Bes design/build, LLC v. United States ( 2022 )


Menu:
  •        In the United States Court of Federal Claims
    No. 20-1834C
    (E-Filed: January 11, 2022)
    )
    BES DESIGN/BUILD, LLC,                       )
    )
    Plaintiff,              )    Motion to Transfer; 41 U.S.C. § 7107(d).
    )
    v.                                           )
    )
    THE UNITED STATES,                           )
    )
    Defendant.              )
    )
    Todd A. Jones, Raleigh, NC, for plaintiff.
    Ioana Cristei, Trial Attorney, with whom were Brian M. Boynton, Acting Assistant
    Attorney General, Martin F. Hockey, Jr., Acting Director, Steven J. Gillingham, Assistant
    Director, Commercial Litigation Branch, Civil Division, United States Department of
    Justice, Washington, DC, for defendant. Bailey Kapfer, of counsel.
    OPINION
    CAMPBELL-SMITH, Judge.
    On September 20, 2021, defendant filed a motion to transfer this case to the
    Civilian Board of Contract Appeals (CBCA) for potential consolidation with plaintiff’s
    cases that are currently pending before that board and to stay all proceedings in this court
    until the court rules on the motion to transfer. See ECF No. 17. Plaintiff filed a response
    in opposition to the motion to transfer on October 18, 2021, see ECF No. 20; and on
    October 29, 2021, defendant filed a reply in support of the motion, see ECF No. 23.
    The motion is now fully briefed, and ripe for decision. The court has considered
    all of the parties’ arguments and addresses the issues that are pertinent to the court’s
    ruling in this opinion. For the following reasons, defendant’s motion is GRANTED in
    part, as to the request for transfer, and DENIED in part as moot, as to the request for a
    stay.
    I.     Background
    Plaintiff filed this Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-09, case on
    December 11, 2020. See ECF No. 1 (complaint). Plaintiff and the United States
    Department of Veteran’s Affairs (VA) contracted in 2015 for plaintiff to provide all the
    necessary labor and materials for a clinic renovation in Fayetteville, Arkansas. See id. at
    1. The VA terminated the contract for default in April 2019. See ECF No. 20 at 6. The
    parties had purportedly agreed to multiple contract modifications and equitable
    adjustments as a result of discrepancies between the contract specifications and the
    conditions at the clinic, including the type of paint required and the location of a sanitary
    sewer to be rerouted. See ECF No. 1 at 4-5, 7. According to plaintiff, defendant
    breached the contract and its duty of good faith and fair dealing when it failed to pay
    plaintiff for these changes. 1 See id. at 9-11.
    Plaintiff also filed two claims at the CBCA—both in October 2019—related to
    defendant’s purported failure to pay plaintiff’s final pay application, defendant’s
    purported failure to compensate plaintiff for a delay, and defendant’s termination of the
    contract for default. See ECF No. 20 at 6-7. Defendant now moves to transfer this case
    to the CBCA to be considered for consolidation with plaintiff’s other cases. See ECF No.
    17 at 10.
    II.    Legal Standards
    Pursuant to the CDA, the court has the authority to direct consolidation or transfer
    of a case under the following circumstances:
    If 2 or more actions arising from one contract are filed in the United States
    Court of Federal Claims and one or more agency boards, for the convenience
    of parties or witnesses or in the interest of justice, the United States Court of
    Federal Claims may order the consolidation of the actions in that court or
    transfer any actions to or among the agency boards involved.
    41 U.S.C. § 7107(d). The decision to consolidate or transfer a case “is a discretionary
    action that embraces a variety of factors, and is an ad hoc determination.” Multi-Roof
    Sys. Co. v. United States, 
    5 Cl. Ct. 245
    , 247 (1984) (citation omitted); see also Joseph
    Morton Co. v. United States, 
    757 F.2d 1273
    , 1280 (Fed. Cir. 1985) (noting the court’s
    “broad discretion in exercising its power to consolidate” matters pursuant to the CDA).
    1
    Plaintiff also alleged a claim related to a delay caused by the discovery of asbestos but
    has since dismissed that claim voluntarily. See ECF No. 14 (stipulation of dismissal).
    2
    In assessing whether consolidation or transfer is appropriate under this statute, the court
    considers several factors, including:
    (1) whether the same contract is involved; (2) whether the cases present the
    same or overlapping issues; (3) whether the [p]laintiff chose to proceed
    initially in the board or at the court; (4) whether substantial efforts have been
    expended in one forum, but not the other; and (5) whether transfer will
    eliminate duplication of efforts.
    Precision Pine & Timber, Inc. v. United States, 
    45 Fed. Cl. 134
    , 135-36 (1999); see also
    In re Morse Diesel Int’l, 163 F. App’x 878, 879 (Fed. Cir. 2006) (upholding a decision by
    this court based on this framework for determining whether consolidation or transfer is
    appropriate).
    III.   Analysis
    In its motion, defendant argues that the circumstances in this case militate in favor
    of transfer. See ECF No. 17 at 6-10. Plaintiff opposes the motion, arguing that the
    factors weigh against transfer. See ECF No. 20 at 10-15. The court will address each
    factor in turn.
    A.     Whether the Same Contract Is Involved
    The parties agree that the claims presented in this case and those addressed in
    plaintiff’s cases before the CBCA “arise under the same [c]ontract.” ECF No. 20 at 10;
    see also ECF No. 17 at 6. As such, this factor is satisfied in favor of transfer.
    B.     Whether the Cases Present the Same or Overlapping Issues
    Defendant argues that this case and the cases before the CBCA, while not
    “packaged in identical counts,” have the same central question—“the nature of
    [plaintiff’s] performance on the [c]ontract.” ECF No. 17 at 7. According to defendant,
    the evidence that plaintiff has presented at the CBCA “involves the issues it is litigating
    before the [c]ourt,” 
    id.,
     and “many of the same witnesses and documents will be central
    to supporting” plaintiff’s case here and at the CBCA, 
    id. at 8
    . Defendant thus argues that
    the issues “arise out of the same operative facts and seek the same relief,” ECF No. 23 at
    2, in addition to requiring “similar, if not identical, legal analysis,” and are therefore
    overlapping, 
    id. at 3
    .
    Plaintiff, however, argues that the issues are “vastly different,” because they
    involve different aspects of defendant’s failure to compensate plaintiff—the CBCA cases
    relate to a delay, a specific pay application, and the termination for default, while this
    case relates to pay for additional paint and sewer line work. ECF No. 20 at 10. Plaintiff
    3
    asserts that the work it claims in this case is not covered by the pay application in the
    CBCA cases and “just because testimony was offered at the CBCA hearing relating to the
    additional paint work and the sanitary sewer lines, does not mean that those issues were
    presented to the Board for adjudication.” 
    Id. at 11
    . Plaintiff further argues that the
    central question is also different—while the CBCA cases may have been about plaintiff’s
    performance on the contract, this case is about “two specific items of performance.” 
    Id. at 12
    .
    After a careful review of the issues raised in each proceeding, the court agrees
    with defendant that this factor supports transfer to the CBCA. Neither the statute nor the
    caselaw requires that the issues presented in each case be entirely synonymous to justify
    consolidation or transfer. Here, plaintiff seeks damages for defendant’s alleged breach of
    contract, which, as defendant argues, is predicated on an analysis of the language of the
    contract and the VA’s duties thereunder. See ECF No. 23 at 3. The same issues, broadly
    speaking, will be addressed by the CBCA as it determines whether plaintiff is entitled to
    compensation for other issues that arose under the contract and whether defendant
    appropriately terminated the contract for default.
    C.     Whether the Plaintiff Chose to Proceed Initially Either before the Board or
    the Court
    According to plaintiff, it appealed the VA’s denial of its first certified claim to
    the CBCA on July 17, 2019, and filed its formal complaint, BES Design/Build, LLC v.
    Department of Veterans Affairs, CBCA Case No. 6560, on October 10, 2019. See ECF
    No. 20 at 6 (citing ECF No. 17-1 at 91). Plaintiff appealed the VA’s failure to issue a
    decision on its second certified claim to the CBCA, BES Design/Build, LLC v.
    Department of Veteran’s Affairs, CBCA Case No. 6453, on October 11, 2019. See 
    id. at 7
     (citing ECF No. 17-1 at 96). Plaintiff filed this case on December 11, 2020. See ECF
    No. 1.
    Plaintiff does not dispute these facts, but argues that this factor does not support
    transfer because its CBCA cases are “so much ‘further along’[ ] that [they] have
    essentially concluded.” ECF No. 20 at 13. Plaintiff argues that because the record is
    closed in its other cases, and the issues in this case were not argued before the CBCA,
    plaintiff “would not be able to have these issues adjudicated based on the current (and
    closed) record before the Board.” 
    Id.
     While this may be true, plaintiff’s argument on this
    point is irrelevant as to which forum it first pursued. Further, this court cannot order
    consolidation of cases in another forum, and trusts that the CBCA would undertake an
    appropriate analysis to determine whether this case should remain a separate but related
    case or be consolidated with plaintiff’s other cases.
    Because plaintiff’s CBCA cases were filed first, this factor favors transfer.
    4
    D.     Whether Substantial Efforts Have Been Expended in One Forum
    Defendant argues that both parties have “already expended—and will continue to
    expend—substantial effort” litigating plaintiff’s CBCA cases. ECF No. 17 at 8. Plaintiff
    repeats its prior argument that the CBCA cases are much further along, to the point that
    they have “essentially concluded.” ECF No. 20 at 14.
    The parties have been through the CBCA’s discovery process and concluded a
    hearing at the CBCA on both cases. See 
    id.
     In comparison, proceedings before the court
    have not progressed even to the filing of an answer. The CBCA has clearly invested
    more substantial resources in plaintiff’s cases than the court has in the instant litigation.
    For these reasons, this factor supports transfer.
    E.     Whether Transfer Will Eliminate Duplication of Efforts
    Given the overlapping nature of the issues presented before the CBCA and the
    court, defendant argues that litigation in one forum will “eliminate unnecessary
    duplication of efforts” and mitigate against the possibility of this court’s decision being
    collaterally estopped by the CBCA’s decision. 
    Id. at 9
    . Specifically, defendant argues
    that the CBCA’s decision, given the evidence before it, “would likely result in claim or
    issue preclusion with one or both claims here.” ECF No. 23 at 5. Defendant further
    contends that transferring this case would permit both the forum and defendant’s
    attorneys with the most familiarity with the facts at issue to hear the case, eliminating
    unnecessary effort by the court and counsel in becoming familiar with the case. See 
    id. at 6
    . In opposition, plaintiff reiterates its argument that the issues in this case are different
    from the CBCA issues, and that a transfer would necessarily require the CBCA to reopen
    discovery and the record to litigate the additional issues. See ECF No. 20 at 14-15.
    The court, again, agrees with defendant. The court’s and the parties’ resources are
    better allocated to matters that are not being evaluated concurrently by a separate
    tribunal. In addition, plaintiff’s argument that the CBCA would be required to re-open
    the previously-filed cases assumes that this matter would be consolidated with the earlier
    cases, which is not necessarily the case. As such, this factor supports transfer.
    IV.    Conclusion
    Accordingly, for foregoing reasons:
    (1)    Defendant’s motion to transfer this case to the CBCA, ECF No. 17, is
    GRANTED in part, as to the request for transfer, and DENIED in part as
    moot, as to the request for stay; and
    5
    (2)   The clerk’s office is directed to TRANSFER this case to the Civilian
    Board of Contract Appeals by DELIVERING a certified copy of this
    opinion, a copy of the docket sheet in this matter, and copies of the
    documents that comprise the balance of the record to:
    Civilian Board of Contract Appeals
    Scott W. Sylke, Clerk of the Board
    1800 M Street, NW, 6th Floor
    Washington, DC 20036
    IT IS SO ORDERED.
    s/Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Judge
    6
    

Document Info

Docket Number: 20-1834

Judges: Patricia E. Campbell-Smith

Filed Date: 1/11/2022

Precedential Status: Precedential

Modified Date: 1/11/2022