Board of Regents of the Nevada System of Higher Education v. United States , 132 Fed. Cl. 435 ( 2017 )


Menu:
  •          In the United States Court of Federal Claims
    No. 16-376C
    (Filed under seal May 31, 2017)
    (Reissued July 5, 2017)
    * * * * * * * * * * * * * * * * * *
    *
    *
    BOARD OF REGENTS OF               *         Post-award bid protest; U.S. Dept. of
    THE NEVADA SYSTEM OF              *         Energy; omissions of required
    HIGHER EDUCATION,                 *         information from proposals; alleged
    on behalf of THE DESERT           *         clerical error; failure to request
    RESEARCH INSTITUTE,               *         clarification; unstated evaluation
    *         method; non-disclosure of incumbent
    Plaintiff,            *         contract staffing information; alleged
    *         disparate treatment due to incumbent
    v.                          *         facilities; Blue & Gold Fleet waiver.
    *
    THE UNITED STATES,                *
    *
    Defendant,            *
    and,                        *
    *
    OAK RIDGE ASSOCIATED              *
    UNIVERSITIES,                     *
    *
    Defendant-Intervenor. *
    *
    * * * * * * * * * * * * * * * * * *
    J. Hatcher Graham, Warner Robins, Ga., for plaintiff.
    Joseph E. Ashman, Commercial Litigation Branch, Civil Division,
    Department of Justice, with whom were Benjamin C. Mizer, Principal Deputy
    Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Deborah A.
    Bynum, Assistant Director, all of Washington, D.C., for defendant. Monekia
    Franklin, Office of General Counsel, and Kristopher D. Muse, Office of Chief
    Counsel, U.S. Department of Energy, Washington, D.C., of counsel.
    Jessica C. Abrahams, Dentons US LLP, with whom was Erin B. Sheppard,
    both of Washington, D.C., for defendant-intervenor. Katherine L. Veeder and
    Deborah N. Rodin, Dentons US LLP, Washington, D.C, of counsel.
    OPINION AND ORDER †
    WOLSKI, Judge.
    This bid protest challenges the award of a contract by the United States
    Department of Energy (DOE or the Agency) to defendant-intervenor Oak Ridge
    Associated Universities (ORAU or intervenor). Plaintiff, the Board of Regents of the
    Nevada System of Higher Education, filed this post-award protest on behalf of the
    Desert Research Institute (DRI), which was an unsuccessful offeror for the award.
    Plaintiff asserts that the Agency made various errors in the evaluation of its
    proposal and that of its competitor; failed to disclose certain information concerning
    the predecessor contract and the manner in which proposals would be evaluated;
    and failed to request clarification regarding an omission from its proposal. The
    Court has determined that the Agency’s decision to award the contract to ORAU
    was in accordance with law, and was neither arbitrary nor capricious. For the
    reasons explained below, defendant’s and intervenor’s cross-motions for judgment
    on the administrative record are GRANTED and plaintiff ’s motion for judgment on
    the administrative record is DENIED.
    I. BACKGROUND
    A. History of the Facility
    The United States Department of Energy maintains the Oak Ridge Institute
    for Science and Education (ORISE), which acts as a liaison between national
    universities and DOE research laboratories to further research opportunities for
    students and faculty. Admin. R. (AR) at 43. For the first 57 years of its existence,
    ORISE was operated under a management and operating agreement between the
    Agency and the Oak Ridge Institute for Nuclear Studies, a state institution. 
    Id. Oak Ridge
    Institute for Nuclear Studies has since been reorganized as the Oak
    Ridge Associated Universities, a consortium of colleges and universities. 
    Id. In June
    of 1991, DOE determined that it would be beneficial to separate ORISE, as an
    entity, from its management, ORAU. 
    Id. In January,
    1999, DOE awarded a
    noncompetitive, cost-reimbursement contract to ORAU as part of a move away from
    the management and operating agreement model and towards free and open
    competition. 
    Id. at 43.
    After a three-month extension, that contract expired on
    March 31, 2000, being replaced by a competitively-awarded, cost-plus fee contract
    that was also received by ORAU. 
    Id. A follow-on
    contract, also a competitively-
    †This opinion was initially filed under seal, to allow the parties the opportunity to
    propose redactions. Intervenor has done so, although most of its request was found
    unwarranted. See Order (July 5, 2017). The opinion is now issued for publication,
    with some minor, non-substantive corrections. Redacted material has been replaced
    in this manner: “[XXXXX].”
    -2-
    awarded, cost-plus fee contract, was awarded to ORAU --- which, after two
    extensions, was set to expire on June 30, 2016. 
    Id. at 43,
    2201.
    B. The Solicitation
    The United States Department of Energy issued Solicitation No. DE-SOL-
    0006230 (the solicitation) on July 22, 2015. AR at 228. The solicitation sought
    proposals to support the scientific efforts of ORISE. AR at 235. The awardee was to
    assist DOE in five principal areas, which were described in detail in the
    Performance Work Statement (PWS): science, technology, engineering, and
    mathematics (STEM) workforce development; scientific and technical resource
    integration; radiation emergency assistance and training; human subject protection
    surveillance; and independent environmental assessment and verification. 
    Id. at 235–39.
    The contract was to be awarded on a cost-plus fee basis, with a transition
    period, a five-year base period, and up to five additional one-year “award term”
    periods. 
    Id. at 230–31.
    During the period between the issuance of the solicitation
    and the due date for proposals, the solicitation was amended seven times. See 
    id. at 2205.
    The solicitation informed offerors that the Agency intended to evaluate
    proposals, and make an award, without conducting discussions. AR at 851.
    Offerors were instructed to submit their proposals in three separate volumes.
    Volume I was to contain the “Offer and Other Documents,” Volume II was for
    “Capabilities and Approach,” and Volume III was to cover “Cost and Fee.” 
    Id. at 731.
    Pursuant to the solicitation’s instructions, offerors were to submit nine
    separate documents in Volume I. AR at 776. First, a fully executed “Proposal
    Form” was to be included. 
    Id. Next, offerors
    were to include certain
    representations and certifications. See 
    id. at 688–701
    (providing 11 different
    representations and certifications, some with subparts, that offerors were to
    execute); 
    id. at 776.
    Third, offerors were to provide price information, including a
    proposed award fee, consistent with the cost information contained in Volume III.
    
    Id. at 230–33
    (blank pricing form to be used by offerors); 
    id. at 776–77.
    Fourth,
    offerors were to submit a pledge to select subcontractors on a competitive basis as
    much as possible, and to justify any non-competitive selections. 
    Id. at 776–77.
    The fifth document was to contain any exceptions to, or deviations from the
    model contract. AR at 776–77. Next would be a summary of exceptions taken in
    other volumes. 
    Id. Seventh, each
    offeror was to provide a numbered listing of its
    commitments to provide anything at no cost to the government. Id.; see also AR at
    789. Eighth, offerors were to provide a completed “Small Business Contracting
    Plan.” 
    Id. at 776.
    The solicitation required that this plan address the elements
    -3-
    listed in 48 C.F.R. § 52.219-9(d). 
    Id. at 777.
    1 And finally, offerors were required to
    execute a certification of intent to maintain the pay and benefits of employees of the
    incumbent contractor who are hired by the contract awardee. 
    Id. at 295–296,
    776,
    778.
    Volume II, the Capabilities and Approach proposal, was limited to 70 pages
    in length, not counting the table of contents and certain other material. AR at 778–
    79. In this proposal, offerors were to address seven specific areas, 
    id. at 779–89,
    which were to be used as the evaluation criteria for the proposal, 
    id. at 851–56.
    Concerning Volume III, the Cost and Fee proposal, offerors were not required to
    certify their data, as the Agency selected Alternate IV of Federal Acquisition
    Regulation (FAR) section 52.215-20. 
    Id. at 789;
    see AR at 755 (incorporating 48
    C.F.R. § 52.215-20, Alternate IV (OCT 2010)). The offerors were instead given a
    detailed description of the information to be provided. 
    Id. at 755–68.
    The solicitation identified two evaluation factors to be used in the best-value
    determination: a technical factor, which was called Capabilities and Approach; and
    the Cost factor. AR at 851. The seven specific topic areas under the Capabilities
    and Approach factor --- which would customarily have been called “subfactors,” see
    48 C.F.R. §§ 15.303(b)(4), 15.304 --- were designated as “criteria,” and the elements
    under them were called “subcriteria.” 2 In weighing these factors, “Capabilities and
    Approach Evaluation Criteria are significantly more important than the Probable
    Cost.” AR at 851. For purposes of relative weight, the Capabilities and Approach
    Evaluation Criteria were broken down into two tiers. The first tier, which
    contained the most important criteria, was composed of “Strategic Vision for ORISE
    as a DOE Institute”; “Leadership, Management, and Direction”; and “Program
    Implementation.” 
    Id. at 852.
    Each of these criteria were of equal importance to one
    another. 
    Id. The second
    tier of criteria, less important than the first tier, consisted
    of “Relevant Experience,” “Past Performance,” “Transition,” and “Offeror’s
    Commitments.” 
    Id. Again, each
    of the criteria in the second tier were of equal
    importance to one another, but the four of them collectively were less important
    than any one of the criteria in the first tier. 
    Id. The first
    criterion, “Strategic Vision for ORISE as a DOE Institute,” had four
    subcriteria. First, the Agency was to evaluate the extent to which the offeror’s
    comprehensive strategic vision would enable ORISE to achieve the “DOE goals as
    articulated in the Performance Work Statement.” AR at 852. Second, DOE would
    evaluate the extent to which the offeror’s plan for achieving that vision would
    1 The solicitation included a model version of such a small business plan for use by
    offerors in submitting their proposals. AR at 678–86.
    2 For the sake of consistency, the Court will use the Agency’s nomenclature
    throughout this opinion.
    -4-
    enable it to leverage limited resources to accomplish the goals articulated in the
    PWS. 
    Id. Third, the
    Agency was to evaluate the offeror’s proposed measures and
    metrics of success. 
    Id. at 853.
    Fourth, DOE was to evaluate the offeror’s proposed
    use of available and newly-developed data to promote the continuous improvement
    of ORISE. 
    Id. The second
    criterion in the first tier, “Leadership, Management, and
    Direction,” had only two subcriteria. The first of these considered the qualifications
    of the offeror’s proposed key personnel, as reflected in their oral presentations and
    résumés. 
    Id. Under the
    second subcriterion, DOE would evaluate the extent to
    which the offeror’s proposed leadership team would “enhance the offeror’s ability to
    overcome barriers and challenges affecting accomplishment of the PWS.” 
    Id. The final
    criterion in the first tier, “Program Implementation,” had three
    subcriteria. AR at 853. Under the first, DOE was to evaluate “the
    comprehensiveness, innovativeness, and feasibility of the offeror’s approach to
    efficiently and effectively managing and executing the contract requirements so as
    to achieve success in all areas of the work scope.” 
    Id. The second
    of the subcriteria
    called for the Agency to evaluate “the offeror’s plan for the use of small businesses
    in work directly impacting the DOE mission.” 
    Id. Under the
    final subcriterion, the
    Agency was to evaluate the offeror’s proposed staff, facilities, equipment, use of
    government-furnished property and equipment, and compensation of professional
    employees. 
    Id. The first
    of the four criteria in the second tier, “Relevant Experience,” had
    five subcriteria. AR at 854. The first subcriterion evaluated each offeror’s relevant
    experience in performing work similar in size, scope, and complexity to that stated
    in the PWS. 
    Id. Under the
    second subcriterion, DOE evaluated the relevant
    experience of proposed subcontractors, again based on work that was similar in
    terms of size, scope, and complexity to the work specified in the PWS. 
    Id. Under the
    third subcriterion, the Agency would compare the prior experience of the offeror,
    or the offeror’s subcontractors, to the work that each was to perform under the
    proposal. 
    Id. The fourth
    subcriterion noted that in the case of a newly-formed
    entity, which lacked experience of its own, the Agency would evaluate the entity’s
    members or parents. 
    Id. The final
    subcriterion informed offerors that the DOE
    “may use information obtained from reference checks to verify experience.” 
    Id. at 854.
    Under the next criterion in the second tier, “Past Performance,” the Agency
    was to evaluate the offeror’s past performance, and that of its teaming partners,
    using seven subcriteria. AR at 854–55. First, DOE would evaluate the quality of
    products or services rendered on prior contracts. 
    Id. at 855.
    Second, the Agency
    would evaluate the timeliness of the delivery of those goods or services. 
    Id. The third
    subcriterion was the extent to which the offeror was able to control costs when
    -5-
    performing prior contracts. 
    Id. Fourth, the
    Agency was to evaluate the extent to
    which the offeror employed efficient and proper business practices. 
    Id. The fifth
    subcriterion DOE would examine was overall customer satisfaction concerning past
    contracts. 
    Id. Sixth, the
    Agency would evaluate the extent to which an offeror had
    safely conducted operations when performing prior contracts. 
    Id. Finally, DOE
    would examine the extent to which an offeror had been able to maintain the
    security of sensitive data when performing prior contracts. 
    Id. The third
    criterion in the second tier concerned the offeror’s “Transition
    Plan.” AR at 855. Under this criterion, DOE was to evaluate the transition plan for
    “feasibility, comprehensiveness, efficiency and effectiveness, including the extent
    that it provides for a smooth and orderly transition.” AR at 855–56.
    The fourth and final criterion in the second tier was “Offeror’s
    Commitments.” AR at 856. Such commitments were defined in section L.31(c)(7) of
    the solicitation as “any proposed resources, services, support, and/or commitments
    . . . that will be provided at no cost to” the Agency. 
    Id. at 789.
    Under this criterion,
    credit would only be given to an offeror’s commitments that would be incorporated
    into the contract. AR at 856. The solicitation also informed offerors that, to the
    extent that commitments were proposed from any party other than the offeror --- for
    example, by “parent corporations, affiliated corporations, universities, or other
    institutions” --- a letter must be provided, on official letterhead, from a person
    authorized to make the commitment on behalf of that other party. AR at 789.
    After the solicitation was issued, but before proposals were submitted,
    prospective offerors were provided the opportunity to submit written questions to
    DOE concerning the procurement. On September 1, 2015, DOE finalized a list of 42
    written questions and responses, some of which had more than one part, which was
    made available to prospective bidders. AR at 870–81. A total of seven questions
    were asked concerning the number of incumbent contractor employees, and the
    costs of employee compensation or facility maintenance incurred in connection with
    the predecessor contract for the operation of ORISE. See 
    id. at 871–72,
    878–80.
    This information was sought because the government would be furnishing certain
    property to the contract awardee for use as part of the contract, which the awardee
    would be responsible for maintaining, AR at 239–40, 564–84 (listing property the
    government would furnish to the awardee), and because the awardee was obligated
    to offer to retain certain incumbent personnel at comparable levels of pay and
    benefits, AR at 272–73 (citing 48 CFR § 52.222-17).
    The Agency did not provide any additional information concerning the
    number of incumbent employees and their benefits, explaining that such
    information was “a contractor record” that could not be released under the terms of
    the previous contracts. AR at 871, 879–80. Regarding government-furnished
    facilities, all of which were located at what was known as the “ORISE South
    -6-
    Campus,” a question was asked about the awardee’s responsibility for two buildings
    which were described as “pending disposal,” and the timeframe for any disposal.
    AR at 871–72; see 
    id. at 584
    (listing buildings SC-9 and SC-16 as “pending
    disposal”). In response, the Agency directed offerors to a document on its website
    entitled the “Ten-Year Site Plan,” which indicated the government’s plans regarding
    the timing of the disposal activities relating to those buildings. 
    Id. at 872;
    Pl.s’ Ex.
    A at 5. That plan noted that, in fiscal year 2014, 608 Full Time Equivalent (FTEs)
    worked in support of the ORISE contract, and that this number was expected to rise
    to 747 by 2024. Pl.’s Ex. A at 3–4. In response to a question concerning annual
    expenses for maintenance activities, the Agency withheld incumbent contractor
    information as “a contractor record” that could not be released, and referred offerors
    to cost projections contained in the Ten-Year Site Plan. AR at 878.
    C. Evaluation of Proposals and Award of Contract
    1. SEB Evaluations
    On September 18, 2015, DOE received two proposals, one from DRI and the
    other from ORAU. AR at 886, 1451. Under the Source Selection Plan (SSP), the
    Source Evaluation Board (SEB) was to consist of three voting members (including a
    chairperson), eleven advisors, and five ex-officio members. AR at 44–45. The plan
    also noted that additional advisors might be appointed, should additional assistance
    be required during the evaluation of proposals. 
    Id. at 45.
    Joseph McBrearty,
    Deputy Director for Field Operations at DOE’s Office of Science, appointed Dr. Julie
    A. Carruthers as the Source Selection Official (SSO) for this procurement. AR at
    2200. Doctor Carruthers in turn appointed the three SEB voting members, the
    initial eleven advisors, and three additional advisors. 
    Id. at 2200–01.
    3
    The SSP contemplated an eleven-step process for evaluating these proposals,
    beginning with an initial review to ensure that the proposals were complete and in
    compliance with the solicitation instructions. AR at 52. Pursuant to that first step,
    the SEB executive secretary reviewed both proposals to verify compliance with the
    solicitation’s basic requirements and to determine whether the proposals were
    “obviously or grossly deficient.” AR at 2213. Apparently, neither proposal was
    found to present such problems during this initial review. See AR at 2213–14, 2327,
    2333.
    The SSP provided five adjectival ratings that evaluators would use to rate the
    Capabilities and Approach factor. AR at 59–60. The possible ratings were
    3 The five ex-officio members of the SEB were part of the board by virtue of their
    positions within DOE. AR at 2201.
    -7-
    “Excellent,” “Good,” “Satisfactory or Neutral,” “Marginal,” and “Unsatisfactory.” 4
    
    Id. An “Excellent”
    proposal was to be one which “demonstrates a comprehensive
    understanding of ” requirements, or “a highly effective approach,” such that there
    was “a very high probability of successful contract performance” and a “likelihood
    that performance expectations will be significantly exceeded.” AR at 59. For such
    proposals, “the chance of unsuccessful performance is extremely low,” and they
    “normally exhibit significant strength(s) and/or multiple strengths, and no
    deficiencies, significant weaknesses, or weaknesses.” 
    Id. “Good” was
    the rating for a proposal which “demonstrates a noteworthy
    understanding of . . . requirements” or “an effective approach,” with a “high
    probability of successful contract performance” and with expectations likely to be
    exceeded. 
    Id. Such a
    proposal would “exhibit significant strength(s) and/or
    strength(s) that collectively provide notable benefit to the Government, few, if any
    significant weaknesses, and/or weaknesses, no deficiencies,” and present a “very
    low” risk of unsuccessful performance. 
    Id. Proposals rated
    “Satisfactory” were to demonstrate “an adequate
    understanding of . . . requirements” and “an acceptable approach,” with “a likely
    probability of successful contract performance.” These would “exhibit significant
    strength(s) and/or strength(s) and offsetting significant weaknesses and/or
    weaknesses or deficiencies,” or have minimally important (or no) strengths or
    weaknesses, and have a risk of unsuccessful performance which is considered “low.”
    
    Id. at 59–60.
    A “Marginal” proposal would be one which “demonstrates a limited
    understanding of the contract” or an approach with “an unlikely probability of
    achieving successful contract performance.” AR at 60. These proposals “would
    normally” contain “few, if any, significant strengths and/or strengths, which are
    outweighed by the impact of weaknesses, significant weakness(es), or
    deficiency(ies),” and present a “significant” risk of unsuccessful performance. 
    Id. Finally, “Unsatisfactory”
    proposals would “demonstrate[ ] an inadequate
    understanding of . . . requirements” and be “highly unlikely” to achieve successful
    performance. 
    Id. These would
    have “no significant strengths or strengths,
    numerous significant weaknesses and/or weaknesses, and at least one deficiency,”
    and would present an “unacceptable level of risk.” 
    Id. Pursuant to
    the SSP, no adjectival ratings were to be employed for the
    evaluation of cost proposals. AR at 50. Proposals were to be evaluated for cost
    realism and cost reasonableness, to assess whether each offeror understood
    requirements, and to derive a probable cost. 
    Id. The members
    of the SEB were not
    4 The adjectival ratings were not described in the solicitation, see AR at 851–56, nor
    otherwise released to offerors.
    -8-
    to view cost information until they had finalized their technical evaluations. 
    Id. at 60.
    The SEB’s technical evaluation of cost information could involve up to five
    separate aspects. These were an examination of an offeror’s total full-time
    equivalents (FTEs) and labor mix; a technical analysis to determine the
    reasonableness of proposed resource use; the ensuring of consistency with the
    strengths and weaknesses identified in the Capabilities and Approach factor review;
    the comparison of the offeror’s cost information to the independent government cost
    estimate; and the development of and justification for any cost adjustments. 
    Id. at 60–61.
    The SEB would also review the draft “Cost Report” prepared by the SEB
    advisors, “to determine if the cost is fair and reasonable.” AR at 61; see also 
    id. at 55.
    The SEB first evaluated Volume II of the offerors’ proposals under the
    Capabilities and Approach factor. 
    Id. at 2214.
    This process began with each voting
    member of the SEB conducting a thorough review of both proposals. 
    Id. at 2215.
    During this review of Volume II of the proposals, no SEB member identified any
    aspects of the proposals which required clarification. 
    Id. Next, voting
    members of
    the SEB, the SSO, the SEB’s legal advisor, the Contracting Officer, and the
    Executive Secretary, attended both offerors’ oral presentations on October 7, 2015
    and October 8, 2015. AR at 2205, 2215–16. The SEB then evaluated each offeror’s
    past performance information. 
    Id. at 2216.
    After they had independently reviewed
    the proposals, and after the offerors had made their oral presentations, the voting
    members of the SEB met to conduct a consensus evaluation and arrive at a
    consensus rating for each proposal. 
    Id. at 2216–17.
    Though the Source Selection
    Plan had a process for preparing dissenting opinions, no such opinions were
    generated by the SEB. 
    Id. at 58,
    2217, 2333.
    The SEB’s 129-page consensus report was completed on February 18, 2016.
    AR at 2193, 2323. In its overview of the proposals received, the SEB noted that
    ORAU had proposed no major subcontractors or teaming partners, but DRI had
    proposed five major subcontractors. AR at 2199. The SEB summarized the results
    of its technical evaluations in a table format. With respect to the first tier of
    criteria, the SEB assigned DRI a rating of Satisfactory for Strategic Vision, and
    ORAU received an Excellent. 
    Id. Under Leadership,
    Management, and Direction,
    DRI received a Marginal rating and ORAU received a rating of Satisfactory. 
    Id. And for
    Program Implementation, DRI received a Satisfactory rating and ORAU
    was rated as Good. 
    Id. In short,
    for each of the most important technical criteria,
    ORAU received a better rating than DRI.
    Turning to the four criteria in the second tier, for Relevant Experience the
    SEB assigned DRI a rating of Satisfactory and ORAU was rated as Excellent. AR
    at 2199. Under Past Performance, both offerors received a Good rating. 
    Id. Under the
    Transition Plan criterion, DRI received a Good rating, while ORAU was
    assigned but a Marginal rating. 
    Id. And finally,
    DRI received a Satisfactory rating
    -9-
    for Offeror’s Commitments, and ORAU was rated as Excellent. 
    Id. Thus, for
    the
    less important technical criteria, ORAU received an equal or superior rating to DRI
    for all but one criterion.
    The SEB began its review of both proposals by reviewing Volume I of each.
    AR at 2224. The SEB determined that both offerors had submitted, in most
    respects, complete proposals. 5 As is relevant to this protest, it was observed that
    both offerors had submitted small business plans. AR at 2224–25. The SEB did
    note, however, that DRI had failed to submit properly authorized letters of
    commitment from entities other than DRI that were purportedly offering property
    or services at no cost to the government. 
    Id. at 2224.
    The SEB considered this
    omission in its evaluation of Volume II of DRI’s proposal. 
    Id. Concerning the
    SEB’s evaluation of Volume II, DRI’s protest focuses on five of
    the criteria, the relevant findings of which are discussed below. The SEB assigned
    four weaknesses to DRI’s proposal under the Strategic Vision criterion. AR at
    2227–28. The first weakness related to DRI’s proposal to move the Radiation
    Emergency Assistance Center/Training Site (REAC/TS) facility to a new, as yet
    unspecified, location. AR at 2229. The SEB found that DRI provided insufficient
    details about this proposed move, such as the resources involved, creating doubt as
    to DRI’s ability to leverage limited resources to accomplish the contract objectives
    and increasing the chance of unsuccessful contract performance. 
    Id. The SEB
    also
    assigned DRI a weakness under this criterion for providing insufficient information
    concerning how it would achieve both its overall long-term vision for ORISE as an
    enterprise and the goals stated in the PWS, AR at 2230; for not communicating a
    vision for Science and Technical Resource Integration (STRI) to meet peer review
    goals, AR at 2230–31; and for purportedly proposing to expand certain REAC/TS
    and Independent Environmental Assessment and Verification (IEAV) activities
    beyond those stated in the PWS, AR at 2231.
    The SEB assigned DRI several weaknesses under the Leadership,
    Management, and Direction criterion. AR at 2242. 6 One weakness was based on a
    combination of findings --- none of the members of DRI’s proposed management
    team were able to satisfactorily answer a question concerning the DOE’s Office of
    Sciences peer review process, four key individuals lacked the requisite qualifications
    on paper, and another failed to show leadership ability during the oral
    presentations. AR at 2244–45. The SEB likewise assigned a weakness to DRI’s
    5 The SEB did note that DRI failed to include a cover letter with its Volume I, but
    considered this omission to be administrative in nature and accordingly did not
    penalize DRI for it. AR at 2224.
    6Although in its rating discussion the SEB states that five weaknesses were found,
    AR at 2242, only four appear to be described, see 
    id. at 2243–46.
                                            - 10 -
    proposal because its proposed director’s résumé, though listing both governmental
    and private sector executive experience, did not clearly reflect experience leading a
    large organization with a wide mission scope, as required for the ORISE contract.
    
    Id. at 2246.
    Another weakness was based on DRI’s having proposed a new
    emergency preparedness position, to be held by a key person, which the SEB did not
    find adequately explained. AR at 2244.
    In the evaluation of DRI’s proposal under the Program Implementation
    criterion, the SEB identified four weaknesses and one significant weakness. AR at
    2252. The significant weakness was assigned because the SEB determined that
    DRI had failed to provide sufficient detail in explaining the proposed labor mix and
    staffing levels. AR at 2255–56. Under this criterion, the SEB assigned a significant
    weakness to ORAU due to the offeror’s limited reliance on small businesses. AR at
    2261. The SEB determined that this was a significant flaw in the proposal as
    ORAU’s proposed small business participation was limited to ancillary aspects of
    the contract. 
    Id. By contrast,
    one of DRI’s two strengths under this criterion was
    for its proposed use of multiple small businesses to do core contract work. AR at
    2253. 7
    With respect to the Transition Plan criterion, the SEB assigned ORAU a
    significant weakness and no strengths, weakness, or deficiencies, resulting in a
    rating of Marginal. AR at 2273. This low rating was due to the SEB treating the
    ORAU proposal as lacking a formal transition plan, as the submitted Volume II
    exceeded the relevant page limit, resulting in the excessive pages (including the
    formal plan) being disregarded. AR at 2273–75. The SEB determined, however,
    that sufficient information was provided concerning transition in those parts of the
    proposal that were evaluated, such as the proposed use of a dedicated transition
    manager and continued use of existing facilities, to justify finding the proposal to be
    Marginal, rather than Unacceptable, under this criterion. 
    Id. Regarding the
    final relevant criterion, Offeror’s Commitments, DRI was
    assigned a weakness because the proposal did not include commitment letters from
    the third parties that DRI claimed would be providing goods or services, at no cost
    to the government, for use in the ORISE contract. AR at 2277. The SEB noted that
    such letters were required by the solicitation and that the failure to include them
    increased the risk of unsuccessful contract performance. 
    Id. After completing
    its technical evaluations, the SEB evaluated Volume III of
    the offerors’ proposals --- the cost and fee information. AR at 2278–79. In its
    evaluation of DRI’s cost and fee information, the SEB noted that the proposal
    appeared to be missing a workbook, entitled “Estimate Assumptions,” that was to
    7 Under this criterion, ORAU was assigned six strengths, two weaknesses, and the
    one significant weakness. AR at 2256–61.
    - 11 -
    provide information concerning the basis for DRI’s estimated costs. AR at 2296.
    The omission of the workbook, DRI’s reliance on its unexplained “professional
    judgment,” and the lack of a narrative explanation for its methodology left the SEB
    without the ability to assess DRI’s proposed costs. AR at 2296–97. Accordingly, the
    SEB determined that no adjustments would be made to DRI’s costs to arrive at a
    most probable cost of performance, but also determined that most of DRI’s proposed
    costs were unrealistic for lack of support. See 
    id. at 2296–309.
    With respect to
    labor hours, the SEB noted that DRI had based its overall headcount on historical
    data regarding FTEs under the predecessor contract but that DRI’s technical
    approach to the current ORISE contract was not similar to that previously
    employed. AR at 2300–01. Accordingly, in the view of the SEB, historical costs
    would be an improper basis upon which to analyze whether DRI’s costs were
    realistic. 
    Id. 2. Source
    Selection Decision
    On March 2, 2016, the SSO, in her 21-page Source Selection Decision,
    determined that the contract would be awarded to ORAU. AR at 2326, 2345. As
    did the SEB, the SSO noted that the material submitted by ORAU which exceeded
    the page limit was not considered during the evaluation. AR at 2333. The SSO
    determined that the SEB’s evaluation was properly conducted and consistent with
    the evaluation criteria listed in the solicitation. 
    Id. She noted
    that she agreed with
    all of the evaluation rankings the SEB had assigned to the two proposals, but had
    made certain additional observations about those proposals. AR at 2334. Based on
    her review of the proposals and the SEB’s ratings, the SSO determined that
    ORAU’s proposal was technically superior to DRI’s. AR at 2336. She based this
    determination largely on the fact that ORAU received superior ratings in five of the
    eight technical criteria, including all three of the more important criteria. 
    Id. With regard
    to the evaluation of DRI’s proposal under the Strategic Vision criterion, the
    SSO observed that DRI’s proposed focus on primary and secondary STEM outreach
    and education was not well aligned with the ORISE contract’s focus, which is
    principally on education at the undergraduate level and above. AR at 2336–37.
    With respect to the Program Implementation criterion, the SSO echoed the SEB’s
    concerns that ORAU had failed to make sufficient use of small businesses in DOE
    mission-related work areas. AR at 2339. The SSO noted that DRI was superior
    with respect to its use of small businesses, but that its proposal was inferior under
    this criterion taken as a whole. AR at 2339–40.
    Turning to the Cost factor, the SSO noted that the proposed costs were “very
    close” between the two proposals. AR at 2343. She agreed with the SEB’s
    determination that most of DRI’s costs were unrealistic, that a probable cost figure
    for DRI could not be derived, and that ORAU’s proposed cost was reasonable. 
    Id. The SSO
    then proceeded to the best value determination. Due to the inability to
    confirm that the proposed costs were realistic, the SSO concluded that DRI’s
    - 12 -
    “proposal is unacceptable and cannot be considered for award.” AR at 2344. She
    nevertheless conducted a best-value tradeoff using DRI’s proposed cost, and
    determined that the benefits from ORAU’s technical approach under the three first-
    tier criteria and the second-tier criterion of Offeror’s Commitments “far outweigh
    any perceived savings” from DRI’s lower proposed cost. 
    Id. 8 The
    SSO noted that
    ORAU also proposed a lower maximum award fee, and that the risk posed by
    ORAU’s lack of a formal transition plan was manageable. 9 She concluded that “the
    overall technical superiority of the ORAU proposal is of better value to the
    Government” than DRI’s proposal, and accordingly awarded the ORISE contract to
    ORAU. AR at 2344–45.
    3. Debriefing
    On March 10, 2016, DRI was informed by letter that its offer had been
    rejected and that ORAU had been selected to receive the contract. AR at 2386.
    Attached to the letter was a written debriefing document, which informed DRI of its
    technical evaluation ratings and the strengths and weaknesses assigned by the
    SEB. AR at 2388–405. That document also disclosed the Agency’s cost analysis of
    DRI’s proposal, and noted the inadequacies in the information provided --- including
    the absence of the workbook --- that had led the SEB and the SSO to determine that
    DRI’s costs of performance could not be determined with any certainty. AR at
    2406–07. An oral debriefing was offered, see AR at 2387, which DRI apparently
    received within a week, Compl. ¶ 5.
    D. The Protest Filed with the Court
    On March 24, 2016, the Board of Regents of the Nevada System of Higher
    Education filed a bid-protest on behalf of DRI, contending that the DOE’s decision
    to award the ORISE contract to ORAU was arbitrary, capricious, and violative of
    law and regulation. Compl. In that complaint, plaintiff asserts five separate
    protest grounds. Compl. ¶¶ 5(A)–(E). First, plaintiff alleges that DOE evaluated
    the proposals based on unstated evaluation criteria, because the solicitation did not
    include the definitions of the adjectival ratings or explain how an offeror could
    obtain a particular rating. 
    Id. ¶¶ 6,
    8. Under this ground, DRI argues that the
    Agency failed to rank the proposals, making any best value determination
    arbitrary. 
    Id. ¶¶ 9–10.
    Second, plaintiff claims that the Agency erred in failing to
    request a clarification from DRI, after the Agency discovered that the workbook
    8 The total probable cost of ORAU’s proposal, including the maximum award fee,
    was $3,214,160,771, which was 2.7% higher than DRI’s proposed cost and fee of
    $3,130,764,506. See AR at 2334.
    9 The maximum award fee under the ORAU proposal was $57,091,516, compared to
    $76,059,587 under the DRI proposal. AR at 2344.
    - 13 -
    “Estimate Assumptions.xlsx” was omitted from Volume III of DRI’s proposal. 
    Id. ¶ 11.
    Plaintiff alleges that during the debriefing, the Agency stated that it did not
    request a clarification regarding this because it believed that doing so would have
    constituted discussions, requiring the Agency to communicate with ORAU as well.
    
    Id. ¶ 12.
    Third, plaintiff alleges that the Agency’s refusal to disclose certain
    information regarding the number of FTEs employed under the predecessor ORISE
    contract, as well as their compensation and labor mix, was improper. Compl.
    ¶¶ 15–17. In support of this claim, plaintiff notes that its proposal was criticized for
    its proposed labor mix and method for estimating labor costs, which it claims was
    the result of the Agency’s refusal to disclose the incumbent’s labor information. 
    Id. ¶¶ 17,
    19. Under the fourth ground, plaintiff challenges several evaluation
    determinations that it contends were erroneous or reflect disparate treatment. 
    Id. ¶¶ 20,
    22, 25, 29–30. Plaintiff takes issue with the following six evaluation
    decisions: the negative evaluation DRI received for its technical understanding of
    DOE’s peer review process, 
    id. ¶¶ 20–21;
    the assignment of a weakness to DRI’s
    proposal regarding its proposed move of the REAC/TS to a larger space, 
    id. ¶¶ 22–
    24; the SSO’s assessment of qualifications of DRI’s proposed program director, 
    id. ¶¶ 25–26;
    the SSO’s characterization of DRI’s emergency management proposal, 
    id. ¶¶ 27–28;
    the SSO’s determination that DRI’s proposal contained both a strength
    and a weakness regarding STRI, 
    id. ¶ 29;
    and the assignment of weaknesses to DRI
    for failure to follow DOE’s “Strategic Vision” or advance its “goals,” which plaintiff
    alleges were not defined in the solicitation, 
    id. ¶¶ 30–31.
    Plaintiff’s fifth ground
    alleges that the SSO was excessively involved in the procurement and acted in a
    partisan manner, rendering her decision insufficiently “independent” to comply with
    48 C.F.R. § 15.308. Compl. ¶¶ 32–36. Plaintiff requested a remand to the Agency
    to correct the purported evaluation errors, as well an award of bid preparation and
    proposal costs and of its attorney’s fees for bringing this protest. 
    Id. ¶ 37
    In its motion for judgment on the administrative record, plaintiff makes five
    arguments in support of its protest, which differ somewhat from those in the
    complaint. 10 Pl.’s Mot. for J. on the R. (Pl.’s Mot.) at 2, 8, 12, 15, 22. First, it argues
    that ORAU’s proposal failed to contain certain required information, and
    accordingly should have been either rejected as nonresponsive or evaluated less
    favorably. 
    Id. at 2–8.
    Next, plaintiff argues that, once the Agency realized the
    workbook containing supporting cost information was omitted from DRI’s Volume
    III, the Agency should have either immediately eliminated DRI from consideration
    10 To the extent any specific matters alleged in the complaint were not raised in
    plaintiff ’s briefs on the motions for judgment, such claims have dropped out of this
    case. Res Rei Dev., Inc. v. United States, 
    126 Fed. Cl. 535
    , 546 n.17 (2016) (citing
    Commissioning Sols. Glob., LLC v. United States, 
    97 Fed. Cl. 1
    , 2–3 n.2 (2011)).
    - 14 -
    or sought a clarification. 
    Id. at 8–12.
    Third, plaintiff argues that DOE improperly
    refused to release certain information related to the staffing levels, labor mix, and
    compensation paid under the predecessor ORISE contract, negatively impacting
    DRI’s proposal. 
    Id. at 12–15.
    Under this ground, DRI also contends that it based
    its proposed staffing on the 608 FTEs that the Ten-Year Site Plan, referenced by the
    Agency, stated were employed in 2014 under the predecessor contract. 
    Id. at 14–15.
    Plaintiff contends that this document either misled it, or shows that ORAU’s much
    lower proposed direct labor of [XXX] FTEs was judged under a different standard
    from DRI’s proposal. 
    Id. Plaintiff’s fourth
    argument concerns a number of challenges to specific
    determinations of the SEB. Pl.’s Mot. at 15–24. 11 The first of these is DRI’s claim
    that its proposal was improperly criticized for not including commitment letters
    from other entities that were promising to provide certain property or assistance at
    no cost to the government. 
    Id. at 16–17.
    Next, DRI contends that its proposal was
    improperly downgraded by the evaluators for suggesting that DRI would study a
    move of the REAC/TS facility to a larger location. 
    Id. at 18–19.
    Third, plaintiff
    disputes the weaknesses identified for its proposed management team. 
    Id. at 19–
    20. Plaintiff ’s next argument is that its key personnel were improperly faulted for
    not being familiar with DOE’s Office of Sciences peer review process. 
    Id. at 20–21.
    Plaintiff also contends that ORAU should not have received a strength under the
    Program Implementation criterion for its use of a part-time workforce. 
    Id. at 21–22.
    Finally, DRI maintains that the Agency treated offerors disparately by not imposing
    on the incumbent the expenses of relocating operations from the ORISE North
    Campus facilities owned by ORAU to the South Campus facilities owned by DOE.
    
    Id. at 22.
    In its fifth argument, DRI reapplies all of its criticisms of the SEB’s findings
    to the SSO, for having adopted them. Pl.’s Mot. at 22. It argues that the SSO
    mischaracterized the SEB’s findings concerning DRI’s capability to leverage limited
    resources. 
    Id. at 23.
    Plaintiff further contends that the SSO based her assessment
    of its proposal on her subjective views of DOE’s goals, and improperly criticized DRI
    for focusing more on primary and secondary STEM education. 
    Id. Defendant, and
    defendant-intervenor, have filed motions for judgment on the
    administrative record, in which they argue that all of plaintiff ’s contentions are
    either untimely, without merit, or both. Def.’s Resp. in Opp’n to Pl.’s Mot. for J. on
    the Admin. R. and Cross Mot. for J. on the Admin. R. (Def.’s Mot.); Intervenor’s
    Resp. and Cross Mot. for J. on the R. (Int.’s Mot.). Together, they argue that any
    protest grounds based on the Agency’s failure to disclose information or evaluative
    11This argument begins with some “general comments” that evaluation factors
    “were amorphous, vague, extremely subjective, and slanted,” and that DOE’s “goals”
    and “vision” were not defined in the solicitation. Pl.’s Mot. at 15–16.
    - 15 -
    criteria, or challenges to the substance of those criteria that were disclosed, are
    untimely under Blue & Gold Fleet, L.P. v. United States, 
    492 F.3d 1308
    (Fed. Cir.
    2007). Def.’s Mot. at 19, 28; Int.’s Mot. at 31–33. Regarding the challenges to the
    technical evaluations, they contend these represent mere disagreements with the
    Agency’s technical judgments, and accordingly do not state a valid protest ground.
    Def.’s Mot. at 11–22, 25–33, 34–41; Int.’s Mot. at 21–31, 34–48. Defendant and
    defendant-intervenor also contend that the Agency properly determined that
    ORAU’s proposal met all solicitation requirements and accordingly was acceptable
    for award. Def.’s Mot. 11–17; Int.’s Mot. at 21–26. After reply papers were filed by
    all parties, the Court held a hearing on the motions, at which all three parties
    participated. This opinion issues after a careful review of the arguments made at
    the hearing and in the briefs and the authorities cited, as well as a thorough
    consideration of the pertinent documents in the administrative record.
    II. DISCUSSION
    A. Legal Standards
    1. Judgment on the Administrative Record in a Bid Protest
    Bid protests are heard by this court under the Tucker Act, as amended by the
    Administrative Dispute Resolution Act of 1996 (ADRA), Pub.L. No. 104–320,
    § 12(a)–(b), 110 Stat. 3870, 3874. The relevant provision requires our court to follow
    Administrative Procedure Act (APA) standards of review in bid protests. 28 U.S.C.
    § 1491(b)(4). Those standards, incorporated by reference, provide that a:
    reviewing court shall . . . (2) hold unlawful and set aside agency action,
    findings, and conclusions found to be --- [¶] (A) arbitrary, capricious, an
    abuse of discretion, or otherwise not in accordance with law; [¶] (B)
    contrary to constitutional right, power, privilege, or immunity; [¶] (C) in
    excess of statutory jurisdiction, authority, or limitations, or short of
    statutory right; [¶] (D) without observance of procedure required by law;
    [¶] (E) unsupported by substantial evidence in a case subject to sections
    556 and 557 of this title or otherwise reviewed on the record of an agency
    hearing provided by statute; or [¶] (F) unwarranted by the facts to the
    extent that the facts are subject to trial de novo by the reviewing court.
    In making the foregoing determinations, the court shall review the
    whole record or those parts of it cited by a party, and due account shall
    be taken of the rule of prejudicial error.
    5 U.S.C. § 706 (2012).
    Based on an apparent misreading of the legislative history, see Gulf Grp., Inc.
    v. United States, 
    61 Fed. Cl. 338
    , 350 n.25 (2004), the Supreme Court had
    - 16 -
    determined, before the 1996 enactment of the ADRA, that the de novo review
    standard of 5 U.S.C. § 706(2)(F) does not usually apply in review of informal agency
    decisions --- decisions, that is, such as procurement awards, see Citizens to Pres.
    Overton Park, Inc. v. Volpe (Overton Park), 
    401 U.S. 402
    , 415 (1971). Instead,
    courts in those cases are supposed to apply the standard of 5 U.S.C. § 706(2)(A):
    whether the agency’s acts were “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law.” See Overton 
    Park, 401 U.S. at 416
    (citation
    omitted); see also Advanced Data Concepts, Inc. v. United States, 
    216 F.3d 1054
    ,
    1057 (Fed. Cir. 2000) (applying 5 U.S.C. § 706(2)(A)). But see Impresa Construzioni
    Geom. Domenico Garufi v. United States (Domenico Garufi), 
    238 F.3d 1324
    , 1332
    n.5 (Fed. Cir. 2001) (also citing 5 U.S.C. § 706(2)(D) as applicable in bid protests).
    The “focal point for judicial review” is usually “the administrative record already in
    existence,” Camp v. Pitts, 
    411 U.S. 138
    , 142 (1973), even when the matter under
    review was not the product of a formal hearing, see Fla. Power & Light Co. v.
    Lorion, 
    470 U.S. 729
    , 744 (1985); Axiom Res. Mgmt., Inc. v. United States, 
    564 F.3d 1374
    , 1379 (Fed. Cir. 2009).
    A motion for judgment on the administrative record under Rule 52.1 of the
    Rules of the United States Court of Federal Claims (RCFC) differs from motions for
    summary judgment under RCFC 56, as the existence of genuine issues of material
    fact does not preclude judgment on the administrative record. See Bannum, Inc. v.
    United States, 
    404 F.3d 1346
    , 1355–57 (Fed. Cir. 2005); Fort Carson Supp. Servs. v.
    United States, 
    71 Fed. Cl. 571
    , 585 (2006). Rather, a motion for judgment on the
    administrative record examines whether the administrative body, given all the
    disputed and undisputed facts appearing in the record, acted in a manner that
    complied with the legal standards governing the decision under review. See Fort
    
    Carson, 71 Fed. Cl. at 585
    ; Greene v. United States, 
    65 Fed. Cl. 375
    , 382 (2005);
    Arch Chems., Inc. v. United States, 
    64 Fed. Cl. 380
    , 388 (2005). Factual findings are
    based on the evidence in the record, “as if [the court] were conducting a trial on the
    record.” 
    Bannum, 404 F.3d at 1357
    ; see also Carahsoft Tech. Corp. v. United States,
    
    86 Fed. Cl. 325
    , 337 (2009); Gulf 
    Grp., 61 Fed. Cl. at 350
    .
    Under the “arbitrary and capricious” standard, the court considers “whether
    the decision was based on a consideration of the relevant factors and whether there
    has been a clear error of judgment” by the agency. Overton 
    Park, 401 U.S. at 416
    .
    Although “searching and careful, the ultimate standard of review is a narrow one.
    The court is not empowered to substitute its judgment for that of the agency.” 
    Id. The court
    will instead look to see if an agency has “examine[d] the relevant data
    and articulate[d] a satisfactory explanation for its action,” Motor Vehicle Mfrs. Ass’n
    v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983), and “may not supply a
    reasoned basis for the agency’s action that the agency itself has not given,” Bowman
    Transp., Inc. v. Ark.-Best Freight Sys., Inc., 
    419 U.S. 281
    , 285–86 (1974). The court
    must determine whether “the procurement official’s decision lacked a rational
    basis.” Domenico 
    Garufi, 238 F.3d at 1332
    (adopting APA standards the D.C.
    - 17 -
    Circuit developed); see also Delta Data Sys. Corp. v. Webster, 
    744 F.2d 197
    , 204
    (D.C. Cir. 1984). A second ground for setting aside a procurement decision is when
    the protester can show that “the procurement procedure involved a violation of
    regulation or procedure.” Domenico 
    Garufi, 238 F.3d at 1332
    . This showing must
    be of a “clear and prejudicial violation of applicable statutes or regulations.” 
    Id. at 1333
    (quoting Kentron Haw., Ltd. v. Warner, 
    480 F.2d 1166
    , 1169 (D.C. Cir. 1973)).
    Under the first rational basis ground, the applicable test is “whether ‘the
    contracting agency provided a coherent and reasonable explanation of its exercise of
    discretion.’” Domenico 
    Garufi, 238 F.3d at 1333
    (quoting Latecoere Int’l, Inc. v.
    United States Dep’t of Navy, 
    19 F.3d 1342
    , 1356 (11th Cir. 1994)). This entails
    determining whether the agency “‘entirely failed to consider an important aspect of
    the problem, offered an explanation for its decision that runs counter to the
    evidence before the agency,’” or made a decision that was “‘so implausible that it
    could not be ascribed to a difference in view or the product of agency expertise.’”
    Ala. Aircraft Indus., Inc.-Birmingham v. United States, 
    586 F.3d 1372
    , 1375 (Fed.
    Cir. 2009) (quoting Motor Vehicle Mfrs. 
    Ass’n, 463 U.S. at 43
    ).
    Because of the deference courts give to discretionary procurement decisions,
    “the ‘disappointed bidder bears a heavy burden of showing that the [procurement]
    decision had no rational basis.’” Domenico 
    Garufi, 238 F.3d at 1333
    (quoting
    Saratoga Dev. Corp. v. United States, 
    21 F.3d 445
    , 456 (D.C. Cir. 1994)). The
    protester must demonstrate, by a preponderance of the evidence, the absence of any
    rational basis for the agency decision. See Overstreet Elec. Co. v. United States, 
    59 Fed. Cl. 99
    , 117 (2003); Info. Tech. & Appl’ns Corp. v. United States, 
    51 Fed. Cl. 340
    ,
    346 (2001) (citing GraphicData, LLC v. United States, 
    37 Fed. Cl. 771
    , 779 (1997)),
    aff’d, 
    316 F.3d 1312
    (Fed. Cir. 2003). If arbitrary action is found as a matter of law,
    the court will then decide the factual question of whether the action was prejudicial
    to the bid protester. See 
    Bannum, 404 F.3d at 1351
    –54.
    2. Injunctive Relief
    In a bid protest, the court has the power to issue a permanent injunction
    pursuant to 28 U.S.C. § 1491(b)(2). In determining whether to grant a motion for a
    permanent injunction, the court applies a four-factored standard, under which a
    plaintiff must show: (a) that it has actually succeeded on the merits; (b) that it will
    suffer irreparable harm if the procurement is not enjoined; (c) that the harm it will
    suffer, if the procurement action is not enjoined, will outweigh the harm to the
    government and third parties; and (d) that granting injunctive relief serves the
    public interest. Centech Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir.
    2009); PGBA, LLC v. United States, 
    389 F.3d 1219
    , 1228–29 (Fed. Cir. 2004); MORI
    Assocs., Inc. v. United States, 
    102 Fed. Cl. 503
    , 551–53 (2011). None of the four
    factors, standing alone, is dispositive; thus, “the weakness of the showing regarding
    one factor may be overborne by the strength of the others.” FMC Corp. v. United
    - 18 -
    States, 
    3 F.3d 424
    , 427 (Fed. Cir. 1993); AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 378 (2009). Conversely, the lack of an “adequate showing with regard to any
    one factor may be sufficient, given the weight or lack of it assigned the other
    factors,” to deny the injunction. Chrysler Motors Corp. v. Auto Body Panels of Ohio,
    Inc., 
    908 F.2d 951
    , 953 (Fed. Cir. 1990). A lack of success on the merits, however,
    precludes the possibility of an injunction. See Amoco Prod’n Co. v. Vill. of Gambell,
    
    480 U.S. 531
    , 546 n.12 (1987) (explaining that a permanent injunction requires
    “actual success” on the merits); Tech Sys., Inc. v. United States, 
    98 Fed. Cl. 228
    , 268
    (2011); Gulf 
    Grp., 61 Fed. Cl. at 364
    .
    B. Analysis
    Plaintiff makes five separate arguments in support of its protest. The first
    three involve claims that the Agency did not follow either the terms of the
    solicitation or the FAR, and the final two challenge several evaluation decisions as
    arbitrary.
    1. ORAU’s Proposal Included All Required Information
    Plaintiff contends that ORAU’s proposal failed to include two items required
    by the solicitation --- a Small Business Subcontracting Plan and a transition plan.
    Pl.’s Mot. at 2, 6. With respect to the first point, defendant and intervenor both
    correctly point out that plaintiff is confusing the Small Business Subcontracting
    Plan with an offeror’s proposed use of small businesses. Def.’s Mot. at 11–15; Int.’s
    Mot. at 22–24. The former was required to be included in Volume I of an offeror’s
    proposal, while the latter was a subcriterion of the Program Implementation
    criterion used to evaluate Volume II. Compare AR at 776–77 (describing the Small
    Business Subcontracting Plan) with AR at 853 (explaining small business use
    subcriterion). As the SEB noted in its evaluation of ORAU’s proposal, a fully
    executed Small Business Subcontracting Plan was included with that proposal. AR
    at 2224–25; see also AR at 1472, 1482–92 (ORAU Small Business Subcontracting
    Plan).
    Plaintiff stresses that under the Program Implementation criterion, offerors
    were to be evaluated on the extent to which they proposed using small business in
    areas “directly impacting” the DOE’s mission, and that ORAU proposed using small
    business subcontractors only in support roles. Pl.’s Mot. at 5–6; see AR at 853
    (evaluation subcriterion for use of small business under the Program
    Implementation criterion); AR at 1563–65 (ORAU proposes using small business
    subcontractors for services such as information technology, meeting planning and
    travel services). The SEB determined that this limited use of small businesses was
    a “significant weakness” in ORAU’s proposal. AR at 2261. Plaintiff argues that this
    should be downgraded to a deficiency. Pl.’s Mot. at 5–6. But DRI has identified no
    objective errors or subjective inconsistencies connected with this particular rating,
    and thus there is no basis for the Court to find it arbitrary or unlawful. See
    - 19 -
    USfalcon, Inc. v. United States, 
    92 Fed. Cl. 436
    , 461 (2010). Plaintiff ’s challenge
    amounts to a request that the evaluation be second-guessed, which is not the
    province of a reviewing court. E.W. Bliss Co. v. United States, 
    77 F.3d 445
    , 449
    (Fed. Cir. 1996).
    The second point raised by DRI is its contention that ORAU’s proposal should
    have been excluded from award consideration based on the failure to include a
    transition plan. Pl.’s Mot. at 6–8. One of the seven “[s]pecific [a]reas to be
    [a]ddressed” by offerors in Volume II was a transition plan, which was to be “a
    detailed and comprehensive plan.” AR at 779, 788. Offerors were told that this
    plan “should describe” a “management approach” and the maintenance of a
    “continuity of operations,” and “should include” seven different transition activities.
    AR at 788. Under the Transition Plan evaluation criterion, this plan was to “be
    evaluated with respect to its feasibility, comprehensiveness, efficiency and
    effectiveness, including the extent to which it provides for a smooth and orderly
    transition, identifies key issues and milestones, identifies potential barriers to a
    smooth transition, proposes solutions to the barriers identified, and minimizes
    impacts on continuity of operations.” AR at 856.
    The transition plan of ORAU was described on pages 64 through 69 of
    Volume II of the proposal submitted. See AR at 1572–77. Intervenor, however,
    neglected to include in its page count the nine pages at the front of this volume
    which contained its list of acronyms and a “crosswalk” matching proposal portions
    with solicitation provisions. See AR at 1500–08. Such materials were not
    excludable from the 70-page limit, AR at 778–79, and accordingly the Contracting
    Officer determined that numbered page 61 was the last page of the volume that
    could be evaluated. AR at 2048. The remainder of the volume, including the pages
    describing the transition plan, were removed from the proposal before it was
    evaluated. 12 AR at 2274, 2333, 2341–42.
    The SEB rated ORAU’s proposal under the Transition Plan criterion as
    Marginal, with a significant weakness and no strengths --- deciding that the
    absence of a formal transition plan decreased the likelihood of successful contract
    performance, but that there was sufficient information in the remainder of the
    proposal regarding transition to mitigate this risk. AR at 2274–75. In particular,
    the SEB noted the presence of “information related to the use of existing facilities
    and systems, the transition manager, retention of current key personnel,
    continuation of employee pay and benefits, and confirmation that right of first
    refusal will be offered,” as well as “information related to relevant experience in
    transitioning and performing work under the current contract.” AR at 2273–74.
    12 The information on numbered page 70, concerning corporate commitments, AR at
    1578, did not count toward the page limit, AR at 779, and was also reviewable, AR
    at 2048.
    - 20 -
    Plaintiff does not dispute that this information was contained in the ORAU
    proposal, which touched on most if not all of the transition activities that offerors
    were advised to include in a transition plan. See AR at 788 (listing, among other
    things, plans for operational control of facilities, handling incumbent employees,
    transferring government property, and assuming control of business and
    management systems); AR at 1511, 1530–32 (ORAU proposal discussing transition
    approach to facilities, equipment and systems, retention of personnel and benefits,
    and transition manager). The SSO concurred in the SEB’s findings and conclusion,
    noting that the absence of a formal transition plan in the ORAU proposal was a
    significant weakness, but that there was sufficient information provided relating to
    transition activities to reduce the risks associated with this flaw to a manageable
    level. AR at 2341–42.
    Plaintiff argues that the absence of a formal transition plan from the ORAU
    proposal should have resulted in the proposal’s exclusion from the competition, or at
    least in a finding of a deficiency and a lower rating. Pl.’s Mot. at 7–8. But DRI has
    provided no reason why the information in the ORAU proposal relating to transition
    could not be considered as meeting the basic requirements of a transition plan,
    albeit one not as detailed and comprehensive as the Agency desired. The SEB gave
    a rational explanation of how information in the ORAU proposal addressed
    transition activities and reduced risk to the continuity of operations. AR at 2274–
    75. It also acknowledged that the absence of information concerning key issues,
    milestones, and potential barriers and their solutions, “appreciably increases the
    risk of unsuccessful contract performance,” AR at 2275, justifying the finding of a
    significant weakness, see AR at 2217. The SSO rationally explained how the
    information in the ORAU proposal allowed for an assessment of “the feasibility,
    comprehensiveness, efficiency and effectiveness of the offeror’s transition activities,”
    making the risk manageable. AR at 2342. While DRI may disagree with these
    assessments, it has not identified any objective errors or subjective inconsistencies
    that could render the judgment arbitrary. See 
    USfalcon, 92 Fed. Cl. at 461
    . 13
    13 Plaintiff argues that at least one SEB member might have improperly reviewed
    ORAU’s formal transition plan, as his preliminary notes stated that ORAU’s
    transition plan was “very thorough and should provide for a successful transition.”
    Pl.’s Mot. at 7 (quoting AR at 2904). But this was clearly a typographical error, as
    the page and section numbers cited in this draft evaluation, AR at 2904, match
    those containing the transition plan in DRI’s proposal and not in ORAU’s proposal,
    see AR at 981–92, 1572–77, and the identical comment was made about DRI’s
    transition plan, see AR at 2887.
    - 21 -
    2. The Agency’s Failure to Seek Clarification from DRI Was Neither Improper
    Nor Prejudicial
    Plaintiff ’s second protest ground concerns the failure of its proposal to
    contain a working link to data that was apparently contained in a workbook called
    “Estimate Assumptions.xlsx.” See Pl.’s Mot. at 8–12; Pl.’s Reply Br. to Mot. for J. on
    the R. (Pl.’s Reply) at 2–6. The solicitation required that Volume III, each offeror’s
    cost proposal, explain any “conditional assumptions” and contain as exhibits
    spreadsheets in which “[a]ll cell formulas must be included.” AR at 767–68.
    Offerors were told that the cost evaluation was to determine the probable cost of
    their approach, and that “[t]he Government will evaluate the offeror’s cost proposal,
    supporting data, basis of estimate, and cost assumptions to determine cost realism,
    cost reasonableness and the offeror’s understanding of the contract requirements.”
    AR at 856. The spreadsheets containing DRI’s cost data exhibits and schedules, AR
    at 1302–73, reference the “Estimate Assumptions.xlsx” workbook in the formulas
    depicted for certain cells, but the link to that workbook could not be opened by the
    advisors preparing the cost report, AR at 2155. Without access to this data, and
    absent an adequate explanation of DRI’s cost estimating methodology in the Volume
    III text, the advisors could not determine the realism and reasonableness of the
    proposed costs and as a consequence could not derive any probable costs for
    plaintiff. AR at 2155–62.
    Plaintiff argues that its omission of the workbook data either was a clerical
    error that should have been the subject of a clarification request under 48 C.F.R.
    § 15.306(a)(2), or was a material defect making its proposal nonresponsive --- in
    which case the proposal should have been rejected before the evaluation stage of the
    procurement process. Pl.’s Mot. at 10–11; Pl.’s Reply at 3–5. Taking the latter (and
    more novel) argument first, DRI contends that the Contracting Officer informed its
    representatives during the oral debriefing “that the absence of the ‘workbook’ was
    noticed when the Plaintiff ’s Proposal was first reviewed.” Pl.’s Reply at 3. The
    record contains no support for this contention. Moreover, while the initial review of
    proposals conducted by the SEB Executive Secretary could have resulted in the
    decision to eliminate a proposal “before a detailed evaluation is performed,” the SSP
    did not mandate such a result and allowed it only when a “proposal is determined to
    be so grossly and obviously deficient as to be totally unacceptable on its face or to
    contain prices that are inordinately high or unrealistically low.” AR at 54.
    Nothing in the record suggests that the inoperative link to the workbook,
    embedded in cost spreadsheets, made the proposal “totally unacceptable on its face.”
    Indeed, considering that the cost report in which the omission was first noted was
    issued on January 12, 2016, AR at 2148, more than three months after DRI’s
    October 7, 2015 oral presentation, AR at 1374–450, it is likely that the Agency was
    not even aware that the data was missing before all of DRI’s proposal costs were
    - 22 -
    incurred. 14 In any event, plaintiff ’s unusual argument that it should have lost the
    competition earlier, sparing it some proposal costs and saving the government
    evaluation expenses, Pl.’s Mot. at 11, is not the sort of claim that can be raised in a
    post-award bid protest. To have standing to challenge alleged errors in the award
    of a government contract, an offeror must allege that those errors --- either
    individually or cumulatively, see 
    USfalcon, 92 Fed. Cl. at 450
    --- deprived it of “a
    substantial chance of receiving an award.” Labatt Food Service, Inc. v. United
    States, 
    577 F.3d 1375
    , 1379–80 (Fed. Cir. 2009); see also Info. 
    Tech., 316 F.3d at 1319
    ; Alfa Laval Separation, Inc. v. United States, 
    175 F.3d 1365
    , 1367 (Fed. Cir.
    1999). The claim that an error delayed the rightful denial of a contract award
    cannot fit under this concept of standing. 15
    Turning to DRI’s more conventional argument concerning the omitted
    workbook data, it contends that the omission was a clerical error which the Agency
    should have sought to have clarified under 48 C.F.R. § 15.306(a)(2). Pl.’s Mot. at
    10–11. Defendant and intervenor note that this FAR provision is permissive and
    does not require that an agency seek a clarification, even when a minor or clerical
    error is discovered. Def.’s Mot. at 26; Int.’s Mot. at 28–29; Intervenor’s Reply in
    Support Cross-mot. for J. on the R. (Int.’s Reply) at 6 n.4. While this is true, there
    have been circumstances when this discretion has been found to have been abused
    by a procuring agency. See BCPeabody Constr. Servs., Inc. v. United States, 
    112 Fed. Cl. 502
    , 512 (2013).
    Plaintiff ’s opponents, however, argue that the omission of the data and cost
    assumptions that were apparently contained in the workbook constitutes a material
    omission, not a clerical error eligible for clarification. Def.’s Mot. at 27–28; Int.’s
    Mot. at 29. Indeed, several precedents from our court have found that the
    erroneous omission of cost data from a proposal was not a minor or clerical error
    under the clarification provision. See Constellation W., Inc. v. United States, 
    125 Fed. Cl. 505
    , 550 (2015) (citing Bus. Integra, Inc. v. United States, 
    116 Fed. Cl. 328
    ,
    337 (2014); ST Net, Inc. v. United States, 
    112 Fed. Cl. 99
    , 110–11 (2013)). Just as in
    those cases, DRI omitted required information that was necessary for the
    evaluation of its proposed price. Although that line of cases was identified by both
    defendant and intervenor, see Def.’s Mot. at 26–27 (discussing Constellation W. and
    14 Under the procedure followed by the Agency, the SEB voting members did not
    see any of the cost information until the Capabilities and Approach factor
    evaluations were completed. AR at 60, 2219.
    15 In addition, the economic harm an agency imposes on itself due to an alleged
    procurement error cannot be the basis for an offeror’s protest, cf. Res Rei Dev., Inc.
    v. United States, 
    126 Fed. Cl. 535
    , 549–50 (2016) (explaining that a protester cannot
    challenge actions harming only third parties), although it can obviously play a role
    in injunctive relief analysis.
    - 23 -
    ST Net); Int.’s Mot. at 29 (citing Constellation W.), DRI failed to address them, and
    cites no authorities in support of its contention that the omission of the workbook
    was a clerical error which imposed a duty to seek clarification on the Agency.
    Instead, plaintiff insists repeatedly that the omission was so “obvious” it must have
    been a clerical error, see Pl.’s Mot. at 10–12, and maintains that the inclusion of the
    workbook data “would not have materially altered the Plaintiff’s cost proposal,” Pl.’s
    Reply at 5. But it must have been obvious in these other cases that the offerors did
    not intend to leave blank certain cells in the spreadsheets contained in their
    proposals, and the missing information represented a small percentage of total
    costs, yet the omissions were found to be material. See Constellation W., 125 Fed.
    Cl. at 549 (noting missing rates would have raised total price by 0.008%); Bus.
    
    Integra, 116 Fed. Cl. at 334
    –35 (explaining missing costs were 0.0041% of total).
    And in any event, while the missing data and assumptions may not have changed
    DRI’s proposed price, they certainly could have had a “non-negligible effect” on the
    probable cost of plaintiff ’s proposal. See Constellation 
    W., 125 Fed. Cl. at 549
    . On
    this record, the Court cannot find that the Agency erred in treating this omission as
    material.
    Even were DRI correct that its omission of the “Estimate Assumptions.xlsx”
    workbook was a clerical error that should have prompted a request for clarification
    from DOE, this protest ground would be of no avail to DRI. As both defendant and
    intervenor point out, see Int.’s Mot. at 30; Def.’s Reply at 4, after finding the DRI
    proposal unacceptable because realism analysis could not be performed to derive a
    probable cost, the SSO nevertheless explained why ORAU’s proposal offered the
    Agency better value because of its technical superiority. AR at 2343–44. The SSO
    used DRI’s proposed cost in her tradeoff analysis. 
    Id. at 2344.
    Thus, the absence of
    the workbook data was not prejudicial to DRI, as a determination that its costs
    were realistic would not have altered the award decision.
    3. The Agency’s Failure to Provide Prospective Offerors With Certain
    Information Was Neither Improper Nor Timely Challenged
    Plaintiff ’s next protest ground is that the Agency improperly failed to provide
    certain information that was requested during the pre-bid question and answer,
    adversely affecting its bid. Pl.’s Mot. at 12–15; Pl.’s Reply at 6–12. Two separate
    arguments are advanced by DRI on this ground: first, that information concerning
    the incumbent’s labor mix and employee compensation and benefits should have
    been shared with prospective offerors, Pl.’s Mot. at 12–14; and second, that without
    access to this information, plaintiff relied on FTE levels contained in a report that
    the Agency referenced, which differed from ORAU’s proposed numbers, 
    id. at 14–15.
    - 24 -
    a. The labor mix and compensation data.
    Two particular types of information are at issue here. First, DRI claims that
    it was harmed by not being provided with information regarding the labor mix for
    the predecessor ORISE contract. Pl.’s Mot. at 12–14. A prospective offeror
    requested this information during the pre-bid question and answer period. AR at
    871. Similarly, questions were asked concerning employee compensation and
    benefits under the incumbent’s contract. 
    Id. at 872,
    879–80. The Agency responded
    to all of these inquiries by stating that all information that could be released
    already had been, and that most of the requested information represented
    contractor records that could not be released. 
    Id. at 871–73,
    879–80.
    Plaintiff argues that without information about the incumbent’s labor mix, it
    could not have proposed staffing levels using the “bottoms up” methodology that the
    Agency preferred, and was thus unfairly criticized by the SEB for using a “top
    down” approach. Pl.’s Mot. at 13–14 (citing AR at 2223, 2255–56, 2299–300); see AR
    at 758 (solicitation instruction requiring either “a detailed ‘bottoms up’ type
    estimating technique” or a “thoroughly explained” alternative methodology).
    Concerning labor costs, DRI contends that its cost proposal would have been
    different had it known the level of benefits paid to the incumbent’s staff, and been
    informed “that [XXXXXXX] of ORAU staff only works part time [XXXXXXX].” Pl.’s
    Mot. at 13.
    Defendant and intervenor argue that this protest ground has been waived,
    under Blue & Gold Fleet, due to DRI’s failure to raise it before either the submission
    deadline or contract award. Int.’s Mot. at 31 (citing Blue & Gold 
    Fleet, 492 F.3d at 1313
    ); Def.’s Mot. at 19 (citing Blue & Gold 
    Fleet, 492 F.3d at 1315
    ). Plaintiff did
    not rebut this argument. See Pl.’s Reply at 6–12. At the hearing on these motions,
    DRI’s counsel acknowledged that the Agency’s refusal to provide the requested
    information was known prior to the deadline for submitting proposals, and conceded
    that he could not distinguish Blue & Gold Fleet. See Tr. (July 29, 2016) (Tr.) at 17–
    18. These concessions were wise, as this protest argument has clearly been waived
    under Blue & Gold Fleet. Plaintiff contends that necessary information was not
    provided along with the solicitation materials, and the importance of its absence
    was established prior to the deadline for submitting proposals --- when requests for
    the information were denied at least one week before proposals were due. See AR at
    870 (questions and answers updated on Sept. 1, 2015). Indeed, the Agency’s
    answers to potential offerors’ questions, updated as new questions were received,
    were issued as amendments to the solicitation, see AR at 227, 2204–05, and thus
    DRI is challenging the terms of the solicitation with this argument. As no objection
    to the Agency’s refusal to provide the information was made prior to the submission
    deadline, this ground has been waived. Blue & Gold 
    Fleet, 492 F.3d at 1313
    –15.
    - 25 -
    b. The Ten-Year Site Plan.
    The second argument DRI makes under this ground focuses on the difference
    between staffing levels as reported in ORISE’s Ten-Year Site Plan and those
    proposed by ORAU. See Pl.’s Mot. at 14–15; Pl.’s Reply at 7–12. Because this plan
    stated that 608 FTEs supported the ORISE contract in fiscal year 2014 and
    projected that same level of staffing for fiscal year 2016, Pl.’s Ex. A at 3–4, DRI
    proposed 608 FTEs to perform the contract --- divided between 511 “direct” FTEs
    and 97 “indirect” FTEs. AR at 1115–16. As intervenor was awarded the contract by
    proposing only 205 FTEs, see AR at 1926, 2311, plaintiff maintains that it was
    either misled by the numbers in the Ten-Year Site Plan or held to a different
    standard from that applied to ORAU. Pl.’s Mot. at 14–15. There are at least three
    problems with this argument of DRI.
    First, the Ten-Year Site Plan was not incorporated into the solicitation, but
    was instead referenced in response to two questions that were unrelated to staffing
    levels under the contract. Potential offerors were told they “should review” the plan
    because it “addresses both the anticipated actions and estimated timeline by which
    activities should be completed” concerning the disposal of two government-
    furnished buildings. AR at 872. They were also informed that they “may reference
    the facility maintenance cost projections” in the plan. AR at 878. Potential offerors
    were not instructed to use the Ten-Year Site Plan for any other purposes, and thus
    the Agency did not mislead DRI into following the staffing projections in that
    document.
    Second, as both defendant and intervenor emphasize, see Def.’s Mot. at 24;
    Int.’s Mot. at 33, DRI’s proposed staffing was not criticized for its total number of
    FTEs proposed, but rather for not adequately explaining the methodology it used to
    arrive at its labor mix and staffing approach. See AR at 2160, 2255–56, 2299–301.
    Even if plaintiff was led to believe, based on the Ten-Year Site Plan projections,
    that the Agency desired 608 FTEs to support the contract, it was not its use of this
    figure but rather its inability to adequately justify how those employees would be
    distributed that negatively affected its evaluation.
    Finally, as the government best explains, see Def.’s Mot. at 24–25, the direct
    labor FTEs proposed by ORAU were not the full measure of its staffing. Included in
    intervenor’s “Other Direct Costs” (ODCs) were the costs of subcontractors and such
    functions as professional services, site services, equipment maintenance, and
    computer support. AR at 2170, 2315–16. These costs were [XXXXXXXXXXXXX]
    than ORAU’s proposed direct labor costs. See AR at 1926. The cost evaluators
    confirmed that the proposed ODCs were consistent with the incumbent’s
    performance history. AR at 2170. According to defendant’s calculations, the
    indirect labor hours implicit in the ODCs category would raise ORAU’s total FTEs
    proposed to be roughly [XX] percent of the DRI figure. Def.’s Mot. at 25 (citing AR
    - 26 -
    at 1960, 1989, 1991, 1993). For our purposes, what is important is that the record
    shows that the calculations of FTEs supporting the ORISE contract historically
    included personnel whose costs were charged as ODCs, and that intervenor’s
    proposal was consistent with that practice. Thus, plaintiff has failed to show that
    the ORAU proposal was evaluated under a different standard regarding staffing
    levels, as staffing costs proposed as ODCs cannot be ignored in assessing the labor
    effort proposed by intervenor.
    4. Plaintiff’s Criticisms of the SEB’s Technical Evaluations are Mere
    Disagreements with the Agency’s Judgment
    The next protest ground raised by DRI consists of criticisms of six specific
    aspects of the SEB’s evaluation of the proposals under the Capabilities and
    Approach factor. See Pl.’s Mot. at 16–22. 16 According to plaintiff, these portions of
    the evaluations either lacked record support, were inconsistent, or were contrary to
    the stated criteria. 
    Id. at 15.
    But as we shall see, no objective errors or subjective
    inconsistencies have been identified, see 
    USfalcon, 92 Fed. Cl. at 461
    , and thus
    DRI’s criticisms merely reflect disagreement with the Agency’s technical judgments
    --- judgments which a court may not second guess, see E.W. Bliss 
    Co., 77 F.3d at 449
    .
    First, DRI takes issue with the weakness it received due to the absence of
    “commitment letters” from its proposal, see AR at 2277, which were supposed to be
    provided by entities supplying goods or services, at no charge to the government, for
    use in connection with the ORISE contract. Pl.’s Mot. at 16–17; AR at 789, 856. It
    is not disputed that DRI failed to provide such letters, as plaintiff instead contends
    that the Agency treated the two offerors disparately. Pl.’s Mot. at 16–17. This
    argument rests on the fact that ORAU did not provide commitment letters from its
    proposed subcontractors. 
    Id. at 17.
    But plaintiff is confusing two different
    solicitation provisions. The solicitation had no requirement that proposed
    subcontractors, who will be providing goods or services in exchange for
    compensation, furnish “commitment letters.” See AR at 785–86. Such letters were
    only required for entities that were pledging to provide free goods or services to
    support the ORISE contract. See AR at 789, 856. Thus, no disparity in treatment
    has been shown.
    16 In addition to the particular critiques, DRI also argues generally that the
    evaluation criteria were vague and that the definitions for the adjectival ratings
    were not disclosed. Pl.’s Mot. at 15–16. But complaints about what the solicitation
    contained or should have contained are waived at this juncture. See Blue & Gold
    
    Fleet, 492 F.3d at 1313
    –15. And plaintiff ’s counsel conceded that he is aware of no
    regulation or statute requiring the prior disclosure of adjectival ratings definitions.
    Tr. at 27. See also 48 C.F.R. § 15.304(d) (“The rating method need not be disclosed
    in the solicitation.”).
    - 27 -
    Second, plaintiff challenges the weaknesses it received, under the Strategic
    Vision and Program Implementation criteria, in connection with its proposed move
    of the REAC/TS operations to a new facility. Pl.’s Mot. at 18–19. The SEB found
    that “the proposal does not contain sufficient information regarding the required
    resources, resource related assumptions, and other assumptions related to the
    proposed move,” and “failed to demonstrate the capability to leverage limited
    resources in developing the Institute’s capabilities.” AR at 2229 (citing AR at 936–
    37, 987). The evaluators were also concerned that a diversion of resources to
    accomplish the proposed move “would have a negative impact on mission execution
    because fewer resources would be available for training.” AR at 2255. These
    weaknesses were based on the application of evaluation subcriteria, see AR at 852–
    53 (Strategic Vision subcriterion 2 and Program Implementation subcriterion 3),
    and the portions of DRI’s Volume II that were referenced did not discuss the
    resources required, as the SEB states, see AR at 936–37, 987. Plaintiff ’s objection is
    that at an unspecified place in the introduction to its proposal, it committed to keep
    expenses within budget. Pl.’s Mot. at 18–19. But this does not contradict the SEB’s
    concerns about a lack of detail regarding the proposed move. The Court finds that
    the SEB adequately explained the reasoning behind these weaknesses.
    Plaintiff ’s third argument relates to weaknesses DRI was assigned under the
    Leadership, Management, and Direction criterion. Pl.’s Mot. at 19–20 (citing AR at
    2243–46). Rather than identifying any objective errors or subjective inconsistencies
    on the part of the SEB, plaintiff instead cites the strengths noted in one individual
    evaluator’s preliminary review of its proposal, which were not reflected in the SEB’s
    final report. 
    Id. at 19
    (citing AR at 2875–76, 2878). But since a consensus approach
    was followed by the SEB, see AR at 2216, such preliminary findings of individual
    evaluators are rarely a basis for undermining the rationality of the ultimate
    evaluation, see Tech 
    Sys., 98 Fed. Cl. at 246
    –48, and DRI has failed to make that
    case here. 17
    The fourth disputed area of the Capabilities and Approach factor evaluation
    concerns a weakness DRI received under the Leadership, Management, and
    Direction criterion. Plaintiff maintains it was “highly criticized” because, during its
    oral presentation, its entire management team was shown to be unfamiliar with
    DOE’s Office of Science peer review process. Pl.’s Mot. at 20–21 (citing AR at 2245).
    The SEB found this to be problematic because understanding the Office of Science’s
    peer review process was necessary to successfully accomplish the Science and
    Technical Resource Integration required by the PWS. AR at 236–37, 2245. Plaintiff
    claims it had “no way” to obtain information about the current peer review process,
    17 Erring in the other direction, DRI also inaccurately attributes to the SEB a
    significant weakness that the same individual evaluator assigned it in his
    preliminary review. See AR at 2876 (noting DRI’s proposed REAC/TS Director was
    not a medical doctor); Pl.’s Mot. at 19 (identifying same).
    - 28 -
    Pl.’s Mot. at 20, but defendant notes that this information is publicly available,
    Def.’s Mot. at 32 n.1 (citing http://science.energy.gov/sc-2/committees-of-visitors); see
    also Int.’s Mot. at 39 n.25. The Court notes that this criticism was merely one of
    seven bullet points listed to support the finding of a weakness regarding the
    qualifications of DRI’s proposed key persons, and did not have the significance that
    plaintiff suggests. See AR at 2244–45. Plaintiff seems to be arguing that it was
    immune from criticism in this area, as it claims that it mentioned “peer review”
    fourteen times in its proposal. Pl.’s Mot. at 20 (citing AR at 929, 933–36). But
    particularly considering that the Statement of Work for STRI required the
    contractor to “[i]dentify improvements to DOE peer review practices,” AR at 237,
    there is no basis for concluding that the SEB acted improperly in finding that a lack
    of knowledge of those practices contributed to a weakness for DRI’s proposed
    management team.
    Plaintiff ’s fifth claim regarding the SEB’s evaluation centers on the strength
    ORAU received for its approach to handling workload fluctuations. The SEB found
    that it was “an efficient business practice” that the majority of ORAU’s proposed
    staff would divide its work between the ORISE contract and other endeavors. AR at
    2258. Plaintiff questions whether this approach should be viewed positively or
    negatively, and posits several potential problems with such an arrangement. Pl.’s
    Mot. at 21–22. But DRI identifies no solicitation provision that is violated by the
    approach and no inconsistency in the SEB’s evaluation. Plaintiff merely disagrees
    with the Agency’s judgment, which is no basis for questioning a procurement
    decision. See E.W. Bliss 
    Co., 77 F.3d at 449
    .
    The final challenge to the SEB’s evaluation concerns an alleged inequality
    created by ORAU’s ownership of certain property, called the North Campus, which
    it could continue to use to perform the contract. Pl.’s Mot. at 22; Pl.’s Reply at 12–
    17. The government-furnished facilities, available for use by the successful offeror,
    were located at the South Campus and in a local medical center. AR at 584.
    Plaintiff argues that any offeror which was not the incumbent would have to bear
    the costs of moving the ORISE operations from the North Campus to other
    buildings, including leasing and renovation costs, and that the Agency should have
    leveled the playing field by removing facilities costs from the procurement. Pl.’s
    Mot. at 22: Pl.’s Reply at 16–17. Curiously, its only support for this proposition are
    two Government Accountability Office (GAO) decisions that explain that
    advantages, including cost advantages, that an incumbent enjoys by virtue of prior
    performance (including the ownership of key property) need not be equalized unless
    that advantage is the result of unfair government action. Pl.’s Reply at 16 (citing
    GTE Automatic Elec., Inc., B-209393, 83-2 CPD ¶ 340, 
    1983 WL 27378
    , at *1–3
    (Comp. Gen. Sept. 19, 1983); Romar Consultants, Inc., B-206489, 82-2 CPD ¶ 339,
    
    1982 WL 27429
    , at *2–3 (Comp. Gen. Oct. 15, 1982)). But DRI has not identified
    anything, in the record or elsewhere, that shows the North Campus was obtained
    through some improper action of the Agency, and the GAO decisions recognize that
    - 29 -
    the advantage enjoyed by an incumbent by virtue of having amortized the costs of
    property that it will continue to use for performance is not an improper advantage
    that must be equalized. GTE Automatic Elec., at *3 (citing B.B. Saxon Co., 57
    Comp. Gen. 501, 513 (June 1, 1978)). Most fatal to this argument, however, is the
    fact that ORAU’s ownership of the North Campus was made known to potential
    offerors in the questions and answers that were issued as amendments to the
    solicitation. See AR at 870–71. Any protest ground based on the solicitation’s
    failure to equalize the advantages of that ownership is waived, since it was not
    raised prior to the deadline for submitting proposals. Blue & Gold 
    Fleet, 492 F.3d at 1313
    –15.
    5. The Source Selection Decision Was Not Arbitrary
    In DRI’s final argument, it takes issue with one sentence in the SSO’s Source
    Selection Decision, which paraphrases SEB findings, and one paragraph from that
    decision containing an independent observation of the SSO. 18 Pl.’s Mot. at 23. Both
    of these are in the SSO’s evaluation of the proposals under the Strategic Vision
    criterion. AR at 2336.
    First, plaintiff challenges the following sentence concerning the SEB’s
    evaluation of its proposal under the first criterion: “The SEB concluded that the
    proposal from DRI failed to demonstrate the capability to leverage limited resources
    in developing ORISE’s capabilities, and specifically does not enable ORISE to
    achieve DOE goals, and would not deliver outcomes consistent with mission goals
    relative to the PWS area.” Pl.’s Mot. at 23 (citing AR at 2336). Plaintiff maintains
    that the SEB did not reach a “general conclusion” concerning its ability to leverage
    limited resources, but made such a finding “on a couple of separate issues” without
    factual support. 
    Id. But the
    SEB fully explained its reasons for these findings ---
    one relating to the proposed move of the REAC/TS facility, and the other concerning
    DRI’s “overall” Strategic Vision and plan for its implementation. AR at 2220–21,
    2229–30. The SSO accurately recounted these conclusions, the second of which was
    a general conclusion about the proposal under this criterion.
    Regarding the back end of this sentence, DRI contends that no facts were
    identified to support the findings concerning DOE goals, and that the term “goals”
    was not defined nor even included in the PWS. Pl.’s Mot. at 23. But the SEB
    report, with which the SSO agreed, AR at 2336, explains in detail the evaluators’
    concerns that DRI would not allow the Agency to achieve its goals for three of the
    18 Plaintiff also makes general comments at the beginning and end of this
    argument that the SSO had prejudged the competition in favor of ORAU. Pl.’s Mot.
    at 23–24. Plaintiff points to no facts to support this claim, other than the particular
    challenges to evaluation decisions discussed above, so the Court will not address it
    further.
    - 30 -
    five activities described in the PWS, AR at 2221, 2230–31 (discussing STRI,
    REAC/TS, and IEAV); see AR at 236–39 (Statement of Work). Moreover, the first
    two subcriteria under Strategic Vision concern “goals as articulated in the
    Performance Work Statement.” AR at 852. If DRI believes that a definition of
    these goals was missing from the solicitation, the time to challenge this was before
    its proposal was due, and accordingly this ground is waived. Blue & Gold 
    Fleet, 492 F.3d at 1313
    –15.
    Plaintiff also contends that the SSO improperly criticized its proposal for
    focusing on primary and secondary education, in addition to ORISE’s traditional
    focus on education at the college level and above. Pl.’s Mot. at 23. Although DRI
    argues that this criticism was inconsistent with the solicitation’s injunction to
    “ensure a robust supply of STEM professionals to meet science and technology
    needs . . . for students and faculty at all educational levels,” 
    id. (citing AR
    at 236),
    the SSO’s concern was the proposal’s “focus on a K-12 outreach,” AR at 2336
    (emphasis added), not the fact that pre-college students would be included in
    programs. In any event, as intervenor notes, Int.’s Mot. at 48, the SSO did not
    assign an additional weakness to DRI because of this issue, and her observation did
    not alter plaintiff ’s rating under the criterion, see AR at 2336–37. As plaintiff has
    identified no objective errors or subjective inconsistencies relating to this particular
    observation, but merely disagrees with the SSO’s judgment, this bid protest ground
    fails. See E.W. Bliss 
    Co., 77 F.3d at 449
    . In sum, plaintiff has failed to demonstrate
    that the SSO’s decision was arbitrary or otherwise improper.
    III. CONCLUSION
    For the foregoing reasons, plaintiff ’s motion for judgment on the
    administrative record is DENIED, and defendant’s and intervenor’s cross-motions
    for judgment on the administrative record are GRANTED. The Clerk shall enter
    judgment accordingly.
    IT IS SO ORDERED.
    s/ Victor J. Wolski
    VICTOR J. WOLSKI
    Judge
    - 31 -
    

Document Info

Docket Number: 16-376C

Citation Numbers: 132 Fed. Cl. 435, 2017 WL 2858890

Judges: Victor J. Wolski

Filed Date: 7/5/2017

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (21)

saratoga-development-corporation-v-united-states-of-america-saratoga , 21 F.3d 445 ( 1994 )

Amoco Production Co. v. Village of Gambell , 107 S. Ct. 1396 ( 1987 )

E.W. Bliss Company v. United States , 77 F.3d 445 ( 1996 )

Impresa Construzioni Geom. Domenico Garufi v. United States , 238 F.3d 1324 ( 2001 )

Labatt Food Service, Inc. v. United States , 577 F.3d 1375 ( 2009 )

Pgba, LLC v. United States, and Wisconsin Physicians ... , 389 F.3d 1219 ( 2004 )

Centech Group, Inc. v. United States , 554 F.3d 1029 ( 2009 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Alfa Laval Separation, Inc. v. United States, and Westfalia ... , 175 F.3d 1365 ( 1999 )

Citizens to Preserve Overton Park, Inc. v. Volpe , 91 S. Ct. 814 ( 1971 )

Camp v. Pitts , 93 S. Ct. 1241 ( 1973 )

latecoere-international-inc-and-latecoere-also-known-as-societe , 19 F.3d 1342 ( 1994 )

Chrysler Motors Corp. v. Auto Body Panels of Ohio, Inc., ... , 908 F.2d 951 ( 1990 )

Alabama Aircraft Industries, Inc.—Birmingham v. United ... , 586 F.3d 1372 ( 2009 )

Fmc Corporation and Monsanto Company v. The United States, ... , 3 F.3d 424 ( 1993 )

kentron-hawaii-limited-v-john-w-warner-secretary-of-the-navy , 480 F.2d 1166 ( 1973 )

Axiom Resource Management, Inc. v. United States , 564 F.3d 1374 ( 2009 )

Advanced Data Concepts, Incorporated v. United States , 216 F.3d 1054 ( 2000 )

Blue & Gold Fleet, L.P. v. United States , 492 F.3d 1308 ( 2007 )

Bannum, Inc. v. United States , 404 F.3d 1346 ( 2005 )

View All Authorities »