Sufi Network Services, Inc. v. United States ( 2015 )


Menu:
  •        In the United States Court of Federal Claims
    No. 11-453C
    (Filed: December 7, 2015)
    **************************************** *
    SUFI NETWORK SERVICES, INC.,             *
    *
    *             Claim for Overhead and Profit as a
    Plaintiff,           *             Mark-up on Recovery of Attorneys’
    *             Fees; Start Date for Running of
    v.                                       *             Interest on Attorneys’ Fees and
    *             Expenses; Proposed Change in
    Method for Determining Attorneys’
    THE UNITED STATES,                       *             Fees.
    *
    Defendant.           *
    *
    **************************************** *
    Frederick W. Claybrook, Jr., with whom was Brian T. McLaughlin, Crowell & Moring
    LLP, Washington, D.C., for Plaintiff.
    Douglas T. Hoffman, with whom were Benjamin C. Mizer, Principal Deputy Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, and Steven J. Gillingham, Assistant
    Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice,
    Washington, D.C., for Defendant.
    OPINION AND ORDER
    WHEELER, Judge.
    This case is before the Court on remand from the U.S. Court of Appeals for the
    Federal Circuit. SUFI Network Servs., Inc. v. United States, 
    785 F.3d 585
    (Fed. Cir. 2015).
    In the decision reviewed on appeal, this Court had awarded attorneys’ fees to SUFI with
    interest, but had denied SUFI’s request for overhead and profit on attorneys’ fees. SUFI
    Network Servs., Inc. v. United States, 
    113 Fed. Cl. 140
    (2013). The Federal Circuit
    affirmed this Court’s award to SUFI of $697,702.50 in attorneys’ fees and $25,486.81 in
    expenses, but vacated and remanded this Court’s ruling with respect to interest, overhead,
    and profit. 
    SUFI, 785 F.3d at 595
    . The parties have briefed these issues on remand. Oral
    argument is unnecessary.
    In considering SUFI’s cross-appeal for recovery of overhead and profit, the Federal
    Circuit observed that “[u]nder applicable common law, damages for breach of contract
    should place the wronged party in as good a position as it would have been had the
    breaching party fully performed.” 
    Id. at 594
    (citing Mass. Bay Transp. Auth. v. United
    States, 
    129 F.3d 1226
    , 1232 (Fed. Cir. 1997)). The Federal Circuit concluded that “we
    vacate the trial court’s denial of overhead and profit and remand with instructions that the
    trial court apply law consistent with this opinion.” 
    Id. at 595.
    The Federal Circuit thus left
    it to this Court to determine, based upon the common law of damages, whether and to what
    extent SUFI should recover overhead and profit on its attorneys’ fees claim.1
    Discussion
    This case is part of a much larger series of administrative appeals and breach of
    contract actions spanning ten years of litigation, in which there have been thirteen decisions
    from the Armed Services Board of Contract Appeals (“ASBCA”), five decisions from this
    Court, and two appeals to the Federal Circuit.2 One additional appeal concerning the
    finality of the ASBCA’s February 3, 2015 decision on the merits is still pending before the
    Federal Circuit. SUFI CFC V, 
    122 Fed. Cl. 257
    (2015), appeal filed, No. 11-804 (Sept.
    24, 2015). The overall dispute stems from a planned fifteen-year contract to provide long-
    distance telephone services in the lodging guest rooms on Air Force bases in Germany.
    The contracting parties were SUFI and the Air Force Non-Appropriated Funds Purchasing
    Office (“Air Force”). The contract was cut short by the Air Force’s material breaches of
    contract.
    1
    SUFI’s assertion that the Federal Circuit mandated the award of overhead and profit on attorneys’ fees to
    SUFI is incorrect. See Pl.’s Oct. 19, 2015 Br. at 1 (citing SUFI Network Servs., Inc. v. United States, 
    785 F.3d 585
    , 594-95 (Fed. Cir. 2015)). The Federal Circuit’s mandate simply requires this Court to review the
    issue again by applying principles of common law damages instead of the Federal Acquisition Regulation.
    2
    The ASBCA’s thirteen reported opinions are referred to as “SUFI ASBCA I” through “SUFI ASBCA
    XIII”. Likewise, the previous opinions in this case, No. 11-453, and its related case, No. 11-804C, are
    referred to, in chronological order, as “SUFI CFC I” through “SUFI CFC V.” SUFI ASBCA I, ASBCA
    No. 54503, 04–1 BCA ¶ 32606 (Apr. 22, 2004); SUFI ASBCA II, ASBCA No. 54503, 04–2 BCA ¶ 32714
    (Aug. 17, 2004); SUFI ASBCA III, ASBCA No. 54503, 04–2 BCA ¶ 32788 (Nov. 1, 2004); SUFI ASBCA
    IV, ASBCA No. 55306, 06–2 BCA ¶ 33444 (Nov. 8, 2006); SUFI ASBCA V, ASBCA No. 55306, 07–1
    BCA ¶ 33485 (Feb. 7, 2007); SUFI ASBCA VI, ASBCA No. 55306, 07–1 BCA ¶ 33535 (Mar. 21, 2007);
    SUFI ASBCA VII, ASBCA No. 55948, 08–1 BCA ¶ 33766 (Jan. 9, 2008); SUFI ASBCA VIII, ASBCA
    No. 55306, 09–1 BCA ¶ 34018 (Nov. 21, 2008); SUFI ASBCA IX, ASBCA No. 55306, 09–2 BCA ¶ 34201
    (Jul. 15, 2009); SUFI ASBCA X, ASBCA No. 55306, 10–1 BCA ¶ 34327 (Dec. 14, 2009); SUFI ASBCA
    XI, ASBCA No. 55306, 10–1 BCA ¶ 34415 (Apr. 5, 2010); SUFI ASBCA XII, ASBCA No. 55306, 15-1
    BCA ¶ 35,878 (Fed. 2, 2015); SUFI ASBCA XIII, ASBCA No. 55306, 15-1 BCA ¶ 35,992 (May 20, 2015);
    SUFI CFC I, 
    102 Fed. Cl. 656
    (2012); SUFI CFC II, 
    105 Fed. Cl. 184
    (2012); SUFI CFC III, 
    108 Fed. Cl. 287
    (2012), aff’d in part, rev’d in part, 
    755 F.3d 1305
    (2014); SUFI CFC IV, 
    113 Fed. Cl. 140
    (2013), aff’d
    in part, vacated in part, 
    785 F.3d 585
    (2015); SUFI CFC V, 
    122 Fed. Cl. 257
    (2015), appeal filed, No. 11-
    804 (Sept. 24, 2015); SUFI Network Servs., Inc. v. United States, 
    755 F.3d 1305
    (Fed. Cir. 2014); SUFI
    Network Servs., Inc. v. United States, 
    785 F.3d 585
    (Fed. Cir. 2015).
    2
    A. Overhead and Profit on Attorneys’ Fees
    Cumulatively, SUFI has succeeded in its quest to be compensated for the Air
    Force’s breaches, including the recovery of lost profits and overhead caused by the Air
    Force’s conduct. In the breach damages award exceeding $110 million, SUFI established
    its entitlement to more than $58 million in lost profits. SUFI also received overhead
    compensation relating to its performance of extra work under the contract. The issue now
    remaining is whether SUFI should receive additional profit and overhead as a mark-up on
    the attorneys’ fees of its outside law firm, Crowell & Moring.
    SUFI contends that it should receive a 25 percent profit on Crowell & Moring’s
    attorneys’ fees, based upon two provisions included in Modification 007 to the contract,
    dated February 18, 2000. These two provisions state as follows:
    3.11.1 “Additional Work Requested”
    Additional work requested by the LFM [Lodging Facilities
    Manager] not specified in the contract will be the responsibility
    of the Lodging operation to fund. This pertains to items such
    as office moves, additional phones, and other requests not
    covered under this contract. The LFM must submit a request
    for proposal to the Contractor specifying the work to be
    accomplished and the time frame required. The Contractor
    will respond within 15 duty days and provide a technical
    proposal and cost proposal of no more than 25% over cost to
    the Lodging Manager and [Air Force] at no additional charge
    to the government.
    3.11.2 “Facility Renovations”
    The LFM must notify the contractor before an existing building
    is scheduled for renovation so the contractor may remove any
    existing telephones, frames, and other equipment. The LFM
    must notify the contractor 60 days in advance for a major
    renovation (i.e. and [sic] entire building) and 30 days in
    advance for a minor renovation (i.e., individual rooms or
    floors. Contractor shall submit a proposal of no more than 25%
    over cost to LFM and [Air Force] in three separate areas: 1)
    removal of equipment prior to renovation; 2) cost of
    reinstalling the system temporarily based on LFM
    requirements during renovation if so desired; 3) and full
    reinstallation of phone system when the building is ready again
    3
    for occupancy. [Air Force] and SUFI Network Service will
    work together on a fair and reasonable cost plus price that is
    agreeable to both parties prior to the start of any work.
    (PX 58 at 1-2.)
    These contract provisions on their face do not apply to SUFI’s claim for recovery
    of attorneys’ fees, and would not justify a mark-up on attorneys’ fees. Neither section
    3.11.1 nor 3.11.2 references anything about attorneys’ fees or legal costs. Based upon the
    plain language of the clauses, they apply to “office moves, additional phones, and other
    requests [from the government] not covered under this contract,” as stated in clause 3.11.1,
    and to “major” and “minor” renovations requiring the removal of “existing telephones,
    frames, and other equipment,” as stated in clause 3.11.2.
    Logic would support a distinction between contract performance work managed by
    SUFI under sections 3.11.1 and 3.11.2, and legal work managed and performed by SUFI’s
    outside law firm. A negotiated profit and overhead rate would be entirely appropriate for
    SUFI’s contract work, and indeed SUFI received this compensation as a mark-up on its
    claims. However, the Court is not aware of any contractual basis to grant SUFI a 25
    percent mark-up on legal work performed by Crowell & Moring. Such a mark-up would
    have the effect of increasing Crowell & Moring’s hourly billing rates by 25 percent for no
    apparent reason. SUFI does not cite any other contract provision supporting its claim for
    overhead and profit on fees.
    Lacking any contractual basis for recovery, the Court will turn to the elements for
    establishing recovery under the common law of damages. Common law breach of contract
    damages “are recoverable where: (1) the damages were reasonably foreseeable by the
    breaching party at the time of contracting; (2) the breach is a substantial causal factor in
    the damages; and (3) the damages are shown with reasonable certainty.” Sys. Fuels, Inc.
    v. United States, 
    666 F.3d 1306
    , 1311 (Fed. Cir. 2012) (citing Ind. Mich. Power Co. v.
    United States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005)). Examining SUFI’s claim for a
    profit and overhead mark-up on Crowell & Moring’s attorneys’ fees, the Court finds that
    SUFI does not satisfy any of these three criteria.
    First, looking to the foreseeability that a breaching party would expect to be
    charged for profit and overhead on top of attorneys’ fees, the Court does not see any
    circumstances under which such a mark-up would be foreseeable. Profit normally is
    viewed as a reward for having assumed a business risk of some kind. See Howard O.
    Hunter, Modern Law of Contracts § 14:10 (2015). Here, SUFI did not assume any risk in
    having an outside law firm prepare a contract claim on a contingent fee basis. If the claim
    were successful, as this one was, SUFI would receive a large sum from the Government,
    and it would owe the law firm an agreed percentage for the law firm’s efforts. If the claim
    was not successful, SUFI presumably would not owe the law firm anything, except
    4
    perhaps for expenses.3 There is no risk to SUFI in this arrangement, and thus no basis for
    the breaching party to believe that SUFI should receive a profit on top of the legal fees.
    Compensation for overhead seemingly would be appropriate if SUFI had played
    some role, and had expended some time and effort, in assisting or overseeing the law
    firm’s claim-preparation tasks. However, there is no evidence that SUFI played any
    significant role in this process. Given the contingent fee arrangement with Crowell &
    Moring, SUFI would have no reason or interest to oversee or manage the law firm’s work.
    This was a case of a novice government contractor turning over the complete claim
    preparation work to an experienced and highly reputable law firm. Where SUFI did not
    add anything material to the claim preparation effort, it is difficult to understand why SUFI
    should receive an overhead component. The Air Force, as the breaching party, would not
    have found it foreseeable to pay SUFI overhead for not doing any material work.
    Second, in assessing whether the breach of contract is a substantial causal factor
    for the claimed damages, the Court is simply unable to identify any damages. As noted
    above, the Court does not see that the Air Force’s breach caused SUFI to lose any profit
    or overhead relating to the law firm’s preparation of the claim. Simply put, the record
    does not support a finding that any profit or overhead damages relating to attorneys’ fees
    even exist. SUFI already has received rulings awarding lost profits and overhead as part
    of its breach of contract claim. Thus, the breach of contract did not cause any additional
    damages.
    Third, in deciding whether SUFI has shown damages with reasonable certainty, the
    only result the Court can reach with reasonable certainty is that no additional overhead
    and profit are warranted. It stands to reason that where the Court is unable to identify any
    damages, those damages cannot be shown with reasonable certainty. The record shows
    that SUFI did not perform any of the work and did not incur any risk justifying a profit.
    Therefore, SUFI has failed to establish any overhead or profit damages with reasonable
    certainty. Further, the Court is not aware of any precedent supporting an overhead and
    profit mark-up on an outside law firm’s fees, and the parties have provided none.
    Accordingly, applying the common law of breach of contract damages, SUFI is not
    entitled to any mark-up for overhead and profit on its law firm’s attorneys’ fees.
    3
    SUFI has not produced its contingent fee agreement with Crowell & Moring, ostensibly on attorney-client
    privilege grounds, and thus the agreement is not part of the evidentiary record. The Court cannot determine
    what the terms of the contingent fee agreement may be, a fact that is neither helpful nor hurtful to SUFI’s
    claim. However, if the agreement had been helpful in some respect, presumably SUFI would have produced
    it.
    5
    B. Interest
    The parties disagree on the date when interest should begin to run for attorneys’
    fees, and whether the application of interest on expenses is still an open issue. Since
    Crowell & Moring handled this matter on a contingent fee basis, SUFI received no legal
    bills and incurred no liability for attorneys’ fees as the work was being performed. Indeed,
    it is doubtful that as of today SUFI has paid anything to Crowell & Moring for attorneys’
    fees because the Air Force’s obligation for breach damages to SUFI is not final. The
    Government contends and the Court agrees that the earliest date of interest accrual would
    be December 29, 2010, the date that SUFI submitted its claim for fees and expenses to the
    contracting officer. Def.’s Nov. 9, 2015 Br. at 16-17. The date of the claim is the time
    that SUFI formally put the Air Force on notice that payment of a sum certain would be
    expected. Every day thereafter represents a day that SUFI was denied the use of the funds.
    Therefore, starting interest on the date of claim submittal is a reasonable outcome, and
    would be in line with the treatment of interest under the Contract Disputes Act, 41 U.S.C.
    § 7109(a) (2011). Although this case is not governed by the Contracts Disputes Act, the
    parties likely would accept such a result as being typical in federal procurement law.
    With regard to the running of interest on expenses, the Court agrees with SUFI that
    the Government has waived the right to challenge the Court’s original judgment. Pl.’s
    Oct. 19, 2015 Br. at 4-6. The Government did not appeal this Court’s ruling relating to
    interest on expenses, and therefore the original ruling remains undisturbed. See SUFI IV,
    
    113 Fed. Cl. 140
    (2013).
    C. Proposed Change in Presenting Attorneys’ Fees Claim
    SUFI has recently raised for the first time that its attorneys’ fees calculation should
    be based on the amount it is required to pay Crowell & Moring under the contingent fee
    agreement, rather than using the traditional lodestar method previously presented. Pl.’s
    Oct. 19, 2015 Br. at 7-10. As the Government points out, SUFI presented a traditional
    lodestar method of rates multiplied by hours in its claim to the contracting officer, in its
    complaint, in pretrial filings, during the trial, and on appeal to the Federal Circuit. Def.’s
    Nov. 19, 2015 Br. at 19-28. During the entire trial, and the discovery leading up to trial,
    the parties focused on the reasonableness of the attorneys’ hourly rates and the amount of
    time spent.
    At no time until now has SUFI argued for the recovery of fees based upon its
    contingent fee agreement. This 180 degree reversal has occurred despite the fact that
    SUFI has refused to produce the contingent fee agreement with Crowell & Moring. SUFI
    itself strongly asserted in a February 13, 2012 motion for summary judgment that
    “contingent fee arrangements between the client and the attorney are to be disregarded
    when setting the appropriate fee. . . .” Pl.’s Mot Summ. J. at 11. SUFI relied upon
    Supreme Court precedent that a plaintiff may not recover an amount pursuant to a
    6
    contingent fee agreement. 
    Id. (citing City
    of Burlington v. Dague, 
    505 U.S. 557
    , 562-63
    (1992) (rejecting supplement to lodestar method due to contingent fee arrangement);
    Blanchard v. United States, 
    489 U.S. 87
    , 92-95 (1989) (rejecting the capping of a lodestar
    award by a contingent fee arrangement). Similarly, SUFI failed to raise its new fee
    calculation when, in ruling upon cross-motions for summary judgment, this Court
    extensively discussed the fact that SUFI’s contingent fee arrangement did not bar SUFI’s
    recovery of attorneys’ fees based upon hourly rates and time spent. SUFI CFC II, 
    105 Fed. Cl. 184
    , 192-95 (2012).
    The triggering event to SUFI’s change of position is that this Court, and later the
    ASBCA, greatly increased the damages award for the Air Force’s breach, and thus greatly
    increased the amount of the contingent fee that SUFI would pay. Yet, the Court’s damages
    award stems from the SUFI CFC III, decision, issued on November 8, 2012. See 108 Fed.
    Cl. 287 (2012). SUFI could have raised its alternative theory for recovery of attorneys’
    fees at any time after that date, but it failed to do so. SUFI could have informed the Federal
    Circuit of this new position, but it did not. The Government relied upon SUFI’s lodestar
    method of presentation at every step of this case, and now would have to formulate a brand
    new mode of defense if SUFI were permitted to proceed. Under these circumstances,
    SUFI is equitably estopped from changing its position. Birkelund v. United States, 
    135 Ct. Cl. 503
    , 512-13, 
    142 F. Supp. 459
    , 465 (1956).
    Finally, the Court doubts that it has subject matter jurisdiction of SUFI’s
    significantly revised claim under the contingent fee agreement because that claim has
    never been presented to the contracting officer for a final decision. The Court
    acknowledges that some claims may be revised in litigation without having to be presented
    to the contracting officer. See, e.g., J.F. Shea Co. v. United States, 
    4 Cl. Ct. 46
    , 54 (1983)
    (permitting revision of claim without submission to contracting officer). In this case,
    however, an attorneys’ fees claim based upon a contingent fee agreement presumably
    would be a drastically larger claim based upon very different legal theories of recovery.
    Using typical contingent fee terms (because SUFI has not produced the actual agreement
    here), a one-third recovery by the law firm could exceed $30 million, as opposed to the
    $697,702.50 awarded by this Court and affirmed by the Federal Circuit. Such a claim
    ought to be submitted initially to the contracting officer. This is not a circumstance where
    plaintiff is correcting an error or adding a new legal basis for recovery.
    For all of the foregoing reasons, the Court will not allow SUFI to change its method
    for recovering attorneys’ fees to the amounts due under the contingent fee agreement.
    Conclusion
    Within fourteen days, on or before December 21, 2015, the parties shall file a joint
    status report indicating whether any further proceedings are necessary in this case, and if
    so, what those proceedings may entail.
    7
    IT IS SO ORDERED.
    s/Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    8
    

Document Info

Docket Number: 11-453C

Judges: Thomas C. Wheeler

Filed Date: 12/7/2015

Precedential Status: Precedential

Modified Date: 11/7/2024