brown & Root, Inc., 166
    S.W.3d at 740.
    Based on the record before us, we cannot say that the trial court abused its
    discretion by granting summary judgment in Appellees’ favor on Appellants’
    quantum meruit claim based on the existence of an express contract. See id.
    We overrule Appellants’ first issue with regard to their assumpsit, quantum
    meruit, and unjust enrichment claims and we affirm the trial court’s grant of
    summary judgment in Appellees’ favor with respect to these claims.
    68
    F.    Tolling of the Statute of Limitations
    Appellants argue on appeal that the statute of limitations for filing their claims
    was tolled by the automatic-stay provision of the United States Bankruptcy Code,36
    their petitions in intervention filed in the First Lawsuit, and the First Lawsuit itself.
    1.     Bankruptcy and Petitions in Intervention in First Lawsuit
    Appellees argue that because Appellants failed to plead tolling of the statute
    of limitations based on bankruptcy or the interventions filed in the First Lawsuit,
    they are precluded from making these arguments on appeal. Although Appellants
    pleaded in their supplemental petition in the Third Lawsuit that the First Lawsuit
    tolled the running of limitations, Appellants did not assert that any bankruptcy
    proceeding or the petitions in intervention filed in the First Lawsuit tolled limitations
    until they filed their response to Appellees’ motions for summary judgment.
    Generally, a summary judgment movant is required to negate the application
    of a tolling provision only if the nonmovant asserts that a tolling provision applies
    in its pleadings. See Via Net, 211 S.W.3d at 313. If, however, an unpleaded tolling
    provision is raised for the first time in response to a motion for summary judgment
    and the movant responds to the defense on the merits without objecting, thereby
    effectively trying the issue by consent, the movant must negate application of the
    36
    Section 362 of the bankruptcy code automatically stays the continuation of a judicial
    action on a claim “against the debtor.” See 
    11 U.S.C.A. § 362
    .
    69
    tolling provision. See 
    id.
     In this case, Appellees objected to Appellants’ assertion
    that bankruptcy or the petitions in intervention filed in the First Lawsuit tolled the
    statute of limitations because Appellants had not alleged either ground for tolling in
    their pleadings and were raising the tolling defenses for the first time in their
    response to the motions for summary judgment.37
    Because Appellants did not plead tolling of limitations based on any
    bankruptcy proceeding or their petitions in intervention filed in the First Lawsuit,
    and Appellees objected to the assertion of tolling on that basis, we conclude that
    these tolling defenses were not tried by consent and thus, Appellees were not
    required to negate either defense in order to meet their summary judgment burden.
    See 
    id.
     (stating that when plaintiff asserted discovery rule for first time in its
    summary-judgment response, defendant “had two choices: it could object that the
    discovery rule had not been pleaded, or it could respond on the merits and try the
    issue by consent”).
    2.     First Lawsuit
    Appellees argued in their motions for summary judgment that the First
    Lawsuit had not tolled limitations on Appellants’ claims because HCCI had
    voluntarily nonsuited its claims against the District and Springwoods. Appellants
    37
    After objecting, Springwoods also addressed the tolling defenses on the merits, out
    of an abundance of caution.
    70
    respond that HCCI’s nonsuit was involuntary, and thus, the First Lawsuit tolled the
    running of limitations on their claims.
    A voluntary nonsuit “extinguishes a case or controversy from the moment the
    motion [for nonsuit] is filed or an oral motion is made in open court” and it “renders
    the merits of the nonsuited case moot.” Travelers Ins. Co. v. Joachim, 
    315 S.W.3d 860
    , 862 (Tex. 2010). Thus, a lawsuit that is voluntarily nonsuited “does not
    interrupt the running of the statute of limitations.” Bailey v. Gardner, 
    154 S.W.3d 917
    , 920 (Tex. App.—Dallas 2005, no pet.); see also Cunningham v. Fox, 
    879 S.W.2d 210
    , 212 (Tex. App.—Houston [14th Dist.] 1994, writ denied) (“A dismissal
    is the equivalent of a suit never having been filed. Therefore, if a suit is dismissed,
    the statute of limitations is not tolled for any new pleading filed.”) (internal citation
    omitted). The statute of limitations may be tolled, however, if the abandonment of
    the suit is “sufficiently explained or accounted for so as to relieve it of being
    voluntary.” See Flatonia State Bank v. Sw. Life Ins. Co., 
    127 S.W.2d 188
    , 193 (Tex.
    1939), set aside on other grounds, 
    133 Tex. 243
    , 
    128 S.W.2d 790
     (1939) (“If the
    reason for such abandonment is sufficiently explained or accounted for so as to
    relieve it of being voluntary, the running of the statute is interrupted by the filing of
    the suit.”); see also Zurich Ins. Co. v. Northline Joint Venture, No. 14-00-00090-
    CV, 
    2001 WL 1288830
    , at *3 (Tex. App.—Houston [14th Dist.] Oct. 25, 2001, pet.
    denied) (mem. op.) (citing Flatonia State Bank, 
    127 S.W.2d at 193
    ).
    71
    It is undisputed that HCCI sued the District and Springwoods on July 26,
    2012, based on their refusal to pay HCCI’s claims for delay damages and that HCCI
    nonsuited its causes of action in the First Lawsuit on October 3, 2016. According
    to Appellants, HCCI’s nonsuit was involuntary because HCCI was acting as their
    agent or partner in the First Lawsuit, the claims HCCI asserted in that suit were
    effectively theirs, and RHC did not authorize HCCI to nonsuit its claims or to take
    any other action. Citing to Texas Mutual Insurance Company v. Ledbetter, 
    251 S.W.3d 31
     (Tex. 2008), RHC further contends that HCCI’s nonsuit should not
    adversely impact its rights as a principal to the Contract or partner of HCCI for
    purposes of the Contract.
    Appellants’ arguments are not persuasive. Even assuming without deciding
    that HCCI was acting as RHC’s and RHB’s agent or partner in the First Lawsuit and
    that RHC and RHB did not consent to or authorize HCCI to nonsuit their claims,
    Appellants have not cited to any legal authority supporting the proposition that an
    agent’s or partner’s unauthorized conduct renders that act involuntary with respect
    to its principal or another partner.
    Appellants also cite to Ledbetter for the proposition that, although a party has
    an absolute right to nonsuit its own claims, it may not nonsuit someone else’s claims.
    Ledbetter, however, did not involve an alleged agent, principal, or partnership
    relationship between the nonsuiting party and the party whose interests in the suit
    72
    was allegedly affected. Rather, the issue in that tort case was whether a trial court
    was required to grant the plaintiffs’ nonsuit and dismiss the plaintiffs from the suit,
    even though an insurance carrier had filed a petition in intervention seeking
    subrogation and a declaratory judgment regarding its duty to make payments to the
    plaintiffs in the future. Ledbetter, 251 S.W.3d at 37–38. Texas Rule of Civil
    Procedure 162, which governs nonsuits, states that “[a]ny dismissal pursuant to this
    rule shall not prejudice the right of an adverse party to be heard on a pending claim
    for affirmative relief.” TEX. R. CIV. P. 162. The Ledbetter court held that the trial
    court abused its discretion by striking the petition in intervention because the
    carrier’s subrogation claim was a claim for affirmative relief and Rule 162 “prohibits
    dismissal if the effect would be to prejudice any pending claim for affirmative relief,
    period.” Ledbetter, 251 S.W.3d at 38–39. The court also reversed the trial court’s
    dismissal of the plaintiffs from the litigation because the carrier’s declaratory
    judgment claim could not be decided in their absence. Id. at 38 (citing TEX. CIV.
    PRAC. & REM. CODE § 37.006(a)). Thus, the facts of Ledbetter are not analogous.
    Furthermore, RHC and RHB were not parties to the First Lawsuit. Although
    RHC and RHB filed petitions in intervention in the First Lawsuit, both petitions were
    struck. “[A]n intervenor is a party for purposes of appeal only if (1) [it] timely files
    a pleading, and (2) the trial court does not strike the pleading before the entry of a
    final judgment.” Johnston v. Crook, 
    93 S.W.3d 263
    , 268 (Tex. App.—Houston
    73
    [14th Dist.] 2002, pet. denied). Because the trial court struck RHC’s and RHB’s
    petitions in intervention before it entered its final judgment, RHC and RHB were not
    parties to the First Lawsuit. See 
    id.
     at 268–69 (holding interveners who “filed
    untimely pleas in intervention after judgment, were never parties and could not have
    appealed the judgment or dismissal of their pleas”). Thus, HCCI’s nonsuit in the
    First Lawsuit did not violate Texas Rule of Civil Procedure 162 because RHC and
    RHB were not parties to the First Lawsuit and, thus, RHC and RHB did not have
    claims pending in that lawsuit. See TEX. R. CIV. P. 162 (“Any dismissal pursuant to
    this rule shall not prejudice the right of an adverse party to be heard on a pending
    claim for affirmative relief.”).
    Appellants also suggest that HCCI’s nonsuit was involuntary as to HCCI’s
    own claims—which are now being asserted derivatively on its behalf by one of its
    purported shareholders, Royce Hassell—because Royce Hassell did not know about
    the nonsuit beforehand or authorize HCCI to take such action. Appellants, however,
    have not directed us to any legal authority supporting their position that a
    corporation’s nonsuit is involuntary because one of its shareholders was unaware of
    the nonsuit beforehand or disagrees with the corporation’s decision to nonsuit its
    claims.
    We overrule Appellants’ argument that the trial court abused its discretion by
    granting Appellees’ motion for summary judgment based on the statute of
    74
    limitations because its claims were tolled by bankruptcy proceedings, RHC’s and
    RHB’s petitions in intervention filed in the First Lawsuit, or the First Lawsuit.
    Conclusion
    We affirm the trial court’s judgment.
    Veronica Rivas-Molloy
    Justice
    Panel consists of Justices Kelly, Countiss, and Rivas-Molloy.
    75
    

Document Info

Docket Number: 01-17-00822-CV

Filed Date: 3/7/2023

Precedential Status: Precedential

Modified Date: 3/13/2023

Authorities (24)

Bailey v. Gardner , 2005 Tex. App. LEXIS 769 ( 2005 )

Chapman v. King Ranch, Inc. , 41 S.W.3d 693 ( 2001 )

Godde v. Wood , 1974 Tex. App. LEXIS 2318 ( 1974 )

FLCT, Ltd. v. City of Frisco , 2016 Tex. App. LEXIS 5623 ( 2016 )

Lockett v. HB Zachry Co. , 2009 Tex. App. LEXIS 7296 ( 2009 )

Johnston v. Crook , 2002 Tex. App. LEXIS 5513 ( 2002 )

Flatonia State Bank v. Southwestern Life Insurance , 133 Tex. 243 ( 1939 )

Cunningham v. Fox , 1994 Tex. App. LEXIS 1096 ( 1994 )

State v. Boyd , 2000 Tenn. Crim. App. LEXIS 672 ( 2000 )

Champion v. State , 126 S.W.3d 686 ( 2004 )

Hester v. Friedkin Companies, Inc. , 2004 Tex. App. LEXIS 2636 ( 2004 )

Gerald Byron Barras v. Leslea Loring Barras , 2013 Tex. App. LEXIS 705 ( 2013 )

Stephen W. Clark v. Dillard's Inc. and the Campbell Agency , 2015 Tex. App. LEXIS 2817 ( 2015 )

King v. Tubb , 1977 Tex. App. LEXIS 2836 ( 1977 )

Solutioneers Consulting, Ltd. v. Gulf Greyhound Partners, ... , 237 S.W.3d 379 ( 2007 )

City & County of Dallas Levee Improvement Dist. v. Halsey, ... , 1947 Tex. App. LEXIS 961 ( 1947 )

Flatonia State Bank v. Southwestern Life Ins. Co. , 128 S.W.2d 790 ( 1939 )

Tri-State Chemicals, Inc. v. Western Organics, Inc. , 83 S.W.3d 189 ( 2002 )

Woods v. William M. Mercer, Inc. , 32 Tex. Sup. Ct. J. 99 ( 1988 )

Hubble v. Lone Star Contracting Corp. , 883 S.W.2d 379 ( 1994 )

View All Authorities »