ARC Designs, Inc. v. Nabors Industrial, Inc. ( 2020 )


Menu:
  • Opinion issued April 21, 2020
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-18-00992-CV
    ———————————
    ARC DESIGNS, INC., Appellant
    V.
    NABORS INDUSTRIES, INC., Appellee
    On Appeal from the 269th District Court
    Harris County, Texas
    Trial Court Case No. 2015-16752
    MEMORANDUM OPINION
    Appellee, Nabors Industries, Inc. (“Nabors”), contracted with appellant, Arc
    Designs, Inc. (“ADI”), for the fabrication and construction of certain drilling rig
    equipment. After ADI failed to deliver the equipment as agreed under the terms of
    the parties’ Fabrication and Construction Contract (“Contract”), Nabors terminated
    the Contract and sued ADI for breach of contract. ADI brought a counterclaim,
    asserting that Nabors breached the Contract by failing to pay as agreed. The trial
    court rendered summary judgment in favor of Nabors on its claim and awarded it
    damages. The trial court denied ADI’s motion for summary judgment on its
    counterclaim. After a trial to the court on the limited issue of attorney’s fees, the
    trial court awarded Nabors its fees.
    On appeal, ADI presents four issues. In its first issue, ADI contends that the
    trial court erred in granting summary judgment for Nabors because ADI presented
    evidence raising a fact issue regarding the applicable termination and damages
    provisions in the Contract. In its second and third issues, ADI contends that the trial
    court erred in granting Nabors’s summary-judgment motion, and denying that of
    ADI, because the trial court misconstrued the Contract terms as providing a right of
    reimbursement and failed to award ADI certain sums due. In its fourth issue, ADI
    contends that the trial court erred in awarding attorney’s fees.
    We affirm.
    Background
    Nabors owns and operates land-based drilling rigs and provides oilfield
    services. ADI is a drilling-structure manufacturing facility and metal fabricator. On
    February 12, 2014, Nabors retained ADI to fabricate and construct five sets (“Sets”)
    of drilling rig components. Each Set was comprised of a mast and a substructure.
    2
    The Contract Price was $651,248.00 for each mast and $1,276,667.00 for each
    substructure, or a total of $1,927,915.00 for each Set. The parties agreed, as
    provided in Article 2.2 of the Contract, that Nabors was to pay the Contract Price for
    each Set in installments, based on the completion of certain “milestones” in the
    fabrication and construction process, as follows:
    20% of Contract Price within 10 days of execution of [the] Contract by
    both parties.
    25% of Contract Price upon [ADI’s] receipt of all structural steel in
    [ADI’s] fabrication facility complete with MTR’s that meet contract
    requirements.
    45% of Contract Price upon completing of all Work, including
    electronic delivery of the Equipment’s data book and all API
    nameplates affixed to the Equipment.
    10% of Contract Price for final payment pursuant to the delivery dates
    set forth on [the Schedule of Delivery].
    Pursuant to the terms of Contract, ADI was to deliver one Set per month for
    five consecutive months, beginning in October 2014 and ending in February 2015.
    According to the Schedule of Delivery, Set 1 was to be delivered on October 31,
    2014; Set 2 on November 30, 2014; Set 3 on December 31, 2014; Set 4 on January
    31, 2015; and, Set 5 on February 28, 2015. The Schedule of Delivery included a
    “penalty date” occurring 30 days after each due date. And, Article III of the
    Contract, governing delivery, provided:
    3.1    [ADI] shall complete the Work as set forth in [Schedule of
    Delivery]. . . . [I]f any of the Equipment is delivered after the
    Penalty Date . . . , then [ADI] shall be liable to [Nabors] for
    liquidated damages in an amount equal to one (1%) of the
    3
    Contract Price for each day that delivery is delayed, provided that
    in no event shall [ADI] be liable to [Nabors] for more than ten
    percent (10%) of the Contract Price.
    3.2   Time is of the essence with respect to the performance of the
    Work and there shall be no extension or postponement of the
    Delivery Date. The Parties agree that this Article is a material
    term of this Contract for all purposes.
    3.3    . . . . Any change to [the Schedule of Delivery] will only be made
    in writing by agreement of the Parties. . . .
    In the event that ADI failed to “conduct its operations” under the Contract
    with diligence or “otherwise breached its obligations,” Article IX, “Unsatisfactory
    Performance,” authorized Nabors to elect whether to cover or to pursue other
    remedies under the law or in equity:
    9.1   If [ADI] has failed to conduct its operations under this Contract
    in a diligent, skillful or workmanlike manner . . . , or if the [ADI]
    has otherwise breached its obligations hereunder, [Nabors] may
    give [ADI] written notice in which the cause of the
    dissatisfaction shall be specified. Should [ADI] fail to remedy
    the dissatisfaction within five (5) days after the receipt of the
    written notice, [Nabors] may, at its discretion take one of the
    following courses of action:
    9.1.1 [Nabors] may retain another Contractor (’’Substitute
    Contractor”) to complete the remaining Work. In such
    event [Nabors] shall have no obligation to pay [ADI] any
    additional sums whatsoever and [ADI] shall be
    responsible to pay to [Nabors] the difference between the
    outstanding relevant Purchase Order and the actual cost of
    completing the Work with the Substitute Contractor.
    9.1.2 [Nabors] may take over and complete the Work using
    [ADI’s] facilities, equipment and personnel. If [Nabors]
    takes over the Work, [Nabor’s] cost in completing the
    Work with no allowance for use of [ADI’s] facilities,
    4
    equipment and personnel shall be deducted from the
    Contract Price . . . .
    9.1.3 Upon [Nabors’s] request and pursuant to [Article XI],
    [ADI] shall allow [Nabors] to remove any and all
    Equipment in whatever stages of completion as well as
    other manufactured products related to the Equipment.
    9.2    The remedies set forth in this Article are in addition to, and not
    in lieu of any and all other remedies available to [Nabors] in law
    or equity.
    And, Article 24.4 provided that the “prevailing party in any lawsuit shall be entitled
    to recover reasonable and necessary attorneys’ fees.”
    Article XI, “Termination of the Contract,” provided that Nabors could also
    terminate the Contract, either at will or for unsatisfactory performance under Article
    IX above, as follows:
    11.1 This Contract may be terminated
    11.1.1        By [Nabors] upon 10 days’ notice.
    ....
    11.1.3        By [Nabors] for unsatisfactory performance as set
    forth in Article IX above.
    In the event that Nabors terminated the Contract pursuant to Article 11.1.1,
    i.e., at will, Article 11.2 governed the amounts owed to ADI as follows:
    [Nabors] shall pay to [ADI] all amounts due and owing at the date of
    termination together with reasonable additional costs incurred by [ADI]
    in terminating the Work including if applicable, costs of shipping and
    the costs of cancellation of subcontracts or purchase orders for
    materials, equipment and supplies. In no event shall [Nabors] be
    entitled to payment for any loss of any profit as a result of such
    termination.
    5
    In the event that Nabors terminated the Contract pursuant to Article 11.1.3,
    i.e., for cause based on ADI’s “unsatisfactory performance as set forth in Article IX
    above,” Article 11.4 provided that ADI “shall not be entitled to any compensation
    whatever [sic].”
    It is undisputed that ADI did not deliver Set 1 by the date specified in the
    Schedule of Delivery, that of October 31, 2014. Rather, ADI delivered a portion of
    Set 1, the substructure, on December 15, 2014. Nabors asserts that, not only was the
    substructure almost two months late, but it was defective, causing Nabors to incur
    $175,000.00 to remedy defects. ADI did not complete the mast component of Set 1
    until January 2015. On February 3, 2014, after Sets 2, 3, and 4, which the Schedule
    of Delivery stated were due by November 30, 2014, December 31, 2014, and January
    31, 2015, respectively, were not delivered, Nabors issued a change order to reduce
    the scope of the Contract to Set 1 and the mast component of Set 2. Nabors
    demanded reimbursement of its milestone payments but stated that it was willing to
    reduce this sum by a mutually agreed upon amount for ADI’s expenses on the three
    masts and four substructures being reduced.
    On February 6, 2015, after the parties were unable to reach a resolution,
    Nabors sent ADI a Notice of Termination, stating that it was terminating the
    Contract, pursuant to Article 11.1.3, with respect to Sets 1 through 4, based on ADI’s
    “unsatisfactory performance” under Article IX, i.e., inability to comply with the
    6
    agreed delivery deadlines. Nabors demanded, pursuant to Article 11.4, repayment
    of $2,804,681.10 that it had paid toward the equipment that ADI had failed to
    deliver. Noting that the terms of the Contract provided, however, that ADI’s
    obligation to deliver was unconditional and effective notwithstanding any dispute
    regarding payment of some or all of the Contract Price, Nabors demanded that ADI
    deliver Set 5 by February 28, 2015, the remaining pending deadline under the
    Contract. Subsequently, however, after ADI failed to timely deliver Set 5, Nabors
    sent ADI notice that that it was terminating the Contract, pursuant to Article 11.1.3,
    with respect to Set 5, based on ADI’s unsatisfactory performance.
    ADI refused to return any of the sums paid toward the equipment that it had
    failed to deliver and refused to release the mast component of Set 1 unless Nabors
    paid an additional $358,186.40.
    Nabors sued ADI, alleging that it had materially breached the Contract by
    failing to deliver the equipment as agreed.       Nabors sought reimbursement of
    $2,388,228.00 in previous payments, as well as delivery and possession of the mast
    component of Set 1.
    ADI filed a counterclaim for breach of contract and quantum meruit, alleging
    that Nabors had taken delivery of the mast component of Set 1, along with some of
    the materials for Sets 2 through 5, and had failed to pay $358,186.40 for work and
    materials supplied under the Contract.
    7
    Nabors moved for a summary judgment on its breach-of-contract claim,
    asserting that it was entitled to judgment as a matter of law because the Contract
    expressly provided for specific delivery deadlines and expressly stated that time was
    of the essence and that these terms were material. Noting that it was undisputed that
    ADI had failed to timely deliver Set 1, Nabors asserted that such failure to meet the
    deadlines in a contract in which time is of the essence, as here, constituted a material
    breach.
    Based on ADI’s breach, Nabors asserted that Article 11.1.3 authorized it to
    terminate the Contract for “unsatisfactory performance” as set forth in Article IX.
    Article IX authorized termination for failure to perform in a diligent manner or if
    ADI otherwise breached its obligations, as here. Nabors sent notice to ADI,
    expressly terminating the Contract pursuant to Article 11.1.3. And, Nabors noted
    that Article 11.4 provided that if the Contract were terminated pursuant to Article
    11.1.3, “Contractor [ADI] shall not be entitled to any compensation whatever [sic].”
    With respect to its damages, Nabors asserted that it had received only one of
    the five Sets for which it had contracted.         The Contract Price per Set was
    $1,927,915.00. Nabors asserted that, after subtracting the maximum ten-percent
    penalty under Article 3.1 for late delivery, or $192,791.50, it owed ADI a total of
    $1,735,123.50 for Set 1. At the time of Nabors’s termination of the Contract, it had
    paid ADI a total of $3,948,351.40, including its milestone payments on all five Sets
    8
    of equipment. Subtracting the total owed on Set 1 from the total it had paid, Nabors
    sought damages of $2,213,227.90. Nabors presented, as its summary-judgment
    evidence, the Contract; February 3, 2015 change order; February 6, 2015 Notice of
    Termination with respect to Sets 1–4; March 20, 2015 termination letter with respect
    to Set 5; a table of costs; affidavit of Nabors’s Senior QA/QC Manager of the
    Engineering Department, Kevin Pennington; various emails between Nabors and
    ADI; deposition excerpts of ADI corporate representative, Joshua W. Norris; and
    ADI’s responses to discovery.
    In its summary-judgment response, ADI argued that Nabors had simply
    terminated the Contract at will, pursuant to Article 11.1.1, and not for cause, and
    thus it was not entitled to any reimbursement of its previous payments. ADI asserted
    that Nabors had previously stated that it was re-evaluating the Contract due to the
    downturn in the oil market. And, ADI had delivered equipment as much as two
    months late under a previous contract between the parties without issue. Further,
    Article 3.1 provided for a late delivery penalty. And, because the parties had thereby
    agreed to liquidated damages, late delivery could not serve as cause for termination
    under Article XI of the Contract. ADI argued that Article 2.2 of the Contract
    provided that milestone payments are due once the milestone is completed and,
    because ADI had completed the initial 20 percent milestones at the time of
    termination, such sums were not subject to refund.
    9
    ADI also filed a cross-motion for summary judgment, arguing that it was
    entitled to judgment as a matter of law on its breach-of-contract counterclaim. It
    asserted that neither Article 2.2 nor Article 11 provided for refunds. Further, ADI
    argued, the evidence established that it was entitled to $358,186.40 in unpaid
    milestone payments for the mast component of Set 1 because ADI had completed
    the work, and Nabors had approved and taken delivery of it.
    The trial court granted summary judgment in favor of Nabors on its breach-
    of-contract claim and awarded it damages in the amount of $2,213,227.90. The trial
    court denied ADI’s competing motion for summary judgment and dismissed ADI’s
    counterclaim for breach of contract. After a trial to the court on the limited issue of
    attorney’s fees, the trial court found that Nabors was entitled to reasonable and
    necessary attorneys’ fees based on the terms of the Contract and pursuant to Texas
    Civil Practice & Remedies Code section 38.001. The trial court awarded Nabors
    attorney’s fees in the amount of $161,023.51 and fees for appeal.
    Summary Judgment
    In its first issue, ADI argues that the trial court erred in granting summary
    judgment in favor of Nabors on its claim because ADI presented evidence raising a
    fact issue regarding the applicable termination and damages provisions in the
    Contract. In its second and third issues, ADI argues that the trial court erred in
    granting Nabors’s summary-judgment motion, and denying that of ADI, because the
    10
    trial court misconstrued the Contract as providing a right of reimbursement of funds
    that Nabors had paid prior to its termination of the Contract and the trial court failed
    to award ADI certain sums outstanding on Set 1.
    A.    Standard of Review and Overarching Legal Principles
    We review a trial court’s summary judgment de novo. Valence Operating Co.
    v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005). In conducting our review, we take as
    true all evidence favorable to the non-movant, and we indulge every reasonable
    inference and resolve any doubts in the non-movant’s favor.
    Id. If a
    trial court
    grants summary judgment without specifying the grounds for granting the motion,
    we must uphold the trial court’s judgment if any of the asserted grounds are
    meritorious. Beverick v. Koch Power, Inc., 
    186 S.W.3d 145
    , 148 (Tex. App.—
    Houston [1st Dist.] 2005, pet. denied).
    In a traditional motion for summary judgment, the movant has the burden to
    establish that there exists no genuine issue of material fact and that it is entitled to
    judgment as a matter of law. See TEX. R. CIV. P. 166a(c); KPMG Peat Marwick v.
    Harrison Cty. Hous. Fin. Corp., 
    988 S.W.2d 746
    , 748 (Tex. 1999). When a plaintiff
    moves for summary judgment on its own claim, the plaintiff must conclusively prove
    all essential elements of its cause of action. MMP, Ltd. v. Jones, 
    710 S.W.2d 59
    , 60
    (Tex. 1986). When a defendant moves for a traditional summary judgment, it must
    either: (1) disprove at least one essential element of the plaintiff’s cause of action or
    11
    (2) plead and conclusively establish each essential element of an affirmative defense,
    thereby defeating the plaintiff’s cause of action. See Rhône–Poulenc, Inc. v. Steel,
    
    997 S.W.2d 217
    , 222–23 (Tex. 1999); Cathey v. Booth, 
    900 S.W.2d 339
    , 341 (Tex.
    1995). Once the movant meets its burden, the burden shifts to the non-movant to
    raise a genuine issue of material fact precluding summary judgment. Centeq Realty,
    Inc. v. Siegler, 
    899 S.W.2d 195
    , 197 (Tex. 1995). The evidence raises a genuine
    issue of fact if reasonable and fair-minded jurors could differ in their conclusions in
    light of all of the summary-judgment evidence. Goodyear Tire & Rubber Co. v.
    Mayes, 
    236 S.W.3d 754
    , 755 (Tex. 2007).
    When both parties move for summary judgment on the same issue and the
    trial court grants one motion and denies the other, as here, the reviewing court
    considers the summary judgment evidence presented by both sides, determines all
    questions presented, and if the reviewing court determines that the trial court erred,
    renders the judgment that the trial court should have rendered. Valence Operating
    
    Co., 164 S.W.3d at 661
    .
    B.    Breach of Contract
    To prevail on its respective breach-of-contract claim, each party was required
    to establish (1) a valid contract between the parties; (2) that the movant tendered
    performance or was excused from doing so; (3) that the non-movant breached the
    terms of the contract; and (4) that the movant sustained damages as a result of the
    12
    breach. AMS Const. Co. v. K.H.K. Scaffolding Hous., Inc., 
    357 S.W.3d 30
    , 41 (Tex.
    App.—Houston [1st Dist.] 2011, pet. dism’d); B&W Supply, Inc. v. Beckman, 
    305 S.W.3d 10
    , 16 (Tex. App.—Houston [1st Dist.] 2009, pet. denied).
    Here, it is undisputed that the Contract constitutes a valid, enforceable
    agreement. It is also undisputed that ADI did not deliver Set 1 by the agreed upon
    date in the Schedule of Delivery and did not deliver Sets 2–5. It is further undisputed
    that Nabors terminated the Contract. The parties disagree as to the applicable
    termination provision in the Contract, i.e., Article 11.1.1 (authorizing termination at
    will) or Article 11.1.3 (authorizing termination for cause), which in turn governs the
    corresponding measure of damages.
    1.     Applicable Termination and Damages Provisions
    In construing a written contract, a court must ascertain and give effect to the
    true intentions of the parties as expressed in the writing itself. Italian Cowboy
    Partners, Ltd. v. Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 333 (Tex. 2011). We
    examine and consider the entire writing in an effort to harmonize and give effect to
    all the provisions of the contract so that none will be rendered meaningless.
    Id. We begin
    our analysis with the contract’s express language.
    Id. And we
    analyze the
    provisions of a contract “with reference to the whole agreement.” Frost Nat’l Bank
    v. L & F Dists., Ltd., 
    165 S.W.3d 310
    , 312 (Tex. 2005); see also Seagull Energy
    E&P, Inc. v. Eland Energy, Inc., 
    207 S.W.3d 342
    , 345 (Tex. 2006) (“No single
    13
    provision taken alone will be given controlling effect; rather, all the provisions must
    be considered with reference to the whole instrument.”). Contract terms will be
    given their plain, ordinary, and generally accepted meanings unless the contract
    itself shows them to be used in a technical or different sense. Valence Operating
    
    Co., 164 S.W.3d at 662
    . “We construe contracts ‘from a utilitarian standpoint
    bearing in mind the particular business activity sought to be served’ and ‘will avoid
    when possible and proper a construction which is unreasonable, inequitable, and
    oppressive.’” Frost Nat’l 
    Bank, 165 S.W.3d at 312
    (quoting Reilly v. Rangers
    Mgmt., Inc., 
    727 S.W.2d 527
    , 530 (Tex. 1987)).
    If, after applying the pertinent contract construction rules, the contract can be
    given a certain or definite legal meaning or interpretation, then it is not ambiguous,
    and we will construe the contract as a matter of law.
    Id. If a
    contract “is subject to
    two or more reasonable interpretations after applying the pertinent rules of
    construction, the contract is ambiguous, creating a fact issue on the parties’ intent.”
    J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003). However, a
    contract is not ambiguous merely because the parties disagree on its meaning.
    Seagull Energy E & P, 
    Inc., 207 S.W.3d at 345
    . Only if a contract is ambiguous
    may we consider the parties’ interpretation and consider extraneous evidence to
    determine the true meaning of the contract. Italian Cowboy Partners, 
    Ltd., 341 S.W.3d at 333
    –34.
    14
    Here, Article III of the Contract, governing delivery, provides:
    3.1    [ADI] shall complete the Work as set forth in [the Schedule of
    Delivery]. . . . [I]f any of the Equipment is delivered after the
    Penalty Date . . . , then [ADI] shall be liable to [Nabors] for
    liquidated damages in an amount equal to one (1%) of the
    Contract Price for each day that delivery is delayed, provided that
    in no event shall [ADI] be liable to [Nabors] for more than ten
    percent (10%) of the Contract Price.
    3.2    Time is of the essence with respect to the performance of the
    Work and there shall be no extension or postponement of the
    Delivery Date. The Parties agree that this Article is a material
    term of this Contract for all purposes.
    (Emphasis added.) Thus, Article III provides that ADI was to complete the work
    by the deadlines set forth in the Schedule of Delivery. The parties agreed that time
    was of the essence, that there would be no extensions, and that this term is material.
    It is undisputed that ADI did not timely deliver Set 1 and did not deliver the
    remaining Sets. Thus, ADI’s failure to timely deliver the equipment at issue
    constitutes a material breach of the Contract. See Mustang Pipeline Co. v. Driver
    Pipeline Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004); Henry v. Masson, 
    333 S.W.3d 825
    ,
    835 (Tex. App.—Houston [1st Dist.] 2010, no pet.); see also Kennedy Ship &
    Repair, L.P. v. Pham, 
    210 S.W.3d 11
    , 21 (Tex. App.—Houston [14th Dist.] 2006,
    no pet.) (holding that failure to timely deliver goods constituted breach).
    The summary-judgment evidence shows that, based on ADI’s breach of the
    Contract, Nabors, on February 6, 2015, sent ADI a Notice of Termination, stating
    15
    that, pursuant to Article 11.1.3, it was terminating the Contract with respect to Sets
    1–4:
    Based on our numerous written attempts to get [ADI] to comply with
    the delivery deadlines for the first four [Sets] specified in the [Contract]
    and [ADI’s] inability to comply given ample opportunity, pursuant to
    Articles IX and XI of the Agreement, Nabors is hereby providing you
    with notice that the [Contract] is being terminated under Article 11.1.3
    for unsatisfactory performance. In accordance with the terms of Section
    11.4 of the Agreement, Nabors demands return of all sums paid to date
    from Nabors, exclusive of the first substructure already delivered,
    totaling $2,804,681,10. In addition, Nabors requests, pursuant to
    Section 9.1.3 that Nabors be allowed to remove any and all Equipment
    in whatever stages of completion as well as other manufactured
    products related to the Equipment.
    (Emphasis added.)
    Further, Nabors’s evidence shows that, on March 5, 2015, it sent ADI notice
    that, pursuant to Article 11.1.3, it was terminating the Contract with respect to Set
    5:
    You were notified on February 6, 2015 that the [Contract] was
    terminated with respect to the first four [Sets] specified therein under
    Article 11.1.3 for unsatisfactory performance.
    You have already demonstrated [ADI’s] inability to comply with the
    [Contract] with respect to the first four [Sets]. Given, your recent
    correspondence, you are clearly unwilling to comply with the
    Agreement with respect to the fifth [Set]. You are hereby notified that
    the Agreement is being terminated under Article 11.1.3 for
    unsatisfactory performance with regard to [Set 5], which was due on
    February 28, 2015. Pursuant to Section 11.4 of the [Contract], Nabors
    demands return of all sums paid for the fifth set, totaling $255,333.40.
    (Emphasis added.)
    16
    Article XI, “Termination of the Contract,” authorizes Nabors to terminate the
    Contract, either at will or for unsatisfactory performance, as follows:
    11.1 This Contract may be terminated
    11.1.1       By [Nabors] upon 10 days’ notice.
    ....
    11.1.3       By [Nabors] for unsatisfactory performance as set
    forth in Article IX above.
    In the event that Nabors terminated the Contract pursuant to Article 11.1.1,
    i.e., at will, Article 11.2 provides the following damages model:
    [Nabors] shall pay to [ADI] all amounts due and owing at the date of
    termination together with reasonable additional costs incurred by [ADI]
    in terminating the Work including if applicable, costs of shipping and
    the costs of cancellation of subcontracts or purchase orders for
    materials, equipment and supplies. In no event shall [ADI] be entitled
    to payment for any loss of any profit as a result of such termination.
    However, in the event that Nabors terminated the Contract pursuant to Article
    11.1.3, i.e., for cause based on ADI’s “unsatisfactory performance as set forth in
    Article IX,” as here, Article 11.4 provides that ADI “shall not be entitled to any
    compensation whatever [sic].”
    Article IX defines “unsatisfactory performance” as including any failure by
    ADI to conduct its operations diligently or any breach of the Contract by ADI and
    authorizes Nabors to elect to cover or to pursue “any and all other remedies
    available to [Nabors] in law or equity”:
    9.1    If [ADI] has failed to conduct its operations under this Contract
    in a diligent, skillful or workmanlike manner . . . , or if the [ADI]
    17
    has otherwise breached its obligations hereunder, [Nabors] may
    give [ADI] written notice in which the cause of the
    dissatisfaction shall be specified. Should [ADI] fail to remedy
    the dissatisfaction within five (5) days after the receipt of the
    written notice, [Nabors] may, at its discretion take one of the
    following courses of action:
    9.1.1 [Nabors] may retain another Contractor (“Substitute
    Contractor”) to complete the remaining Work. In such
    event [Nabors] shall have no obligation to pay [ADI] any
    additional sums whatsoever and [ADI] shall be
    responsible to pay to [Nabors] the difference between the
    outstanding relevant Purchase Order and the actual cost of
    completing the Work with the Substitute Contractor.
    9.1.2 [Nabors] may take over and complete the Work using
    [ADI’s] facilities, equipment and personnel . . . .
    9.1.3 Upon [Nabors’s] request and pursuant to [Article XI],
    [ADI] shall allow [Nabors] to remove any and all
    Equipment in whatever stages of completion as well as
    other manufactured products related to the Equipment.
    9.2   The remedies set forth in this Article are in addition to, and not
    in lieu of any and all other remedies available to [Nabors] in law
    or equity.
    (Emphasis added.) Thus, the summary-judgment evidence shows that Nabors
    expressly terminated the Contract under Article 11.1.3, based on ADI’s
    “unsatisfactory performance,” and that the Contract authorized such termination.
    ADI, in its summary-judgment response and in its brief, argues that it
    presented evidence creating a fact issue regarding whether Nabors actually
    terminated the Contract at will, pursuant to Article 11.1.1, and not for cause,
    pursuant to Article 11.1.3. Specifically, ADI points to an email from Nabors, dated
    January 15, 2015, in which Nabors, noting that the “global drilling industry had
    18
    recently begun showing signs of a dramatic slowdown,” asked ADI for an
    “immediate update on cost to date for the remaining mast and sub orders.” And,
    Nabors stated that the purpose of its request was to “determine whether [to] proceed
    or cancel some or all of the remaining orders.” ADI argues that this evidence
    establishes that Nabors’s representation that its termination of the Contract was
    based on ADI’s failure to timely deliver equipment was simply pretext for its at-will
    termination based on market conditions.
    Taking as true, as we must, the evidence that Nabors considered whether to
    proceed on its outstanding orders based on market conditions does not, however,
    negate or contradict the evidence that, ultimately, Nabors expressly terminated the
    Contract pursuant to Article 11.1.3, “for unsatisfactory performance as set forth in
    Article IX,” based on ADI’s undisputed failure to deliver the Sets as agreed.
    Next, ADI argues that the “parties’ ongoing course of conduct” demonstrates
    that Nabors did not actually terminate the Contract for cause. ADI points to its
    summary-judgment evidence that Nabors previously accepted late delivery of three
    rigs in “a prior contract between the Parties in 2013-2014.”
    A “‘course of dealing’ is a sequence of conduct concerning previous
    transactions between the parties to a particular transaction that is fairly to be regarded
    as establishing a common basis of understanding for interpreting their expressions
    and other conduct.” TEX. BUS. & COM. CODE § 1.303. Because a sequence of events
    19
    is required, a single transaction cannot constitute a course of dealing. See Shell
    Trading (US) Co. v. Lion Oil Trading & Transp., Inc., No. 14-11-00289-CV, 
    2012 WL 3958029
    , at *6, 8 (Tex. App.—Houston [14th Dist.] Sep. 11, 2012, pet. denied)
    (mem. op.).
    ADI further argues that Nabors could not have terminated the Contract for
    cause under Article 11.1.3 because Article 3.1 of the Contract provides that the
    remedy for a failure to timely deliver is “not termination but merely a late delivery
    penalty of no more than 10% of the Contract price.” Without citation to authority,
    ADI asserts that, because the parties “agreed to liquidated damages in the event of
    late delivery, late delivery cannot be a cause for termination.” Again, Article 3.1
    states:
    3.1   [ADI] shall complete the Work as set forth in [Schedule of
    Delivery]. . . . [I]f any of the Equipment is delivered after the
    Penalty Date . . . , then [ADI] shall be liable to [Nabors] for
    liquidated damages in an amount equal to one (1%) of the
    Contract Price for each day that delivery is delayed, provided that
    in no event shall [ADI] be liable to [Nabors] for more than ten
    percent (10%) of the Contract Price.
    Setting aside that ADI seems to posit that it could simply accept a ten percent
    penalty and perpetually delay delivery of any equipment, ADI’s argument overlooks
    that we must analyze Article 3.1 with reference to the whole agreement and give
    effect to all the provisions so that none will be rendered meaningless. See Italian
    Cowboy Partners, 
    Ltd., 341 S.W.3d at 333
    (noting that we examine and consider
    20
    entire writing in effort to harmonize); Frost Nat’l 
    Bank, 165 S.W.3d at 312
    ; see also
    Seagull Energy E&P, 
    Inc., 207 S.W.3d at 345
    (“No single provision taken alone will
    be given controlling effect; rather, all the provisions must be considered with
    reference to the whole instrument.”).
    The language used in Article 3.1 caps the amount of damages for which ADI
    will be liable in the event that Nabors sought recovery on a claim for delay damages,
    i.e., in a claim for consequential damages based on ADI failing to deliver the
    equipment on time. See Valence Operating 
    Co., 164 S.W.3d at 662
    (noting we give
    contract terms their plain, ordinary, and generally accepted meanings). Article 3.1
    does not state that it constitutes the sole remedy in the event of a termination of the
    Contract.
    Rather, as discussed above, Article XI, which governs “Termination of the
    Contract,” has its own damages provisions, i.e., Articles 11.2 and 11.4. And, Article
    XI expressly authorizes Nabors to “terminate” the Contract for “unsatisfactory
    performance” under Article IX, which includes circumstances in which ADI has
    “failed to conduct its operations under this Contract in a diligent, skillful or
    workmanlike manner . . . , or if [ADI] has otherwise breached its obligations
    hereunder.” (Emphasis added.)
    Taking as true all evidence favorable to ADI and indulging every reasonable
    inference in its favor, we conclude that Nabors has conclusively established that it
    21
    terminated the Contract pursuant to Article 11.1.3, “for unsatisfactory performance
    as set forth in Article IX,” based on ADI’s undisputed failure to deliver the Sets as
    agreed.
    We overrule ADI’s first issue.
    2.    Nabors’s Damages
    In its second issue, ADI argues that the trial court erred in granting Nabors’s
    motion for summary judgment as to its damages because ADI established that the
    trial court misconstrued the Contract as authorizing a “reimbursement” or a “refund”
    of the first milestone payment pertaining to each Set.
    We concluded above that Nabors terminated the Contract pursuant to Article
    11.1.3. Article 11.4 expressly provides that if Nabors terminates the Contract
    pursuant to Article 11.1.3, ADI “shall not be entitled to any compensation whatever
    [sic].”
    Nabors’s summary-judgment evidence shows that Pennington, in his
    affidavit, testified that, at the time of Nabors’s termination of the Contract, it had
    paid ADI a total of $3,948,351.40 but had received only 1 of the 5 Sets for which it
    had contracted. Thus, testified Pennington, ADI was entitled to payment for Set 1,
    or $1,927,915.00, less the ten percent penalty under Article 3.1 for its late delivery
    of the equipment, or $197,791.50, for a total of $1,735,123.50. And, subtracting this
    amount from the amount that Nabors paid had ADI, $3,948,351.40, established
    22
    Nabors’s damages in the amount of $2,213,227.90. The trial court’s judgment
    reflects that it awarded Nabors damages in the amount of $2,213,227.90.
    ADI, in its summary-judgment response, asserted that it was entitled to retain
    Nabors’s initial “20% Milestone payments” under Article 2.2 for each of the
    “remaining rigs,” i.e., Sets 2 through 5. Article 2.2 provides for payment of “20%
    of [the] Contract Price within 10 days of execution of [the] Contract by both parties.”
    ADI asserts that this initial 20 percent functioned as a “down payment” or “booking
    fee” on Sets 2 through 5 and that, notwithstanding that they were not delivered,
    neither Article 2.2 nor Article XI provides for any “refund” of milestone payments.
    Again, Article 11.4 expressly provides that if the Contract is terminated
    pursuant to Article 11.1.3, as here, then ADI “shall not be entitled to any
    compensation whatever [sic].”
    We conclude that ADI did not present evidence raising a genuine issue of
    material fact concerning the calculation of Nabors’s damages and that Nabors
    conclusively established its damages. We hold that the trial court did not err in
    granting summary judgment for Nabors on its breach-of-contract claim.
    We overrule ADI’s second issue.
    3.     ADI’s Damages
    In its third issue, ADI argues that the trial court erred in denying its motion
    for summary judgment on its counterclaim because its evidence shows that Nabors
    23
    breached the contract by failing to pay an outstanding balance of $358,186.40 for
    “the unpaid Milestone payments related to Mast 1,” i.e. the mast component of Set
    1. In support, ADI presented the affidavit of its representative, Norris, who testified,
    in pertinent part:
    4.     Under Section 2.2 of the Contract, Nabors was required to pay
    20% of the Contract price of each mast or substructure to ADI
    within 10 days of the execution of the Contract, 25% of the
    Contract price of each mast or substructure to ADI upon receipt
    of all structural steel for each mast or substructure, 45% of the
    Contract price for each mast or substructure to ADI upon
    completion of all work for each mast or substructure, and 10%
    of the Contract price for each mast or substructure to ADI upon
    delivery of each mast or substructure. . . . Nabors has made all
    payments required of it by Section 2.2 of the Contract, except for
    the 45% and 10% payments regarding Mast 1. . . . Nabors owes
    ADI a balance of $358,186.40 for those unpaid Milestones.
    5.     ADI has made not less than two (2) written demands to Nabors
    requesting payment of the $358,186.40 balance due for the
    unpaid Mast 1 Milestones but, as of this date, Nabors has refused
    to pay. . . .
    (Emphasis added.)
    As discussed above, the trial court’s judgment reflects that the trial court
    credited ADI with the full Contract price of Set 1, including both the mast and
    substructure, against the damages that the trial court awarded to Nabors. Thus, the
    record does not support ADI’s issue on appeal. Accordingly, we hold that the trial
    court did not err in denying ADI’s motion for summary judgment.
    We overrule ADI’s third issue.
    24
    Attorney’s Fees
    In its fourth issue, ADI argues that the trial court erred in awarding attorney’s
    fees to Nabors that “(1) exceed what was reasonable and necessary to achieve the
    results obtained; and/or (2) were not reduced sufficiently to segregate Nabors’
    warranty claims.” ADI asserts that, during trial on the limited issue of attorney’s
    fees, its expert, Stephen A. Mendel, testified that the “fee invoices produced by
    Nabors included hours worked that were not necessary to achieve the results that
    Nabors’s counsel obtained” and included discovery that was “irrelevant to the
    outcome of the case.” ADI asserts that a “reasonable fee for the results Nabors’
    counsel achieved would be approximately $45,000.00.” ADI further asserts that,
    although Nabors segregated its fees pertaining to previous warranty claims and
    reduced its fees by “5-10%” for related tasks, “the reduction should have been
    19.4%.”
    In its brief, ADI presents its assertions globally and does not present argument
    or analysis with respect to any specific fees or discovery matters. Further, ADI does
    not present a single citation to legal authority to support its argument under this
    point. As such, we conclude that this issue is inadequately briefed and presents
    nothing for our review. See TEX. R. APP. P. 38.1(i) (“The brief must contain a clear
    and concise argument for the contentions made, with appropriate citations to
    authorities . . . .”); Tesoro Petroleum Corp. v. Nabors Drilling USA, Inc., 106
    
    25 S.W.3d 118
    , 128 (Tex. App.—Houston [1st Dist.] 2002, pet. denied) (concluding
    that “Rule 38 requires [the appellant] to provide us with such discussion of the facts
    and the authorities relied upon as may be requisite to maintain the point at issue” and
    that “[t]his is not done by merely uttering brief conclusory statements, unsupported
    by legal citations,” and holding that appellant waived its complaints “[b]y presenting
    such attenuated, unsupported argument”); see also Strange v. Cont’l Cas. Co., 
    126 S.W.3d 676
    , 678 (Tex. App.—Dallas 2004, pet. denied) (“An issue on appeal
    unsupported by argument or citation to any legal authority presents nothing for the
    court to review.”).
    We hold that ADI has waived its fourth issue.
    Conclusion
    We affirm the trial court’s judgment.
    Sherry Radack
    Chief Justice
    Panel consists of Chief Justice Radack and Justices Kelly and Goodman.
    26