Trans-Vac Systems, LLC v. Hudson Insurance Company ( 2023 )


Menu:
  •                                    COURT OF APPEALS
    EIGHTH DISTRICT OF TEXAS
    EL PASO, TEXAS
    TRANS-VAC SYSTEMS, LLC,                           §               No. 08-22-00232-CV
    Appellant,         §                  Appeal from the
    v.                                                §            171st Judicial District Court
    HUDSON INSURANCE COMPANY,                         §             of El Paso County, Texas
    Appellee.          §              (TC# 2022-DCV-0258)
    MEMORANDUM OPINION
    This is an interlocutory appeal from an order denying a motion to compel arbitration filed
    by Appellant Trans-Vac Systems, LLC (Trans-Vac) in which it sought to arbitrate its dispute with
    Appellee Hudson Insurance Company (Hudson) arising under a performance bond that Hudson
    had issued to Trans-Vac’s subcontractor, MGB Group, Inc. (MGB), on a construction project. The
    bond itself did not contain an arbitration agreement, but the contract between Trans-Vac and MGB
    did, which was incorporated by reference into the performance bond. We conclude, however, that
    the parties’ arbitration agreement only applied to disputes between Trans-Vac and MGB arising
    under the terms of the construction contract and therefore did not bind Hudson to arbitrate disputes
    arising solely under the performance bond. And here, because the only dispute between the parties
    centered on Hudson’s affirmative defense that Trans-Vac was time-barred from seeking payment
    from Hudson under the terms of the bond itself, we agree with the trial court’s order denying Trans-
    Vac’s motion to compel arbitration.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    A. Trans-Vac and MGB enter into a subcontract
    Trans-Vac is a specialized contractor that provides and installs pneumatic waste collection
    and transport systems. In 2014, a general contractor (the Prime Contractor) that had been hired by
    the US Army Corps of Engineers to build a new healthcare complex at the Fort Bliss Army Base
    in El Paso, Texas (the Project) hired Trans-Vac to construct a pneumatic laundry service for the
    complex. In turn, Trans-Vac contracted with MGB “to perform a portion of the work . . . that had
    been assigned to Trans-Vac” for $600,000 (the Subcontract). The Subcontract contained various
    provisions requiring MGB to perform its work to Trans-Vac and the U.S. Army’s satisfaction in
    compliance with applicable laws and rules. It also explained the dispute resolution proceedings to
    be followed in the event of a dispute between the two parties, with arbitration governed by the
    Federal Arbitration Act (FAA) and under the American Arbitration Association’s (AAA) rules as
    the final step.
    B. Hudson issues its performance bond
    The Subcontract required MGB to furnish performance and payment bonds to Trans-Vac’s
    satisfaction. 1 In compliance therewith, in February of 2015, MGB entered into a “subcontract
    performance bond” agreement with Hudson as the surety (the Performance Bond). The
    Performance Bond provided that if Trans-Vac declared MGB in default, (1) Hudson could
    “promptly remedy the default subject to the provisions of paragraph 3 herein,” or (2) after
    reasonable notice to Hudson, Trans-Vac could arrange for the completion of MGB’s performance
    (or Hudson could demand that Trans-Vac complete the performance). If the latter option was
    chosen, and if Trans-Vac complied with its obligations under the bond, Hudson would be obligated
    1
    The contract provided that: “Subcontractor shall at its sole expense, on bond forms furnished by, and with a surety
    satisfactory to Contractor: (i) furnish a performance bond for the full amount of the sum identified in Exhibit A as
    security for the faithful performance of this Subcontract (the “Performance Bond”).”
    2
    to pay Trans-Vac its reasonable costs in completing MGB’s work to the extent the cost of
    completion exceeded the balance of the amount owed on the $600,000. Hudson also issued a
    subcontract labor and material payment bond to ensure payment to MGB’s subcontractors.
    C. Trans-Vac notifies MGB of its default and completes MGB’s work
    The record reflects that MGB completed a portion of its work, and Trans-Vac paid MGB
    $230,692 of the $600,000 contract amount. 2 However, MGB allegedly defaulted on its contractual
    obligations to Trans-Vac sometime prior to July 2016, shortly before MGB’s owner passed away.
    When Hudson learned of the possibility that MGB was in default—presumably due to MGB’s
    failure to pay its subcontractors—Hudson sent a letter to Trans-Vac dated July 15, 2016,
    demanding that Trans-Vac not further pay MGB without Hudson’s written consent. The record
    does not indicate whether Trans-Vac ever responded to this letter.
    On July 18, 2016, Trans-Vac sent a formal notice to MGB regarding its default under the
    Subcontract, giving it 24 hours to take corrective action. When MGB failed to take corrective
    action, Trans-Vac chose to complete the work through a different subcontractor and thereafter
    charge the costs of completion to MGB. 3 However, the record does not indicate that Trans-Vac
    notified Hudson of MGB’s default at that time.
    D. Hudson refuses Trans-Vac’s demand for payment
    Almost two years later, on March 5, 2018, Trans-Vac sent a letter formally notifying
    Hudson of MGB’s default and advising Hudson that it had hired another subcontractor to perform
    MGB’s remaining work on the Project. Trans-Vac enclosed the letter that it had sent to MGB in
    2
    The Subcontract required MGB to submit monthly payment applications for its work, and upon approval, Trans-
    Vac was to remit payment to MGB monthly. Final payment to MGB was dependent upon approval of the entities
    involved as well as upon the Prime Contractor’s payment to Trans-Vac.
    3
    The Subcontract provided that after notifying MGB of its default, Trans-Vac had the right to supply its own workers
    and materials to complete the agreed-upon work; to hire subcontractors to complete the work; or to withhold payment
    to MGB while giving MGB the opportunity to take “corrective action” to complete the work itself. If Trans-Vac
    completed the work itself or through subcontractors, the costs of doing so would be charged to MGB.
    3
    July of 2016 regarding its default, as well as an itemized statement reflecting that Trans-Vac had
    already paid MGB $230,692 of the agreed-upon $600,000 for its initial work but that it had cost
    Trans-Vac $1,058,966 to complete the remaining work. Trans-Vac therefore requested payment
    of its excess costs of $458,966, stating that this amount reflected the damages it incurred from
    MGB’s default.
    In response, on May 7, 2018, Hudson sent a letter to Trans-Vac, stating that it was assuming
    Trans-Vac had elected its remedy under the Subcontract to complete MGB’s work upon its default.
    However, Hudson advised Trans-Vac that because it had failed to provide Hudson with timely
    notice of MGB’s default, this “prejudiced Hudson from exercising its bargained-for-right to
    mitigate damages by arranging for the completion of the work under the Subcontract.” It further
    advised Trans-Vac that it had “voided the Bond” by failing to give Hudson timely notice and that
    Trans-Vac’s “claim on the bond must be denied.”
    It does not appear that Trans-Vac took any further action against Hudson at that time.
    Thereafter, according to Trans-Vac, the Project struggled with a number of delays unrelated to its
    own performance, and Trans-Vac did not receive final payment from the Prime Contractor on the
    Project until April of 2021.
    E. Trans-Vac demands arbitration
    In December of 2021, Trans-Vac filed a demand for arbitration against Hudson with the
    American Arbitration Association (AAA), seeking “damages stemming from [MGB’s] default and
    [Hudson’s] improper denial of the resulting claim and failure to reimburse [Trans-Vac].” Hudson,
    however, objected to the arbitration, and informed Trans-Vac and the AAA that it would not
    voluntarily participate in the arbitration. 4
    4
    Initially, Hudson objected to holding the arbitration in Colorado, where Trans-Vac was incorporated, but shortly
    thereafter objected to the arbitration in its entirety.
    4
    F. Hudson files suit and Trans-Vac counterclaims
    In January of 2022, Hudson filed its petition in the trial court seeking the following
    declaratory relief : “1) that Trans-Vac’s claim against Hudson’s performance bond is time-barred
    under the contractual limitations period set forth in the performance bond; and 2) that Trans-Vac’s
    claim against Hudson’s bond is not arbitrable because Hudson does not have an arbitration
    agreement with Trans-Vac and it is not a signatory to the alleged arbitration agreement [contained
    in the Subcontract] between Trans-Vac and MGB.” Hudson’s contention that Trans-Vac’s claim
    was time-barred centered on two provisions in the Performance Bond. First, it pointed to the
    provision stating that: “[a]ny suit under this bond must be instituted before the expiration of two
    years from date on which final payment under the subcontract falls due.” Second, it pointed to a
    rider that was attached to the Performance Bond, stating that Chapter 2253 of the Texas
    Government Code applied. The rider provided as follows:
    Notice of Applicability of Chapter 2253 of the Texas Government Code These
    bonds are furnished in an attempt to comply with Chapter 2253 of the Texas
    Government Code. These bonds shall be construed to comply with such Chapter
    regarding the rights created, limitations on those rights, and remedies provided.
    Any provision in the bonds to which this Rider is attached that expands or restricts
    a right or liability under such Chapter shall be disregarded, and such Chapter shall
    apply to these bonds.
    Hudson pointed out that a suit under a performance bond issued under Chapter 2253
    (relating to public work contracts) must be brought within one year after a contractor abandons a
    project. See TEX. GOV’T CODE ANN. § 2253.078 (a) (“[a] suit on a performance bond [under this
    Chapter] may not be brought after the first anniversary of the date of final completion,
    abandonment, or termination of the public work contract”). And Hudson argued that it was
    “undisputed that MGB abandoned the Project in June, 2016,” thereby rendering Trans-Vac’s
    claims “time-barred” as of June of 2017, or at the latest, June of 2018. Hudson therefore requested
    5
    a stay of the arbitration until its claim for declaratory relief could be resolved, as well as attorney’s
    fees and costs.
    Trans-Vac filed a response to Hudson’s petition and also filed a counterclaim against
    Hudson alleging a breach of contract for its failure to remit payment on the Performance Bond,
    while reserving its right to compel Hudson to arbitrate their dispute. Trans-Vac further opposed
    Hudson’s request to stay the arbitration. Hudson answered the counterclaim, raising several
    affirmative defenses, including the applicable statutes of limitations; Trans-Vac’s failure to
    mitigate damages; Trans-Vac’s alleged prior breach of contract; equitable estoppel; waiver; lack
    of causation; and lack of damages, in effect blaming Trans-Vac’s negligence for the extra costs
    that it incurred in completing the Project.
    G. Trans-Vac files a motion to compel arbitration
    Trans-Vac thereafter filed a motion to compel arbitration, arguing that Hudson was bound
    by the arbitration agreement in the Subcontract due to its incorporation by reference in the
    Performance Bond. Hudson opposed the motion, again arguing that it was not bound by the
    arbitration agreement as it was not a signatory to the agreement. Hudson further argued that the
    arbitration agreement only applied to disputes between Trans-Vac and MGB arising from MGB’s
    performance under the contract, and that the dispute between Trans-Vac and Hudson only related
    to Hudson’s defenses under the Performance Bond, i.e., whether Trans-Vac timely notified
    Hudson of MGB’s default to give Hudson the opportunity to remedy MGB’s default on its own,
    and whether Trans-Vac’s claim was time-barred under the terms of the Performance Bond due to
    its failure to bring suit in a timely manner as required by the Performance Bond.
    H. The trial court denies arbitration and Trans-Vac appeals
    In April of 2022, the trial court held a hearing on Trans-Vac’s motion to compel arbitration,
    together with Hudson’s motion to stay the arbitration. After the trial court notified the parties by
    6
    email that it intended to deny Trans-Vac’s motion to compel arbitration, Hudson nonsuited all of
    its claims against Trans-Vac “save and except the request for a declaration that Trans-Vac’s claim
    against the performance bond issued by Hudson for the subject project is time-barred by one or
    more applicable statutes or periods of limitations.” The trial court thereafter entered its order
    denying Trans-Vac’s motion to compel arbitration.
    This appeal followed. In one issue, Trans-Vac contends that the trial court erred by denying
    its motion to compel arbitration, arguing that Hudson was bound by the arbitration provisions in
    the Subcontract based on the Subcontract’s incorporation by reference in the Performance Bond.
    We disagree.
    II. STANDARD OF REVIEW AND APPLICABLE LAW
    A. Determining whether a dispute is subject to arbitration
    A party seeking to compel arbitration has the burden to prove that (1) a valid and
    enforceable arbitration agreement exists, and (2) the claims raised fall within that agreement’s
    scope. 5 J.M. Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 233 (Tex. 2003); see also Rachal v.
    Reitz, 
    403 S.W.3d 840
    , 843 (Tex. 2013); In re Rubiola, 
    334 S.W.3d 220
    , 223 (Tex. 2011).
    A trial court’s determination regarding the validity and scope of an arbitration agreement
    are questions of law that we review de novo. Baby Dolls Topless Saloons, Inc. v. Sotero, 
    642 S.W.3d 583
    , 586 (Tex. 2022) (whether an arbitration agreement is valid is reviewed de novo);
    Henry v. Cash Biz, LP, 
    551 S.W.3d 111
    , 115 (Tex. 2018) (whether a claim falls within the scope
    of a valid arbitration agreement is reviewed de novo).
    5
    Trans-Vac contends that our interpretation of the arbitration agreement should be governed by the FAA, as the
    agreement itself stated that the arbitration was to be governed by the FAA and because the parties are incorporated in
    different states. See In re ReadyOne Indus., Inc., 
    294 S.W.3d 764
    , 769 (Tex. App.—El Paso 2009, no pet.) (recognizing
    that the FAA may apply in both instances). As Hudson points out, however, even if the FAA were to apply, it only
    preempts state law to the extent the laws are in conflict. See In re D. Wilson Const. Co., 
    196 S.W.3d 774
    , 779
    (Tex. 2006) (holding that the FAA only preempts contrary state law not consonant state law (emphasis in the
    original)). Here, we see no conflict between the FAA and state law in terms of determining whether Hudson is bound
    to the Subcontract’s arbitration agreement.
    7
    The question of whether a valid and enforceable agreement exists includes proving that
    both parties consented to the agreement. See Aerotek, Inc. v. Boyd, 
    624 S.W.3d 199
    , 204
    (Tex. 2021). Thus, although the law generally favors arbitration, it does not create an obligation to
    arbitrate where none exists; arbitration is a “matter of consent, not coercion,” and a party may not
    be compelled to arbitrate where it has not consented to do so. See Volt Info. Scis., Inc. v. Bd. of
    Trs. of Leland Stanford Junior Univ., 
    489 U.S. 468
    , 478 (1989) (arbitration “is a matter of consent,
    not coercion”); see also In re Kellogg Brown & Root, Inc., 
    166 S.W.3d 732
    , 737 (Tex. 2005) (while
    there is a strong policy favoring arbitration, this policy does not apply to the initial determination
    of whether there is a valid arbitration agreement binding on a party). Therefore, despite “strong
    presumptions that favor arbitration, a valid agreement to arbitrate is a settled, threshold
    requirement to compel arbitration.” Kmart Stores of Tex., L.L.C. v. Ramirez, 
    510 S.W.3d 559
    , 564
    (Tex. App.—El Paso 2016, pet. denied).
    Once the moving party establishes a valid and binding arbitration agreement, a presumption
    exists that the parties’ dispute falls within the scope of the agreement, and “courts must resolve
    any doubts about an arbitration agreement’s scope in favor of arbitration.” See In re FirstMerit
    Bank, N.A., 
    52 S.W.3d 749
    , 754 (Tex. 2001); see also Rubiola, 334 S.W.3d at 225 (in determining
    the agreement’s scope, courts employ a “strong presumption in favor of arbitration”). Nonetheless,
    “the strong policy in favor of arbitration cannot serve to stretch a contractual clause beyond the
    scope intended by the parties or to allow modification of the unambiguous meaning of the
    arbitration clause.” Carter v. ZB, Nat’l Ass’n, 
    578 S.W.3d 613
    , 619 (Tex. App.—Houston
    [14 thDist.] 2019, no pet.); see also FD Frontier Drilling (Cyprus), Ltd. v. Didmon, 
    438 S.W.3d 688
    , 694 (Tex. App.—Houston [1st Dist.] 2014, pet. denied) (same); Gerwell v. Moran, 
    10 S.W.3d 28
    , 31 (Tex. App.—San Antonio 1999, no pet.) (same). In other words, “[e]ven the exceptionally
    strong policy favoring arbitration cannot justify requiring litigants to forego a judicial remedy
    8
    when they have not agreed to do so.” Carr v. Main Carr Dev., LLC, 
    337 S.W.3d 489
    , 496
    (Tex. App.—Dallas 2011, pet. denied) (citing E.E.O.C. v. Waffle House Inc., 
    534 U.S. 279
    ,
    293– 94 (2002).
    “Arbitration agreements are interpreted under traditional contract principles.” J.M.
    Davidson, Inc., 128 S.W.3d at 227. In determining the scope of an arbitration within a contract, a
    court “must examine and consider the entire writing in an effort to harmonize and give effect to
    all the provisions of the contract.” FirstMerit Bank, 52 S.W.3d at 754 (citing J.M. Davidson, 128
    S.W.3d at 229). Even though arbitration clause wording may be broad, language elsewhere in the
    agreement may limit its scope. Id. Moreover, in determining “whether a party’s claims fall within
    an arbitration agreement’s scope, we focus on the complaint’s factual allegations rather than the
    legal causes of action asserted.” FirstMerit Bank, 52 S.W.3d at 754; see also Rubiola, 334 S.W.3d
    at 224–26.
    B. Determining whether an arbitration agreement binds a nonsignatory
    Normally, because arbitration is contractual in nature, only parties to an arbitration
    agreement can be compelled to arbitrate. See Kellogg, 166 S.W. 3d at 737–39 (citing Bridas
    S.A.P.I.C. v. Government of Turkmenistan, 
    345 F.3d 347
    , 356 (5th Cir. 2003); see also Rubiola,
    334 S.W.3d at 224 (Tex. 2011) (ordinarily, “parties must sign arbitration agreements before being
    bound by them”). However, Texas courts have long recognized the six theories, arising out of
    common principles of contract and agency law, that may bind non-signatories to arbitration
    agreements: “(1) incorporation by reference; (2) assumption; (3) agency; (4) alter ego; (5)
    equitable estoppel, and (6) third-party beneficiary.” Kellogg, 166 S.W.3d at 739; see also Taylor
    Morrison of Tex., Inc. v. Ha, 
    660 S.W.3d 529
    , 532 (Tex. 2023) (“[N]onparties may be bound to an
    arbitration clause when the rules of law or equity would bind them to the contract generally.”).
    Here, Trans-Vac relies solely on the theory of incorporation by reference, pointing out that the
    9
    Subcontract containing the arbitration provision was incorporated by reference into the
    Performance Bond and arguing Hudson was therefore bound to arbitrate any and all disputes with
    Trans-Vac.
    The parties agree that the question of whether Hudson, as a nonsignatory, is bound by the
    agreement is a gateway matter for the court to determine. In re Labatt Food Serv., L.P., 
    279 S.W.3d 640
    , 643 (Tex. 2009) (whether an arbitration agreement binds a nonsignatory is a gateway matter
    to be determined by courts rather than by arbitrators unless the parties clearly and unmistakably
    provide otherwise) (citing In re Weekley Homes, L.P., 
    180 S.W.3d 127
    , 130 (Tex. 2005); Howsam
    v. Dean Witter Reynolds, Inc., 
    537 U.S. 79
    , 83–84 (2002)); see also Jody James Farms, JV v.
    Altman Group, Inc., 
    547 S.W.3d 624
    , 631-32 (Tex. 2018) (whether a nonsignatory is bound by an
    arbitration agreement is a matter for “judicial determination”). 6 And, in line with the general
    principle that the party seeking to compel arbitration has the burden to establish the validity of an
    arbitration agreement, the “party seeking arbitration bears the burden of establishing that the
    arbitration agreement binds a nonsignatory.” See Meritage Homes of Tex., LLC v. Pouye, No. 03-
    21-00281-CV, 
    2023 WL 1998889
    , at *2 (Tex. App.—Austin Feb. 15, 2023, no pet.) (mem. op.)
    (citing Santander Consumer USA, Inc. v. Mata, No. 03-14-00782-CV, 
    2017 WL 1208767
    , at *2
    (Tex. App.—Austin Mar. 29, 2017, no pet.) (mem. op.)); see also In re Weekley Homes, L.P., 180
    S.W.3d at 130 (placing the burden on the moving party to show a valid agreement to arbitrate was
    binding on a “nonparty”).
    We apply state law in determining whether a nonsignatory can be bound by an arbitration
    agreement regardless of whether the agreement is governed by the Federal Arbitration Act (FAA)
    6
    When an agreement incorporates the AAA rules, this generally establishes a clear and unmistakable agreement to
    delegate such questions exclusively to the arbitrator. See Lennar Homes of Tex. Land & Constr., Ltd. v. Whiteley, No.
    21-0783, 
    2023 WL 3398584
    , at *5 (Tex. May 12, 2023). However, when, as here, the party resisting arbitration is not
    a signatory to the arbitration agreement incorporating the AAA rules, it is for the court to decide whether the
    nonsignatory is bound by the agreement. 
    Id.
     (citing Jody James Farms, JV v. Altman Group Inc., 
    547 S.W.3d 624
    ,
    631-32 (Tex. 2018).
    10
    or the Texas Arbitration Act (TAA). In re Labatt Food Serv., L.P., 
    279 S.W.3d 640
     at 643 ; see
    also In re Weekley Homes, 180 S.W.3d at 131 (court applies state law in determining whether a
    “nonparty” is bound to an arbitration agreement “while endeavoring to keep it as consistent as
    possible with federal law”); Todd v. Steamship Mut. Underwriting Ass’n (Bermuda) Ltd., 
    601 F.3d 329
    , 335 (5th Cir. 2010) (recognizing that the U.S. Supreme Court has made it clear that state law
    controls whether an arbitration clause can apply to nonsignatories) (citing Arthur Andersen LLP v.
    Carlisle, 
    556 U.S. 624
    , 630 (2009)).
    III. DISCUSSION
    A. The nature of the dispute
    The parties agree that the Subcontract was incorporated by reference into the Performance
    Bond by its express terms. 7 But they disagree on the applicability of the arbitration agreement
    contained therein.
    Trans-Vac argues that because the Subcontract was incorporated by reference into the
    Performance Bond “without restriction or limitation,” the parties intended for all of the provisions
    in the Subcontract, including the arbitration clause, to apply “whole cloth” to Hudson, thereby
    binding Hudson to arbitrate any and all disputes it might have with Tran-Vac—even those arising
    under the Performance Bond. Trans-Vac contends that Hudson cannot parse out the provisions in
    the Subcontract and selectively decide which portions apply to it and which do not. And Trans-
    Vac further reasons that by agreeing to act as MGB’s surety, Hudson agreed to “stand in the shoes”
    7
    The Performance Bond states that the “subcontract is by reference made a part hereof. . . . ” “[Texas] law has long
    recognized that the terms of a separate contract may be incorporated by reference into an insurance policy if that
    reference is clearly manifested in the terms of the policy itself.” ExxonMobil Corp. v. Nat’l Union Fire Ins. Co. of
    Pittsburgh, PA, No. 21-0936, 
    2023 WL 2939596
    , at *1 (Tex. Apr. 14, 2023). And “when a document is incorporated
    into another by reference, both instruments must be read and construed together.” See St. David’s Healthcare P’ship,
    LP v. Fuller, 
    627 S.W.3d 707
    , 712 (Tex. App.—Austin 2021, pet. dism’d) (citing Bob Montgomery Chevrolet, Inc. v.
    Dent Zone Companies, 
    409 S.W.3d 181
    , 189 (Tex. App.—Dallas 2013, no pet.); In re C & H News Co., 
    133 S.W.3d 642
    , 645-46 (Tex. App.—Corpus Christi 2003, orig. proceeding)).
    11
    of MGB for virtually all aspects of the parties’ relationship, therefore Hudson was bound to all of
    the same contractual provisions that bound MGB. We disagree for two reasons.
    First, we agree with Hudson that the parties’ general intent in incorporating the Subcontract
    into the Performance Bond was to make Hudson aware of MGB’s contractual obligations it was
    undertaking to guarantee. See AgGrow Oils, L.L.C. v. Nat’l Union Fire Ins. Co. of Pittsburgh, PA,
    
    242 F.3d 777
    , 781 (8th Cir. 2001) (recognizing that the incorporation of a construction contract
    into a performance bond “clarified the performance obligations” of the subcontractor that the
    surety undertook to guarantee). And Hudson concedes that if Trans-Vac had notified it of MGB’s
    default in a timely manner and if Hudson had undertaken to remedy MGB’s default by completing
    its work, it would have “stepped into” MGB’s shoes for that purpose and been bound by all of the
    same contractual obligations that were imposed on MGB, including the duty to arbitrate disputes
    arising from Hudson’s performance in completing the work. See Beard Family P’ship v.
    Commercial Indem. Ins. Co., 
    116 S.W.3d 839
    , 845 (Tex. App.—Austin 2003, no pet.) (recognizing
    that a surety “stands in the shoes” of its principal in the event of a default by its principal, and
    therefore, to the extent the surety undertook to complete the principal’s performance, the surety
    was bound to do so under the same contractual terms to which the principal agreed).
    However, Trans-Vac did not give Hudson the opportunity to remedy MGB’s default;
    instead, it remedied the default itself and later sought payment from Hudson for its excess
    expenses. And, given Hudson’s nonsuit of its other affirmative defenses, the only pending dispute
    between the parties is whether Trans-Vac fulfilled its obligation to make a timely demand for
    payment under the terms of the Performance Bond. 8 Under these circumstances, Hudson cannot
    8
    Trans-Vac concedes that Hudson nonsuited its other affirmative defenses to payment, which arguably could be
    related to MGB’s performance under the Subcontract, but Trans-Vac points out that Hudson’s nonsuit was without
    prejudice, and therefore, Hudson could raise those defenses in the future if the court determines that Trans-Vac’s claim
    was not time-barred. While this may be true, we cannot concern ourselves with matters that may or may not occur in
    the future. Instead, we must resolve the issue before us based solely on the appellate record from the trial court. See
    Hogg v. Lynch, Chappell & Alsup, P.C., 
    480 S.W.3d 767
    , 773 (Tex. App.—El Paso 2015, no pet.) (“With limited
    12
    be said to stand in MGB’s shoes for the purposes of litigating this particular dispute. See Dobson
    Bros. Constr. Co. v. Ratliff, Inc., No. 4:08CV3103, 
    2009 WL 806800
    , *11 (D. Neb. Feb. 27, 2009)
    (rejecting the argument that a surety “stands in the shoes” of its principal when the surety never
    assumes the principal’s duties, as a surety bond is not the same as an insurance policy); Weaver &
    Tidwell, L.L.P. v. The Guarantee Co. of N. Am. USA, No. 05-10-00557-CV, 
    2011 WL 635261
    , at
    *3 (Tex. App.—Dallas Feb. 23, 2011, no pet.) (mem. op.) (holding that a surety did not stand “in
    the same shoes” as its principal—and therefore was not subject to the terms of an arbitration clause
    in an agreement between the principal and the defendant—where the surety’s claim was not based
    on any of the terms or requirements of the contract containing the arbitration clause and was instead
    based on an independent tort claim for fraud and breach of fiduciary duty).
    Second, because arbitration is a matter of consent, we agree with Hudson that the
    Subcontract’s incorporation by reference into the Performance Bond does not automatically give
    rise to an inference that it consented to arbitrate disputes relating solely to whether Trans-Vac
    complied with the Performance Bond terms. AgGrow Oils, 
    242 F.3d at 781
     (mindful that
    arbitration is a matter of consent, not coercion, court was “unwilling to construe an incorporation
    clause whose obvious purpose was to clarify the extent of the surety's secondary obligation as also
    reflecting a mutual intent to compel arbitration of all disputes between the surety and the obligee
    under the bond”). Other courts have distinguished disputes arising from the parties’ performance
    obligations in an underlying construction contract from those arising solely from a violation of the
    terms of a performance bond. See, e.g., Id; see also Fid. & Deposit Co. of Maryland v. Parsons &
    Whittemore Contractors Corp., 
    48 N.Y.2d 127
    , 131, 
    397 N.E.2d 380
    , 382 (1979) (distinguishing
    exceptions not material here, an appellate court may not consider matters outside the appellate record.”) (citing In re
    M.S., 
    115 S.W.3d 534
    , 546 (Tex. 2003) (“this Court—or any appellate court—may only consider the record presented
    to it”)); see also Quorum Intern. v. Tarrant Appraisal Dist., 
    114 S.W.3d 568
    , 572 (Tex. App.—Fort Worth 2003, pet.
    denied) (recognizing that appellate court is “bound to determine [an appeal] on the record as filed”).
    13
    between disputes arising from the parties’ obligations in the underlying construction contract and
    disputes arising solely under performance bond terms); Gloucester City Bd. of Educ. v. Am.
    Arbitration Ass’n, 
    333 N.J. Super. 511
    , 523, 
    755 A.2d 1256
    , 1262 (App. Div. 2000) (distinguishing
    between claims relating to the parties’ performance obligations under a construction contract and
    those involving the surety’s personal defenses arising from the bond provisions).
    Here, since the only dispute between the parties is Hudson’s affirmative defense that Trans-
    Vac’s claim for payment was time-barred by the Performance Bond terms, i.e., a “unique” bond
    defense, we must examine arbitration agreement itself to determine if the parties intended for that
    particular dispute to be subject to arbitration. AgGrow Oils, 
    242 F.3d at 781-82
     (examining the
    nature of the parties’ agreement to determine if disputes involving a surety’s “unique” defenses
    was subject to arbitration); see generally Branch Law Firm L.L.P. v. Osborn, 
    532 S.W.3d 1
    , 13
    (Tex. App.—Houston [14th Dist.] 2016, pet. denied) (recognizing that the question of who is
    bound by an arbitration agreement is ultimately a function of the parties’ intent as expressed within
    the terms of the agreement itself) (citing Rubiola, 334 S.W.3d at 224); see also Lucchese Boot Co.
    v. Solano, 
    473 S.W.3d 404
    , 414 (Tex. App.—El Paso 2015, no pet.) (recognizing same).
    In other words, we see the issue before us as focusing on the second step in the analysis,
    i.e., whether the parties intended for their particular dispute to fall within the scope of the
    arbitration agreement. 9 See Granite Re Inc. v. Jay Mills Contracting Inc., No. 02-14-00357-CV,
    
    2015 WL 1869216
    , at *4 (Tex. App.—Fort Worth Apr. 23, 2015, no pet.) (mem.op.) (recognizing
    that even if a valid arbitration clause contained in a construction contract was incorporated by
    reference into a performance bond, the claims brought between the obligee and the surety still had
    to fall within the scope of the arbitration clause); Ideal Mfg., Inc. v. NGC Group, Inc., No. 1:19-
    9
    Our role is not to resolve the merits of this dispute but only to determine whether the dispute falls within the scope
    of the arbitration agreement, making it proper for the arbitrator to decide, or whether it falls outside the scope, making
    a court the proper forum in which to resolve the dispute.
    14
    CV-164, 
    2020 WL 826638
    , at *4 (S.D. Tex. Feb. 4, 2020), report and recommendation adopted,
    No. 1:19-CV-00164, 
    2020 WL 824102
     (S.D. Tex. Feb. 19, 2020) (same); Suretec Ins. Co. v. C.R.
    Crawford Constr., LLC, No. 6:21-CV-00398-JDK, 
    2021 WL 6280376
    , at *8 (E.D. Tex. Dec. 15,
    2021), report and recommendation adopted, No. 6:21-CV-398-JDK, 
    2022 WL 45056
     (E.D. Tex.
    Jan. 4, 2022) (having determined that a valid arbitration agreement existed between the parties due
    to the agreement’s incorporation by reference into another contract, the court was then required to
    determine whether “the dispute in question falls within the scope of that arbitration agreement”);
    see generally In re Rubiola, 334 S.W.3d at 224–26 (even though the parties moving for arbitration
    were identified as non-signatories authorized to compel arbitration, there remained the question of
    whether the parties’ underlying claims fell within the arbitration agreement’s scope).
    B. Discerning the parties’ intent
    (1) The distinction between general and specific arbitration agreements
    In discerning whether the parties intended for a surety’s bond defense to fall within the
    scope of an arbitration agreement, we agree with Hudson that we must draw a distinction between
    an agreement that contains “broad” and “general” language indicating that it applies to “any claims
    arising from or relating to the contract” and an agreement that contains “specific” or “narrow”
    language demonstrating an intent to only bind the signatories to the agreement. Hudson appears
    willing to concede that when an arbitration agreement contains broad language and does not name
    the parties to whom it applies, it can bind a surety to arbitrate any disputes relating to the contract,
    including those relating to the surety’s unique bond defenses. 10
    10
    See, e.g., Suretec Ins. Co. v. C.R. Crawford Constr., LLC, No. 6:21-CV-00398-JDK, 
    2021 WL 6280376
    , at *8 (E.D.
    Tex. Dec. 15, 2021) (where construction contract contained a “broad” arbitration agreement subjecting “[a]ny Claim
    arising out of or related to the Contract” to arbitration, which was incorporated by reference into surety’s performance
    bond, the parties’ disputes, which included the surety’s defenses under the performance bond and disputes regarding
    whether the principal under the bond adequately performed its obligations under the construction contract, fell within
    the scope of the agreement); Granite Re Inc. v. Jay Mills Contracting Inc., No. 02-14-00357-CV, 
    2015 WL 1869216
    ,
    at *4-5 (Tex. App.—Fort Worth Apr. 23, 2015, no pet.) (mem. op) (where “broad” arbitration agreement contained in
    a construction contract providing that “all claims, disputes and controversies arising out of or relating to [the contract]
    shall be decided by arbitration” was incorporated by reference into a surety performance bond, dispute between
    15
    As Hudson points out, however, numerous courts have held that when an arbitration
    agreement specifies the parties to whom it applies, e.g., the contractor and subcontractor, a
    different analysis applies. In that instance, if the dispute between the surety and the contractor does
    not involve performance issues under the contract, and instead only involves issues relating to the
    terms of the performance bond, then the dispute does not fall within the scope of the arbitration
    agreement. See, e.g., Ideal Mfg, 
    2020 WL 826638
    , at *1 (where arbitration agreement in
    subcontracts, which were incorporated into a performance bond, referred specifically to disputes
    between contractor and subcontractor arising under the subcontracts, surety’s dispute with
    contractor arising under the performance bond did not fall within the scope of the agreement). 11
    contractor and surety arising under the bond fell within the scope of the agreement) (citing Pennzoil Exploration &
    Prod. Co. v. Ramco Energy Ltd., 
    139 F.3d 1061
    , 1067 (5th Cir.1998) (“Broad arbitration clauses [governing disputes
    relating to the contract] are not limited to claims that literally ‘arise under the contract,’ but rather embrace all disputes
    between the parties having a significant relationship to the contract regardless of the label attached to the dispute.”));
    see also Jewish Fed’n of Greater New Orleans v. Fidelity &Deposit Co., No. 01-30371, 
    2001 WL 1085096
     (5th Cir.
    Aug. 29, 2001) (per curiam) (recognizing that arbitration agreement in a construction contract providing “[a]ny
    controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration”
    could bind a surety to litigate its disputes with the contractor where the agreement was incorporated by reference into
    the surety’s performance bond); Thomas H. Hayman et al., Incorporation By Reference: A Surety’s Duty to Arbitrate,
    11 E. Bond Claims Rev. 2 at 7 (2008) (the majority of courts recognize that “arbitration clauses, which do not
    specifically identify the parties agreeing to arbitration, will be considered broad enough to include the surety.”).
    11
    Numerous other federal and state courts have recognized the same principle. See Developers Sur. & Indem. Co. v.
    Carothers Constr., Inc., 
    320 F. Supp. 3d 386
    , 392 (D. Conn. 2018) (where arbitration provision incorporated by
    reference into surety’s performance bond specified that it applied to disputes between the contractor and the
    subcontractor, surety’s dispute with the contractor did not fall within the scope of the agreement); W. Sur. Co. v. U.S.
    Eng’g Co., 
    211 F. Supp. 3d 302
    , 308 (D.D.C. 2016) (where arbitration agreement in construction contract incorporated
    by reference in a performance bond provided that it applied to any controversy or claim involving contractor and
    subcontractor, claims involving surety’s obligations under the performance bond did not fall within the scope of the
    agreement); M.A. Mortenson Co. v. Saunders Concrete Co., Inc., No. CIV. 11-935 DWF/FLN, 
    2011 WL 2672248
    , at
    *7 (D. Minn. July 8, 2011) (mem.op.), aff’d, 
    676 F.3d 1153
     (8th Cir. 2012) (where arbitration agreement in
    construction contract incorporated by reference into a performance bond by its express terms only governed disputes
    between contractor and subcontractor arising under the subcontract, a dispute between the contractor and the surety
    arising under the bond was beyond the scope of the arbitration agreement); Schneider Electric Buildings Critical Sys.,
    Inc. v. Western Surety Co., 
    454 Md. 698
    , 
    165 A.3d 485
    , 491-92 (2017) (where an arbitration clause “unambiguously
    limits its application to disputes between [contractor and subcontractor],” a court should not “alter the language of
    that promise to include [the surety]”); Fid. & Deposit Co. of Maryland v. Parsons & Whittemore Contractors Corp.,
    
    48 N.Y.2d 127
    , 131, 
    397 N.E.2d 380
    , 382 (1979) (although an arbitration agreement in a construction contract
    incorporated into a performance bond expressed an intent to bind the surety to arbitrate disputes arising under the
    contract, it did not, standing alone, express an intent to bind the surety to arbitrate disputes arising under the bond);
    Gloucester City Bd. of Educ. v. Am. Arbitration Ass’n, 
    333 N.J. Super. 511
    , 523, 
    755 A.2d 1256
    , 1262 (App. Div.
    2000) (contractor’s claim against subcontractor’s statutory surety was not subject to arbitration clause contained in
    construction contract and incorporated into performance bond because contractor’s claim did not involve performance
    of underlying construction contract but involved surety’s personal defenses arising from the provisions of the bond
    itself). Various commentators have also recognized this principle. See Chris McRae & Erin Berger, Arbitration and
    16
    While conceding that other courts have drawn this distinction between general and specific
    arbitration agreements, Trans-Vac contends that Texas law does not support doing so, pointing out
    that Hudson did not cite any Texas court cases supporting the distinction. And Trans-Vac contends
    that we should not adopt the reasoning of these other courts. We note, however, that the distinction
    between general and specific arbitration agreements has been generally recognized in Texas case
    law as a factor in determining the agreement’s intended scope. See Greystone Multi-Family
    Builders, Inc. v. Tes Elec., LP, No. 01-15-00640-CV, 
    2016 WL 3362208
    , at *5
    (Tex. pp.— Houston [1st Dist.] June 16, 2016, no pet.) (mem. op.) (recognizing the distinction
    between broad and narrow arbitration agreements as a factor in determining the agreement’s
    intended scope). In addition, in Granite Re, the Fort Worth Court of Appeals found it significant
    that an arbitration agreement found in a subcontract contained “broad” language providing that it
    applied to “all claims, disputes and controversies arising out of or relating to [the contract],” in
    determining that the surety was required to arbitrate its disputes with the contractor. Granite Re,
    
    2015 WL 1869216
    , at *5. As well, in Rubiola, the Texas Supreme Court found it significant that
    an arbitration agreement contained “broad” language defining arbitrable disputes to include “any
    and all controversies between the parties of whatever type or manner” in determining that a dispute
    involving non-signatories to the agreement came within scope of the agreement. Rubiola, 334
    S.W.3d at 224–26; see also FirstMerit Bank, 52 S.W.3d at 755 (finding the “broad” language used
    in an arbitration agreement to be a factor in determining its scope); Branch Law Firm, 
    532 S.W.3d at 20
     (recognizing that arbitration agreements containing “broad” language providing for
    arbitration of all claims arising under a contract evidences the parties’ intent to apply the agreement
    liberally to embrace any dispute having any connection to the contract). Accordingly, we agree
    the Surety: The Good, the Bad, and How It Can Get Ugly, Part II, 61 No. 11 Dri For The Defense 36, 38 (2019); see
    also Neal J. Sweeney, Compelling the Surety to Arbitrate — “Not So Fast, My Friend!,” 38-SUM CONSTR. L. 27,
    27 (2018).
    17
    with Hudson that it is appropriate under Texas law to consider whether the Subcontract’s
    arbitration agreement contained either “broad” or “specific” language in determining the parties’
    intent to bind a surety to the terms of the arbitration agreement.
    (2) The arbitration agreement language was specific to Trans-Vac and MGB
    Trans-Vac argues that even if we were to draw a distinction between broad and specific
    arbitration agreements, Subcontract’s arbitration agreement language was broad enough to support
    a finding that the parties intended to arbitrate all disputes between them, even those arising under
    the Performance Bond. We disagree with this argument as well.
    The Subcontract contained a series of dispute resolution provisions that culminated in
    arbitration. Article 10 of the Subcontract, entitled “Claims and Disputes,” provides a very detailed
    claims resolution procedure, beginning with Article 10.6: “Subcontractor hereby agrees that all
    claims, disputes and other matters arising out of or relating to the Subcontract or the Subcontract
    Documents . . . shall be resolved through the following dispute resolution procedures.” 12 Article
    10.6.1 then provides that if the “Contractor and Subcontractor cannot reach resolution on a matter
    relating to or arising out of the Subcontract or Subcontractor's performance in connection with the
    Project,” the “Parties” must first engage in good faith negotiations. And the Subcontract defines
    “Parties” as the “Contractor” and the “Subcontractor.” If the negotiations are unsuccessful,
    Articles 10.6.2 and 10.6.3 next require the Parties to engage in mediation under the AAA, with the
    Parties sharing the mediation fee. If mediation is unsuccessful, Articles 10.6.4 and 10.6.5 provide
    for arbitration as the final resolution:
    10.6.4: “For any claims subject to but not resolved by mediation pursuant to
    Articles 10.6.2 and l0.6.3, the method of binding dispute resolution shall be . . .
    Arbitration pursuant to Article 10.6.5 of this Subcontract.”
    12
    The Subcontract defined the term “Subcontract Documents” to include the upstream contract and associated
    documents; the prime contract and associated documents; all modification and change orders; and various documents
    setting forth the scope of work and the parties’ performance obligations. It did not list the Performance Bond among
    these documents.
    18
    10.6.5: “If the Parties have selected arbitration as the method of binding dispute
    resolution in Article 10.6.4, any claim subject to, but not resolved by, mediation
    shall be subject to arbitration which, unless the Parties mutually agree otherwise,
    shall be conducted in accordance with the Construction Industry Arbitration Rules
    of the American Arbitration Association in [effect] on the date of service of the
    demand for arbitration (the Arbitration rules).”
    In arguing that the Subcontract’s dispute resolution provisions are broad in nature, Trans-
    Vac focuses primarily on only two of those provisions: (1) Article 10.6, which broadly states that
    the Subcontractor [MGB] is agreeing to the dispute resolution procedures with regard to “all
    claims, disputes and other matters arising out of or relating to the Subcontract or the Subcontract
    Documents”; and (2) Article 10.6.4, which also refers to “any claims” not previously resolved by
    mediation, without identifying the parties to whom the article applies. And Trans-Vac contends
    that the language referring to “any claims” is similar to the “broad” language used in other
    arbitration agreements, which various courts have found sufficient to bind a surety. In particular,
    Trans-Vac relies on the federal district court’s opinion in Western Surety Company where it held
    that a construction contract’s arbitration agreement, which was incorporated by reference into a
    surety’s performance bond, applied to the surety’s bond dispute with the contractor, finding it
    significant that the agreement was “broadly worded, applying to ‘[a]ll claims, disputes and other
    matters in question,’ without limitation to particular named parties, and without excluding [the
    surety] from its application.” 13 See W. Sur. Co., 
    2022 WL 2057725
    , at *5-6.
    13
    Trans-Vac finds it significant that the Subcontract herein also did not expressly “exclude” the surety from the
    arbitration provisions in the Subcontract or in the Performance Bond, as it could have easily done. See W. Sur. Co. v.
    Caddell Constr. Co., Inc., No. 7:21-CV-153-FL, 
    2022 WL 2057725
    , at *7 (E.D.N.C. June 7, 2022) (finding it
    significant that the subcontract did not expressly exclude the surety from application of an arbitration agreement that
    was incorporated by reference into the surety’s performance bond). As Hudson points out, however, if the parties had
    wished to require it to participate in arbitration, they could have expressly included the surety as one of the defined
    “parties” required to participate in the dispute resolution provisions, yet they failed to do so. See, e.g., Rubiola, 334
    S.W.3d at 224 (arbitration agreement in a contract expressly provided that “certain non-signatories are to be parties to
    the agreement.”). We therefore conclude that the Subcontract’s failure to exclude Hudson in the arbitration agreement
    does not reflect the parties’ intent to bind Hudson to the agreement.
    19
    In contrast to Western Surety, however, here the Subcontract’s dispute resolution
    provisions contain several other key clauses that did in fact name particular parties, i.e., the
    contractor and the subcontractor, and that must be read in context. As set forth above, those clauses
    provide that the “Subcontractor” and “Contractor,” which are defined as the “Parties” in other
    portions of the Subcontract, are required to participate in both negotiations and mediation before
    submitting to arbitration if those steps are unsuccessful. And they further provide that when the
    “Parties have selected arbitration,” the proceedings shall be governed by the AAA’s arbitration
    rules. Thus, when we view the dispute resolution provisions as a whole, as we must, it becomes
    clear that—unlike the provisions in Western Surety—the provisions in the Subcontract did in fact
    expressly limit the arbitration agreement to disputes between Trans-Vac and MGB arising under
    the Subcontract itself. See generally J.M. Davidson, Inc., 128 S.W.3d at 229 (recognizing that we
    must examine the entire writing when construing a contract and that “[n]o single provision taken
    alone will be given controlling effect”).
    Trans-Vac also compares the dispute resolution provisions in the Subcontract with those
    in Granite Re, in which the court found that an arbitration agreement incorporated into a
    performance bond was binding on the surety. Granite Re, 
    2015 WL 1869216
    , at *3-4. We find this
    case distinguishable as well. In Granite Re, a contractor and subcontractor had entered into a
    “blanket” construction contract, and when the subcontractor allegedly defaulted on its obligations,
    the contractor completed its work. Id. at *1. Thereafter, when the surety refused to remit payment
    on the bond (for reasons that are not clear from the opinion), the contractor filed a breach-of-
    contract claim against the surety. Id. In concluding that the contractor’s claim fell within the scope
    of the arbitration agreement, the court focused on the “broad” language in the arbitration
    agreement, which provided “all claims, disputes and controversies arising out of or relating to this
    Blanket Agreement and any Work Orders issued hereunder . . . shall be decided by arbitration.”
    20
    Id. at *4. Although this language is broad, Trans-Vac finds it significant that the arbitration clause
    in that case also stated that the “claimant” in any such arbitration proceeding “could be” either the
    “Contractor” or “Subcontractor.” Id. at *1. Trans-Vac contends this language transformed the
    agreement into a specific one between the contractor and subcontractor, thus Granite Re stands for
    the proposition that even an arbitration agreement expressly naming the contractor and the
    subcontractor as parties to the agreement can be interpreted broadly enough to bind a surety to
    resolve disputes arising under a performance bond.
    In Granite Re, however, the court expressly noted that the language in the arbitration clause
    identifying the contractor and subcontractor as potential claimants in an arbitration proceeding did
    not limit the clause’s scope to disputes between the contractor and the subcontractor and instead
    was simply intended to clarify that either potential “claimant” could bring an arbitration
    proceeding—without limiting who the claimant could name as a party to the arbitration. Id. at *4,
    n. 6. Accordingly, the court concluded that the arbitration agreement was broad enough to allow
    the contractor, as a “claimant,” to bring an arbitration proceeding against the surety. Id. In contrast,
    as set forth above, the Subcontract herein contains language that limits the arbitration agreement
    solely to the contractor and the subcontractor; it does not simply identify who may be a “claimant”
    in the proceeding. 14
    14
    Hudson also points out that the Subcontract expressly states “[t]he Subcontract Documents shall not be construed
    to create a contractual relationship of any kind between anyone other than Contractor and Subcontractor.” Hudson
    contends, therefore, that “the subcontract plainly cannot impose any contractual duty (to arbitrate) running from
    Hudson to Trans-Vac.” We disagree with such a broad statement, as it is clearly possible for the parties—who have
    entered into what is essentially a tripartite contractual relationship—to bind the surety to an arbitration provision
    despite such language in a contract. See Granite Re Inc. v. Jay Mills Contracting Inc., No. 02-14-00357-CV, 
    2015 WL 1869216
    , at *1, 3-4 (Tex. App.—Fort Worth Apr. 23, 2015, no pet.) (mem. op); see generally Great Am. Ins. Co.
    v. N. Austin Mun. Util. Dist. No. 1, 
    908 S.W.2d 415
    , 418 (Tex. 1995) (recognizing that “suretyship involves a tripartite
    relationship between a surety, its principal, and the bond obligee, in which the obligation of the surety is intended to
    supplement an obligation of the principal owed to the bond obligee”).
    21
    Given the specific language in the Subcontract requiring only Trans-Vac and MGB to
    engage in the dispute resolution provisions with regard to disputes between them, we conclude
    that the contract does not reflect the parties’ intent to require Hudson to arbitrate its disputes with
    Trans-Vac arising solely under the Performance Bond.
    (3) The language of the performance bond confirms this conclusion
    We also agree with Hudson that the Performance Bond terms confirm that the parties did
    not intend for Hudson’s unique bond defenses to be subject to arbitration. First, Hudson points out
    that the Performance Bond stated, “Any suit under this bond must be instituted before the
    expiration of two years from date on which final payment under the subcontract falls due.” And in
    turn, Hudson points out that the term “suit” is typically defined as a court action. See McGinnes
    Indus. Maint. Co rp. v. Phoenix Ins. Co., 
    477 S.W.3d 786
    , 798 (Tex. 2015) (recognizing that the
    common, ordinary meaning of “suit” is “a proceeding in court”). Hudson also directs our attention
    to the “rider” attached to the Performance Bond providing that Chapter 2253 of the Texas
    Government Code applied, and Hudson points out that a dispute regarding a Performance Bond
    issued under that Chapter for a public work project must be brought in a court in the county in
    which the project was located. See TEX. GOV’T CODE ANN. § 2253.077. While we express no
    opinion on whether those provisions do in fact serve as time-bars to Trans-Vac’s claim, we
    nevertheless find that they do confirm that the parties intended to resolve disputes arising under
    the bond in court rather than through arbitration. See AgGrow Oils, 
    242 F.3d at 781
     (finding it
    significant that a provision in a performance bond referred to the “judicial resolution of disputes”
    in determining that the parties did not intend for disputes arising under the bond to be subject to
    arbitration).
    Accordingly, we find no language in either the Subcontract or the Performance Bond that
    convinces us that the parties intended to submit disputes between Hudson and Trans-Vac arising
    22
    under the Performance Bond to arbitration. And in the absence of any such language, Hudson
    cannot be coerced into giving up its right to a judicial resolution of this dispute with Trans-Vac.
    See AgGrow Oils, 
    242 F.3d at 781
     (in the absence of evidence demonstrating the parties intended
    for a surety to be bound to an arbitration agreement, it could not conclude that the surety had the
    right to mandate arbitration of its claims under the bond); see also Liberty Mut. Ins. Co. v.
    Mandaree Pub. School Dist. #36, 
    503 F.3d 709
    , 711 (8th Cir. 2007) (concluding that contractor
    could not compel arbitration of surety’s claims arising under the terms of the performance bond,
    where the intent to arbitrate such disputes was not clearly expressed in the parties’ contracts). We
    therefore conclude that the trial court did not err in denying Trans-Vac’s motion to compel
    arbitration.
    We overrule Trans-Vac’s first and only issue.
    IV. CONCLUSION
    We affirm the trial court’s order denying the motion to compel arbitration and remand to
    the trial court for further proceedings consistent with our opinion.
    LISA J. SOTO, Justice
    June 23, 2023
    Before Rodriguez, C.J., Palafox, J., Soto, J.
    23