Summit Global Contractors, Inc. v. Enbridge Energy, Limited Partnership and Enbridge Gathering (North Texas) L.P. ( 2019 )


Menu:
  • Affirmed and Majority and Concurring Opinions filed December 10, 2019.
    In The
    Fourteenth Court of Appeals
    NO. 14-18-00052-CV
    SUMMIT GLOBAL CONTRACTORS, INC., Appellant
    V.
    ENBRIDGE ENERGY, LIMITED PARTNERSHIP AND ENBRIDGE
    GATHERING (NORTH TEXAS) L.P., Appellees
    On Appeal from the 215th District Court
    Harris County, Texas
    Trial Court Cause No. 2013-69313
    MAJORITY OPINION
    This appeal involves two agreements for the fabrication of pipes called
    “spools” used in the oil and gas industry. Summit Global Contractors, Inc., brought
    breach of contract and quantum meruit claims against Enbridge Energy, Limited
    Partnership (Enbridge Energy) and Enbridge Gathering (North Texas) L.P.
    (Enbridge Gathering). After a bench trial, the trial court found that the Enbridge
    parties did not breach the contracts and concluded that Summit’s quantum meruit
    claim was precluded by the express contracts. Summit challenges the sufficiency
    of the evidence in support of the trial court’s findings and challenges the trial
    court’s conclusion regarding the quantum meruit claim. We affirm.
    Background
    The Enbridge parties began construction of a natural gas processing plant in
    Wheeler, Texas. International Alliance Group (IAG) was hired to solicit bids for
    the project. IAG in turn placed Summit on its potential vendor list. IAG sent
    Summit a “Pipe Fabrication Inquiry Requisition” form requesting a bid for “pipe
    spool fabrication.” The scope of work was to include “all labor, material
    (exclud[ing] items furnished by customer), small tools, consumables, storage,
    overheads, etc.” The requisition form also required the fabricator to “quote Lump
    Sum.”
    Summit offered an initial “Lump Sum proposal” including overtime but also
    specifying that “[a]ny down time will be handled on a Time and Material basis.”
    “Extra Work” was to be billed for materials at cost plus 15% and labor at $85 per
    hour. Summit’s owner, Rich Miller, testified that “lump sum” means a “fixed
    price” for everything in the scope of the contract, which includes some overtime.
    “Time and material” pricing, on the other hand, is based on the time expended and
    the materials used for the job. Miller also specified that payment terms would be
    “NET 30” from invoice date, meaning payment was due within 30 days of
    invoicing. The first bid included a price quote from a pipe supplier called
    Wolseley.
    Summit was awarded the job, and a purchase order was issued that
    incorporated Summit’s bid terms and called for a 20% advanced payment.
    Enbridge Energy was identified as the party to be billed. Enbridge was also
    2
    required to provide valves for Summit to use in the spool fabrication.1 The
    purchase order stated, “PRICE(S) ARE FIRM” and “PRICING AND
    AVAILABILITY CONFIRMED WITH Rich Miller.”
    By the time Summit was awarded the job, however, Wolseley’s price
    quote—upon which Summit’s bid was based—had expired. Two days after the
    purchase order was issued, Summit issued a $10,847.54 change order request
    based on an increase in Wolseley’s price. Approximately two weeks later, Summit
    submitted another change order request for a materials price increase from
    Wolseley of $87,113.10, which included the amount of the prior request for
    $10,847.54.
    IAG’s representative contacted a representative from Wolseley regarding the
    price increase. The Wolseley representative informed the IAG representative that
    Wolseley’s price quote included in Summit’s bid package had been valid for only
    15 days and Wolseley received the order past its quote validity date. Following
    negotiations, Wolseley agreed to decrease its increased price from $87,113.10 to
    $44,365.53. The purchase order was revised to reflect the $44,365.53 price
    increase. The record does not reflect which Enbridge entity paid that price
    increase, but it was paid.
    Summit submitted its second “Lump Sum proposal” on June 12, 2012 “to
    provide labor, material, equipment & delivery necessary to fabricate Pipe Stools.”
    Payment terms, again, were to be “NET 30 from invoice date,” and “[a]ny down
    time [would] be handled on a Time and Material basis.” The proposal included
    overtime. A second purchase order was issued, again with Enbridge Energy
    identified as the party to be billed. That purchase order incorporated Summit’s
    1
    The purchase order does not specify which Enbridge party was required to provide the
    valves.
    3
    terms and again required a 20% advanced payment. The second purchase order
    was issued on June 22, 2012. Summit submitted an invoice for the advanced
    payment on the same day. That invoice was paid on July 13, 2012.
    Summit met its first deadline for delivering spools. Summit then fell behind
    on meeting its remaining delivery deadlines, which were extended. According to
    Summit, one or both Enbridge parties caused the late deliveries due to delays in
    making the second advanced payment, negotiating the price decrease with
    Wolseley, and delivering the valves. Summit contends that it incurred expenses for
    unexpected overtime and other overhead due to the delays. Summit submitted
    change order requests after the job was completed totaling $390,088.95 for the
    purported delays. Representatives from Summit, the Enbridge parties, and IAG met
    to discuss the change order requests. The Enbridge parties and IAG concluded the
    requested change orders were not justifiable.
    Summit filed an affidavit of lien against Enbridge Energy for $390,088.95
    and filed this lawsuit, bringing claims, in relevant part, for breach of contract,
    quantum meruit, and promissory estoppel. In its petition, Summit alleged that both
    Enbridge Energy and Enbridge Gathering were parties to the relevant purchase
    orders. Referring to the Enbridge parties collectively as “Enbridge,” Summit
    alleged that Enbridge breached the contracts. Summit also asserted quantum meruit
    and other alternative liability claims against both Enbridge parties.
    The Enbridge parties answered and filed counterclaims in which they also
    referred to themselves collectively as “Enbridge.” Although both purchase orders
    identify Enbridge Energy as the party to be billed, the Enbridge parties did not
    dispute that both defendants were bound by the purchase orders.2
    2
    The purchase orders specified that bills would be sent to Enbridge Energy and identified
    the “Purchaser” as “the Enbridge entity identified on the face of the Order.” The letterhead on
    4
    After a bench trial, the trial court found that (1) as to the first purchase order,
    it incorporated Summit’s bid terms for a lump sum contract; the payment terms
    were net 30, and the prices were firm; despite this, the price for materials in
    Summit’s bid had increased; and Summit made its first delivery on time but made
    subsequent deliveries late; (2) as to the second purchase order, it incorporated
    Summit’s bid terms for a lump sum contract; (3) “Enbridge” paid Summit the
    entire amount due under both purchase orders plus “over $30,000 that resulted
    from drawing changes, material price increases, and the like”; and (4) Summit’s
    change order requests totaling $390,088.95 were “untimely and unsupported.” The
    trial court concluded that (1) the purchase orders were valid and enforceable
    “lump-sum bid contracts”; (2) “Enbridge” did not breach the contracts; (3) Summit
    is not entitled to recover damages for breach of contract or attorney’s fees; and
    (4) Summit’s quasi contract and promissory estoppel claims are precluded by
    express contract. The trial court referred to both Enbridge parties collectively as
    “Enbridge” in its findings and conclusions, as did the parties in their proposed
    findings and conclusions. The court signed a take nothing judgment in favor of the
    Enbridge parties.
    Discussion
    In four issues, Summit challenges the legal sufficiency of the evidence in
    support of the trial court’s findings and rulings on Summit’s breach of contract and
    quantum meruit claims. We conclude that Summit has not established as a matter
    of law that either Enbridge party breached the purchase orders. We further
    conclude that Summit’s quantum meruit claim is precluded by express contract.
    the purchase orders identified the entity only as “Enbridge.” The purchase orders also state,
    “Enbridge terms and conditions apply.” Enbridge Gathering is not identified on either purchase
    order as a party.
    5
    We review a legal sufficiency challenge to court findings using the same
    standards applied in reviewing the evidence supporting jury findings.3 Catalina v.
    Blasdel, 
    881 S.W.2d 295
    , 297 (Tex. 1994). We review the evidence in the light
    most favorable to the challenged findings and indulge every reasonable inference
    that would support them. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 822 (Tex.
    2005). We credit favorable evidence if a reasonable factfinder could and disregard
    contrary evidence unless a reasonable factfinder could not. 
    Id. at 827.
    We sustain a legal sufficiency or “no evidence” challenge only when (1) the
    record discloses a complete absence of evidence of a vital fact; (2) the court is
    barred by rules of law or of evidence from giving weight to the only evidence
    offered to prove a vital fact; (3) the evidence offered to prove a vital fact is no
    more than a mere scintilla; or (4) the evidence establishes conclusively the
    opposite of the vital fact. Marathon Corp. v. Pitzner, 
    106 S.W.3d 724
    , 727 (Tex.
    2003); Vast Constr., LLC v. CTC Contractors, LLC, 
    526 S.W.3d 709
    , 719 (Tex.
    App.—Houston [14th Dist.] 2017, no pet.). A party attacking the legal sufficiency
    of an adverse finding on an issue on which it had the burden of proof must show
    that the evidence conclusively establishes all vital facts in support of the issue.
    Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001).
    We apply these standards mindful that the factfinder is the sole judge of the
    credibility of the witnesses and the weight to be given to their testimony. See City
    of 
    Keller, 168 S.W.3d at 819
    , 822; 2900 Smith, Ltd. v. Constellation NewEnergy,
    Inc., 
    301 S.W.3d 741
    , 745 (Tex. App.—Houston [14th Dist.] 2009, no pet.). When,
    as here, there is a complete reporter’s record of the trial, the trial court’s findings of
    3
    We may review a trial court’s findings for both legal and factual sufficiency, see
    Catalina v. Blasdel, 
    881 S.W.2d 295
    , 297 (Tex. 1994), but Summit cites the standards of review
    only for legal sufficiency and analyzes the case under those standards, so we limit our analysis to
    a legal sufficiency review.
    6
    fact will not be disturbed on appeal if there is any evidence of probative force to
    support them. See Barrientos v. Nava, 
    94 S.W.3d 270
    , 288 (Tex. App.—Houston
    [14th Dist.] 2002, no pet.).
    In an appeal from a bench trial, we review a trial court’s conclusions of law
    de novo and will uphold them if the judgment can be sustained on any legal theory
    supported by the evidence. BMC Software Belgium, N.V. v. Marchand, 
    83 S.W.3d 789
    , 794 (Tex. 2002); Stavinoha v. Stavinoha, 
    126 S.W.3d 604
    , 608 (Tex. App.—
    Houston [14th Dist.] 2004, no pet.). We review the legal conclusions drawn from
    the facts to determine their correctness. BMC 
    Software, 83 S.W.3d at 794
    ;
    
    Stavinoha, 126 S.W.3d at 608
    . Incorrect conclusions of law do not require reversal
    if the controlling findings of fact support the judgment under a correct legal theory.
    BMC 
    Software, 83 S.W.3d at 794
    ; 
    Stavinoha, 126 S.W.3d at 608
    .
    A trial court should make additional findings of fact only if they have some
    legal significance to an ultimate issue in the case. Stuckey Diamonds, Inc. v. Harris
    Cty. Appraisal Dist., 
    93 S.W.3d 212
    , 213 (Tex. App.—Houston [14th Dist.] 2002,
    no pet.); Vickery v. Comm’n for Lawyer Discipline, 
    5 S.W.3d 241
    , 255 (Tex.
    App.—Houston [14th Dist.] 1999, pet. denied). Summit asserts that because it
    requested additional findings of fact, we cannot presume the trial court relied upon
    proper legal principles or factual findings to support the challenged findings or
    conclusions. That is incorrect because Summit requested additional findings that
    are inconsistent with the trial court’s judgment. This court noted long ago that
    “[t]he primary purpose for findings of fact is to assist the losing party in narrowing
    his issues on appeal by ascertaining the true basis for the trial court’s decision.”
    
    Vickery, 5 S.W.3d at 255
    . When a party requests findings contrary to the judgment,
    as Summit did, the court’s failure to make such findings is consistent with its
    judgment. See 
    Vickery, 5 S.W.3d at 256
    . The presumption of validity is not
    7
    rebutted by the court’s failure to make findings contrary to its judgment. 
    Id. With these
    standards in mind, we turn to Summit’s issues presented on appeal.
    I.     Summit did not conclusively establish that it suffered damages
    because of Enbridge Energy’s purported delays.
    In three issues, Summit contends that Enbridge Energy’s purported delays in
    making advanced payments, negotiating with Wolseley, and providing valves
    constituted breach of the purchase order agreements and Summit incurred damages
    because of Enbridge Energy’s delays.4 We conclude that Summit has not shown as
    a matter of law that it suffered damages because of any delay by Enbridge Energy.5
    A. Contract Interpretation Principles
    Summit’s argument is based in part on its interpretation of the parties’
    agreements. Thus, we refer to the general principles concerning contract
    interpretation. See Port of Houston Auth. of Harris Cty. v. Zachry Constr. Corp.,
    
    513 S.W.3d 543
    , 551 (Tex. App.—Houston [14th Dist.] 2016, pet. denied).
    In construing a contract, we look to the language of the parties’ agreement.
    Barrow-Shaver Res. Co. v. Carrizo Oil & Gas, Inc., No. 17-0332, 
    2019 WL 2668317
    , at *5 (Tex. June 28, 2019). We construe contracts de novo. 
    Id. We give
    effect to the parties’ agreement as expressed in the instrument. 
    Id. We give
    the
    contract its plain, grammatical meaning unless it “would clearly defeat the parties’
    intentions.” 
    Id. If we
    determine that the contract’s language is unambiguous—in
    other words, it can be given a certain or definite legal meaning or interpretation—
    we construe it as a matter of law. 
    Id. 4 In
    its appellate briefing, Summit refers to Enbridge Energy as “Enbridge” and Enbridge
    Gathering as “Enbridge Gathering.”
    5
    Summit also argues that the trial court erred in failing to award Summit attorney’s fees.
    Because of our holding, we need not reach this issue.
    8
    Both parties contend that the agreements are unambiguous, but they disagree
    on the interpretation. Summit argues that Enbridge Energy was required to make
    20% advanced payments at the time the purchase orders were issued. The Enbridge
    parties argue these payments instead were due within 30 days after invoicing.6
    Summit also argues that it incurred overhead for work outside the scope of the
    agreements caused by Enbridge Energy’s delays. The Enbridge parties argue that
    any overhead incurred by Summit was included in the parties’ “lump sum”
    agreements.
    Summit asserts that we can look outside the four corners of the parties’
    agreements to interpret the parties’ intentions. The supreme court recently
    reiterated that our primary duty in construing an unambiguous contract is to
    ascertain the intent of the parties from the language within the four corners of the
    instrument. U.S. Shale Energy II, LLC v. Laborde Props., L.P., 
    551 S.W.3d 148
    ,
    151 (Tex. 2018). However, we consider the words used “in light of the facts and
    circumstances” surrounding the execution of the agreement. 
    Id. We may
    consider
    these circumstances only when they inform but not when they contradict the
    instrument. 
    Id. Summit further
    contends that we can look to the bid proposals to support our
    interpretation of the purchase orders. We agree that we can consider the bid
    proposals because they are part of the parties’ agreements. Texas’s version of the
    Uniform Commercial Code applies to the sale of goods. See Tex. Bus. & Com.
    Code § 2.102. When a contract contains a mix of sales and services, the UCC
    applies if the sale of goods is the “dominant factor” or “essence” of the transaction.
    Cont’l Casing Corp. v. Siderca Corp., 
    38 S.W.3d 782
    , 787 (Tex. App.—Houston
    6
    On appeal, the Enbridge parties again refer to themselves collectively as “Enbridge.”
    Summit challenges only the trial court’s contractual breach findings as to Enbridge Energy.
    9
    [14th Dist.] 2001, no pet.). The spools are without question goods as defined by the
    UCC. Tex. Bus. & Com. Code § 2.105. The UCC states that a “contract to sell”
    applies to not only a present sale of goods but also an agreement to sell goods at a
    future time. 
    Id. § 2.106(a)-(b).
    The purchase orders contemplate the sale of “Goods, and the services related
    thereto.” Although Summit agreed to fabricate the spools, Enbridge ultimately
    contracted for a finished product. We conclude that the future sale of spools to
    Enbridge was the dominant factor of the transaction. See Cont’l Casing 
    Corp., 38 S.W.3d at 787-88
    . Accordingly, the UCC applies. See 
    id. Under the
    UCC, a contract is formed for the sale of goods by an offer and
    acceptance. Section 2.106 provides, in pertinent part: “Unless otherwise
    unambiguously indicated by the language or circumstances[,] an offer to make a
    contract shall be construed as inviting acceptance in any manner and by any
    medium reasonable in the circumstances.” Tex. Bus. & Com. Code § 2.206(a).
    Under section 2.207, additional terms in the acceptance of the offer are
    incorporated into the contract under most circumstances.7 
    Id. § 2.207(b).
    The parties agree that the purchase orders incorporated Summit’s bid terms.
    We conclude that Summit’s bid proposals are offers and the purchase orders are
    acceptances under the UCC. They together form the parties’ agreements, and we
    may consider them both in our interpretation of the agreements. See Peterson v.
    NCNB Tex. Nat’l Bank, 
    862 S.W.2d 182
    , 183 (Tex. App.—Eastland 1993, writ
    denied) (noting a bid is an offer and a binding contract consists of an offer and
    acceptance).
    7
    Additional terms do not become part of the contract when “(1) the offer expressly limits
    acceptance to the terms of the offer; (2) they materially alter it; or (3) notification of objection to
    them has already been given or is given within a reasonable time after notice of them is
    received.” Tex. Bus. & Com. Code § 2.207(b). These exceptions do not apply here.
    10
    B. Breach of Contract Claims
    We turn to Summit’s arguments regarding Enbridge Energy’s purported
    breach of contract. A contractor is entitled to recover damages from an owner for
    losses due to a breach of contract based on delay and hindrance of the contractor’s
    work only if the contractor proves (1) that its work was delayed or hindered,
    (2) that it suffered damages because of the delay or hindrance, and (3) that the
    owner was responsible for the act or omission that caused the delay or hindrance.
    Zachry Constr. 
    Corp., 513 S.W.3d at 560
    .
    Advanced Payments. Summit argues that the delay in making the second
    advanced payment resulted in damages to Summit. The Enbridge parties contend
    that they were not required to make the payment until within 30 days after
    invoicing by Summit. Summit’s bid proposals and the purchase orders both specify
    that the payment terms were “net 30.” In other words, under the purchase orders,
    invoices were to be paid “within thirty . . . days of receipt.” However, the purchase
    orders also required a “20% advanced payment.” The “net 30” requirement reflects
    the general rule requiring payment of all invoices within thirty days. However, the
    requirement of a 20% advanced payment suggests an exception to this rule.
    Applying the plain, grammatical meaning of the adjective “advance,” we
    note that it means “ahead of time or beforehand.” The American Heritage
    Dictionary 81 (2d col. ed. 1991). We conclude “advanced” in the context of this
    sentence means what it says: the payment was due “ahead of time or beforehand,”
    in other words, before the work started. Our holding is consistent with long-
    established precedent: no phrase, sentence, or section of a contract should be read
    in isolation and considered apart from the other provisions, and a specific contract
    provision controls over a general one. See Pathfinder Oil & Gas, Inc. v. Great W.
    Drilling, Ltd., 
    574 S.W.3d 882
    , 889 (Tex. 2019). We conclude that Enbridge
    11
    Energy generally was required under the parties’ agreements to make payments
    within 30 days of invoicing. However, Enbridge Energy was also required to make
    a 20% advanced payment at the outset of each agreement.
    Summit submitted a change order request for $41,920 representing 640 work
    hours. Summit contends it had to extend its “overhead, equipment and facilities . . .
    an additional four weeks” because the second advanced payment was not made on
    time. But Summit does not point to any evidence in the record establishing that it
    suffered damages from this delay.
    The second advanced payment was made on the date of Summit’s first
    delivery deadline—July 13, 2012. Although Summit made that delivery on time, it
    contends the late payment nevertheless caused delays in production. Summit
    presented expert testimony that the purpose of an advanced payment is for the
    vendor to be able to buy equipment and materials for a project. Summit’s expert
    testified that the payment should have been made at the outset of the parties’
    agreement. Despite this testimony, Summit presented no evidence linking this late
    payment to the purported “additional four weeks” needed to complete the project.
    Negotiation with Supplier, Delivery of Valves. Summit also submitted
    change orders totaling $348,168.95 representing expenses Summit allegedly
    incurred due to the Enbridge parties’ purported delays in negotiating with
    Wolseley and delivering valves late.8
    Two days after the first purchase order was issued, Summit issued a
    $10,847.54 change order request based on an increase in Wolseley’s materials
    price. Nearly two weeks after the first purchase order was issued, Summit
    submitted another change order request for a materials price increase from
    8
    As discussed, Summit argued below that the delays were caused by both Enbridge
    parties and not just Enbridge Energy.
    12
    Wolseley of $87,113.10, which included the prior change order request amount of
    $10,847.54. Summit complains on appeal that Enbridge Energy negotiated with
    Wolseley between May 24 and June 7, 2012 to reduce the increased price from
    $87,113.10 to $44,365.22, which was paid. Summit contends, however, that its
    ability to perform was impaired because Summit “remained nearly idle” during the
    negotiations.
    Summit points to no evidence in the record showing it incurred any expenses
    as a result of the negotiations with Wolseley. In fact, Summit’s own expert testified
    that the Enbridge parties were “totally divorced from” the delay because it was
    caused by Summit’s failure to honor the fixed price for the materials it originally
    had quoted. Moreover, the Enbridge parties presented evidence that Wolseley
    shipped the materials on schedule, so there is evidence from which the trial court
    could infer the negotiations did not cause any damages to Summit.9
    Summit also contends that Enbridge Energy delivered valves late, resulting
    in additional costs borne by Summit outside the scope of the parties’ agreements.
    Whether most of the valves were delivered late resulting in damages to Summit
    was hotly contested at trial.10
    Summit submitted a change order request for the first phase of the project
    for $118,949 in “manhours” with regard to 81 spools that purportedly “were
    handled multiple times during the process of waiting for the valves to show up.”
    Summit began fabricating the spools in May 2012, and the Enbridge parties began
    9
    This evidence is in a letter from a Wolseley representative admitted at trial, stating:
    “[Our supplier] was able to reduce the prices and deliver most of the items, for the first release in
    time. Whatever they could not deliver or reduce the prices on, we supplied those items from our
    stocks.”
    10
    The Enbridge parties presented evidence that many of the valves were delivered well in
    advance of the time the spools had to be ready.
    13
    shipping valves to Summit the same month. Summit asserted that it had fabricated
    certain spools, but then had to wait on the valves, causing Summit to pay for
    1,399.4 extra “manhours.” Summit used an estimating program to arrive at that
    number of hours but did not keep records of the actual number of extra hours
    purportedly paid. The first phase of the project called for 195 fabricated spools to
    be delivered by July 13, 2012. By June 20, 2012, Summit had received all the
    valves required for the first phase. The first spool delivery was on time.
    Six weeks into the project, Earl Carpenter, a representative from IAG, was at
    the Summit facility managing the materials most of the time. He testified that the
    shop was never at a standstill awaiting delivery of valves to finish fabrication.
    Summit likewise never reported to IAG that there was a hold on fabrication due to
    the absence of valves. Another representative from IAG, Kenneth Neumann,
    testified that if Summit had reported the valves were not there on time, they would
    have been shipped out.
    At one point, Summit notified Carpenter that “a couple . . . valves which
    [Summit] should have had in their possession” were missing. Carpenter told
    Summit that the valves had been shipped to Summit. The clear implication was
    that Summit somehow misplaced the valves, but Carpenter asked Summit to “go
    ahead and ship the spools without the valves installed.” Carpenter told Neumann
    via email that a change order had been justified for Summit “to re-handle 81
    spools” to add valves. He noted, however, that the amount of the requested change
    order was based on Summit’s estimating program. Carpenter later testified that
    IAG agreed the late shipment of valves “would generate a certain amount of a . . .
    valid change order,” but he said IAG approved a lesser amount, “like 40 something
    thousand dollars.”
    Another IAG representative conceded in deposition testimony admitted at
    14
    trial that “at least in some way . . . the cost to Summit increased” because the
    valves were not timely delivered. On cross-examination during trial, he testified
    that “the valves were not late,” but he then agreed with Summit’s counsel that not
    all of the valves were “available as needed.” He also admitted that double handling
    the spools could increase costs.
    A representative of the Enbridge parties conceded at trial that there were
    valve delays, but he did not agree that the delays “impacted Summit’s ability to
    efficiently produce spools.” He stated that the dispute between the parties was over
    the amount of the $118,949 change order. When asked whether missing parts can
    disrupt a fabricator’s assembly line process, he responded, “It can.” He ultimately
    stated, “My belief is . . . that there were costs on both sides—costs to Enbridge and
    costs to Summit. How it nets out, I truly do not know. That is the additional
    documentation that I was looking for [from Summit.]” He said after meeting with
    Summit, “it was determined that we did not see any evidence that we owed
    additional money to Summit.” The trial court, as the factfinder, was entitled to
    weigh this conflicting testimony regarding whether the valves were late and
    whether late delivery of the valves resulted in additional expenses to Summit. See
    City of 
    Keller, 168 S.W.3d at 819
    .
    While Summit used an estimating program to arrive at the 1,399.4 hours
    purportedly expended handling the spools multiple times, the Enbridge parties,
    using the same estimating program, presented evidence that such work, if needed,
    would amount to only 96 hours for a total of $3,300. But the Enbridge parties did
    not concede that they owed Summit even this lesser amount.
    Summit submitted three more change orders for more expenses allegedly
    incurred based on purported delays. These change orders were based on delays
    purportedly caused by the negotiations with Wolseley and “late delivery of
    15
    valves,” resulting in “extra manhours,” a 15% loss of productivity, and overtime
    incurred by Summit’s vendor in testing the spools. The first of these requested
    change orders references the Wolseley negotiation and purported late delivery of
    valves and requests a total of $82,846.37. The second requested change order
    merely states that the vendor “was also required to work overtime.” The final of
    these requested change orders states that the delays “created a loss of 33 scheduled
    work days.”
    Summit points to evidence that the valves arrived on a rolling basis and not
    all at the outset of the project, but the Enbridge parties presented evidence that they
    were not required to deliver the valves all at once because the spools were being
    fabricated on a rolling basis. The fact that the valves were delivered periodically
    during the fabrication process does not conclusively demonstrate that Summit was
    damaged. The Enbridge parties, moreover, accepted Summit’s late delivery of
    spools after the project deadlines had passed, so the trial court could infer that
    Summit did not suffer damages by delivering the spools late.
    Summit’s expert testified that the delays prevented Summit from taking on
    other projects. The Enbridge parties’ counsel argued this testimony regarding
    potential damage to Summit was speculative. The expert testified it was an
    approximation based on an estimated success rate for bids by Summit. We defer to
    the trial court to weigh the credibility of this evidence. See 
    id. Although the
    trial court was free to infer delays were caused by Enbridge
    Energy, the evidence also shows that Summit had a small shop, which resulted in
    difficulties handling and storing the spools and disorganization. The trial court
    could have inferred that Summit was not capable of handling a job of this
    magnitude given the size of its facilities and its workforce. Summit presumably
    took these factors into consideration when bidding the project. Thus, the trial court
    16
    could have inferred that the delays were not caused by Enbridge Energy but instead
    were caused by Summit’s inability to handle a large project and by its own
    shortfalls in the bidding process or that any delays caused by Enbridge Energy did
    not cause Summit damage.11 It was within the trial court’s province as factfinder to
    find that any extra expenses incurred by Summit were not caused by Enbridge
    Energy’s delays, if any. The parties presented conflicting evidence on this issue.
    Moreover, Summit had the burden to prove not only that it incurred damages but
    also the amount of its damages. See Golden Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 772 (Tex. 2003) (“[W]hether to award damages and how much is
    uniquely within the factfinder’s discretion.”). The trial court, as the factfinder, was
    entitled to weigh the credibility of Summit’s evidence in support of its claim for
    damages and find it lacking.
    Scope of the Agreements. Summit argues that it incurred expenses outside
    of the scope of the parties’ agreements resulting from Enbridge’s delays. The
    Enbridge parties argue that all expenses incurred by Summit were included in the
    scope of the agreements. The bid proposals, referred to explicitly as “Lump Sum
    proposal[s],” included “overtime,” but also specified that “[a]ny down time
    [would] be handled on a Time and Material basis.” “Extra Work” was to be billed
    for materials at cost plus 15% and labor at $85 per hour. Miller testified that
    overtime was to be paid on a “time and material” basis if Summit had to wait for
    the Enbridge parties to supply valves. However, the bid proposals do not expressly
    restrict the amount of overtime. Summit presented evidence that only “standard
    11
    Given these facts, this is not a situation in which the factfinder ignored the
    uncontroverted fact of an injury and denied recovery. See Schwartz v. Pinnacle Commc’ns, 
    944 S.W.2d 427
    , 436 (Tex. App.—Houston [14th Dist.] 1997, no writ) (“[W]here the evidence of an
    injury is uncontroverted, the fact finder may determine the extent of injury and the appropriate
    amount of damages to be awarded based on the facts, but it may not ignore uncontroverted
    evidence by completely denying recovery.”).
    17
    overtime” was included in the bids but did not present evidence of what the phrase
    “standard overtime” means. Presuming without deciding that the parties’
    agreement included “down time” to be paid by Summit as overtime, we conclude
    Summit did not prove as a matter of law that it incurred damages resulting from
    any purported delays by Enbridge.
    Conclusion. Considering the conflicting evidence presented at trial and
    deferring to the trial court as factfinder as we must, we conclude Summit has not
    established as a matter of law that Enbridge Energy’s failure to make an advanced
    payment on time caused damages to Summit. Similarly, Summit has not
    conclusively demonstrated that Enbridge Energy delayed the project by negotiating
    with Wolseley. Summit further has not conclusively shown it suffered damages
    from any delays by Enbridge Energy. Viewing the evidence in the light most
    favorable to the findings, we conclude that that the evidence was legally sufficient
    to support the trial court’s findings and judgment. We overrule Summit’s issues
    challenging the trial court’s findings on breach of contract.
    II.   Summit’s quantum meruit claim is precluded by express contract.
    Summit also challenges the trial court’s conclusion that its quantum meruit
    claim was barred by express contract. According to Summit, the services rendered
    in the requested change orders were not covered by the parties’ agreement, and
    thus Summit was entitled to recover under quantum meruit for those services.
    As a general rule, a party cannot recover under quantum meruit when there
    is a valid contract covering the services or materials furnished. Hill v. Shamoun &
    Norman, LLP, 
    544 S.W.3d 724
    , 737 (Tex. 2018). An exception applies when the
    reasonable value of work performed and accepted is not covered by the parties’
    contract. 
    Id. We review
    de novo whether an express contract covers the services at
    issue. 
    Id. 18 Several
    terms in the parties’ agreements address Summit’s ability to recover
    for overtime or change orders. Although the parties dispute the amount of overtime
    included in the parties’ agreements, there is no dispute that the bid proposals
    included “overtime” and also specified that “[a]ny down time [would] be handled
    on a Time and Material basis.” Moreover, the purchase orders state, “No claim for
    an increase in price or schedule extension shall be recognized unless such was
    authorized in advance and in writing by Purchaser.” Thus, the agreements address
    the approval process for change orders. Accordingly, the parties’ agreements
    contemplated overtime, extra work to be handled on a time and material basis, and
    change orders. See, e.g., Gotham Ins. Co. v. Warren E & P, Inc., 
    455 S.W.3d 558
    ,
    563 (Tex. 2014) (“[T]hese clauses indicate that the contract addresses the matter at
    issue, and [the plaintiff] is limited to the contract rather than equity when
    determining liability.”); Dardas v. Fleming, Hovenkamp & Grayson, P.C., 
    194 S.W.3d 603
    , 620 (Tex. App.—Houston [14th Dist.] 2006, pet. denied) (“[W]hen a
    valid, express contract covers the subject matter of the parties’ dispute, there can
    be no recovery under a [quantum meruit] theory.”).
    Summit presents no other argument to reverse the judgment in favor of
    Enbridge Energy. Additionally, Summit does not argue that Enbridge Gathering is
    not a party to the contracts. Thus, Summit presents no other ground on which to
    reverse the judgment dismissing the quantum meruit claim against Enbridge
    Gathering. We overrule Summit’s issue challenging the trial court’s conclusion
    that the quantum meruit claim is precluded by express contract.12
    Conclusion
    12
    Summit also contends that Enbridge Energy failed to prove its claims and defenses as a
    matter of law. Because we conclude that Summit did not prove as a matter of law that it suffered
    damages from any purported delays by Enbridge Energy, we need not reach this issue.
    19
    We affirm the judgment of the trial court.
    /s/    Frances Bourliot
    Justice
    Panel consists of Chief Justice Frost and Justices Jewell and Bourliot. (Frost, C.J.,
    concurring).
    20