S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc. ( 2024 )


Menu:
  •                                      In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    __________________
    NO. 09-22-00261-CV
    __________________
    S&B ENGINEERS & CONSTRUCTORS, LTD. AND
    ZURICH AMERICAN INSURANCE COMPANY, Appellants
    V.
    SCALLON CONTROLS, INC., Appellee
    __________________________________________________________________
    On Appeal from the 172nd District Court
    Jefferson County, Texas
    Trial Cause No. E-198,919
    __________________________________________________________________
    MEMORANDUM OPINION
    In this appeal, defendants (and an insurer) who paid to settle a lawsuit are
    seeking a recovery from a third-party-defendant for the amounts paid in the
    settlement. Appellant S&B Engineers and Constructors, Ltd. (“S&B”) appeals from
    an Order on Cross Motions for Summary Judgment. In the order, the trial court
    granted summary judgment in favor of Appellee Scallon Controls, Inc. (“Appellee”
    or “Scallon”) on all claims asserted against Scallon and denied S&B’s motion for
    1
    partial summary judgment against Scallon. In four issues on appeal, S&B argues that
    the trial court erred. Appellant Zurich American Insurance Company (“Zurich”),
    who was an intervenor in the trial court and asserted subrogation rights as Sunoco’s1
    insurer, also appeals. As explained herein, we affirm.
    Background
    Seven individual plaintiffs (“Individual Plaintiffs”) filed a personal injury
    lawsuit against Sunoco Logistics Partners Operations GP LLC, Sunoco Logistics
    Partners LP (collectively “Sunoco”), and S&B. 2 The Individual Plaintiffs alleged
    they were employed by Insulations, Inc. as insulators and insulator helpers, and on
    January 5, 2015, they were working at a Sunoco Logistics Terminal. While working,
    they heard a loud noise or explosion and saw a thick “chemical cloud” (later
    determined to be a fire suppressant chemical called “Purple K”) moving toward
    them. As they tried to leave the work area, several of them fell and sustained injuries.
    According to the petition, the Fire Suppression System was activated while the S&B
    instrument technicians were working in the area, and when they attempted to “put
    the system in alarm fail,” it caused the loud noise the Individual Plaintiffs heard and
    1
    Sunoco is not a party to this appeal. At trial, Sunoco Logistics Partners
    Operations GP LLC and Sunoco Logistics Partners LP (collectively “Sunoco”) were
    defendants.
    2
    We do not name the individual plaintiffs but rather refer to them herein
    collectively as “the Individual Plaintiffs” because the Individual Plaintiffs settled
    their claims, and this appeal concerns claims between the defendant S&B, Sunoco’s
    insurer (intervenor Zurich), and third-party defendant Scallon.
    2
    the cloud that the Individual Plaintiffs saw. The Individual Plaintiffs alleged that the
    Defendants’ (S&B and Sunoco) negligence proximately caused their injuries.3
    S&B filed a general denial answer and an Original Third-Party Petition
    against Scallon. In the Third-Party Petition S&B alleged that Scallon’s negligence
    in performing “PLC Technical Services”4 was a proximate cause of the release of
    Purple K and of the Individual Plaintiffs’ injuries. S&B also asserted that if S&B is
    found liable for Individual Plaintiffs’ damages, then Scallon, as a third-party
    defendant, would be liable to S&B for contribution. According to S&B’s third-party
    petition, it entered into a Subcontract Agreement (“Subcontract”) with Scallon that
    included a provision that Scallon defend, indemnify, and hold S&B harmless against
    any and all losses. S&B asserted a claim for contribution and indemnity under the
    Subcontract Agreement and a Purchase Order.
    3
    Specifically, the Individual Plaintiffs alleged the following acts or omissions
    of negligence by all the Defendants: failure to provide a safe environment; failure to
    inspect the worksite to make sure it was safe; failure to remedy the condition on the
    premises that caused the Individual Plaintiffs’ injuries; failure to warn the Individual
    Plaintiffs of the sound of an explosion or the release of the cloud; negligent
    installation of the fire suppression system; negligent check of the fire suppression
    system in a crowded area with workers present; negligent inspection of the fire
    suppression system; negligent coordination of work on the fire suppression system
    and in the Area 250 Pipe Rack; negligent training of employees working on or
    around the fire suppression system; and negligent purchase and use of the fire
    suppression system.
    4
    A purchase order included in the record reflects “PLC” refers to
    “Programmable Logic Controller.”
    3
    Sunoco also filed a third-party petition against Scallon. According to Sunoco,
    discovery revealed that software and hardware errors had resulted from Scallon’s
    negligence, Scallon had subcontracted with S&B to provide services, and Scallon’s
    negligence was the proximate cause of the accidental release of fire retardant.
    Sunoco sought contribution and indemnity from Scallon.
    In its Answer, Scallon asserted a general denial and the following affirmative
    defenses: the injuries were caused by the acts or omissions of others for whom
    Scallon was not responsible; the injuries resulted from new and independent
    intervening or superseding causes; the injuries resulted from Third-Party Plaintiff’s
    own negligence. We include a chart below to demonstrate the relationship of the
    parties.
    4
    Over the course of the underlying lawsuit, S&B amended its petition against
    Scallon, and S&B’s Ninth Amended Original Petition was S&B’s live pleading
    when the trial court rendered its Final Judgment. In the Ninth Amended Original
    Petition, S&B asserted claims against Scallon pursuant to its Subcontract, as well as
    the Terms and Conditions of the Purchase Order. S&B asserted a claim for breach
    of contract, alleging that Scallon (1) changed the work from what was instructed
    without obtaining prior written approval by S&B, and (2) Scallon failed to indemnify
    S&B as required by the Purchase Order and Subcontract. S&B also asserted a claim
    against Scallon for breach of express warranty under both the Purchase Order and
    Subcontract, alleging that Scallon’s work had defects and did not conform to S&B’s
    specifications. Specifically, S&B alleged that it directed Scallon that both the inputs
    and outputs of the Fire Suppression System should be configured as “non-fail-safe”
    but that Scallon configured the inputs as “fail-safe.” S&B also asserted claims for
    breaching the implied warranty of fitness for a particular purpose and the warranty
    of merchantability under the UCC. 5 S&B sought damages of $2,350,000 that it paid
    in settling with the Individual Plaintiffs plus $2,000,000 paid by insurers on its
    behalf, Zurich American Insurance Company (“Zurich”) and American Guarantee
    and Liability Insurance Company.
    5
    Citing 
    Tex. Bus. & Com. Code Ann. §§ 2.314
    , 2.315.
    5
    Scallon filed a Counterclaim against S&B, alleging that S&B failed to meet
    its obligations under the Sunoco Contract, and S&B’s errors and omissions were the
    proximate cause of the equipment failure, the release of Purple K, and the Individual
    Plaintiffs’ injuries, and sought a recovery of Scallon’s attorney’s fees and expenses
    in the lawsuit. Scallon also demanded that S&B defend and indemnify Scallon
    pursuant to the parties’ Subcontract. The Counterclaim also stated a claim for breach
    of contract, alleging that S&B breached its obligations under the Subcontract to
    defend and indemnify Scallon. Scallon pleaded actual and consequential damages,
    attorney’s fees, and interest.
    S&B and Sunoco settled with all the Individual Plaintiffs. Copies of the
    confidential settlement agreements that are in the record include a provision in which
    the Individual Plaintiffs agree that all their claims against Defendants S&B and
    Sunoco are fully released and discharged, and a provision in which S&B and Sunoco
    fully and completely release and discharge each other from all claims relating to the
    matter. After the settlements, the lawsuit was restyled as S&B Engineers and
    Constructors, Ltd., Sunoco Logistics Partners Operations GP LLC, and Sunoco
    Logistics Partners LP, Plaintiffs v. Scallon Controls, Inc., Defendant. Thereafter,
    Sunoco also nonsuited its claims without prejudice, and Zurich filed a Petition in
    Intervention asserting subrogation claims, seeking to recover the amounts it paid on
    behalf of Sunoco, its insured, to settle with the Individual Plaintiffs.
    6
    Subcontract and Purchase Order
    The Subcontract between S&B and Scallon is styled “Short Form Subcontract
    Agreement[,] PLC Technical Services” and states that it is for “Subcontracted
    Services (Services/Work)”—namely, “labor, equipment, tools, and consumables
    necessary as needed to complete the PLC Technical Services”—and “[t]hese
    services are for equipment purchased on S&B Purchase order number C1505-
    I0050.” (“Purchase Order”) The Subcontract was signed by the parties’
    representatives in September and October of 2014. The first page of the Subcontract
    defines the S&B as the Contractor and Scallon as the Subcontractor. The Subcontract
    includes the following provisions at issue in this lawsuit:
    2. Warranty and Guarantee. All articles, materials and Work,
    furnished by or through SUBCONTRACTOR shall be of good quality
    and free from any defects and conform to CONTRACTOR’S
    specifications, and shall at all times be subject to CONTRACTOR’S
    inspection; but neither CONTRACTOR’S inspection nor failure to
    inspect shall relieve SUBCONTRACTOR of any obligation hereunder.
    9. Liability Indemnity. SUBCONTRACTOR [SCALLON] SHALL
    BE SOLELY RESPONSIBLE FOR ALL MATERIALS,
    EQUIPMENT AND SERVICES UNTIL THE WORK IS
    COMPLETED          TO     CONTRACTOR’S   SATISFACTION.
    SUBCONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR
    TOOLS, EQUIPMENT AND OTHER PROPERTY OWNED,
    RENTED OR LEASED BY SUBCONTRACTOR OR
    EMPLOYEE WHICH ARE NOT TO BE INCORPORATED
    INTO THE WORK.
    SUBCONTRACTOR SHALL DEFEND, INDEMNIFY AND
    SAVE HARMLESS THE CONTRACTOR [S&B] AND OWNER
    [SUNOCO] AND THEIR PARENTS AND AFFILIATED
    COMPANIES (“INDEMNITEES”) FROM AND AGAINST ANY
    7
    AND ALL LOSS, DAMAGE, INJURY, LIABILITY, AND CLAIMS
    THEREOF FOR INJURY TO OR DEATH OF ANY PERSON
    (INCLUDING AN EMPLOYEE OR SUBCONTRACTOR OF AN
    INDEMNITEE) OR FOR LOSS OF OR DAMAGE TO PROPERTY
    (INCLUDING THE PROPERTY OF INDEMNITEES) OR FOR LOSS
    OR DAMAGE ARISING FROM ATTACHMENTS, LIENS OR
    CLAIMS OF MATERIALMEN OR LABORERS TO THE EXTENT
    CAUSED BY THE NEGLIGENT ACTS OR OMISSIONS OF
    SUBCONTRACTOR.     CONTRACTOR      SHALL    DEFEND,
    INDEMNIFY AND SAVE HARMLESS THE SUBCONTRACTOR
    FROM AND AGAINST ANY AND ALL LOSS, DAMAGE, INJURY,
    LIABILITY, AND CLAIMS TO THE EXTENT CAUSED BY
    CONTRACTOR. THIS INDEMNITY SHALL NOT APPLY TO THE
    EXTENT THAT SUCH INDEMNIFICATION IS VOID OR
    OTHERWISE UNENFORCEABLE UNDER APPLICABLE LAW IN
    EFFECT ON OR VALIDLY RETROACTIVE TO THE DATE OF
    THIS AGREEMENT. THE INDEMNITEES’ RIGHTS TO
    INDEMNIFICATION BY SUBCONTRACTOR UNDER THE
    FOREGOING SHALL BE INDEPENDENT OF THEIR RIGHTS
    UNDER INSURANCE PROVIDED UNDER SECTION 10.
    13. Changes. SUBCONTRACTOR shall make no change in the Work,
    or perform any additional Work without CONTRACTOR’S specific
    prior written approval, CONTRACTOR may order changes in the
    Work, or require additional Work at any time, and
    SUBCONTRACTOR shall comply therewith, but the price hereunder
    shall be increased by an amount as approved by CONTRACTOR.
    24. CONSEQUENTIAL, INDIRECT, INCIDENTAL OR
    SPECIAL DAMAGES. NOTWITHSTANDING ANYTHING TO
    THE CONTRARY CONTAINED HEREIN, NEITHER PARTY
    SHALL BE LIABLE TO THE OTHER FOR CONSEQUENTIAL,
    INDIRECT, INCIDENTAL, OR SPECIAL DAMAGES INCLUDING
    BUT NOT LIMITED TO LOSS OF PLANT CAPACITY, LOSS OF
    BUSINESS OR ANY OTHER SUCH LOSS, HOWSOEVER
    CAUSED, INCLUDING BY THE NEGLIGENCE OR STRICT
    LIABILITY OF EITHER PARTY.
    8
    The parties’ Purchase Order number C1505-I0050, dated December 13, 2013,
    states that it “will be governed by the attached mutually agreed upon terms and
    conditions between S&B Engineers and Constructors, Ltd. and Scallon Controls,
    Inc., dated 11/19/13.” The Terms and Conditions attached to the Purchase Order
    include the following relevant provisions:
    11. WARRANTY. Seller [Scallon] represents and WARRANTS: (1)
    that the articles herein described are fit for use for the specified purpose
    for which they are purchased by S&B and are free from defect in
    design, workmanship, and material and are in strict accordance with the
    specifications hereof, unless otherwise agreed in writing and Seller
    agrees to replace without cost any article, material or workmanship
    which shall be found defective within eighteen (18) months after start-
    up or twenty-four (24) months from shipment, whichever occurs first;
    (2) that said articles and the sale or use of them does not infringe,
    directly or indirectly, any valid patent, copyright or trademark, and that
    Seller will, at Seller’s cost and expense, defend, indemnify and hold
    S&B, and its affiliated companies, sub-contractors, and clients
    harmless from and against any claims, demands, actions and litigation
    based on alleged or actual infringement thereof; (3) that all amounts
    charged by the Seller and payable pursuant hereto are lawfully
    chargeable under and shall not violate, directly or indirectly, the
    provisions of any present or future laws, decrees, regulations, rules or
    orders of any governmental authority which in any manner fix, limit,
    regulate, or otherwise affect prices at which said articles may be sold;
    (4) that all United States statutes, applicable to furnishing labor and
    materials or sales merchandise for use on government contracts, have
    been fully complied with; and (5) that where Seller is furnishing articles
    in accordance with designated plans and specifications, that all articles
    furnished meet and perform in accordance with such plans and
    specifications. These WARRANTIES are in addition to, and shall not
    be construed as restricting or limiting any warranties of the Seller,
    express or implied, or which are provided by law or exist by operation
    of law. These warranties shall run to the benefit of S&B and its
    affiliated companies, subsidiaries and clients.
    9
    12. LIABILITY AND INDEMNITY.
    ...
    Other Claims. TO THE MAXIMUM EXTENT PERMITTED BY
    APPLICABLE LAW, SELLER [Scallon] SHALL DEFEND,
    INDEMNIFY AND HOLD HARMLESS S&B, AND ITS
    AFFILIATED COMPANIES, SUBSIDIARIES AND CLIENTS
    FROM AND AGAINST ANY AND ALL LOSS, DAMAGE, CLAIM,
    SUIT, LIABILITY, STRICT LIABILITY, PRODUCT LIABILITY,
    JUDGMENT AND EXPENSE (INCLUDING ATTORNEY’S FEES
    AND OTHER COSTS OF LITIGATION) AND ANY FINES,
    PENALTIES AND ASSESSMENTS, ARISING OUT OF (A)
    DAMAGE TO OR LOSS OF PROPERTY OR (B) BODILY INJURY,
    DISEASE OR DEATH TO PERSONS OTHER THAN EMPLOYEES
    OF SELLER, ITS AGENTS OR SUBCONTRACTORS RESULTING
    FROM OR IN CONNECTION WITH THE EXECUTION OF THIS
    PURCHASE ORDER TO THE EXTENT OF SELLER’S
    NEGLIGENCE OR WILLFUL MISCONDUCT. IN CASE OF
    COMPARATIVE, CONCURRENT AND/OR CONTRIBUTING
    NEGLIGENCE, FAULT OR STRICT LIABILITY OF SELLER OR
    BUYER, WHETHER THROUGH ITS EMPLOYEES AND/OR
    REPRESENTATIVES, SELLER’S DUTY TO INDEMNIFY AND
    HOLD HARMLESS REFERRED TO IN THE PREVIOUS
    SENTENCE SHALL BE SELLER’S ALLOCABLE SHARE OF
    COMPARATIVE, CONCURRENT AND/OR CONTRIBUTING
    NEGLIGENCE, FAULT OR STRICT LIABILITY.
    Motions for Summary Judgment
    Scallon’s Traditional and No-Evidence MSJ Against S&B
    Scallon filed a traditional and no-evidence motion for summary judgment
    seeking a judgment against S&B. Therein, Scallon argues that, although S&B
    alleged that Scallon breached the parties’ Subcontract by configuring the inputs as
    “fail-safe” when the work called for them to be configured as “non-fail-safe,” the
    Final Acceptance Testing sign off sheets (which were exhibits to Scallon’s motion)
    10
    reflect that S&B approved the configuration and that Scallon installed the inputs the
    way they were approved by S&B. Scallon also argues that the indemnity provision
    in the Subcontract is unenforceable against Scallon because the Individual Plaintiffs
    only alleged negligence claims against S&B and Sunoco, and the Individual
    Plaintiffs made no allegations of negligence by Scallon.6 According to Scallon,
    because S&B settled with the Individual Plaintiffs, S&B’s claim against Scallon for
    indemnification “effectively seeks to have Scallon pay for [S&B’s] settlement.”
    Scallon argues it is also entitled to judgment as a matter of law on S&B’s
    claims for breach of contract and breach of express warranty. As to S&B’s breach
    of contract claim, Scallon argues there is no evidence that Scallon breached the terms
    of the Subcontract or that S&B sustained damages as a result of any breach. As to
    S&B’s claim for breach of express warranty, Scallon argues there is no evidence of
    an express promise by Scallon relating to the goods, no evidence that S&B relied on
    any promise, no evidence that the goods failed to comply with any promise, and no
    evidence that S&B was injured thereby.7
    6
    Citing Fisk Elec. Co. v. Constructors & Assocs., 
    888 S.W.2d 813
     (Tex. 1994)
    (applying the “express negligence doctrine,” whereby a party seeking indemnity
    from consequences of its own negligence must clearly express that intent in language
    that contains specific terms within the four corners of the contract).
    7
    Citing Great Am. Prods. v. Permabond Int’l, 
    94 S.W.3d 675
    , 681 (Tex.
    App.—Austin 2002, pet. denied) (reciting the elements for breach of express
    warranty).
    11
    S&B’s Traditional Motion for Partial Summary Judgment
    S&B filed a traditional motion for partial summary judgment on its claims
    against Scallon for breach of the warranty of merchantability, breach of an implied
    warranty of fitness for a particular purpose, and breach of an express warranty. S&B
    alleged as follows:
    . . . S&B hired Scallon to design, build and configure the logic for a
    Safety Control System at the Mariner South Terminal Project (“the
    Project”). The logic included control of a fire suppression system
    (“FSS”) for Tank 2201 on the Project. Relying on his “personal
    experience,” an employee configured the input for the FSS as “fail-
    safe” or energized. Due to this configuration, the FSS inadvertently
    discharged when there was a brief momentary loss of power at the
    Project. As a matter of law, the evidence established the logic in
    question operating the FSS was not fit for the purpose desired by S&B
    and the logic was not free of defects.
    S&B attached selected pages from a transcript of the deposition of Chris
    Lampman, a systems engineer for Scallon who worked on the Sunoco project. In the
    S&B motion, S&B alleged that Lampman testified that he generally designs a
    program to operate in the way the client wants, and the safety control system at
    Sunoco was the first time he was involved with a Fire Suppression System.
    Lampman testified that he used the “cause and effects and control philosophy” to
    design and build the logic for the fire suppressant system, but he also acknowledged
    that if the cause and effects philosophy would not have all the information necessary
    to design and build the logic, in that event he would have either exercised his
    independent judgment or asked for a consultation with S&B, but he did not recall
    12
    having requested a consultation with S&B for this project. Lampman testified that,
    if the cause and effects provided by the client did not specify whether the input for
    the solenoid on the fire safety system should be non-fail-safe, he would “go with []
    the common practice of a fail-safe[.]” In his deposition, Lampman also
    acknowledged that when the power failed at the project, the dry chemical Fire
    Suppression System activated because the logic for the fire safety system’s inputs
    were “fail-safe,” not non-fail-safe.
    S&B also attached selected pages from a transcript of the deposition of Peter
    Mondello, the Vice President of Systems for Scallon. Mondello testified that he did
    not know whether S&B directed Lampman to configure the inputs as “fail-safe.”
    Mondello also testified that the fire safety system activated on loss of power to the
    input and that he could not think of a reason why a refinery or chemical plant would
    want a fire safety system to discharge in the absence of a fire. According to
    Mondello, when S&B signed off on and accepted Scallon’s work at the conclusion
    of Factory Acceptance Testimony (“FAT”), the FAT would not reflect whether the
    fire safety system was configured in fail-safe or non-fail-safe mode.
    Another attachment to the motion was selected pages from a transcript of the
    deposition of Paul Dougharty, who was in charge of Process Control & Safety
    Systems for S&B at the Project and who was the technical contact for the project.
    Dougharty testified that S&B told Scallon that the fire safety system needed to be
    13
    configured as non-fail-safe mode or “de-energized,” but that Scallon “pushed back”
    on this requirement. Dougharty testified there were several discussions between
    S&B and Scallon employees during which Dougharty explained to Scallon that the
    fire safety system, unlike other components of the Safety Control System, was to be
    configured as non-fail-safe or de-energized. According to Dougharty, Scallon was
    provided documents that indicated that the fire safety system was to be a non-fail-
    safe system. Dougharty testified that, in an investigation after the incident, he
    learned from Lampman that Scallon had programmed the system so that all the
    inputs were configured as fail-safe.
    S&B argued that Scallon breached the implied warranties of merchantability
    and fitness for a particular purpose under the Uniform Commercial Code (“UCC”)
    as codified in the Texas Business and Commerce Code. According to S&B, the
    undisputed evidence reflects that Scallon sold goods to S&B, including the logic
    control for the fire safety system, and the logic control for the fire safety system was
    not fit for its ordinary purpose because it activated and discharged in the absence of
    a fire. S&B argued that the undisputed evidence also reflects that Scallon knew that
    S&B hired it to design, build, and configure the logic that would operate the fire
    safety system, that S&B relied on Scallon’s skill to develop a logic that would
    operate the fire safety system, and that S&B notified Scallon of its breach shortly
    14
    after the “inadvertent” discharge of the fire safety system. S&B argued that both of
    these breaches caused S&B to be sued and to incur substantial financial damages.
    As to its claim for breach of express warranty, S&B noted that the Subcontract
    provided that Scallon agreed to provide the labor, equipment, tools, and consumables
    necessary to complete the PLC Technical Services. S&B argued that paragraph 2 of
    the Subcontract was an express warranty by which Scallon warranted that all articles,
    materials, and work it furnished “shall be of good quality and free from any defects
    and conform to Contractor’s specifications[.]” According to S&B, it relied on
    Scallon’s expertise in system integration, and Scallon configured the fire safety
    system input as “fail-safe[,]” which was “clearly a defect in the logic created by
    Scallon.” S&B argued that because the logic as Scallon configured it was not free of
    defects, Scallon breached an express warranty to S&B.
    Scallon’s MSJ Against S&B and Sunoco and Scallon’s Response to S&B’s MPSJ
    Scallon also filed a combined MSJ on S&B’s and Sunoco’s claims against
    Scallon and a response to S&B’s MPSJ. Scallon asserted that there is no enforceable
    indemnity agreement, and the express negligence rule precludes S&B and Sunoco
    from recovering from Scallon. Scallon argues that the indemnity language in its
    Subcontract with S&B 8 is insufficient under the express negligence rule set forth in
    8
    Paragraph 2, titled “Warranty and Guarantee,” quoted supra.
    15
    Ethyl Corp. v. Daniel Construction Co., 
    725 S.W.2d 705
    , 708 (Tex. 1987). In Ethyl,
    the Court stated:
    The express negligence doctrine provides that parties seeking to
    indemnify the indemnitee from the consequences of its own negligence
    must express that intent in specific terms. Under the doctrine of express
    negligence, the intent of the parties must be specifically stated within
    the four corners of the contract.
    
    Id.
     According to Scallon, in this case S&B and Sunoco are suing for reimbursement
    of monies they paid in the face of Individual Plaintiffs’ negligence claims for
    personal injury, and therefore, they are seeking to get indemnity for their own
    negligence, which is impermissible under the express negligence rule and Ethyl.
    Scallon also argues that S&B and Sunoco cannot argue that the indemnity provision
    of the Subcontract “equates to contractual comparative responsibility” because the
    Ethyl Court also concluded that “[p]arties may contract for comparative indemnity
    so long as they comply with the express negligence doctrine[.]” 
    Id. at 708-09
    .
    Scallon also argues that the Subcontract was primarily for services and not for
    the sale of goods, so that the UCC does not apply, and therefore, S&B (nor Sunoco,
    by extension) has no warranty claims. The Subcontract states it is for “Subcontracted
    Services (Services/Work)[.]” Scallon argues that the UCC expressly applies only to
    contracts for the sale of goods, 9 but where a contract is for both goods and services,
    courts determine whether the dominant factor in the transaction is the sale of goods
    9
    Citing 
    Tex. Bus. & Com. Code Ann. §§ 2.102
    , 2.106.
    16
    or of services.10 According to Scallon, because the dominant factor of the
    Subcontract is the sale of services, the UCC does not apply, and S&B is not entitled
    to summary judgment on its UCC breach of warranty claims. Quoting S&B’s MPSJ,
    Scallon also states that S&B’s complaints against Scallon relate to services it
    rendered on the configuration of the Fire Suppression System, wherein S&B “relied
    on the expertise of Scallon as self-proclaimed experts in the field of system
    integration [] to complete site acceptance testing of hardware and software Scallon
    designed, developed, built and configured.”
    But even assuming S&B asserted a common law breach of warranty claim for
    services, Scallon argues that S&B cannot succeed because S&B has failed to
    establish a breach. According to Scallon, it configured the inputs as “fail-safe”
    pursuant to industry customs, and there were no written specifications otherwise.
    Scallon also argues that S&B relies on deposition testimony of “an alleged
    conversation between Paul Dough[a]rty (S&B) and Scallon employees Steven
    Erickson, Chris Lampman and Bret Jordan[,]” but section 13 of the Subcontract
    expressly requires that change orders be made in writing. Even so, Scallon argues
    10
    Citing Palmer v. Espey Huston & Assocs., Inc., 
    84 S.W.3d 345
    , 355-56 (Tex.
    App.—Corpus Christi 2002, pet. denied); Geotech Energy Corp. v. Gulf States
    Telecomms. & Info. Sys., Inc., 
    788 S.W.2d 386
    , 389 (Tex. App.—Houston [14th
    Dist.] 1990, no writ).
    17
    that a fact issue exists as to what specifications S&B gave to Scallon, which
    precludes S&B from prevailing on its MPSJ.
    Finally, Scallon argues that paragraph 24 of the Subcontract expressly
    disclaims any liability for consequential, indirect, incidental, or special damages.
    According to Scallon, by statute, only actual damages are recoverable for a seller’s
    breach of an implied warranty of merchantability—that is, the difference between
    the value of the goods accepted and the value of the goods as warranted—and that
    under the language of its Subcontract, there is a disclaimer for consequential
    damages that result from its breach. 11 According to Scallon, paragraph 24 of the
    Subcontract disclaims consequential damages in a provision that it claims “broadly
    and unambiguously negates any liability by either party for all indirect damages.”
    Since “personal injury damages for breach of contract are ‘consequential’, not
    ‘direct’, damages, Scallon concludes they are therefore not recoverable because they
    “fall within the liability disclaimer for consequential damages.” Scallon further
    argues that the Warranty and Guarantee provision of the Subcontract limits the
    available remedy to repair or replacement.
    S&B’s Response to Scallon’s MSJ
    S&B filed a response to Scallon’s MSJ based on the Ethyl express negligence
    doctrine, and S&B argues that the Terms and Conditions of the Purchase Order
    11
    Citing 
    Tex. Bus. & Com. Code Ann. §§ 2.714
    (b), 2.715(b).
    18
    included warranty and indemnity provisions under which “Scallon agreed to
    indemnify S&B and its client, Sunoco, for losses and damages incurred by them as
    a result of Scallon’s negligence and fault.” According to S&B, the Terms and
    Conditions did not contain a provision regarding consequential damages.
    S&B maintains that it entered into a separate Subcontract with Scallon on or
    about October 1, 2013, under which Scallon agreed to provide PLC Technical
    Services. The Subcontract states it is for “services [] for equipment purchased on
    S&B Purchase order number C1505-I0050.” The Subcontract includes a “Warranty
    and Guarantee” provision, requiring Subcontractor’s (Scallon’s) materials and work
    to conform to Contractor’s (S&B’s) specifications. The Subcontract also includes a
    provision requiring that Subcontractor make no changes to the work without
    Contractor’s specific prior written approval. According to S&B, the Subcontract also
    requires Scallon to indemnify and hold S&B harmless from any and all loss or
    damage incurred by S&B as a consequence of Scallon’s negligence.
    S&B argues that Paul Dougharty instructed Scallon that the Fire Suppression
    System should be configured as non-fail-safe or de-energized. Dougharty testified
    that he gave this instruction, and that this specification was provided to Scallon in
    the “CB&I documents[,]”12 although Dougharty could not recall when such
    documents were provided to Scallon. However, in an investigation after the incident,
    12
    The “CB&I documents” are not in our appellate record.
    19
    S&B determined that Scallon had programmed inputs as fail-safe. And Scallon’s
    Vice President of Systems, Peter Mondello, testified in his deposition that Chris
    Lampman, a systems engineer for Scallon, decided to configure the Fire Suppression
    System inputs as fail-safe. Mondello also testified in his deposition that Factory
    Acceptance Testing would not have revealed whether the inputs were configured as
    fail-safe or non-fail-safe.
    S&B argues that there is no dispute that the inputs were configured as fail-
    safe, and this action was a change in the work without prior written authorization
    from S&B. Therefore, S&B argues that Scallon breached the parties’ Subcontract.
    And S&B contends that it incurred damages as a consequence of the release of
    Purple K when the Fire Suppression System activated, including paying $2.2 million
    to settle with the Individual Plaintiffs, so S&B seeks indemnification from Scallon
    for Scallon’s negligence and not for S&B’s negligence, which means the express
    negligence rule does not apply.
    S&B further argues that the Terms and Conditions applicable to the Purchase
    Order included an express warranty, and the Subcontract itself included a warranty.
    According to S&B, Scallon’s argument that there is no express warranty because the
    parties’ Subcontract was predominantly for “services” not covered by the UCC is
    “baseless” because the parties’ agreements encompassed goods, such as hardware,
    20
    cabinets, and workstations. S&B also argues that, under Texas law, an implied
    warranty need not be for tangible goods to be enforceable. 13
    S&B further argues that because Scallon built and configured the Process
    Control System and Safety Control System pursuant to the Purchase Order, S&B is
    not precluded from seeking consequential damages because the Terms and
    Conditions that apply to the Purchase Order do not contain a contractual disclaimer
    of consequential damages. According to S&B, the consequential damages disclaimer
    in the Subcontract “has no bearing on the scope and effect of the indemnity provision
    found earlier in the Subcontract.” S&B then argues that Scallon’s argument
    regarding the distinction between consequential and direct damages only applies to
    damages proximately caused by breach of terms of the Subcontract and not the
    Purchase Order.
    S&B attached to its response copies of the parties’ Purchase Order, the Terms
    and Conditions to the Purchase Order, the Subcontract, selected pages from the
    transcript of Paul Dougharty’s deposition, selected pages from the transcript of Chris
    Lampman’s deposition, and selected pages from the transcript of Peter Mondello’s
    deposition.
    13
    Citing 
    Tex. Bus. & Com. Code Ann. §§ 2.314
    , 2.315; Nghiem v. Sajib, 
    567 S.W.3d 718
    , 724-25 (Tex. 2019).
    21
    Sunoco’s Response to Scallon’s MSJ
    Sunoco also filed a response to Scallon’s motion for summary judgment.
    Therein, Sunoco alleged that “Scallon supplied a defective electrical control product
    to Sunoco, leading to the Plaintiffs’ injuries in this case for which Sunoco now seeks
    indemnification.” Sunoco further alleged that the Purchase Order included a
    warranty provision that runs to its benefit as S&B’s client, and it has an applicable
    indemnity provision. Sunoco also alleged that the Subcontract between S&B and
    Scallon also included warranty and indemnity provisions. Sunoco alleged that it filed
    its cross-claim against Scallon for breach of contract for failing to indemnify Sunoco
    against the Individual Plaintiffs’ claims for breaching the specific and implied
    warranties in the Purchase Order and the Subcontract.
    Sunoco argues that Scallon is just wrong about the application of the express
    negligence rule because it does not preclude Sunoco from recovering because
    Sunoco is seeking a recovery for Scallon’s negligence and not for a recovery of
    damages caused by Sunoco’s negligence. Sunoco also argues that the implied
    warranties under the UCC apply because the system Scallon sold to S&B and to
    Sunoco is a good, as defined under the UCC. According to Sunoco, Scallon’s motion
    only addresses its Subcontract with S&B, and Scallon has failed to address the terms
    of the Purchase Order. And Sunoco argues that the services Scallon supplied were
    “incidental” to the goods for the PLC/Safety Control Services, which were valued
    22
    in excess of $1.3 million. Further, Sunoco maintains that, under the UCC, computer
    programming is embedded in computer hardware (or goods), so that the computer
    programming at issue in this case is a “good” and that the UCC’s warranties apply.
    In addition, Sunoco argues that the disclaimer of consequential damages in
    the Subcontract does not negate Scallon’s liability because Sunoco’s damages are
    direct. In support of this position, Sunoco points to the “liability and indemnity”
    provision of the Terms and Conditions attached to the Purchase Order, in which the
    seller is obligated to indemnify S&B and its clients from any and all loss, including
    bodily injury “resulting from or in connection with the execution of this Purchase
    Order to the extent of seller’s negligence or willful misconduct.” Sunoco contends
    that, Scallon maintains that Sunoco is limited to repair-and-replace remedies, but the
    parties did not expressly agree that these were the exclusive remedies, and the
    Purchase Order and Subcontract “specifically contemplate[] the damages sought in
    this case.”
    Scallon’s Post-Hearing Brief in Support of its MSJ
    In an additional brief filed after the hearing on Scallon’s motion for summary
    judgment, Scallon argues, “Scallon was never sued by Plaintiff[s]. Plaintiff[s] only
    asserted allegations of negligence against S&B and Sunoco. S&B and Sunoco
    entered into a voluntary settlement with Plaintiffs. [] The only damages sought by
    S&B and Sunoco are the amounts paid by each to defend and resolve the underlying
    23
    litigation.” Scallon also states that, although S&B’s first third-party claim against
    Scallon asserted claims for negligence and contribution, the live pleading asserted
    claims only for breach of contract and warranty. Scallon also asserts that Sunoco had
    also “recast” its claims against Scallon for contribution, negligence, and indemnity
    as claims for breach of contract and warranty.
    According to Scallon, S&B’s and Sunoco’s claims for contribution and
    indemnity are contingent on the Individual Plaintiffs’ recovery of damages. Scallon
    argues that the Purchase Order and Subcontract in this case include no language
    providing that S&B and Sunoco with a right to settle claims brought against them
    and then seek reimbursement for what they paid in settlement from Scallon.14
    Scallon argues that by voluntarily settling with the Individual Plaintiffs, S&B and
    Sunoco “‘have destroyed any forum for determining who was at fault.’”15
    Scallon argues that the UCC provides only that the measure of direct damages
    for a breach of warranty claim is the difference between the value of the goods
    accepted and the value of the goods if they had been as warranted, but that S&B and
    14
    Distinguishing Air Liquide Am. Corp. v. Crain Bros., Inc., 
    11 F.Supp.2d 709
    (S.D. Tex. 1997) (finding that the contract specifically provided that Air Liquide
    could settle claims against it and then seek indemnity from Crain, even absent a
    finding of fault by Crain).
    15
    Quoting MAN GHH Logistics GMBH v. Emscor, Inc., 
    858 S.W.2d 41
     (Tex.
    App.—Houston [14th Dist.] 1993, no writ) (where co-defendants cross-claimed
    against one another for contribution after settling with plaintiffs, the defendants’
    contract provided for reciprocal indemnity obligations but not for contractual
    contribution to reimburse the other for any voluntary settlements with plaintiffs).
    24
    Sunoco are seeking “the damages that they paid to the Plaintiffs and defense costs []
    as a result of a voluntary settlement[,]” which would not be recoverable under a
    breach of warranty theory.
    S&B’s Response to Scallon’s Post-Hearing Brief
    Responding to Scallon, S&B alleged that Texas law recognizes claims for
    reimbursement after settlement under a contractual indemnity provision and that
    Scallon’s position that S&B is recasting its contribution and indemnity claims as a
    breach of warranty claim is “fallacious[.]” S&B further argues that, under Texas law,
    a claimant may recover incidental and consequential damages for a breach of
    warranty claim.16
    Sunoco Nonsuit and Zurich Intervention
    In a separate post-hearing brief, Sunoco adopted the arguments in S&B’s post-
    hearing brief. Sunoco subsequently non-suited all claims against Scallon, and the
    trial court dismissed the Sunoco’s claims without prejudice. The following day,
    Zurich filed a petition in intervention, arguing that as Sunoco’s subrogee, it was
    entitled to recover the amount it paid to defend Sunoco and to settle the suit filed by
    the Individual Plaintiffs against Sunoco, its insured. According to Zurich,
    Zurich, as a subrogated Intervenor, asserts that Defendant Scallon
    Control, Inc.’s breaches of contract to indemnify Sunoco, together with
    its breaches of warranty, express and implied, caused the accident and
    the incident which injured the workers who were plaintiffs in the
    16
    Citing 
    Tex. Bus. & Com. Code Ann. § 2.715
    .
    25
    Underlying Case, harm for which Zurich paid both to defend and
    resolve. . . . With respect to Scallon’s contractual indemnity obligations,
    Zurich asserts that Scallon was negligent and the sole or dominant legal
    cause of the accident leading to the Underlying Case and expenses
    sought herein.
    In a response that Zurich filed to Scallon’s motion for summary judgment, Zurich
    adopted the responses Sunoco filed to Scallon’s motion. In a separate Supplemental
    Brief, Zurich adopted S&B’s arguments and argued that after a settlement, a
    contractual indemnity agreement may be enforced.
    Scallon’s MSJ Against Zurich
    Scallon also filed a motion for summary judgment on Zurich’s claims.
    Attached to that motion are copies of the confidential settlement agreements with
    the seven Individual Plaintiffs, executed in June of 2019. In the settlement
    agreements, the Individual Plaintiffs agreed to fully release and discharge their
    claims against Defendants. In another of the provisions in the settlement agreement,
    S&B and Sunoco fully released and discharged each other from any and all claims.
    Scallon argues there is an “insurmountable problem for [Zurich] that it filed
    its intervention one day after Sunoco’s nonsuit was granted *and* 6 years, 11 months
    and 4 days after the underlying loss *and* there is an absolute 4 year statute of
    limitations applicable to UCC warranty claims[].” According to Scallon, Zurich
    seeks to “spin an express or implied warranty claim into a right of full tort
    indemnity[.]” Scallon again argues that neither the Purchase Order (and its Terms
    26
    and Conditions) nor the Subcontract meet the express negligence test. Scallon
    explains that the indemnity language in the Purchase Order is limited to
    indemnification for “Seller’s allocable share of comparative[] negligence[,]” so that
    Scallon is not obligated to indemnify Zurich nor S&B for Sunoco’s nor S&B’s
    negligence. Applying the express negligence rule, Scallon argues that Zurich may
    not recover the “settlement dollars and defense dollars” which it claims. In addition,
    Scallon argues that Zurich and S&B, as settling tortfeasors, have no right to post-
    settlement contribution.17 Due to the settlement and subsequent dismissal of the
    Individual Plaintiffs’ claims against S&B and Sunoco, there is no evidence that, in
    settling, S&B paid more than its percentage of liability, and Zurich may not seek
    indemnity for the costs of defending Sunoco.
    Scallon also argues that implied warranties under the UCC are subject to a
    four-year statute of limitations, the statute of limitations on Zurich’s intervention
    began to run on the date of the underlying loss, and Zurich’s intervention is too late.
    In this case, Scallon states, “all [seven] settling plaintiffs dismissed their claims
    against [S&B and Sunoco] at a time when no plaintiff was claiming against Scallon
    *and* Scallon was before the Court as a third-party defendant[.]” In addition, the
    17
    Citing Beech Aircraft Corp. v. Jinkins, 
    739 S.W.2d 19
    , 21 (Tex. 1987) (The
    Court held that defendants who settled the plaintiff’s entire claim could not preserve
    the right to contribution from an alleged joint tortfeasor who did not participate in
    the settlement and stated, “An agreed judgment incorporating a settlement does not
    provide a basis for subsequent contribution claims.”).
    27
    discovery rule cannot save Zurich because the rule does not apply to UCC breach of
    implied warranty claims.18 Further, the discovery rule does not apply where a
    claimant knows it has sustained a loss, as here, when the Individual Plaintiffs sued
    in August of 2016 for injuries allegedly sustained in January of 2015. Scallon also
    cites to other cases holding that a warranty to perform in a good and workmanlike
    manner may not be used to seek indemnity for negligent injuries to third parties.19
    Zurich’s Response to Scallon and Its First Amended Petition in Intervention
    After Scallon filed its MSJ against Zurich, Zurich filed a First Amended
    Petition in Intervention claiming that, as subrogee or assignee to Sunoco’s rights, it
    is either a direct or a third-party beneficiary under the Purchase Order and
    Subcontract between Scallon and S&B and that its rights to indemnification derive
    from these agreements. Zurich states that its claim for damages is based on Scallon’s
    breach of its contractual obligation to indemnify Zurich, as Sunoco’s subrogee, for
    damages caused by Scallon’s negligent acts or omissions. Zurich specifically denies
    that the negligence of any party other than Scallon caused the mistake in the design
    of the system inputs that resulted in the release of Purple K fire suppressant. And
    18
    Citing PPG Indus., Inc. v. JMB/Hous. Ctrs. Partners Ltd. P’ship, 
    146 S.W.3d 79
     (Tex. 2004) (holding that the UCC requires suit on a breach of warranty
    claim within four years of delivery unless the warranty explicitly guarantees
    performance beyond four years).
    19
    Citing Haring v. Bay Rock Corp., 
    773 S.W.2d 676
    , 680 (Tex. App.—San
    Antonio 1989, no writ); Exxon Corp. v. Roberts, 
    724 S.W.2d 863
    , 871 (Tex. App.—
    Texarkana 1986, writ ref’d n.r.e.).
    28
    Zurich alleges that Scallon’s breaches of contract in failing to indemnify Sunoco and
    Zurich are the cause of the expenses and damages for which it seeks recovery.
    In Zurich’s First Amended Petition in Intervention, Zurich alleges Scallon was
    negligent as follows: (1) Scallon failed to investigate and obtain the information
    necessary to design the circuit in a way that would avoid a discharge due to a brief
    power outage; (2) Scallon failed to anticipate and plan for the effect of a power
    outage; and (3) it failed to assign adequately trained personnel and supervision to
    the project.
    In Zurich’s Response to Scallon’s motion for summary judgment against it,
    Zurich argues that the express negligence rule does not apply because Zurich is not
    seeking indemnity for Sunoco’s negligence but for Scallon’s negligence. Zurich also
    argues that Scallon’s reliance on Beech Aircraft Corp. v. Jinkins, 
    739 S.W.2d 19
    (Tex. 1987), is misplaced because Beech only addresses contribution for tort liability
    and not contractual indemnity. Zurich further asserts that a claim for contractual
    indemnity from a third party does not ripen until the underlying case is resolved and
    the indemnitee’s liability becomes fixed and certain.20 Zurich’s response also
    incorporates all prior responses by S&B and Sunoco.
    20
    Citing Gilbert Tex. Constr., L.P. v. Underwriters at Lloyd’s London, 
    327 S.W.3d 118
    , 134 (Tex. 2010).
    29
    Trial Court Orders
    On January 27, 2022, the trial court granted Scallon’s motion for summary
    judgment and denied S&B’s motion for partial summary judgment. The Order
    expressly stated that it was interlocutory because it did not address Zurich’s
    intervention. On July 15, 2022, the trial court granted Scallon’s motion for summary
    judgment against Zurich.
    On August 17, 2022, the trial court entered a Final Judgment, stating in
    relevant part:
    [I]t is now ORDERED, ADJUDGED AND DECREED that:
    1. S&B Engineers and Constructors LTD and Zurich American
    Insurance Company take nothing by reason of their suits against
    Scallon Controls, Inc.
    2. All costs of court incurred herein are hereby ordered taxed
    against S&B Engineers and Constructors LTD.
    3. This judgment disposes of all issues and parties now before
    the Court.
    4. All relief not expressly granted is denied.
    5. This Judg[]ment is Final.
    Then on September 21, 2022, the trial court signed a nunc pro tunc order confirming
    that the July 15, 2022 order “was intended to be and is a full and final disposition of
    all claims by all parties[.]” S&B and Zurich timely filed their Notices of Appeal.
    Issues
    Appellant S&B raises four issues on appeal. In its first issue, S&B argues that
    the trial court erred in ordering summary judgment for Scallon because the Purchase
    Order was for the sale of goods—namely software programming and system
    30
    integration—that caused the accident. S&B argues that the Purchase Order included
    an express warranty that the goods were fit for their specified purpose, an
    enforceable promise of indemnification for personal injury, and did not include a
    disclaimer of liability for consequential damages.
    In its second issue, S&B argues that the trial court erred if it granted summary
    judgment for Scallon due to a lack of evidence that Scallon’s breach of express or
    implied warranties caused the personal injuries for which S&B paid a settlement to
    the Individual Plaintiffs.
    In its third issue, S&B argues that the trial court erred in granting summary
    judgment for Scallon based on the express negligence rule because that rule does not
    apply to Scallon’s obligations under the Terms and Conditions of the Purchase
    Order, and because the Terms and Conditions obligate Scallon to indemnify S&B
    for Scallon’s own fault.
    In its fourth issue, S&B argues that the trial court erred by granting summary
    judgment for Scallon because S&B’s right to contractual indemnity is “by
    definition” not tort contribution and can be enforced after a settlement.
    Appellant Zurich raises two issues in its brief. In its first issue, Zurich argues
    that the trial court erred by granting summary judgment in favor of Scallon based on
    the express negligence rule because that rule does not void Scallon’s contractual
    obligations.
    31
    In its second issue, Zurich argues that the trial court erred by granting
    summary judgment for Scallon if it did so based on Scallon’s argument that Zurich’s
    claim is not a contractual indemnity claim but rather a claim for contribution under
    tort law.
    Standard of Review
    We review grants of summary judgment de novo. Helena Chem. Co. v. Cox,
    
    664 S.W.3d 66
    , 72 (Tex. 2023); Cantey Hanger, LLP v. Byrd, 
    467 S.W.3d 477
    , 481
    (Tex. 2015). In our review we take as true all evidence favorable to the non-movant,
    indulging every reasonable inference in favor of the non-movant, and resolving any
    doubts in the non-movant’s favor. See Helena Chem. Co., 664 S.W.3d at 73; Valence
    Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005).
    To defeat a no-evidence motion, the non-movant must produce evidence
    raising a genuine issue of material fact as to the challenged elements. See Tex. R.
    Civ. P. 166a(i) (stating that the trial court must grant a no-evidence motion for
    summary judgment “unless the respondent produces summary judgment evidence
    raising a genuine issue of material fact[]”); Helena Chem. Co., 664 S.W.3d at 72. A
    genuine issue of material fact exists if the evidence “‘rises to a level that would
    enable reasonable and fair-minded people to differ in their conclusions.’” First
    United Pentecostal Church of Beaumont v. Parker, 
    514 S.W.3d 214
    , 220 (Tex. 2017)
    (quoting Merrell Dow Pharms., Inc. v. Havner, 
    953 S.W.2d 706
    , 711 (Tex. 1997)).
    32
    The evidence does not create an issue of material fact if it is “‘so weak as to do no
    more than create a mere surmise or suspicion’” that the fact exists. 
    Id.
     (quoting Kia
    Motors Corp. v. Ruiz, 
    432 S.W.3d 865
    , 875 (Tex. 2014)). “Both direct and
    circumstantial evidence may be used to establish any material fact.” Ford Motor Co.
    v. Ridgway, 
    135 S.W.3d 598
    , 601 (Tex. 2004).
    A party moving for a traditional summary judgment must establish that no
    genuine issue of material fact exists, and it is entitled to judgment as a matter of law.
    Tex. R. Civ. P. 166a(c); Randall’s Food Mkts., Inc. v. Johnson, 
    891 S.W.2d 640
    ,
    644 (Tex. 1995). If the moving party produces evidence entitling it to a summary
    judgment, the burden shifts to the nonmovant to present evidence that raises a fact
    issue. Walker v. Harris, 
    924 S.W.2d 375
    , 377 (Tex. 1996). In determining whether
    there is a disputed fact issue precluding summary judgment, evidence favorable to
    the nonmovant will be taken as true. Nixon v. Mr. Prop. Mgmt. Co., 
    690 S.W.2d 546
    ,
    548-49 (Tex. 1985). We review the summary judgment record in the light most
    favorable to the non-movant, “indulging every reasonable inference and resolving
    any doubts against the motion.” City of Keller v. Wilson, 
    168 S.W.3d 802
    , 824 (Tex.
    2005).
    When the parties cross move for summary judgment and the trial court grants
    one motion and denies the other, we consider both sides’ summary judgment
    evidence, determine all questions presented, and render the judgment the trial court
    33
    should have rendered. Concho Res., Inc. v. Ellison, 
    627 S.W.3d 226
    , 233 (Tex. 2021)
    (citing Gilbert Tex. Constr., L.P. v. Underwriters at Lloyd’s London, 
    327 S.W.3d 118
    , 124 (Tex. 2010)).
    Zurich’s Claims
    We examine Zurich’s subrogation claims first. Zurich contends it has rights
    as Sunoco’s subrogee. Zurich filed its original Petition in Intervention on December
    10, 2021—almost 6 years after the incident and almost 5 years after the Individual
    Plaintiffs filed their Original Petition. Zurich did not intervene until after Sunoco
    had already settled with the Individual Plaintiffs and after Sunoco nonsuited all of
    its counter and crossclaims against all other parties.
    Generally, subrogation actions are subject to the same defenses, including
    limitations, that would apply if the action had been brought by the subrogor. Guillot
    v. Hix, 
    838 S.W.2d 230
    , 232 (Tex. 1992); PNC Mortg. v. Howard, 
    651 S.W.3d 154
    ,
    157 (Tex. App.—Dallas 2021), aff’d, 
    668 S.W.3d 644
     (Tex. 2023). Therefore,
    Zurich’s claims for breach of contract, whether in common law or under the UCC,
    are still subject to a four-year statute of limitations. See PPG Inds., Inc. v. JMB/Hous.
    Ctrs. Partners Ltd. P’ship, 
    146 S.W.3d 79
    , 92 (Tex. 2004) (“The UCC generally
    requires suit on breach of warranty claims within four years of delivery, regardless
    of when the buyer discovers defects in the goods.”) (citing 
    Tex. Bus. & Com. Code Ann. § 2.725
    (a), (b)); Stine v. Stewart, 
    80 S.W.3d 586
    , 592 (Tex. 2002) (explaining
    34
    that a four-year statute of limitations applies to claims for breach of contract) (citing
    
    Tex. Civ. Prac. & Rem. Code Ann. § 16.051
    )). Because Zurich filed its Petition in
    Intervention outside the applicable limitations period, the trial court could have
    based its summary judgment on the conclusion that the intervention seeking
    subrogation was wholly barred by limitations. We agree and we overrule both of
    Zurich’s issues on appeal.
    S&B’s Issues on Appeal
    S&B’s petition alleges two breaches of contract by Scallon: (1) a breach of
    the “Changes” provision of the Purchase Order and the Subcontract by making
    changes to the work as instructed by S&B without obtaining prior written approval,
    and (2) a breach of the contractual obligation to indemnify S&B. We first examine
    the indemnification issue.
    S&B’s Claim for Breach of Contract for Alleged Failure to Indemnify
    Both the Subcontract and the Purchase Order include indemnification
    provisions. Paragraph 9 of the Subcontract, titled “Liability Indemnity[,]” provides,
    in relevant part,
    SUBCONTRACTOR SHALL DEFEND, INDEMNIFY AND
    SAVE HARMLESS THE CONTRACTOR AND OWNER AND
    THEIR   PARENTS     AND    AFFILIATED   COMPANIES
    (“INDEMNITEES”) FROM AND AGAINST ANY AND ALL LOSS,
    DAMAGE, INJURY, LIABILITY, AND CLAIMS THEREOF FOR
    INJURY TO OR DEATH OF ANY PERSON (INCLUDING AN
    EMPLOYEE OR SUBCONTRACTOR OF AN INDEMNITEE) OR
    FOR LOSS OF OR DAMAGE TO PROPERTY (INCLUDING THE
    35
    PROPERTY OF INDEMNITEES) OR FOR LOSS OR DAMAGE
    ARISING FROM ATTACHMENTS, LIENS OR CLAIMS OF
    MATERIALMEN OR LABORERS TO THE EXTENT CAUSED BY
    THE    NEGLIGENT       ACTS   OR    OMISSIONS    OF
    SUBCONTRACTOR.        CONTRACTOR   SHALL    DEFEND,
    INDEMNIFY AND SAVE HARMLESS THE SUBCONTRACTOR
    FROM AND AGAINST ANY AND ALL LOSS, DAMAGE,
    INJURY, LIABILITY, AND CLAIMS TO THE EXTENT CAUSED
    BY CONTRACTOR. THIS INDEMNITY SHALL NOT APPLY TO
    THE EXTENT THAT SUCH INDEMNIFICATION IS VOID OR
    OTHERWISE UNENFORCEABLE UNDER APPLICABLE LAW IN
    EFFECT ON OR VALIDLY RETROACTIVE TO THE DATE OF
    THIS AGREEMENT. . . .
    Paragraph 12 of the Terms and Conditions of the Purchase Order, titled “Liability
    and Indemnity[,]” provides, in relevant part,
    OTHER CLAIMS. TO THE MAXIMUM EXTENT PERMITTED
    BY APPLICABLE LAW, SELLER SHALL DEFEND, INDEMNIFY
    AND HOLD HARMLESS S&B, AND ITS AFFILIATED
    COMPANIES, SUBSIDIARIES AND CLIENTS FROM AND
    AGAINST ANY AND ALL LOSS, DAMAGE, CLAIM, SUIT,
    LIABILITY, STRICT LIABILITY, PRODUCT LIABILITY,
    JUDGMENT AND EXPENSE (INCLUDING ATTORNEY’S FEES
    AND OTHER COSTS OF LITIGATION) AND ANY FINES,
    PENALTIES AND ASSESSMENTS, ARISING OUT OF (A)
    DAMAGE TO OR LOSS OF PROPERTY OR (B) BODILY INJURY,
    DISEASE OR DEATH TO PERSONS OTHER THAN EMPLOYEES
    OF SELLER, ITS AGENTS OR SUBCONTRACTORS RESULTING
    FROM OR IN CONNECTION WITH THE EXECUTION OF THIS
    PURCHASE ORDER TO THE EXTENT OF SELLER’S
    NEGLIGENCE OR WILLFUL MISCONDUCT. IN CASE OF
    COMPARATIVE, CONCURRENT AND/OR CONTRIBUTING
    NEGLIGENCE, FAULT OR STRICT LIABILITY OF SELLER OR
    BUYER, WHETHER THROUGH ITS EMPLOYEES AND/OR
    REPRESENTATIVES, SELLER’S DUTY TO INDEMNIFY AND
    HOLD HARMLESS REFERRED TO IN THE PREVIOUS
    SENTENCE SHALL BE SELLER’S ALLOCABLE SHARE OF
    36
    COMPARATIVE, CONCURRENT AND/OR CONTRIBUTING
    NEGLIGENCE, FAULT OR STRICT LIABILITY.
    In Scallon’s motions for summary judgment, Scallon argued that the express
    negligence rule precludes S&B from seeking indemnification from Scallon for
    S&B’s own negligence. Under the express negligence rule, “parties seeking to
    indemnify the indemnitee from the consequences of its own negligence must express
    that intent in specific terms [] within the four corners of the contract.” Ethyl Corp.,
    725 S.W.2d at 708; see also Fisk Elec. Co. v. Constructors & Assocs., 
    888 S.W.2d 813
    , 813-14 (Tex. 1994); SpawGlass, Inc. v. E.T. Servs., Inc., 
    143 S.W.3d 897
    , 899
    (Tex. App.—Beaumont 2004, pet. denied) (per curiam) (“The express negligence
    rule requires that the intent of the party seeking indemnity from the consequences of
    that party’s own future negligence must be expressed in unambiguous terms within
    the four corners of the contract.”). The rule is one of contract construction or
    interpretation. See Fisk, 888 S.W.2d at 814.
    In Fisk, Fisk Electric Company (“Fisk”) entered into a contract with
    Constructors & Associates (“Constructors”). Id. One of Fisk’s employees was
    injured on the job, and the employee sued Constructors for negligence. Id.
    Constructors then brought a third-party action against Fisk seeking indemnification.
    Id. The contract between Fisk and Constructors provided, “to the fullest extent
    permitted by law, [Fisk] shall indemnify, hold harmless, and defend [Constructors]
    . . . from and against all claims, damages, losses, and expenses” arising out of or
    37
    resulting from the performance of Fisk’s work. Id. Applying Ethyl, the Texas
    Supreme Court held Fisk had no obligation to indemnify Constructors under the
    parties’ contract because the claim against Constructors was for Constructors’ own
    negligence and because the parties’ contract did not meet the requirements of the
    express negligence rule. Id.
    Many Texas courts, including our Court, have discussed the application of the
    express negligence doctrine. For example, in Faulk Management Services v. Lufkin
    Industries, Inc., 
    905 S.W.2d 476
    , 478 (Tex. App.—Beaumont 1995, writ denied),
    Faulk Management Services (“Faulk”) provided janitorial services to Lufkin
    Industries (“Lufkin”) under a written agreement between the parties which contained
    an indemnity provision. 
    Id. at 477
    . Harrison, one of Faulk’s employees, was injured
    while working at Lufkin. 
    Id.
     Harrison sued Lufkin for negligence, alleging that
    Lufkin failed to provide a safe place to work or failed to warn of hidden dangers. 
    Id.
    Lufkin demanded indemnity and defense from Faulk based on its contract with
    Faulk. 
    Id. at 477-48
    . The trial court granted summary judgment in favor of Lufkin.
    
    Id. at 477
    . On appeal, this Court affirmed the trial court’s judgment because the
    parties’ contract expressly provided, in relevant part,
    It is the intention of the Seller and/or Contractor to indemnify Lufkin
    Industries, Inc. even in the event that any such claims, demands,
    actions or liability arises in whole or in part from warranties, express
    or implied, defects in materials, workmanship or design, condition of
    property or its premises and/or negligence of Lufkin Industries, Inc. or
    any other fault claims as a basis of liability for Lufkin Industries, Inc.
    38
    
    Id. at 478
    . This Court held that the contract met the express negligence test because
    it did not limit indemnification to claims caused by Faulk and provided for indemnity
    arising out of performance of the contract, even if wholly caused by Lufkin’s
    negligence. Id.; see also SpawGlass, Inc., 
    143 S.W.3d at 900-01
     (holding that the
    parties’ agreement expressly provided that the subcontractor indemnify the
    contractor for the consequences of contractor’s own negligence).
    In the agreements at issue here, unlike the language at issue in Faulk, here the
    indemnity language fails to specify that Scallon will indemnify S&B for S&B’s own
    negligence and it is more like the language in Gilbane Building Co. v. Keystone
    Structural Concrete, Ltd., 
    263 S.W.3d 291
     (Tex. App.—Houston [1st Dist.] 2007,
    no pet.). In Gilbane, Gilbane Building Co. (“Gilbane”), a general contractor,
    executed a subcontract with Keystone Structural Concrete, Ltd. (“Keystone”) for
    work at Rice University. 
    Id. at 294
    . One of Keystone’s employees was injured during
    construction, and the employee sued Gilbane for negligence. 
    Id.
     The employee
    settled with Gilbane, and Gilbane’s insurers paid the settlement. 
    Id.
     Then Gilbane
    sued Keystone and its insurer seeking to recover the amounts Gilbane paid to settle
    the employee’s claim. 
    Id.
     The appellate court affirmed the summary judgment on
    Gilbane’s claim for contractual indemnity because “the contractual indemnity
    provision [was] not enforceable because Gilbane was sued for its own negligence,
    the indemnity provision [did] not expressly indemnify Gilbane for its own
    39
    negligence, and therefore, it [did] not comply with the express negligence test
    mandated by Texas law.” 
    Id. at 296
    . The Court further stated, “only Gilbane was
    sued for negligence; Keystone was not sued.” 
    Id. at 297
    . As stated by the Gilbane
    court, the policy underlying the express negligence rule is to prevent post-settlement
    “satellite litigation” about who caused the plaintiff’s injury. 
    Id. at 298
    .
    Here, S&B and Sunoco were sued for negligence, and the Individual Plaintiffs
    made no claim against Scallon. S&B and Sunoco settled with the Individual
    Plaintiffs, and then sought indemnification under the contract (either the Subcontract
    and Purchase Order, or both) for the amounts they paid to settle. However, in this
    case, the indemnification provisions of both the Subcontract and the Purchase Order
    only require Scallon to indemnify S&B (and its clients) for Scallon’s negligence and
    not for S&B’s own negligence. We conclude that S&B’s claim against Scallon for
    indemnification is barred by the express negligence rule. See Fisk, 888 S.W.2d at
    814; Ethyl Corp., 725 S.W.2d at 708; Faulk Mgmt. Servs., 905 S.W.2d at 478. As in
    Gilbane, S&B and Sunoco were sued for their own negligence. Scallon was not sued
    by the Individual Plaintiffs. S&B may not seek indemnification from Scallon where
    S&B settled the Individual Plaintiffs’ claims against S&B for negligence, and the
    Individual Plaintiffs did not state a claim for negligence against Scallon, and where
    the contracts between S&B and Scallon did not expressly provide that Scallon was
    obligated to indemnify S&B for S&B’s own negligence. See Gilbane, 
    263 S.W.3d 40
    at 296-97. And we agree with Gilbane that the application of the express negligence
    rule prevents post-settlement “satellite litigation” about who caused the Individual
    Plaintiffs’ injuries. Id. at 298.
    Although S&B maintains that its claim for contractual indemnity is not one
    for contribution, we also note the record provides no basis for S&B to seek
    contribution against Scallon. Although the terms “contribution” and “indemnity”
    may be used interchangeably, they do not mean the same thing. “Contribution” refers
    to the payment by each tortfeasor of its proportionate share of the plaintiff’s
    damages. See Gus M. Hodges, Contribution and Indemnity Among Tortfeasors, 
    26 Tex. L. Rev. 150
    , 150 (1947). By contrast, indemnity refers to the “shifting [of] the
    entire burden of loss from one tortfeasor to another.” B & B Auto Supply, Sand Pit
    & Trucking Co. v. Cent. Freight Lines, Inc., 
    603 S.W.2d 814
    , 816 (Tex. 1980). The
    Texas Supreme Court has explained that “[t]he essential prerequisites for a
    contribution claim are a judgment finding the party seeking contribution to be a joint
    tortfeasor and the payment by such party of a disproportionate share of the common
    liability. An agreed judgment incorporating a settlement does not provide a basis for
    subsequent contribution claims.” Beech Aircraft Corp., 739 S.W.2d at 21. The
    appellate record in this case does not include a judgment finding Scallon to be a joint
    tortfeasor with S&B. See 
    Tex. Civ. Prac. & Rem. Code Ann. § 32.002
     (Recovery for
    contribution is only available against a “codefendant against whom judgment is also
    41
    rendered.”). Therefore, the record provides no basis for S&B to claim contribution
    against Scallon. See id.; Beech Aircraft Corp., 739 S.W.2d at 21.
    S&B’s Claims for Breach of Contract and Breach of Warranty
    Appellants do not argue in their appellate briefs that the trial court erred in
    granting summary judgment for Scallon on S&B’s claim for breach of contract or
    breach of warranty claims based on Scallon’s alleged failure to obtain prior written
    approval for changes in the work or for failing to design and install a non-fail-safe
    system. However, in one statement in their appellate brief, S&B does state that
    breach of warranty is a type of “fault” that would trigger Scallon’s contractual duty
    to indemnify S&B. That said, Appellants’ briefs do not include a “succinct, clear,
    and accurate statement” of any argument supported by relevant authority and
    citations to the record that the trial court erred in granting summary judgment for
    Scallon on S&B’s claim for breach of contract or breach of warranty claims based
    on Scallon’s alleged failure to obtain prior written approval for changes in the work
    or for failing to design and install a non-fail-safe system. See Tex. R. App. P. 38.1(h),
    (i). Additionally, Appellants have failed to identify evidence of damages incurred
    due to any such alleged breach, and under the UCC, the remedy for breach for non-
    conforming goods is the “difference at the time and place of acceptance between the
    value of the goods accepted and the value they would have had if they had been as
    warranted[.]” See 
    Tex. Bus. & Com. Code Ann. § 2.714
    (b).
    42
    Conclusion
    To summarize, we conclude that the trial court did not err in granting summary
    judgment in favor of Scallon on S&B’s and Zurich’s claims for indemnity, for breach
    of contract, and breach of warranty. We overrule S&B’s and Zurich’s issues, and we
    affirm the trial court’s judgment.
    AFFIRMED.
    LEANNE JOHNSON
    Justice
    Submitted on September 18, 2023
    Opinion Delivered May 23, 2024
    Before Golemon, C.J., Johnson and Wright, JJ.
    43
    

Document Info

Docket Number: 09-22-00261-CV

Filed Date: 5/23/2024

Precedential Status: Precedential

Modified Date: 5/24/2024