Nextera Energy, Inc. v. Public Utility Commission of Texas ( 2020 )


Menu:
  • Dismissed as Moot and Memorandum Opinion filed March 10, 2020.
    In The
    Fourteenth Court of Appeals
    NO. 14-18-00667-CV
    NEXTERA ENERGY, INC., Appellant
    V.
    PUBLIC UTILITY COMMISSION OF TEXAS, Appellee
    On Appeal from the 201st District Court
    Travis County, Texas
    Trial Court Cause No. D-1-GN-17-003234
    MEMORANDUM OPINION
    This appeal challenges a decision by appellee Public Utility Commission of
    Texas (the “Commission”) denying appellant NextEra Energy, Inc.’s (“NextEra”)
    application for regulatory approval of its proposed acquisition of Oncor Electric
    Delivery Company, LLC (“Oncor”).       For the reasons below, we conclude the
    issues in NextEra’s appeal are moot and do not fall within an exception to the
    mootness doctrine.    We dismiss NextEra’s appeal for lack of subject matter
    jurisdiction.
    BACKGROUND
    In its application, NextEra sought regulatory approval under two statutes in
    the Texas Public Utility Regulatory Act (“PURA”): sections 39.262(m) and
    39.915(b). See Act of June 15, 2007, 80th Leg., R.S., ch. 1186, § 1, 2007 Tex.
    Gen. Laws 4049, 4049 (amended 2017) (current version at Tex. Util. Code Ann.
    § 39.262); Act of June 15, 2007, 80th Leg., R.S., ch. 939, § 25, 2007 Tex. Gen.
    Laws 3241, 3252 (amended 2017) (current version at Tex. Util. Code Ann.
    § 39.915). 1   These sections require the Commission’s approval before certain
    utility sales, transfers, or mergers may be completed.               In relevant part, these
    sections state:
    The commission shall approve a transaction under [these sections] if
    the commission finds that the transaction is in the public interest. In
    making its determination, the commission shall consider whether the
    transaction will adversely affect the reliability of service, availability
    of service, or the cost of service of the electric utility or transmission
    and distribution utility.
    Act of June 15, 2007, 80th Leg., R.S., ch. 1186, § 1, 2007 Tex. Gen. Laws 4049,
    4049 (amended 2017); Act of June 15, 2007, 80th Leg., R.S., ch. 939, § 25, 2007
    Tex. Gen. Laws 3241, 3252 (amended 2017).
    To secure its acquisition of Oncor, NextEra sought the Commission’s
    approval with respect to two separate transactions. In the first transaction, NextEra
    would acquire an 80.03 percent indirect ownership interest in Oncor held by
    Energy Future Holdings Corporation (the “EFH Transaction”).                      Through the
    second transaction, NextEra would acquire a 19.75 percent minority ownership
    interest in Oncor indirectly held by Texas Transmission Holdings Corporation (the
    “TTHC Transaction”).           NextEra’s application stated the EFH and TTHC
    1
    We cite to the versions of these statutes in effect when NextEra filed its application in
    October 2016.
    2
    Transactions had a combined value of approximately $18.7 billion and assumed a
    100 percent ownership interest in Oncor.
    The Commission held an evidentiary hearing on NextEra’s application and
    issued an order denying it.         After NextEra filed a motion for rehearing, the
    Commission issued an “Order on Rehearing” again denying NextEra’s application
    and concluding the EFH and TTHC Transactions were “not in the public interest”
    under PURA sections 39.262(m) and 39.915(b).
    NextEra appealed the Commission’s denial of its application to the Travis
    County District Court. The Commission filed a plea to the jurisdiction asserting
    the issues raised in NextEra’s action were moot because the EFH and TTHC
    Transactions had been terminated.             The trial court held a hearing on the
    Commission’s plea and the parties filed a joint exhibit containing documents
    showing the EFH and TTHC Transactions were terminated.2 At the hearing,
    NextEra did not disagree with the Commission’s contention that its issues were
    moot but asserted that its action could proceed nonetheless under exceptions to the
    mootness doctrine.
    The trial court denied the Commission’s plea to the jurisdiction. The trial
    court signed a final judgment on June 19, 2018 affirming the Commission’s “Order
    on Rehearing.” NextEra timely appealed and its case was transferred to this court
    by Supreme Court of Texas Transfer Order. 3
    2
    Specifically, the EFH and TTHC Transactions’ terminations were discussed in
    NextEra’s 2017 Form 10-Q and Form 8-K filings with the United States Securities and Exchange
    Commission.
    3
    Because of the transfer, we must decide the case in accordance with the precedent of the
    Third Court of Appeals if our decision otherwise would have been inconsistent with that court’s
    precedent. See Tex. R. App. P. 41.3.
    3
    ANALYSIS
    NextEra asserts four issues on appeal:
    1.    The Commission improperly expanded its public interest review under
    PURA sections 39.262(m) and 39.915(b);
    2.    the Commission misapplied the public interest factors in sections
    39.262(m) and 39.915(b);
    3.    the Commission violated NextEra’s due process and equal protection
    rights by applying a new public interest standard; and
    4.    the Commission unlawfully exercised jurisdiction over the TTHC
    transaction.
    The Commission asserts the issues raised in NextEra’s appeal are moot because the
    EFH and TTHC Transactions have been terminated.4 NextEra does not dispute
    that its claims are moot but argues that we should apply either of two exceptions to
    the mootness doctrine: (1) the “capable of repetition, yet evading review”
    exception or (2) the “public interest” exception. Because these arguments go to the
    court’s jurisdiction over NextEra’s appeal, we address them first.
    I.         The Issues Raised in NextEra’s Appeal Do Not Fall Within the
    “Capable of Repetition, Yet Evading Review” Exception.
    The “capable of repetition, yet evading review” exception “applies only in
    rare circumstances.” Williams v. Lara, 
    52 S.W.3d 171
    , 184 (Tex. 2001); accord
    Kingdomware Techs., Inc. v. U.S., 
    136 S. Ct. 1969
    , 1976 (2016) (exception applies
    “only in exceptional situations” (internal quotation omitted)); Coburn v. Moreland,
    
    433 S.W.3d 809
    , 825 (Tex. App.—Austin 2014, no pet.) (same). To invoke the
    exception, a plaintiff must show (1) the challenged action was too short in duration
    to be litigated fully before the action ceased or expired; and (2) a reasonable
    4
    When a case is moot, we lack subject matter jurisdiction to act on the merits. See Tex.
    Quarter Horse Assoc. v. Am. Legion Dep’t of Tex., 
    496 S.W.3d 175
    , 180-81 (Tex. App.—Austin
    2016, no pet.).
    4
    expectation exists that the same complaining party will be subjected to the same
    action again. 
    Coburn, 433 S.W.3d at 825
    (citing 
    Williams, 52 S.W.3d at 184
    ).
    For the “too short in duration” prong, we inquire whether the challenged
    activity is by its very nature so short in duration that it cannot be adjudicated while
    live. Tex. A&M Univ.-Kingsville v. Yarbrough, 
    347 S.W.3d 289
    , 291 (Tex. 2011);
    see also Gates v. Tex. Dep’t of Family & Protective Servs., No. 03-15-00631-CV,
    
    2016 WL 3521888
    , at *6 (Tex. App.—Austin June 23, 2016, pet. denied) (mem.
    op.). “The plaintiff must show that the time between the challenged action and its
    expiration is always so short as to evade review.” 
    Coburn, 433 S.W.3d at 825
    ;
    accord Spencer v. Kemna, 
    523 U.S. 1
    , 18 (1998).
    Plaintiffs satisfying this prong of the exception have shown the challenged
    activity or action endures only for a definite, limited period of time. See, e.g.,
    Kingdomware Techs., 
    Inc., 136 S. Ct. at 1974-76
    ; Mr. W. Fireworks, Inc. v. Comal
    Cty., No. 03-06-00638-CV, 
    2010 WL 1253931
    , at *5 (Tex. App.—Austin Mar. 31,
    2010, no pet.) (mem. op.); Ben Robinson Co. v. Tex. Workers’ Comp. Comm’n,
    
    934 S.W.2d 149
    , 152-53 (Tex. App.—Austin 1996, writ denied). In Kingdomware
    Technologies, Inc., the plaintiff challenged a decision by the Department of
    Veteran Affairs awarding a federal contract to a non-veteran-owned 
    company. 136 S. Ct. at 1975
    . The federal contract at issue was for a one-year period with an
    option to extend the agreement for two additional years — the Department
    exercised the option once and the contract was fully performed in two years. 
    Id. at 1975-76.
    Concluding the plaintiff’s action fell within the “capable of repetition,
    yet evading review” exception, the Supreme Court held the exception “applies to
    these short-term contracts” and stated that “a period of two years is too short to
    complete judicial review of the lawfulness of the procurement.” 
    Id. at 1976.
    The Third Court of Appeals also has limited the “capable of repetition, yet
    5
    evading review” exception to claims that challenge finite actions or conduct. In
    Mr. W. Fireworks, Inc., the plaintiff challenged a fireworks ban issued by Comal
    County. 
    2010 WL 1253931
    , at *2-3. Concluding this action satisfied the “too
    short in duration” prong, the court noted the New Year’s fireworks season ended
    on January 1st and the ban had been issued two days before on December 30th. 
    Id. at *5.
    The court held that, “[b]ecause the period of time between the execution of
    the ban and the end of fireworks season was so brief, it was impossible for Mr. W.
    to fully litigate the matter before the controversy became moot.” 
    Id. Likewise, in
    Ben Robinson Co., the plaintiff’s action challenging an extra-hazardous employer
    designation that required the implementation of an accident prevention plan in
    seven-to-ten months was considered “too short in duration” to be adjudicated while
    
    live. 934 S.W.2d at 152-53
    .
    But a claim does not fit within the “capable of repetition, yet evading
    review” exception if there is “nothing inherently short” about the action it
    challenges. Amarillo v. R.R. Comm’n of Tex., 
    511 S.W.3d 787
    , 795 (Tex. App.—
    El Paso 2016, no pet.). In Amarillo, the cities of Amarillo and Lubbock challenged
    the Railroad Commission’s decision regarding 2012 gas utility rates. 
    Id. at 792.
    But the cities approved a new set of utility rates in 2014, rendering their appeal
    moot. See 
    id. at 794-95.
    This approval, the court concluded, also prevented the
    cities’ attempted invocation of the “capable of repetition, yet evading review”
    exception. 
    Id. at 795.
    Pointing out that the Commission’s rate decision could have
    been adjudicated “[b]ut for” the cities’ approval of the new rates, the court
    concluded that “there was nothing inherently short about the time period that
    precluded judicial review.” 
    Id. at 795;
    see also Entergy Servs., Inc. v. Fed. Energy
    Regulatory Comm’n, 
    391 F.3d 1240
    , 1245-46 (D.C. Cir. 2004) (plaintiffs’
    contractual challenges were moot where contracts at issue had been cancelled;
    6
    action did not fall into exception to mootness doctrine because the plaintiffs
    “themselves chose to abandon the undertakings that gave rise to the controversy”).
    Here, NextEra’s issues on appeal challenging the Commission’s
    determination regarding the EFH and TTHC Transactions do not fall within the
    “capable of repetition, yet evading review” exception to the mootness doctrine.
    Having failed to satisfy the exception’s first prong, NextEra has not shown that the
    challenged action — namely, the Commission’s decision denying NextEra’s
    application for approval — is by its very nature so short in duration that it evades
    judicial review. See Tex. A&M 
    Univ.-Kingsville, 347 S.W.3d at 291
    ; see also
    Gates, 
    2016 WL 3521888
    , at *6.
    With respect to this prong, NextEra argues “[t]he duration of electric utility
    transactions of the type here does not allow for issues on appeal to be resolved
    before the transactions are terminated.” NextEra supports this assertion with the
    affidavit of Mark Hickson, its executive vice president of corporate development,
    strategy, quality, and integration. In the affidavit, Hickson states, in relevant part:
    3.     It is my experience that the exigent nature of transactions
    involving electrical utilities is dictated by changing market
    conditions, such as changes in interest rates, credit rating
    agency reports, and other market sensitive data that changes
    daily. This is due to the fact that these types of transactions
    require financing instruments involving hundreds or millions or
    even billions of dollars.
    4.     It is also my experience that electric utility transactions are
    expensive and dependent on the variant interests of numerous
    parties and stakeholders including the buyer and seller, electric
    customers, financing entities and their related interests, and
    other interested buyers. These factors, in turn, dictate the
    timing under which transactions must be completed.
    To the extent the transactions at issue are the proper focus of the “too short in
    duration” prong, Hickson’s affidavit does not show electric utility transactions of
    7
    this type are always of limited duration. At most, Hickson’s affidavit states these
    types of transactions are pressing, demanding, and dependent on the convergence
    of multiple variables. But this showing is not what the applicable standard requires
    — instead, the plaintiff “must show that the time between the challenged action
    and its expiration is always so short as to evade review.” 
    Coburn, 433 S.W.3d at 825
    (emphasis added); accord 
    Spencer, 523 U.S. at 18
    . Hickson’s affidavit does
    not make this showing.
    Moreover, the transactions at issue did not expire or terminate after a set
    amount of time had elapsed — rather, the terminations were effected by the parties
    to the agreements.5 But for these actions, the EFH and TTHC Transactions would
    not have been terminated and NextEra’s issues on appeal would not be moot.
    Accord 
    Amarillo, 511 S.W.3d at 794-95
    .              The role of these elective actions
    counsels against the conclusion that transactions of this type are always so short as
    to evade review. See Entergy Servs., 
    Inc., 391 F.3d at 1245-46
    . Furthermore, the
    issues NextEra raises on appeal nonetheless could be subject to judicial review
    even if the transactions had been approved and closed.               See, e.g., Pub. Util.
    Comm’n of Tex. v. Cities of Harlingen, 
    311 S.W.3d 610
    , 615 (Tex. App.—Austin
    2010, no pet.) (the Commission approved entity’s application for regulatory
    approval of certain transactions, transfers, and rates; intervening parties appealed
    the Commission’s decision and asserted issues challenging the Commission’s
    statutory interpretations, provision of due process, and findings).
    NextEra’s issues on appeal challenging the Commission’s review of the
    EFH and TTHC Transactions therefore do not fall within the “capable of
    5
    In its June 30, 2017 Form 10-Q filing, NextEra stated the EFH Transaction was
    terminated after EFH “provided written notice . . . terminating the agreement and plan of
    merger.” In its October 31, 2017 Form 8-K filing, NextEra stated that “TTHC had by delivery of
    the notice terminated the agreement and plan of merger.”
    8
    repetition, yet evading review” exception to the mootness doctrine.
    II.     The Issues Raised in NextEra’s Appeal Do Not Fall Within the “Public
    Interest” Exception.
    The “public interest” exception to the mootness doctrine “allows appellate
    review of a question of considerable public importance if that question is capable
    of repetition between either the same parties or other members of the public but for
    some reason evades appellate review.” Univ. Interscholastic League v. Buchanan,
    
    848 S.W.2d 298
    , 303 (Tex. App.—Austin 1993, no writ). The Supreme Court of
    Texas has not addressed the viability of this exception. See Fed. Deposit Ins.
    Corp. v. Nueces Cty., 
    886 S.W.2d 766
    , 767 (Tex. 1994); see also A.I. Divestitures,
    Inc. v. Tex. Comm’n on Envtl. Quality, No. 03-15-00814-CV, 
    2016 WL 3136850
    ,
    at *5 n.5 (Tex. App.—Austin June 2, 2016, no pet.) (mem. op.).
    Like the “capable of repetition, yet evading review” exception, the “public
    interest” exception requires that the complained-of action be capable of repetition
    yet not effectively reviewable. Fed. Deposit Ins. 
    Corp., 886 S.W.2d at 767
    ; see
    also Meeker v. Tarrant Cty. Coll. Dist., 
    317 S.W.3d 754
    , 761-62 (Tex. App.—Fort
    Worth 2010, pet. denied) (discussing the exceptions’ “common element”). In our
    analysis of the “capable of repetition, yet evading review” exception, we concluded
    that NextEra could not make this showing because it did not demonstrate that the
    Commission’s decision is by its nature always so short in duration that it evades
    judicial review. Presuming the viability of the “public interest” exception, this
    conclusion also would foreclose NextEra’s prevailing under this exception to the
    mootness doctrine. See Fed. Deposit Ins. 
    Corp., 886 S.W.2d at 767
    ; 
    Meeker, 317 S.W.3d at 761-62
    .
    CONCLUSION
    We conclude NextEra’s issues on appeal do not invoke an exception to the
    9
    mootness doctrine and so dismiss NextEra’s suit for lack of subject matter
    jurisdiction.
    /s/    Meagan Hassan
    Justice
    Panel consists of Chief Justice Frost and Justices Wise and Hassan.
    10