BBX Operating, LLC v. American Fluorite, Inc., GeoSouthern Energy Partners, LP, and GeoSouthern Energy Corp. ( 2021 )


Menu:
  •                                        In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    ________________
    NO. 09-19-00278-CV
    ________________
    BBX OPERATING, LLC, Appellant
    V.
    AMERICAN FLUORITE, INC., GEOSOUTHERN ENERGY PARTNERS,
    LP, and GEOSOUTHERN ENERGY CORP., Appellees
    ________________________________________________________________________
    On Appeal from the 1st District Court
    Jasper County, Texas
    Trial Cause No. 35155
    ________________________________________________________________________
    MEMORANDUM OPINION
    The underlying litigation arises from a dispute over revenue payments, joint
    interest billings, and expenses incurred in the development of oil and gas prospects.
    In six issues, BBX Operating, LLC (BBX) appeals the trial court’s summary
    judgments in favor of American Fluorite, Inc. (AFI), GeoSouthern Energy Partners,
    LP (GSEP), and GeoSouthern Energy Corp. (GSEC) (collectively, “GeoSouthern”
    1
    or “Appellees”). For the following reasons, we affirm the trial court’s judgment in
    part and reverse and remand in part.
    I. Background
    A. Parties’ Relationship
    BBX and GeoSouthern had a lengthy relationship pursuing oil and gas drilling
    opportunities within various East Texas counties. As a means to develop these
    prospects and achieve producing wells within defined geographical areas, the parties
    entered into joint development agreements (JDAs), which preceded the joint
    operating agreements (JOAs). 1 The JDAs at issue are the Neches II AMI (or “area
    of mutual interest”) and Make My Day JDA. Pursuant to these agreements, BBX
    acted as the operator, and the GeoSouthern entities held working interests in varying
    percentages. 2
    The underlying lawsuit involved a dispute over BBX withholding
    GeoSouthern’s production revenues, GeoSouthern’s payment of joint interest
    billings to BBX (“JIBs”), and amounts sought by BBX through “Cash Call” letters,
    which BBX characterized as “Prospect Development Costs.” 3 BBX incurred the
    1
    The parties also referred to these as “areas of mutual interest” or “AMIs”
    throughout the trial record.
    2
    There are also other working interest owners, which are not parties to this
    litigation.
    3
    The parties also referred to these expenses as “unproposed well costs” and
    “pre-development costs” throughout the record.
    2
    costs delineated in the “Cash Call” letters after the acquisition of the leasehold
    interests but before drilling wells.
    1. Neches II AMI
    The Neches II agreement designated BBX as the operator and provided that
    any party to the agreement could acquire leasehold interests within the AMI.
    Likewise, any party to the agreement could propose wells by giving written notice
    as follows:
    WELL PROPOSALS: Well proposals shall include a) a plat showing
    the proposed surface and bottom hole locations, b) a geological
    prognosis to include the intended target zone (or zones), and c) AFE.
    Each Party will either elect to participate in the proposed well within
    thirty (30) days of receipt of the well proposal or go non-consent in the
    proposed well pursuant to the terms of the JOA. All operations on each
    well drilled on the subject lands or lands pooled therewith shall be
    governed by the terms of the JOA. Although the designated Operator
    shall use its best efforts to prepare and provide to each Party for
    execution a separate JOA for each well and unit in which each Party
    elects to participate, the terms of such JOA will apply to and be binding
    on the Parties regardless of whether same is actually executed. If there
    are any conflicts between the terms of the JOA and this Agreement, the
    terms of this Agreement shall super[s]ede and control. Upon the
    completion of any well, each non-operating Party shall timely receive
    all geological well information, permits, and government reports.
    2. Make My Day JDA
    The Make My Day agreement also designated BBX as the operator, and BBX
    would “have the sole option to propose units and wells within the defined areas;
    however, the JOA shall govern the right to propose wells within defined units.” The
    contract provided wells would be proposed as follows:
    3
    INITIAL WELL PROPOSALS. Any proposal of a well will include,
    but will not be limited to, the selection of the drill site, a good faith
    estimate of the size and configuration of the proposed unit for said
    well(s), the approximate total acreage to be included in the unit, a
    geological prognosis to include the intended target zone or zones, and
    an Operating Agreement, which will govern all operations conducted
    within such boundaries of the unit (“Proposed Unit”), identical to the
    form attached hereto as Exhibit B, as to those Parties electing to
    participate in the drilling of the proposed well and all operations to be
    conducted within the proposed unit. The proposed well will be
    designated as the “Initial Well” as that term is described and used in
    article VI, A. of the JOA. Additionally, such notice will contain the
    surface location of the well, the objective depth of the well and an
    estimate of the cost of drilling and completing the well for production.
    The parties receiving the Initial Well proposal shall have thirty (30)
    days after receipt of the proposal to notify the proposing party in
    writing, whether they elect to participate in the cost of the Initial
    Well (“Participating Parties”) or elect to relinquish their interest in the
    proposed well, and all future well(s) proposals, along with rights to any
    future leasehold purchased, within the proposed unit area. All parties
    electing to participate in the Initial Well will immediately execute and
    return the Operating Agreement provided in the proposal. If one (1) or
    more Parties elect not to participate in the Initial Well, then the
    proposing party shall give written notice of same to those Participating
    Parties within twenty (20) days following the expiration of the thirty
    (30) day election period set forth above. The Participating Parties shall
    then have the option for ten (10) days, following receipt of such written
    notice to elect to participate for their proportionate share of the interest
    available.
    ...
    All future proposals and operations conducted within any established
    JOA contract area following the drilling of the Initial Well in a unit
    shall be governed by the terms and conditions of the JOA which will
    supersede the provisions in this Agreement.
    (Emphasis added.) The Make My Day JDA further provided that “[p]articipation in
    any of the Areas of Mutual Interest identified may be reduced, relinquished or
    4
    otherwise limited based on elections not to participate or any failure to submit any
    payments required as provided elsewhere in this agreement.”
    3. Prospect Development
    AMIs or JDAs precede JOAs; once a well is put on production, a JOA is
    usually the next contract. Under the terms of the JDAs, well proposal submissions
    to the interest owners contained certain requisite information, along with an
    “authorization for expenditure” (“AFE”), which broke down the costs incurred in
    pursuing the well. The well proposal also included an election where the interest
    owner could consent or non-consent the well. If the interest owner consented,
    thereby electing to participate, they signed the operating agreement included with
    the proposal. If participating, the interest owner also sent payment for its
    proportionate share of the costs in the AFE. If an interest owner elected to non-
    consent the well, it would not pay the AFE costs, but it relinquished any interest in
    the well and any subsequent wells in the unit, and its interest would be offered to the
    other interest owners; if the other interest owners elected to participate, they would
    then pick up that share of the costs.
    After the parties agreed to a well proposal and the JOA was in place, BBX
    began sending JIBs for monthly costs associated with each well to the participating
    interest owners. According to BBX’s accountant, Laurel Vance, “Cash Calls” were
    handled as “off book” transactions, but if a party consented to a well, those were
    5
    handled as prepayment. 4 Once the participating parties executed a JOA, that
    agreement governed the payment of revenues, as well as remedies for non-payment
    of JIBs. According to BBX’s accountant, JIBs are generated on a well-by-well basis.
    Under the JOA, BBX, as the operator, had the right to offset or net JIBs if any party
    defaulted only within that particular contract area. 5
    4. “Cash Calls” and Dispute
    In May 2015, BBX sent nine “Cash Call” letters to the GeoSouthern entities
    for costs it purportedly incurred in the areas covered by these two agreements,
    totaling $4,219,597.55, and asserted in the letters that the AMIs/JDAs gave them the
    authority to do so. Each “Cash Call” letter cited to the applicable JDA, and stated
    that the agreement “allows BBX Operating, LLC to “Cash Call” partners for the
    expenses incurred for brokers fees, title examination, title curative and other
    expenses incurred for preparing tracts of land to be included in a future Drilling
    Unit(s).” The letters further advised:
    [The GeoSouthern entity] has 30 days from receipt [of] this notice to
    elect and pay its share of expenses. Under our agreement, if [the
    GeoSouthern entity] elects not to pay its share of the expenses then [the
    GeoSouthern entity] shall be deemed to have elected not to participate
    in the Leasehold Acquisition and deemed to have elected not to
    participate in any drilling and development of the leasehold within the
    AMI. Based on the deemed elections, [the GeoSouthern entity’s]
    4
    “Off book” transactions were costs accumulated by the operator for which
    no division of interest had been created to bill out on a joint interest billing.
    5
    The record reflects that GeoSouthern does not dispute BBX’s right to net or
    offset JIB payments against revenues.
    6
    leasehold and right to participate in a future Drilling Unit will be
    offered to any participating parties within the [Prospect Area].
    GeoSouthern contended that the Neches II and Make My Day JDAs did not
    permit BBX to recover these costs in the absence of a specific well proposal.
    GeoSouthern further argued it was not liable for costs submitted with a well proposal
    if they non-consented the proposal. Beginning in August 2015, BBX withheld
    GeoSouthern’s revenue payments. While GeoSouthern refused to pay the prospect
    development costs demanded in the “Cash Call” letters, it continued paying JIBs
    until Estis Compression placed liens on certain wells. GeoSouthern then withheld
    JIB payments only on the wells with liens. On December 17, 2015, GeoSouthern
    sent a letter demanding BBX release their revenue payments and filed suit against
    BBX shortly thereafter.
    B. Procedural History
    1. Original Petition
    On December 23, 2015, the plaintiffs filed their original petition against BBX.
    In it, they alleged that BBX is the operator of certain oil and gas leases (the “Subject
    Leases”) in Jasper, Tyler, and Polk County, Texas. The GeoSouthern entities also
    alleged that they own undivided mineral leasehold working interests in the Subject
    Leases and that BBX and AFI, among other entities, are parties to certain joint
    operating agreements and related development agreements. In support of its claims,
    GeoSouthern attached its demand letter to BBX and BBX’s “Cash Call” letters dated
    7
    May 27, 2015, alleged to represent costs incurred and paid by BBX in conjunction
    with the Neches II Prospect which include the Turkey Creek, Lake Tejas, Frog Pond,
    and Fish Camp Prospects in Tyler County; Make My Day and Swamper Prospects
    in Jasper County; and the Ollie East Prospect in Polk County. GeoSouthern asserted
    claims for breach of contract, conversion, statutory lien, declaratory judgment, and
    a Texas Natural Resources Code claim. On January 29, 2016, BBX filed its original
    answer, asserting a general denial.
    2. Rule 11 Agreement
    On March 7, 2016, less than three months after GeoSouthern sued BBX, the
    parties entered into a Rule 11 Agreement, 6 providing in relevant part:
    4. Payment of Revenue to GeoSouthern for March 2016 and thereafter.
    Beginning March 25, 2016 and continuing on the 25th day of each
    month thereafter (or the next business day if the 25th day falls on a
    weekend or legal holiday), BBX shall wire transfer in immediately
    available funds GeoSouthern’s revenue payment for production for the
    preceding month; provided however, nothing herein shall modify or
    alter GeoSouthern’s right to take in kind or seek division orders
    respecting payment of revenue or any other rights of GeoSouthern
    under the applicable joint operating agreements or related documents
    or applicable law.
    5. Payment of joint interest billing charges for August 2015 through
    January 2016. Provided that GeoSouthern receives the payments
    referenced in paragraph 3 by 12:00 p.m., central standard time, on the
    same day that GeoSouthern receives the payments in paragraph 3
    herein, GeoSouthern shall wire transfer immediately available funds of
    6
    During oral argument, the parties explained that the Rule 11 agreement was
    intended to provide for agreeable payment schedules of all expenses and revenues,
    save and except the Prospect Development Costs.
    8
    $1,295,761.29 to BBX for GeoSouthern’s joint interest billings for
    August, September, October, November, and December 2015, and
    January 2016, after adjustments for cash call payments, as set forth on
    Exhibit C. Otherwise, GeoSouthern will wire transfer such funds the
    next business day. Such payment shall not waive, impair, prejudice or
    otherwise affect GeoSouthern’s right to audit or dispute any joint
    interest billing charges under the terms of the applicable joint operating
    agreements or related agreements or applicable law.
    6. Payment of joint interest billings for February 2016 and thereafter.
    GeoSouthern will pay joint interest billings from BBX for the month of
    February 2016 and thereafter in accordance with the terms of the
    applicable joint operating agreements.
    A dispute subsequently arose regarding the Rule 11 Agreement, with each
    party alleging the other failed to perform. 7 Beginning with the October 25, 2016
    payment, BBX withheld revenue payments from GeoSouthern and began netting
    their JIBs. Although BBX’s corporate representative, John Gaines, and accountant,
    Laurel Vance, testified that GeoSouthern’s JIB amounts had been netted and
    GeoSouthern did not owe any JIB amounts, BBX continued to withhold revenue
    payments from GeoSouthern.
    7
    Both parties filed motions to enforce the Rule 11 Agreement, with the trial
    court ruling in GeoSouthern’s favor. BBX filed a petition for writ of mandamus,
    which this Court conditionally granted. See In re BBX Operating, LLC, No. 09-17-
    00079-CV, 
    2017 WL 1437135
    , at *1–2 (Tex. App.—Beaumont Apr. 20, 2017, orig.
    proceeding) (mem. op.).
    9
    3. Third Amended Petition
    According to their third amended petition, 8 the Appellees and BBX entered
    into certain joint operating agreements and related development agreements (the
    “Subject Contracts”) that govern the parties’ rights and obligations with respect to
    operations on the Subject Leases. GeoSouthern alleged that they had fully paid all
    undisputed JIBs, but that BBX improperly withheld and continued to withhold
    GeoSouthern’s proceeds from hydrocarbon sales. GeoSouthern asserted various
    claims against BBX: (1) breach of contract; (2) conversion; (3) section 91.402(a) of
    the Natural Resources Code; (4) foreclosure of a statutory lien; (5) breach of Rule
    11 Agreement; and (6) declaratory judgment pertaining to the amounts lawfully
    owed, the authority to withhold, net, or offset revenue, and for BBX’s removal and
    replacement as operator.
    4. First Motion for Partial Summary Judgment and Order
    In its first motion for partial summary judgment, GeoSouthern addressed its
    affirmative claims, including its claim for breach of contract based on the JDAs and
    Rule 11 Agreement and its claim for declaratory judgment. The summary judgment
    record included GeoSouthern General Land Manager Doug Dahmann’s affidavit,
    the Neches II JDA, the Make My Day JDA, the parties’ Rule 11 Agreement, the
    8
    The third amended petition was the live pleading on file at the time
    GeoSouthern filed its first and second partial summary judgment motions.
    10
    deposition testimony of BBX corporate representative John Gaines, Turkey Creek
    Well Proposal dated August 24, 2015, AFI’s letter indicating it “elected to go non-
    consent” to the Turkey Creek Well Proposal, BBX General Counsel Mark
    Helmueller’s Affidavit dated December 13, 2016, BBX’s authenticated “Statement
    of Account” reflecting what GeoSouthern and BBX owed, and BBX’s May 2015
    “Cash Call” Letters.
    In response, BBX objected to the affidavit testimony of Dahmann and argued
    GeoSouthern’s summary judgment evidence was not sufficient to entitle it to
    judgment as a matter of law on its claims for breach of contract.
    The trial court granted GeoSouthern a partial summary judgment as to the
    breach of contract claims and found the summary judgment record conclusively
    showed the amount of $1,714,547.65 for production revenues was owed to
    GeoSouthern as of July 31, 2017, and awarded it damages in that amount. The trial
    court also rendered declaratory judgment in GeoSouthern’s favor:
    2. Non-joint operating agreements and/or demands which are included
    in the summary judgment record including the (i) “Cash Call Letters”
    (attached as Exhibit A-2 to the MPSJ); (ii) Area of Mutual Interest
    Agreement Neches II Prospect Area Tyler County, Texas (attached as
    Exhibit A-3 to the MPSJ); or (iii) Make My Day Joint Venture
    Development Agreement Tyler and Jasper Counties, Texas (attached as
    Exhibit A-4 to the MPSJ) do not authorize BBX to withhold oil and gas
    revenues from GeoSouthern;
    3. Non-joint operating agreements and/or demands which are included
    in the summary judgment record including the (i) “Cash Call Letters”
    (attached as Exhibit A-2 to the MPSJ); (ii) Area of Mutual Interest
    11
    Agreement Neches II Prospect Area Tyler County, Texas (attached as
    Exhibit A-3 to the MPSJ) or (iii) Make My Day Joint Venture
    Development Agreement Tyler and Jasper Counties, Texas (attached as
    Exhibit A-4 to the MPSJ); do not authorize BBX to net or offset
    revenues that BBX owes to GeoSouthern against any non-joint interest
    billing amounts asserted by BBX; and
    4. GeoSouthern has no obligation under the Area of Mutual Interest
    Agreement Neches II Prospect Area Tyler County, Texas (attached as
    Exhibit A-3 to the MPSJ) to pay any pre-development or unproposed
    well costs that BBX claims in connection with the Turkey Creek
    Prospect.
    5. BBX’s Counterclaims
    In February of 2018, BBX filed its amended counterclaim against
    GeoSouthern and brought breach of contract claims under the Neches II and Make
    My Day agreements, in addition to claims for quantum meruit seeking to recover
    those portions of the unproposed well service expenses it attributed to GeoSouthern.
    6. Second Motion for Partial Summary Judgment and Order
    GeoSouthern’s second motion for partial summary judgment addressed
    BBX’s counterclaims for breach of contract and quantum meruit. GeoSouthern
    sought dismissal of BBX’s breach of contract claims because the JDAs expressly
    provided for the recovery of the costs BBX sought in the “Cash Call” letters; that is,
    only after a written well proposal was presented to the working interest owners and
    the working interest owners expressly elected to participate in the proposed well
    would a party pay its portion of such expenses when it returned a signed agreement.
    GeoSouthern also argued that the trial court should dismiss BBX’s quantum meruit
    12
    “Cash Call” Claims since the JDAs expressly provided for the sharing of those costs
    between interest owners who elected to participate thereby barring the claims by the
    express contract rule. GeoSouthern finally contended that GeoSouthern did not
    accept or benefit from the unproposed well services and BBX did not reasonably
    notify GeoSouthern it expected payment for them. Only if the working interest
    owners elected to participate in a proposed well, at that point, each participant would
    pay for their share of the costs associated with the development and drilling of the
    well. If the interest owners elected not to participate, they would not be responsible
    for their proportionate share of expenses, but in doing so, they forfeited their right
    to participate in that well, as well as future wells within the leasehold, with their
    share being offered for reallocation to the other working interest owners.
    In response, BBX argued a) there was no express contract, specifically a JOA,
    that could address BBX’s recovery of prospect development costs, and b) there
    remained genuine issues of material fact regarding the elements of its quantum
    meruit claim that would preclude summary judgment. BBX contended that neither
    the JOAs or JDAs address how prospect development costs—those costs incurred to
    develop and operate wells within the prospect areas after leasehold interests are
    acquired—are to be incurred and paid for by the interest owners. BBX contended
    that the JDAs covered leasehold acquisitions costs and well proposals, but the
    payment of prospect development costs was to be addressed by a separate contract,
    13
    the JOAs. BBX argued that expenses incurred after leasehold acquisition but before
    a well proposal were not expressly covered under the JDA provisions pertaining to
    well proposals but were informally consented to by the parties and subsequently
    reimbursed to BBX by the interest owners.
    The summary judgment evidence included the Neches II JDA and Make My
    Day JDA, the “Cash Call” letters, BBX’s notice of withdrawal as operator,
    deposition testimony from BBX corporate representative John Gaines, BBX General
    Counsel Mark Helmueller’s deposition testimony, BBX Accountant Laurel Vance’s
    deposition testimony, October 16, 2015 correspondence from Mark Helmueller,
    Lake Tejas Well Proposal and JOA, Turkey Creek Well Proposal and non-consent,
    and Doug Dahmann’s affidavit. The trial court again granted GeoSouthern’s
    summary judgment motion ruling that the JDAs were written contracts that expressly
    covered the costs associated with the prospect development expenses, the contracts
    did not permit the recoupment of the prospect development costs in the manner
    sought by BBX and therefore, GeoSouthern did not breach the JDAs by its refusal
    to pay the “Cash Call” Claims. Finally, the trial court granted GeoSouthern’s second
    motion for partial summary judgment in its entirety and dismissed all counterclaims
    BBX asserted.
    14
    7. BBX’s Second Amended Counterclaim
    In October 2018, BBX filed its second amended counterclaim. In addition to
    its breach of contract and quantum meruit claims, BBX added affirmative claims for
    promissory estoppel.
    8. Fourth Amended Petition
    On March 4, 2019, GeoSouthern filed its fourth amended petition, asserting
    (1) breach of contract claims for damages based on the JOAs and Rule 11
    Agreement, (2) a claim pursuant to Texas Natural Resources Code section 91.402,
    (3) a statutory lien claim pursuant to Texas Business and Commerce Code section
    9.343, and (4) declaratory judgment for all amounts lawfully owed by GeoSouthern
    based on the AMI Agreements, the Turkey Creek proposal and non-consent, and
    Rule 11 Agreement. In addition to liquidated damages, GeoSouthern sought pre-
    judgment and post-judgment interest, costs, and attorneys’ fees.
    9. Motion for Final Summary Judgment and Order
    GeoSouthern’s motion for final summary judgment addressed its outstanding
    affirmative claims against BBX and BBX’s outstanding counterclaim for promissory
    estoppel against GeoSouthern. Specifically, GeoSouthern set out in the motion that
    it sought final judgment on all revenues from hydrocarbon sales BBX owed
    GeoSouthern, because the first partial summary judgment only addressed revenues
    through July 31, 2017. In relation to this claim, GeoSouthern sought total revenues
    15
    due in the “Principal Amount” of $2,659,473.20 or the “Alternate Principal Amount”
    of $2,441,732.24, dependent on whether BBX was authorized to withhold
    $217,740.96 in revenues that Murphy Energy Corp. had refused to pay BBX for the
    sale of hydrocarbons. 9 In the further alternative, GeoSouthern sought the “Admitted
    Principal Amount” of $2,436,547.65 based on BBX corporate representative’s
    deposition testimony. With respect to prejudgment interest on the unpaid revenues,
    GeoSouthern sought:
    (i) $261,548.32 in prejudgment interest on the Principal Amount under
    the Texas Finance Code, (ii) $249,266.38 in prejudgment interest on
    the Alternate Principal Amount, or (iii) $145,789.28 on the Admitted
    Principal Amount.
    OR
    GeoSouthern seeks (i) $158,202.54 in prejudgment interest under the
    Texas Natural Resources Code on the Principal Amount, (ii)
    $152,387.66 in prejudgment interest on the Alternate Principal
    Amount, or (iii) $69, 199.52 on the Admitted Principal Amount.
    GeoSouthern also sought post-judgment interest on all amounts BBX owed at the
    rate of five percent per annum. Finally, GeoSouthern sought “reasonable and
    necessary attorneys’ fees” of not less than $550,060, and “such other and further
    relief to which they show themselves justly entitled.”
    9
    The record reflected that purchaser Murphy Energy filed for bankruptcy and
    failed to pay BBX the of amount $217,740.96 attributable to GeoSouthern’s
    revenues.
    16
    With respect to BBX’s promissory estoppel counterclaim, GeoSouthern
    sought summary judgment based on the “legal ground that promissory estoppel is
    not recognized as an affirmative cause of action[.]” GeoSouthern incorporated the
    “findings and rulings” of the trial court’s prior summary judgment orders into its
    motion for final summary judgment and argued that “[i]n addition to the reasons set
    forth in the Court’s 10/2018 MPSJ Order, the Court should dismiss BBX’s
    promissory estoppel claims” because “promissory estoppel is defensive only, and
    cannot constitute a basis for affirmative relief.”
    The summary judgment evidence included: (a) the affidavit of GeoSouthern
    Controller David Post with supporting exhibits, including revenue statements from
    BBX, a summary of the revenue statements, interest calculations under the Texas
    Natural Resources Code and Texas Finance Code; (b) GeoSouthern General Land
    Manager Doug Dahmann’s affidavit with supporting exhibits, including the JDAs
    and JOAs, “Cash Call” letters, well proposal payment chart, GeoSouthern’s demand
    letter, BBX’s response to demand letter, Rule 11 Agreement with JOAs and
    accounting procedures; (c) Kenneth Green’s Affidavit with supporting exhibits
    including fee chart, redacted invoices, and interest calculations; and (d) Blake
    Hamm’s affidavit with supporting exhibits including prior summary judgment
    orders, orders for issuance of prejudgment writs of garnishment, Laurel Vance’s
    17
    deposition transcript, bankruptcy hearing transcripts, and Murphy Energy Corp.
    bankruptcy schedules.
    In its response to GeoSouthern’s final summary judgment motion, BBX
    contended GeoSouthern failed to prove its breach of contract claim under the Rule
    11 Agreement, specifically that GeoSouthern failed to conclusively establish its
    performance and damages. BBX also argued that GeoSouthern failed to meet the
    statutory requirements of the TNRC, and BBX had paid GeoSouthern an amount
    exceeding its initial demand. BBX asserted its entitlement to bring an affirmative
    claim for damages based on promissory estoppel as a matter of law. Finally, BBX
    challenged GeoSouthern’s right to recover attorneys’ fees. Additional evidence BBX
    included with its response was GeoSouthern General Land Manager Doug
    Dahmann’s Deposition, Laurel Vance’s affidavit averring Murphy Energy still had
    not paid $217,740.96 owed to BBX and attributable to GeoSouthern’s revenues,
    BBX CEO Matthew Telfer’s Affidavit regarding the parties’ relationships and the
    JDAs, and BBX’s counsel’s affidavit challenging the reasonableness and necessity
    of attorneys’ fees.
    The trial court granted GeoSouthern’s motion for final summary judgment
    against BBX in its entirety. The trial court declared that neither the “Cash Call”
    letters nor the JDAs authorized BBX to withhold GeoSouthern’s oil and gas
    revenues nor net/offset revenues owed to GeoSouthern against any non-JIB amounts
    18
    asserted by BBX, and GeoSouthern had no obligation under the Neches II JDA to
    pay any pre-development or unproposed well costs in connection with the Turkey
    Creek Prospect. The trial court ordered that BBX was liable to:
    • AFI in the principal amount of EIGHT HUNDRED FORTY-SIX
    THOUSAND ONE HUNDRED SIXTY-FOUR AND 84/100 U.S.
    DOLLARS ($846,164.84), plus (i) EIGHTY-ONE THOUSAND NINE
    HUNDRED AND 95/100 U.S. DOLLARS ($81,900.95) in
    prejudgment interest under the Texas Finance Code, (ii) ONE
    HUNDRED SEVENTY-FIVE THOUSAND TWENTY-NINE AND
    09/100 U.S. DOLLARS ($175,029.09) in reasonable and necessary
    attorneys’ fees, (iii) an additional TWENTY THOUSAND AND NO/
    100 U.S. DOLLARS ($20,000.00) in reasonable and necessary
    attorneys’ fees if this Final Judgment is appealed and AFI is the
    successful party, (iv) an additional TWENTY-FIVE THOUSAND
    AND NO/IOO U.S. DOLLARS ($25,000.00) in reasonable and
    necessary attorneys’ fees if petition is made to the Texas Supreme Court
    and AFI is the successful party, and (v) post-judgment interest at the
    rate of five percent (5%) per annum on all foregoing amounts;
    • GSEP in the principal amount of ONE HUNDRED EIGHT[Y]-SIX
    THOUSAND FIVE HUNDRED TWENTY AND 03/100 U.S.
    DOLLARS ($186,520.03), plus (i) SEVENTEEN THOUSAND FOUR
    HUNDRED SEVENTEEN AND 94/100 U.S. DOLLARS
    ($17,417.94) in prejudgment interest under the Texas Finance Code,
    (ii) Thirty-Eight Thousand Five Hundred Fifty-Nine and 20/100 U.S.
    Dollars ($38,539.20) in reasonable and necessary attorneys’ fees, (iii)
    an additional TWENTY THOUSAND AND NO/100 U.S. DOLLARS
    ($20,000.00) in reasonable and necessary attorneys’ fees if this Final
    Judgment is appealed and GSEP is the successful party, (iv) an
    additional TWENTY-FIVE THOUSAND AND NO/100 U.S.
    DOLLARS ($25,000.00) in reasonable and necessary attorneys’ fees if
    petition is made to the Texas Supreme Court and GSEP is the successful
    party, and (v) post-judgment interest at the rate of five percent (5%) per
    annum on all foregoing amounts;
    • GSEC in the principal amount of ONE MILLION SIX HUNDRED
    TWENTY-SIX THOUSAND SEVEN HUNDRED EIGHTY-EIGHT
    19
    AND 33/100 U.S. DOLLARS ($1,626,788.33), plus (i) ONE
    HUNDRED SIXTY-TWO THOUSAND TWO HUNDRED
    TWENTY-NINE AND 43/100 U.S. DOLLARS in prejudgment
    interest under the Texas Finance Code, (ii) THREE HUNDRED
    THIRTY-SIX THOUSAND FOUR HUNDRED SEVENTY-ONE
    AND 70/100 U.S. DOLLARS ($336,471.70) in reasonable and
    necessary attorneys’ fees, (iii) an additional TWENTY THOUSAND
    AND NO/100 U.S. DOLLARS ($20,000.00) in reasonable and
    necessary attorneys’ fees if this Final Judgment is appealed and GSEP
    is the successful party, (iv) an additional TWENTY-FIVE
    THOUSAND AND NO/100 U.S. DOLLARS ($25,000.00) in
    reasonable and necessary attorneys’ fees if petition is made to the Texas
    Supreme Court and GSEP is the successful party, and (v) post-
    judgment interest at the rate of five percent (5%) per annum on all
    foregoing amounts.
    BBX timely appealed the trial court’s final summary judgment order.
    II. Standard of Review
    We review a trial court’s decision to grant summary judgment de novo.
    See Shell Oil Co. v. Writt, 
    464 S.W.3d 650
    , 654 (Tex. 2015) (citation omitted). We
    view the evidence in the light most favorable to the nonmovant. 
    Id.
     (citing City of
    Keller v. Wilson, 
    168 S.W.3d 802
    , 824 (Tex. 2005)). In doing so, we indulge every
    reasonable inference and resolve any doubts against the motion. See City of Keller,
    168 S.W.3d at 824. “Undisputed evidence may be conclusive of the absence of a
    material fact issue, but only if reasonable people could not differ in their conclusions
    as to that evidence.” Buck v. Palmer, 
    381 S.W.3d 525
    , 527 (Tex. 2012) (citation
    omitted).
    20
    When a no-evidence motion has been filed, it “is essentially a pretrial directed
    verdict, and we apply the same legal sufficiency standard in reviewing a no-evidence
    summary judgment as we apply in reviewing a directed verdict.” King Ranch, Inc.
    v. Chapman, 
    118 S.W.3d 742
    , 750–51 (Tex. 2003) (citations omitted).
    A no evidence point will be sustained when (a) there is a complete
    absence of evidence of a vital fact, (b) the court is barred by rules of
    law or of evidence from giving weight to the only evidence offered to
    prove a vital fact, (c) the evidence offered to prove a vital fact is no
    more than a mere scintilla, or (d) the evidence conclusively establishes
    the opposite of the vital fact.
    Merrell Dow Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 711 (Tex. 1997) (citation
    omitted).
    A party moving for traditional summary judgment has the burden of
    establishing there is no genuine issue of material fact as to at least one requisite
    element of the asserted cause of action and that it is entitled to judgment as a matter
    of law. See Tex. R. Civ. P. 166a(c); Lightning Oil Co. v. Anadarko E&P Onshore,
    LLC, 
    520 S.W.3d 39
    , 45 (Tex. 2017) (citations omitted). When the trial court fails
    to specify the grounds on which it granted summary judgment, we must affirm if any
    of the summary judgment grounds are meritorious. FM Props. Operating Co. v. City
    of Austin, 
    22 S.W.3d 868
    , 872–73 (Tex. 2000) (citation omitted).
    If    a    defendant      files    a        combined   traditional   and     no-
    evidence summary judgment motion, we first review the judgment under the no-
    evidence standards of Rule 166a(i). Ford Motor Co. v. Ridgway, 
    135 S.W.3d 598
    ,
    21
    600 (Tex. 2004); Werth v. Johnson, 
    294 S.W.3d 908
    , 909 (Tex. App.—Beaumont
    2009, no pet.). When the underlying facts are undisputed, the analysis becomes a
    question of law for the judge; however, if the facts are disputed, it is a question for
    the trier of fact. See Richey v. Brookshire Grocery Co., 
    952 S.W.2d 515
    , 518 (Tex.
    1997).
    III. Analysis
    A. Issue One: Breach of Contract
    In its first issue, BBX challenges GeoSouthern’s entitlement to summary
    judgment on its breach of contract claim. BBX contends that GeoSouthern failed to
    conclusively establish its damages and that it failed to establish its performance or
    excuse from performance.
    A Rule 11 agreement can be enforced as a contract. See Ford Motor Co. v.
    Castillo, 
    279 S.W.3d 656
    , 663 (Tex. 2009) (explaining that “party seeking
    enforcement of the settlement agreement must pursue a separate claim for breach of
    contract[]”). To be entitled to traditional summary judgment on its breach of contract
    claim, GeoSouthern was required to prove all elements of its claim. See Tex. R. Civ.
    P. 166a(c). The essential elements of a breach of contract cause of action are: “(1)
    the existence of a valid contract; (2) the plaintiff performed or tendered performance
    as the contract required; (3) the defendant breached the contract by failing to perform
    or tender performance as the contract required; and (4) the plaintiff sustained
    22
    damages as a result of the breach.” USAA Tex. Lloyds Co. v. Menchaca, 
    545 S.W.3d 479
    , 501 n.21 (Tex. 2018) (citations omitted).
    1. Damages
    BBX makes three sub-arguments in support of this issue: (1) GeoSouthern
    employee Dahmann’s affidavits were conclusory; (2) GeoSouthern failed to prove
    its entitlement to additional damages including the “Murphy Amount;” and (3) the
    damages, as awarded in the final summary judgment order, were not requested in
    the motion.
    As proof of its damages with its first partial motion for summary judgment,
    GeoSouthern included evidence in the form of an affidavit from Douglas Dahmann.
    Additionally, the summary judgment evidentiary record included, in part, BBX’s
    Corporate Representative John Gaines’s deposition testimony, which BBX
    submitted with its response. In support of its final motion for summary judgment,
    GeoSouthern included as evidence another affidavit from Dahmann authenticating
    and attaching the various JDAs, 10 GeoSouthern’s demand letter, the Rule 11
    Agreement, BBX’s response to the demand letter, and an affidavit from David Post,
    GeoSouthern’s Controller. Post’s affidavit authenticated and included revenue
    10
    The Make My Day JDA in the final summary judgment record included a
    copy of “A.A.P.L. Form 610-1982 Model Form Operating Agreement Modified to
    Provide for Horizontal Wells” as well as the COPAS accounting procedures for the
    JOA.
    23
    statements received from BBX, as well as internal GeoSouthern accounting records.
    These records showed the amounts of monthly revenues owed by BBX to each
    GeoSouthern entity and the JIB amounts that BBX offset against the revenues. Post’s
    affidavit explained how he used the attached accounting records to calculate the
    amounts owed to GeoSouthern from BBX.
    BBX objected to Dahmann’s affidavit and argues Dahmann’s testimony
    regarding damage amounts is conclusory and not supported by documentary
    evidence or otherwise how he arrived at the damage amounts. In its brief, BBX
    contends “Mr. Dahmann’s affidavit is devoid of means to calculate how
    GeoSouthern arrives at approximately $2.6M in claimed damages[,]” and “[n]o
    documents are attached to assist in or verify the calculation.”
    A conclusory affidavit is substantively defective. See Brown v. Brown, 
    145 S.W.3d 745
    , 751 (Tex. App.—Dallas 2004, pet. denied). Rule 166a(f) governs
    affidavits submitted in support of summary judgments and provides as follows:
    Supporting and opposing affidavits shall be made on personal
    knowledge, shall set forth such facts as would be admissible in evidence
    . . . [s]worn or certified copies of all papers or parts thereof referred to
    in an affidavit shall be attached thereto or served therewith. The court
    may permit affidavits to be supplemented or opposed by depositions or
    by further affidavits.
    Tex. R. Civ. P. 166a(f).
    BBX further disagrees with the amounts set forth in the affidavit of
    GeoSouthern’s Controller, David Post. Post’s affidavit attached the revenue
    24
    statements from BBX, explained what the various amounts in those statements were,
    and specified how he used those to calculate the amount BBX owed GeoSouthern.
    BBX does not dispute that it owes and has withheld revenues from GeoSouthern.
    Despite disagreeing with the amounts claimed to be owed by GeoSouthern, BBX
    failed to provide any contrary evidence to substantiate the revenue amounts it
    collected on behalf of GeoSouthern for the months in question.
    Even if we agree that Dahmann’s affidavit is conclusory as to damage
    amounts, the trial court may also consider the evidence attached to BBX’s summary
    judgment responses to make its ruling. See Wilson v. Burford, 
    904 S.W.2d 628
    , 629
    (Tex. 1995); see also Schlumberger Tech. Corp. v. Pasko, 
    544 S.W.3d 830
    , 835
    (Tex. 2018) (“Rule 166a(c) plainly provides for the court to consider evidence in the
    record that is attached either to the motion or response[]”). BBX included the
    deposition testimony of its corporate representative, John Gaines, as evidence with
    its response to GeoSouthern’s first motion for partial summary judgment. In that
    deposition, Gaines testified that in October 2016, BBX made the decision to begin
    netting JIB amounts GeoSouthern owed against the revenues due. Gaines testified
    that BBX did so pursuant to Article XV, Section D of the JOAs, and the Rule 11
    Agreement incorporated the JOAs by reference. Gaines testified that after netting
    JIB amounts GeoSouthern owed between October 2016 and July 2017 against the
    revenues BBX owed GeoSouthern, the net revenue amount BBX owed GeoSouthern
    25
    was $1,714,547.65. Therefore, with respect to damages, the evidence in the first
    partial summary judgment record conclusively established that as of July 2017, BBX
    owed GeoSouthern $1,714,547.65 in revenues.
    In response to GeoSouthern’s motion for final summary judgment, BBX
    complains that GeoSouthern incorporated the $1,714,547.65 revenue amount from
    the first motion but failed to account for how the additional amount of $727,184.59
    or $944,925.55 was derived. However, Post’s affidavit clearly explains that between
    August 2016 through October 2017, “BBX owe[d] GeoSouthern not less than the
    total principal amount of $2,659,473.20” or alternatively, if BBX rightfully withheld
    the “Murphy Oil Payments” from GeoSouthern’s revenue in an amount of
    $217,740.96, then the revenue amount owed GeoSouthern was $2,441,732.24. Post
    explains how he calculated these “net revenues” with specificity using the revenue
    statements BBX sent to GeoSouthern. The BBX statements and the summaries
    contained data for these amounts that included JIB deduction amounts, and Post
    attached these statements and summaries to his affidavit. BBX complains that the
    calculations in the affidavits for the motion for final summary judgment did not but
    should have accounted for JIBs; however, the testimony of BBX’s accountant,
    Laurel Vance, conclusively established that GeoSouthern did not owe any additional
    JIB payments, because BBX had netted them or offset them against GeoSouthern’s
    26
    revenues, and the “unnetted revenue” remains in BBX’s revenue account until the
    check clears the bank.
    “[I]ssues a non-movant contends avoid the movant’s entitlement to summary
    judgment must be expressly presented by written answer to the motion or by other
    written response to the motion[.]” McConnell v. Southside Indep. Sch. Dist., 
    858 S.W.2d 337
    , 341 (Tex. 1993) (citing City of Hous. v. Clear Creek Basin Authority,
    
    589 S.W.2d 671
    , 678 (Tex. 1979)). In its response to GeoSouthern’s motion for final
    summary judgment, BBX only disputed that it owed $944,925.55, because it
    disputed that it owed the “Murphy Amount” of $217,740.96 as it had never received
    those funds from the purchaser. BBX did not challenge the remaining revenue
    amounts GeoSouthern claimed. Therefore, to the extent that BBX disputes the
    revenue amounts owed in the final judgment beyond the “Murphy Amount,” BBX
    failed to address the remaining revenue damages in its summary judgment response.
    See 
    id.
    The summary judgment evidence conclusively established the total damage
    amount of $2,659,473.20, less the amount awarded in the first summary judgment
    order of $1,714,547.65, totaled $944,925.55, which was the exact amount
    GeoSouthern claimed to be owed. Evidence in the summary judgment record also
    supported that the alternate number of $2,441,732.24 was derived by deducting the
    “Murphy Amount” of $217,740.96, should the trial court determine BBX lawfully
    27
    withheld this amount, then subtracting the $1,714.547.65 awarded in the initial
    summary judgment, totaled $727,184.59. Despite BBX’s complaint that there
    remained a genuine issue of material fact regarding the proper calculation of any
    damages, the trial court was able to decide as a matter of law whether Murphy Oil’s
    failure to pay BBX by its subsequent bankruptcy excused BBX from including the
    “Murphy Amount” of $217,740.96 in the revenue calculations from a plain reading
    of the Rule 11 Agreement.
    Finally, BBX argues that GeoSouthern did not request the itemized measure
    of damages awarded to each separate GeoSouthern entity in the final summary
    judgment order. Generally, a judgment for damages exceeding the pleaded amount
    is erroneous, even when the evidence supports a larger award. Lehmann v. Har-Con
    Corp., 
    39 S.W.3d 191
    , 202 (Tex. 2001); see also Tex. R. Civ. P. 301 (requiring
    judgment to conform to pleadings); Garrett v. Brinkley, No. 03-17-00295-CV, 
    2017 WL 6503043
    , at *2 (Tex. App. —Austin Dec. 12, 2017, pet. denied) (mem. op.)
    (explaining how the rule developed). However, when appellate courts have reversed
    summary judgments because a trial court granted more relief than a party requested
    in its motion for summary judgment, the summary judgment motion “wholly failed
    to address a claim for relief or theory of liability.” Levertov v. Hold Props., Ltd., No.
    11-11-00284-CV, 
    2014 WL 887225
    , at *5–6 (Tex. App.—Eastland Feb. 27, 2014,
    no pet.) (mem. op.) (affirming summary judgment granting damages for more
    28
    months’ rent than specifically requested in motion where evidence supported award,
    body of motion referenced more months than specifically requested in prayer) (citing
    Science Spectrum, Inc. v. Martinez, 
    941 S.W.2d 910
    , 911–12, (Tex. 1997); Bever
    Props., L.L.C. v. Jerry Huffman Custom Builder, L.L.C., 
    355 S.W.3d 878
    , 886–87
    (Tex. App.—Dallas 2011, no pet.); Rust v. Tex. Farmers Ins. Co., 
    341 S.W.3d 541
    ,
    552 (Tex. App.—El Paso 2011, pet. denied); Muston v. Nueces Cty. Sheriff’s Dep’t,
    
    122 S.W.3d 469
    , 473 (Tex. App.—Corpus Christi 2003, no pet.)).
    BBX has failed to cite any cases, nor have we found any, where an appellate
    court reversed a trial court for awarding the amount of damages sought in a summary
    judgment motion but itemized the damage awards among the various plaintiff
    movants, who were related entities. Here, GeoSouthern identified the three separate
    entities as Plaintiffs, AFI, GSEP, and GSEC in its summary judgment motion, which
    it collectively referred to as “GeoSouthern.” It incorporated the trial court’s prior
    partial summary judgment award to GeoSouthern in the amount of $1,714,547.65
    through July 31, 2017. GeoSouthern asserted the entities were owed total additional
    revenues of $944,925.55 between August 2017 through January 2018 if the trial
    court determined as a matter of law that BBX improperly withheld the “Murphy
    Amount” or alternatively, $727,184.59 if BBX was excused from including the
    “Murphy Amount” in revenue payments. The evidence in the form of Post’s
    affidavit, supporting revenue statements, and summaries expressly enumerated the
    29
    revenue amounts owed to each GeoSouthern entity and supported the exact amount
    of revenues awarded by the trial court, which importantly, BBX does not contest.
    BBX only disputes that the “Murphy Amount” should be included in the revenue
    payments. Finally, in its summary judgment motion prayer, GeoSouthern sought
    “such other and further relief to which they show themselves justly entitled.”
    GeoSouthern conclusively established its damages, and the summary judgment
    evidence supports the trial court’s delineation of the amounts owed to each Plaintiff.
    2. Performance
    On appeal, BBX argues that GeoSouthern failed to prove it performed under
    the contract or that its performance was excused and that BBX asserted the
    affirmative defense of prior material breach. Only a party’s material breach will
    excuse the other contracting party’s performance. See Hernandez v. Gulf Group
    Lloyds, 
    875 S.W.2d 691
    , 692 (Tex. 1994); see also Mustang Pipeline Co., Inc. v.
    Driver Pipeline Co., Inc., 
    134 S.W.3d 195
    , 196 (Tex. 2004) (“It is a fundamental
    principle of contract law that when one party to a contract commits a material breach
    of that contract, the other party is discharged or excused from further
    performance.”). “Generally, the issue of whether a breach rises to the level of a
    material breach that will render the contract unenforceable presents a dispute for
    resolution by the trier of fact.” Hiles v. Arnie & Co, P.C., 
    402 S.W.3d 820
    , 831 (Tex.
    App.—Houston [14th Dist.] 2013, pet. denied) (citation omitted). However,
    30
    materiality of a breach and the agreement’s resulting unenforceability can present
    questions for the court to resolve as a matter of law. See id.; see also Mustang
    Pipeline Co., 134 S.W.3d at 199–200 (determining that when contract provided time
    was of the essence and a party failed to perform, other party’s performance was
    excused as a matter of law).
    In determining the materiality of a breach, courts consider, among other
    factors, the extent to which the nonbreaching party is deprived of the benefit it could
    have reasonably expected from the other party’s full performance. Hernandez, 875
    S.W.2d at 693. “The less the non-breaching party is deprived of the expected benefit,
    the less material the breach.” Id. at 693.
    BBX’s corporate representative admitted that GeoSouthern paid JIB amounts
    on wells where there was no lien and only withheld JIB amounts on those properties
    which had a lien filed by a subcontractor. The same corporate representative testified
    that BBX netted GeoSouthern’s JIB amounts against the revenues and the “JIBs are
    now current as a result of the cumulative netting.” The summary judgment record
    likewise established that BBX’s accountant testified GeoSouthern was current on
    their JIB amounts and owed no further JIBs because BBX had netted or offset against
    all JIB amounts owed.
    In the Rule 11 Agreement, the parties agreed to pay the JIBs and revenues in
    a manner consistent with the JOAs but set forth a monthly deadline by which BBX
    31
    had to pay the prior month’s revenues. GeoSouthern does not dispute BBX’s right
    to net or offset JIB payments against revenues. The JOAs contained a provision
    allowing BBX to offset or net late JIB payments owed to them against revenues due
    the working interest owner. Since the Rule 11 Agreement required JIBs to be paid
    in accordance with the JOAs, the remedy of offsetting or netting those amounts owed
    to BBX against the revenues due to GeoSouthern was a remedy available and one
    BBX exercised to make itself whole with respect to the JIBs. GeoSouthern
    conclusively established that the summary judgment evidence showed BBX netted
    the entire JIB amounts against GeoSouthern’s revenues, it no longer owed any JIB
    amounts, and therefore, BBX received the benefit of the bargain. BBX presented no
    evidence establishing a genuine issue of material fact existed as to the materiality of
    any alleged breach by GeoSouthern to the extent it failed to pay JIBs on liened
    properties. Therefore, BBX was still required to pay revenue amounts owed under
    the contract.
    Having determined that GeoSouthern conclusively established its damages
    and BBX failed to present evidence creating a genuine issue of material fact as to
    the materiality of a breach, we overrule BBX’s first issue.
    32
    B. Issue Two: Declaratory Judgment
    BBX challenges the trial court’s entry of declaratory judgment for
    GeoSouthern and specifically contests “that certain agreements [did] not authorize
    BBX to net or offset revenues.” BBX argues GeoSouthern failed to establish as a
    matter of law its entitlement to a declaratory judgment that BBX is not allowed to
    net or offset revenues, therefore the burden never shifted to it to show the existence
    of a material fact issue exists. BBX claims that it pleaded the affirmative defenses
    of usage and trade and recoupment, and even if the burden shifted, it presented
    evidence that every other working interest owner paid or agreed to pay the prospect
    development costs. BBX further asserts that GeoSouthern failed to bring forth any
    evidence other than the agreements and Dahmann’s affidavit, which BBX maintains
    is conclusory.
    GeoSouthern pleaded claims for declaratory judgment pursuant to Texas Civil
    Practice and Remedies Code Chapter 37 and sought among other things,
    declarations: 11 (1) “determining amounts lawfully owed under the Subject Contracts
    and Rule 11 Agreement, including production revenues, JIBs, Unproposed Well
    11
    GeoSouthern’s fourth amended petition contained the same claims for
    declaratory relief as the third amended petition. The third amended petition was the
    live pleading when it filed its first motion for partial summary judgment, and the
    fourth amended petition was the live pleading when GeoSouthern filed its motion
    for final summary judgment, which incorporated the trial court’s rulings from the
    first summary judgment.
    33
    Costs and related charges. Such determination should also include an accounting of
    all amounts billed and paid by GeoSouthern, including cash call prepayments;” 12 (2)
    “an election by AFI to go non-consent on BBX’s Turkey Creek Well Proposal under
    the Neches II AMI Agreement results in no obligation for AFI to pay the Unproposed
    Well Costs for that prospect, and specifically that AFI did elect to go non-consent
    on the Turkey Creek Well Proposal and therefore has no obligation to pay either
    Unproposed Well Costs or Well AFE[;]” (3) “[t]he AMI Agreements, Rule 11
    Agreement and Subject Contracts do not authorize BBX to withhold revenue
    payments, offset or net against revenue payments in connection with the Unproposed
    Well Costs. To the extent BBX has limited authority under the JOAs to offset/net
    JIBs against revenue payments (as opposed to Unproposed Well Costs), such
    authority is limited to offsetting/netting for specific JIB charges owed under the
    applicable joint operating agreement against revenue payments from wells governed
    by such joint operating agreement.”
    When a cause of action seeks a declaratory judgment of a contract’s
    construction, the only evidence of the contract’s interpretation may be the contract
    itself. See Piranha Partners v. Neuhoff, 
    596 S.W.3d 740
    , 743–44 (Tex. 2020) (an
    unambiguous contract’s meaning is determined as a matter of law, looking to the
    12
    GeoSouthern’s petitions defined “Subject Contracts” as “certain joint
    operating agreements and related development agreements” between GeoSouthern
    and BBX.
    34
    parties’ intent as expressed in the written agreement); IE.Com Ltd. v. Peeler, No. 05-
    19-00496-CV, 
    2020 WL 3424913
    , at *3 (Tex. App.—Dallas June 23, 2020, no pet.)
    (mem. op.) (noting that in a declaratory action regarding contract construction, the
    only evidence may be the contract itself). No party asserts that the Subject Contracts
    are ambiguous. With its first motion for partial summary judgment, GeoSouthern
    included the relevant JDAs and Rule 11 Agreement, “Cash Call” letters, BBX’s
    Turkey Creek Well Proposal dated August 2015, and AFI’s election to “go non-
    consent” in response to the Turkey Creek Well Proposal. With its motion for final
    summary judgment, GeoSouthern included these same documents and the JOAs. In
    the absence of any claim of ambiguity, these contracts alone can conclusively
    establish the parties’ rights. See Piranha Partners, 596 S.W.3d at 743–44. The
    construction of an unambiguous contract is a question of law for the court. Tawes v.
    Barnes, 
    340 S.W.3d 419
    , 425 (Tex. 2011). When discerning the parties’ intent, we
    examine the entire agreement, giving effect to each provision so that none is
    rendered meaningless. See 
    id.
    GeoSouthern requested that the trial court determine the parties’ rights under
    the Subject Contracts and Rule 11 Agreement. The “Cash Call” letters indicate they
    were sent under the Make My Day JDA and Neches II AMI Agreements,
    respectively. The applicable provisions in these agreements make clear that they
    governed the parties’ relationships before a JOA came into place and that to the
    35
    extent the JOA was inconsistent with the Make My Day JDA or the Neches II JDA,
    the JDAs would supersede.
    The Neches II JDA, the agreement covering the Turkey Creek Well Proposal,
    addressed leasehold acquisitions and well proposals in a defined area. The Neches
    II JDA did not limit leasehold acquisitions to BBX. Instead, any party to the
    agreement could be an acquiring party, and while the agreement required “acquiring
    parties” to complete title and curative work, the agreement also stated that the parties
    to the agreement “shall have the right to participate in any acquisitions within the
    AMI[.]” With respect to leasehold acquisitions, the Neches II required the acquiring
    party to give written notice within thirty (30) days of completing such acquisition to
    the other parties and provide them with a “complete description of the Lease(s) or
    Farmout Agreement(s) acquired and a copy of the Instrument(s) by which such
    interest was acquired and all other pertinent information, including the number of
    gross and net lease acres, the costs incurred in making the acquisition . . . .”
    (Emphasis added.) The contract further provides that “[i]f the election is to
    participate in the purchase of a Lease, the notice of election shall be accompanied
    by a check for the cost of the proportionate interest such Party elects to take based
    upon the costs specified in the original notice.” (Emphasis added.) The clear and
    unambiguous language of the agreement provides for the parties’ right to participate
    by way of election. The conditional language makes clear that sending a check for
    36
    the proportionate share of costs was to occur if the party elected to participate. The
    contract notes that the parties shall have the “right” to participate rather than the
    “obligation” to participate. The Neches II AMI also provided a consequence for
    parties electing not to participate in leasehold acquisitions: a party’s “[f]ailure to
    timely deliver a written election to purchase (and payment) or to participate will
    constitute a conclusive relinquishment of the right to acquire an interest in the
    Lease[.]” Pursuant to the Neches II JDA Well Proposals likewise could be submitted
    by any party and gave the parties the right to “elect” to participate.
    Unlike the Neches II, the Make My Day JDA provided that BBX “will have
    the sole option to propose units and wells in the defined areas[]” and that “[w]ell
    proposals will be proposed under the terms and conditions of section B of this
    Agreement and shall be governed by the terms of the JOA attached hereto and made
    a part hereof as Exhibit B.” The Make My Day JDA also required written notice of
    well proposals and “such notice will contain the surface location of the well, the
    objective depth of the well and an estimate of the cost of drilling and completing the
    well for production.” The Make My Day JDA stated as follows:
    The parties receiving the Initial Well proposal shall have thirty (30)
    days after receipt of the proposal to notify the proposing party, in
    writing, whether they elect to participate in the cost of the Initial Well
    (“Participating Parties”) or elect to relinquish their interest in the
    proposed well, and all future well(s) proposals, along with rights to any
    future leasehold purchased, within the proposed unit area. All parties
    electing to participate in the Initial Well will immediately execute and
    return the Operating Agreement provided in the proposal. If one (1) or
    37
    more Parties elect not to participate in the Initial Well, then the
    proposing party shall give written notice of same to those Participating
    Parties within twenty (20) days following the expiration of the thirty
    (30) day election period set forth above. The Participating Parties shall
    then have the option for ten (10) days, following receipt of such written
    notice to elect to participate for their proportionate share of the interest
    available.
    With respect to leasehold acquisitions, the Make My Day JDA provided that
    any interest 13 acquired by any party within the defined AMI “shall be offered to the
    other Parties” to the agreement. Further,
    [t]he Party acquiring any such Interest (“Notifying Party”) shall notify
    the other Parties (“Receiving Parties”) in writing within 30 days of
    completing such acquisition and shall provide the Receiving Parties
    with a Lease Purchase Report containing a complete description of the
    Lease(s) acquired or a copy of the Farmout Agreement entered into,
    including the number of gross and net lease acres, the costs incurred in
    making the acquisition, the amount of any known overriding royalties
    or other existing lease burdens affecting the Interest, the obligations
    associated with or required to earn such Interest, a mineral ownership
    report, and a copy of any agreements(s) by which the Leases were
    acquired, including the Oil and Gas Lease, filed Memorandum of Oil
    and Gas Lease, and any electronic shape files or other plat identifying
    the acquisition. For thirty (30) days from receipt of notice, the
    Receiving Parties shall have the right to acquire their Participating
    Interest (hereinafter defined) share in such Leases(s) or Farmout
    Agreement by providing written notice to the Notifying Party within
    such 30 day period accompanied by a check or wire transfer to the
    Notifying Party’s bank account for the cost of all of its Participating
    Interest based upon the costs specified in the original notice. If the
    election to participate in a Farmout Agreement is made by any of the
    Receiving Parties, it shall send its notice of election to the Notifying
    Party and shall include an agreement to assume and be bound by the
    obligations imposed by the Farmout Agreement to the extent of all of
    the Receiving Parties’ Participating Interests. Failure to timely deliver
    13
    Interest was defined as “Leases” in Section C of the agreement.
    38
    a written election to purchase or to participate as required above or the
    failure to pay for the cost of the Participating Interest at the time the
    written election is delivered will constitute a conclusive relinquishment
    of all of the right to acquire an interest in the Lease or to participate in
    the Farmout Agreement.
    (Emphasis added.)
    We are cognizant that our primary concern is to give effect to the parties’
    intent as expressed in the contract by considering the entire agreement and
    harmonizing all provisions so none are rendered meaningless. See Seagull Energy
    E&P, Inc. v. Eland Energy, Inc., 
    207 S.W.3d 342
    , 345 (Tex. 2006). To adopt BBX’s
    position would render these election provisions meaningless. See 
    id.
     The JDAs
    provided consequences of non-participation or non-consenting to leasehold
    acquisitions or drilling, whether that non-consent was an affirmative written election
    or a deemed non-consent for failure to timely provide a written election to consent.
    The express and clear consequence provided in these agreements did not include
    BBX’s offsetting or netting revenues, rather the consequence was the loss of the
    party’s right to participate in future drilling or leasehold acquisitions under the
    agreements. See 
    id.
     (explaining that dispute under a JOA turned on whether the
    parties expressly agreed upon consequences of election). Even though BBX sent the
    “Cash Call” letters with express language citing the JDAs, BBX creatively attempted
    to carve out the costs from the agreements by calling them “prospect development
    costs.” The “Cash Call” letters also stated that if the GeoSouthern entity elected not
    39
    to pay their share of expenses, they will be deemed to have elected not to participate
    in future drilling or leaseholds. This was consistent with the language contained in
    the Subject Contracts that the consequence for electing not to pay the costs resulted
    in a forfeiture of the right to participate in future drilling or leasehold acquisition
    rather than BBX having the right to withhold, net, or offset revenues from already
    producing wells. Finally, the Rule 11 Agreement unconditionally required BBX to
    pay GeoSouthern its revenues and was devoid of any mention of “Cash Call” costs.
    BBX contends on appeal that it pleaded usage of trade and recoupment, and
    the fact that all other working interest owners agreed to pay the “Cash Call” costs
    created a fact issue. “[W]hen a contract is unambiguous, we do not consider outside
    evidence, including industry custom and usage, to alter or contradict the terms.”
    Barrow-Shaver Res. Co. v. Carrizo Oil & Gas, Inc., 
    590 S.W.3d 471
    , 486 (Tex.
    2019) (citing URI, Inc. v. Kleberg Cty., 
    543 S.W.3d 755
    , 757-58 (Tex. 2018); Nat’l
    Union Fire Ins. of Pittsburgh v. CBI Indus., Inc., 
    907 S.W.2d 517
    , 520-21 (Tex.
    1995) (per curiam)). Likewise, an unambiguous contract silent as to an immaterial,
    non-essential term, requires no further supplementation. 
    Id.
     We decline to
    supplement clear and easily understood provisions with extrinsic evidence. See 
    id.
    We overrule this issue.
    40
    C. Issue Three: Quantum Meruit and BBX’s Expenses
    BBX argues that the trial court erred by granting summary judgment in favor
    of GeoSouthern regarding BBX’s quantum meruit claim for prospect development
    costs. BBX contends that GeoSouthern failed to meet its summary judgment burden
    to prove its affirmative defense of express contract. BBX asserts that the trial court
    erred by concluding the Neches II and Make My Day JDAs expressly addressed
    recovery of the expenses sought.
    A party may plead breach of contract and quantum meruit as alternate theories
    of recovery. See Tex. R. Civ. P. 48. Generally, though, the existence of an express
    contract covering the subject matter of the dispute precludes recovery in quantum
    meruit. See In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 732
    , 740 (Tex. 2005);
    see also Hill v. Shamoun & Norman, LLP, 
    544 S.W.3d 724
    , 733 (Tex. 2018).
    “Whether an express contract covers the services at issue is a legal question
    for the court.” Young v. Dimension Homes, Inc., No. 01-14-00331-CV, 
    2016 WL 4536407
    , at *3 (Tex. App.—Houston [1st Dist.] Aug. 30, 2016, no pet.) (citation
    omitted). If the evidence shows that no contract covers the services at issue, then the
    question of the party’s recovery in quantum meruit is for the trier of fact. See Gulf
    Liquids New River Project, LLC v. Gulsby Eng’g, Inc., 
    356 S.W.3d 54
    , 70 (Tex.
    App.—Houston [1st Dist.] 2011, no pet.).
    41
    In addition to the written JDAs, GeoSouthern submitted BBX’s “Cash Call”
    letters for unproposed development costs in support of its motion for summary
    judgment. The “Cash Call” letters contained language that either of the applicable
    JDAs “allows BBX Operating LLC to Cash Call partners for the expenses incurred
    for brokers fees, title examination, title curative and other expenses incurred for
    preparing tracts of land to be included in a future Drilling Unit(s).” The evidence
    supporting GeoSouthern’s second motion for partial summary judgment also
    included Gaines’s deposition testimony. Gaines testified that the prospect
    development costs or unproposed well costs “are owed pursuant to the underlying
    AMI agreements as costs that were incurred by BBX Operating on behalf of the non-
    op partners primarily for title, curative – title examination, curative expenses.”
    This evidence established that BBX’s representatives sent the “Cash Calls”
    pursuant to the express contracts. Most importantly, the plain language of the
    agreements covered the services that BBX tried to recover via “Cash Calls.” Those
    agreements unequivocally contained election provisions whereby the working
    interest owners could choose to participate in the costs, and if so, they reaped the
    rewards when a well produced. Their election not to participate resulted in the
    consequence of forfeiture of future participation rights.
    The summary judgment record supports the trial court’s determination that
    GeoSouthern conclusively established that the Neches II and Make My Day JDA
    42
    contracts expressly covered the services at issue and therefore, barred BBX’s
    quantum meruit recovery. 14 See Fortune Prod. Co. v. Conoco, Inc., 
    52 S.W.3d 671
    ,
    684–85 (Tex. 2000) (no recovery under a quasi-contract or unjust enrichment theory
    where valid express contract covers the subject matter of parties’ dispute). We
    overrule BBX’s third issue.
    D. Issue Four: Dismissal of BBX’s Counterclaim for Promissory Estoppel
    BBX advances several arguments challenging the trial court’s dismissal of its
    promissory estoppel claim, which GeoSouthern affirmatively addressed in its final
    motion for summary judgment. For the reasons explained above, the JDAs were
    express contracts covering the subject matter of the “Cash Call” costs sought by
    BBX and expressly provided for therein. If a valid contract covers the alleged
    promise, the plaintiff cannot recover for the promise under promissory estoppel.
    Fertic v. Spencer, 
    247 S.W.3d 242
    , 250 (Tex. App.—El Paso 2007, pet. denied); see
    also Subaru of Am., Inc. v. David McDavid Nissan, Inc., 
    84 S.W.3d 212
    , 226 (Tex.
    2002) (promissory estoppel doctrine presumes no contract exists); Fortune Prod.
    Co., 52 S.W.3d at 684 (Tex. 2000). BBX’s promissory estoppel claim is barred as a
    matter of law because an express contract governs the subject matter of the parties’
    dispute. We overrule issue four.
    14
    Having concluded express contracts cover the services at issue, thus barring
    recovery under this theory, we do not address the evidence of the individual quantum
    meruit elements. See Tex. R. App. P. 47.1.
    43
    E. Issue Five: TNRC Claim
    In its fifth issue, BBX contends that GeoSouthern failed to prove its Texas
    Natural Resource Code claim as a matter of law. Texas Natural Resource Code
    sections 91.402 and 91.403 require a payor of oil and gas revenues to pay interest to
    the payee if the revenue payments are not paid timely. See 
    Tex. Nat. Res. Code Ann. § 91.402
    (a) (requiring timely payment), § 91.403(a) (requiring payment of interest);
    Valence Operating Co. v. Anadarko Petroleum Corp., 
    303 S.W.3d 435
    , 445 (Tex.
    App.—Texarkana 2010, no pet.) (discussing Texas Natural Resources Code
    provisions governing timely payment of revenues). Pre-suit notice is a condition
    precedent to instituting a legal action under these provisions. See 
    id.
     § 91.404(a)
    (requiring written notice as a prerequisite to beginning judicial action against
    nonpayor for nonpayment).
    BBX seems to complain about the adequacy of GeoSouthern’s pre-suit notice
    and that the Rule 11 Agreement was insufficient evidence to establish
    GeoSouthern’s entitlement to revenue payments under the statute. BBX further
    argues that it has raised a fact issue about whether GeoSouthern’s demand was
    satisfied by the Rule 11 Agreement or by BBX’s payment of the amounts owed in
    satisfaction of the demand.
    GeoSouthern’s summary judgment evidence included a December 2015 letter
    sent to BBX wherein it notified BBX of non-payment of revenues that BBX had
    44
    wrongfully withheld and cited to the pertinent Texas Natural Resource Code
    provisions. GeoSouthern subsequently filed suit to collect those revenues. The
    summary judgment evidence also included the executed Rule 11 Agreement wherein
    BBX agreed to pay revenues it owed GeoSouthern on a specific timeline. BBX’s
    argument that because GeoSouthern agreed to accept an amount different than the
    demand letter and BBX’s payment of a portion of the revenues precluded the
    recovery under the Texas Natural Resources Code lacks merit. The evidence shows
    that while BBX may have paid an initial sum that addressed the amounts of revenues
    when GeoSouthern sent the demand, BBX had an ongoing obligation to pay
    revenues pursuant to the Rule 11 Agreement on a set schedule. Despite making an
    initial payment, BBX’s corporate representative admitted BBX continued to
    withhold revenues after the parties entered into the Rule 11 Agreement. Moreover,
    the evidence established the prejudgment interest amount GeoSouthern sought was
    limited to those additional revenue amounts that BBX had not paid and was
    consistent with the Principal Amount of $2,659,473.20. We overrule this issue.
    F. Issue Six: Prejudgment Interest
    In its sixth issue, BBX challenges the trial court’s award of prejudgment
    interest. In its motion for final summary judgment, GeoSouthern moved for
    prejudgment interest under Texas Finance Code section 302.002 and Texas Natural
    Resources Code section 91.403(a). See 
    Tex. Fin. Code Ann. § 302.002
    ; Tex. Nat.
    45
    Res. Code Ann. § 91.403(a). The trial court awarded prejudgment interest at a rate
    of six percent pursuant to Texas Finance Code section 302.002. 15 BBX argues a
    question of fact existed regarding the “Murphy Amount,” which put the total
    principal amount in question, and therefore, GeoSouthern failed to conclusively
    establish its entitlement to prejudgment interest on any theory.
    As explained above, the trial court decided as a matter of law whether BBX
    lawfully withheld the “Murphy Amount” by interpreting the Rule 11 Agreement and
    the applicable JDAs. The trial court determined BBX improperly withheld the
    “Murphy Amount,” and the Subject Principal Amount of $2,659,473.20 was readily
    ascertainable given the summary judgment evidence. GeoSouthern provided
    prejudgment interest calculations in Post’s affidavit with supporting documentation
    including the “Murphy Amount” and without the “Murphy Amount.” The
    prejudgment interest calculation did not include the initial amount BBX paid
    pursuant to the Rule 11. Rather, the calculation only included the amounts for the
    payment of ongoing revenues BBX failed to pay.
    15
    A Texas Natural Resources Code claim allows a payee to recover
    prejudgment interest. See 
    Tex. Nat. Res. Code Ann. § 91.403
    (a). In its brief, BBX
    incorrectly states that the trial court awarded pre-judgment interest under both the
    Texas Natural Resources Code and the Finance Code, in the alternative. This is
    incorrect. Although the trial court’s Order noted that GeoSouthern was entitled to
    prejudgment interest at the rate of six percent under the Texas Finance Code section
    302.002 and, in the alternative, the rates specified under Texas Natural Resources
    Code section 91.403, the trial court only awarded pre-judgment interest at the
    Finance Code rate of six percent. See 
    Tex. Fin. Code Ann. § 302.002
    .
    46
    Texas Finance Code section 302.002 provides as follows:
    If a creditor has not agreed with an obligor to charge the obligor any
    interest, the creditor may charge and receive from the obligor legal
    interest at the rate of six percent a year on the principal amount of the
    credit extended beginning on the 30th day after the date on which the
    amount is due. If an obligor has agreed to pay to a creditor any
    compensation that constitutes interest, the obligor is considered to have
    agreed on the rate produced by the amount of that interest, regardless
    of whether that rate is stated in the agreement.
    
    Tex. Fin. Code Ann. § 302.002
    . The Texas Finance Code defines “creditor” as “a
    person who loans money or otherwise extends credit. The term does not include a
    judgment creditor.” 
    Id.
     § 301.002(a)(3). A “loan” is defined as “an advance of
    money that is made to or on behalf of an obligor, the principal amount of which
    the obligor has an obligation to the pay the creditor. The term does not include a
    judgment.” Id. § 301.002(a)(10). An obligor is “a person to whom money is loaned
    or credit is otherwise extended. The term does not include . . . a judgment
    debtor[.]” Id. § 301.002(a)(13); see Smith v. Huston, 251 S.W.3d. 808, 827–28 (Tex.
    App.—Fort Worth 2008, pet. denied) (discussing statutory definitions and
    applicability of 302.002). The summary judgment record in this case does not
    include any evidence establishing that GeoSouthern is a creditor as that term is
    defined in the Finance Code, that it loaned money to BBX, or that BBX had credit
    extended to it by GeoSouthern. The trial court erred by awarding prejudgment
    interest under Texas Finance Code section 302.002 at a rate of six percent pursuant
    47
    when the evidence did not establish that GeoSouthern met the statutory definition of
    a creditor.
    GeoSouthern pleaded in the alternative that it was entitled to prejudgment
    interest pursuant to Texas Natural Resources Code section 91.403. See 
    Tex. Nat. Res. Code Ann. § 91.403
    (a). Although the trial court did not award prejudgment
    interest under Texas Natural Resource Code, the trial court determined, in the
    alternative, that GeoSouthern established its entitlement to prejudgment interest in
    accordance with that provision. The Texas Natural Resources Code requires that
    “proceeds derived from the sale of oil or gas production from an oil or
    gas well located in this state . . . must be made to each payee on a timely
    basis according to the frequency of payment specified in a lease or other
    written agreement between payee or payor.”
    See 
    Tex. Nat. Res. Code Ann. § 91.402
    (a). The Rule 11 Agreement expressly
    provided that BBX agreed to pay the previous month’s revenues by the 25th day of
    each month, which it failed to do. See 
    id.
     BBX’s failure to pay the revenues in a
    timely manner entitled GeoSouthern to the recovery of prejudgment interest at the
    specified statutory rate. See 
    id.
     § 91.403(a). As explained elsewhere in this opinion,
    BBX does not contest that it owed GeoSouthern revenues or that it failed to pay
    these revenues. Moreover, the trial court determined as a matter of law that BBX
    improperly withheld the “Murphy Amount.” GeoSouthern is entitled to prejudgment
    interest as specified in the Texas Natural Resources Code.
    48
    We sustain issue six as it applies to the recovery of prejudgment interest under
    Texas Finance Code section 302.002 but overrule it with respect to recovery of
    prejudgment interest pursuant to Texas Natural Resource Code section 91.403.
    G. Issue Seven: Attorney’s Fees
    In its final issue, BBX challenges the trial court’s award of attorney’s fees. 16
    GeoSouthern moved for summary judgment on the issue of attorney’s fees,
    requesting the total amount of $550,060, which the trial court awarded by splitting
    it among the three GeoSouthern entities based upon the Principal Amount awarded
    to each. The trial court also awarded conditional attorney’s fees in the event BBX
    appealed. 17 The trial court’s order further reflected that GeoSouthern was entitled to
    recovery of “reasonable and necessary” attorney’s fees from BBX pursuant to Texas
    Civil Practice and Remedies Code Chapter 37 and Texas Natural Resources Code
    section 91.406. In support of this issue, BBX asserts that: (1) a fact issue exists as to
    the reasonableness of the amount of attorneys’ fees; (2) since it is a limited liability
    company, no attorneys’ fees can be awarded against it pursuant to Texas Civil
    16
    BBX’s controverting affidavit does not mention the anticipated fees
    awarded in the event of an appeal, and those fees remain uncontested. See Cammack
    the Cook, L.L.C. v. Eastburn, 
    296 S.W.3d 884
    , 895 (Tex. App.—Texarkana 2009,
    pet. denied) (noting failure to mention anticipated fees awarded in the event of an
    appeal meant “those fees remain uncontested”).
    17
    Although the Order indicated that GeoSouthern was entitled to the $550,060
    in “reasonable and necessary” fees, the individual amounts the trial court awarded
    to the three entities totaled $550,039.99.
    49
    Practice and Remedies Code chapter 38; (3) “a declaratory judgment plea does not
    transform an unviable Chapter 38 claim for attorneys’ fees into a viable one[;]” and
    (4) the trial court erred in awarding attorneys’ fees under the Texas Natural
    Resources Code for the same reasons damages are not recoverable.
    Texas follows the American Rule, which provides that a prevailing party has
    no inherent right to recover attorney’s fees from the non-prevailing party absent
    specific statutory or contractual authority allowing it. See Rohrmoos Venture v.
    UTSW DVA Healthcare LLP, 
    578 S.W.3d 469
    , 487 (Tex. 2019); In re Nat’l Lloyds
    Ins. Co., 
    532 S.W.3d 794
    , 809 (Tex. 2017) (orig. proceeding).
    [T]o secure an award of attorney’s fees from an opponent, the
    prevailing party must prove that: (1) recovery of attorney’s fees is
    legally authorized, and (2) the requested attorney’s fees are reasonable
    and necessary for the legal representation, so that such an award will
    compensate the prevailing party generally for its losses resulting from
    the litigation process.
    Rohrmoos Venture, 578 S.W.3d at 487.
    1. Authorization for Attorney’s Fees
    At issue in this case is statutory authorization for attorney’s fees. Texas
    Natural Resources Code section 91.406 provides that for suits filed under that
    subchapter, “the court shall include in any final judgment in favor of the plaintiff an
    award of . . . reasonable attorney’s fees.” 
    Tex. Nat. Res. Code Ann. § 91.406
    (1).
    GeoSouthern filed a claim pursuant to this subchapter, and this provision provides
    the statutory authority for recoupment of GeoSouthern’s reasonable attorney’s fees.
    50
    See 
    id.
     The use of “shall” indicates that such an award is required should the plaintiff
    receive a judgment in its favor, as GeoSouthern did here. See 
    id.
    GeoSouthern filed for a declaratory judgment seeking interpretation of the
    parties’ written agreements and responsibilities thereunder, including the JDAs and
    Rule 11 Agreement. The trial court entered judgment in GeoSouthern’s favor and
    determined GeoSouthern was entitled to its reasonable attorney’s fees pursuant to
    Texas Civil Practice and Remedies Code Chapter 37. Under the Uniform
    Declaratory Judgment Act, “the court may award costs and reasonable and necessary
    attorney’s fees as are equitable and just.” 
    Tex. Civ. Prac. & Rem. Code Ann. § 37.009
    . To be entitled to recover fees under the UDJA, “[t]he declaratory judgment
    claim must do more ‘than merely duplicate the issues litigated’ via the contract or
    tort claims.” Etan Indus., Inc. v. Lehmann, 
    359 S.W.3d 620
    , 624 (Tex. 2011)
    (quoting MBM Fin. Corp. v. Woodlands Operating Co., 
    292 S.W.3d 660
    , 669 (Tex.
    2009)). In other words, where a claim for declaratory relief is merely “tacked onto”
    other claims that do not allow for the recovery of fees, permitting the recovery of
    fees pursuant to the UDJA would defeat the rule that specific provisions prevail over
    general. See 
    id.
    Here, we cannot say that GeoSouthern’s claims for declaratory relief simply
    repleaded its breach of contract action. Although the issues were intertwined,
    GeoSouthern’s breach of contract claim dealt with the recovery of its revenues,
    51
    which necessarily implicated BBX’s offsetting JIB amounts, whereas the claims for
    declaratory relief primarily dealt with the questionable “Cash Calls” for “prospect
    development” or “unproposed well costs.” In theory, those declarations resolve
    BBX’s ability to rightfully net or offset those amounts against revenues and the
    viability of BBX’s counterclaims for breach of contract. Moreover, GeoSouthern’s
    Texas Natural Resources claim for revenue payments permitted the recovery of
    attorney’s fees. Thus, the claims were not merely “tacked onto” other claims that did
    not permit recovery of fees.
    The trial court correctly concluded that Texas Natural Resources Code section
    91.406 and Texas Civil Practice and Remedies Code section 37.009 statutorily
    authorized GeoSouthern to recover attorney’s fees. 18
    2. Reasonableness
    We next determine whether such fees were reasonable. BBX contends a fact
    issue exists as to the reasonableness of the fees. The reasonableness of attorney’s
    fees is generally a fact question. See, e.g., Bocquet v. Herring, 
    972 S.W.2d 19
    , 21
    (Tex. 1998). However, it is settled that “the affidavit of the attorney representing a
    claimant constitutes expert testimony that will support an award of attorney’s fees
    in a summary judgment proceeding.” Haden v. David J. Sacks, P.C., 
    332 S.W.3d 18
    As the trial court’s final Order does not reflect that such fees were
    recoverable pursuant to Chapter 38 of the Texas Civil Practice and Remedies Code,
    we do not address this issue. See Tex. R. App. P. 47.1.
    52
    503, 513 (Tex. App.—Houston [1st Dist.] 2009, pet. denied); Tesoro Petroleum
    Corp. v. Coastal Refining & Mktg., Inc., 
    754 S.W.2d 764
    , 767 (Tex. App.—Houston
    [1st Dist.] 1988, writ denied). If a movant presents expert testimony in support of
    attorney’s fees, the burden shifts to the non-movant to raise a fact issue. Jordan v.
    Centerpoint Energy Hous. Elec., LLC, No. 14-18-00663-CV, 
    2019 WL 5565978
    , at
    *10 (Tex. App.—Houston [14th Dist.] Oct. 29, 2019, pet. denied) (mem. op.).
    Absent controverting evidence, the movant’s affidavit will support summary
    judgment. Id.; Tesoro, 754 S.W.2d at 767. “If an attorney’s affidavit regarding fees
    is properly controverted by an opposing attorney, a fact issue is raised on
    reasonableness and summary judgment is precluded.” Sun Tec Computer, Inc. v.
    Recovar Grp., LLC, No. 05–14–00257–CV, 
    2015 WL 5099191
    , at *5 (Tex. App.—
    Dallas Aug. 31, 2015, no pet.) (mem. op.); see also Jordan, 
    2019 WL 5565978
    , at
    *10.
    GeoSouthern’s summary judgment evidence supporting its request for
    attorneys’ fees included the affidavit of GeoSouthern’s attorney, along with itemized
    billing records and invoices. He explained his experience, his familiarity with the
    case and subject matter, the hourly rate charged explaining that it was reasonable
    considering the location and subject matter of the litigation. He also described the
    various claims in the litigation, the tasks performed, and the billing records showed
    who worked on what tasks, how long each worked on the task, and the hourly rate
    53
    each charged. He outlined the lodestar factors and averred he considered them in
    determining the reasonable hourly rate. See El Apple I, Ltd. v. Olivas, 
    370 S.W.3d 757
    , 761-63 (Tex. 2012) (discussing lodestar method). He also averred the total
    number of hours reasonably worked on the litigation and that $550,060 was a
    reasonable fee for the work performed. 19 The billing records also specified with great
    particularity the individual tasks performed, the length of time each took, the person
    working on the task, and the rate of the billing individual.
    To constitute competent summary judgment evidence, an affidavit must be
    based on personal knowledge, set forth facts that would be admissible in evidence,
    and affirmatively show the affiant’s competence to testify as to the matters contained
    therein. Tex. R. Civ. P. 166a(f). BBX’s counsel included a controverting affidavit in
    its summary judgment response. BBX’s attorney described his qualifications,
    experience, and stated he knew the history of the case. He also averred that it was
    his opinion that GeoSouthern’s fees were not reasonable and necessary. Although
    he did not specifically contest the reasonableness of the $350 hourly rate, the
    affidavit contained testimony that the total sum of $550,060 was unreasonable given
    the causes of action involved. As a basis for this, BBX’s attorney averred that the
    19
    While the affidavit stated GeoSouthern’s attorneys spent more than 2,000
    hours working on the file, the affidavit also stated that “1,571.6 hours is a reasonable
    amount of time for attorneys providing similar services to have spent[]” and
    multiplied that by a “reasonable hourly” rate of $350, which provided the $550,060
    figure.
    54
    billing invoices of GeoSouthern’s attorney contained duplicative entries and wholly
    unnecessary entries. He testified that
    [n]othing incurred evaluating, analyzing or conducting research on any
    claims for relief by BBX was reasonable or necessary to pursue any
    claims by GeoSouthern. Nothing pertaining to Trinity River Resources’
    bankruptcy proceeding or dealings with any party’s bankruptcy counsel
    was reasonably or necessarily incurred to prosecute a breach of
    contract, declaratory judgment action or claim under the TNRC.
    Nothing incurred pursuing the separate garnishment action was
    reasonable or necessary to pursue the claims in this case.
    Finally, BBX’s counsel averred that the number of depositions taken in the case was
    less “compared to most cases that have lasted this long.”
    The controverting affiant noted his legal experience generally and his
    experience with this specific case. Likewise, he averred the statements were based
    on his personal knowledge. Although he did not point to specific time entries, he
    based his dispute regarding the reasonableness of GeoSouthern’s fee on particular
    tasks    GeoSouthern    performed    and    challenged   whether    they   advanced
    GeoSouthern’s claims. The expert’s specific complaint that tasks performed
    defending BBX’s counterclaims are unavailing as a matter of law. See, e.g., Tony
    Gullo Motors I, L.P. v. Chapa, 
    212 S.W.3d 299
    , 314 (Tex. 2006) (explaining that
    some recoverable and non-recoverable tasks are so intertwined as a matter of law
    that they cannot be segregated and to prevail on a contract claim a party must
    overcome all affirmative defenses like prior material breach, and the opposing party
    who raises them should not be allowed to suggest to the jury that overcoming those
    55
    defenses was unnecessary). Yet, we agree that work performed on a garnishment
    proceeding or other entities’ bankruptcy proceedings are not so clear cut. BBX’s
    controverting affidavit raised a genuine issue of material fact as to reasonableness
    and specifically, whether fees for certain tasks should have been segregated or were
    so interwoven with claims having recoverable attorney’s fees they could not be
    segregated. See 
    id.
     at 313–14 (“[O]nly when discrete legal services advance both a
    recoverable and unrecoverable claim that they are so intertwined that they need not
    be segregated.”). Given the existence of a genuine fact issue regarding the
    reasonableness of the attorney’s fees, remand is necessary. See Wich v. Fleming, 
    652 S.W.2d 353
    , 358 (Tex. 1983) (“the determination of the disputed fact issue of
    attorney’s fees was improper in a summary judgment proceeding.”). We sustain this
    issue.
    Conclusion
    We determine GeoSouthern conclusively established its breach of contract
    claim, declaratory judgment claim, and Texas Natural Resources claim.
    GeoSouthern was entitled to statutory prejudgment interest under Texas Natural
    Resources Code section 91.403. GeoSouthern further conclusively established that
    express contracts provided for recovery of payment for the services BBX sought in
    its “Cash Call” letters, precluding any recovery by BBX in quantum meruit and
    conclusively negating BBX’s right to recover under promissory estoppel. We
    56
    reverse the prejudgment interest award under Texas Finance Code section 302.002,
    and we remand to the trial court for a prejudgment interest calculation under Texas
    Natural Resources Code section 91.403. We reverse the attorney’s fees award and
    remand to the trial for further proceedings consistent with this opinion.
    AFFIRMED IN PART, REVERSED AND REMANDED IN PART.
    ________________________________
    CHARLES KREGER
    Justice
    Submitted on June 10, 2021
    Opinion Delivered July 29, 2021
    Before Kreger, Horton and Johnson, JJ.
    57