Certified Construction Co. of Kentucky, LLC v. United States ( 2016 )


Menu:
  •            In the United States Court of Federal Claims
    No. 15-1049C
    (Filed: October 31, 2016)
    )                  Keywords: Contract Disputes Act;
    CERTIFIED CONSTRUCTION CO. OF )                  Breach of Contract; Requirements
    KENTUCKY, LLC,                )                  Contract; Scope of Requirement;
    )                  Maximum-Order Limitation
    Plaintiff,    )
    )
    v.
    )
    THE UNITED STATES OF AMERICA, )
    )
    Defendant.    )
    )
    Thomas E. Roma, Jr., Ackerson & Yann, PLLC, Louisville, KY, for Plaintiff.
    Igor Helman, Trial Attorney, Commercial Litigation Branch, with whom were Donald E.
    Kinner, Assistant Director, Robert E. Kirschman, Jr., Director, and Benjamin C. Mizer,
    Principal Deputy Assistant Attorney General, U.S. Department of Justice, Washington,
    DC, for Defendant. Thomas S. Hong, Litigation Attorney, General Litigation Division,
    U.S. Army Legal Services Agency, Ft. Belvoir, VA, Of Counsel.
    OPINION AND ORDER
    KAPLAN, Judge.
    In this breach-of-contract case, Plaintiff Certified Construction of Kentucky, LLC
    (Certified) claims that the government breached three requirements contracts Certified
    held for completing concrete pavement and/or placement work at the U.S. Army base at
    Ft. Knox, Kentucky. In particular, it contends that the government diverted work within
    the scope of the contracts to other contractors, thus breaching the contracts and entitling
    Certified to an award of lost profits. The government has moved for summary judgment
    on the claims.
    For the reasons discussed below, the Court concludes that—contrary to the
    government’s arguments—the contracts at issue in this case were, in fact, enforceable
    requirements contracts because each granted Certified an exclusive right to perform the
    work falling within its scope. Further, based on the plain language of the contracts, the
    Court has determined that the work to be performed under the contracts included concrete
    pavement work, but did not extend to structural concrete work. However, because the
    government has not demonstrated the absence of any genuine issue of material fact with
    respect to whether any particular projects that may have been performed by other
    contractors fell within this category, it is not entitled to summary judgment as to
    Certified’s claims. Accordingly, the government’s motion is DENIED.
    BACKGROUND1
    Certified is a long-time contractor for the U.S. Department of the Army (Army).
    See Pl.’s Resp. to Mot. for Summ. J. (Pl.’s Resp.) at 2–3, ECF No. 25. From 1998 until
    2010, it held several contracts to perform concrete placement, asphalt surface treatment,
    and pavement marking projects at the Army’s base at Ft. Knox, Kentucky. Id.; see also
    Pl.’s Resp. App. at PA 0012 (affidavit of Allan W. Buckles, Certified’s president). This
    action concerns three contracts awarded to Certified covering the years from 2006
    through 2010. Compl. ¶¶ 5–8; Pl.’s Resp. at 3–6.
    I.        The 2006 Contract
    On October 26, 2005, the Army awarded Certified a “requirements-type contract
    for concrete placement, asphalt surface treatments and pavement markings” at Ft. Knox.
    Def.’s Mot. for Summ. J. (Def.’s Mot.) App. at A127–28. The contract’s initial term was
    to run until October 31, 2006. 
    Id. at A127.
    The contract’s “Scope” section described the contractor’s work as follows:
    The contractor shall furnish all labor, materials, equipment,
    transportation, traffic control and supervision for construction and
    repair of asphalt pavement work (to include new asphalt pavement,
    asphalt overlays, asphalt surface treatments, etc.) and concrete
    pavement work (to include concrete services for roads, airfields,
    test sites, walks, retaining walls, parking lots, appurtenances, etc.)
    in family housing and post areas at Fort Knox, Kentucky. Also
    included is the placement of traffic control markings on or along
    existing and new pavements.
    
    Id. at A177.
    The same section of the contract also noted that “[t]he contract will be a
    requirements-type contract to be ordered on individual delivery orders”; and that, with
    respect to concrete work, the services ordered might “include but not be limited to” the
    following:
    1
    Unless otherwise specified, the facts set forth in this section are undisputed.
    2
    Throughout this Opinion, citations to the evidence submitted by the parties will refer to
    the Bates-stamped page numbers found in the parties’ respective appendices—e.g., “Pl.’s
    Resp. App. at PA 001” for the first page of Certified’s appendix and “Def.’s Mot. App. at
    A1” for the first page of the government’s appendix.
    2
    
    Id. Several other
    provisions further delineated the contract’s scope. Thus, in a clause
    in the contract’s “Important Notes” section, the government “reserve[d] the right to
    perform the work included in this contract with in-house personnel, Job Order
    contracting,3 troop labor, or by another contract where concrete placement, asphalt
    surface treatment, or pavement marking is incidental to other work.” 
    Id. at A172–73.
    The contract also incorporated two provisions taken from the FAR. 
    Id. at A174.
    The first, titled “Order Limitations,” noted that the contractor was “not obligated to
    honor” any order of less than $2,000 for a single item; any order of more than $200,000
    for any single item; or any order of more than $400,000 for a combination of items. 
    Id. In addition,
    the provision stated that “[i]f this is a requirements contract . . . the Government
    is not required to order a part of any one requirement from the Contractor if that
    requirement exceeds the maximum-order limitations [set forth] above.” 
    Id. The second,
    titled “Requirements. (OCT 1995) -- Alternate I (APR 1984),” stated
    that “[t]his is a requirements contract” and that “[t]he estimated quantities are not the
    total requirements of the Government . . . but are estimates of requirements in excess of
    the quantities that the [government] may itself furnish within its own capabilities.” 
    Id. Thus, it
    continued, “[e]xcept as this contract otherwise provides, the Government shall
    order from the Contractor all of [its] requirements for supplies and services specified in
    the [contract] that exceed the quantities that the [government] may itself furnish within its
    own capabilities.” 
    Id. Further, the
    provision stated that “[t]he Government is not required
    to purchase from the Contractor requirements in excess of any limit on total orders under
    this contract.” 
    Id. II. The
    2008 Contract
    After exercising options extending the 2006 contract through April 30, 2008, see
    Compl. ¶¶ 5–6, the Army entered into another one-year contract with Certified on May
    15, 2008. Def.’s Mot. App. at A187–88. The 2008 contract was identical to the 2006
    3
    According to the government, “Job Order Contracting (JOC) involves cont[r]acts for the
    small scale, non-programmed military construction projects that are a regular feature of
    garrison maintenance and upgrades,” and “[t]he scope of the JOC includes paving
    activities associated with construction projects.” Def.’s Mot. at 6 n.3.
    3
    contract in many material respects, but included some changes. Thus, in addition to
    “concrete placement, asphalt surface treatments, [and] pavement markings,” the 2008
    contract also covered “site preparation” work. 
    Id. at A187.
    The contract’s “Scope”
    section was also modified somewhat. 
    Id. at A290.
    Specifically, the “Scope” section now
    provided that:
    The contractor shall furnish all labor, materials, equipment,
    transportation, traffic control and supervision for construction and
    repair of asphalt pavement work (to include new asphalt pavement,
    asphalt overlays, asphalt surface treatments, etc.), concrete
    pavement work (to include concrete placement for roads, airfields,
    test sites, walks, retaining walls, parking lots, appurtenances, etc.)
    and site work associated with the placement of concrete and
    asphalt or stand alone site work (to include excavation, placing fill,
    finish grading, turf re-establishment, etc.) for completion of a total
    project in post areas at Fort Knox, Kentucky. Also included is the
    placement of traffic control markings on or along existing and new
    pavements and incidentals as listed below.
    
    Id. (emphasis added
    to changes made from the 2006 contract).
    As with the 2006 contract, the 2008 contract included an “Important Notes”
    section with a clause stating that the government “reserve[d] the right to perform the
    work included in this contract with in-house personnel, Job Order contracting, troop
    labor, or by another contract where concrete placement, asphalt surface treatment, or
    pavement marking is incidental to other work.” 
    Id. at A285.
    Unlike the 2006 contract,
    though, the 2008 contract defined the term “incidental” to mean “work in, on, and up to a
    perimeter of 5 feet around the structure, or to complete an item of work if its origin is
    within the 5 foot perimeter.” 
    Id. Finally, like
    the 2006 contract, the 2008 contract included the “Order Limitations”
    and “Requirements (OCT 1995) -- Alternate I (APR 1984)” provisions taken from the
    FAR. 
    Id. at A286–87.
    III.   The 2009 Contract
    After the 2008 contract expired, the Army entered another one-year contract with
    Certified on May 29, 2009. 
    Id. at A295–96.
    The 2009 contract remained similar to the
    2008 contract in some respects, but also included substantial changes. First, the general
    description of the 2009 contract included several references to “pavement” that did not
    appear in the equivalent description in the 2008 contract. 
    Id. at A295.
    Specifically, the
    contract description stated that the 2009 contract was a “requirements-type contract for
    construction/repair of asphalt pavement, concrete pavement, pavement markings, and site
    preparation at Fort Knox, KY.” Id.; see also 
    id. at A187
    (describing the 2008 contract as a
    “requirements-type contract for concrete placement, asphalt surface treatments, pavement
    markings, and site preparation at Ft. Knox, KY”).
    4
    The 2009 contract’s “Scope” clause also expanded the scope of the contractor’s
    work, which now included furnishing:
    all labor, materials, equipment, transportation, traffic control,
    engineering, layout, and supervision for construction and repair of
    asphalt pavement work (to include preparing subgrade to receive
    compacted crushed stone base, new asphalt pavement, asphalt
    overlays, asphalt surface treatments, etc.), concrete pavement
    work (to include preparing subgrade to receive compacted crushed
    stone base, concrete placement for roads, airfields, test sites,
    walks, retaining walls, parking lots, appurtenances, etc.) and site
    work associated with the placement of concrete and asphalt or
    stand alone site work (to include clear & grubbing, excavation,
    placing compacted fill, finish grading, turf reestablishment, etc.)
    for completion of a total project in post areas at Fort Knox,
    Kentucky.
    
    Id. at A322
    (emphasis added to changes from the 2008 contract).
    The 2009 contract also omitted the “Important Notes” section found in the other
    two contracts. Thus, the 2009 contract did not include a clause reserving to the
    government the right to have work falling within the scope of the contract performed in-
    house, with job order contracting, with troop labor, or by another contract where the work
    was incidental to other projects. See 
    id. at A320–23;
    Def.’s Mot. at 9.
    Finally, while the 2009 contract incorporated the same “Order Limitations”
    provision derived from the FAR as the 2006 and 2008 contracts, it included a different
    version of the “Requirements” provision. Thus, the version found in the 2009 contract
    was titled “Requirements (OCT 1995)” rather than “Requirements (OCT 1995) --
    Alternate I (APR 1984).” See Def.’s Mot. App. at A320–21. In the version found in the
    2009 contract, paragraph (c) of the provision differed in several ways from the equivalent
    paragraph in the version found in the 2006 and 2008 contracts. First, in the 2006 and
    2008 contracts, but not the 2009 contract, paragraph (c) began with the following
    sentence: “The estimated quantities are not the total requirements of the
    Government . . . but are estimates of requirements in excess of the quantities that the
    [government] may itself furnish within its own capabilities.” See 
    id. at A174,
    A286–87,
    A320.
    Further, in the 2009 contract, paragraph (c) stated only that “[e]xcept as this
    contract otherwise provides, the Government shall order from the Contractor all the
    supplies or services specified in the Schedule that are required to be purchased by the
    Government.” 
    Id. at 320.
    In the 2006 and 2008 contracts, by contrast, paragraph (c) also
    provided that: “[e]xcept as this contract otherwise provides, the Government shall order
    from the Contractor all of [its] requirements for supplies and services specified in the
    Schedule that exceed the quantities that the [government] may itself furnish.” See 
    id. at A174,
    A287 (emphasis added).
    5
    IV.    Certified’s Claims to the CO
    On September 17, 2012, Certified submitted a claim to the CO for damages under
    the 2006 contract. See 
    id. at A325–26.
    Certified alleged that the government had
    “diverted substantial portions of work falling within the Work Scope to [other]
    contractors,” and that the diverted work “was not incidental to the other work being
    performed by those contractors and, therefore, did not fall into the exclusion for which
    the Government provided in the Contract.” 
    Id. at A326.
    Certified estimated that “its lost
    profits from said work would have exceeded approximately $4,000,000.” 
    Id. In a
    subsequent letter, Certified reduced its estimated lost profits to $2,989,818.13. See 
    id. at A328–29.
    On May 14, 2014, Certified submitted another claim to the CO, this time seeking
    damages under the 2008 contract. See 
    id. at A333–34.
    As with its first claim, Certified
    asserted that the government had diverted work falling within the scope of the 2008
    contract to other contractors, and that the diverted work was not incidental to other work
    performed by those contractors. 
    Id. at A334.
    Certified maintained that although it had
    tried to “determine the exact scope of work diverted from its Contract” by requesting
    copies of the government’s other delivery orders via the Freedom of Information Act, it
    had been unsuccessful. 
    Id. In the
    absence of this information, it estimated its lost profits
    under the 2008 contract at $5,811,371.90. 
    Id. On December
    5, 2014, Certified submitted a third claim to the CO, now seeking
    damages under the 2009 contract. See 
    id. at A340–41.
    Certified again contended that the
    government had diverted work falling within the scope of its contract to other contractors.
    
    Id. at A340.
    It estimated that its lost profits under the 2009 contract totaled
    $3,645,409.67. 
    Id. at A341.
    The CO issued a final decision denying Certified’s first claim on June 29, 2015.
    See Compl. Ex. D. The CO agreed that the 2006 contract was a “requirements type
    contract” but determined that the work performed by the other contractors “d[id] not fall
    within the scope of your contract.” 
    Id. at 1–3.
    According to the CO, it was “clear” that
    Certified’s contract “[was] for paving and paving associated activities.” 
    Id. at 3.
    Further,
    “[i]n specific relation to concrete, the scope include[d] those activities based on
    horizontal placement of concrete for roads[,] parking lots[,] and walkways[,] and any
    structural concrete work incidental to these paving activities,” such as installing “drains,
    culverts, retaining walls and porches and steps and patios.” 
    Id. By contrast,
    the CO determined that the work performed by the other contractors
    consisted of “concrete placement of standalone concrete structures or incidental concrete
    placement included in larger vertical construction projects associate[d] with buildings or
    other non-paving projects.” 
    Id. Thus, the
    “projects identified in [Certified’s] claim f[e]ll
    outside any obligation of the government to utilize [its] contract for placement of
    associated concrete work.” 
    Id. The CO
    apparently never issued a decision on Certified’s
    claims under the 2008 and 2009 contracts. See Pl.’s Resp. at 8.
    6
    V.     This Action
    Certified filed its complaint in this Court on September 21, 2015. ECF No. 1. It
    alleged that the 2006, 2008, and 2009 contracts were requirements contracts for concrete
    placement, asphalt surface treatments, and pavement markings, and that the government
    breached the contracts by diverting work within the scope of the contracts to other
    contractors. 
    Id. ¶¶ 13–14,
    26, 28–29, 35, 37–38, 46. As a result, Certified claimed that it
    was entitled to an award of lost profits. 
    Id. ¶¶ 26,
    35, 46.
    The government answered the complaint on December 21, 2015, ECF No. 8, and
    indicated to the Court during a status conference that it intended to file a motion for
    summary judgment, see Order at 1–2, ECF No. 13. After the government filed its motion
    for summary judgment, Certified informed the Court that it would require some
    discovery to effectively respond to the government’s motion. See Pl.’s Notice Pursuant to
    Order of March 11, 2016 at 1–2, ECF No. 20. The Court then extended the deadline for
    Certified’s response to the government’s motion several times. See ECF Nos. 22, 24.
    On July 5, 2016, Certified filed its response to the government’s motion. ECF No.
    25. In it, Certified noted that although the government had not yet produced all the
    documents it had requested, it believed enough evidence existed to demonstrate the
    existence of genuine issues of material fact and thus preclude summary judgment. See
    Pl.’s Resp. to Mot. for Summ. J. (Pl.’s Resp.) at 9. The government filed a reply in
    support of its motion on July 29, 2016, ECF No. 30, and the Court heard oral argument
    on the motion on October 26, 2016.
    DISCUSSION
    I.     Jurisdiction
    Pursuant to the Tucker Act, the United States Court of Federal Claims may
    “render judgment upon any claim against the United States founded either upon the
    Constitution, or any Act of Congress or any regulation of an executive department, or
    upon any express or implied contract with the United States, or for liquidated or
    unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a) (2012).
    Subsection (a)(2) of section 1491 further grants the Court of Federal Claims “jurisdiction
    to render judgment upon any claim by or against, or dispute with, a contractor arising
    under section 7104(b)(1) of title 41”—that is, the Contract Disputes Act (CDA), 41
    U.S.C. §§ 7101–09—“including a dispute concerning termination of a contract, rights in
    tangible or intangible property, compliance with cost accounting standards, and other
    nonmonetary disputes on which a decision of the contracting officer has been issued
    under section 6 of that Act.” 28 U.S.C. § 1491(a)(2).
    The CDA sets forth its own jurisdictional requirements. See M. Maropakis
    Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327–28 (Fed. Cir. 2010). In particular,
    it states that a contractor may bring an action de novo in federal court “within 12 months
    from the date of receipt of a contracting officer’s decision.” 41 U.S.C. § 7104(b)(3).
    Thus, the Federal Circuit has held that for the Court of Federal Claims to possess
    7
    jurisdiction, the contractor must have first submitted a valid claim to the contracting
    officer and received the contracting officer’s final decision on that claim. M. Maropakis
    
    Carpentry, 609 F.3d at 1327
    –28; see also Dalton v. Sherwood Van Lines, Inc., 
    50 F.3d 1014
    , 1017 (Fed. Cir. 1995) (“When the [CDA] applies, it provides the exclusive
    mechanism for dispute resolution; [it] was not designed to serve as an alternative
    administrative remedy, available at the contractor’s option.”). Further, “[f]ailure by a
    contracting officer to issue a decision on a claim . . . is deemed to be a decision by the
    contracting officer denying the claim.” 41 U.S.C. § 7103(f)(5).
    Here, the government does not contest that Certified submitted valid claims to the
    CO regarding its allegations of breach under the 2006, 2008, and 2009 contracts, and that
    the CO either denied the claims or failed to respond to them. Accordingly, the Court has
    jurisdiction over this action under 28 U.S.C. § 1491(a)(2).
    II.    Standard for Summary Judgment
    The standards for granting summary judgment are well established. Summary
    judgment may be granted where there is no genuine issue of material fact and the movant
    is entitled to judgment as a matter of law. Rules of the Court of Federal Claims (RCFC)
    56(a); Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 250 (1986). A fact is material if it
    “might affect the outcome of the suit under the governing law.” 
    Anderson, 477 U.S. at 248
    . An issue is genuine if it “may reasonably be resolved in favor of either party.” 
    Id. at 250.
    The moving party bears the burden of establishing the absence of any genuine
    issue of material fact, and all significant doubts regarding factual issues must be resolved
    in favor of the party opposing summary judgment. Mingus Constructors, Inc. v. United
    States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). “Once the moving party has satisfied its
    initial burden, the opposing party must establish a genuine issue of material fact and
    cannot rest on mere allegations, but must present actual evidence.” Crown Operations
    Int'l, Ltd. v. Solutia Inc., 
    289 F.3d 1367
    , 1375 (Fed. Cir. 2002), citing 
    Anderson, 477 U.S. at 248
    . The court should act with caution in granting summary judgment and may
    deny summary judgment “where there is reason to believe that the better course would be
    to proceed to a full trial.” 
    Anderson, 477 U.S. at 255
    .
    III.   Standards for Contract Interpretation
    The interpretation of a contract begins with its language. Bell/Heery v. United
    States, 
    739 F.3d 1324
    , 1331 (Fed. Cir. 2014). “When interpreting the contract, the
    document must be considered as a whole and interpreted so as to harmonize and give
    reasonable meaning to all of its parts.” NVT Techs., Inc. v. United States, 
    370 F.3d 1153
    ,
    1159 (Fed. Cir. 2004). If the contract’s “provisions are ‘clear and unambiguous, they
    must be given their plain and ordinary meaning.’” Coast Fed. Bank, FSB v. United
    States, 
    323 F.3d 1035
    , 1040 (Fed. Cir. 2003) (quoting Landmark Land Co. v. Fed.
    Deposit Ins. Corp., 
    256 F.3d 1365
    , 1373 (Fed. Cir. 2001)); see also Sea-Land Serv., Inc.
    v. United States, 
    553 F.2d 651
    , 658 (Ct. Cl. 1977). Therefore, “the court may not look to
    8
    extrinsic evidence to interpret [unambiguous] provisions.” TEG-Paradigm Envtl., Inc. v.
    United States, 
    465 F.3d 1329
    , 1338 (Fed. Cir. 2006).
    If, on the other hand, the contract’s language “can reasonably be interpreted in
    more than one way,” LAI Servs. v. Gates, 
    573 F.3d 1306
    , 1314 (Fed. Cir. 2009), the
    court “may appropriately look to extrinsic evidence to aid in [its] interpretation of the
    contract.” Gardiner, Kamya & Assocs., P.C. v. Jackson, 
    467 F.3d 1348
    , 1354 (Fed. Cir.
    2006) (quoting Metro. Area Transit, Inc. v. Nicholson, 
    463 F.3d 1256
    , 1260 (Fed. Cir.
    2006)). Such extrinsic evidence may include the contemporaneous circumstances,
    evidence of the parties’ intent, and/or their course of performance. See Pub. Serv. Co. of
    Okla. v. United States, 
    88 Fed. Cl. 250
    , 258 (2009).
    IV.    Whether the 2006 and 2008 Contracts Are Enforceable Requirements
    Contracts
    A.      Principles of Contract Interpretation With Respect to Requirements
    Contracts
    As the Federal Circuit has observed, federal supply contracts ordinarily fall into
    one of three categories: “those for a definite quantity, those for an indefinite quantity[,]
    and those for requirements.” Ace-Fed. Reporters, Inc. v. Barram, 
    226 F.3d 1329
    , 1331
    (Fed. Cir. 2000) (quoting Torncello v. United States, 
    681 F.2d 756
    , 761–62 (Ct. Cl.
    1982)). The key characteristic of an enforceable requirements contract is the
    government’s agreement “to fill all its actual requirements for specified supplies or
    services during the contract period by purchasing from the awardee, who agrees to
    provide them at the agreed price.” Rumsfeld v. Applied Cos., Inc., 
    325 F.3d 1328
    , 1334
    (Fed. Cir. 2003) (quoting Medart, Inc. v. Austin, 
    967 F.2d 579
    , 581 (Fed. Cir. 1992)); see
    also Maint. Eng’rs v. United States, 
    749 F.2d 724
    , 725–26 (Fed. Cir. 1984). Thus, the
    touchstone right conferred on the contractor by a requirements contract is exclusivity. See
    Modern Sys. Tech. Corp. v. United States, 
    979 F.2d 200
    , 205 (Fed. Cir. 1992); Mason v.
    United States, 
    615 F.2d 1343
    , 1348 (Ct. Cl. 1980).
    Because a contractor holding a requirements contract has a right of exclusive
    access to some portion of the government’s business, the government may breach the
    contract if it diverts work falling within the contract’s scope to another contractor. See
    Ace-Fed. 
    Reporters, 226 F.3d at 1332
    –33; 
    Mason, 615 F.2d at 1347
    . The contractor may
    then seek damages in the form of lost profits—a remedy that is not available to a
    contractor with an indefinite quantity contract. See Ace-Fed. 
    Reporters, 226 F.3d at 1332
    –33.
    Finally, when determining whether a particular contract constitutes an enforceable
    requirements contract, the court “should not be blinded by how one labels [the] contract.”
    
    Id. at 1331
    (citing Maint. Eng’rs v. United 
    States, 749 F.2d at 726
    n.3). Instead, the court
    should examine the contract to “determin[e] the respective rights conferred by [its]
    terms” on the parties. 
    Mason, 615 F.2d at 1347
    .
    9
    B.      Application of Principles
    In this case, the government has conceded that the 2009 contract was a valid
    requirements contract. See Def.’s Reply at 9–10; Oral Argument at 1:46–2:04. It argues,
    however, that the 2006 and 2008 contracts were not enforceable requirements contracts
    because they did not obligate the government to turn exclusively to Certified to fulfill its
    needs for work falling within the contracts’ respective scopes. See Def.’s Mot. at 14–15;
    Def.’s Reply at 2–3. The government’s argument centers on the clause in the contracts’
    “Important Notes” sections in which the government reserved the right to “perform the
    work included in this contract with in-house personnel, Job Order contracting, troop
    labor, or by another contract where concrete placement, asphalt surface treatment, or
    pavement marking is incidental to other work.” Def.’s Mot. at 15–16; see also Def.’s
    Mot. App. at A173 (2006 contract); 
    id. at A285
    (2008 contract).
    The government contends that under a plain reading of the clause, the final
    modifying phrase—“where concrete placement, asphalt surface treatment, or pavement
    marking is incidental to other work”—applies only to the term “by another contract,”
    which immediately precedes that phrase. Def.’s Mot. at 15–16. In its view, had the parties
    intended that the phrase modify the full list of possible labor sources—i.e., “in-house
    personnel, Job Order contracting, troop labor, or by another contract”—they would have
    placed the modifying phrase at the beginning of the clause, or offset the list of labor
    sources from the modifying phrase by placing a comma between the words “contract”
    and “where.” Oral Argument at 5:35–58, 6:56–7:29. Therefore, the government argues,
    the Army was free to turn to in-house personnel, job order contracting, or troop labor to
    supply all of its needs for work within the scope of the contract.
    On the other hand, Certified urges the Court to read the modifying phrase as
    applying to every labor source listed in the clause. See Pl.’s Resp. at 13–14. Thus, under
    Certified’s reading, it retained the exclusive right to perform all “concrete placement,
    asphalt surface treatment, or pavement marking” that was not “incidental to other work.”
    Neither interpretation is foreclosed by the clause’s language, viewed in isolation.
    As noted above, however, the Court’s interpretive task is not fulfilled by parsing the
    meaning of the clause in isolation; rather, it must consider the contract “as a whole” and
    interpret it “so as to harmonize and give reasonable meaning to all of its parts.” See NVT
    Techs., 
    Inc., 370 F.3d at 1159
    . Taking the contract as a whole into consideration, the
    Court finds Certified’s reading more persuasive.
    Thus, it is obvious to the Court that the parties intended to form an enforceable
    requirements contract: the contract describes itself as a “requirements-type” contract; it
    includes FAR provisions meant for inclusion only in a requirements contract; and the CO
    himself believed that the 2006 contract was a requirements contract. Under the
    government’s reading, though, a single clause in the contract renders the parties’
    agreement illusory. The government’s interpretation therefore does not “harmonize and
    give reasonable meaning” to all the provisions of the contract. To the contrary, it negates
    the multiple representations in the contracts that they were requirements contracts.
    Accordingly, the Court will interpret the modifying phrase “where concrete placement,
    10
    asphalt surface treatment, or pavement marking is incidental to other work” as applying
    to all four sources of labor listed in the clause.
    So interpreted, the clause does not vitiate Certified’s exclusive right to work
    under the contracts, but simply sets a boundary on the scope of the concrete placement,
    asphalt surface treatment, or pavement marking work that must go to Certified. That is, it
    carves out an exception that applies where such work is incidental to other work. Even
    with this carve-out in place, the contract meaningfully constrained the government’s
    discretion to obtain pavement work from sources other than Certified because the
    government had to turn to Certified for any project for which asphalt or concrete
    pavement work was not incidental to another project, and which did not exceed the
    maximum order limitations in the contracts.
    Accordingly, the Court concludes that the clause included in the 2006 and 2008
    contracts’ “Important Notes” sections did not render the contracts unenforceable or
    negate the parties’ clear intent to enter requirements contracts. Thus, that clause does not
    provide a basis for granting summary judgment in the government’s favor with respect to
    those two contracts.4
    4
    The Court notes that both the 2006 and 2008 contracts include the FAR’s
    “Requirements (OCT 1995) -- Alternate I (APR 1984)” provision, which states that the
    government “shall order from the Contractor all of that activity’s requirements for
    supplies and services specified in the Schedule that exceed the quantities that the activity
    may itself furnish within its own capabilities.” In Horn v. United States, 
    98 Fed. Cl. 500
    ,
    504–05 (2011), and Ralph Constr., Inc. v. United States, 
    4 Cl. Ct. 727
    , 731 (1984) the
    courts held that contracts that include this provision do not confer an exclusive right on
    the contractor to perform all the government’s requirements, and are therefore not
    requirements contracts, because the clause specifies that the government would order
    only those services that exceeded the quantities that the government might “itself furnish
    within its own capabilities.” 
    Horn, 98 Fed. Cl. at 504
    ; Ralph 
    Constr., 4 Cl. Ct. at 732
    .
    It is unclear to what extent the government is relying upon the FAR provision for its
    arguments here. See Oral Argument at 4:33–55 (counsel for the government stating that
    “I don’t think the Court needs to reach t[he] issue” raised in Horn and Ralph Constr.
    because the “Important Notes” provision in this case went beyond the reservation found
    in the FAR provision). But in any event, in this Court’s view, the reasoning in Horn and
    Ralph Constr. is unpersuasive. The right conferred by a requirements contract is the right
    to exclude entities other than the contractor from obtaining some defined portion of the
    government’s business. See Ace-Fed. 
    Reporters, 226 F.3d at 1332
    –33; see also 
    Mason, 615 F.2d at 1347
    –48. Inclusion of the FAR provision (which after all only appears in
    contracts that are ostensibly requirements contracts) has the effect of defining the portion
    of the government’s business to which a contractor has the exclusive right—i.e., all
    services within the contract’s scope that the government cannot furnish with its own
    capabilities. In other words, where a contract “b[inds] the government to order from the
    11
    V.     The Scope of the Requirement
    The work descriptions found in the contracts make clear that they covered paving
    projects, along with subsidiary tasks necessary to complete such paving projects (as well
    as stand-alone site work). First, the contracts’ general descriptions all relate to paving or
    other surface work. Thus, the general description of the 2006 contract stated that it was a
    “requirements-type contract for concrete placement, asphalt surface treatments and
    pavement markings.” Def.’s Mot. App. at A127. The equivalent provision in the 2008
    contract stated that it was a “requirements-type contract for concrete placement, asphalt
    surface treatments, pavement markings, and site preparation.” 
    Id. at A187.
    And the
    description in the 2009 contract stated that it was a “requirements-type contract for
    construction/repair of asphalt pavement, concrete pavement, pavement markings, and site
    preparation.” 
    Id. at A295.
    Further, each contract’s “Scope” section provided additional detail about the types
    of paving projects that Certified could expect. With respect to concrete work, these
    descriptions varied slightly from contract to contract, using different combinations of the
    terms “concrete pavement,” “concrete placement,” and “concrete services.” Thus, the
    2006 contract’s Scope section described the work as including “concrete pavement work
    (to include concrete services for roads, airfields, test sites, walks, retaining walls, parking
    lots, appurtenances, etc.).” 
    Id. at A177.
    The 2008 contract’s Scope section stated that the
    work would include “concrete pavement work (to include concrete placement for roads,
    airfields, test sites, walks, retaining walls, parking lots, appurtenances, etc.). 
    Id. at A290.
    And the 2009 contract’s Scope section described the concrete work as “concrete
    pavement work (to include preparing subgrade to receive compacted crushed stone base,
    [and] concrete placement for roads, airfields, test sites, walks, retaining walls, parking
    lots, appurtenances, etc.). 
    Id. at A322
    .
    In addition, each contract’s Scope section also set forth an identical list of
    representative, paving-type tasks, as follows:
    
    Id. at A177,
    A290, A322. Further, the contract line items (CLINs) incorporated in each
    contract all related to paving and pavement-related work. See, e.g., 
    id. at A131
    (CLIN
    contractor if it order[s] at all,” the contract is a valid requirements contract. See John
    Cibinic, Jr. et al., Formation of Government Contracts 1348 (4th ed. 2011).
    12
    calling for contractor to “[c]lean and seal joints in concrete pavement in accordance
    with . . . the Specifications); 
    id. at A190
    (CLIN calling for contractor to place “[c]oncrete
    entrance pavement conforming to Standard); 
    id. at A298
    (CLIN calling for contractor to
    place “[c]oncrete curb & gutter conforming to standard [d]rawing . . . and in accordance
    with . . . the specifications). Finally, each contract incorporated by reference the
    “Standard Specification for Road and Bridge Construction” published by the Kentucky
    Department of Highways. 
    Id. at A180,
    A291, A323.
    Certified’s textual argument for a broader construction of the contract’s scope that
    includes structural work is unpersuasive. Despite the contracts’ identification of their
    scope as including concrete “placement” and/or “pavement” work, Certified argues that
    they also encompassed projects that were primarily structural in nature, such as the
    construction of concrete walls, building pads, and loading docks. See Pl. Resp. at 15–16;
    see also Pl.’s Resp. App. at PA1979–2297 (examples of orders placed under Certified’s
    contracts). But the use of the words “placement” and “pavement” as opposed to
    “construction,” along with the examples of tasks set forth above, the CLINs, and the fact
    that the contract incorporates specifications for road and bridge but not building
    construction, all indicate a scope that is much narrower than the one urged by Certified..
    Indeed, given the estimated cost of the contracts—ranging from $1,350,000 per contract
    year to approximately $9,000,000 per contract year—Certified’s argument that it was
    given a requirements contract for all structural concrete projects at Fort Knox is
    implausible.
    Certified also points to the “may include but not be limited to” proviso found in
    the “Scope” sections, contending that the contracts’ lists of representative tasks were
    “non-exhaustive” and thus that the contracts did not specifically exclude “structural and
    non-pavement work.” Pl.’s Resp. at 16. In the context of the Scope sections as a whole,
    however, the proviso is best read as providing a non-exhaustive list of tasks that fall
    under the rubric of either construction and repair of asphalt pavement or concrete
    pavement as opposed to tasks undertaken for different purposes.
    Finally, Certified argues that the government “frequently order[ed] Certified to
    perform work of a structural nature” under its previous contracts, which it claims had the
    same scope as the contracts at issue. Pl.’s Mot. at 16. But it would be improper for the
    Court to consider such extrinsic evidence in interpreting the scope of the contract, given
    that the contract’s plain language clearly concerns only non-structural types of concrete
    work. See United States v. Ford Motor Co., 
    463 F.3d 1267
    , 1278–79 (Fed. Cir. 2006)
    (“Course of performance evidence in most circumstances is relevant to interpretation of
    an instrument only if the terms of that instrument are ambiguous.”); Barron Bancshares,
    Inc. v. United States, 
    366 F.3d 1360
    , 1375 (Fed. Cir. 2004) (same); McAbee Constr. Inc.
    v. United States, 
    97 F.3d 1431
    , 1435 (Fed. Cir. 1996) (court “may not resort to extrinsic
    evidence to interpret” contract if its terms are unambiguous).
    In short, the plain language of the contracts shows that each contract’s scope was
    limited to paving and related surface projects (with the understanding that the 2006 and
    2008 contracts included an additional carve-out for paving projects that were incidental to
    other work performed with in-house personnel, job order contracting, troop labor, or by
    13
    another contract). Stand-alone structural concrete projects were not within the scope of
    the contracts. In addition, in light of the maximum order limitations in the contracts, the
    government’s obligation to procure the covered services through Certified is limited to
    orders that did not exceed $200,000 for a single item or $400,000 for a combination of
    items.
    At this point in the case, discovery has not been completed and the record before
    the Court is unclear as to which of the projects Certified claims were improperly diverted
    fell within the scope of the contracts, as set forth above, and which did not. Because the
    government has not established the absence of any genuine dispute of material fact with
    respect to this issue, it is not entitled to summary judgment.
    CONCLUSION
    For the reasons discussed above, the government’s motion for summary judgment
    is DENIED.
    IT IS SO ORDERED.
    /s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge
    14