Dyncorp International LLC v. United States ( 2018 )


Menu:
  •                  United States Court of Federal Claims
    No. 18-557 C
    Filed: August 9, 2018
    Reissued: September 6, 20181
    )
    DYNCORP INTERNATIONAL LLC,                )
    )
    Plaintiff,                )
    )
    v.                                        )
    )
    THE UNITED STATES,                        )
    )
    Defendant                  )
    )
    and                                 )
    )
    JPATS LOGISTICS SERVICES,                 )
    )
    Defendant-Intervenor.      )
    )
    )
    David M. Nadler, Blank Rome LLP, Washington, DC, for plaintiff.
    Eric J. Singley, U.S. Department of Justice, Civil Division, Washington, DC, for defendant.
    J. Alex Ward, Morrison & Foerster, LLP, Washington, DC, for defendant-intervenor.
    OPINION AND ORDER
    SMITH, Senior Judge
    This post-award bid protest comes before the Court on the parties’ Cross-Motions for
    Judgment on the Administrative Record. Plaintiff, DynCorp International, LLC (“DynCorp”),
    filed its Complaint on April 17, 2018, objecting to the United States Air Force’s (“Air Force” or
    “Agency”) award of the $2.2 billion Solicitation No. FA8617-18-R-6213 (“Solicitation” or
    “RFP”) for the Contractor Operated and Maintained Base Supply (“COMBS”) III contract to
    defendant-intervenor, JPATS Logistics Services, LLC (“JLS”). Administrative Record
    (hereinafter “AR”) at 1. Plaintiff seeks an order (1) awarding equitable relief in the form of an
    injunction against the COMBS III award to JL, and (2) requiring the Air Force to award the
    1
    An unredacted version of this opinion was issued under seal on August 9, 2018. The parties
    were given an opportunity to propose redactions, and those redactions are reflected herein.
    COMBS III contract to plaintiff, or, in the alternative, obligating the Agency to re-evaluate the
    offers and make a new source selection decision. Complaint (hereinafter “Compl.”) at 1-2. For
    the following reasons, plaintiff’s Motion for Judgment on the Administrative Record is denied,
    and defendant and defendant-intervenor’s Cross-Motions for Judgment on the Administrative
    Record are granted.
    I.      Background
    On December 9, 2016, the Air Force issued the Solicitation for the COMBS III
    procurement, a follow-on to the COMBS II contract and its successor, the COMBS Bridge
    contract. AR 1. Plaintiff is the incumbent for both the COMBS II and the COMBS Bridge
    contracts. AR 8866. Plaintiff notes that, as a successor contract, the COMBS III contract is
    substantially similar to the COMBS II and COMBS Bridge contracts. Compl. at 5. The
    Solicitation calls for an award of a single Indefinite Delivery/Indefinite Quantity hybrid contract
    with both Firm Fixed Price and Cost Reimbursable No Fee Contract Line Items. AR at 2450.
    The Solicitation provided that the award would be made according to a best-value
    trade-off analysis, and that determination would be based on an assessment of the following
    three factors: (1) Technical Acceptability, (2) Past Performance, and (3) Price. AR 2491. The
    Agency also declared that a best-value trade-off between past performance and price would be
    made among proposals determined to be technically acceptable, and past performance would be
    significantly more important than price. AR 2491. The Solicitation stated that the Air Force
    would assign offerors a past performance rating of “Substantial Confidence, Satisfactory
    Confidence, Limited Confidence, or No Confidence” based on factors of Relevancy and Quality.
    AR 2495. The Agency also determined whether each offeror was responsible, pursuant to
    Federal Acquisition Regulation (“FAR”) 9.104-1(a). AR 5740, 5759, 5787, 5805. The Agency
    published its responsibility determinations in the Defense Contracting Management Agency’s
    (“DCMA”) Pre-Award Survey (“Survey”) for each offeror. AR 5739-5740, 5759, 5786-5787,
    5804-5805.
    On December 21, 2017, DynCorp received notice that its offer was unsuccessful, and that
    the Air Force had awarded the COMBS III contract to JLS. AR 8622. On January 2, 2018,
    DynCorp filed a protest with the Government Accountability Office (“GAO”). AR 8866. On
    April 12, 2018, the GAO denied DynCorp’s protest. AR 17933. On April 17, 2018, DynCorp
    filed its Complaint. See generally Compl. In its Complaint, plaintiff alleges the following: (1)
    the Air Force improperly awarded the follow-on the COMBS III contract to JLS; (2) JLS’s bid
    price was so low that it could not have included the basic inventory levels required for successful
    performance, and the Air Force ignored serious indicators that JLS lacked the financial resources
    to complete the contract; and (3) JLS’ proposal was technically deficient under the terms of the
    Solicitation. Id. at 2-4.
    On May 25, 2018, DynCorp filed its Motion for Judgement on the Administrative
    Record. See generally Plaintiff DynCorp International LLC’s Motion for Judgment on the
    Administrative Record (hereinafter “P’s MJAR”). On June 15, 2018, the government filed its
    Cross-Motion for Judgment on the Administrative Record, and Response to Plaintiff’s Motion
    for Judgment on the Administrative Record. See generally Defendant’s Cross-Motion for
    -2-
    Judgment on the Administrative Record, and Response to Plaintiff’s Motion for Judgment on the
    Administrative Record (hereinafter “D’s CMJAR”). On June 15, 2018, defendant-intervenor,
    JLS, filed its Response and Cross-Motion for Judgment on the Administrative Record. See
    generally Defendant-Intervenor JPATS Logistics Services, LLC’s Response and Cross-Motion
    for Judgment on the Administrative Record (hereinafter “DI’s CMJAR”).
    On June 26, 2018, DynCorp filed its Response to Defendant and Defendant-Intervenor’s
    Cross-Motions for Judgment on the Administrative Record and Reply in Support of its Motion
    for Judgment on the Administrative Record. See generally Plaintiff DynCorp International
    LLC’s Response to Defendant and Defendant-Intervenor’s Cross-Motions for Judgment on the
    Administrative Record and Reply in Support of its Motion for Judgment on the Administrative
    Record (hereinafter “P’s Reply”). On July 9, 2018 the government filed its Reply to Plaintiff’s
    Response to Defendant’s Cross-Motion for Judgment on the Administrative Record. See
    generally Defendant’s Reply to Plaintiff’s Response to Defendant’s Cross-Motion for Judgment
    on the Administrative (hereinafter “D’s Reply”). On July 9, 2018, JLS filed its Reply in Support
    of Its Cross-Motion for Judgement on the Administrative Record. See generally Defendant-
    Intervenor JPATS Logistics Service, LLC’s Reply in Support of Its Cross-Motion for Judgement
    on the Administrative Record (hereinafter “DI’s Reply”). The Court held oral argument on this
    matter on July 17, 2018. The parties’ motions are fully briefed and ripe for review.
    II.     Standard of Review
    This Court’s jurisdictional grant is found primarily in the Tucker Act, which provides the
    Court of Federal Claims the power “to render any judgment upon any claim against the United
    States founded either upon the Constitution, or any Act of Congress or any regulation of an
    executive department, or upon any express or implied contract with the United States . . . in cases
    not sounding in tort.” 
    28 U.S.C. § 1491
    (a)(1) (2012). Although the Tucker Act expressly
    waives the sovereign immunity of the United States against such claims, the act “does not create
    any substantive right enforceable against the United States for money damages.” United States
    v. Testan, 
    424 U.S. 392
    , 398 (1976). Rather, in order to fall within the scope of the Tucker Act,
    “a plaintiff must identify a separate source of substantive law that creates the right to money
    damages.” Fisher v. United States, 
    402 F.3d 1167
    , 1172 (Fed. Cir. 2005) (en banc in relevant
    part).
    This Court has jurisdiction over bid protest actions pursuant to 
    28 U.S.C. § 1491
    (b). The
    Court evaluates bid protests under the standard of review for an agency action set forth in the
    Administrative Procedure Act (“APA”). Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1351
    (Fed. Cir. 2005) (citing Impresa Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1332 (Fed. Cir. 2001)). An agency procurement action may be set aside only if it is
    “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.” 
    28 U.S.C. § 1491
    (b)(4); 
    5 U.S.C. § 706
    (2)(A) (2012). “The arbitrary and capricious standard
    applicable [in bid protests] is highly deferential.” Advanced Data Concepts v. United States, 
    216 F.3d 1054
    , 1058 (Fed. Cir. 2000). Agencies, and contracting officers in particular, are “‘entitled
    to exercise discretion upon a broad range of issues confronting them’ in the procurement
    process.” Savantage Fin. Servs v. United States, 
    595 F.3d 1282
    , 1286 (Fed. Cir. 2010) (quoting
    Impresa, 
    238 F.3d at 1332
    ).
    -3-
    When reviewing a motion for judgment on the administrative record pursuant to Rule
    52.1 of the Rules of the United States Court of Federal Claims (“RCFC”), the Court assesses
    whether the administrative body, given all the disputed and undisputed facts in the record, acted
    in a manner that complied with the legal standards governing the decision under review.
    Supreme Foodservice GmbH v. United States, 
    109 Fed. Cl. 369
    , 382 (2013) (citing Fort Carson
    Supp. Servs. v. United States, 
    71 Fed. Cl. 571
    , 585 (2006); Greene v. United States, 
    65 Fed. Cl. 375
    , 382 (2005); Arch Chems., Inc. v. United States, 
    64 Fed. Cl. 380
    , 388 (2005)). Under RCFC
    52.1, the parties are limited to the Administrative Record, and the Court makes findings of fact
    as if it were conducting a trial on a paper record. See Bannum, 
    404 F.3d at 1354
    . Looking to the
    Administrative Record, the Court must determine whether a party has met its burden of proof
    based on the evidence in the record. 
    Id. at 1355
    .
    When a protestor claims that the agency’s decision violates a statute, regulation, or
    procedure, the protestor must show that the violation was “clear and prejudicial.” Impresa, 
    238 F.3d at 1333
    . The Court will “interfere with the government procurement process only in
    extremely limited circumstances.” EP Prods., Inc. v. United States, 
    63 Fed. Cl. 220
    , 223 (2005)
    (quoting CACI, Inc.-Fed. v. United States, 
    719 F.2d 1567
    , 1581 (Fed. Cir. 1983)). “If the court
    finds a reasonable basis for the agency’s action, the court should stay its hand even though it
    might, as an original proposition, have reached a different conclusion as to the proper
    administration and application of the procurement regulations.” Honeywell, Inc. v. United
    States, 
    870 F.2d 644
    , 648 (Fed. Cir. 1989) (quoting M. Steinthal & Co. v. Seamans, 
    455 F.2d 1289
    , 1301 (D.C. Cir. 1971)). The Court cannot substitute its judgment for that of the agency,
    even if reasonable minds could reach differing conclusions. Bowman Transp., Inc. v. Ark.-Best
    Freight Sys., Inc., 
    419 U.S. 281
    , 285-86 (1974).
    Standing in bid protests is framed by 
    28 U.S.C. § 1491
    (b)(1), which requires the bid
    protest to be brought by an “interested party.” A protestor is an “interested party” if it is
    “(1) [an] actual or prospective bidder and (2) possess[es] the requisite direct economic interest.”
    Weeks Marine, Inc., v. United States, 
    575 F.3d 1352
    , 1359 (Fed. Cir. 2009) (citing Rex Serv.
    Corp. v. United States, 
    448 F.3d 1305
    , 1308 (Fed. Cir. 2006)). In a post-award protest, a bidder
    has a direct economic interest in a procurement if it can show that “there was a substantial
    chance it would have received the contract award but for the alleged error in the procurement
    process.” Linc Gov’t Servs., LLC. v. United States, 
    96 Fed. Cl. 672
    , 694. (2010) (quoting Info.
    Tech. & Applications Corp. v. United States, 
    316 F.3d 1312
     (Fed. Cir. 2003)). The nature of the
    protest will dictate the necessary factors for a “direct economic interest.” Sys. Appl. & Techs. v.
    United States, 
    691 F.3d 1374
    , 1382 (Fed. Cir. 2012).
    III.    Discussion
    A. Standing
    As previously noted, to have standing in a bid protest, a protester must establish that it
    “(1) is an actual or prospective bidder and (2) possesses the requisite direct economic interest.”
    Weeks Marine, Inc., 575 F.3d at 1359. While no party questions whether plaintiff was a bidder,
    defendant argues that plaintiff lacks the direct economic interest required to establish standing.
    -4-
    D’s CMJAR at 10. Specifically, defendant contends that plaintiff, as the fourth ranked offeror,
    lacked any substantial chance of winning the COMBS III contract, so it fails to qualify as an
    interested party under 
    28 U.S.C. § 1491
    (b)(1). 
    Id. at 10-11
    .
    The Court disagrees. The “allegational prejudice” plaintiff must demonstrate to satisfy
    standing centers on the “impact that the alleged procurement errors had on a plaintiff’s prospect
    for award, taking the allegations as true.” Linc Gov’t Servs., 96 Fed. Cl. at 695. DynCorp
    alleges that, absent the agency’s evaluation errors, the company would have “received the
    highest past performance rating,” and that DynCorp would be in direct contention for the
    COMBS III contract. P’s Reply at 5. That allegation satisfies the substantial chance doctrine.
    See Linc Gov’t Servs., 96 Fed. Cl. at 694. Thus, this Court holds that plaintiff has the requisite
    standing to proceed to a decision on the merits.
    B. Responsibility Determination
    This Court will defer to an agency’s expertise in making procurement decisions, unless
    the agency has “entirely failed to consider an important aspect of the problem, offered an
    explanation for its decision that runs counter to the evidence before the agency, or [issued a
    decision that] is so implausible that it could not be ascribed to a difference in view or the product
    of agency expertise.” Ala. Aircraft Indus., Inc. v. United States, 
    586 F.3d 1372
    , 1375 (Fed. Cir.
    2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983)). In its Motion, plaintiff argues that the Agency unreasonably determined that JLS was a
    responsible offeror when the Contracting Officer (“CO”) “reflexively accepted” JLS’s Survey
    “without meaningful review.” P’s MJAR at 12, 14. As plaintiff highlights, defendant-
    intervenor’s initial offer described JLS as a “[joint venture] formed between” IAP Worldwide
    Services (“IAP”) and Kellstrom Defense Aerospace (“KDA”), with IAP serving “as the
    managing partner.” P’s MJAR at 12; AR 5000. JLS’s Survey, meanwhile, described defendant-
    intervenor as a “majority-owned subsidiary” of IAP. AR 5786.
    Plaintiff avers that this discrepancy in the description of the corporate relationship
    between JLS and IAP Worldwide Services (“IAP”) constituted a “fundamental error” in the
    DCMA’s analysis, and that the CO’s failure to “identify this obvious flaw” was unreasonable.
    P’s MJAR at 12. DynCorp further contends that this semantical difference prevented both the
    DCMA and the CO from “properly consider[ing] the risk” that JLS might lack the “financial
    resources to perform the contract, or the ability to obtain them.” P’s MJAR at 13-14; see also
    FAR 9.104-1(a). Plaintiff offers DCMA’s Postaward Financial Surveillance on IAP Worldwide
    Services, Inc. (“Post Award Report”) as evidence of JLS’s “dire financial condition,” citing
    IAP’s “2014 restructuring [and]                                       .” P’s MJAR at 14; see also
    AR 8421 (referencing IAP’s “debt restructuring” stemming from “financial difficulties”).
    Plaintiff concludes that the Agency’s failure to heed these financial red flags created a
    “fundamental flaw in [JLS’s] financial responsibility evaluation.” P’s MJAR at 17.
    Rather than demonstrating prejudicial error, plaintiff’s efforts serve to highlight the
    reasonableness of the Agency’s actions, particularly given the deference the Court owes to
    agency responsibility determinations. See Impresa, 
    238 F.3d at 1334-35
    ; John C. Grimberg Co.,
    Inc. v. United States, 
    185 F.3d 1297
    , 1303 (Fed. Cir. 1999); Bowman Transp., Inc., 
    419 U.S. 281
    at 285-86. Plaintiff attempts to fault the CO for “reflexively accept[ing]” JLS’s Survey results.
    -5-
    P’s MJAR at 12. However, the courts have long held that a contracting officer determines
    “what, and how much, information” he or she requires to make the responsibility determination.
    John C. Grimberg, 
    185 F.3d at 1303
    . Here, the CO took appropriate steps to determine JLS’s
    responsibility, including its financial health, based on the Source Selection Authority’s
    “extensiv[e]” review of “all available documents pertaining to the acquisition,” including IAP’s
    status as JLS’s guarantor and IAP’s “financial capacity to support” JLS. E.g. AR 5784, 8419-20,
    8618.
    DynCorp further argues that the Agency unreasonably ignored JLS’s financial instability,
    which stemmed from IAP’s debt restructuring. P’s MJAR at 14; see also AR 8421 (referencing
    IAP’s “debt restructuring” and “financial difficulties”). However, the record demonstrates that
    the CO did not ignore JLS’s financial instability, but rather reasonably relied on the relevant
    Survey’s conclusion that JLS and IAP were not financially unstable. AR 5786, 8420. Indeed,
    the DCMA stated in JLS’s Survey that intervenor had or could “obtain adequate financial
    resources . . . necessary for the successful completion” of the COMBS III contract, based in part
    on IAP’s role as a “corporate [g]uarantor.” AR 5783-84, 8420. In its Post Award Report, the
    DCMA took additional steps to review JLS’s ability to execute the COMBS III contract, finding
    that JLS’s financial condition was “satisfactory to support its financial obligations.” AR 8426.
    In evaluating IAP’s potential instability, refinancing does not necessarily impair a
    company’s financial position, but rather, it can improve it. AR 8423. Indeed, the DCMA noted
    an “upward trend in sales, net worth, and cash flow” for IAP after the company’s restructuring.
    
    Id.
     Given the steps that the Agency took to reasonably determine JLS’s responsibility, plaintiff
    fails to demonstrate a “clear and prejudicial error” that would warrant ignoring well-established
    principles of judicial deference. Bowman Transp., Inc., 
    419 U.S. 281
     at 285-86; Impresa, 
    238 F.3d at 1333
    .
    C. Past Performance
    As previously iterated, this Court will defer to an agency’s expertise in making
    procurement decisions unless the agency has “entirely failed to consider an important aspect of
    the problem, offered an explanation for its decision that runs counter to the evidence before the
    agency, or [issued a decision that] is so implausible that it could not be ascribed to a difference in
    view or the product of agency expertise.” Ala. Aircraft Indus., Inc., 
    586 F.3d 1372
     at 1375. The
    Solicitation required the Agency to assign an adjectival rating to each offeror based on the
    “result of the Quality and Relevancy Assessments of the recent contracts evaluated.” AR 2498.
    Here, plaintiff argues that the Agency unreasonably evaluated Past Performance Quality and
    Relevancy subfactors, and that plaintiff was prejudiced by that unfair treatment. P’s MJAR at
    22, 28, 29, 35.
    DynCorp avers that JLS’s past performance was not relevant because the size,
    complexity, and nature of JLS’s assessed contracts were small, simple, and dissimilar to the
    COMBS III contract. P’s MJAR at 22. In light of these alleged deficiencies, DynCorp contends
    that the Air Force “arbitrarily inflated JLS’s Past Performance” rating by assessing JLS’s prior
    experience as “Relevant.” 
    Id.
     Plaintiff further argues that the Air Force acted irrationally in
    assigning L-3 Communications Vertex Aerospace (“L3V”) the highest overall past performance
    -6-
    rating, despite the DCMA assigning L3V a “Marginal” rating for its Army C-12 contract. Id. at
    29. DynCorp also challenges its own Past Performance rating, arguing that the Agency
    undervalued plaintiff’s “exceptional performance on the COMBS II contract” and “unreasonably
    assessed” plaintiff’s performance on the C-21 contract. Id. at 35, 37. While acknowledging that
    a subcontractor used an “unauthorized paint stripper” for plane maintenance on the C-21
    contract, plaintiff emphasizes that this “isolated issue” did not warrant the comparatively lower
    Past Performance rating. P’s MJAR at 37-38.
    DynCorp also contends that the Air Force, in other ways, unfairly evaluated offeror past
    performance, thereby prejudicing plaintiff by arbitrarily reducing its rank relative to other
    offerors. See P’s MJAR at 24-29. Plaintiff highlights the disparity between the small numbers
    of aircraft JLS serviced in its evaluated contracts compared to plaintiff’s own highly relevant
    experience maintaining more numerous aircraft as the COMBS II incumbent. Id. at 22-23.
    Given this numerical difference, plaintiff concludes that the Air Force unreasonably “inflated
    JLS’s Past Performance” while underrating plaintiff. Id. DynCorp also contrasts its paint
    thinner problems with the “serious Information Technology” issue on JLS’s E-6B CLS contract,
    arguing that the Air Force irrationally penalized plaintiff more than JLS. P’s MJAR at 38; AR
    13245. Finally, plaintiff claims that the Air Force unreasonably rated DynCorp lower than L3V
    for the Supply Chain Management subfactor, despite both offerors receiving a mix of ratings
    throughout their evaluated contracts. P’s MJAR at 31.
    Plaintiff’s past performance arguments are unpersuasive. The Court is mindful that,
    given the subjective nature of past performance evaluations, deference is owed to the Agency.
    Vanguard Recovery Assistance v. United States, 
    101 Fed. Cl. 765
    , 785 (2011); see also Glenn
    Def. Marine (ASIA), PTE Ltd. v. United States, 
    720 F.3d 901
    , 909 (Fed. Cir. 2013). But even if
    the Court did not defer to the Agency, DynCorp still does not prevail. First, despite plaintiff’s
    arguments to the contrary, the record shows that the Agency took appropriate steps in assessing
    offeror past performance, including the Quality subfactor. See e.g. AR 6137-6140, 6141-6142,
    6143-6144, 6145-6146, 6147-6150, 6151-6154, 6155-6158, 6159-6161, 12283-12286, 13338-
    13341, 13342-13345, 13346-13347, 13348-13351, 13392-13397.
    In particular, DynCorp focuses on the Air Force’s evaluation of L3V’s C-12 contracts,
    stating that transition and “maintenance procedur[e]” problems did not justify L3V’s rating of
    “Substantial Confidence.” P’s MJAR at 29, 31. It is true that the Agency assigned a Marginal
    rating for one of L3V’s quality subfactors in its Army C-12 contract. AR 18305. However, out
    of 15 non-redacted, ranked subfactors, L3V received three “Exceptional” ratings (the highest),
    seven “Very Good” ratings, four “Satisfactory” ratings, and only one “Marginal” rating (the
    lowest). 
    Id.
     It seems reasonable that the Agency could assign an overall rating of “Substantial
    Confidence,” particularly given that the lowest ratings occurred in the Transition period, which
    only accounts for a small percentage of the overall life of the contract. 
    Id.
    Plaintiff also questions its own Quality subfactor ranking, arguing that its record on the
    COMBS II contract “warrants a Substantial Confidence rating,” rather than the “Satisfactory
    Confidence” rating the Agency assigned. P’s MJAR at 35; AR 12367. Looking to the totality of
    the 10 non-redacted, ranked subfactors, the Agency assigned three “Very Good” ratings and
    seven “Satisfactory” ratings. AR 12367. Similar to the Agency’s evaluation of L3V, it seems
    -7-
    reasonable that the Agency could have assigned the rating that it did, since two-thirds of the
    subfactor ratings mirrored the overall rating. Plaintiff therefore fails to raise valid concerns
    regarding the reasonableness or fairness of the Agency’s Past Performance evaluation process.
    Instead, DynCorp seeks to have the Air Force penalize JLS and L3V for their prior
    problems, while overlooking plaintiff’s own past challenges. P’s MJAR at 27, 37-38. While
    plaintiff may disagree with the Agency’s assessments, its objections to the Air Force’s Quality
    subfactor determinations are merely a disagreement with the Agency’s evaluations. AR 17943.
    The GAO concluded that the Agency reasonably assessed the quality of offeror past performance
    in accordance with the terms of the Solicitation, and the Court concurs. See AR 17937.
    Similarly, the Agency acted within its reasonable discretion to define “relevancy” when
    analyzing offeror past performance. AR 17942. As the GAO noted, JLS’s numerically smaller
    contracts were relevant because the planes serviced were “significantly more complex” than
    those in the COMBS III contract. AR 17942. The GAO emphasized that the Solicitation “did
    not expressly define” relevancy, “thereby affording the Air Force even greater discretion to
    determine the relevance of offeror’s past performance.” 
    Id.
    Finally, Plaintiff alleges agency unfairness but confuses differing assessments with unfair
    treatment. The record shows that the plaintiff’s substandard quality on the C-21 contract resulted
    in its lower, “Satisfactory” rating for Past Performance. AR 12278-12279. Based on the record,
    it seems to this Court that the Agency did not engage in unfair or unequal treatment. AR 12279,
    17947. Instead, the Agency reasonably weighed Relevance against Quality in assigning its
    ratings.
    As the GAO report concluded, these types of qualitative assessments lie at the heart of
    the Agency’s prerogative, “since it is the agency that must bear the burden of any difficulties
    resulting from a defective evaluation, and we will not substitute our judgment for a reasonably
    based past performance rating. 
    Id.
     (citing PEMCO World Air Servs., B-284240.3 et al., Mar. 27,
    2000, 2000 CPD ¶ 71 at 7). Given the deference courts generally afford to agencies, the
    reasonableness of the CO’s actions, and the prerogative of the Agency, this Court can only
    determine that plaintiff has failed to show “clear and prejudicial error” in the Air Force’s Past
    Performance evaluation. See e.g. Bowman Transp., Inc., 
    419 U.S. 281
     at 285-86; Impresa, 
    238 F.3d at 1333
    .
    D. Pricing Proposal and Best-Value Determination
    In addition to plaintiff’s previously-discussed, more substantive arguments, DynCorp
    made two additional assertions. P’s MJAR at 17, 40. First, plaintiff alleges that the Agency
    unreasonably evaluated offeror pricing proposals. P’s MJAR at 17. Plaintiff contends that JLS
    and AAR Corp. “improperly shifted the cost” of Contractor Furnished Property (“CFP”) to the
    Agency. 
    Id.
     Plaintiff argues that the Solicitation requires that materials, including CFP, will be
    “provided by the Contractor,” but plaintiff does not successfully demonstrate that the Solicitation
    barred offerors from including the cost of the CFP in their pricing proposals. 
    Id.
     at 17 (citing AR
    252). Moreover, as JLS notes, the relevant statute “expressly allowed” offerors to include the
    -8-
    cost of materials, such as CFP, in their pricing proposals. DI’s CMJAR at 12 (citing 
    48 C.F.R. § 31.205-26
    ).
    Plaintiff also alleges that defendant-intervenor’s pricing proposal “cannot support its CFP
    purchase,” which would “intensify” JLS’s alleged “financial difficulties.” P’s MJAR at 20.
    Plaintiff further contends that JLS’s “dramatically low” price “demonstrate[d] a lack of
    understanding” of the Solicitation requirements. 
    Id. at 20-21
    . This sufficiency argument appears
    to be grounded in plaintiff’s disagreement with the way in which the Agency evaluated price.
    See AR 3371, 3408.
    The Solicitation required the Agency to evaluate price proposals for completeness, and
    plaintiff fails to demonstrate why JLS’s price was incomplete. 
    Id.
     DynCorp believes defendant-
    intervenor could not perform the COMBS III contract at a price lower than plaintiff’s proposed
    price. P’s MJAR at 20-21. However, the Agency determined that JLS’s price was not
    unreasonably low and accepted it. AR 3371, 3408, 4735-4740, 7637-7642, 5795, 8419. Without
    any hard evidence to the contrary, this decision is well within the Agency’s discretion. As such,
    plaintiff has not shown to the Court that the Agency acted unreasonably.
    Second, plaintiff argues that the Agency’s best-value determination was unreasonable.
    P’s MJAR at 40. Plaintiff alleges that “had the Air Force conducted a proper proposal
    evaluation, it would have determined that [plaintiff] offered the best value.” 
    Id.
     In keeping with
    the previously stated analysis, the Court disagrees. The Court finds the best-value determination
    reasonable, as it was based on real evidence and the Agency’s assessment of JLS’s ability to
    perform, both of which the Court discussed in detail above.
    A best-value determination is in part subjective. As such, it was well within the
    Agency’s discretion to determine that JLS’s offer presented the best value, based upon the
    Agency’s procedures and the factual record. Tech Sys., Inc. v. United States, 
    98 Fed. Cl. 228
    ,
    262 (2011) (affirming an agency’s discretion in determining best value). Plaintiff posits that
    best-value determinations based on “defective” evaluations should be overturned. P’s MJAR at
    40 (citing Femme Comp Inc. v. United States, 
    83 Fed. Cl. 704
    , 757-70 (2008)). Objective
    parameters may indeed constrain agency decisions, but so long as the Agency’s determination
    comports with the parameters of the Solicitation, as it did here, the Court will uphold that
    decision. The Agency’s evaluations were not defective, and, thus, plaintiff’s best-value
    determination argument is unpersuasive.
    Even if this Court disagreed with the Agency’s decision to award the COMBS III
    contract to JLS, there is still a rational basis for the Air Force’s award. It appears to the Court
    that the Air Force’s choice of JLS was reasonable, based upon a record of proper evidentiary
    evaluations. This is not a case in which the Agency “failed to consider an important aspect of
    the problem” or “issued a decision that is so implausible that it could not be ascribed to a
    difference in view or the product of agency expertise.” Ala. Aircraft Indus., 
    586 F.3d 1372
     at
    1375. The Administrative Record supports the Air Force’s decision to award the COMBS III
    contract to JLS. As such, plaintiff has failed to demonstrate that the Agency’s decision was
    arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.
    -9-
    IV.    Conclusion
    For the reasons set forth above, plaintiff’s MOTION for Judgment on the Administrative
    Record is DENIED. Defendant’s CROSS-MOTION for Judgment on the Administrative Record
    is GRANTED. Defendant-Intervenor’s CROSS-MOTION for Judgment on the Administrative
    Record is GRANTED. The Clerk is directed to enter judgment in favor of defendant and
    defendant-intervenor, consistent with this opinion.2
    IT IS SO ORDERED.
    s/   Loren A. Smith
    Loren A. Smith,
    Senior Judge
    2
    This opinion shall be unsealed, as issued, after August 23, 2018, unless the parties identify